HARADH & HAWIYAH FIELD GAS COMPRESSION PLAN
PRE-COMMISSIONING NOTIFICATION
DATE FROM: 3-Jul-21 TO: 8-Jul-21
TIME: FROM: 07:00AM TO: 05:00PM
PROJECT SOUTH/ PACKAGE 3 UNIT 522-HDGCP-3
TESTING & COMMISSIONING ACTIVITY AT GIS BUILDING & GIL GANTRY AREA
PRE-COM ACTIVITY ALL LCC PANELS, EARTH SWITCH,PDMAR AND PDMCR PANEL
TESTING(522-310-CP-004 TO 522-310-CP-029 & 522-310-CP-047&048) FILLING AND RECOVERY OF SF6 GAS IN GIS.
Subcontractor NCC PTW Number NCCPC-00452
EQUIPMENT NUMBER LOCATION ACTIVITY ADDITIONAL INFORMATION
Testing & Commmissioning,punch point
522-310-SG-701 GIS ALL LCC PANEL TESTING
clearance
Area Incharge: sathya/0507134573
SUB-CONTRACTOR Area HSE: Jimmar / 0560914302
HSE Manager: Abdi / 0500481434
CONTACT INFO Precom Incharge: Moises/0592531720
CONTRACTOR Area HSE Incharge: Abdullah / 0540281055
Precom
Antonio / 0592464136
Superintendent
TR MEDICAL TEAM HOTLINE 0533 99 22 00
Minimum Requirements for Precom Restricted Area
1. Whoever need to work at indicated area shall take permission from Pre Com department prior to commence activity. (Precom PTW)
2. Related area must barricaded(hard barricade and blue tape) and posted Pre-Com signage.
3. Everyone who works at mentioned area must have Electrical Building Entry Pass.
4. Subcontractors must inform their employees regarding Restricted Area and minimum requirements.
5. Standby man must avaliable with entry log full time at the entrance of the restricted area.
ATTACHED MARKED LOCATION OF PLOT PLAN
ALL LCC PANEL TESTING AT GIS BUILDING and GANTRY AREA