Lifting and Rigging Written Program
Lifting and Rigging Written Program
Lifting and Rigging Written Program
INTRODUCTION:
This document refers to the lifting of moving loads by using mechanical devices. The objectives of the
hoisting and rigging program are to protect all Lufkin employees from injury and to protect the
environment from harm and equipment and property from damage.
Improper design, use or maintenance of cranes, fixtures or any other lifting devices and rigging
accessories can cause equipment to failure, load to drop from the lifting system resulting in personal
injury, death, damage to the environment or significant property loss. the first line supervisor directing
hoisting and lifting is responsible for ensuring that personnel who they supervise and who perform
hoisting and rigging activities such as designing, inspecting, maintaining and using hoisting and rigging
equipment, preparation and approval of lift plans, and review of equipment compliance are qualified to do
so. A person may be qualified to perform one of these tasks, but not qualified to perform another.
Supervisors must be knowledgeable of the specific types of hoisting and rigging operations under their
supervision. Further, supervisor must be familiar with applicable rules and procedures implemented at the
site to ensure that hoisting and rigging work under their control is done efficiently and safely, with safety
as top priority. Supervisor must ensure that employees fully understand the importance of safety and they
categorize their own authority and responsibility to stop activity when safety is questionable.
1. All cranes and lifting appliances shall have current valid test certificates in accordance with they’re
rated capacity and shall be fully insured against third party liability. A copy of the test and insurance
certificate must be kept with the vehicle at all times whilst it is on Lufkin sites.
2. The Contractor shall ensure that persons employed to operate cranes or lifting equipment are
competent to do so and have been trained in the application of correct of lifting principles and safe
working loads.
3. It is not permitted for any person to carry out work, stand, or walk directly, below a load suspended
from a crane or hoist.
5. All lifting slings must be in good condition and may be subject to inspection, by Lufkin operation
department.
1. scope:
This document applies to all personnel and equipment used to perform any hoisting
and rigging activities. Activities involving the following equipments are included:
1. Cranes, hoists, and miscellaneous lifting devices.
2. Rigging hardware and accessories.
2. Definitions:
1. Free rigging: the direct attachment to or placement of rigging to the tines ( fork) of
a powered industrial truck below –the – tines lift.
2. Below the hook lifting device: device that designed to be used in conjunction with
a hoist to lift specific types of loads .examples include tongs,C-Hooks,sheet lifters,
spreader beams, mill roll lifters, horizontal sheet lifters, lift bails, plate grades,
battery lifters, pouring bails, vacuum lifters and trail lifters.
3. Safe upper limit travel: is the highest position of hoist travel that prevents any
strain on the hoist rope, or contact of the hook or lower hook block with any part of
the hoist or trolley or crane.
4. Sling: wire rope, chain, synthetic web, and metal mesh made into forms.
5. Designated person; an individual selected or designed as being qualified to
perform specific duties.
6. qualified person; a person who, by possession of a recognized degree, certificate or
professional standing or who by extensive knowledge training, and experience has
successfully demonstrated an ability and competence to solve or resolve problems
relating to the subject matter and work.
7. Positioning device: is a device designed to cut off the control of the hoist motor
automatically below the upper over travel device in the upward direction, the
positioning device generally will be subject to frequent use during normal hoist
operation.
8. Power circuit limit switch: is a device designed to cut off the power to the hoist
motor automatically when tripped. The switch is to be used automatically only as
an upper over travel device, never a positioning device. The switch shall be rated for
full nameplate power of the hoist motor.
9. Material Safety Data Sheet (MSDS): Materials (e.g. chemicals, solutions, solvents,
man made fiber, cranes, slings, chains etc.) Containing banned substance is not
permitted on the premises.
10. Attachment: A device other than conventional forks or load backrest extension, mounted permanently
or removable on the elevating mechanism of a truck for handling the load. Popular types are fork
extension clamps, rotating devices, side shifters, and load stabilizers.
11. AUXILLARY HOIST: Supplemental hoisting unit of lighter capacity and usually
higher speed than the main hoist.
12. Bending stress: stress on wires of a wire rope imposed by bending. This stress need not be added to
direct load stresses. When sheaves and drums are of suitable size, bending stress does not affect the
normal life of the wire rope.
13. Birdcage: a colloquialism describing the appearance of a wire rope that is forced into
compresasion.the outer strands from a cage and at times displaces the core.
14. Birdcaging: the twisting of fiber or wire rope in an isolated area in the opposite
direction of the rope lay, causing it to take on the appearance of birdcage.
15. Boom line (crane): a wire rope for supporting or operating the boom on derricks,
cranes, draglines, shovels, and the like.
16. Boom: a member hinged to the rotating superstructure and used for supporting the
hoisting tackle.
17. Bridle slings: a sling composed of multiple legs (branches), the top ends of which
terminate in a fitting that latches onto the lifting hook.
18. Bull ring: the main large ring of a sling to which sling legs are attached.
19. Cable: a term loosely applied to wire ropes, wire strands, manila ropes, and electric
conductors.
20. CHOKER ROPE: A short wire-rope sling used to form a slip noose around the object to be
moved or lifted.
21. CRANE: A machine used for lifting and lowering a load vertically and moving it horizontally
and that has a hoisting mechanism as an integral part of it.
CRANES, TYPES OF:
22. Automatic Crane: A crane that, when activated, operates through a preset cycle or cycles.
23. Cab-Operated Crane: A crane controlled by an operator in a cab located on the bridge or
Trolley.
24. Cantilever Gantry Crane: A gantry or semi gantry crane in which the bridge girders
Or trusses extend transversely beyond the crane runway on one or both sides.
25. Floor-Operated Crane: A crane whose operation is controlled by use of a pendant in
The hands of an operator on the floor or on an independent platform.
26. Gantry Crane: A crane similar to an overhead crane, except that the bridge for carrying the
Trolley or trolleys is rigidly supported on two or more legs running on fixed rails or other runway.
27. Jib Crane: A fixed crane with a vertical rotating member supported at the bottom (also
At the top in some types) from which an arm extends to carry the hoist trolley. Jib cranes are most
commonly mounted on a vertical Column, supplied as part of the jib crane, or on existing structural
members (e.g., a wall mounted jib crane).
28. Mobile Crane: For the purposes of this chapter, mobile cranes are defined as wheel mounted
Cranes, truck cranes, and crawler cranes.
activities or any job restrictions imposed by crane operations, and ensure job site
coordination of cranes. Crane inspectors should become aware of these issues and
prior to starting an inspection, take time to observe the overall crane operations
with respect to load capacity, site conditions and any job site restriction in effect.
This document defines the minimum hoist design criteria required for verifying
proper operation prior the operation, periodic inspection requirements and crane
isolation for periodic inspection maintenance and repair.
This document defines the minimum hoist design criteria required for verifying
proper operation of the upper over travel device prior the operation, periodic
inspection requirements and crane isolation for periodic inspection maintenance
and repair.
3. In Lufkin where all hoist devices are leased, so, it is the responsibility of the site
supervisor to establish a documented plan to make sure of the suitable
requirements of cranes and chains and also to make sure of the inspection to be
take place according to the requirements of this document.
4. RESPONSIBILITIES
4.1 HSE Manager Responsibilities:
Setting the documented instructions and written program and make sure of
distributing this program to all interested parties.
Periodically verifying monthly test and inspection reports.
Interpreting crane and hoist safety rules and standards.
Providing management planning and technical assistance
Performing periodic audit in every location to make sure of the implementation of
this procedures.
Investigating any incident related to the crane operation whether leased or owned
by the company.
Ensuring that employees under their supervision receive the required training
and are certified and licensed to operate the cranes and hoists in their areas.
Providing training for prospective crane and hoist operators.
Evaluating crane and hoist trainees using crane safety checklist and submitting
a qualification form to the operation department or designee to obtain operator’s
license.
Ensuring that hoisting equipment is inspected and tested monthly by a
responsible, designated individual, that rigging equipment is inspected annually,
and that inspection results are documented on –site.
4.3 Cranes and Hoist operator are responsible for :
Avoid side pulls and /or load swinging. These can cause the hoist rope to slip
out of the drum groove, damaging the wire.
To prevent shock loading, avoid sudden stops or starts. Shock loading can occur
when a suspended load is accelerated or decelerated, and can overload the crane
or hoist
When completing an upward or downward motion, ease the load slowly to stop.
5. Pre-operational test:
In Lufkin where the cranes and all hoist equipment are leased and not owned by
the company, the supervisor should make sure that the following tests are done
by the operator of the leased crane.
At the start of the lifting operation by using cranes, operators should do the
following steps
Test the upper –limit switch. Slowly raise the unloaded hook until the limit
switch trips.
Visually inspect the hook, load lines, trolley and bridge as much as possible
from the operator’s station.
If provided test the lower limit switch.
Test all direction and speed controls for both bridge and trolley travel.
Test the pendant emergency stop
Test the hoist brake to verify there is no drift without a load.
Lockout and tagout for repair any crane that shown malfunction. Do not return
to service until maintenance is completed.
Except for under hung hoists, each hoist shall be equipped with a clearly
identifiable on/ off switch, emergency stop pushbutton or power safety switch
that the operator can easily reach to interrupt power to the hoist and set the
hoist brake in any event.
It is not required to have a separate on / off switch or hoist emergency stop
pushbutton or power safety switch for a hoist if there is such a device for the
entire crane brakes regardless of where the operator hoist control is positioned.
2. The upper over travel device shall not be used for positioning of the hoist. It is
used only as a safety device in the event of emergency. Employee must work in a
3. It is preferred to implement only a weight actuated power circuit limit switch that
interrupts the power to the hoist motor. It should be electrically or pneumatically
positioned so that it is the last device before the motor power input. It should be
on the output( load) side of the power source.
4. On all AC.3 phase control circuits, where a double pole power limit switch is
employed, a contact or similar device shall be installed in the control circuit to de-
energize the third phase of the motor power connection.
5. Lower travel limit device should be provided where the load block enters a pit ot
hatchway during normal operation.
6. The device shall be designed to be checked for proper operation once every twenty
–four hours for automatic material handling hoists once per shift, prior to use for
material handling hoists manually controlled.
1. Each hoist system shall have a braking system to control load lowering.
2. The hoist brake shall not be changed to a different specification from that
furnished for the application without written approval of the hoist
manufacturer or qualified person.
3. Any change shall be documented and the documentation retained including
the written approval of the change.
4. Brakes using standard couplings as brakes wheels are prohibited. A
mechanical load brake is preferred on underhung hoists of 5 brakes does not
need to be replaced.
5. The trip setting of each upper over travel device shall be determined by tests
with an empty hook or reeve in device traveling in increasing speeds up to the
maximum speed.
6. The actuating mechanism of the upper over travel device shall be located so
that it will trip under all conditions in sufficient time to prevent any strain on
the crane rope.
7. If below – the hook lifting device or hook attached device is used, then the tests should also be
conducted with the device in place or determined by a qualified person.
8. The hoist rope or chain shall not be changed to different specifications from that furnished for
the application without written approval of the hoist manufacturer or qualified person. Any
such change should be documented and the documentation retained, including the written
approval of change.
1. Except for under hung hoists, each hoist shall be equipped with a clearly identifiable on/ off
switch, emergency stop pushbutton or power safety switch that the operator can easily reach to
interrupt power to the hoist and set the hoist brake in any event.
2. it is not required to have a separate on / off switch or hoist emergency stop pushbutton or power
safety switch for a hoist if there is such a device for the entire crane brakes regardless of where
the operator hoist control is positioned.
9. Each hoist system shall have a braking system to control load lowering.
10. The hoist brake shall not be changed to a different specification from that
furnished for the application without written approval of the hoist
manufacturer or qualified person.
11. Any change shall be documented and the documentation retained including
the written approval of the change.
12. Brakes using standard couplings as brakes wheels are prohibited. A
mechanical load brake is preferred on underhung hoists of 5 brakes does not
need to be replaced.
6.1.1 inspection requirements for mobile crane:
1. Prior to the initial use of any crane during each lift, the crane operator shall verify
the operation of the primary device. The primary device is defined as the first device
intended to stop the upward direction of hoist travel that the hoist actuates in the
raising direction. If the primary device shall is used as a positioning device, both
devices shall be checked prior to the individual use of the hoist during each lift.
2. The device shall e checked by raising the crane in the slowest possible speed as the
lower block approaches the device trip point.
inspection records
how to conduct a mobile crane inspection
Basic crane inspection list.
3. Maintain inspection record. All plug and sockets shall be industrial type.
out. They must be cut out and replaced with lacing to the manufacturer's specifications,
procedures, and approval.
o Inspect tires for cuts, tears, breaks, and proper inflation.
o Visually inspect the crane for fluid leaks, both air and hydraulic.
o Visually check that the crane is properly lubricated. The fuel, lubricating oil, coolant and
hydraulic oil reservoirs should be filled to proper levels.
o Check that the crane is equipped with a fully charged fire extinguisher and that the
operator knows how to use it.
o Check all functional operating mechanisms such as: sheaves, drums, brakes, locking
mechanisms, hooks, the boom, jib, hook rollers brackets, outrigger components, limit
switches, safety devices, hydraulic cylinders, instruments, and lights.
o Check the turntable connections for weld cracks and loose or missing bolts. If they are
loose, there is a good chance that they have been stretched.
o When checking the outriggers be sure that neither the beams nor the cylinders are
distorted. Check that the welds are not cracked and that both the beams and cylinders
extend and retract smoothly and hold the load. Check the condition of the floats, and
check that they are securely attached.
o Inspect and test all brakes and clutches for proper adjustment and operation.
o Always inspect boom hoist lockout and other operator aids, such as anti-two-block
devices (ATB) and load moment indicators (LMI), for proper operation and calibration.
o While the engine is running, check all gauges and warning lights for proper readings and
operate all controls to see that they are functioning properly.
o Check for any broken or cracked glass that may affect the view of the operator
2. Periodic inspection:
This is not a task performed by Lufkin supervisor or Lufkin inspector in the present
time, since all cranes are leased, but it needs to be mentioned here for the future
usage and to be useful for inspecting the crane of the supplier.
From 1 : 12 month
Includes items listed in daily inspection as well as structural defects, excessive
wear, hydraulic or air leak.
From 1 : 12 month
Includes items listed in daily inspection as well as structural defects, excessive
wear, hydraulic or air leak it may be summarized as follows:
Inspect the entire crane for structural damage. Be careful to check for distortion or cracks in main
frame, outrigger assemblies, and structural attachments of the upper works to the carrier.
Inspect all welded connections for cracks. Inspect the main chords and lacings and other
structural items for paint flaking and cracking which may indicate potential failure, as well as for
dents, bends, abrasions, and corrosion. Check hydraulic booms for bending, side sway, or droop.
Check for deformed, cracked, or corroded members in the load/stress bearing structure. Magnetic
particle or other suitable crack detecting inspection should be performed at least once each year
by an inspection agency retained by the owner. Inspection reports should be requested and
retained in the crane file.
Inspect cracked or worn sheaves and drums.
Inspect for worn, cracked, or distorted parts such as: pins, bearings, shafts, gears, rollers, locking
devices, hook roller brackets, removable outrigger attachments lugs, and welds.
Inspect for excessive wear on brake and clutch system parts, linings, pawls, and ratchets.
Inspect all indicators, including load and boom angle indicators, for proper operation and
calibration.
Inspect all power plants for proper operation.
Inspect for excessive wear on drive sprockets and/or chain stretch.
Inspect for correct action of steering, braking, and locking devices.
Check that the counterweight is secure.
Check that the identification number is permanently and legibly marked on jibs, blocks, equalizer
beams, and all other accessories.
Inspect all hydraulic and pneumatic hoses, fittings, and tubing. Any deterioration of any system
component should cause the inspector to question whether further use would constitute a safety
hazard. Conditions, such as the following, require replacement of the part in question.
Any evidence of oil leaks on the surface of flexible hoses or at the point at which the hose in
question joins the metal and the couplings.
Any abnormal deformation of the outer covering of hydraulic hose, including any enlargement,
local or otherwise.
Any leak at connections which cannot be eliminated by normal tightening.
Any evidence of abrasive wear that could have reduced the pressure retaining capabilities of the
hose or tube effected. The cause of the rubbing or abrasion must immediately eliminated.
Slings should be visually inspected before each use to ensure their effectiveness.
Improper use of hoisting equipments – including slings may result in overloading,
excessive speed or sudden acceleration or deceleration of equipment.
There are generally six types of slings: chain, wire rope, metal mesh, natural fiber
rope, or synthetic webs.
When selecting a wire rope sling to give the best services. There are four
characteristics to consider; strength, ability to withstand, fatigue (to bend without
distortion, ability to withstand abuse.
1. Strength: is a function of its size,grade,and construction and must be sufficient to
accommodate the maximum applied load.
2. Fatigue: Fatigue failure of wire rope is caused by the development of small cracks
during small radius bends. The best means for preventing fatigue failure of wire
rope slings is to use blocking or padding to increase the bend radius.
3. Abrasive to wear: The ability of wire rope to withstand abrasion is determined by
the size and number of the individual wires used to make up the rope. Smaller
wires bend more readily and offer greater flexibility, but are less able to withstand
abrasion. Larger wires are less flexible, but withstand abrasion better
4. Abuse: Misuse or abuse of wire rope slings will result in their failure long before
any other factor. Abuse can lead to serious structural damage, resulting in kinks
or bird caging. (In bird caging, the wire rope strands are forcibly untwisted and
become spread outwards.) To prevent injuries to workers and prolong the life of the
sling, strictly adhered to safe and proper use of wire rope slings.
The center of gravity of an object is that point at which the entire weight may be
considered to be concentrated. To make a level lift, the hoist hook must be located
directly above this point. If the hook is too far to either side of the center of gravity,
dangerous tilting will result, causing unequal stress in the sling legs. Load
imbalances must be corrected immediately.
The rated capacity of a sling varies depending upon the type of material the sling is
made of, the size of the sling, and the type of hitch. Workers must know the capacity
of the sling, and can obtain this information through charts or tables available
through the manufacturer. The rated capacity of a sling must not be exceeded, under
any circumstances.
10.0 training
(14) Main Boom, Jib Boom, Boom Extension Boom jibs, or extensions, must not be
cracked or corroded. Bolts and rivets must be
tight. Certification that repaired boom
members meet manufacturers original design
standard shall be documented. Non-certified
repaired members shall not be used until
recertified.
(15) Load Hooks and Hook Blocks Hooks and blocks must be permanently
labeled with rated capacity. Hooks and
blocks are counterweighted to the weight of
the overhaul line from highest hook position.
Hooks must not have cracks or throat
openings more than 15% of normal or twisted
off center more than 10o from the longitudinal
axis. All hooks used to hoist personnel must
be equipped with effective positive safety
catches especially on hydraulic cranes.
(16) Hydraulic Hoses Fittings and Tubing Flexible hoses must be sound and show no
signs of leaking at the surface or its junction
with the metal and couplings. Hoses must not
operator's manual.
(19) Wire Rope Main hoist and auxiliary wire rope inspection
should include examining for
Broken wires.
Excess wear.
External damage from crushing,
kinking, cutting or corrosion.