BOQ Alt 4-Spur Added
BOQ Alt 4-Spur Added
BOQ Alt 4-Spur Added
a Cost of removal, storage, protection and replanting in a protected and Prov. Sum
fenced-off area of selected vegetation
b Charge on provisional sum of item 21.04(a) %
Demolition, Removal, Disposal or storage of Existing structures and
2200
installations
22.06 Removal of existing concrete and masonry structures
b Reinforced concrete m3
c Masonry Structures - mortared m3
2000 SITE CLEARANCE -TOTAL (Carried forward to Summary) 3,272,528.53
Cast in-situ concrete lining (Class 20/20 concrete for Rectangular open
a m3 2,815.04 3,297.79 9,283,410.76
drain) including Reinforcement & Formwork (with U2 surface finish)
33.17 Paved Drains in Urban Areas and Reinforced Drain Covers -
a U-shaped drains in urban areas (as per Drawings) -
Stone Masonry (Class B U-shaped Masonry – Internal size 0.6m depth by
i m3 -
0.8m width)
b Reinforced Concrete Drain Covers (as per Drawings) -
Pedestrian crossing covers (Class 25/20 RC Concrete – size
i No. 14,424.00 1,162.28 16,764,735.17
1.4mX0.6mX0.15m)
Vehicle crossing covers (Class 25/20 RC Concrete – size
ii No. 500.00 1,363.30 681,650.00
1.4mX0.6mX0.2m)
3400 Stone Pitching, Masonry, Precast Concrete Block and Riprap -
34.01 Stone Pitching -
b Grouted pitching -
i For outlet & inlet of culverts m2 459.57 471.40 216,639.18
ii For Road side drains m2 4,851.00 460.94 2,236,019.94
iii For Ditch on benches and paved furrow ditch m2 -
34.03 Stone Masonry Walls -
b Cement-mortared stone walls m3 27,654.38 2,001.30 55,344,670.73
34.04 Concrete Pitching -
b Interlocking pre-cast concrete block pitching (type and thickness indicated m2 -
Pre-cast concrete blocks for side walk pavement (300x300x60mm Pre-
c m2 19,353.40 1,877.27 36,331,557.22
colored concrete block on sand base including any jointing work)
3000 DRAINAGE -TOTAL (Carried forward to Summary) 145,454,708.62
11.1 Labour
11.2 Material
11.3 Equipment
SUB TOTAL
Allow specified percent of sub-total for %
Contractor's overheads, profit etc
15.01 Accommodating traffic and maintenance temporary diversion km 13.6 354,382.43 4,819,601.05