Fujairah Port - Ceg - Roelevink - 2007
Fujairah Port - Ceg - Roelevink - 2007
Fujairah Port - Ceg - Roelevink - 2007
EXPANSION PROJECT
Master thesis
Graduation committee:
Technical University of Delft Prof.ir. H. Ligteringen
Faculty of Civil Engineering and Geosciences ir. H. J. Verhagen
Hydraulic and offshore section
ir. F.A.M. Soons
Student:
G.J. Roelevink
Stdnr. 1184474
B.V. Ingenieursbureau M.U.C.
Preface
This is the final report of the Msc. thesis for my study at Delft University Faculty of Civil Engineering
and Geosciences. The project was carried out with Ingenieursbureau M.U.C. and under guidance of Prof.
ir H. Ligteringen, ir F.A.M. Soons and ir. H.J.Verhagen.
In January 2006 M.U.C. was assigned to prepare tender documents for the civil and marine works of the
expansion of the Port of Fujairah. Included in this assignment where the detailed technical designs of
quay walls, coastal protection works and a liquid bulk jetty and the development of a new port layout.
Although there was a strong demand by the port authorities to finish the designs and tender documents, a
clear masterplan which should guide the expansion project was not present yet. In fact no study on the
subject of throughput and shipping expectations or throughput capacities was carried out.
The absence of a masterplan gave the opportunity for this thesis. During the preparation of this report,
b.v. Ingenieursbureau M.U.C. focused on the preparation of tender documents and designs of quay walls
and liquid bulk jetties whereas in my thesis attention was paid to planning aspects. Uncertainties such as
the involvement of DP World for the container terminal, the required capacity of the liquid and dry bulk
terminals or the realization of the Fujairah Land Reclamation Project have changed plans many times
during the process. Finally the graduation project was uncoupled from the actual developments in
Fujairah to be able to finalize the report.
The parts of the study on hydraulic subjects where carried out under guidance of Alkyon. The
information on liquid bulk trade in Fujairah and oil terminals where gained with help from Capt. P. Nix,
who has been terminal manager of the Vopak (VHFL) terminal in Fujairah for several years. The greater
part of the information that was used to carry out this study was gathered during several visits to
Fujairah. Further many (port) development projects in the area of Fujairah have been visited to be able to
put together this report.
First of all I would like to thank my graduation committee for the guidance and advices during the
project. Further I owe thanks to MUC for providing a good working environment, Alkyon for providing
technical support, Paul Nix for the valuable information and my family and friends for their support.
Special thanks to Jan Udink and his family who made me feel welcome in Fujairah and made it possible
to carry out this study in the first place.
Gert-Jan Roelevink
Delft, October 2007
i
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Summary
The Port of Fujairah is situated on the Eastern coast of the UAE, approximately 70 nautical miles south
from the Straits of Hormuz. The port mainly serves as a dry bulk export port and oil terminal. The export
of aggregates is a the main activity in the port, together with the bunker trade. Other commodities are
being handled in the port, though on a much smaller scale. Currently the port faces a capacity shortage.
N N
Location of Fujairah
The market for aggregates in the Middle East is growing considerably due to rapid developments and
expansion plans in this region. Fujairah as a main supplier of high quality aggregates wants to anticipate
and increase its export. The aggregate ship loader of the Port of Fujairah however has reached its
maximum capacity several years ago. The quay that was originally built for container handling is now
being used to load bulk carriers with ship based cranes. Besides the inefficiency of this operation, the
capacity of this solution has also grown to its limit. It is not possible to improve this operation by placing
a new ship loader on the quay since it is leased out to Dubai Port including Container Handling facilities.
In addition to the expansion of the export capacity of dry bulk facilities, there are plans to build a new
steel factory in Fujairah for which additional dry bulk unloading facilities are required. The raw material
for this plant is planned to be brought in by ship. Vessels will be unloaded in the Port of Fujairah.
Besides dry bulk loading facilities, the Port of Fujairah currently offers liquid bulk loading and unloading
facilities. These facilities are primarily being used for the loading and unloading of oil carriers that
supply the oil storage of the Fujairah Refinery (FRCL). This refinery does not operate as a refinery but is
only utilized as oil storage facility.
Although currently three oil terminal berths (OTB’s) can satisfy the required capacity, the oil storage
market is tending to grow rapidly. At the moment many single hull oil storage ships operate in the waters
in front of Fujairah. Due to new international regulations that require a double hull for off shore oil
storage, a great part of this off shore storage will be shifted to onshore. Several local oil storage firms
have expressed their interest to increase their storage capacity and to build new oil storage tanks in
Fujairah. The Port of Fujairah wants to anticipate and build the loading and unloading facilities for the
ships that are to supply these new oil storage tanks. Besides oil, some growth in the demand for
throughput capacity of chemicals is foreseen.
However the Port of Fujairah is not using their container loading facilities actively, Dubai Port that is
current leasing the quay and cranes in the Port of Fujairah has expressed their desire to be able to unload
bigger vessels and handle more containers. This is not possible with the current facilities. The Port of
Fujairah intends to investigate the possibilities for the handling of large size container vessels.
ii
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
For the above mentioned reasons, the local authorities of Fujairah are planning to expand the existing
Port of Fujairah. The expansion should supply for the anticipated growth of the coming 25 years. The
Port of Fujairah Authorities have invited B.V. Ingenieursbureau M.U.C. to carry out a masterplan study
for this expansion project.
The objective of this study is twofold. The first objective is to find a favorable layout for the Expansion
of the Port of Fujairah in which the port can expand its activities for the coming 25 years. The second
objective is to propose technical designs for the civil and marine works of the expansion project. In fact
this study covers the masterplan process including analysis, generation of layout alternatives, evaluation
nd selection of these alternatives and preliminary engineering. Further evaluation of the most promising
alternatives should be part of further study.
The Port Authorities have indicated that the emphasis is on realization of the first construction phase on
the short term. This means that the proposed technical solutions for the civil and marine parts of the
project will directly be used for startup of the first construction phase of the project.
The port expansion should be realized, preferably north of the existing port and south of the existing oil
terminal that is run by VHFL. VHFL is a joint Venture between Vopak and Horizon Terminals Ltd.
These spatial constraints will have an essential influence on the shape of the port expansion. South of the
port there is space for developments. The authorities have indicated however that this location will
preferably be used for other purposes.
Since it is extremely difficult to make a realistic forecast of the demand in throughput capacity, several
throughput scenarios have been composed. For the greater part of the commodities in the port,
throughput development depends on many unknown factors. Especially the regional demand for export
products is hard to predict.
For these reasons, three scenarios of growth in demand for throughput capacity have been composed for
each of the above mentioned commodities. These three scenarios represent low, medium and strong
growth which all result in a number of layout requirements for the new port expansion.
To determine the requirements for the new port a basic simulation model was developed. The model is
based on the Monte Carlo method which uses random numbers. The number of input variables makes it
impossible to use the queuing theory.
Based on the spatial constraints and the requirements according to the composed scenarios, a number of
layout alternatives have been proposed. A monetary evaluation as well as a multi criteria analysis finally
resulted in the selection of a limited number of most promising layouts. Several layouts where not
capable of supplying the required throughput capacity according the highest growth scenario. For a valid
assessment, all layouts have been evaluated for each scenario separately.
For the marine and civil parts of the project, the quay walls, coastal protection works, liquid bulk
terminal and dredging, several principle technical designs where proposed. The cost estimations that
where used for the monetary evaluation where based on these designs. These designs are discussed in
detail in the annexes to this document.
The final conclusion is that realization of the port expansion north and partly south of the existing port is
necessary to reach the throughput capacity as described by the highest growth scenario.
The area south of the port was originally reserved for other developments. The available area, north of
the existing port however does not provide enough space for a terminal that is capable of achieving the
anticipated throughput. It is proposed to realize the container terminal south of the existing port and to
handle other commodities at the preferred location, north of the existing port. An additional advantage is
that the soil that is gained by dredging the harbour basin for the container terminal can be used for the
Fujairah Land Reclamation Project. This project will be realized 1.5 km north of the existing port.
The masterplan is worked out to a level that it can be used for preparations of tender documents. This
means that several subjects on the field of port planning have been described superficially and that other,
more detailed technical parts of the expansions plan have been paid more attention to.
iii
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Contents
List of tables ....................................................................................................................................... viii
List of figures ....................................................................................................................................... ix
List of annexes....................................................................................................................................... x
List of abbreviations ............................................................................................................................. xi
1 Introduction .................................................................................................................................... 1
1.1 Introduction............................................................................................................................ 1
1.1.1 Fujairah ........................................................................................................................ 1
1.1.2 The port of Fujairah ..................................................................................................... 1
1.1.3 Problem definition ....................................................................................................... 1
1.2 Objective ................................................................................................................................ 2
1.3 Scope of this study ................................................................................................................. 2
1.4 Backgrounds........................................................................................................................... 3
1.5 Structure of this report ........................................................................................................... 3
iv
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
v
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
vi
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
7 Technical designs.......................................................................................................................... 80
7.1 Introduction.......................................................................................................................... 80
7.2 Quay wall design.................................................................................................................. 80
7.3 Coastal protection works...................................................................................................... 80
7.4 Liquid bulk terminal............................................................................................................. 81
References 83
vii
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
List of tables
table 2.1 Number of calls and tonnage per commodity 2006 ............................................................. 11
table 2.2 Calls and tonnage of bulk vessels differentiated for 2006 ................................................... 11
table 2.3 Cargo tonnage of aggregate ships calling the Port of Fujairah ............................................ 14
table 2.4 Calls and tonnage of loading and unloading of liquid bulk vessels per terminal for 2006. . 16
table 2.5 Berth occupancy liquid bulk berths Port of Fujairah and VHFL ......................................... 16
table 2.6 Marine and operation rates Port of Fujairah......................................................................... 19
table 3.1 Omnidirectional wind speeds according to records made at the VHFL-jetty. ..................... 22
table 3.2 Water levels.......................................................................................................................... 23
table 3.3 Current velocities according to measurements made at the VHFL-jetty.. ........................... 23
table 3.4 Percentages of time that the wave heights in the given direction are exceeded at the location
of the VHFL-jetty according to transformed ship observations........................................... 24
table 3.5 Extreme near shore wave (depth line 14) heights and directions for given return period and
direction according to corrected ship observations. ............................................................. 24
table 3.6 Near shore significant wave heights for different return periods and water depths............. 25
table 3.7 Soil composition .................................................................................................................. 26
table 4.1 Critical wave height for ships berthed on VHFL jetty. ........................................................ 30
table 4.2 Estimated downtime on OSTT............................................................................................. 30
table 4.3 Summary throughput scenarios............................................................................................ 37
table 4.4 Dry bulk vessel size distribution according to Lloyd’s register vessel statistics ................. 38
table 4.5 Liquid bulk vessel size distribution according to Lloyd’s register vessel statistics ............. 39
table 4.6 Container vessel size distribution according to Lloyd’s register vessel statistics ................ 39
table 4.7 Simulation results aggregates............................................................................................... 42
table 4.8 Simulation results dry bulk import....................................................................................... 43
table 4.9 Average ship sizes per storage type. .................................................................................... 44
table 4.10 Number of liquid bulk berths ............................................................................................... 45
table 4.11 Container vessel size distribution used for simulation......................................................... 46
table 4.12 Results from container throughput simulation study ........................................................... 46
table 4.13 Summary required quay length and number of cranes......................................................... 47
table 4.14 Required area for container terminal.................................................................................... 49
table 5.1 Areas oil storage facilities in Fujairah.................................................................................. 67
table 6.1 Weighted score criteria ........................................................................................................ 71
table 6.2 Net present value 2032, layout alternatives scenario 1 ........................................................ 72
table 6.3 Multi criteria analysis........................................................................................................... 74
table 6.4 NPV per value point............................................................................................................. 74
viii
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
table 6.5 Net present value 2032, layout alternatives scenario 2 ........................................................ 75
table 6.6 Multi criteria analysis scenario 2 ......................................................................................... 76
table 6.7 NPV per value point scenario 2 ........................................................................................... 76
table 6.8 Net present value 2032, layout alternatives scenario 3 ........................................................ 77
table 6.9 Multi criteria analysis scenario 3 ......................................................................................... 78
table 6.10 NPV per value point scenario 3 ........................................................................................... 79
table 7.1 Specific dimensions quay walls ........................................................................................... 80
table 7.2 Summary design revetment straight section......................................................................... 81
List of figures
ix
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
List of annexes
x
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
List of abbreviations
CD = Chart Datum
ECH = Empty Container Handling truck
FHD = Fujairah Harbour datum
HAT = Highest Astronomical Tide
HWL = High Water Level
IB = Industrial Berth
LAT = Lowest Astronomical Tide
MARPOL = Marpol" is short for marine pollution
MCA = Multi Criteria Analysis
MHHW = Mean Higher High Water
MHLW = Mean Higher Low Water
MLHW = Mean Lower High Water
MLLW = Mean Lower Low Water
MSL = Mean Sea Level
NPV = Net present value
OSTT = Open Sea Tanker Terminal
OTB = Oil Tanker Berth
P.o.F. = Port of Fujairah
RTG = Rubber Tired Gantry
TGS = 20-foot container ground slots
SBB = South Breakwater Berth
SPM = Single Point Mooring (buoy)
STB = Sea Tanker Berth
VHFL = Vopak Horizon Fujairah Ltd.
xi
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
1 Introduction
1.1 Introduction
1.1.1 Fujairah
Fujairah is one of the seven emirates of the United Arab Emirates. The United Arab Emirates has a
highly industrialized economy that makes the country one of the most developed in the world. Fujairah is
the only emirate that borders the UAE s east coast, overlooking the Gulf of Oman. Within its territory
there are some coastal enclaves belonging to Sharjah (Khor Fakkan, Kalba and part of Dibba and some
landlocked enclaves belonging to Oman (Madhab and part of Dibba). The area of the emirate is 1165
kms2, which is equivalent to 1.5% of the country s total area, excluding the islands. Fujairah has
dramatic mountain scenery, which has been a major factor in its fast developing tourism trade. Fujairah s
port, built in 1982, has been enlarged and sea road and sea air traffic expanded considerably. It is now the
world s third largest tanker refueling and bunkering station.
The Port of Fujairah is situated on the Eastern coast of the UAE, approximately 70 nautical miles south
from the Straits of Hormuz. The port mainly serves as a dry bulk export port and oil terminal. The export
of aggregates is the main activity in the port, together with the bunker trade. Other commodities are being
handled in the port, though on a much smaller scale.
The market for aggregates in the Middle East is growing considerably due to rapid developments and
expansion plans in this region. Fujairah as a main supplier of high quality aggregates wants to anticipate
and increase its export. The aggregate ship loader of the Port of Fujairah however has reached its
maximum capacity several years ago. The quay that was originally built for container handling is now
being used to load bulk carriers with ship based cranes. Besides the inefficiency of this operation, the
capacity of this solution has also grown to its limit. It is not possible to improve this operation by placing
a new ship loader on the quay since it is leased out to Dubai Port including Container Handling facilities.
In addition to the expansion of the export capacity of dry bulk facilities, there are plans to build a new
steel factory in Fujairah for which additional dry bulk unloading facilities are required. The raw material
for this plant is planned to be brought in by ship. Vessels will be unloaded in the Port of Fujairah.
Besides dry bulk loading facilities, the Port of Fujairah currently offers liquid bulk loading and unloading
facilities. These facilities are primarily being used for the loading and unloading of oil carriers that
supply the oil storage of the Fujairah Refinery. This refinery does not operate as a refinery but is only
utilized as oil storage facility.
Although currently three oil terminal berths can satisfy the required capacity, the oil storage market is
tending to grow rapidly. At the moment many single hull oil storage ships operate in the waters in front
of Fujairah. Due to new international regulations that require a double hull for off shore oil storage, a
great part of this off shore storage will be shifted to onshore. Several local oil storage firms have
expressed their interest to increase their storage capacity and to build new oil storage tanks in Fujairah.
The Port of Fujairah wants to anticipate and build the loading and unloading facilities for the ships that
are to supply these new oil storage tanks. Besides oil, some growth in the demand for throughput
capacity of chemicals is foreseen.
10/29/2007 1
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
However the Port of Fujairah is not using their container loading facilities actively, Dubai Port that is
current leasing the quay and cranes in the Port of Fujairah has expressed their desire to be able to unload
bigger vessels and handle more containers. This is not possible with the current facilities. The Port of
Fujairah intends to investigate the possibilities for the handling of large size container vessels.
For the above mentioned reasons, the local authorities of Fujairah are planning to expand the existing
Port of Fujairah. The expansion should supply for the anticipated growth of the coming 25 years. The
Port of Fujairah Authorities have invited B.V. Ingenieursbureau M.U.C. to carry out a masterplan study
for this expansion project. The port expansion should be realized, preferably north of the existing port
and south of the existing oil terminal that lies 1.5 km north of the existing port.
1.2 Objective
The objective of this study is twofold. The first objective is to find a favorable layout for the Expansion
of the Port of Fujairah in which the port can expand its activities for the coming 25 years. The second
objective is to propose technical designs for the civil and marine works of the expansion project.
The purpose of the masterplan is to have a blue print for future development, reserving space where it
may need in the future, taking into account of regulatory, and creating an efficient and economic port
operation. This Masterplan Study should take into account the existing port capacity, hinterland
connections, industrial developments and environmental constraints.
This study covers several steps in the masterplan process. These steps include the analysis phase, the
generation of layout alternatives, the evaluation and selection of these alternatives and preliminary
engineering. Optimization of the most promising alternatives should be part of further study. This is
further illustrated in graph 1.1
An economic analysis or separate study on cargo flow and shipping expectations did not go ahead of this
study. This means that this subject lies within the scope of this study but is based on a large number of
assumptions.
The environmental impact assessment of the port expansion, social impacts and safety aspects will only
be discussed superficially in this study. Further, nautical, hydraulic and cost optimization of the most
promising alternative will not be part of this study.
The Port Authorities have indicated that the emphasis is on realization of the first construction phase on
the short term. This means that the proposed technical solutions for the civil and marine parts of the
project will directly be used for startup of the first construction phase of the project.
10/29/2007 2
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
- Spatial aspects
Generation of alternatives
1.4 Backgrounds
B.V. Ingenieursbureau MUC caries out the masterplan study as assigned by H.H. Sheikh Saleh bin
Mohammad Al Sharqi. This entails that the study is to be carried out, keeping in mind that the Port
Expansion Project must serve the interests of the emirate of Fujairah as a whole.
In this first chapter of this report, an introduction is given of the project and the main objectives and
project limitations. The present situation of the Port of Fujairah is described in detail in chapter two. In
this chapter an evaluation of the capacity and possibilities of the current port is made. In chapter three,
the relevant environmental boundary conditions are described. These comprise data on wind, wave,
currents and geotechnical conditions. The derivation of these boundary and the sources used to find them,
can be found in Annex 1 to this report. With the information described in chapter two and three it is
attempted to construct a thorough foundation for the study of further development of the port.
Based on expectations of the port of Fujairah several throughput scenarios are composed in chapter four.
These scenarios are used to determine quay lengths and number of berths for the new port by execution
of several simulations.
In chapter five, several layout alternatives for the new harbour basin as well as for the Open Sea Tanker
Terminal and onshore areas are proposed. These layouts are evaluated using a monetary evaluation and
multi criteria analysis in chapter six. The analysis will focus on throughput capacity, growth possibilities,
cost and safety of navigation. For the estimation of cost of quay walls coastal protection, dredging and
the OSTT, several principle designs are made in Annex 4 - Annex 7. The result of the evaluation is the
selection of a number of most promising alternatives. The optimization of these layouts will be part of
additional study.
10/29/2007 3
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
2.1 Introduction
In this chapter a description is given of the current Port of Fujairah. This comprises a rough description
of the port regarding the water and land areas of the harbour. Subsequently the present commodities and
throughput numbers are described in this chapter. Information for this chapter is gathered during several
site visits and interviews with the Port of Fujairah port Authorities.
Further, several reports (among others; the yearly “Bulk loader and lift grab report” and “Statistical
report”) made available by the Port of Fujairah have been used.
Fujairah Port is situated on the Eastern coast of the UAE, approximately 70 nautical miles south from the
Straits of Hormuz. This strategic position has proved to be attractive to both a range of users of the multi-
purpose port and for the significant numbers of vessels calling at the Fujairah Anchorage for Bunkers,
Supplies and Service.
Fujairah was developed in the early 1980s to provide the Arab Emirates with a major container facility
outside the straight of Hormuz. From this site it was possible to carry out containers by road into the rest
of the UAE, should conditions in the Arabian Gulf become unstable. It has since developed as a container
transshipment centre with APL as its major carrier. A land bridge system is operated to link it to the rest
of the United Arab Emirates.
The other major Port activity is as a center for supply boats servicing ships waiting for orders offshore.
In the mild 1990s, a small refinery was built immediately to the North of the port, with its oil being
handled from vessels lying to a pair of buoys at the north end of the harbour.
N N
2.1 Location of Fujairah
The harbour is entirely artificial, being formed by a pair of rubble mound breakwaters, armoured on the
outside with pre-cast concrete Dolos armour units and locally quarried rock. These breakwaters curve out
from the shoreline and overlap so that the entrance faces South-southeast. This produces generally calm
conditions in the port, particularly at the south end where a floating jetty is operated.
10/29/2007 4
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
The original design of the breakwaters is based on a wave analysis performed on the basis of hind casting
from local wind conditions. But wave recordings carried out during the construction of the port,
demonstrated that the main wave action originated well out in the Gulf of Oman and that local wind had
little effect. One result of this is that the design of the Fujairah breakwaters is conservative and they
suffer no significant overtopping. The other result is that at certain times there is significant penetration
of southerly waves into the harbour. Local reporting indicates that these events are rare and that the
maximum local wave action near the root of the north breakwater has amplitude of less than one meter.
The breakwaters are founded onto the original seabed and the area within the harbour basin was then
dredged according to the requirements for each zone of the harbour. The soils are generally sandy
becoming more cemented with depth until they can be classified as rock.
All berthing facilities of the PoF are quay walls, also for oil handling and aggregate loading. VHFL uses
only open sea tanker facilities, no quays.
As described in paragraph 2.4 the Port of Fujairah has been expanding during its existence. In these
projects different quay wall solutions have been chosen. The main quay wall consists both of combi wall
structures and of blockwork walls. The part of the quay on which container cranes operate is a combi
wall; the part on which the aggregate ship loader operates is a blockwork wall. The OTB’s and the South
breakwater berth that is currently under construction are combi wall structures. The water depth in front
of the quays differs and is shown in figure 2.3.
10/29/2007 5
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
3 -15 m
-12.6 m -7.6m
2 1
4
7 8
Harbour entrance
1: Container and aggregates berths 6: Free zone facilities
2: Aggregates Berths 7: Development area
3: Oil Tanker Berths 8: Commercial facilities
4: Service vessel berths 9: Development of South Breakwater Berths
5: Port operation area
2.3 Layout of the existing Port of Fujairah
10/29/2007 6
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
2.3.2 VHFL
North from the Port of Fujairah an oil terminal is run by Vopak in combination with Horizon Terminal
Ltd. The Joint venture is called Vopak Horizon Fujairah Ltd. (VHFL). A wholly owned Enoc subsidiary.
EBFL has also committed to contracting 1 of 2 bunker VHFL berths to improve facilities for customers.
EBFL is a joint venture between ENOC, which holds 51-pc of the equity, the Fujairah Government,
which has a 25-pc stake, the Kuwait's Independent Petroleum Group (IPG) with the remaining 24-pc.
The joint venture provides offshore and inport marine products in Fujairah. Vopak (former companies
Van Ommeren and Pakhoed) Vopak provides independent storage and handling of liquid oil products,
chemicals, vegetable oils and liquefied gases.
This terminal operates independently from the Port of Fujairah. Only the marine operations are under
control of the Port of Fujairah. VHFL offers storage facilities for different types of products to clients all
over the world.
B.V. Ingenieursbureau M.U.C. was invited by the Port of Fujairah to carry out the masterplan study for
the Port of Fujairah Expansion Project.
2.4 History
Fujairah was developed in the early 1980s to provide the Arab Emirates with a major container facility
outside the straight of Hormuz (figure 2.1). From this site it was possible to carry out containers by road
into the rest of the UAE, should conditions in the Arabian Gulf become unstable. It has since developed
as a container transshipment center with APL as its major carrier. A land bridge system is operated to
link it to the rest of the United Arab Emirates. The other major Port activity is as a center for supply
boats servicing ships waiting for orders offshore.
In the mild 1990s, a small refinery was built immediately to the North of the port, with its oil being
handled from vessels lying to a pair of buoys at the north end of the harbour.
10/29/2007 7
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
In November 2002 the Port of Fujairah Bulk Loader became fully operational coinciding with the
completion of an additional 600 meters of main quay dredged to 15 meters. The planning, building and
commissioning of the Bulk Loader was based on the need to meet a sustained and growing demand for
quality aggregate exports from the Emirate building projects in the Inner Gulf and beyond. Previously
shipments were handled by vessels using their own gear and performing a load and grab operation from
the quay.
Since the Dubai Port has leased the Port of Fujairah container handling facilities for strategic reasons,
container throughput has decreased. The emphasis is now on loading of aggregates and oil loading and
unloading.
In the nineties Vopak in combination with other parties (VHFL) opened an oil storage facility North of
the Port of Fujairah. The mild wave climate made it possible to run this facility outside the harbour basin.
The facility included a jetty with 2 berths and a single point mooring facility 2 kilometers from the coast
for loading and unloading the ships that provide the material.
However the marine operations controlled by Port of Fujairah Marine Department, the terminal operation
of this storage facility are not controlled by Port of Fujairah. In 2004 the construction two extra berths
finalized (VHFL berth 3 and 4). Currently there are preparations being made to construct two additional
berths.
In 2006 the construction of an Oil Terminal Berth (OTB) inside the harbour basin was finalized. This
OTB consists of a quay wall on which maximal five small ships or three medium sized ships can berth.
The quay wall lies parallel to the northern breakwater of the existing port. The main function of this
facility is to serve as load and unload facility for the Fujairah Refinery (FRCL)
The port operates as a Landlord port. This means that the land of the port is owned by the Port
Authorities and concessions are given to companies for provisions of cargo handling and storage
services. The port authorities are responsible for the infrastructure, the nautical safety and access,
including access channels and harbour basins. A more detailed description about port operations per
commodity is given in the following paragraphs.
10/29/2007 8
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Chairman of the Port of Fujairah is His Highness Sheikh Saleh bin Mohammad Al Sharqi. The port is
controlled by the general manager. The general manager has a staff of eight managers, each operating on
a different area. Figure 2.4
General Manager
The area inside the harbour basin (shown in figure 2.3) is approximately 1.5 km in a north south direction
and 1 km east west. The depth of the basin is CD -15 m in front of the Oil Terminal Berths, the aggregate
berths and the container berths. The rest of the harbour basin has a depth of CD -12.6 m
The access channel has a depth of CD- 15 m. It is directed to the Southeast. The depth outside the
harbour basin at the access of the harbour basin is 13 m. The slope of the sea bottom at this location is
1:100. This means that the access channel is short and the surface level difference between the original
sea bottom and the access channel surface level is small. The width of the access channel between the
breakwaters at the location of the harbour entrance is 230 m. This means that the access channel has one
lane. There are currently no capacity problems regarding this restriction.
For approaching ships, the direction of the access channel is not the most favorable regarding wind and
wave directions. However since the wave and wind climate in Fujairah is very mild
At the location of the VHFL jetty some dredging works haven taken place several years ago to bring the
sea bottom in front of the largest berths at CD -18 m. There are no coastal structures in the vicinity of the
jetty that hinder navigation around these berths. The coast in front of the VHFL terminal is a beach that
dissipates wave energy.
The land area that is controlled by the Port of Fujairah has the same length in the North-West direction as
the water area. The width of this area is approximately 500 m. Additionally to the area right behind the
10/29/2007 9
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
quay wall, there is an aggregate stockpile area Figure 2.5 shows the layout of the land area of the Port of
Fujairah.
SPM
VHFL jetty
The land area can be divided in 5 main areas. The use per area and the boundaries of these areas are
shown in figure 2.5. Within the Port of Fujairah gates the three main areas are a container storage area,
port operation area, container storage area and an area for commercial activity. The activities on these
areas are further described in the following paragraphs.
2.8 Commodities
The main activity in the Port of Fujairah is currently the loading of aggregate ships and handling oil
vessels. Besides for the OTB’s inside the port, the marine services for the VHFL berths outside the port
are controlled by the Port of Fujairah. The following number of vessels per commodity has called
Fujairah port 2006:
10/29/2007 10
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
It can be seen that general cargo, containers and other commodities form a minor part of the port
throughput. However container throughput is decreased dramatically in the past years, the container
handling facilities and quay wall are still a source of income for the Port of Fujairah since they are leased
by Dubai Port.
Dry bulk cargo handled in the Port of Fujairah can be differentiated as shown in table 2.2:
Aggregates form the largest quantity of dry bulk throughput in the Port of Fujairah. In fact the tonnage of
exported aggregates forms 95.5 % of the total dry bulk throughput. The other material that form the
resulting 5 % are Clinker (2%), Copper slag (0.8%), Coal (0.8%) and Cement (0.3%) and other (0.3%).
2.9.2 Aggregates
Aggregate
Construction aggregate, or simply, aggregate, is the broad category of basic materials used in
construction, in this case crushed stone. Aggregates are a basic resource, necessary for any kind of
modern construction. Aggregates are the basic input materials to concrete and asphalt. Additionally,
aggregates are used as base materials under foundations and roads. Fujairah is one of the main producers
of aggregates in the Middle East. The material is well known throughout the region for its high quality.
Due to the developments and economic activities in the region, the demand for good quality aggregates is
high. Aggregates from Fujairah are produced by blasting and crushing of rock material in several
quarries in the area.
Currently, the aggregate loading facilities are not capable of offering the required capacity. The market
for aggregates in the Middle East is growing considerably due to rapid developments and expansion
plans in this region. Fujairah as a main supplier of high quality aggregates wants to anticipate and
increase its export.
The aggregate ship loader of the Port of Fujairah however has reached its maximum capacity several
years ago. Currently the quay that was originally built for container handling is now being used to load
10/29/2007 11
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
bulk carriers with ship based cranes. Besides that this is an inefficient, time consuming operation, the
capacity of the operation has grown to its limit. It is not possible to improve the operation by placing a
new ship loader on this quay since the quay including Container Handling facilities is being rent by
Dubai Port. Aggregates are loaded on berths 5 and berth 6 in the existing harbour. Berth 6 is strictly
allocated for aggregate loading and berth 5 was originally arranged for container handling but is used
now in case berth 6 is occupied.
The occupancy of the quay wall on which the aggregate ship loader is operating, has been very high
during the last years. In 2006 the occupancy reached 90%. The occupancy of the berth on which
aggregates are loaded using ship based cranes is lower. This is due to the fact that this berth is only being
used when the ship loader is occupied.
Due to the shortage in export capacity, currently a great part of the material produced in Fujairah is
transported by truck to Dubai. This causes a constant stream of trucks on the 140 km long main road
between Fujairah and Dubai. Another large part of the material is loaded on a temporary ramp structure.
South from the Port of Fujairah, an artificial peninsula for holiday residences is currently under
construction. The reclamation works for this peninsula are expected to finalize in 2010. Until this
moment the reclaimed land is used for loading of barges with aggregates and large rock. The material is
brought in from the quarries by truck and stored on the peninsula. The temporary ramp structures are
used by dumper trucks with which the barges are loaded. Since no large structures are required, this is a
relatively cheap operation. However due to the water depth in front of the ramp structure, the size of the
ship is limited. The advantage of the operation is that besides aggregates, also large rock can be handled,
which is not possible with the ship loader. Almost all material that is loaded on the ramp structure is
shipped to Qatar and projects in Raslaffen.
Quarries
There are about 60 quarries in Fujairah. Currently 19 of these quarries use the Fujairah harbour as export
facility. The three main quarries that export aggregates through the Port of Fujairah are:
- Tiger Transport
- Arabian Est. Transport & Supply
- Fujairah Rock & Aggregate company
These quarries take charge of almost 60 % of the total aggregate export through the port of Fujairah. The
operation of a quarry is a discontinue process. The production starts with the preparation of a part of rock
to be blasted. After blasting the rock is brought to the crushers by large dumper trucks. In several steps
the material is reduced in size. Some rocks have to be re-blasted when they do not fit in the crusher.
Two main transport modes for transport of aggregates from the quarries to the exporting ships that are
currently used can be differentiated are by conveyor belt and ship loader and by lift and grab operation.
Loading by conveyor belt is a continue transport process between stockpile area and the ship. The lift and
grab operation is a discontinue process.
Ship loader
The material is transported by truck from the quarries to the Port of Fujairah stacking area. The stacking
area lies west from the Road to Khor Fakkan. At the place a part of the material is stored and from there
transported to the quay by a ship loader - conveyor system. The major part of the material is transported
to the conveyor loading point by truck as the vessel is laden. The aggregate ship loading system consists
of a ship loader crane, and a conveyor belt from the stacking area to this ship loader crane. The loading
of the aggregates is by this means, a continuous process. The ship loader crane is traveling on the quay
wall to which the ship is berthed and is fed by the conveyor belt.
10/29/2007 12
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
The Port of Fujairah owns both the stacking area and the ship loader. This stacking area has a total area
of 368,000 m3, which is put out to lease to quarries and stevedoring firms. The total length of this
transport line is 5 km.
2.9.5 Vessels
In 2006 there where 313 vessels calling the Port of Fujairah for loading of aggregates. Given the fact that
these ships where empty at arrival, this means that the average cargo tonnage of these ships was 49 K ton
10/29/2007 13
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
The average time that a vessel stays in the port differs for the different loading operations. Loading by
ship loader is quicker than by ship born cranes. Loading these ships takes place with a First Come First
Served (FCFS).system. The cargo tonnage of ships calling the Port of Fujairah for loading of aggregates
in 2004, 2005 and 2006 was:
Year 10 – 20 K 20 – 30 K 30 – 40 K 40 – 50 K 50 – 60 K 60 – 70 K Total
2004 26 29 26 57 85 44 267
2005 26 29 26 50 59 23 213
2006 313
table 2.3 Cargo tonnage of aggregate ships calling the Port of Fujairah
Fujairah does not have known significant oil reserves; no oil is produced in Fujairah. The oil handling
facilities only supply for the loading and unloading of ships that fill and empty storage tanks. These
storage tanks are mostly used for speculative storage of oil (further explained in next paragraph). The
materials that are stored in Fujairah are mainly crude oil and petrol’s. No oils for consumption are
handled or stored.
There are two main facilities for oil handling in Fujairah.
- Oil Terminal Berths (OTB’s), 3 berths in the harbour basin of the Port of Fujairah
- The independently operating VHFL terminal outside the harbour basin, four berths and one SPM.
10/29/2007 14
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
VHFL VSPM
VHFL 1
VHFL 3
VHFL 2
VHFL 4 OTB 3
OTB 2
FRCL storage GPS / Emarat
OTB 1
VHFLstorage
As mentioned there are two main unloading facilities. The OTB’s inside the harbour basin formerly
where jetties. In 2006 however the construction of the OTB quay wall was finalized. Following the curve
of the breakwater, there is a bend in this quay wall. The OTB’s 2 and 3 can both handle one medium
sized ship or two smaller ships at the same time. This is made possible by placing four 16” loading arms
as well as two times two 12” inch loading arms.
The total length of the OTB quay wall is 840 m (OTB1 = 240 m, OTB2 and OTB3 each 300 m). There
are totally 8 sets of loading arms (total 20 loading arms) on this quay wall. OTB 1 is dedicated to the
FRCL refinery. There are 2 sets of loading arms (total 4 loadings arms, two black and two white) Each
loading arm is 12”. OTB2 and OTB3 both have 2 sets of 2 loading arms each 12” (two black and two
white) for 2 small vessels (20,000 – 25,000 DWT). Besides these small loading arms, there are 4 loadings
arms, each 16” (two black and two white) for 1 larger vessel (240 – 250 m, 70,000 DWT).
VHFL is a joint-venture between the government of Fujairah (share 20%), the ENOC-subsidiary Horizon
Terminals (30%), Vitol (10%), the Independent Petroleum Group IPG from Kuwait (10%) and
Koninklijke Vopak N.V., having a share of 30% and is responsible for all operational tasks and the
terminal management.
VHFL initially began in 1998 in Fujairah with a storage capacity of 500.000 m3 and two jetties with a
capacity of respectively 150.000 DWT and 60,000 DWT. Since then the storage capacity is expanded up
to 1,1 million m3 and a SPM load and unload facility was installed on which ships up to 175.000 DWT
can berth. It is proven that this SPM operates efficiently but maintenance costs are fairly high.
Currently VHFL has four berths on two finger piers. There are plans to build an extra finger pier directed
to the north, attached to the most sea ward finger.
10/29/2007 15
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
It can be seen that currently the greatest part of the tonnage vessel loading and unloading (65 %) takes
place at the VHFL berths. In the beginning of 2006, the OTB’s where not fully operational. This is partly
the reason that throughput for these berths was lower in this year. It is expected that in 2007 the OTB will
draw near the numbers that VHFL reaches with their facilities.
The berth occupancies for the OTB’s and the VHFL berths are given in table 2.5.
10/29/2007 16
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
this, the Port of Fujairah provides for the marine services. Although the direct benefits for the Port of
Fujairah itself are not very large, there are secondary profits for the Government of Fujairah.
For blending
Products with a relatively low quality are blended with material having a relatively high quality. The low
quality material that is usually cheaper can be improved in this way so that finally the material
requirements are reached. Since the material stays in the tanks for a short period the berth occupancy is
high for blending. Blending takes place in the VHFL terminal. The main sources of supply for this
business are the refiners in Arabian Gulf (Saudi Arabia, Iran, Iraq and Kuwait). It is expected that the
supply is decreasing (especially from Saudi Arabia and Kuwait) due to the increasing cracking capacity
and increasing demand of these countries. Given the diversity of grades coming out of the refineries in
the region there is a strong demand for blending and accumulation of cargoes.
Industrial process
The Fujairah refinery (FRCL storage, see figure 2.6) does not operate as refinery but merely as an oil
storage facility. If it is decided to start any industrial process, storage capacity is required to store the
crude oil as well as the refined product.
It is not foreseen that the existing refinery will restart operating as a refinery but there are plans
10/29/2007 17
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
There are four main storage facilities in Fujairah. The total storage volumes is 2.04 ⋅ 10 6 m3.
- FRCL 0.42 ⋅ 10 6 m3
- VHFL: 1.12 ⋅ 10 6 m3
- Emarat and GPS 0.5 ⋅ 10 6 m
The locations of these terminals are shown on figure 2.6. All these tanker companies only store crude oil
and petroliums. No oils for consumption are stored.
Container handling was one of the major activities of the port of Fujairah shortly after construction of the
port. Nowadays the container handling facilities and the quay that was originally allocated for container
handling is been leased out to Dubai Port. However this particular part of the Port of Fujairah is leased
out, it is still being used. The container throughput however has dramatically decreased. Container
throughput is low nowadays but Dubai Port still recognizes the value of the Port of Fujairah and its
location outside the street of Hormuz. In January 2005, DPI signed agreements with the port authorities
of Abu Dhabi and Fujairah Port, which paved the way for greater cooperation in the UAE's container
terminal operations, giving consistent and equal service levels for customers.
2.11.2 Throughput
The container terminal has a quay length of 1,330m and a depth: 11.5-15m. On this quay 6 Panamax
gantry cranes (40 ft) operate. The total area behind the quay wall is 200,000 m2 in concession agreement
including space used for workshop, shed and offices etc. 7,500 TGS (20' Ground slots) under RTG's
(Rubber Tired Gantries) plus approx 500 TGS in block stacks for Empties using ECH’s (Empty
Container Handling truck). Currently the port uses 11 RTG’s (1 over 3) handling 35ft – 40ft containers.
The capacity of the Port of Fujairah container terminal is approx 1.6 million TEU. In 2005 the throughput
was 65,700 TEU (4% of the total capacity).
The Port handles a significant proportion of the Steel Billets, Steel Bars, Copper Concentrate, Chrome
Ore, Iron Ore, Coal, Bagged Aluminum Hydroxide and Industrial Salt, which moves to and from the
UAE , GCC countries and beyond. A major proportion of the Project cargo associated with the UAE
Federal Qidfa Desalination plant Facility, including the water and Gas Pipeline was handled through the
10/29/2007 18
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Port of Fujairah. The Port of Fujairah has a paved storage area of half a million square meters which can
accommodate general and project cargo.
2.12.2 Ro-ro
Car carriers and Ro-Ro vessels equipped with quarter ramp can be handled. The container storage yard is
currently also used for storage of cars after arrivals of Ro-Ro vessels.
Financial benefits for the Port of Fujairah are categorized in rates for load and unload operations and
rates for marine services. Additional to these two sources of income, users of the aggregates stockpile
area, west of the Port, pay a renting rate for the stockpile surface that is leased. Operation rates are
charged per ton for bulk and general cargo. For containers no operation rates are charged by the Port of
Fujairah. The container quay wall, cranes and other facilities are leased out to Dubai Port so operation
charges are raised by that party. For operations on the VHFL jetty also only charges are raised for marine
services.
The current operation rates (2007) for the various commodities are given in table 2.6:
The stockpile area that is leased out has a total surface of 368,000 m2. The rental rate is 5 Dh/m2 per year.
Recent years the stockpile area was fully occupied. A part of this rate (2 Dh) is paid as a royalty to the
Government of Fujairah which means that 3 Dh is income for the Port of Fujairah.
Several kilometers north of the Port of Fujairah, in the emirate Sharjah also outside the strait of Hormuz,
operates Khor Fakkan Container Terminal (KCT). KCT is a direct competitor on this market for Fujairah
and is merely a container port on which no other commodities are handled. The management and
operation of KCT is taken over by Gulftainer. Gulftainer has the exclusive handling containers on KCT
as well as on Sharjah Container Terminal in Port Khalid (600 m quay). Since Gulftainer has taken over
this function, the throughput has increased dramatically. In 2006, KCT and SCT handled 2.01m TEU,
slightly lower than in 2005, owing to the break-up of the Supergalax consortium. However, Gulftainer
expects growth to top 10% this year.
Gulftainer Company Limited was established in 1976 in the Emirate of Sharjah in the UAE. The
company's prime role is to manage and operate the container terminals in Port Khalid and also
10/29/2007 19
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Khorfakkan on behalf of Sharjah Port Authority. Khor Fakkan has a 1,460 meter long quay having a 16
meter draft alongside. Containers are handled by fourteen ship to shore gantries.
Jebel Ali is located 35 km southwest of the city of Dubai. Jebel Ali is the home port of DP World with
which the Port of Fujairah is to cooperate. The port was constructed in the 1970’s. With 67 berths, Jebel
Ali is the biggest port in the Middle East. Jebel Ali is operated by Dubai Port (DP World). DP World is a
company owned by the government of Dubai. DP World has taken delivery of 14 mega gantry cranes,
installed at the Jebel Ali container terminal in 2005 and an additional 6 in 2006, bringing the total to 45.
These gantries are able to lift two 40 foot or four 20 foot containers simultaneously. In 2006 the total
throughput was 8.9 million TEU. DP world aspires to increase the container transport through the port of
Fujairah to Dubai.
Although this study primarily focuses on the Port of Fujairah expansion project, several other
developments in the Fujairah region will be discussed in this report. For some of these projects, there is a
direct interaction with the expansion of the Port of Fujairah.
North of the proposed location for the expansion plans reclamation of a strip of land is proposed. This
Reclamation Project is initiated to anticipate on the foreseen growth in the demand for oil storage
capacity in Fujairah. This growth is described in paragraph 4.4.3 of this report. The feasibility study for
the reclamation project is not carried out by order of the Port of Fujairah Authorities but for the
Municipality of Fujairah Some choices made in this study depend on the development of this project.
Especially the required soil for the reclamation project affects the choice for the preferred layout of the
Port expansion. B.v. Ingenieursbureau M.U.C. is involved in this project as technical consultant for the
Municipality of Fujairah
DP world is planning to construct a railway between Dubai and Fujairah. This railway is planned to be
executed simultaneously to the expansion of container handling facilities in Fujairah and Khor Fakkan
and will mainly be used for container transport. BV. Ingenieursbureau is not involved in the development
of this transport line.
The road between Fujairah and Khor Fakkan is currently under construction. The number of lanes is
expanded to four and its alignment is changed to give room for industrial development on the onshore
part of the reclamation project location.
10/29/2007 20
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
South of the Port of Fujairah an artificial peninsula is under construction. The final destination for this
peninsula will be for holiday residences. It will take several years until it will be completed to serve this
purpose. Until this time it is used for the loading of dry bulk barges. These barges are currently loaded
here at high rate and for extremely low cost.
The only Hinterland transport mode from and to the Port of Fujairah is road transport. There is no inland
waterways transport system in the UAE and, however there are construction plans, there is currently no
railway system.
Fujairah lies three hours or less from the UAE’s main centers of population, Dubai, Sharjah and Abu
Dhabi. Fujairah currently mainly operates as a bunker port and as a port where material is loaded
produced in the vicinity of Fujairah. Therefore, the main over land transport stream to the harbour is
aggregate trucks. These trucks come from the quarries in the Fujairah region, all less than 30 km from the
port.
There are two main roads between Fujairah and Sharjah, Dubai and Abu Dhabi. These four lane
motorways are currently intensively used by trucks transporting rock from Fujairah to Dubai. The road
between Fujairah and Khor Fakkan is currently being reconstructed into a four lane motorway.
10/29/2007 21
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
3.1 General
In this section the site conditions that are relevant for the design of elements of the new northern Port of
Fujairah extension, are briefly described. A more profound description of the environmental and
hydraulic boundary conditions is given in Annex 1. This annex also evaluates the different sources and
recordings that where analyzed to come to this summary.
All variables have units according to the international SI conventions. Wave and wind directions refer to
the direction from which the waves and winds are coming. The direction is given in degrees, measured
clockwise with respect to North.
3.2.1 Wind
Winds in Fujairah are fairly light. Wind speeds of 8 m/s are not exceeded 90 % of the time but strong
winds from the west do occur. These winds are described as Katabatic winds by the Port Authorities. It is
expected that these north-westerly winds are caused by the “Shamal” weather system.
With a return period of 100 years, wind speeds of 34 m/s can be reached. These winds most likely come
from the Northwest.
3.2.2 Temperature
Fujairah has a tropical climate with a daily average temperature of 34.2°C in summer and 17.8°C in
winter. Temperatures vary between 12.1°C and 24.5°C in winter and between 27.6°C and 42.3°C in
summer.
3.2.3 Visibility
Visibility at Fujairah is generally good but during strong offshore winds, there can be problems with
dust. Visibility is still possible over a hundred meters, allowing berthing using modern navigation aids.
10/29/2007 22
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
The seawater at Fujairah has a density 1024.2 kg/m3. This value has been determined by sample analysis.
Seawater temperatures vary between 22° C and 24° C in winter and between 30° C and 33° C in summer.
3.3 Currents
Current velocities at the location of the proposed Port expansion are relatively low, not exceeding 0.2 m/s
most of the time. Currents are aligned parallel to the coast, mainly directed to the North but currents
directed to the South do occur a few hours per day during low water and in July, during the Monsoon
period.
At the location of the VHFL-jetty, current speeds and directions where measured hourly for several
years. These measurements show a north-easterly directed current with velocities that are relatively low
and do not exceed 0.54 m/s, 90 %.
Alkyon Hydraulic Research and Consultancy has carried out a numerical modelling study to estimate
flow velocities for the waters in front of Fujairah. According to this study the flow velocity is in the order
of 3 to 10 cm/s, depending on the location (nearshore or offshore). The flow is directed towards the north
during the flood phase of tide and directed towards the south during the ebb phase of the tide.
10/29/2007 23
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
3.4 Waves
The normal wave climate at the location of the proposed new Port expansion is mild. Waves are
relatively low, only exceeding 1.5 m 0.5% of the time (1.8 days per year). The main wave direction is
from the East and Southeast. Wave data is available from ship and satellite observations and
measurements at the VHFL-jetty.
Wave heights for different directions at the location of the new Port Expansion, according to transformed
ship observations are distributed according to table 3.4.
Hs (m) 15° - 45° 45° - 75° 75° - 105° 105° - 135° 135° - 165° 165° - 15° Total
[%] [%] [%] [%] [%] [%] [%]
> 0.2 7.86 4.96 7.43 12.67 6.71 .19 39.83
0.2 - 0.4 2.93 3.13 5.48 9.02 2.94 .01 23.51
0.4 - 0.6 1.03 1.42 3.48 5.53 1.20 . 12.66
0.6 - 0.8 .19 .72 2.23 3.23 .39 . 6.76
0.8 - 1.0 .06 .25 .96 1.40 .20 . 2.87
1.0 - 1.2 .02 .14 .37 .68 .08 . 1.28
1.2 - 1.4 .01 .06 .12 .29 .03 . .51
1.4 - 1.6 . .01 .06 .13 .02 . .21
1.6 - 1.8 . . .03 .07 .01 . .11
1.8 < . . .01 .06 . . .07
table 3.4 Percentages of time that the wave heights in the given direction are exceeded at the location of the VHFL-jetty
according to transformed ship observations.
In this table the percentage of time is shown that wave heights are exceeded and come from the given
direction and in the last column, the total percentage of time that wave heights are exceeded (joint
probability of wave height and direction).
It can be seen that the highest waves near shore (at a depth of 14 m) come from a direction between 105°
and 135°. This means that although offshore waves from a more southern direction are higher, due
refraction waves from a direction between 105° and 135° are decisive.
For different water depths, wave characteristics can be summarized according to table 3.6.
10/29/2007 24
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
In normal practice the seismic loads are considered with the UBC 1997. According the UBC 1997
however Fujairah is in seismic zone 0. This will imply no seismic action thus no expected earthquake.
The seismic loading according UBC 1997 will be based on a vertical acceleration of 0.06 g and a vertical
acceleration of 0.075 g.
3.6 Geotechnical
For the Northern Port extension project a full geotechnical investigation has been carried out. This
geotechnical investigation comprises 28 boreholes with full data per bore hole.
The existing sea bed profile as reported by Fugro in the Soil Investigation report as mentioned above
consist of upper soil sediments and underlying bedrock. The sub seabed conditions of the dredging area
consist mainly of very loose, grey to black, medium to fine sand in the upper soil layer. Below this top
layer there is a soft rocky layer which consists most of the time of weak to very weak sandstone, but is
also known to consist of siliceous calcarenite, and conglomerate. At a few places these ‘harder’ layers
have, according to the soil laboratory tests report, an Unconfined Compressive Strength (UCS) higher
than 2 MPa.
The estimated composition of the soil in the dredging area for land reclamation consists approximately:
- 53 % of sandy material
- 47 % of soft rocky material
The highest UCS encountered during the soil investigation in the designated dredge area was 20.78 MPa.
This particular material has been defined as weak to moderately weak conglomerate/calcirudite.
10/29/2007 25
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Further composition percentage of the soil available at the dredging area can be seen in table 3.7:
Percentage of Soil
Soil Type
composition (%)
Sand 38.9
calcareous sandstone 28.4
carbonate sand 8.1
Carbonate sandstone 6.5
Calcarenite 6.4
Calcirudite 5.2
Calcareous sand 3.9
Cobbles 1.4
Calcareous siltstone 0.5
Calcisiltite 0.4
carbonate silt 0.3
TOTAL 100
table 3.7 Soil composition
The Bathymetry of the near shore area in front of the reclamation project area is determined by Gulf
Cobla by survey done in April ’06. The bathymetry drawings from this survey show parallel depth
contours and a bottom slope of approximately 1:100. For a further confirmation of the sea bottom profile,
the sea bottom levels as mentioned in an off shore soil investigation report by Fugro Middle East where
analyzed. The levels mentioned in this report where rather consistent with the result of the survey done
by Gulf Cobla.
The existing quay walls of the port of Fujairah and the pavement of the port areas have a surface level of
CD+ 4.75 m.
3.8 Sedimentation
Based on the available information on the existing harbour basin (and entrance channel) there are no
signs of significant sedimentation. A relatively steep profile (above water level) can be seen just north of
the existing port. This could be interpreted as downdrift erosion.
The existing Port of Fujairah and the port expansion project location is enclosed on both sides by the
Naval Base and the Marina. Both the Naval Base and the Marina have breakwaters that curve out
seaward. These hard structures are assumed to have a positive effect on the sedimentation at the project
location. This effect will probably be that any sediment is stopped by these hard coastal structures.
The harbour master reports that no maintenance dredging is required in Fujairah. Regarding the current
velocities and sediment characteristics not much sedimentation or erosion is expected. This can be
confirmed by the fact that scour around the piles of jetties in Fujairah is negligible.
10/29/2007 26
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
4.1 Introduction
In this part of the study the requirements for the new port layout are described. These requirements are
subdivided in functional requirements and throughput requirements. Based on expectations by the port of
Fujairah several throughput scenarios will be composed. These scenarios give an upper and lower limit to
the expected demand for throughput capacity in the new port. Subsequently a shipping forecast will be
made based on global vessel statistics. Both throughput scenarios as vessel statistics where used as input
values for a simulation study. By this study the required number of berths and cranes and the required
quay lengths for the new layouts will be determined.
The invitation for the masterplan study came with a number of requirements. It has however been made
clear by the Fujairah Port Authorities that these requirements only form the basis for the study and that
all the relevant topics to arrive at the scheme should be studied.
4.2 Commodities
The main commodities that are part of the masterplan study are:
- Liquid bulk
- Dry bulk
- Containers
The market for aggregates in the Middle East is growing considerably due to rapid developments and
expansion plans in this region. Fujairah as a main supplier of high quality aggregates wants to anticipate
and increase its export. The aggregate ship loader of the Port of Fujairah however has reached its
maximum capacity several years ago. The quay that was originally built for container handling is now
being used to load bulk carriers with ship based cranes. Besides the inefficiency of this operation, the
capacity of this solution has also grown to its limit. It is not possible to improve this operation by placing
a new ship loader on the quay since it is leased out to Dubai Port including Container Handling facilities.
In addition to the expansion of the export capacity of dry bulk facilities, there are plans to build a new
steel factory in Fujairah for which additional dry bulk unloading facilities are required. The raw material
for this plant is planned to be brought in by ship. Vessels will be unloaded in the Port of Fujairah.
Besides dry bulk loading facilities, the Port of Fujairah currently offers liquid bulk loading and unloading
facilities. These facilities are primarily being used for the loading and unloading of oil carriers that
supply the oil storage of the Fujairah Refinery (FRCL). This refinery does not operate as a refinery but is
only utilized as oil storage facility.
Although currently three oil terminal berths (OTB’s) can satisfy the required capacity, the oil storage
market is tending to grow rapidly. At the moment many single hull oil storage ships operate in the waters
in front of Fujairah. Due to new international regulations that require a double hull for off shore oil
storage, a great part of this off shore storage will be shifted to onshore. Several local oil storage firms
10/29/2007 27
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
have expressed their interest to increase their storage capacity and to build new oil storage tanks in
Fujairah. The Port of Fujairah wants to anticipate and build the loading and unloading facilities for the
ships that are to supply these new oil storage tanks.
Besides oil, the Port of Fujairah wants to anticipate on a possible growth in the demand for throughput
capacity of chemicals.
4.2.3 Containers
However the Port of Fujairah is not using their container loading facilities actively, Dubai Port that is
current leasing the quay and cranes in the Port of Fujairah has expressed their desire to be able to unload
bigger vessels and handle more containers. This is not possible with the current facilities. The Port of
Fujairah intends to investigate the possibilities of handling large size container vessels.
The two main requirements given by the Port of Fujairah Authorities for the location of the new Port
expansion are that the port is in the vicinity of the existing Port of Fujairah and that the port expands
northward. The preferred location for the port expansion project is shown in figure 4.1.
Ships
Possible location approach
Port Expansion line
VHFL jetty
Existing Port
The main reasons to realize the port in the vicinity of the existing port are the following:
- To limit the distance between all existing harbour facilities and the new port. The distance that the
tugs have to travel for berthing assistance is very important and should be minimized. Finally it will
be necessary to settle a new tugboat facility inside the new harbour basin, but for the earlier phases,
the tugboat facility of the existing port will most likely be used.
10/29/2007 28
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
- To limit the distance between the aggregate stacking area and the aggregate berths. This distance
determines the length of the conveyor belts. The length of a conveyor belt partly determines the
construction cost as well as operation cost.
- To limit the distance between the oil storage facilities and the oil tanker terminal. Long oil transport
pipes will require booster stations. Booster stations ensure adequate flow velocities in the pipes.
Because of the extra construction and operation cost of these facilities, they should be avoided if
possible. However when flow velocities are too low, load or unload operations will last unacceptably
long.
Realization of the new port expansion north of the existing port is preferred for the following reasons:
- There are several developments planned south from the existing port. Southward expansion is
impossible without affecting these plans. One of these plans is the construction of a dry dock on this
location. There are intentions to develop this area with other functions than port function. However it
is preferred not to use this land, southward expansion is not excluded from possibilities.
- An expansion of the port southward will affect the approach of ships to the existing port. The
approach channel of the existing port is directed to the south. Breakwaters for a new port expansion
will form an obstruction. In general the safe approach of the existing port should be maintained.
- North from the VHFL a strip of land is planned to be reclaimed from the sea. On this strip of land
several oil storage tanks will be realized. The distance from the oil terminal to these tanks should not
be too long to avoid the necessity of booster pumps or low flow velocities.
The location of the berths for different commodities within the port expansion depends on the specific
requirements for the berthed vessels and connections to onshore facilities.
With the generation of layouts the navigational safety of ships approaching the existing harbour, the
VHFL terminal and the new port expansion will have to be taken into account. Sufficient space for
turning is required. These requirements are further described in paragraph 4.9. The requirements for the
location of the main commodities in the port expansion are described in the following paragraphs.
Since the wave climate in front of Fujairah is mild and oil vessels have large critical wave heights, it may
be possible to operate an open sea tanker terminal without having excessive downtime. The tanker
terminal north of the existing port that is operated by VHFL can operate economically in an unsheltered
area. Realization of the oil terminal outside the harbour basin is preferred since a breakwater protecting
the oil terminal at deep water will be very expensive. For this reason the feasibility of an open sea tanker
terminal is investigated. The feasibility of handling oil at open sea partly depends on the downtime at the
jetty.
Downtime at a new terminal at open sea depends on:
- Waves
- Currents
- Wind
Downtime due to waves occurs when the critical wave height, for which load or unload operations are
aborted is exceeded. The critical wave height depends on the vessel type and size and the angle of attack.
The critical wave height for oil vessels is relatively large. The wave parameters height and direction
differ over the water depths due do refraction and shoaling. Further the reflection of waves by coastal
structures influences the wave height at the berths.
In table 3.4 the wave climate at the project location is given. This table is used to estimate downtime at
an unsheltered area. It is assumed that an open sea tanker terminal will be realized at a depth of between
10/29/2007 29
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
CD - 14 m and CD – 18 m. Due to refraction and shoaling, the direction and height of waves at the
location of the open sea tanker terminal.
At the VHFL terminal, operations are aborted when a wave height of 1.2 m at the bow of the ship is
exceeded, 1.5 m bow quartering waves and 2 m head and stern waves. These criteria are used for all ship
dimensions at the VHFL jetty. Using the data presented in table 3.4, it is estimated that operations must
stopped for not more 0.99 % of the time which is 3 – 4 days per year. The real average downtime at the
VHFL jetty is 3 – 5 days per year which is comparable.
For the new terminal the limiting wave criteria as given in table 4.1 are assumed.
With these criteria and the wave parameters from table 3.4, the downtimes of two vessel sizes are
estimated. The results are given in table 4.2. Downtime in
Current velocities may affect oil handling at open sea. As can be seen in table 3.3, current velocities in
Regarding the estimated downtime due to wave height exceedence and the experience that VHFL has
with oil handling at open sea, it seems feasible to realize the oil terminal outside the area sheltered by
breakwaters.
front of the coast of Fujairah are very low. This table indicates that 90% of the time, the current velocity
stays below 0.54 m/s. It is assumed that these velocities do not affect the operation.
Wind is assumed to have the same effect inside the harbour basin as outside the harbour basin and does
therefore not influence the location of the oil terminal.
When the liquid bulk terminal is realized outside the protected harbour basin, the orientation of these
berths with respect to prevailing wave and current directions influences the downtime of this terminal.
Berthed vessels are generally more sensitive for bow waves than for head or stern waves. This is due to
the fact that the width of the ship is smaller than its length. A wave attacking a vessel at the bow will
cause a roll angle that is larger than the pitch angle caused by the same wave, attacking the vessel from
the head or the stern. Since the prevailing wave direction is from the Southeast (as can be seen in table
3.4) and the highest waves are expected to come from this direction, the preferred alignment is with the
head of the vessels in South-eastern direction. VHFL however has aligned their berths perpendicular to
the beach. This means that waves from the dominant direction attack the ships obliquely.
Besides a jetty attached to the shore, the feasibility of Single Point Mooring Buoys will have to be
investigated. The location of these facilities can be near the proposed location of the oil terminal or in
front of the Fujairah Land Reclamation project area.
Loading of dry bulk vessels can be executed in a relative exposed location. Dry bulk vessels are filled at
one single point which is not connected to the ship. Unloading operation of dry bulk vessels has a lower
critical wave height. To operate the grab or bucket wheel in the vessel the ship must be kept relatively
stable as contact with the ship is unavoidable. The downtime on the quay due to exceedence of the
critical wave height partly dictates the location of the dry bulk quay wall. The port authorities desire a
flexible port in which quay functions can be changed if demand for handling capacity of commodities
shift. It is assumed that dry bulk berths (loading and unloading) can not operate economically at open
10/29/2007 30
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
sea. The locations of the dry bulk berths in the proposed harbour layouts will therefore be in a sheltered
area protected by breakwaters.
Regarding the location of the dry bulk berths, a short distance between stockpile area and quay wall is
preferred, to limit the length of relative expensive conveyors. Since the stockpile area will not be directly
behind the quay wall, and material is transported by conveyor belt, the required land behind the quay
does not need to be very wide.
The critical wave height for container handling is very low. Container handling has the risk of the
spreader getting stuck in the cell guide due to vessel motion. The container terminal should therefore be
realized at a location sheltered from waves. Other than dry bulk and oil handling, container handling
requires a relatively large area behind the quay wall for stacking containers.
A thorough market and cargo flow investigation reaches beyond the scope of this study. For this reason
three scenarios will be used for each commodity, weak, medium and strong growth of the demand for
throughput capacity. These scenarios are not forecasts but only assumed possible developments of the
size of the cargo flows through the Port of Fujairah. For each commodity, three scenarios are composed:
- Scenario 1: Strong growth, representing the upper limit of the demand for throughput capacity.
- Scenario 2: Medium growth
- Scenario 3: Weak growth or decrease in the demand for throughput capacity.
Off course the size of the cargo flow does not only depend on the demand for a certain product but also
on the available handling capacity of the port, availability of vessels to transport the material. On the one
hand, there is the direct demand for a product. On the other hand, the presence of the port facilities will
help attract new industries. This complicated interaction is very hard to predict and reaches beyond the
scope of this study.
Developments that can not be foreseen at this moment can have a great impact on the throughput figures
of the expanded Port of Fujairah. An example of a political decision which has had great influence is the
decision to let the floating storage phase out. This will have as a consequence that the bunkering market
will be served from the port, and onshore storage capacity will have to increase dramatically. Other
developments in the Middle East and the growth of the population in the area will have a large effect on
the demand for aggregates used in the building industry. Because of uncertainties and the restriction of
this study on this subject, the margins between the scenarios on the long term will be quite large. The
scenario will not be a throughput forecast but will be assumptions within reasonable limits. The scenarios
will be based on several grounds:
10/29/2007 31
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
them. Economic growth will generally increase the demand for all commodities and regression will
restrain the growth or cause a decrease in the demand.
To follow the growth of the cargo flow through the port, the expansion project will be executed in three
phases. Since the rate of this growth is not known, the timing of these phases can not be determined
exactly at the moment. Only the recent throughput capacity demand can be approximated and the
demand for the near future can be forecasted. The second and the third phase are executed when it is
foreseen that the need for new facilities will be there within several years.
- Phase1
The first phase will supply for the current demand in throughput capacity and will serve for the
required capacity for the coming 5 years. This is more or less known for aggregates and oil. For
containers, the plans from Dubai Port are less transparent.
- Phase2
The second phase will cater for the following 10 years of the project. The layout of this phase differs
for the different scenario’s. If there are large differences between the main commodities. It may be
possible to split the execution of this phase in time for different commodities.
- Phase3
The last phase will be the fully developed port after 25 years. Different fully or partly developed
layouts will be proposed for this phase for different scenarios. This layout will be the final layout of
the port for the expansion plan as described in this study.
10/29/2007 32
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Regarding the production of aggregates, there is virtually no limit to the possible amount of material
produced per year and to the available amount of material. The amount of quarried rock is negligible in
relation to the total volume of available rock in Fujairah.
Besides the construction of the cement factory and the bauxite plant, there are no other known
developments that require large amounts of raw material to be imported.
10/29/2007 33
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
The market for bunker-fuels in Fujairah is foreseen to continue its growth and more and more volumes in
this industry will need to be handled onshore. The market for building bulk and blending on specification
of fueloil will continue, even as supply and demand patterns in producing and receiving countries are
subject to change.
Regional developments in the Arabian Gulf will have a positive impact on bunker sale volumes in
Fujairah. The seven countries within the Arabian Gulf basin have embarked on massive scale
development projects, particularly in the area of oil, gas and chemicals leading to an anticipated increase
in vessel activity passing the Strait of Hormuz.
The UAE authorities have observed the MARPOL regulations, though the UAE is not yet a signatory to
the MARPOL regulation. Marpol is the International Convention for the Prevention of Pollution From
Ships, 1973 as modified by the Protocol of 1978. (Marpol" is short for marine pollution) The Port of
Fujairah has banned single hull tankers older than 25 years from entering its territorial waters (except for
non-oil related activities). The port also announced that single hull tankers aged between 15 and 25 years
involved in moving dirty petroleum products must have so called CAS Certificate (Condition Assessment
Scheme) and flag state SOC.
Oil handling
The amount of oil through the port of Fujairah is directly linked to the volume of oil stored. The cargo
flow through the Port of Fujairah is determined by two main factors:
- The total storage volume that must be served and the average occupancy of these storage tanks.
- The term that oil is stored in the storage tanks in Fujairah.
At the moment it is known that in addition to the existing oil storage firms at least three new parties have
shown interest in investing in storage tanks in Fujairah. These firms are Enoc and Joint Venture I and
Joint Venture II. The total volume that these parties intend to install is roughly 3 million m3.
For the total development of the demand for storage volume, three scenarios have been composed. It is
assumed that there will be growth in the demand for oil storage in any case. In the first phase, the
demand is more or less equal for all three scenarios. After phase 1, the total demand for oil storage is
expected to reach 3 - 4 million m3. The scenarios represent the following growth in demand for storage
capacity:
- Scenario C1: In this scenario, the demand for storage capacity will eventually increase to a level of
11 million m3 in the third phase. The growth will continue during the first half of the third phase.
- Scenario C2: Medium growth in the demand for oil storage capacity. After phase 3 the demand will
be 8 million m3.
- Scenario C3: For this scenario, the growth in the demand in the second phase is less. In the third
phase hardly any growth. The demand at the end of phase 3 is 6 million m3.
The term that oil is stored determines the cargo flow through the port. Long term storages will require
less capacity from loading and unloading facilities than short term storages. It is assumed that during the
entire project life the storage terms are distributed equally. These terms are divided in long term, medium
term, short term and very short term storage. These can be devided as follows.
- Long term storage (> 1 year), mostly strategic, is generally large volumes. This type of storage does
not have a large effect on berth occupancy. The material is brought in with large vessels. It is
assumed that the demand for this type of storage is 40% of the total demand for storage capacity.
Further it is assumed that the long term storages are mainly crude oils, 80%, against 20% petroliums.
- Medium term storage (6 – 12 months) are mostly speculative storage. Since the material stays
relatively long in the tanks, the occupancy at the berths is not high. It is assumed that the demand for
this type of storage is 20% of the total demand for storage capacity. Like Long term storages it is
again assumed that these types of storages mainly concern crude oils, 70%, against 30% petroliums.
10/29/2007 34
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
- Short term storage (3 – 6 months): Generally speculative storage. It is assumed that the demand for
this type of storage is very low, 5% of the total demand for storage capacity. This type of storage is
assumed to be as much crude oils as white products.
- Very short term storage (<3 months): Storage for blending, bunker fuel storage and break of bulk and
make of bulk. Since the material is for a short period in the tanks, the occupancy at the berths is
largely determined by these types of storage. It is assumed that the demand for this type of storage is
very rather high regarding the fact the bunker trade is and will be very important for the Port of
Fujairah. Therefore it is assumed that the demand will be 35% of the total demand for storage
capacity. Since blending and storage for the bunker market are white products, it is assumed that the
largest parts of this storage are white products (petroliums).
This can be graphically represented as shown in graph 4.1.
31% 31%
Long term black
Long term white
Medium term black
Medium term white
Short term black
4%
8% Short term white
3%
Very short term black
3% 14% very short term white
6%
graph 4.1 Oil storage terms and percentage of black or white products.
According to the above mentioned assumptions, a storage tank is filled and emptied, 4.8 times per year
on average. The total stored volume of black products (crude oil, 52%) is almost as big as the total
volume of white products (petroliums, 48%) as can be seen in graph 4.2. The second pie in graph 4.2
shows the total handled volume of oil. The amount of handled white product is considerably larger. This
is due to the fact that the storage term of petroliums is generally shorter than that of crude oils.
Stored volume Transport
17%
Crude oils
48% 52% Petroliums
83%
graph 4.2 Storage and transport of black and white products (crude oils and petroliums)
According these assumptions, for storing one ton of oil for one year, 9.6 ton of oil is handled at the
berths. Of this total amount of transported material, 1.63 ton will be black products and 7.97 ton will be
white products.
10/29/2007 35
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
In the case that the demand for oil storage capacity develops according to scenario C1, the total
throughput after 25 years will be more than 100 million ton per year. According scenario C3, the
throughput will be 50 million ton per year.
4.4.4 Containers
DP World has signed management contracts in Fujairah. DP World plans to build up its container traffic
to complement operations at Jebel Ali. The port is seen as an east coast hub that could handle 6,000 TEU
container ships and can reach a throughput of 3 million TEU per year. In this way the port will give a
strategic position. Dubai Port has the intention to improve the existing container facilities and to build
new quay walls and storage areas. Parallel to increasing container handling capacity in Fujairah, Dubai
Port has the intention to construct a railway connection between Fujairah and Dubai.
Currently, the amount of containers handled in the Port of Fujairah is very low. However because of the
above mentioned developments, the required container handling capacity of the Port of Fujairah is
expected to grow significantly.
Again three scenarios have been composed according to which container throughput may develop.
- Scenario D1: This scenario represents very strong growth in the demand for container handling
capacity in the Port of Fujairah. Immediately after the start of phase 1, the demand increases until a
throughput capacity of more than 1 million TEU per year is required. After phase 2, the demand is
3.5 million TEU.
- Scenario D2: Represents moderate growth. After phase 3 a throughput of 3 million TEU is required.
- Scenario D3: Represents limited growth. The final demand for throughput capacity is 1 million TEU
after phase 3. In phase 1 there is hardly any growth.
Based on Dubai Port Statistics, it is assumed that 60% of the total container throughput is import and
40% is export. It is further assumed that all these containers are transported over land, where 50% is
transported by the planned railway line to Dubai and 50% is transported by truck. It will probably take
several years until the railway line is operational. Until finalization of this project, all containers are to be
transported by truck. Modal split as shown in 4.2 is assumed for further calculation.
The Port of Fujairah Authorities have indicated that an increase in the trade of chemicals is expected.
Currently chemicals are being handled on a small scale within the existing Port. Volumes and
requirements for this commodity are not known yet. For this study the possibility of chemicals handling
is considered.
10/29/2007 36
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
4.4.6 Summary
The scenarios described in the previous paragraphs are summarized in table 4.3.
Chemicals Sc 1 [M ton/yr]
2007 0.1
End of phase 1: 2012 0.2
End of phase 2: 2022 0.5
End of phase 3: 2032 1
table 4.3 Summary throughput scenarios
Numbers of vessels and vessel dimensions partly determine the development of the port expansion.
Important dimensions are the length over all (LOA), draught and beam. The length governs the length
and layout of single berth terminals, the length of the quays. The length also influences the width and
bends of channels and the size of the turning areas. Beam or breadth; governs the reach of cargo handling
equipment and influences the width of the channels and basins. Draught; governs the water depth along
the berths, in channels and in basins. Further , the vessel size distribution has a large influence on the
capacity of the new facilities.
The Port of Fujairah Authorities demand that Cape size aggregate vessels can be handled in the new port
expansion. These vessels have a size of generally 150,000 to 175,000. The longest vessels with this
weight have a length of 300 m. The draught of this class is up to 18 m. According to Lloyd’s register
vessel statistics, there is a large group of these vessels.
10/29/2007 37
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
The Port of Fujairah Authorities also demand that the new liquid bulk terminal must be able to handle oil
tankers up to cape size. These tankers also have draughts up to 18 m.
The water depth in front of the current aggregate loading berths is 15 m. According to the Lloyd’s
register of shipping of 1999, 67% of the ships with this draught have a size between 70,000 and 80,000
DWT. From the ships with this size, 55% had a length over all of between 225 and 229. This means that
the largest expected dry bulk vessels in the existing port of Fujairah have a length of 230 m. Statistics
from the Port of Fujairah about the measured length of ships calling the Port of Fujairah show that the
largest group of vessels do not have the maximum length and that the maximum length is indeed 230 m.
The point of gravity lies between 180 and 200 m.
Further, the LOA of dry bulk vessels as by the data from Lloyd’s tables seems to be consistent with the
actual distribution of vessel sizes calling the Port of Fujairah. In these statistics the point of gravity of this
range, also lies around a length of 190 m as well. Of course, the percentages of the total sum are
different, but this is due to the fact that for the Lloyd’s register statistics, an amount of ships larger than
230 m is taken into account. For further calculations, the distribution of lengths according to Lloyd’s
register vessel statistics will be used for forecasts of ship sizes calling the new Port of Fujairah and
throughput estimations. These estimations will be carried out by simple simulation models. In these
models, average dimensions of four different ship sizes (Handysize, Handymax, Suezmax and Panamax
and Cape Size) will be use.
Handysize, refers to a dry bulk vessel with deadweight of 15,000–50,000 tons. Above this size are
Handymax bulkers. Handysize is the most widespread size of bulk carrier, with nearly 2000 units in
service for a total of 43 million tons of carriage. Handymax is typically between 35,000 and 60,000
deadweight tonnage. A handymax is typically 150-200 meters in length, though certain bulk terminal
restrictions such as those in Japan mean that many handymax ships are just under 190 meters in overall
length. Modern handymax designs are typically 52,000-58,000 DWT in size, have five cargo holds and
four cranes of 30 metric ton lifting capacity. These smaller Handysize and Handymax vessels are general
purpose in nature, and not only comprise 71% of all bulkers, but also have the highest rate of growth.
This is partly due to new regulations coming into effect which put greater constraints on the building of
larger vessels. The growth of the economy of the People's Republic of China (with its great demand for
raw materials) and increasing congestion in the Suez and Panama canals has led to an increase in the
number of capesize vessels ordered.
Data from Lloyd’s register of shipping on dry bulk vessels are summarized in table 4.4.
Dry bulk vessels DWT Length [m] Draught [m] Breadth [m] %
Handysize 6,000 – 50,000 120 – 220 6 – 12.5 15 – 30 71 %
Suezmax/Panamax 50,000 – 100,000 200 – 250 10 – 15 30 – 40 21 %
Cape size 100,000 – 150,000 240 – 285 15 – 17.5 38 – 48 4%
Cape Size 150,000 – 175,000 265 – 300 17 – 18 45 – 48 4%
table 4.4 Dry bulk vessel size distribution according to Lloyd’s register vessel statistics
The distribution of liquid bulk vessel sizes can also be made according to Lloyd’s register vessel
statistics. These data are shown in table 4.5. Though for the different storage types (for example
bunkering) specific vessels are used to transport the oil to and from the storage tanks. For this reason, the
data as given in table 4.5 will not be used for estimation of throughput capacities but the specific vessel
dimension that is connected to the type of storage. This is further described in paragraph 4.7.3.
10/29/2007 38
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Since detailed insight in future development of ship types and ship sizes is not available and falls beyond
the scope of this study, assumptions will be made on which agreement is reached with the Fujairah Port
Authorities. The basis of these assumptions will be information derived from Lloyds Register vessel
statistics (1999).
It is assumed that as a result of the size of container flows around the world and their potential,
containerships are the only ships that will increase further in size. For other commodities than containers
(oil and dry bulk), it is assumed that ship sizes have reached their optimum and will not develop
significantly. It is further assumed that the optimal container vessel size will lie between 17.500 and
20,000 TEU and that the Europe – Far East routes and the Trans Pacific routes are the only routes where
ships of this size can perform economically.
As mentioned, container vessels are likely to increase in size significantly, especially at the routes
between Europe and the Middle East. These vessels that can carry up to 20,000 TEU are likely to have a
larger draught than the 15 m of the existing port but will not exceed an 18 m draught.
General cargo does not form part of the commodities in the primary studies for the new port extension.
However use of the new port extension by general cargo ships is not excluded from this study, it is not
expected that the design is influenced by these ships.
As mentioned above, container vessels are the only ships that are expected to increase in size
significantly. In table 4.6, the assumed distribution of container vessel sizes are given.
10/29/2007 39
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
aggregates loading do not have to be close to each other. It is proposed that the ship loader inside the
existing harbour basin remains operational as the port expands.
4.7.1 Introduction
In the previous chapters, demand for throughput capacity scenarios where composed and vessel size
distributions where assumed. In this paragraph, the required number of berths and cranes to reach the
required throughput is determined. The aim will be to maximize the berth occupancies and minimize
quay length and waiting time. Berth occupancies and waiting times are determined by simple simulation
runs. The details and results of the various simulations are given in Annex 3. Simulation is required if
analytical solutions are not available. In this situation this is due to the fact that the berth concept is
replaced by the total length of the quay concept and all arriving ships can not be accommodated at all
berths.
Subsequently the required quay length is determined. For multiple berths in a straight continuous quay
front, the quay length is based on the average vessel length, according to formula [4.7.1].
( )
Lq = 1.1 ⋅ Ls + 15 + 15 [4.7.1]
10/29/2007 40
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
This allows for a gap of 15 m between the ships moored next to each other and additional 15 at the two
outer berths. The factor 1.1 allows from a study carried out by UNCTAD. For a number of actually
observed ship length distributions and for the relation average berth length / average vessel length as a
variable, the probability of additional waiting time as a result of simultaneous berthing of several above-
average vessels was determined (UNCTAD, 1984).
The required length as determined in this part of the report will only give an indication which will be
used to compose different harbour layouts. Allocating different function to one quay wall may reduce the
total required quay length.
10/29/2007 41
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
The details of the simulation study are described in Annex 3. The results of the simulation study are
given in table 4.7. As can be seen from this table the berth occupancy gets higher as the number of berths
increases.
Required Total new quay Total no of new Average berth Average waiting
throughput length cranes occupancy time
[M ton/yr] [m] [hr]
15 340 1 44% 1.23
20 605 2 37% 0.67
30 645 2 52% 0.95
40 810 3 50% 1.48
50 910 3 63% 1.60
60 1190 4 57% 0.50
70 1190 4 66% 1.00
80 1335 5 62% 1.04
90 1395 5 68% 1.01
100 1435 5 77% 1.95
table 4.7 Simulation results aggregates.
The port Authorities have indicated that a ship loader that works from a quay wall is highly preferred
over an open or platform construction. A jetty construction will not fit in the port plans since a
commodity shift is easer when a quay wall is applied. To make it possible to handle other types of cargo
on the quay the main effort will be to change the super structures. Off course the required land behind the
quay is less for a ship loader with conveyor belts and stockpiles at some distance from the loading cranes,
than for example the land that is required for container storage. This means that the width of the land
behind the quay wall should not determined just to fit for conveyor belts but will allow the handling and
storage of other materials than aggregates. The port has also negative experience with a ship loader on a
jetty and the filling procedure of the vessel.
Additional advantage of a quay wall is the flexibility in which ships can be moored and the fact that if
necessary one ship can be served by more than one ship loaders if available.
Disadvantages of a quay wall over a jetty construction are the cost and the influence on the wave climate
in the harbour basin. The construction costs of a quay wall are most likely higher than for an open
structure. A quay wall has a wave reflection coefficient that is much higher than the coefficient of the
slope protection behind an open structure. The negative influence of the quay wall on the wave climate in
the harbour basin will be much higher than for an open structure.
The required quay length for the three phases and scenarios does greatly depend on the distribution of
vessel sizes. As mentioned, the preferred crane type is a traveling shiploader. This means that the loading
point can be varied over the length of the quay. The number of large cape size dry bulk vessels is limited
as can be seen in table 4.4. The chance that a cape size vessel arrives while an other large size vessel is
being loaded is small. Simulations show that there is hardly any influence on the berth occupancy and
waiting times for the same throughput if the quay length for two vessels is reduced such that two cape
size vessels can not berth. The port authorities have indicated however that at least in the first phase, they
desire a quay that can handle two of the largest size vessels at the same time.
10/29/2007 42
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
For scenario B1, one crane will be sufficient to serve for the demand until the end of phase 1. For phase 2
and 3, a second crane is needed. Scenario B2, representing medium growth, it will be possible to serve
for the demand in import capacity for phase 1 and 2, eventually in phase 3, a second crane is needed. In
scenario B3, import increases only slightly. It will not be necessary to realize the proposed ship unloader
with conveyor belt. In fact, these amounts of material can be handled by ship based crane (lift and grab
operation) at an unoccupied quay in the new or existing port.
The role of the Port of Fujairah in the oil storage and trading process is primarily to deliver the oil
handling facilities for the oil storage and stevedoring companies. Besides the guaranty of safe navigation
in and around the port this comprises providing sufficient berths to avoid long waiting times and the
ability to reach sufficient loading and unloading discharge rates. Pumps are located at the storage
facilities; the Port is responsible for piping and loading arms.
For the planning aspects if the new liquid bulk terminal, it is assumed that the vessel size distribution
according to table 4.5 does not represent the distribution of vessel sizes that is expected at the new oil
terminal. It would be more appropriate to assume that vessel sizes depend on the function of the delivery.
Per storage function and for import and export, an average vessel type is assumed. Material with longer
storage times is transported by larger vessels. Material for blending is transported by medium size
vessels. Bunker fuel storage is replenished by large size vessels. The bunker vessels are smaller ships.
These assumptions will be used for throughput, waiting time and berth occupancy calculations and are
summarized in table 4.9. The second and third columns give the percentage of the total storage volume
that is used for the specific function. The last to columns give the ship sizes that are used for the specific
delivery.
10/29/2007 43
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
The speed of the load and unload operations of these ships depend on the flow velocities in the pipes, the
diameters of loading arms and the number of loading arms per berth. The flow velocities again depend on
the onshore pump capacities, the onboard pump capacity of ships and pipe properties. The following
average flow velocities for load and unload operations are assumed. (based on VHFL experience and
calibrated with VHFL berth occupancy and waiting times)
- Loading of black material: 3 m/s
- Unloading of black material 3.5 m/s
- Loading of white material: 4 m/s
- Unloading of white material 4.5 m/s
The velocities for clean products (white) are higher as these have a lower viscosity and less pipe
resistance as a consequence.
The distribution of the inter arrival time of the ships is assumed to be Erlang 3. The arrival pattern is
expected to be relatively regular. The idle time is assumed to be 3 hours on every berth and ship size. The
system is assumed to be First in First Out. With the parameters described in this paragraph, the
throughput capacity of several numbers of berths having several different sizes has been estimated. The
current berths OTB1, OTB2 and OTB3, as described in paragraph 2.10.2, are assumed to be part of the
total system so they are implemented in the model. The model has been used to estimate the maximum
throughput of the OTB’s for an average waiting time, not longer than 1 hour. It resulted from this test
that the OTB’s can handle a total throughput of 16.4 M ton per year. With the distribution of storage
times as given in graph 4.1, this means a total storage volume of 2.13 M m3 can be served with this
facility.
The model was calibrated by analysis of the existing VHFL terminal throughput, waiting times and berth
occupancy data from 2006. For several storage volumes the required number of berths is determined
using all assumptions mentioned in this report. These proposed numbers of berths are given in table 4.10.
These figures present the outcome of the simulation study including the OTB’s.
OTB 1 and OTB 2 can both be used for one medium size vessel of for two smaller vessels. Since these
berths are in the sheltered harbour basin, it is proposed that as they are used for handling the smaller
tankers. These tankers will suffer a higher downtime if they are berthed at the more exposed Open Sea
Tanker Terminal. The range of bigger tankers will be handled at the new OSTT. These vessels are less
sensitive for wave motions.
10/29/2007 44
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
4.7.4 Containers
The dimensions of the new container terminal is based on assumptions on the following assumptions:
- Container vessel sizes are distributed according to table 4.6 derived from Lloyd’s register vessel
statistics. Besides this, growth of vessel sizes is taken into account by allowing the anticipated
vessels with sizes of up to 400 m and 11,000 in the new port expansion.
- The TEU factor is assumed to be 1.7. This means that twice as much FEU (Forty feet Equivalent
Unit) as TEU are expected in the new port. This TEU factor is determined with the following
expression: f = (N 20 + 2 ⋅ N 40 ) N tot .
- The gross production of the cranes is assumed to be 25 TEU moves per hour. The assumed maximum
number of cranes is given in the last column of table 4.11.
- The ship sizes as shown in table 4.11 are assumed, taking into account the Lloyd’s register vessel
statistics and the assumption that ships will continue to grow in size. For the calculation of waiting
times and berth occupancies when a throughput capacity of 0.5 M TEU is required, it is assumed that
the largest ships do not call the port of Fujairah.
10/29/2007 45
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
TEU Length [m] Draught [m] Breadth [m] % of ships Max number
of cranes
100 – 1000 75 – 185 3 – 10.5 11 – 28 30 % 2
1000 – 2000 145 – 214 8 – 12 23 – 33 32.5 % 3
2000 – 3000 180 – 260 10 – 12.5 29 – 33 15 % 4
3000 – 4000 235 – 285 11.5 – 13 32 – 33 10 % 5
4000 – 5000 250 – 300 12.5 – 14.5 32 – 38 5% 6
5000 – 7000 265 – 315 12.5 – 14.5 38 - 42 5% 8
7,000 – 11,000 315 - 400 14.0 – 15.5 42 - 56 2.5 % 10
table 4.11 Container vessel size distribution used for simulation
- The number of containers that need to be handled per vessel is 50% to 100% of the total vessel
capacity, equally distributed between this maximum and minimum. It is further assumed that import
and export of container is according figure 4.2.
- The simulation is carried out using a fixed number of berths. This means that the throughput
capacity, berth occupancies and waiting times are not determine for a number of quay lengths.
Instead the number of berths, the berth capacity and the number of cranes are varied to find
acceptable values for waiting times and occupancy. It is assumed that an average waiting time of 0.5
hours is acceptable.
- For the determination of the waiting time an average downtime of 3 days is assumed. This downtime
represents the downtime due to unworkable weather, unusable cranes due to maintenance and
downtime due to exceedence of the maximal allowable ship movement. This movement is caused by
wave penetration. The wave penetration depends on the layout of the port, the protection of the
harbour basin by breakwaters and the reflection coefficient of the quays.
- The total required quay length as given in table 4.12 is determined using [4.7.1].
Using the above mentioned assumptions several number of berths and cranes where tested. The results of
these simulations are given in Annex 3.
According to the composed scenarios as proposed in paragraph 4.4, it can be seen that for scenario D1, at
the end of phase 1 a total quay length of 1432 m is required. For scenario D2 a total quay length of 775 is
required at the end of phase 1, 1702 m at the end of phase 2 and finally after phase 3, 2050 m to able to
handle 3 M TEU per year. In scenario D3, a total length of 1022 is required to be able to handle the total
throughput of 1 M TEU/yr that is anticipated for at the end of phase 2 and 3 in this scenario.
10/29/2007 46
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
4.7.5 Chemicals
In scenario 1 it is anticipated that there might be an increase in the demand for the handling capacity of
chemicals. For this reason one berth for handling of chemicals is considered is the first construction
phases and 2 berths in the last construction phase.
PHASE 1
Scenario 1 Scenario 2 Scenario 3
Quay No of Quay No of Quay No of
length cranes length cranes length cranes
Aggregates 910 3 810 2 810 2
Other dry bulk 280 1 280 1 - -
Oil 2 berths - 2 berths - 2 berths -
Containers 1432 19 675 9 675 9
Chemicals 1 berth - - - - -
PHASE 2
Scenario 1 Scenario 2 Scenario 3
Quay No of Quay No of Quay No of
length cranes length cranes length cranes
Aggregates 1395 5 910 3 810 2
Other dry bulk 525 2 280 1 - -
Oil 5 berths - 4 berths - 3 berths -
Containers 2110 40 1927 28 1022 15
Chemicals 1 - - - - -
PHASE 3
Scenario 1 Scenario 2 Scenario 3
Quay No of Quay No of Quay No of
length cranes length cranes length cranes
Aggregates 1435 5 910 3 340 1
Other dry bulk 525 2 525 2 - -
Oil 6 berths - 4 berths - 2 berths -
Containers 2110 40 2050 36 1022 15
Chemicals 2 - - - - -
table 4.13 Summary required quay length and number of cranes
10/29/2007 47
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
therefore depends on the width of aggregate loading cranes, the number of conveyor belts and the width
for these conveyor belts. The number of conveyor belts that have to operate next each other both depend
on the scenario as on the proposed layout. The required area will therefore be determined per proposed
layout.
The current conveyor belt has a capacity of max 2,200 tons per hour. The new conveyor is planned to
have almost a doubled capacity of 4,000 tons per hour. The required width for this conveyor is 15 m. The
placement of conveyors next to each other is preferred over the placement of one conveyor over each
other.
Stockpile area
The current stockpile area is fully occupied by the Fujairah Rock and aggregate which quarry is direct
behind the Port of Fujairah. As mentioned, the aggregate from other quarries is supplied at the conveyor
feeder point as the vessel is laden. It is possible to feed the conveyor by four trucks simultaneously. With
the increase of the exported tonnage of aggregates and the increased export rate however, a more
effective approach is required. Instant delivery and filling with the new rates will require a drastic
increase in the amount of trucks from the quarries. The design of a new aggregate supply system falls
beyond the scope of this study. It is however assumed that more space is necessary to be able to feed
vessels with a sufficient rate.
Conveyor belts
For the end of phase 3 in scenario A1 the total export amounts100 M ton. In table 4.13 it is estimated that
5 cranes with an average capacity of 3,300 ton/hr are necessary to load the dry bulk vessels. This means
that also 5 conveyor lines will have to connect the stockpile area with the berths. Besides the conveyor
belts to the aggregate loading berths, the dry bulk import berths needs to be provided of a transport
system from the quay to future users. It is anticipated that this will take place by conveyor belt as well. It
is assumed that the maximum number of lines between the quay and the hinterland is 6. For an average
width of 10 m per conveyor a total width of 60 m is needed for this transport line.
The onshore part of the oil terminal contains the storage tanks, piping, manifolds and control rooms and
offices. The required area for this terminal is estimated using the following assumptions.
- Average height of storage tanks is 22 m,
- The average diameter of these tanks is 40 m.
- The average distance between the tanks is 25 m
- The area that is needed for manifolds, piping, roads, offices, control rooms, service and switchgear
buildings is 35% of the total area.
With these assumptions, a total amount of 3.5 m3 can be stored per m2. These numbers are based on the
area that VHFL needs for oil storage. VHFL currently stores 1.1 million m3 on 32 ha. This includes area
for manifolds offices, roads and piping, etc. For long term storage, usually tanks are used with a larger
diameter and height than these for blending or make/break of bulk. This means that more oil can be
stored on the same area.
For the demand in storage capacity at the end of phase 3 for the scenario 1, the required area for these oil
storage terminals according to the above mentioned assumptions is 328 ha. This can never be realized
within the existing available port site. For this reason it is anticipated that expansion of the oil storage
capacity is realized outside the existing port area. The first expansions will be realized West of the
existing port, between the road to Khor Fakkan and the mountains. Later expansions will be realized
North of VHFL on a new area reclaimed from the sea.
10/29/2007 48
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
4.8.3 Containers
The following assumptions where made to calculate the container stacking area.
- The distribution between import/export remains the same over various throughput changes.
- The Apron area has width of 60 m. This width comprises a 4 m service lane, a 24 m crane track, 10
space for hatch covers and 22 m for traffic lanes.
- The maximum dwell time (within 98% of the containers have left the terminal) is assumed to be 15
days, which means that the average dwell time is 5.67
- Because of their relatively low maintenance cost, and relatively long life, RTG will be used in the
container stacking area. When RTG are used (rubber tired gantries) it will be possible to apply a
stacking height of 4 containers height. (1 over 4). This means that on average 7 m2 must be taken
into account needed per TEU.
The area of the storage yard is determined with formula [4.8.1] for import and export containers and
empties.
Ci ⋅ t d ⋅ F
O= [4.8.1]
r ⋅ 365 ⋅ mt
In which:
O = required area
Ci = number of container movements per year
t d = average dwell time
F = required area per TEU inclusive equipment traveling lanes
r = average stacking height / nominal stacking height
mi = acceptable average occupancy rate
The area for a container freight station (CFS) is determined using formula [4.8.2].
C ⋅ V ⋅ t d ⋅ f 1 ⋅ f 12
O= i [4.8.2]
ha ⋅ 365 ⋅ mi
In which:
Ci = number of TEU movements per year through CFS
V = Volume of 1 TEU container (29 m)
f1 = gross area / net area
f2 = Bulking factor
ha = average height of cargo in the CFS (m)
As mentioned the possibility of container transport between Fujairah and Dubai by rail is investigated.
This means that not only for a road transfer area but also for a rail transfer space must be available. The
10/29/2007 49
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
connection with the new railway requires that the location of the container terminal can be reached by
railway line.
The access channel links the harbour basin to the open sea. The location and layout of this channel will
have an effect on the wave, current and wind conditions met by the ships in the channel. Although
Fujairah has a mild wind and wave climate and long shore current velocities are low, a properly lined out
access channel remains important.
Further the size of the channel determines the amount of dredged material. In the case of the Port of
Fujairah, this will be of minor importance since the access channel does not have to be very long. This is
due to the fact that the 20 m depth contour line is relatively close to the harbour entrance.
Since the new port expansion is planned to be realized in between the existing port and the existing
VHFL jetty, the approach of ships to these facilities should be taken into consideration with determining
the location and layout of the access channel.
Channel depth
The design vessel having the largest draught is the loaded cape size dry bulk vessel. This vessel has a
draught of 18 m. In this study it is assumed that no tidal window has to be applied. A tidal window would
have an effect on the average waiting time of the largest (and most expensive) vessels. The entrance
channel will probably be very short and the amount of soil to be dredged will probably not be large. It is
therefore assumed that the cost for deepening the entrance channel will be less than the introduction of a
tidal window. Besides this, there is the expectation that there is a large amount of soil required for the
land fills of the port expansion and the emphasized reclamation, north of the project location.
The required depth of the access channel is determined with the following expression.
d = T + ( D + s max + r ) [4.10.1]
In which:
- Tidal level beneath which no entrance is allowed.
This level is the CD+0 level. This is the lowest astronomical tide. No tidal window is applied.
- D = Draught of the design ship, 18 m.
- smax = Squat
Squat is the tendency of the design ship to change its under keel clearance as it moves ahead or
astern, or is passed by an other vessel close by. The following simple expression is suggested:
∇ Fnh2
s = 2 .4 2 ⋅
L pp ( )
1 − Fnh2
[4.10.2]
In which:
∇ = volume of displacement (m3) = Cb ⋅ L pp ⋅ B ⋅ T
10/29/2007 50
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Channel width
The design vessel with the largest beam is a container vessel having a beam of 56. Container vessels
having this beam and a length of almost 400 m do exist, but are not expected to enter the Port of Fujairah
very often in the near future. These vessels can handle 11,000 TEU.
Further the width of the channel is greatly dependant on the number of lanes. Since these very large
container vessels are not expected to call the Port of Fujairah very often, it will not be necessary to
design a two lane access channel for these ships. On the other hand, the frequency of arriving and leaving
medium handy size dry bulk vessels might get rather high. For these reasons, the width of the access will
be the largest of the one lane channel for the 11,000 container vessel or the two lane channel for the
handy size dry bulk vessel. Handysize bulk vessels have breaths up to 30 m.
The required channel width is described by the PIANC rules with equation [4.10.3] for a one way
channel.
∑
W = WBM + Wi + 2 ⋅ WB [4.10.3]
For a two lane channel equation [4.10.4] must be used.
∑
W = WBM + Wi + 2 ⋅ WB [4.10.4]
It is assumed that the entrance channel will be straight. The width of the entrance channel is built up from
a basic width to which are added a number of increments. The basic width is that required by the design
ship to move in calm water with no wind.
⎧1.6 ⋅ B , 1.25 ⋅ D < d < 1.5 ⋅ D
WBM = ⎨ [4.10.5]
⎩1.7 ⋅ B , d < 1.25 ⋅ D
The draught of the largest expected container vessel is 15.5 m.
The depth of the access channel is set to 20 m. This means that a basic width is used of 1.6 ⋅ B .
The factors for additional width ∑W i are determined according to PIANC (1997) tables. Additional
widths for straight channel section depend on wind, wave and current conditions. Prevailing cross winds
are described in paragraph 3.2.1. In table 3.1, omnidirectional wind velocities are given. From this table
it can be seen that a wind speed of 14 m/s is only exceeded 1.5% of the time. These winds are expected
to come from the Northwest. This means that no additional width has to be taken into account for cross
winds.
10/29/2007 51
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Paragraph 3.3 describes the current velocities near the coast of Fujairah. From table 3.3 it can be seen
that 93% of the time, current velocities do not exceed 0.55 m/s. An additional width of 0.3 ⋅ B is used for
channel width.
The only longitudinal currents that are expected are due to the astronomical tide, water flowing in and
out of the new harbour basin. The tidal range is in the order of 1 meter and the surface of the existing
harbour basin is 1.3 Mm, which means that 1.3 Mm of water is exchanged during each tidal cycle. The
flow velocities depend on the width and depth of the access channel. This velocity will never exceed 2.4
m/s which mean that no extra width for longitudinal currents is applied.
Also the wave climate is mild. The daily wave climate is described in 3.4.1. In table 3.4 the exceedence
percentages for significant wave heights are shown. It can be seen that 94% of the time, the significant
wave height does not exceed 1.0 m. When a moderate vessel speed is assumed, the required additional
width is 0.1 ⋅ B .
The aids to navigation are good. An additional width of 0.1 ⋅ B is applied.
The seabed characteristics are sandy soils which are smooth and soft. Additional width is 0.1 ⋅ B .
Oil tankers do not enter the port via the access channel but stay outside the basin since the tanker
terminal is at open sea. Chemical tankers however are expected to enter the basin. These tankers will not
have the dimensions of the design vessel. This means that no extra width for hazardous cargo will be
taken into account.
Since the access channel runs through two breakwaters, the additional width for bank effects is taken
1 .0 ⋅ B .
The additional width for two way traffic depends on the vessel speed and the traffic density. A low vessel
speed is assumed (5 – 8 knots) and a moderate traffic density. This means that the additional width
increments are 1.6 ⋅ B for vessel speed and 0.2 ⋅ B for traffic density.
The width of the one lane channel according to [4.10.3] and the above mentioned additional width
increments is 184 m. The width of the two lane channel according to [4.10.4] is 246 m. This means that
the channel width will be at least 246 m.
Channel length
The required length of the access channel depends on the stopping length of the largest vessels. Ships
need to sail with a certain speed to not lose rudder control. The minimum speed to maintain sufficient
rudder control is 3 to 4 kn under mild conditions like the waters in front of Fujairah.
To assist the vessels further to the berthing place, tug assistance is necessary as can be learned from the
existing Port of Fujairah operations. On the other hand, the channel length should be the smallest
possible, compatible with safety. This minimizes time taken to transit the channel
The following is assumed:
- Max vessel speed to tie up = 5-6kn
- Max wave height to tie up = 1.5 m
Preferred alignment
Ideally prevailing wind, wave and current directions should not lie perpendicular to the channel.
Preferably there is a small angle between the access channel and the prevailing wave direction.
Concerning the soil and the dredgability of the soil, there is no preferred alignment of the access channel.
There are no hard rocks, other obstacles or areas with extreme sediment accretion.
Bends in the access channel need to be avoided for reasons of safe navigation.
The width of the turning basin should at least be 2 ⋅ Ls . With the largest vessels expected to have a LOA
of 400 m, the diameter of the turning basin should be at least 800 m.
Wave penetration in the harbour basin should be minimized to prevent downtime at the quay and to
provide good mooring conditions. This should be subject of further study.
10/29/2007 52
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
10/29/2007 53
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
5.1 Introduction
One of the objectives of this masterplan study is to search for a favorable layout for the expansion of the
Port of Fujairah. In this chapter several new harbour layout alternatives will be proposed and discussed.
For these alternatives, the requirements and data as described in the previous chapters will be the
guideline. The main criteria for the development of the layouts will however be geometrical
considerations.
The first step will be to search for a final harbour layout, with the requirements of phase 3 of the
proposed scenarios. The second step will be to get into detail for phase 1 and 2 for different scenarios this
will be done in the next chapter. The Port Expansion will be discussed per separate section. These
sections are show in figure 5.1.
The layouts discussed in this chapter are shown on a larger scale in Annex 2 to this report.
A
C
D
E
10/29/2007 54
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
The three commodities that will be handled in a sheltered area behind breakwaters are aggregates
loading, handling of other dry bulk and container handling. To arrange these commodities in the new
harbour layout, the following aspects need to be considered.
- The dry bulk quays must preferably connected with the stockpile area by short lines.
- The width of the area behind the dry bulk quay can be relatively narrow. The minimum width is
discussed in paragraph 4.8.1. However it must be taken into account that it may be necessary to use
this area for transport lines for other commodities. The area behind the container quay must be
relatively large. The total required area for the container terminal is given in table 4.14.
- Straight quay walls are preferred over quays with bends. On one straight quay, there is more
flexibility in mooring the ships. Required quay lengths according to table 4.13.
- The container terminal requires a good connection with road and rail.
- Quays need to be on a sheltered location in the layout especially container handling.
- Quay lengths are according to table 4.13
Hydraulic requirements
The qualitative hydraulic requirements such as dimensions of access channel and turning circle are
described in paragraph 4.10. Further, it is desired that ships can be turned in the basin since the length of
the basin will be more than 1000 m.
With the generation of layouts it is taken into account that the manoeuvrability around the VHFL
terminal is possible and navigation is safe. For this reason the same relation between turning circle
diameter and vessel dimensions that is maintained inside the harbour basin will also be used for the
VHFL jetty.
10/29/2007 55
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Northern boundary
Expansion to the North is restricted by the VHFL terminal. It has been made clear by the Port Authorities
that these facilities can not be relocated.
In this paragraph, three harbour layout alternatives are proposed. These layouts principally differ in size.
In the first layout (A1), the maximum quay length is fitted at the proposed location, north of the existing
port. The final total quay length in this layout approaches but does not reach the required quay length for
phase 3 and scenario 1. The second layout (A2) presents a total quay length that is adequate for phase 3
scenario 3. This layout has the possibility to increase throughput capacity by construction of extra jetties.
The third proposed layout (A3) represents the expansion of the port partly south of the existing harbour.
However it was preferred that this area would not be part of the Port of Fujairah port expansion project,
the feasibility of expansion at this location will be part of the study since the required throughput
capacity according to scenario 1 can not be reached with layout 1 and therefore an other solution must be
found.
Layout 1
Layout 1 is shown in figure 5.2.
Entrance Prevailing
N channel wave
direction
525 m
Tugs
Harbour 1050 m
basin
1150 m
880 m
Corridor A
Corridor C
Corridor B
Dry bulk export terminal
Dry bulk import terminal
Container terminal
5.2 Sketch of the proposed harbour expansions layout 1
After completion of the port with layout A1, a total quay length of 3605 m is realized at the proposed
location, north of the existing port. With this layout the port expands maximal within the boundaries of
the proposed location, north of the existing port. The maximum possible throughput that can be achieved
with this layout approximates but dos not reach the throughput as describes by scenario 1.
Dry bulk is handled south of the new harbour basin. A 1000 m long dry bulk quay wall is attached to the
existing Northern breakwater. Between this new quay wall and the existing northern breakwater, a
relatively narrow strip of land is created which will be sufficient for cranes, conveyor belts and a pipe
rack to the new OSTT. The dry bulk berths are located directly north of the existing port for several
10/29/2007 56
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
reasons. The aggregate loading facility has the greatest need to increase in export capacity and will
therefore be constructed first. In this layout the dry bulk quay wall is attached to the existing port so that
this facility can be connected with the existing port functions. It will also be possible to operate this quay
without extensive protection against wave attack. This will be subject of further study. It will be possible
to access this quay wall from the existing port thru corridor A as shown in figure 5.2.
Attached to the southern breakwater of the new port expansion, a 700 m long quay wall is planned for
handling of dry bulk. This will be loading of aggregates or unloading of clinker. This quay wall can be
constructed in a later stage. It will also serve as protection against wave attack for the container quay
walls. Since the dry bulk handling requires a relatively narrow strip of land the amount of material for
land fill remains within acceptable limits. The coastal protection for this part of the new port will have to
be heavy since this section borders deep water and relatively vulnerable structures are present right
behind it.
Containers are handled west and north of the new harbour basin. A large strip of land behind the quay is
used for container storage. Two quays are planned, having a total length of 2030 m. West from the
harbour basin a quay with a length of 880 m and North from the harbour basin a length of 1150 m. The
width of the land behind these quays is 550 m (west) and 500 m (north). The total surface of the
container terminal is 178.6 ha. The transport of containers over land takes place through corridor B. This
corridor links up directly with the road between Fujairah and Khor Fakkan. Since the dominant wave
direction is from the southeast, it is expected that wave motion in this part of the basin is less, since it is
sheltered by the new southern breakwater.
The entrance channel has a width of 250 m as determined in paragraph 4.10.1. The width or alignment
has no effect for the dredging quantity since the harbour entrance is at the 20 m depth. The distance
between the breakwater heads however is determined by this width. Since the
With the construction of the existing oil terminal berths, it was foreseen that expansion to the North
would take place. The pipe rack for this terminal is supplied with a pipe bridge as a corridor to the new
port expansion. Corridor A will be the connection between the existing and the new port. Since the bulk
cargo is preferably constructed first, this corridor will serve than as the access for these construction
works. Tug facilities are planned to be realized attached to the northern breakwater.
Layout A2
Layout A2 is based on a minimization of the amount of required material for land fills. Within this layout
less space is available for quays and terminals. Layout A2 is shown in figure 5.3.
10/29/2007 57
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Prevailing
N Entrance wave
channel direction
Tugs
Harbour 1050 m
1020 mbasin
Container Dry bulk
terminal terminal
700 m
Corridor A
Corridor C
Corridor B
The total quay length after completion of the port expansion with this layout is 2070 m comprising two
quays south and north of the harbour basin. This is the required quay length of phase 3 and scenario 3
representing minimum growth in the demand for export capacity. West from the harbour basin, no quay
will be constructed. This part of the new port will kept free for dry bulk or for liquid bulk jetties.
The total quay length for handling of dry bulk cargo is 1050. The terminal is located directly north of the
existing northern breakwater. As mentioned above, the dry bulk terminal is planned to be constructed
first.
The container terminal is located in the northern part of the port expansion. The container quay lies
directly north of the harbour basin and has a length of 1020 m. The total area of the container terminal is
102 ha. As in layout 1, the transport of containers over land takes place through corridor B.
Layout A3
With layout A3 all quay length and terminal area can be realized that is required for scenario 1. Since is
not possible to realize a port that can reach this throughput at the preferred location, the area south of the
port is considered. However other developments where planned in the area south of the existing Port of
Fujairah, the feasibility of a container terminal at this location is studied as well. In layout A3 the dry
bulk berths are positioned north of the existing port at the original port expansion location. Only the
container terminal is shifted to the south. Layout A3 is shown in figure 5.4
10/29/2007 58
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
N
Entrance
Entrance channel
channel
1050 m Partly
removal Harbour
of SBB basin
2110 m
910 m
Corridor A
Corridor C
The container quay wall has a total length of 2110 m without bends and starts directly south from the
existing southern breakwater. The total area of the terminal behind this quay is 165 ha. The container
terminal is protected against wave penetration by a breakwater stretching out from the south end of the
new quay and encloses the entire terminal. The entrance channel is directed to the Northeast. This will
also be the new entrance channel for the existing port. Ships will sail to the turning circle where they will
be turned and towed to their berthing position.
With this port layout it will be necessary to make an adjustment to the existing port and the part of the
port that is currently under construction. It is assumed in this part of the study that it is necessary to
remove the seaward part of the existing southern breakwater and a part of the new South Breakwater
Berth. An advantage of this layout will be the extra protection of the existing port against penetration of
swell from southern directions.
The total length of the dry bulk quay walls is 1960 m. The two quays do not form an enclosed basin. It is
assumed that one single breakwater, attached to the existing northern breakwater gives sufficient shelter
against waves to keep downtime within acceptable limits. The loading of dry bulk vessels has a rather
large critical wave height. The downtime due to exceedence of the critical wave height will be
investigated in this study.
It must be taken into account with the generation of alternatives for the liquid bulk terminal that the
entrance channel for this alternative partly runs through the proposed area for the Open Sea Tanker
Terminal. Probably an alternative location will have to be chosen for the new liquid bulk terminal. It may
be possible to construct the new terminal directly south of VHFL.
Layout A4
An alternative for the dry bulk terminal for layout A3 is to attach the western quay to the new
breakwater. It is expected that wave height at the eastern quay will be less than at the western quay. The
required amount of soil material for the reclamation of land in this solution will be higher as well as the
amount of material for the coastal protection works. Further, absence of the western quay wall makes it
possible to realize the liquid bulk terminal, north of the turning circle.In layout A4 a strip of land is
10/29/2007 59
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
planned at this location. The function of this strip is to partly realize the liquid bulk terminal onshore.
The feasibility of reclaiming land in stead of construction of offshore trestle bridges is to be investigated
in Annex 8, layout evaluation. Layout A4 is shown in figure 5.5
Corridor A
Corridor C
Additional to the advantage of reduced wave height at the quay, harbour basin layout A4 gives the
possibility to realize the liquid bulk terminal, north of the Port.
10/29/2007 60
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Layout A5
Harbour basin layout A5 is based on harbour basin layout A4. These layouts differ by the reclaimed strip
of land that is proposed in layout A5, directly south of the VHFL terminal. In stead of reclaiming land
and using pipe racks, off shore trestle bridges are proposed in this layout.
Corridor A
Corridor C
5.3.1 Introduction
The proposed layout for the Open Sea Tanker Terminal is related to the preferred layout for the harbour
basin. The existing OTB has two berths that are able to handle one medium size vessel or two smaller
vessels up to 15,000 DWT. It is assumed that the existing OTB will be used for the handling of smaller
ships up to 15,000 DWT. In this way the current facilities are able to handle four vessels up to 15,000
and one vessel up to 90,000 DWT simultaneously. The small vessels are more vulnerable for waves. The
handling of these vessels in the sheltered harbour basin will minimize downtime due to wave motion.
The new terminal will handle the cape size vessels up to 165,000 DWT. These ships are less vulnerable
for wave motion and currents. As mentioned in paragraph 4.7.3, five new berths are required to be able to
provide the capacity for scenario 1and three new berths for scenario 3.
With the generation of alternatives, the following is taken into account:
- A short connection to manifold is preferred. The pipeline routing is preferably over land since pipe
racks are less expensive than trestle bridges.
- The dominant wave direction is preferably on the heads of the moored ships.
10/29/2007 61
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
- Access to the berths must be easy with sufficient manoeuvring/turning space. Approach lines should
not cross the other harbour entrances.
- The oil terminal is preferred to be located away from other commodities like containers and dry bulk.
N
5
4
3 OSTT
2
1
Pipe rack
Manifold OTB’s
5.7 Sketch of the proposed OSTT layout B1 and harbour basin layout A1
Berths are orientated parallel to the dominant wave direction as preferred. An onshore pipe rack connects
the manifold with the new berths. The existing OTB’s will be connected to this manifold as well. Three
finger piers stretch out perpendicular to the Eastern quay wall. These finger piers are all connected via an
abutment to an onshore pipe rack, running parallel to the Eastern dry bulk quay wall. The liquid bulk
terminal can be constructed in phases, starting with the first finger pier, berth 1 and 2. This layout
provides the possibility to expand the number of new berths to 6 since north of berth 5 an extra berth can
be realized if necessary. The construction of a pipe rack is relatively cheap and can be executed quick
and simultaneous to the construction of the finger piers. The water depth at the location of the OSTT is
between CD-16 m and CD -24 m. This means that some dredging will be necessary to bring the shallow
part to the depth required for the larger oil tankers expected in Fujairah.
Layout B2
When the demand for storage capacity does not follow the rapid growth as described by scenario 1 and 2,
it will possibly not be necessary to build the liquid bulk terminal outside the harbour basin. In this case
the dry bulk terminal can be relocated in the new port. For this scenario layout B2 is proposed. This
layout is shown in figure 5.8.
10/29/2007 62
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
3
2
1
5.8 Sketch of the proposed OSTT layout B2 for harbour basin layout A2
In layout B2 the liquid bulk berths take the position of the dry bulk berths at the Southern quay. Dry bulk
is handled at the Western quay wall. It may be possible use a jetty at the liquid bulk berths in stead of a
quay wall. Besides the fact that the costs of a jetty will possibly be lower than the costs of a quay wall,
this has the advantage of a low wave reflection coefficient of the light revetment over the full reflection
of a vertical wall. This means that the reflected wave height at the Northern container quay wall will be
less which can bring a significant reduction in the downtime on this quay. Waves from the Northeast
reflected by the new Southern quay wall, attack container vessels at the Northern quay at the bow. From
this angle of attack, vessels are most sensitive.
If the demand for storage and throughput capacity grows significantly, expansion of number of liquid
bulk berths is possible by construction of extra berths attached to the Southern breakwater or at open sea
as proposed in layout B1.
Layout B3
Layout B3 presents the proposed liquid bulk terminal directly south from the VHFL terminal. This
location is merely feasible when the container terminal is realized south of the existing port according to
layout A3, A4 or A5. The absence of the northern quay of the northern port expansion in this layout
provides the possibility to realize the new oil terminal directly south from VHFL. Oil terminal with
layout B3 can be realized partly onshore with harbour layout A4 or as a jetty with layout A5. Layout B3
is shown in figure 5.9.
10/29/2007 63
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
5.9 Sketch of the proposed OSTT layout B3 for harbour basin layout A5
Layout B4
Liquid bulk terminal B4 is located north of the new turning basin. Merely the alignment of the berths
differs from layout B3. Layout B4, can only be realized in combination with harbour basin layout A3, A4
and A5. Oil terminal with layout B3 can be realized partly onshore with harbour layout A4 or as a jetty
with layout A5. Layout B4 is shown in figure 5.10.
5.10 Sketch of the proposed OSTT layout B4 for harbour basin layout A5
The main function of the new reclaimed north of the port expansion project land will be to serve the
demand for space for oil storage facilities in the vicinity of the Port of Fujairah and the planned Port of
Fujairah expansions. Besides for oil storage tanks, the new reclaimed land will also give room for other
industrial developments in Fujairah such as the new planned cement factory.
10/29/2007 64
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
The outer limits of this reclamation project are defined by the Naval base in the North and the Port
expansion of the port of Fujairah in the South. The proposed width of the new reclaimed land is 500 m
from the existing coastline to the new coastal protection. There are no alternative layouts proposed in this
study since this study focuses on the Port Expansion Project. The total surface of the new gained land
will be:
- West of existing coast line 500 ha
- East of existing coast line 225 ha
There are two main different approaches to realize this reclamation project;
1) The material with which the new land is reclaimed, is gained by deepening the sea bottom
east from the new coast line. This solution is further mentioned in this report as: “dredging
solution”.
2) The new reclaimed land is built up from material gained by blasting several parts of the
mountainous area west from the road between Fujairah and Khor Fakkan. This solution is
further mentioned is this report as “blasting solution”.
The construction will be carried out simultaneously with the construction works of the expansion of the
Port of Fujairah. The use of dredged material for the reclamation project will also influence the choice
for the layout of the port of Fujairah since a dredging surplus will be used for the reclamation project if
the dredging solution is selected.
Study to this subject has made clear that the construction cost for dredging and blasting are comparable.
The area of the land that is reclaimed from the mountains is relatively small. Further blasting has the
disadvantage that blasting the required material takes roughly twice as long as the dredging construction
time. The Municipality of Fujairah has indicated that this factor will be decisive.
The surface level of the new reclaimed land and the rest of the project area are set at CD + 5.0 m. This is
the same surface level as the VHFL terrain on the South boundary of the project area.
Al Sodha area
The project area lies west from a more or less flat land between the mountainous area and the shore line.
Between these mountains and the shore also lies the road between Fujairah and Khor Fakkan. This road
was formerly curving around a small village called Qurayya. Currently construction works are carried out
to change this profile into a straighter route. Several houses of the village have already been removed to
make this possible.
10/29/2007 65
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
East from the road, the land is entirely flat without any masses of rock. The main requirement is that
available space is utilized as efficient as possible. This means that as much square meters must be gained
as possible within the set boundaries. Not only the area East from the road is considered but also the area
between the road and the mountains must be taken into account. This will have effect on the choice
between the dredging and the blasting solution. If the blasting solution is chosen, the total area will
finally be bigger which will be an advantage for this solution.
Oil
storage Conveyor belt
New stockpile
area
10/29/2007 66
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
FRCL refinery 69 ha
JV1 5.5 ha
JV2 26 ha
Emarat GPS 25 ha
ENOC 40 ha
IPIC 160 ha
Total 165.6 326 ha
table 5.1 Areas oil storage facilities in Fujairah
With the relation of 3.5 m3/m2, the assumed possible storage volume on the available area is 11.4 million
m3. This volume can be increased to 12 million m3 for scenario 1, by using higher tanks or larger
diameters.
FRCL
IPIC
ENOC
JV1 Emarat /
JV2 GPS
To build extra storage facilities west of the road to Khor Fakkan, rock will have to be removed. The
feasibility of reclaiming parts of the mountainous area will have to be studied.
In layout A1, the space available for the container terminal is 178 ha. This is sufficient for a container
terminal with a yearly throughput of 3 M TEU. The available space in layout A2 for the container
terminal is 102 ha. This is more than enough for a container terminal with a throughput of 1 M TEU. In
fact it might be possible to increase the throughput of the terminal to approx. 2 M TEU with the available
space for storage and quays. This would mean however that the Western quay wall would be used for
container handling and the growth of dry bulk throughput capacity is restricted. The available space in
layout A3, A4 and A5 for the container terminal is 165 ha which is sufficient for a container terminal
with a yearly throughput of 3.5 M TEU.
10/29/2007 67
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Merely scenario 1 requires berths for handling of chemical. Two berths for vessels up to are planned,
north of the reclaimed area behind the new northern quay wall for harbour basin layouts A1 and A2. For
harbour basin layouts
10/29/2007 68
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
6.1 Introduction
In this chapter the layouts proposed in the previous chapter are evaluated. The large number of different
combined throughput scenarios, the number of combination layout alternatives, their limitations and the
phasing of the project, make it very complicated to carry out this evaluation. Consequently it is
indispensable to simplify the stated problem.
The joint proposed harbour basin layouts and liquid bulk terminal layouts will be evaluated. Several of
these combined layouts can not achieve the throughput capacity for the highest growth scenario. As a
result no valid comparison can be made between layouts that are capable of providing scenario 1
throughput, and the layouts in which it is not possible to achieve this throughput.
The evaluation of layouts is carried out for three groups of layouts. These are the layouts that can achieve
the required throughput for the three scenarios. For each group the layouts are evaluated using two
different techniques. A monetary evaluation is performed as well as a multi criteria analysis. The two
evaluations are coupled by a cost per value point rating.
The proposed harbour layout combinations including intermediate phasing are shown in Annex 2 to this
report. The monetary evaluation, as well as the multi criteria analysis, are described in detail in Annex 8.
6.2 Simplifications
The first simplification is the combination of the composed throughput scenarios. In reality it may be
possible that the demand for throughput capacity for one commodity will grow strongly as for other
commodities the throughput capacity will lag behind. For a practicable evaluation however this will give
too many possibilities. It is assumed that correlated development of demand in throughput capacity is not
unrealistic. This simplification results in the reduction of the number of scenarios to the total of 3.
The layouts, as discussed in the masterplan report are combinations of layout alternatives for the new
port harbour basin and for the liquid bulk terminal. The liquid bulk terminal is planned to be an open sea
terminal. There are five alternatives for the harbour basin and four alternatives for the liquid bulk
terminal. Finally nine layout combinations will be discussed in this annex. These are the following
combinations:
10/29/2007 69
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
8) A5 – B3
9) A5 – B4
The layout alternatives will be assessed by multi criteria analysis (MCA). A multi criteria analysis is a
decision making tool developed for complex problems. It is particularly applicable to cases where a
single criterion approach, such as cost-benefit analysis falls short. The MCA will be used to asses the
alternatives by a number of unequal validated criteria.
6.3.1 Objectives
To carry out the MCA, clear objectives should be specified. The main objectives for the expansion of the
Port of Fujairah are summarized as follows:
- Flexibility in throughput capacity expansion.
- Optimization of handling facilities efficiency
- Optimization or improvement of safety
Costs are not part of this analysis since these are quantitative and the multi criteria analysis uses
qualitative criteria. The proposed layout alternatives will be the options for achieving the above
mentioned objectives. Each criterion will be given a specific weight.
Flexibility in throughput capacity expresses not only the possibility of the port layout alternative to
expand in size, but also to adapt when the relative position of commodities and their throughput changes.
This means that this objective gives two criteria that will both be assessed for the terminal area as well as
the water area in the port. Further this objective gives the criteria of serving larger ships in the future.
Larger vessels will give other requirements for turning basin and channel dimension and water depth of
the harbour basin.
- The possibility to expand
- The possibility to adapt
- Possibility of serving larger ships
The subject of minimizing or reduction of hazard to the environment is partly classified under the
objective of nautical safety, terminal safety. It is assumed that the difference between the considered
layouts has no influence on the hazard to the environment or the urban areas.
10/29/2007 70
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Criteria
Length of
adaptability
possibilitie
vessel size
Downtime
Increasing
Weighted
score [%]
hydraulic
Terminal
transport
Nautical
Growth
Layout
safety
safety
ff t
Total
li
Growth possibilities X 1 1 1 1 1 1 6 29%
Layout adaptability 0 X 1 0 0 0 0 1 5%
Increasing vessel size 0 0 X 0 0 0 1 1 5%
Downtime hydraulic effects 0 1 1 X 1 0 1 4 19%
Length of transport lines 0 1 1 0 X 0 0 2 9%
Nautical safety 0 1 1 1 1 X 1 5 24%
Terminal safety 0 1 0 0 1 0 X 2 9%
Total 21 100%
table 6.1 Weighted score criteria
From table 6.1 it can be seen that growth possibilities are the most important criteria. For each layout a
score between 0 and 3 will be given for each individual criterion. This score can be explained according
to the following list:
- 0: Has effects that are opposite to the objectives
- 1: Hardly any positive or negative influences
- 2: Has a positive effect on achieving the objectives
- 3: Meets the objectives
Beside the MCA, a monetary evaluation is carried out. In this evaluation, the proposed technical civil and
marine designs (discussed in chapter 7 and annexes 4 – 7 ) are used to determine the project cost for all
proposed layout combinations. The construction costs for the final layout are estimated as well as
construction the costs for the intermediate phases.
This monetary evaluation is discussed in detail in Annex 8.
4) A3 – B1
5) A4 – B3
6) A4 – B4
10/29/2007 71
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
7) A5 – B1
8) A5 – B3
9) A5 – B4
Since quay length, number of berths is equal for all layouts it is assumed in this paragraph that the
throughput capacity of all layout combinations is equal. In reality the capacity will differ somewhat
because of different berth configurations. However taking this into account, reaches beyond the scope of
this study. This means that the evaluation of these layouts will purely be based on cost and other aspects
excluding throughput capacity.
The capacity of these layouts for three construction phases is given in Annex 8. Following the growth
according to scenario 1, the following phasing is proposed:
- 2007 - Construction of phase 1:
- 2012 – Construction of phase 2
- 2022 – Construction of phase 3
Costs are given by net present value, at the end of the project span in 2032. For this calculation a
discount rate of 7% is taken into account. Only the costs for civil and marine works are taken into
account. Since costs for mechanical works, super structures and benefits are assumed to be comparable
for all layout alternatives, these are excluded from this calculation. Also the loss of income due to the
unavailability of the area south of the port is left out of the NPV calculation since this is equal for all
layouts. Merely factors that are unequal are taken into
From table 6.2 it can be concluded that the net present value for layout A3B1 in 2032 will be higher than
for all other layout alternatives. For the layouts with the liquid bulk terminal north of the harbour basin,
layout A5B3 has the highest NPV in 2032. The following conclusions can be drawn:
- It is more economical to realize a new quay wall at the west of the new harbour basin harbour
basin (layout A3) than east of the harbour basin (layout A4 and A5)
- It is more economical to realize the liquid bulk terminal, attached to the new southern breakwater
than north of the harbour basin.
- Realization of an offshore liquid bulk terminal on trestle bridges is less expensive than an on
shore terminal on new reclaimed land. Even when it is taken into account that dredged material
from the harbour can be used.
For the proposed layouts, each criterion as described in paragraph Error! Reference source not found.
will be given a score in this paragraph.
10/29/2007 72
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Growth possibilities
Layout A3B1 and A5B1 give the possibility to expand the harbour further in northern direction since the
liquid bulk terminal is realized north of the existing port. It would be possible to expand until a harbour
layout similar to the proposed layout A2 is reached. This means that roughly 1000 m extra quay length
can be realized. The liquid bulk terminal is expandable up to 6 berths very easily. Further expansion of
this terminal is possible in southern direction.
The other layouts have less expansion possibilities. It is possible to expand the liquid bulk terminal at the
location of layout B1. This however would mean extra investments on pipe racks to this location. Extra
quay length will be hard to realize within these proposed layouts. It would be necessary to use the
harbour basin of the container terminal, south of the existing port for further expansion.
The expansion possibilities of the container terminal are not evaluated. The container terminal layout is
similar for all proposed layouts for scenario 1.
Layout adaptability
Since all layouts have the same quay length distribution, this criterion is of minor importance for the
evaluation of the scenario 1 layouts. Each layout will be valued equally.
Nautical safety
The vessel manoeuvring in the turning area in front of liquid bulk terminal layout B1 may hinder the
vessels that approach the existing harbour basin. This approach line has turned northward as the existing
southern breakwater is reconstructed. On the other hand, the reduction of the amount of vessels in the
new harbour basin may create a safer situation in this part of the port.
Terminal safety
With the realization of the liquid bulk terminal north of the new harbour basin (B3 and B4), liquid bulk
handling and storage are centered at one location. Layout B1 will require oil handling in the direct
vicinity of several dry bulk handling facilities. However this is feasible, separate handling is preferable.
The above mentioned arguments are used to compose an MCA matrix, given in table 6.3. It can be seen
that layout alternative A5B1 has the highest score. This can be explained by the good expansion
possibilities and low sensitivity for wave action for the dry bulk berths. Layout A3B1 seems to be the
second best option close to layout A5B1.
10/29/2007 73
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Criteria
Increasing vessel
hydraulic effects
Terminal safety
Weighted score
Nautical safety
transport lines
possibilities
adaptability
Downtime
Length of
Growth
Layout
size
[%]
Weight factor 29% 5% 5% 19% 9% 24% 9%
A3 – B1 3 1 2 2 3 1 1 2.00
A4 – B3 1 1 0 2 2 1 2 1.32
A4 – B4 1 1 0 2 2 1 2 1.32
A5 – B1 3 1 2 3 1 1 1 2.01
A5 – B3 1 1 0 2 2 1 2 1.32
A5 – B4 1 1 0 1 2 1 2 1.13
table 6.3 Multi criteria analysis
The monetary evaluation is coupled to the multi criteria analysis by composing a cost per value point
rating. This rating is given in table 6.4 in which NPV of 2032 is divided by value points. This table
shows that layout A3B1 has the lowest cost per value point. It can be concluded that layout A3B1 not
only is the cheapest layout that can achieve scenario 1 throughput but also that this layout has good
qualitative properties.
The conclusion can be drawn that if it is desirable that the new port expansion should reach the
throughput capacity as described by the combined scenario 1, layout A3B1 would be the most favourable
layout followed by layout A5B1. This means that the area south of the existing port should be part of the
Port Expansion plans.
10/29/2007 74
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
The capacity of the evaluated layouts is not equal over the proposed phasing. To achieve the required
capacity for scenario 2, the following phasing is proposed:
- 2007 - Construction of phase 1 for both layouts.
- 2012 – Construction of phase 2 for layout A1B1
- 2022 – Construction of phase 3 for layout AB1, phase 2 for A3B1
Costs are given by net present value, at the end of the project span in 2032. For scenario 2, an equal
discount rate of 7% is used as for scenario 1. Only the costs for civil and marine works are taken into
account. Since costs for mechanical works, super structures and benefits are assumed to be comparable
for all layout alternatives, these are excluded from this calculation.
Since for layout A3B1, the area south of the port is used for the expansion of the container terminal, the
loss of income of the lease of this land is included in the NPV calculation. The net present value at the
end of 2032 is given in table 6.5. However for layout A3 it is necessary to construct a very costly new
breakwater, the cost of the reclamation works that are required for the container terminal of layout A1
exceeds the cost of coastal protection works for layout A3.
A1B1 A3B1
NPV 2032 $ -452.9 M $ -503.5 M
table 6.5 Net present value 2032, layout alternatives scenario 2
From table 6.5 it can be concluded that the net present value of the civil and marine works, including loss
of income due to unavailability of land is highest for layout A1B1.
For both layouts, each criterion will be given a score in this paragraph.
Growth possibilities
The growth possibilities for layout A3B1 are significantly better than for layout A1B1. At the end of
phase 2032 layout A1B1 has run out of expansion possibilities as quay walls are constructed at all sides
of the harbour basin. Since only phase 1 and 2 of Layout A3B1 need to be realized to achieve the
required throughput capacity, growth possibilities are better. When the land south of the port the port is
leased out, it is assumed to be impossible to regain this for port expansion.
Layout adaptability
All commodities concentrated around one harbour basin will increase the flexibility of allocating
functions to quay walls. This means that layout A3B1 would be less flexible.
10/29/2007 75
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
where the harbour basin is not enclosed by breakwaters, downtime due to wave motion is expected to be
high.
Aggregate vessels are less sensitive for wave motion. The open character of the northern expansion is
therefore not expected to cause significant downtime.
Nautical safety
Some interference between the vessels, approaching the existing harbour basin and the new liquid bulk
terminal is expected. The changed alignment of the approach channel for the existing basin with layout
A3B1 has a negative effect on safe navigation.
The approach to the new harbour basin, north of the port according to layout proposal A1B1 will cause
interference with ships approaching the VHFL terminal.
Terminal safety
The location of the container terminal in the direct vicinity of petrochemical industry with layout A1B1
might be seen as a disadvantage. Layout A3B1 offers a location for the container terminal, free from
other commodities that can threat safety on the terminal.
The above mentioned arguments are used to compose an MCA matrix, given in table 6.6. It can be seen
that layout alternative A3B1 has the highest score. This can be explained by the good expansion
possibilities for layout A3 and pour possibilities for layout A1 and by the exposure to waves of the
intermediate phases of layout A1B1.
Criteria
Increasing vessel
hydraulic effects
Terminal safety
Weighted score
Nautical safety
transport lines
possibilities
adaptability
Downtime
Length of
Growth
Layout
size
[%]
Weight factor 29% 5% 5% 19% 9% 24% 9%
A1 – B1 0 2 1 0 1 1 1 0.57
A3 – B1 3 1 1 2 2 1 3 1.95
table 6.6 Multi criteria analysis scenario 2
The monetary evaluation is coupled to the multi criteria analysis by composing a cost per value point
rating. In table 6.7 the NPV, divided by the number of value points is given.
A1B1 A3B1
$ -794.6 M $ -258.2 M
table 6.7 NPV per value point scenario 2
It can be concluded that layout A3B1 is the most favorable layout although layout A3B1 has higher
construction cost. The reduction of the project cost by using dredged material for the Fujairah land
10/29/2007 76
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Reclamation project, the lease of the land south of the existing port play an important role in the
assessment.
6.7 Scenario 3
The capacity of the evaluated layouts is not equal over the proposed phasing. To achieve the required
capacity for scenario 3, the following phasing is proposed:
- 2007 - Construction of phase 1 for all layouts.
- 2008 – Construction of phase 2 for layout A2B2
- 2012 – Construction of liquid bulk terminal phase 2 for layout A1B1 and A3B1 and construction
of phase 2 for layout A2B1.
- 2022 – Construction of phase 3 for layout A2B1
It must be noted that achieving the required throughput of scenario 3 for layout A1B1 and A3B1 for the
last project will higher berth occupancy and cause longer waiting times with this phasing.
Costs are given by net present value, at the end of the project span in 2032. A discount rate of 7% is used
as for scenario 1. Costs for mechanical works, super structures and benefits are assumed to be
comparable for all layout alternatives; these are excluded from this calculation. Included in the
calculation is the rental rate of the area south of the port for layout A3.
From table 6.5 it can be seen that the cost for layout alternative A3B1 are high. This can be explained by
the fact that the initial costs for this alternative are high. For layout A1B1 construction of a breakwater
attached to the southern quay is included in the calculation. This breakwater is necessary to keep
downtime due to wave motion at the container terminal within acceptable limits.
10/29/2007 77
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Layout adaptability
Since expansion is centered north of the existing port for layouts A1 and A2, these alternatives give more
possibilities for modification of commodities at the quays. Especially layout A2B2 is very suitable for
adjustment of quay length or number of berths per commodity.
Nautical safety
In layout alternative A2B2, berthing takes place is inside the sheltered harbour basin. The approach line
of the VHFL terminal is free for layout A1B1 and A3B1.
Terminal safety
In layout alternatives A1B1, A2B1 and especially A2B2 the container terminal is operated in the direct
vicinity of the liquid bulk terminal.
The above mentioned arguments result in the following matrix. It can be seen that the harbour layout
A3B1 reaches the highest score.
Criteria
Increasing vessel
hydraulic effects
Terminal safety
Weighted score
Nautical safety
transport lines
possibilities
adaptability
Downtime
Length of
Growth
Layout
size
[%]
10/29/2007 78
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
6.7.6 Conclusion
From table 6.10 it can be seen that the most favorable layout alternative is A2B2 for scenario 3. Layout
A3B1 reaches a higher score in the MCA but construction costs are too high to make this layout cost
effective, with a low economical growth.
The results of the multi criteria analysis and monetary evaluation can be summarized as follows:
- When it is desired that scenario 1 or scenario 2 throughput can be achieved the most promising
layout alternative is harbour basin layout A3 in combination with liquid bulk terminal layout B1.
- When it is desired that only scenario 3 throughput can be achieved, the most promising layout
alternative is harbour basin layout A2 in combination with liquid bulk terminal layout B2.
Harbour basin layouts A1, A4 and A4 as well as liquid bulk terminal layout B3 and B4 do not form the
most favorable solution in any case. Layouts A3B1 and A2B2 have several elements in common. These
are the location and alignment of the southern and western quay walls and the, geometry of the dredged
basin for the expansion works, north of the existing port.
10/29/2007 79
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
7 Technical designs
7.1 Introduction
In this chapter, technical designs of the civil and marine parts of the port expansion are proposed. These
designs are not discussed in detail in this report but are further described in Annex 4, Annex 5 and Annex
7 to this report. The designs where used for the cost estimations that where part of the monetary
evaluation of the proposed harbour layouts.
The technical design of the quay walls is discussed in Annex 4 to this report. For all quay walls in the
layout the same design has been considered.
The most favorable type of quay wall cost as well as construction time wise is a combi sheet pile wall.
The specific dimensions of this structure are given in table 7.1. The quay wall is designed for a depth of
CD – 18.0 m, the surface level of the reclamation (and top of the quay wall is CD + 4.75 m. So the
retaining height of the structure is 22.75 m). All the quay wall designs are based upon the same
geometry. The quay wall design is assumed to be a combi wall structure.
Tubulars L = 28.5 m
Ø = 1.42 m
d = 16 mm
Infill sheeting Larssen 605
W = 600 mm
L = 22 m
Copping beam 4.0 ⋅ 3.5 m3
table 7.1 Specific dimensions quay walls
For the back anchoring of the combi wall structure several systems and options have been looked at. Self
drilling anchors with grout cover tie back anchors to a sheet pile wall, both with Dywidag rods or
bundled strand tendons.
The design of coastal protection works is discussed in Annex 5 to this report. In this annex a design
proposal is given for four main parts of the coastal protection works. These are:
- Revetment section in the exposed areas
- Breakwater part. (water on both sides)
- A breakwater round head and convex bends in the revetment sections.
- Revetment section in the sheltered areas
For both sections the stability of several slopes and stone weights for wave loads with different return
periods are tested.
10/29/2007 80
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
The Open Sea Tanker terminal is built up from the following elements:
- Concrete product platforms on steel piles on which the loading arms are installed.
- Concrete breasting platforms founded on steel piles.
- Concrete mooring platforms founded on steel piles.
- Steel catwalks between breasting, mooring and product platforms .
- Steel access bridges from the shore to the product platforms. These access bridges are founded on
concrete platforms and steel piles. The length of the bridges is 37.5 m each.
The trestle bridges carry a minimum of 8 pipes with a diameter of 16”.
10/29/2007 81
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
8.1 Conclusions
- The current cargo flow and the anticipated growth in the demand for throughput capacity require a
throughput capacity that can not be provided by the current facilities of the Port of Fujairah.
Especially current dry bulk export facilities are under dimensioned.
- The wave climate of the waters in front of Fujairah is mild. Current velocities are low.
- When it is desirable that the new port expansion should be able to achieve throughput as described
by scenario 2 or scenario 1 representing moderate to strong growth, it is indispensable that the area
south of the existing Port of Fujairah is part of the expansion project. This means that it is necessary
to reserve space for port expansion south of the existing port of Fujairah. The most favorable harbour
basin layout to reach the required capacity for moderate or high growth is harbour basin layout A3
and liquid bulk terminal layout B1.
- When economic growth is limited according to scenario 3, describing weak growth the most
favorable harbour layout is A2B2. In this layout liquid bulk is handled inside the new harbour basin,
north of the existing port. The area south of the port can be used for other purposes.
- The existing aggregate export and liquid bulk handling facilities can remain operational in the Port of
Fujairah. Container handling is more efficient when all facilities are concentrated in the new port
expansion. The remaining space in the existing port is advised to be utilized for anticipated growth in
the number of RoRo vessels, general cargo ships, cruise ship and ship repair facilities.
- The most favorable type of quay wall cost as well as construction time wise is a combi sheet pile
wall. The most favorable type of armour for coastal protection is rock.
8.2 Recommendations
- Many assumptions in the basic data where made to be able to carry out this study. The assumptions
require changes when more data is available to increase the validity of the outcome of this study.
- Wave penetration in the new harbour basins and downtime due to waves and currents at the quays as
well as at the liquid bulk terminal.
- Ship manoeuvrability for the proposed harbour layouts. Manoeuvring to new and existing harbour
basin, new liquid bulk terminal and the existing VHFL terminal.
- Project cost of super structures (cranes and conveyor belts) and project benefits.
- Channel width and alignment optimization.
- Feasibility of single point mooring buoys in front Fujairah.
10/29/2007 82
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
References
10/29/2007 83
A1 Annex 1: Derivation of boundary Conditions
10/29/2007 A1 - 1
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 1: Derivation of boundary Conditions
Contents
List of tables
table A 1.1 Omnidirectional wind speeds according to records made by the Port of Fujairah Marine
Department............................................................................................................................. 7
table A 1.2 Omnidirectional wind speeds according to records made at the VHFL-jetty. ....................... 7
table A 1.3 Omnidirectional wind speeds according ships observations.................................................. 8
table A 1.4 Omnidirectional wind according to satellite observations. .................................................... 8
table A 1.5 Percentage of time that the weather is in the given conditions based on observations by the
Port of Fujairah Marine department..................................................................................... 15
table A 1.6 Water levels ......................................................................................................................... 15
table A 1.7 Current velocities according to measuremtents made at the VHFL-jetty.. .......................... 16
table A 1.8 Percentages of time that the wave heights in the given direction are exceeded at the location
of the VHFL-jetty according to transformed ship observations........................................... 18
table A 1.9 Percentage of time that the state of the sea is in the given condition recorded by the Port of
Fujairah Marine Department................................................................................................ 18
table A 1.10 Wave heights according to satellite observations. ............................................................... 19
table A 1.11 Wave heights according to off shore Ship observations transformed to the location of the
VHFL-jetty........................................................................................................................... 20
table A 1.12 Joint probability of occurrence of wave periods and heights............................................... 20
10/29/2007 A1 - 2
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 1: Derivation of boundary Conditions
table A 1.13 Extreme off shore wave heights and periods for given return periods and directions
according to corrected ship observations. ............................................................................ 27
table A 1.14 Extreme near shore wave (depth line 14) heights and directions for given return period and
direction according to corrected ship observations.............................................................. 27
table A 1.15 Near shore significant wave heights for different return periods and water depths............. 28
List of Figures
10/29/2007 A1 - 3
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 1: Derivation of boundary Conditions
A 1.1 General
In this section the site conditions, relevant for the design of elements of the new northern Port of Fujairah
expansion, are described. All variables have units according to the international SI conventions. Wave
and wind directions refer to the direction from which the waves and winds are coming. The direction is
given in degrees, measured clockwise with respect to North.
Wind and wave data are presented in the form of wind and wave roses. Wind and wave roses provide a
quick way of summarizing the directional wind and wave conditions statistics. The number in the centre
of the rose represents the percentage of the time that calm conditions occur. The direction that the arm
points in represents the direction that the winds or waves come from. The length of an arm represents the
percentage of the time that winds or waves come from the corresponding direction. This can be seen in
the bar (under the roses), which indicates the percentage represented by unit length. The width and
pattern of a section of the arm indicate the corresponding speed or height class. The length of each
section of the arm represent the percentage of the time that wind or waves come from that direction in a
given speed or height class.
In this document four different data sources where used to determine the boundary conditions. These
sources are:
- Recordings from Port of Fujairah Marine Department;
- Recordings from the VHFL-jetty;
- Ship observations from Hydrobase;
- Satellite observations from Argos.
All to be found in the Data report annex 2 to 07-5211-Ph.1
At a distance of 500 m north of the proposed new port expansion, Vopak Horizon Fujairah Ltd. (VHFL)
runs an open sea tanker terminal. At the jetty, measurements are being made on wave heights and
directions, wind speeds and directions, water temperatures and current speeds. In this report, the results
of these measurements are further mentioned as the records from the VHFL-jetty.
Measurements have been made with an instrument using the Doppler shift principle over orbital motion
for wave heights and directions. Recordings are available over a fairly long period and they could have
been the most important data source. The placement of the instrument however raises some questions
about the reliability of the results. The instrument on the jetty is placed southwest from the largest berth
on the jetty. During occupation of this berth, the instrument lies on the lee side of the ship for waves
coming from the northeast. Most likely for this reason, waves from the northeast are poorly represented
in the measurements results. Wave data from the measurements will be analyzed to check other sources
but will not be decisive for the designs.
For the determination of the environmental boundary conditions, measurements by the Port of Fujairah
Marine Department as well as ship and satellite observations are available. Wind and wave data from
ship observations are derived from the Hydrobase database. Wind and wave data from satellite
observations are derived from the Argoss database.
10/29/2007 A1 - 4
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 1: Derivation of boundary Conditions
A 1.3.1 Wind
Winds in Fujairah are fairly light. According measurements and ship and satellite observations, wind
speeds of 8 m/s are not exceeded 90 % of the time but strong winds from the west do occur. These winds
are described as Katabatic winds by the Port Authorities. It is expected that these north-westerly winds
are caused by the “Shamal” weather system.
In graph A 1.1, omnidirectional wind speeds according to four data sources are plotted. It can be seen
that these sources show fairly consistent wind speeds. As the wind roses in figures1.1 to 1.6 show, wind
directions according to available sources differ somewhat. This can be explained by the difference of the
location where data is derived from and local influences like obstacles that block winds from certain
directions.
35.00
30.00
25.00
Wind speed [m/s]
20.00
15.00
10.00
5.00
0.00
0.01 0.1 1 10 100
Exceedence [%]
graph A 1.1 Wind speed exceedence according to four data sources, omnidirectional.
For the available sources wind data, the extreme values were determined using a Weibull distribution. In
graph A 1.2, the extreme omnidirectional values for these four sources are plotted. It can be seen that
with a return period of 100 years, wind speeds of 34 m/s can be reached. These winds most likely come
from the Northwest.
10/29/2007 A1 - 5
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 1: Derivation of boundary Conditions
40
35
30
wind speed [m/s]
25
20
15
10
0
1 10 100
return period [yrs]
Argos satelite (off shore) Port authorities measured
Ship observations (off shore) VHFL measured 2 (at jetty)
graph A 1.2 Extreme Wind speeds according to four data sources, omnidirectional.
For the determination of the wind climate, the following data sources where analyzed.
- Recordings from Port of Fujairah Marine Department;
- Recordings from the VHFL-jetty;
- Ship observations from Hydrobase;
- Satellite observations from Argos.
The Port of Fujairah Marine Department hourly reports the state of the weather. Measurements of wind
speeds and directions are part of this weather report. Figure 1.1 shows the annual wind rose of recordings
made in the January 2005 to December 2005. This wind rose shows that the most and strongest winds
come from the West. Percentages of occurrence of omnidirectional wind speeds according to records
made by the Port of Fujairah Marine Department are distributed as shown in table A 1.1.
10/29/2007 A1 - 6
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 1: Derivation of boundary Conditions
VHFL recordings
The wind data measured at the VHFL jetty was provided in the form of a time series of 10-minute
average wind speed and direction (i.e. average taken over the previous 10 minutes) every 10 minutes for
the period from April 2001 to January 2004. This series was converted to a time series of hourly
averaged wind speed and direction. This was done by averaging the wind speed over one hour. The
direction was taken by averaging the x component and the y component of the wind velocity and taking
the vectorial direction of these averages.
Figure 1.2 shows the annual wind rose resulting from this analysis. This rose indicates that the wind
conditions at the site are very mild, with winds less than 6 m/s for most of the time. For a small part of
the time (3.3 %) Shamal winds occur from the Northwest of 6 m/s or more. Only very weak winds (<4
m/s) come from the Northeast. These wind conditions seem to be milder than suggested by the Port
Authorities, although the directional characteristics are similar. Percentages of occurrence of
omnidirectional wind speeds according to records made at the VHFL-jetty are distributed as follows:
Ship observation
Figure 1.3 shows the annual wind rose for the wind climate based on ship observations. According to
these observations, most winds are force 4 or less (less than 8 m/s). Wind speeds, higher than 8 m/s occur
about 5% of the time. Most of the winds with these speeds come from westerly directions (i.e. from the
land).
From the monthly wind roses, figures 1.4 and 1.5, it can be seen that in the period from December to
March the dominant direction is from the West and Northwest. In the period from July to September the
dominant direction is from the East and Southeast.
In general it may be expected that winds over open sea are significantly higher than wind over land
because of boundary layer effects. Furthermore, if the wind is less than 8 m/s, the wind direction may be
considerably different at the coast than on open sea due to the effect of sea breezes. Further, the high
wind speeds from the West in the ships observations are also expected to be caused by the same Shamal
weather system that causes the winds from Northwest at the coast. Percentages of occurrence of
omnidirectional wind speeds according to ship observations are given in table A 1.3.
10/29/2007 A1 - 7
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 1: Derivation of boundary Conditions
Satellite observations
Figure 1.6 shows the annual wind rose for the wind climate based on satellite observations. The centre of
the area where this scatterometer data is derived from is at 25° 11’N, 57° 00’E. Data from 1232 passes is
derived from an area with size 100 x 100 km.
The wind rose shows the offshore wind climate. The main wind directions are from the West and from
the Southeast, where the strongest winds, up to 12 m/s come from the West. According to these satellite
observations, most of the time wind speeds stays below 8 m /s. Wind speeds higher than 8 m /s occur
about 4 % of the time. Percentages of occurrence of omnidirectional wind speeds according to satellite
observations are given in table A 1.4:
10/29/2007 A1 - 8
0,3
1,7
2,7
4,3
5,7
7,3
1
A 1.3.2 Temperature
According to the Port of Fujairah Marine Department weather information, Fujairah has a tropical
climate with a daily average temperature of 34.2°C in summer and 17.8°C in winter. Temperatures vary
between 12.1°C and 24.5°C in winter and between 27.6°C and 42.3°C in summer.
A 1.3.3 Visibility
According to the Port of Fujairah Marine Department weather information, visibility at Fujairah is
generally good but during strong offshore winds, there can be problems with dust. Visibility is still
possible over a hundred meters, allowing berthing using modern navigation aids.
The Port of Fujairah Marine Department records weather conditions. According to these recordings the
state of the weather for the year 2005 is described as follows:
According to Port of Fujairah tidal information water levels are distributed as shown below:
The seawater at Fujairah has a density 1024 kg/m3. This value has been determined by sample analysis.
The data report contains a copy of the certificate of this sample analysis. According to the Port of
Fujairah weather information, seawater temperatures vary between 22° C and 24° C in winter and
between 30° C and 33° C in summer.
10/29/2007 A1 - 15
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 1: Derivation of boundary Conditions
The harbour master reports that there is no maintenance dredging required in Fujairah. Regarding the
current velocities and sediment characteristics not much sedimentation or erosion is expected.
A 1.4 Currents
Current velocities at the location of the proposed Port expansion are relatively low, not exceeding 0.2 m/s
most of the time. Currents are aligned parallel to the coast, mainly directed to the North but currents
directed to the South do occur a few hours per day during low water and in July, during the Monsoon
period.
At the location of the VHFL-jetty, current speeds and directions where measured hourly for several
years. These measurements show a north-easterly directed current with velocities that are relatively low
and do not exceed 0.18 m/s, 90 % In graph A 1.3 the exceedence of current speeds measured at the
VHFL-jetty are plotted.
0.6
0.5
current velocity [m/s
0.4
0.3
0.2
0.1
0
0.01% 0.10% 1.00% 10.00% 100.00%
Exceedence [%]
graph A 1.3 Exceedence graph of omnidirectional current velocities according to VHFL measurements
10/29/2007 A1 - 16
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 1: Derivation of boundary Conditions
According to the Port of Fujairah Marine Department, the Arabian Sea Pilot indicates maximum current
velocities of 0.39 m/s occurring during July (The Southwest Monsoon period). This current is aligned
parallel to the coast in a Southerly direction. Observations made during the site investigations for the
construction of the port showed currents not exceeding 0.26 m/s, with the direction flow being generally
to the North and reversing to the South for a few hours during on of the low water periods each days.
Floater measurements made in April and May 2006 confirm that southerly directed currents do occur and
current velocities are relatively low. The average measured current velocity lies at 0.09 m/s and reach a
maximum velocity of 1.2 m/s. Measurements are made at different spots at the location of the new port
expansion according to the map in. A plot of the floater displacements shows generally southern directed
currents. It must be regarded that the results of these measurements must be seen as momentary.
A 1.5 Waves
Sumary
The normal wave climate at the location of the proposed new Port expansion is mild. Waves are
relatively low, only exceeding 1.5 m 0.5% of the time (1.8 days per year). The main wave direction is
from the East and Southeast.
Wave data is available from ship and satellite observations and measurements at the VHFL-jetty.
In graph A 1.4 the wave height exceedence statistics for waves at the location of the VHFL terminal
derived from ship observations and from measurements made at this location are plotted. It can be seen
that the wave height distributions of the two wave climates are rather consistent.
3.0
2.5
2.0
Wave height [m]
1.5
1.0
.5
.0
.01 .10 1.00 10.00 100.00
Exceedence [%]
Ship Observations VHFL-measurements
10/29/2007 A1 - 17
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 1: Derivation of boundary Conditions
graph A 1.4 Wave height exceedence by Ship observations and VHFL measurements
For the determination of the normal wave climate, both ship observations and measurements at the
VHFL-jetty are considered. The wave height distributions of these wave climates agree very well but the
wave climate based on ships observations contains significantly more waves from the Northeast than the
wave climate according to the measurements at the VHFL-jetty. This can possibly be explained by the
location where the measurements have taken place and the possible blocking of waves by moored ships
at the VHFL-jetty. The measurement from the VHFL-jetty do also not represent all months. For these
reasons, the emphasis is on the wave data from the ships observations as this includes waves from the
Northeast and contains data from all months.
Wave heights for different directions at the location of the VHFL-jetty according to the transformed ship
observations are distributed according to table A 1.8.
Hs (m) 15° - 45° 45° - 75° 75° - 105° 105° - 135° 135° - 165° 165° - 15° Total
[%] [%] [%] [%] [%] [%] [%]
> 0.2 7.86 4.96 7.43 12.67 6.71 .19 39.83
> 0.4 2.93 3.13 5.48 9.02 2.94 .01 23.51
> 0.6 1.03 1.42 3.48 5.53 1.20 . 12.66
> 0.8 .19 .72 2.23 3.23 .39 . 6.76
> 1.0 .06 .25 .96 1.40 .20 . 2.87
> 1.2 .02 .14 .37 .68 .08 . 1.28
> 1.4 .01 .06 .12 .29 .03 . .51
> 1.6 . .01 .06 .13 .02 . .21
> 1.8 . . .03 .07 .01 . .11
> 2.0 . . .01 .06 . . .07
table A 1.8 Percentages of time that the wave heights in the given direction are exceeded at the location of the VHFL-jetty
according to transformed ship observations.
In this table the percentage of time is shown that wave heights are exceeded and come from the given
direction and in the last column, the total percentage of time that wave heights are exceeded (joint
probability of wave height and direction).
The directions of waves are not indicated. As stated, at the moments that rough seas are recorded, also
high waves are measured at the VHFL jetty. It shows that the state of the sea is smooth or slight for most
of the time. Although these data have a low accuracy and can not be used in further calculations, they are
used to verify the moments that high waves are measured at the VHFL-jetty.
Port of Fujairah Marine Department gives information based on a study that has been carried out in 1979
for a location offshore of the harbour. This study can be summarized as follows:
10/29/2007 A1 - 18
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 1: Derivation of boundary Conditions
Most severe waves come from the directions between East and Southeast with waves with an Hs of 3.5 m
exceeded for 0.1% of the time and waves higher than 1.5 m exceeded for 0.5% of the time.
Moderately high waves also come from the North. East Northeast and South Southeast; where significant
wave heights of 2 m are exceeded for 0.1% of the time
It should be born in mind that these wave conditions are offshore and should be expected to be milder
close to the coast both due to sheltering and shallow water effects.
It can be seen from figure 1.7 that most of the time waves come from the East and Southeast. Since the
measurements are made near the jetty, there is a possible influence of berthed ships on waves from the
Northeast. Berthed ships may possibly block waves that come from this direction. The data set with wave
measurements from this site contained no information of wave periods.
Ship observations
Offshore wave data from Ship observations are available of observations in the period between 1960 and
1997. A selection of these data was made in a coastal strip of length 100 km (centered on Fujairah) and
width 70 km. Figure 1.10 shows the wave rose according to wave data from these ship observations. A
standard correction was applied to the observed wave height to get the significant wave height
(multiplication by 0.8). The offshore wave conditions from the ship observations (without correction) are
broadly consistent with the information given by the harbour master.
The climate based on the corrected ship observations was transformed to the site of the VHFL terminal to
account for refraction, shoaling and dissipation by bottom friction. The wave rose of transformed wave
data is plotted in figure 1.11.
10/29/2007 A1 - 19
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 1: Derivation of boundary Conditions
The part of the wave crest closer to shore is in shallower water and moving slower than the part away
from the shore in deeper water. The wave crest in deeper water catches up so that the wave crest tends to
become parallel to the shore.
Shoaling occurs as the waves enter shallower water. The wave speed and wavelength decrease in shallow
water, therefore the energy per unit area of the wave has to increase, so the wave height increases. The
wave period remains the same in shoaling.
Distribution of ship observed wave periods are show in table A 1.12. In this table the joint probability of
observed wave periods and significant wave heights are shown.
Hs (m) < 5.5 7.5 9.5 11.5 13.5 15.5 17.5 19.5 21.5
Low Up 5.5 7.5 9.5 11.5 13.5 15.5 17.5 19.5 21.5 > total
< .25 42.73 . . .65 . . . . . . 43.38
.25 .75 33.53 .94 .39 .13 .13 .03 . . . . 35.15
.75 1.25 12.87 1.67 .18 .03 .05 .08 . . . . 14.88
1.25 1.75 3.02 .65 .31 . . .03 . . . . 4.01
1.75 2.25 1.28 .42 .08 .05 .03 . . . . . 1.85
2.25 2.75 .29 .08 . .03 . . . . . . .39
2.75 3.25 .13 .05 .03 . . . . . . . .21
3.25 4.25 . .08 . . . . . . . . .08
4.25 5.25 . .03 . . . . . . . . .03
5.25 6.25 . . . .03 . . . . . . .03
Total 93.85 3.91 .99 .91 .21 .13 . . . . 100
table A 1.12 Joint probability of occurrence of wave periods and heights
From table A 1.12 a relation between observed wave period and significant wave height in deep water as
given in equation [1.5.1] can be found.
Further the relation between the observed period and peak period based on experience with ship
observations is given in equation [1.5.2].
10/29/2007 A1 - 20
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 1: Derivation of boundary Conditions
Satellite observations
Offshore wave data from satellite observations are available in the form of scatter tables with the
occurrence frequency of wave heights versus wind speeds. The directions of the waves are not indicated.
These data show wave heights that are larger than the heights from the ship observations database and
measurements of the VHFL-jetty. This can be explained by the fact that this dataset contains waves
generated by storms with winds that come from the West and the Northwest. These winds generate
waves that travel in southern and south-easterly direction. These waves do not arrive at the location of
the Port of Fujairah. For this reason the wave heights from the satellite observations are not used to
determine the near shore normal wave climate.
10/29/2007 A1 - 21
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 1.7
Wave rose, Fujairah, source: measurements VHFL jetty (Dec 2003 – Feb. 2006)
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 1.8
Wave roses seasonal. Fujairah, source: measurements VHFL jetty
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 1.9
Wave roses seasonal. Fujairah, source: measurements VHFL jetty
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 1.10
Wave rose, Fujairah off shore, source: ship observations
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 1.11
Wave rose, Fujairah, source: ship observations
M.U.C. Engineering
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 1: Derivation of boundary Conditions
The extrapolation is carried out, using a Weibull fit on the frequency distribution of the Hydrobase off
shore ship observation and the Argoss off shore satellite observation. The Weibull technique fits a curve
to the frequency distribution of the return periods. These Weibull curves are presented in figures 1.12 to
1.17. For this Weibull extrapolation, the full data set of ship observations is used. There is no selection of
storms being made to fit these curves on, since other effects than the winds that cause the normal wave
climate are not expected. Although the Shamal weather system causes high waves in the region, these
winds are directed to the east and will not cause large wave heights near the Fujairah coast.
The numerical results of the Weibull extrapolation of the offshore extreme wave heights are shown in
table A 1.13.
The stated wave periods are based on an assumption of constant wave steepness derived from the relation
[1.5.1] between significant wave height and observed period. From table A 1.13 it can be seen that the
highest waves come from a southeasterly direction between 135° and 165°. The offshore wave heights
are translated to near shore conditions (14 m. depth line) taken into account the effects of refraction,
shoaling and dissipation due to bottom friction. Additional to these effects, a factor of 10% uncertainty is
added to these resulting wave heights. This results in the near shore wave heights and directions as given
in table A 1.14.
10/29/2007 A1 - 27
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 1: Derivation of boundary Conditions
It can be seen that the highest waves near shore (at a depth of 14 m) come from a direction between 105°
and 135°. This means that although offshore waves from a more southern direction are higher, due
refraction waves from a direction between 105° and 135° are decisive.
In figures 1.18 to 1.21, the characteristics of waves from a direction between 105° and 135° are shown
for different return periods. From these figures it can be seen that for different water depths, wave
characteristics can be summarized according to table A 1.15.
The finals near shore design wave characteristics with a return period of 100 year are:
Hs 3.80 m
Tp 10.0 s
dir 110.7°
The other two sources with wave data, VHFL-jetty measurements and Argoss satellite observations have
not been taken into account for the determination of the extreme near shore wave climate.
The extreme wave height that is determined using the Argoss satellite observations data set is 5.8 m.
Since only omnidirectional wave heights are available from satellite observations, this is the
omnidirectional extreme off shore wave height for a return period of 100 years. Directional information
from satellite observations is available through wind data. The wind rose of the extreme values from
satellite observations, show that maximum wind speeds are expected to be in a southern direction. Waves
generated by these winds are not expected to reach the coast of Fujairah and do therefore not represent
the extreme near shore wave climate at the location of the new Port of Fujairah.
The data from the VHFL-measurements is near shore wave data. As stated in the previous paragraph,
waves from northern directions are not represented in the data. Since for this reason it would not be
correct to determine the extreme wave climate directly from these records, the data is used to check the
wave data from ship observations. This is done by determining the omnidirectional extreme wave heights
from the VHFL-measurements and from the ship observations transformed to near shore values. These
values seem to be consistent.
10/29/2007 A1 - 28
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 1.12
Extreme off shore wave height, omnidirectional, source: ship observations
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 1.13
Extreme off shore wave height, angle of incidence 15° - 45°, source: ship observations
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 1.14
Extreme off shore wave height, angle of incidence 45° - 75°, source: ship observations
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 1.15
Extreme off shore wave height, angle of incidence 75° - 105°, source: ship observations
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 1.16
Extreme off shore wave height, angle of incidence 105° - 135°, source: ship observations
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 1.17
Extreme off shore wave height, angle of incidence 135° - 165°, source: ship observations
M.U.C. Engineering
Breaking
Wave height
4.3
4.2
4.1
4
3.9
3.8
23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5
Hs0 = 4.33 m
T = 9.4 sec.
Wave length
150
100
50
0
23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5
Angle of incidence
30
20
10
0
23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5
4
3.9
3.8
3.7
3.6
23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5
Hs0 = 4.09 m
T = 9.1 sec
Wave length
150
100
50
0
23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5
Angle of incidence
30
20
10
0
23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5
3.2
3.1
2.9
23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5
Hs0 = 3.26 m.
T = 8.1 sec.
Wave length
120
100
80
60
40
20
0
23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5
Angle of incidence
40
30
20
10
0
23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5
2.5
2.4
2.3
2.2
2.1
23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5
Hs0 = 2.42 m.
T = 7.0 sec.
Wave length
100
80
60
40
20
0
23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5
Angle of incidence
40
30
20
10
0
23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5
A 1.6 Bathymetry
The bathymetry for the present situation is based on a survey carried out in November 2005 from the
southern breakwater of the existing port to the southern breakwater of the Naval Base. According to the
survey the bottom slope is mild at the location of the proposed new port expansions and is 1:102 with
parallel depth contours.
A 1.7 Geotechnical
In October 2006, Fugro Middle East performed a near shore geotechnical investigation for the Northern
Port Expansion Project. This investigation comprised a complete geotechnical survey of 38 boreholes to
various depths, including sampling and coring.
The borehole observations and laboratory tests results indicated that the subsurface is relatively
consistent throughout the site, consisting of two main units that are:
- Upper soil sediments
- Underlying bedrock
The upper soil sediments consisted mainly of grey, silty to very silty, medium to fine sand, with varying
amounts of shell fragments that reached gravel size. The thickness of this layer varies throughout the site
from less than 2.0 m to more than 11.0 m. This unit is observed to thicken mainly in the proposed
harbour dredging and landfill area. This phenomenon might be explained by limited sediment transport in
this area facing the existing breakwater wall. A thinner seabed sand layer is observed in the proposed
berth area, located further south east of the site where sediment transport might be more considerable.
Generally, the upper 3 meters of the soil sediments unit were proven to be very loose. Towards the
bottom, the unit becomes medium dense.
The underlying bedrock consisted mainly of intercalating layers of siliceous calcarenite, calcareous
sandstone and conglomerate. These three sub units are essentially similar, with difference in silt and
carbonate content, the sandstone being siltier and less carbonaceous. Limited presence of calcareous
siltstones and siliceous calcirudites, most probably in the form of lenses, are encountered within the
major bedrock unit. The bedrock extended throughout the site, from beneath the soil unit to the full depth
of the boreholes. The overall strength of the bedrock ranged from extremely weak to weak; indicating
slightly indurated/cemented rock mass. Fracturing spacing ranged from being wide to medium fractured
with occasional presence of zones of very closely fractured, non indurate/cemented rock
A 1.7.2 Seismic
The site is recognized as being in an area with low seismic activity and conservative design values
sourced from reference codes and other projects being applied.
10/29/2007 A1 - 39
A2 Annex 2 Harbour layout alternatives
10/29/2007 A2 - 1
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 2 Harbour layout alternatives
Contents
List of Figures
10/29/2007 A2 - 2
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 2 Harbour layout alternatives
10/29/2007 A2 - 3
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 2 Harbour layout alternatives
A 2.1 Introduction
This annex to the report Masterplan for the Port of Fujairah Expansion Project gives the proposed
harbour layouts and oil terminal layouts that are described in chapter 5 of the report. Further the locations
of the oil storage facilities and the aggregate stockpile area are shown
The figures 2.12 to 2.41 show combined proposed harbour basin and liquid bulk terminal layouts.
10/29/2007 A2 - 4
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.1
Layout A1
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.2
Layout A2
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.3
Layout A3
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.4
Layout A4
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.5
Layout A5
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.6
Layout B1
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.7
Layout B2
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.8
Layout B3
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.8
Layout B4
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.10
Location of oil storage facilities
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.11
Location of aggregate stockpile areas
M.U.C. Engineering
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 2 Harbour layout alternatives
The following figures show combined harbour basin and liquid bulk terminal layouts.
10/29/2007 A2 - 16
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.12
Layout A1 B1 phase 1 option A
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.13
Layout A1 B1 phase 2 option A
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.14
Layout A1 B1 phase 3 option A
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.15
Layout A1 B1 phase 1 option B
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.16
Layout A1 B1 phase 2 option B
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.17
Layout A1 B1 phase 3 option B
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.18
Layout A2 B2 phase 1
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.19
Layout A2 B2 phase 2
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.20
Layout A2 B2 phase 3
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.21
Layout A2 B1 phase 1
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.22
Layout A2 B1 phase 2
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.23
Layout A2 B1 phase 3
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.24
Layout A3 B1 phase 1
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.25
Layout A3 B1 phase 2
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.26
Layout A3 B1 phase 3
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.27
Layout A4 B3 phase 1
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.28
Layout A4 B3 phase 2
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.29
Layout A4 B3 phase 3
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.30
Layout A4 B4 phase 1
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.31
Layout A4 B4 phase 2
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.32
Layout A4 B4 phase 3
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.33
Layout A5 B1 phase 1
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.34
Layout A5 B1 phase 2
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.35
Layout A5 B1 phase 3
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.36
Layout A5 B3 phase 1
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.37
Layout A5 B3 phase 2
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.38
Layout A5 B3 phase 3
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.39
Layout A5 B4 phase 1
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.40
Layout A5 B4 phase 2
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 2.41
Layout A5 B4 phase 3
M.U.C. Engineering
A3 Annex 3 Ship simulation model
10/29/2007 A3 - 1
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 3 Ship simulation model
Contents
List of tables
table A 3.1 Dry bulk vessel size distribution according to Lloyd’s register vessel statistics ................... 7
table A 3.2 Simulation results dry bulk export 20 M ton/yr ..................................................................... 8
table A 3.3 Simulation results dry bulk export 30 M ton/yr ..................................................................... 9
table A 3.4 Simulation results dry bulk export 40 M ton/yr ..................................................................... 9
table A 3.5 Simulation results dry bulk export 50 M ton/yr ................................................................... 10
table A 3.6 Simulation results dry bulk export 60 M ton/yr ................................................................... 10
table A 3.7 Simulation results dry bulk export 70 M ton/yr ................................................................... 11
table A 3.8 Simulation results dry bulk export 80 M ton/yr ................................................................... 11
table A 3.9 Simulation results dry bulk export 90 M ton/yr ................................................................... 12
table A 3.10 Simulation results dry bulk export 100 M ton/yr ................................................................. 12
table A 3.11 Simulation results aggregates............................................................................................... 13
table A 3.12 Simulation results dry bulk import 2 M ton/yr .................................................................... 14
table A 3.13 Simulation results dry bulk import 4 M ton/yr .................................................................... 14
table A 3.14 Simulation results dry bulk import 6 M ton/yr .................................................................... 15
table A 3.15 Simulation results dry bulk import 8 M ton/yr .................................................................... 15
table A 3.16 Simulation results dry bulk import 10 M ton/yr................................................................... 16
table A 3.17 Simulation results dry bulk import....................................................................................... 16
10/29/2007 A3 - 2
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 3 Ship simulation model
10/29/2007 A3 - 3
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 3 Ship simulation model
A 3.1 Introduction
This annex to the Masterplan for the Port of Fujairah Expansion Project, describes the simulation models
developed for the Port of Fujairah Expansion Project. The following sections describe the basic logic of
the simulation model and provide details of how the model behaves given specific events.
A standard spreadsheet program was used to develop the – discrete event simulation model. The type of
simulation that was used uses the Monte Carlo method, which makes use of random numbers to select
model inputs from pre-defined statistical distributions. By repeatedly testing the model, a statistical
distribution can be developed for the solution of variables. Monte Carlo methods are suitable for
simulation of bulk terminals, due to the complex interaction of random variables.
For the Expansion Project of the Port of Fujairah several simulation models where developed.
The main topics that were studied are:
- Throughput capacity of a new dry bulk terminal in combination with the existing dry bulk
facilities in the Port of Fujairah.
- Throughput capacity of a new liquid bulk terminal in combination with the existing liquid bulk
facilities in the Port of Fujairah.
- Throughput capacity of a new Container terminal.
The throughput capacities of these terminals where tested in two steps. The first step gives an estimate
for the quay length, number of berths and number of cranes that is required to reach a certain throughput.
The input values for these runs are the proposed throughput scenarios, vessel dimension and assumed
capacities of cranes and conveyor belts. The results of this step are used to create layout alternatives. The
second step is to estimate the throughput capacities of the proposed layout alternatives. The results of
these calculations are used for the evaluation and selection of the proposed layouts.
The model generates ships calling the port of Fujairah. The size of the ships and the inter arrival time are
according to predefined statistical distributions. The ship enters the port of Fujairah and is served at a
free berth that is able to handle the specific ship size. This can be immediately or when all berths are
occupied after waiting. The ship that arrives first is being served first. This system is called FIFO (first in
first out). The number of berths and the capacity of the berths can be varied.
The model is first used to determine the required quay length and number of berths for several desired
throughput capacities. For this purpose, the average inter arrival time for which the desired throughput
can be reached is determined. Subsequently the number of berths is varied until average waiting times are
at an acceptable level.
10/29/2007 A3 - 4
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 3 Ship simulation model
0.2
0.15
0.1
0.05
0
0 5 10 15 20
10/29/2007 A3 - 5
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 3 Ship simulation model
graph A 3.1 Erlang 3 distributions with average inter arrival time of 3.5 hr.
Where x is the set of simulation outputs and n is the number of simulation runs. The minimum number of
runs to assure that the estimate of the mean lies within 10% of the true mean with α = 0.05 is given:
⎡ ⎧⎛ ⎫⎤
( ) p ⎞
m
∑
tα 2 ⋅ var( X i ) ⋅ ⎢1 + 2 ⋅ ⎨⎜1 −
2
p =1 ⎩⎝
⎟ ⋅ ρ p1 x ⎬⎥
m +1⎠ ⎭⎦⎥
n= ⎣⎢ [Annex 3.3.6]
(dμ ) 2
Further a basic criteria for the minimum duration of the simulation period is that the queue length at the
beginning of the simulation period is independent of the queue length at the end of the period
A 3.4.1 Introduction
The dry bulk terminal exists of two parts. One part is exclusively used for to the loading of aggregates
and one part for the unloading of other dry bulk. This other material will most likely be clinker or
bauxite. One of the planned developments in the emirate of Fujairah is the construction of a cement
factory. This will be the main reason to make the aggregate unloading facility.
Vessel dimensions
Dimensions of dry bulk vessels are distributed according to table A 3.1 for dry bulk. These values are
derived from Lloyd’s register vessel statistics.
10/29/2007 A3 - 6
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 3 Ship simulation model
The dry bulk terminal at least for phase 1, will be designed for cape size vessels. (150,000 – 175,000
DWT ) and smaller.
The loading of aggregates will be a continuous process where ship loaders will be fed by a conveyor belt
system from the stockpile area. The port has ordered cranes that have loading rates of maximum 4.4 ton
per hour. The average loading rate of this crane is 3,400 ton per hour. The cranes are capable of loading
ships up to 175,000 DWT. These cranes are travelling shiploader types which mean that they can move
parallel to the quay.
To determine the required number of cranes for the port expansion and the composed scenario’s
according to the previous chapter, a basic simulation of the port system has been carried out.
For this simulation the following assumptions have been made:
- Ships sizes of dry bulk vessels that call the future Port of Fujairah are distributed according to
table A 3.1. It is also assumed that the average parcel size of these vessels is evenly distributed
between half full and full.
- The existing port (only the aggregate ship loader and not lift and grab operation) is part of the
system. The average loading rate for this berth is 1,700 ton per hour. Ships calling the Port of
Fujairah will be berthed in the existing port first. Since the maximum draft is only 15 m in the
existing port, only ships up to 100,000 DWT can be handled in the existing port.
- Ships are handled according to a “first in first out” system. If the size of the vessel admits it, it
will first be berthed at the existing port. If this berth is occupied it will be berthed at a quay in the
new port expansion.
10/29/2007 A3 - 7
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 3 Ship simulation model
- The average idle time is 3 hours. This is the time that the berth can not be used by other ship
while the ship loader is not operating. This time is used for mooring the ship, administrative
processes and for getting the required material on the conveyor belt.
- Ships arrive at the port according to an Erlang-3 distribution. This distribution is chosen because
the interval of arriving ships is expected to be relatively regular. The material is transported by a
limited number of shipping agents.
- One ship is served by not more than one ship loader.
A 3.4.3 Results
20 M ton yearly
Average inter arrival time 20.5 hr
10/29/2007 A3 - 8
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 3 Ship simulation model
30 M ton yearly
Average inter arrival time 14.3 hr
40 M ton yearly
Average inter arrival time 10.8 hr
10/29/2007 A3 - 9
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 3 Ship simulation model
50 M ton yearly
Average inter arrival time 8 hr
60 M ton yearly
Average inter arrival time 6.8 hr
10/29/2007 A3 - 10
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 3 Ship simulation model
70 M ton yearly
Average inter arrival time 5.85 hr
80 M ton yearly
Average inter arrival time 5.15 hr
Service time [hr] 18.2 26.2 10.6 10.6 18.8 30.0 30.2
table A 3.8 Simulation results dry bulk export 80 M ton/yr
10/29/2007 A3 - 11
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 3 Ship simulation model
90 M ton yearly
Average inter arrival time 4.64 hr
Service time [hr] 18.0 25.2 16.1 16.1 14.7 27.6 26.5
table A 3.9 Simulation results dry bulk export 90 M ton/yr
Service time [hr] 17.8 25.3 15.7 15.7 17.5 23.2 23.5
table A 3.10 Simulation results dry bulk export 100 M ton/yr
10/29/2007 A3 - 12
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 3 Ship simulation model
A 3.4.4 Summary
The results of the simulation study are given in table A 3.11. As can be seen from this table the berth
occupancy gets higher as the number of berths increases.
Required Total new quay Total no of new Average berth Average waiting
throughput length cranes occupancy time
[M ton/yr] [m] [hr]
15 340 1 44% 1.23
20 605 2 37% 0.67
30 645 2 52% 0.95
40 810 3 50% 1.48
50 910 3 63% 1.60
60 1190 4 57% 0.50
70 1190 4 66% 1.00
80 1335 5 62% 1.04
90 1395 5 68% 1.01
100 1435 5 77% 1.95
table A 3.11 Simulation results aggregates.
10/29/2007 A3 - 13
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 3 Ship simulation model
A 3.4.5 Results
2 M ton yearly
Average inter arrival time 180 hr
4 M ton yearly
Average inter arrival time 95 hr
10/29/2007 A3 - 14
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 3 Ship simulation model
6 M ton yearly
Average inter arrival time 53.5 hr
8 M ton yearly
Average inter arrival time 69 hr
10/29/2007 A3 - 15
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 3 Ship simulation model
10 M ton yearly
Average inter arrival time 45 hr
A 3.4.6 Summary
For scenario B1, one crane will be sufficient to serve for the demand until the end of phase 1. For phase 2
and 3, a second crane is needed. Scenario B2, representing medium growth, it will be possible to serve
for the demand in import capacity for phase 1 and 2, eventually in phase 3, a second crane is needed. In
scenario B3, import increases only slightly. It will not be necessary to realize the proposed ship unloader
with conveyor belt. In fact, these amounts of material can be handled by ship based crane (lift and grab
operation) at an unoccupied quay in the new or existing port.
For the planning aspects if the new liquid bulk terminal, it is assumed that the vessel size distribution
according to Lloyd’s vessel statistics does not represent the distribution of vessel sizes that is expected at
the new oil terminal. It would be more appropriate to assume that vessel sizes depend on the function of
the delivery. Per storage function and for import and export, an average vessel type is assumed. Material
with longer storage times is transported by larger vessels. Material for blending is transported by medium
10/29/2007 A3 - 16
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 3 Ship simulation model
size vessels. Bunker fuel storage is replenished by large size vessels. The bunker vessels are smaller
ships. These assumptions will be used for throughput, waiting time and berth occupancy calculations and
are summarized in table A 3.18. The second and third columns give the percentage of the total storage
volume that is used for the specific function. The last to columns give the ship sizes that are used for the
specific delivery.
The speed of the load and unload operations of these ships depend on the flow velocities in the pipes, the
diameters of loading arms and the number of loading arms per berth. The flow velocities again depend on
the onshore pump capacities, the onboard pump capacity of ships and pipe properties. The following
average flow velocities for load and unload operations are assumed. (based on VHFL experience and
calibrated with VHFL berth occupancy and waiting times)
- Loading of black material: 3 m/s
- Unloading of black material 3.5 m/s
- Loading of white material: 4 m/s
- Unloading of white material 4.5 m/s
The velocities for clean products (white) are higher as these have a lower viscosity and less pipe
resistance as a consequence.
The distribution of the inter arrival time of the ships is assumed to be Erlang 3. The arrival pattern is
expected to be relatively regular. The idle time is assumed to be 3 hours on every berth and ship size. The
system is assumed to be First in First Out. With the parameters described in this paragraph, the
throughput capacity of several numbers of berths having several different sizes has been estimated. The
current berths OTB1, OTB2 and OTB3, are assumed to be part of the total system so they are
implemented in the model. The model has been used to estimate the maximum throughput of the OTB’s
for an average waiting time, not longer than 1 hour. It resulted from this test that the OTB’s can handle a
total throughput of 16.4 M ton per year. With the distribution of storage times as described in the
masterplan report, this means a total storage volume of 2.13 M m3 can be served with this facility.
The model was calibrated by analysis of the existing VHFL terminal throughput, waiting times and berth
occupancy data from 2006. For several storage volumes the required number of berths is determined
using all assumptions mentioned in this report. These proposed numbers of berths are given in table A
3.19. These figures present the outcome of the simulation study including the OTB’s.
OTB 1 and OTB 2 can both be used for one medium size vessel of for two smaller vessels. Since these
berths are in the sheltered harbour basin, it is proposed that as they are used for handling the smaller
tankers. These tankers will suffer a higher downtime if they are berthed at the more exposed Open Sea
Tanker Terminal. The range of bigger tankers will be handled at the new OSTT. These vessels are less
sensitive for wave motions.
10/29/2007 A3 - 17
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 3 Ship simulation model
A 3.5.3 Containers
The simulation of the container terminal is carried out using the following assumptions:
- Container vessel sizes are distributed according to Lloyd’s register vessel statistics. Besides this,
growth of vessel sizes is taken into account by allowing the anticipated vessels with sizes of up
to 400 m and 11,000 in the new port expansion.
- The TEU factor is assumed to be 1.7. This means that twice as much FEU (Forty feet Equivalent
Unit) as TEU are expected in the new port. This TEU factor is determined with the following
expression: f = ( N 20 + 2 ⋅ N 40 ) N tot .
- The gross production of the cranes is assumed to be 25 TEU moves per hour. The assumed
maximum number of cranes is given in the last column of table A 3.20.
- The ship sizes as shown in table A 3.20 are assumed, taking into account the Lloyd’s register
vessel statistics and the assumption that ships will continue to grow in size. For the calculation of
waiting times and berth occupancies when a throughput capacity of 0.5 M TEU is required, it is
assumed that the largest ships do not call the port of Fujairah.
10/29/2007 A3 - 18
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 3 Ship simulation model
TEU Length [m] Draught [m] Breadth [m] % of ships Max number
of cranes
100 – 1000 75 – 185 3 – 10.5 11 – 28 30 % 2
1000 – 2000 145 – 214 8 – 12 23 – 33 32.5 % 3
2000 – 3000 180 – 260 10 – 12.5 29 – 33 15 % 4
3000 – 4000 235 – 285 11.5 – 13 32 – 33 10 % 5
4000 – 5000 250 – 300 12.5 – 14.5 32 – 38 5% 6
5000 – 7000 265 – 315 12.5 – 14.5 38 - 42 5% 8
7,000 – 11,000 315 - 400 14.0 – 15.5 42 - 56 2.5 % 10
table A 3.20 Container vessel size distribution used for simulation
- The number of containers that need to be handled per vessel is 50% to 100% of its total capacity,
equally distributed between this maximum and minimum. It is further assumed the number of
imported containers is equal to the number of exported containers.
- The simulation is carried out using a fixed number of berths. This means that the throughput
capacity, berth occupancies and waiting times are not determine for a number of quay lengths.
Instead the number of berths, the berth capacity and the number of cranes are varied to find
acceptable values for waiting times and occupancy. It is assumed that an average waiting time of
0.5 hours is acceptable.
- For the determination of the waiting time an average downtime of 3 days is assumed. This
downtime represents the downtime due to unworkable weather, unusable cranes due to
maintenance and downtime due to exceedence of the maximal allowable ship movement. This
movement is caused by wave penetration. The wave penetration depends on the layout of the
port, the protection of the harbour basin by breakwaters and the reflection coefficient of the
quays.
Using the above mentioned assumptions several number of berths and cranes where tested. The results of
these simulations are given in table A 3.21.
According to the composed scenarios, it can be seen that for scenario D1, at the end of phase 1 a total
quay length of 1432 m is required. For scenario D2 a total quay length of 775 is required at the end of
phase 1, 1702 m at the end of phase 2 and finally after phase 3, 2050 m to able to handle 3 M TEU per
year. In scenario D3, a total length of 1022 is required to be able to handle the total throughput of 1 M
TEU/yr that is anticipated for at the end of phase 2 and 3 in this scenario.
10/29/2007 A3 - 19
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 3 Ship simulation model
10/29/2007 A3 - 20
A4 Annex 4 Principle quay wall design
10/29/2007 A4 -1
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 4 Principle quay wall design
Contents
List of tables
List of Figures
A 4.1 Introduction
This annex describes a principle design for the quay walls in the Port of Fujairah Expansion Project. The
quay wall design was not carried out as a part of this study but is carried out by B.V. Ingenieursbureau
M.U.C.
The most favorable type of quay wall cost as well as construction time wise is a combi sheet pile wall.
The specific dimensions of this structure are given in table A 4.1. The quay wall is designed for a depth
of CD – 18.0 m, the surface level of the reclamation (and top of the quay wall is CD + 4.75 m. So the
retaining height of the structure is 22.75 m). All the quay wall designs are based upon the same
geometry. The quay wall design is assumed to be a combi wall structure.
Tubulars L = 28.5 m
Ø = 1.42 m
d = 16 mm
Infill sheeting Larssen 605
W = 600 mm
L = 22 m
Copping beam 4.0 ⋅ 3.5 m3
table A 4.1 Specific dimensions quay walls
For the back anchoring of the combi wall structure several systems and options have been looked at. Self
drilling anchors with grout cover tie back anchors to a sheet pile wall, both with Dywidag rods or
bundled strand tendons.
A vertical cross section of the proposed design is shown in figure 4.1, a horizontal cross section is shown
in figure 4.2.
10/29/2007 A4 -2
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A
Principle quay wall design cross section
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A
Principle quay wall design top view
M.U.C. Engineering
A5 Annex 5 Principle design Coastal Protection works
Contents
List of tables
10/29/2007 A5 - 2
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
List of Figures
10/29/2007 A5 - 3
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
A 5.1 Introduction
A 5.1.1 General
In this annex to the report “Masterplan for the expansion of the Port of Fujairah” the technical design of
coastal protection works is described in detail.
Fujairah harbour is built on the gulf of Oman coast. This coast runs North South and is almost straight
except for a bay further north at Khorfakkan. The harbour is entirely artificial, being formed by a pair of
rubble mound breakwaters, armoured on the outside with pre-cast concrete Dolos armour units and
otherwise constructed from locally quarried rock.
The breakwaters curve out from the shoreline and overlap so that the entrance faces South-southeast.
This produces generally calm conditions in the port, particularly at the south end where a floating jetty is
operated.
The original design of the breakwaters is based on a wave analysis performed on the basis of hind casting
from local wind conditions. But wave recordings carried out during the construction of the port,
demonstrated that the main wave action originated well out in the Gulf of Oman and that local wind had
little effect. One result of this is that the design of the Fujairah breakwaters is conservative and they
suffer no significant overtopping. The other result is that at certain times there is significant penetration
of southerly waves into the harbour. Local reporting indicates that these events are rare and that the
maximum local wave action near the root of the north breakwater has amplitude of less than one meter.
The breakwaters are founded onto the original seabed and the area within the harbour basin was then
dredged according to the requirements for each zone of the harbour. The soils are generally sandy
becoming more cemented with depth until they can be classified as rock.
10/29/2007 A5 - 4
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
return
period Design life
Years 1 5 10 20 50 100
2 50% 97% 100% 100% 100% 100%
5 20% 67% 89% 99% 100% 100%
10 10% 41% 65% 88% 99% 100%
50 2% 10% 18% 33% 64% 87%
100 1% 5% 10% 18% 39% 63%
225 0% 2% 4% 9% 20% 36%
495 0% 1% 2% 4% 10% 18%
990 0% 1% 1% 2% 5% 10%
table A 5.1 Occurrence probabilities
It should be noted that combined probabilities of multiple events will be less. Where the events are
independent, the combined probability is the product of the individual probabilities.
In reality, events related to marine design conditions are rarely totally independent. An example of this is
the water level is not independent of wave conditions (since the storm surge component is related to the
wave). For these events the combined probability is intermediate between the probability of the single
events and their product. For partially dependent events (waves and water levels), the assessment of the
combined probability is less easy. The combination of a 100 yr water level wit a 100 yr wave has a
combined return which is less than the value corresponding to totally independent events (10,000 years)
but much more than the value of 100 years, corresponding to totally dependent events.
The designs that are proposed in this report will be reviewed on effects due to conditions with varying
return periods. Each of these effects will be treated in a separately way. For effects of combined events,
such as overtopping (dependant on wave height and water level), reasonable assumption will be made for
both values.
A 5.2.2 Structural
Although there are many options for the structural type of revetments that can be applied in the new Port
of Fujairah (mound types, monolithic types, composite types or unconventional types), the choice for a
mound type is quickly made due to the wide availability of rock in Fujairah.
In many cases, the mayor costs of revetments are determined by the price of the rocky material. In areas
where rock is not available, it is being shipped in from mountainous regions. In these situations, the
purchase and transport cost of rocky material can exceed the cost of the construction of a monolithic or
other unconventional structure. Fujairah though, is a mayor supplier of rock for the use of breakwaters.
As the rocky material is produced in quarries, only several kilometers from the New Port, transport costs
are very low.
An advantage of the rubble revetment other than cost is the interaction between the structure and the
subsoil and the behavior at failure. The rubble types are more or less flexible and can even follow uneven
10/29/2007 A5 - 5
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
settlements of the foundation layers. Monolithic structures require a solid foundation that can cope with
high and often dynamic loads.
The behavior of the structure close to failure is also quite different. When a critical load value is
exceeded, a monolithic structure will lose stability at once, whereas a mound type of structure will fail
more gradually as elements from the amour layer disappear one after another.
For the reason mentioned above, rubble-mound breakwaters are the most commonly applied types of
breakwater in the area of Fujairah. In fact, all coastal structures from the northern, to the southern Oman
border are rubble mound.
For these reasons further study on the application of monolithic, composite or unconventional revetments
for the first phase of the New Northern Port Expansion of the Port of Fujairah is not carried out.
A 5.2.3 Armour
For the type of armour it is assumed that rock, available from the mountainous area in Fujairah is cheaper
than the application of new cast concrete armour units. Concrete armour units are not only more
expensive due to material and fabrication cost but will also demand extra skills and equipment for
placement which are cost increasing. Concrete armour units are generally applied when the wave climate
demands a slope stability that can not be reached with rock armour.
An other choice that must be made is whether to make the breakwater with or without crown wall. With
applying a crown wall it is possible to reduce the height of the revetment, while overtopping still remains
within the limits. Though a concrete wall is an expensive structure, it is still possible to reduce cost
because less rocky material is required. In this report both a design proposal is given for a revetment with
and without crown wall.
A 5.2.4 Overtopping
Where berths reclaimed areas, roads, buildings, etc are located behind and close to breakwaters and
revetments, overtopping may cause inconvenience or problems. The amount of allowable overtopping
therefore depends on the function of the particular structure. If the function is to protect an area with
relatively vulnerable structures, lower overtopping discharges are allowed.
Besides the structures behind the revetment, the stability of the inner slope and the transition of the
armoured part of the revetment with the pavement of the land fills, depends on the load of overtopping
waves. Since the reclaimed areas contain roadways, storage areas, and buildings located just behind the
revetments, the allowable amount of overtopping is restricted to a certain limit. Standard references for
commonly accepted damage levels for different overtopping discharges are those indicated in the
(CIRIA-CUR 1991, C5) and are presented in the figure 5.1. The maximum values for return periods of 1,
10 and 100 yr are chosen, taken into account the vulnerability of the structures behind the revetment
(cranes and conveyors). Besides this, the design philosophy is such that preventing is damage is more
important than finding an optimum between maintenance and construction cost.
The estimation of the mean overtopping over the breakwaters and revetments is based on the equation by
Van der Meer and Janssen’s (1995) for run-up and overtopping [Annex 5.2.1] and [Annex 5.2.2]. The
resulting overtopping discharge from wind-generated waves is very unevenly distributed in time and
space because the amount varies considerably from wave to wave. The major part of the overtopping
discharge during a storm is due to a small fraction of the waves. In fact the local overtopping discharge
from a single wave can be more than 100 times the average overtopping discharge during the storm peak.
Overtopping is calculated for the situation with and without crown wall. For these two situations,
different equations are used. With the calculation of overtopping discharges for both situations, Mean
Lower High Water level is used (CD +2.3 m). Additional to this level, a height of 0.50 m is used for
global sea level rise.
10/29/2007 A5 - 6
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
For ξ op > 2
q ⎛ R 1 ⎞
= 0.2 exp⎜⎜ − 2.6 c ⎟
⎟ [Annex 5.2.2]
q ⋅ Hs
3
⎝ H s γ r γ bγ hγ β ⎠
Where:
Rc = the height of the crest with respect to the water level.
For the situation with crown wall, the overtopping discharges are determined, using the equation by
Bradbury and Allsop (1988)
−b
q ⎡⎛ R ⎞
2
s om ⎤
= a ⎢⎜⎜ c ⎟⎟ ⎥ [Annex 5.2.3]
g ⋅ H s ⋅ Tom ⎢⎣⎝ H s ⎠ 2π ⎥
⎦
The coefficients a and b have been determined with physical model testing. For these coefficients, the
values determined by Aminti and Franco (1988) where used.
10/29/2007 A5 - 7
100 yr.
10 yr.
1 yr.
10/29/2007 A5 - 8
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
Where:
ξ m = sm−0.5 tan α [Annex 5.2.6]
ξ mc = (6.2 ⋅ P 0.31 (tan α ) 0.5 )1 /( P +0.5 ) [Annex 5.2.7]
Where:
P = Permeability coefficient
Van der Meer’s equation takes into account the permeability of the slope design calculations through a
notational permeability parameter. (P). This will be taken here as 0.4 for breakwater design and 0.3 for
revetment sections.
Van der Meer takes into account the duration of the sea state thru an n number of waves. This will is
taken here as 2000 waves.
Damage classification
For two-layer rock amour, the damage level S classified as follows (Van der Meer 1988):
10/29/2007 A5 - 9
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
Under similar wave conditions the round head of a rubble-mound structure normally sustains more
extensive and more frequent damage than the structure trunk. One reason is the very high cone-overflow
velocities, sometimes enhanced in certain areas by wave refraction. Another reason is the reduced
support from neighboring units in the direction of wave overflow in the lee side of the cone.
Carver and Heimbaugh (1989) investigated the head stability of rock. Model tests resulted in the
following stability equation:
H
= A ⋅ ξ 2 + B ⋅ ξ + Cc [Annex 5.2.9]
Δ ⋅ Dn 50
tan α
ξ= [Annex 5.2.10]
H /L
Where L = Local wave length at the structure toe. For the determination of the wave length, the peak
period is used.
10/29/2007 A5 - 10
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
A, B, Cc = Empirical coefficients dependant on the type of amour unit and the slope.
According to the Coastal Engineering Manual, the armouring of the head of the breakwater should be the
same on the lee side slope as on the seaside slope for a distance of about 15 to 45 m from the structure
end.
Van der Meer, ‘d Angremond and Gerding investigated the relation between the unit weight of toe
elements, toe level and damage (Nod). They derived the following relation.
Hs ⎛ h ⎞
= ⎜⎜ 0.24 ⋅ b + 1.6 ⎟⎟ N od0.15 [Annex 5.2.11]
Δ ⋅ Dn 50 ⎝ Dn 50 ⎠
N od = Character of damage
Nod = 0.5 : Start of damage
Nod = 1.0 : Acceptable damage
Nod = 4.0 : Severe damage (Failure)
The criteria for damage levels of the toe structure for storms with varying return periods are give in table
A 5.3
The filter criteria between the amour and the under layer (from CIRIA-CUR 1991):
W15 a
≤5 [Annex 5.2.12]
W85u
W50 a
10 ≤ < 15 [Annex 5.2.13]
W50 u
10/29/2007 A5 - 11
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
D15( l arg er )
≤5 [Annex 5.2.14]
D85( smaller )
D15( l arg er )
4≤ ≤ 25 [Annex 5.2.15]
D15( smaller )
D50 ( l arg er )
≤ 25 [Annex 5.2.16]
D50 ( smaller )
Where:
D is the nominal size of the units considering and the suffixes “15”, “50”and “85” refer to the
percentages of material not exceeding that size. For criteria between the under layer and the core (from
CIRIA-CUR, 1991). Migration between under layer and core:
D15u
≤5 [Annex 5.2.17]
D85c
D50u
5≤ ≤ 60 [Annex 5.2.18]
D50 c
With the suffixes “u” and “c” referring to under layer and core respectively.
The CEM advises that the first under layer should weigh about one tenth of the weight of the overlying
amour layer units if the first under layer and the cover layer are both quarry stones.
Layer thickness
The thickness r of a layer must be the greater of either 0.3 m, or one of the following, whichever of the
three is the greatest:
1/ 3
⎛W ⎞
r = 2.0 ⋅ ⎜⎜ 50 ⎟⎟ [Annex 5.2.19]
⎝ wa ⎠
Where W50 is the weight of the 50-percent size in the gradation, or:
1/ 3
⎛W ⎞
r = 1.25 ⋅ ⎜⎜ max ⎟⎟ [Annex 5.2.20]
⎝ wa ⎠
Where Wmax is the heaviest stone in the gradation.
Fujairah is one of the most important sources of rock and aggregates in the region. This is due to the high
quality of the rocky material (high density and strength) and the wide availability. Although the main
products of quarries in Fujairah are aggregates, there is a lot of experience with the production and
transportation of large blocks for breakwaters and revetments.
Quarries can produce and transport every desired gradation up to approx. 10 tons. However blocks up to
10 ton can be produced, handling of these blocks is difficult and time consuming. Experience learns that
stones with a weight up to 7 tons can be handled relatively easy. The produced material has a high
10/29/2007 A5 - 12
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
density, which varies between 2800, and 3000 kg/m3. For the stability calculations, a material density of
2800 kg/m3 is applied.
A 5.2.12 Equipment
For the design of the breakwaters and revetments, the use of rolling equipment is taken into account.
Floating equipment requires unnecessary load and unload activity that will increase the construction cost
of the project. It is assumed that the material of the core will therefore simply be brought in by dump
trucks that also pick up the material at the quarry. The major advantages of this construction method are
the potential use of cheap local equipment and the independence of working conditions at sea (fog,
waves, swell and currents).
Since rolling equipment can be used, the dam is built out with a work front in several phases, for core,
under layer, toe. The crest of the core is used as main supply road. Therefore this crest must be high
enough above high water level to guarantee the safety of equipment and personnel.
In general the problem of breakwater construction is to build out the core and cover layers consecutively
in such a manner that the parts that are not yet stabilized by its cover is not damaged by the
environmental conditions during construction. All damage which occurs during construction has to be
repaired according to the prescribed layer profile, as the functioning of the breakwater depends on the
filter design rules. Therefore it is necessary to consider tolerances and to maintain a very strict position
control during construction.
Since the wave climate in Fujairah is mild however, damage to the unprotected core is not expected to be
excessive. Other projects in the area of Fujairah have been constructed in the same way and have not
experienced high erosion of the unprotected slope.
10/29/2007 A5 - 13
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
A 5.4.1 Introduction
In this chapter a design proposal is given for four main parts of the coastal protection works. These parts
are:
1. Revetment section in the exposed areas
2. Breakwater part. (water on both sides)
3. A breakwater round head and convex bends in the revetment sections.
4. Revetment section in the sheltered areas
For both sections the stability of several slopes and stone weights are tested for wave loads with different
return periods are tested. For the revetment section the both a design with and without crown wall is
proposed.
Amour layer
The selected gradation for the amour layer of the revetment is 4 to 7 tons. This gradation has a median
stone weight of 5.5 tons. For quarries in Fujairah, this is a convenient stone size to produce and transport.
For the stability calculations, wave heights according to table A1.15 in Annex 1 and the relation between
wave height and period where used. Further the following parameter where applied.
For three slopes, respectively 1:1.5, 1:2 and 1:2.5 the damage levels under varying wave attack are
calculated. With equations [Annex 5.2.6] and [Annex 5.2.7] the values for ξm1 and ξmc1 are calculated to
determine if waves are plunging or surging for each of these slopes.
10/29/2007 A5 - 14
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
From table A 5.5 it can be seen that waves are plunging. This means that for all stability calculations
equation [Annex 5.2.4] will applied using waves conditions with varying return periods of 1 to 200 years
according to table A1.15.
The resulting damage levels of these calculations are shown in graph A 5.1. It can be seen that for return
periods up to 200 year and slope angles less steep than 1:2, the damage level S does not exceed 3.0,
which means that damage would remain in the range, classified as intermediate damage.
7.00
6.00
5.00
cot a=1.5
4.00
cot a=2
S (damage level)
2.00
1.00
0.00
1 10 100 1000
Return period [Yr]
graph A 5.1 Damage level of the selected gradation for wave load with different return periods according to stability
equation of Van der Meer (1988) with a slope of 1:1.5, 1:2 and 1:2.5 for breakwater sections (P=0.4)
It can be seen that a slope angle of 1:5 immediately results in larger values for the damage level. The
difference between a slope of 1:2 and 1:2.5 is less. For this reason a slope of 1:2 is chosen. With this
median stone weight, the thickness of the amour layer is 2.5 m, which is two times the nominal diameter
of the rock in this layer.
10/29/2007 A5 - 15
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
8.00
7.00
6.00
cot a=2.5
3.00
2.00
1.00
0.00
1 10 100 1000
Return period [Yr]
graph A 5.2 Damage level of the selected gradation for wave load with different return periods according to stability
equation of Van der Meer (1988) with a slope of 1:1.5, 1:2 and 1:2.5 for revetment sections (P = 0.3)
From graph A 5.2 it can be seen that for the reduced permeability higher damage levels are expected. For
the 100 year return period wave characteristics, the expected damage level is 2.77 which still is
acceptable.
Under layer
For the under layer a gradation of 300 – 1000 kg is chosen. The rock material for this layer has a median
weight of 650 kg. With this median weight, the thickness of the under layer is 1.23 m, which is two times
the nominal diameter of this layer.
Toe
For the toe, the material of the under layer with a gradation of 300 – 1000 kg is extended over the berm
of the breakwater. The damage levels for the toe material for wave loads with return periods between 1
and 200 years and water depths of 4, 6 and 8 m are determined using the equation of Van der Meer,
d’Angremond and Gerding for toe stability [Annex 5.2.11]. This water depth is the depth from mean
lower low water to the top of the toe. The same parameters as in table A 5.4 where used for these
calculations.
The results of the calculations are plotted in graph A 5.3. For a return period of 200 year and water
depths of 6 and 8 m, it can be seen that the damage level (Nod) does not exceed 1, which represents
“acceptable damage”. For a water depth of 4 m, this damage level exceeds 3 for the wave load with a
return period of 200 years.
10/29/2007 A5 - 16
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
3.50
3.00
2.50
Nod (damage level
hb=4
2.00 hb=6
1.50 hb=8
1.00
0.50
0.00
1 10 100 1000
Return period [Yr]
graph A 5.3 Damage level of the toe of the revetment for wave load with return periods varying between 1 and 200 years and
for different depths.
The top of the toe will be constructed at a water depth of 6 m since damage stays within the acceptable
range for this depth and waves with a return period of 200 years.
Core
The core is build up from quarry run. A quarry run gradation from 0 – 1000 kg is proposed. The sea side
of the under water slope of the breakwater will not be armed with a selected heavy stone gradation but
will be extended over 4 meters. During a heavy storm, the lighter material will be washed away so that
the heavier material remains on the slope. The stability of this material, having a median stone weight of
500 kg is calculated using the toe stability equation of Van der Meer [Annex 5.2.11].
The wave parameters according to Annex 1 table A1.15 and the relation [Annex1, 1.5.1] where used to
determine the damage levels for the different water depths.
0.80
0.70
0.60
Nod (damage level
0.50 W50=100
W50=250
0.40
W50=500
0.30
0.20
0.10
0.00
1 10 100 1000
Return period [Yr]
graph A 5.4 Damage level of material of material on the front side of the toe
10/29/2007 A5 - 17
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
Crest height
The crest height of the revetment depends on the maximum allowable average overtopping discharge.
Limits for return periods of 1, 10 and 100 years are given in figure 5.1.
Overtopping of the revetment is analyzed for the situation with and without crown wall and for crest
heights varying between 7.5 m and 10.5 m relative to chart datum. For these calculations the equation of
Van der Meer and Janssen [Annex 5.2.1]and the equation of Bradbury and Allsop [Annex 5.2.3] have
been used.
For the stability calculations, wave heights according to Annex 1 table A1.15 an relation [Annex1, 1.5.1]
where used. Further the following parameter where applied.
For the calculation of the average overtopping discharges for the revetment type without crown wall, the
permeability of the armour layer is taken into account. This layer consists of large blocks thru which still
large discharges are possible. To calculate the discharge using the top of this layer would be optimistic
and not right. For this reason, a crest height reduction is applied with the thickness of the armour layer.
The results of the calculations have been plotted out in graph A 5.5. It can be seen that the overtopping of
the revetment for a design without crown wall is very high. In fact, only with a crest height of 10.5
meters, the overtopping stays within acceptable limits. The overtopping of the revetment with crown wall
is already within acceptable limits for a height of 8.5 m. Since both solutions are possible, construction
cost will determine which option is preferred.
10/29/2007 A5 - 18
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
11.00
10.00
9.00
8.00 h = 7.5
h = 8.5
7.00 h = 9.5
6.00 h = 10.5
Overtopping [l/s/m]
h = 7. 5, with crownwall
5.00 h = 8.5, with crown wall
4.00 h = 9.5, with crown wall
h = 10.5, with crown wall
3.00 allowable overtopping discharge
2.00
1.00
0.00
1 10 100 1000
Return period [Yr]
graph A 5.5 Average overtopping discharges of the revetment with different heights, with and without crown wall.
Geotextile
To prevent loss of stability of the inner slope of the revetment by migration of dredged material thru the
armour layers, a geotextile is to be applied between the quarry run core and the dredged material and
between the quarry run core and the under layer on the top of the revetment. This geotextile does not
need to be extended over the full cross section but from a depth of 2 m below top level of hydraulic fill to
the seaward end of the crest of the quarry run core.
Summary
The design of the revetment can be summarized as follows and is shown in figure 5.2:
Slope: 1:2
Crest height: CD + 8.5 m (with crown wall)
CD +10.5 m (without crown wall)
Material quantity
The amount of material in the cross section is given in table A 5.9
10/29/2007 A5 - 19
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
10/29/2007 A5 - 20
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title 5.2
Cross section revetment design phase 1 (straight part) without crown wall
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title 5.3
Cross section revetment design phase 1 (straight part) with crown wall.
M.U.C. Engineering
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
Amour layer
The armour layer as present in the cross section of the proposed design for the revetment will be
continued on the breakwater. The stability criteria and the load on the breakwater armour layer are
similar to that of the revetment.
Crest height
The breakwater has no overtopping criteria. Its height is determined by the height of the core. As
mentioned this will be built out from the shore. For this reason the height of the crest of the breakwater
head is set at CD + 7.75, which is the top core plus the layer thickness of the amour layer.
Summary
The design of the breakwater section can be summarized as follows and is shown in figure
Slope: 1:2
Crest height: CD +7.75 m
Material quantity
The amount of material in the cross section is given in table A 5.10
10/29/2007 A5 - 23
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title 5.4
Cross section breakwater sections
M.U.C. Engineering
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
Amour layer
For this breakwater head, slopes of 1:2, 1:2.5 and 1:3 have been evaluated using equation [Annex 5.2.9].
The required median stone weights for these slopes according to the equation of Carver and Heimbough
(1989) are given in graph A 5.6.
A 0.272
B -1.749
Cc 4.179
table A 5.11 Empirical coefficients of Carver and Heimbough
14000
Required weight armour layer [kg
12000
10000
cot a =2
8000
cot a =2.5
6000 cot a =3
4000
2000
0
1 10 100 1000
Return period [Yr]
The selected gradation for the amour layer of the breakwater round head is 4 to 7 tons. This gradation has
a median weight of 5.5 tons. For the design of the head section, the wave with a return period of 10 years
is used. From graph A 5.6 it can be seen that for the wave load with a return period of 100 years and a
slope of 1:3, the required median stone weight is 4.90. This means that the amour layer from the
revetment section with a median stone weight of 5.50 ton can safely be continued over the temporary
head section.
The fact that the radius of this breakwater head is relatively large (50 to 75 m) is positive for the stability
of the material in the armour layer.
Crest height
The breakwater head has no overtopping criteria. Its height is only determined by its earth retaining
function. For this reason the height of the crest of the breakwater head is set at CD + 7.25, which is the
top of the landfill plus the layer thickness of the amour layer. Since overtopping can be significant with
10/29/2007 A5 - 25
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
this height, special attention should be paid on the protection of the inner slope. The under layer is
therefore extended over the entire area of the head section.
Summary
The design of the temporary breakwater round head is equal to the breakwater cross section and is shown
in figure 5.5:
Material quantity
The amount of material in the cross section is given in table A 5.10
10/29/2007 A5 - 26
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title 5.5
Cross section permanent round head design
M.U.C. Engineering
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 5 Principle design Coastal Protection works
The revetment on the northern part of the new port (in layout 1 and layout 2) is sheltered from the
dominant wave direction by the container terminal. It is assumed that the wave height reduces by 80% on
these revetment sections.
3.00
2.50
2.00
cot a=1.5
cot a=2
1.50
S (damage level)
cot a=2.5
1.00
0.50
0.00
1 10 100 1000
Return period [Yr]
Material quantity
The amount of material in the cross section is given in table A 5.13
10/29/2007 A5 - 28
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title 5.4
Cross section breakwater sections
M.U.C. Engineering
A6 Annex 6 Dredging quantities
10/29/2007 A6 - 1
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 6 Dredging quantities
Contents
A6 Annex 6 Dredging quantities......................................................................................................... 1
List of tables .......................................................................................................................................... 2
List of Figures ....................................................................................................................................... 2
A 6.1 General................................................................................................................................... 3
A 6.1.1 Introduction ................................................................................................................. 3
A 6.1.2 Dredgability ................................................................................................................. 3
A 6.1.3 Phasing......................................................................................................................... 3
A 6.2 Quantities ............................................................................................................................... 3
A 6.2.1 Introduction ................................................................................................................. 3
A 6.2.2 Layout A1 .................................................................................................................... 4
A 6.2.3 Layout A2-B2 .............................................................................................................. 6
A 6.2.4 Layout A3 .................................................................................................................... 9
A 6.2.5 Layout A4 .................................................................................................................. 11
A 6.2.6 Layout A5 .................................................................................................................. 13
A 6.3 Cost estimation......................................................................Error! Bookmark not defined.
List of tables
table A 6.1 Dredging and reclamation quantities layout A1, phase 1 ...................................................... 4
table A 6.2 Dredging and reclamation quantities layout A1, phase 2 ...................................................... 4
table A 6.3 Dredging and reclamation quantities layout A1, phase 3 ...................................................... 4
table A 6.4 Dredging and reclamation quantities Layout A2 – B2, phase 1 ............................................ 6
table A 6.5 Dredging and reclamation quantities Layout A2-B2, phase 2 ............................................... 6
table A 6.6 Dredging and reclamation quantities Layout A2-B1, phase 1 ............................................... 7
table A 6.7 Dredging and reclamation quantities Layout A2-B1, phase 2 ............................................... 7
table A 6.8 Dredging and reclamation quantities Layout A3, phase 1 ..................................................... 9
table A 6.9 Dredging and reclamation quantities Layout A4, phase 1 ................................................... 11
table A 6.10 Dredging and reclamation quantities Layout A4, phase 2 ................................................... 11
table A 6.11 Dredging and reclamation quantities Layout A4, phase 1 ................................................... 13
table A 6.12 Dredging and reclamation quantities Layout A4, phase 2 ................................................... 13
List of Figures
10/29/2007 A6 - 2
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 6 Dredging quantities
A 6.1 General
A 6.1.1 Introduction
This annex describes the dredging and reclamation works for the Port of Fujairah expansion project. It
focuses on the proposed alternative harbour basin layouts 1 – 5. Attention is paid to the Fujairah Land
Reclamation project which is planned to be realized north of the Port. Goal of this part if the masterplan
study is to estimate the dredging and reclamation cost of the different layouts.
The following assumptions where made:
- The dredged material can be used for hydraulic fill of the land behind the new quays.
- The surplus of material can be used for the Fujairah land reclamation project. Costs saved for this
project are reduced from the dredging cost of the Port Expansion Project.
- If not enough material is available for filling of land behind quay walls, quarry run produced in
Fujairah is used.
A 6.1.2 Dredgability
The material in the designated dredge area is believed to be suitable for the land reclamation works.
Details of the soil composition are given in annex 2 of the masterplan report.
A 6.1.3 Phasing
For each layout a project phasing is proposed. The quantities given in this annex are given per phase.
A 6.2 Quantities
A 6.2.1 Introduction
The layouts that where used for calculation of the dredging and land fill quantities, are shown in figures
attached to this annex. The bulking factor is assumed to be 10%. The bulking factor comprises the
material volume increase after dredging and includes compaction after hydraulic fill. In fact it represents
the relation between fixed volume in situ before excavation and fixed volume in site after hydraulic fill.
The estimated amount of material that comes free by dredging the entire harbour basin and entrance
channel of the proposed layout is given in the following paragraphs:
10/29/2007 A6 - 3
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 6 Dredging quantities
A 6.2.2 Layout A1
Phase 1
Layout 1 4.75 4.75 -19 -16 Land fill dredging
d1 d2 avg area [m2] area [m2] area [m2] area [m2] vol [m3] vol [m2]
1 -3 -1 395,037 0 0 0 2,271,463 0
-3 -5 -4 165,788 0 0 0 1,450,645 0
-5 -7 -6 183,288 0 0 0 1,970,346 0
-7 -9 -8 190,102 0 0 0 2,423,801 0
-9 -11 -10 25,269 0 110,476 0 372,718 -994,284
-11 -13 -12 37,444 0 177,651 0 627,187 -1,243,557
-13 -15 -14 97,211 0 250,326 0 1,822,706 -1,251,630
-15 -17 -16 112,932 0 368,512 0 2,343,339 -1,105,536
-17 -19 -18 0 0 327,725 0 0 -327,725
-19 -21 -20 0 0 213,974 0 0 213,974
13,282,204 -4,922,732
table A 6.1 Dredging and reclamation quantities layout A1, phase 1
Phase 2
Layout 1 4.75 4.75 -19 -16 Land fill dredging
d1 d2 avg area [m2] area [m2] area [m2] area [m2] vol [m3] vol [m2]
1 -3 -1 0 0 0 0 0 0
-3 -5 -4 0 0 0 0 0 0
-5 -7 -6 0 0 0 0 0 0
-7 -9 -8 0 0 0 0 0 0
-9 -11 -10 0 86,838 0 0 1,280,861 0
-11 -13 -12 0 98,683 0 0 1,652,940 0
-13 -15 -14 0 137,601 0 0 2,580,019 0
-15 -17 -16 0 173,123 0 0 3,592,302 0
-17 -19 -18 0 153,847 0 0 3,500,019 0
-19 -21 -20 0 0 0 0 0 0
12,606,141 0
table A 6.2 Dredging and reclamation quantities layout A1, phase 2
Phase 3
Layout 1 4.75 4.75 -19 -16 Land fill dredging
d1 d2 avg area [m2] area [m2] area [m2] area [m2] vol [m3] vol [m2]
1 -3 -1 0 0 0 0 0 0
-3 -5 -4 0 0 0 0 0 0
-5 -7 -6 0 0 0 0 0 0
-7 -9 -8 0 0 0 0 0 0
-9 -11 -10 0 0 0 0 0 0
-11 -13 -12 0 0 0 0 0 0
-13 -15 -14 0 0 0 0 0 0
-15 -17 -16 0 0 0 0 0 0
-17 -19 -18 76,084 0 0 0 1,730,911 0
-19 -21 -20 60,435 0 0 0 1,495,766 0
1,730,911 0
table A 6.3 Dredging and reclamation quantities layout A1, phase 3
10/29/2007 A6 - 4
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 6.1
Dredging and reclamation areas layout A1
M.U.C. Engineering
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 6 Dredging quantities
Phase 2
Layout 2 4.75 4.75 -19 -16 Land fill dredging
d1 d2 avg area [m2] area [m2] area [m2] area [m2] vol [m3] vol [m2]
1 -1 0 0 0 0 0 0 0
-1 -3 -2 0 0 0 0 0 0
-3 -5 -4 0 72,422 0 0 633,693 0
-5 -7 -6 0 58,426 0 0 628,080 0
-7 -9 -8 0 62,379 0 0 795,332 0
-9 -11 -10 0 79,729 0 0 1,176,003 0
-11 -13 -12 0 81,028 0 0 1,357,219 0
-13 -15 -14 0 113,552 0 0 2,129,100 0
-15 -17 -16 0 0 0 0 0 0
-17 -19 -18 0 0 0 0 0 0
-19 -21 -20 0 0 0 0 0
6,719,426 0
Phase 3
No dredging is required in phase 3 for layout 2A-B2
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 6 Dredging quantities
Layout A2-B1
Phase 1
Layout 2 4.75 4.75 -19 -16 Land fill dredging
d1 d2 avg area [m2] area [m2] area [m2] area [m2] vol [m3] vol [m2]
1 -1 0 219,565 0 0 0 1,042,934 0
-1 -3 -2 137,135 0 38,112 0 925,661 -647,904
-3 -5 -4 17,803 0 81,795 0 155,776 -1,226,925
-5 -7 -6 20,576 0 94,302 0 221,192 -1,225,926
-7 -9 -8 22,829 0 109,864 0 291,070 -1,208,504
-9 -11 -10 25,269 0 116,415 0 372,718 -1,047,735
-11 -13 -12 37,444 0 194,534 0 627,187 -1,361,738
-13 -15 -14 58,838 0 318,621 0 1,103,213 -1,593,105
-15 -17 -16 0 0 242,845 0 0 -728,535
-17 -19 -18 0 0 200,511 0 0 -200,511
-19 -21 -20 0 0 250,396 0 250,396
4,739,750 -8,990,487
table A 6.6 Dredging and reclamation quantities Layout A2-B1, phase 1
Phase 2
Layout 2 4.75 4.75 -19 -16 Land fill dredging
d1 d2 avg area [m2] area [m2] area [m2] area [m2] vol [m3] vol [m2]
1 -1 0 0 0 0 0 0 0
-1 -3 -2 0 0 0 0 0 0
-3 -5 -4 0 72,422 0 0 633,693 0
-5 -7 -6 0 58,426 0 0 628,080 0
-7 -9 -8 0 62,379 0 0 795,332 0
-9 -11 -10 0 0 0 0 0 0
-11 -13 -12 0 0 0 0 0 0
-13 -15 -14 0 0 0 0 0 0
-15 -17 -16 0 0 0 0 0 0
-17 -19 -18 0 0 0 0 0 0
2,057,104 0
table A 6.7 Dredging and reclamation quantities Layout A2-B1, phase 2
Phase 3
Layout 2 4.75 4.75 -19 -16 Land fill dredging
d1 d2 avg area [m2] area [m2] area [m2] area [m2] vol [m3] vol [m2]
1 -1 0 0 0 0 0 0 0
-1 -3 -2 0 0 0 0 0 0
-3 -5 -4 0 0 0 0 0 0
-5 -7 -6 0 0 0 0 0 0
-7 -9 -8 0 0 0 0 0 0
-9 -11 -10 0 79,729 0 0 1,176,003 0
-11 -13 -12 0 81,028 0 0 1,357,219 0
-13 -15 -14 0 113,552 0 0 2,129,100 0
-15 -17 -16 0 0 0 0 0 0
-17 -19 -18 0 0 0 0 0 0
-19 -21 -20 0 0 0 0 0
4,662,322 0
Dredging and reclamation quantities Layout A2-B1, phase 3
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 6.2
Dredging and reclamation areas layout A2
M.U.C. Engineering
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 6 Dredging quantities
A 6.2.4 Layout A3
Phase 1
Layout 3 4.75 4.75 -19 -16 Land fill dredging
d1 d2 avg area [m2] area [m2] area [m2] area [m2] vol [m3] vol [m2]
1 -1 0 117,967 123,218 0 0 1,145,629 0
-1 -3 -2 98,380 205,619 0 0 2,051,993 0
-3 -5 -4 26,096 280,127 112,441 0 2,679,451 -1,686,615
-5 -7 -6 20,675 0 117,100 215202 222,256 -3,674,320
-7 -9 -8 22,829 0 133,617 235628 291,070 -3,354,811
-9 -11 -10 25,269 0 131,837 337458 372,718 -3,211,281
-11 -13 -12 37,444 0 234,700 732685 627,187 -4,573,640
-13 -15 -14 58,838 0 380,063 0 1,103,213 -1,900,315
-15 -17 -16 0 0 297,319 0 0 -891,957
-17 -19 -18 0 0 200,511 0 0 -200,511
-19 -21 -20 0 0 250,396 0 0 250,396
8,493,517 -19,243,054
table A 6.8 Dredging and reclamation quantities Layout A3, phase 1
Phase 2
No dredging and reclamation works in phase 2 of layout A3.
Phase 3
No dredging and reclamation works in phase 3 of layout A3.
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 6.3
Dredging and reclamation areas layout A3
M.U.C. Engineering
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 6 Dredging quantities
A 6.2.5 Layout A4
Phase 1
Layout 4 4.75 4.75 -19 -16 Land fill dredging
d1 d2 avg area [m2] area [m2] area [m2] area [m2] vol [m3] vol [m2]
1 -1 0 309,661 123,218 0 0 2,056,175 0
-1 -3 -2 73,152 205,619 134,935 0 1,881,704 -2,293,895
-3 -5 -4 84,607 280,127 82,078 0 3,191,423 -1,231,170
-5 -7 -6 38,072 0 124,390 215202 409,274 -3,769,090
-7 -9 -8 44,068 0 143,092 235628 561,867 -3,459,036
-9 -11 -10 51,809 0 143,948 337458 764,183 -3,320,280
-11 -13 -12 37,444 0 238,639 732685 627,187 -4,601,213
-13 -15 -14 58,838 0 385,416 0 1,103,213 -1,927,080
-15 -17 -16 0 289,717 0 0 -869,151
-17 -19 -18 0 183,449 0 0 -183,449
-19 -21 -20 0 250,396 0 0 250,396
10,595,025 -21,403,968
table A 6.9 Dredging and reclamation quantities Layout A4, phase 1
Phase 2
Layout 4 4.75 4.75 -19 -16 Land fill dredging
d1 d2 avg area [m2] area [m2] area [m2] area [m2] vol [m3] vol [m2]
1 -1 0 0 0 0 0 0 0
-1 -3 -2 0 0 0 0 0 0
-3 -5 -4 0 0 0 0 0 0
-5 -7 -6 0 0 0 0 0 0
-7 -9 -8 0 0 0 0 0 0
-9 -11 -10 0 0 0 0 0 0
-11 -13 -12 37,531 0 0 0 628,644 0
-13 -15 -14 58,363 0 0 0 1,094,306 0
-15 -17 -16 0 0 0 0 0 0
-17 -19 -18 29,506 0 0 0 671,262 0
-19 -21 -20 0 0 0 0 0 0
2,394,212 0
table A 6.10 Dredging and reclamation quantities Layout A4, phase 2
Phase 3
No dredging and reclamation works in phase 3 of layout A4.
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 6.4
Dredging and reclamation areas layout A4
M.U.C. Engineering
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 6 Dredging quantities
A 6.2.6 Layout A5
Phase 1
Layout 4 4.75 4.75 -19 -16 Land fill dredging
d1 d2 avg area [m2] area [m2] area [m2] area [m2] vol [m3] vol [m2]
1 -1 0 53,686 123,218 0 0 840,294 0
-1 -3 -2 205,619 134,935 0 1,387,928 -2,293,895
-3 -5 -4 17,347 280,127 82,078 0 2,602,898 -1,231,170
-5 -7 -6 20,576 0 124,390 215202 221,192 -3,769,090
-7 -9 -8 22,829 0 143,092 235628 291,070 -3,459,036
-9 -11 -10 25,269 0 143,948 337458 372,718 -3,320,280
-11 -13 -12 37,444 0 238,639 732685 627,187 -4,601,213
-13 -15 -14 58,838 0 385,416 0 1,103,213 -1,927,080
-15 -17 -16 0 289,717 0 0 -869,151
-17 -19 -18 0 183,449 0 0 -183,449
-19 -21 -20 0 250,396 0 0 250,396
7,446,499 -21,403,968
table A 6.11 Dredging and reclamation quantities Layout A4, phase 1
Phase 2
Layout 4 4.75 4.75 -19 -16 Land fill dredging
d1 d2 avg area [m2] area [m2] area [m2] area [m2] vol [m3] vol [m2]
1 -1 0 0 0 0 0 0 0
-1 -3 -2 0 0 0 0 0 0
-3 -5 -4 0 0 0 0 0 0
-5 -7 -6 0 0 0 0 0 0
-7 -9 -8 0 0 0 0 0 0
-9 -11 -10 0 0 0 0 0 0
-11 -13 -12 0 0 0 0 0 0
-13 -15 -14 0 0 0 0 0 0
-15 -17 -16 0 0 0 0 0 0
-17 -19 -18 29,506 0 0 0 671,262 0
-19 -21 -20 0 0 0 0 0 0
671,262 0
table A 6.12 Dredging and reclamation quantities Layout A4, phase 2
Phase 3
No dredging and reclamation works in phase 3 of layout A4.
The amount of soil required in situ for the Fujairah Land Reclamation Project is 28.7 M m3. This means
that all material that comes free from the Port Expansion Project can be used for the reclamation project
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A 6.5
Dredging and reclamation areas layout A5
M.U.C. Engineering
A7 Annex 7 Principle Tanker Terminal design
10/29/2007
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 7 Principle Tanker Terminal design
Contents
List of Figures
A 7.1 Introduction
This annex describes the principle design of the Open Sea Tanker Terminal in the Port of Fujairah
Expansion Project. The designs for this part of the project where not carried out as a part of this study but
where carried out by B.V. Ingenieursbureau M.U.C.
The Open Sea Tanker terminal is built up from the following elements:
- Concrete product platforms on steel piles on which the loading arms are installed.
- Concrete breasting platforms
- Concrete mooring platforms
- Steel catwalks between breasting, mooring and product platforms
- Steel access bridges from the shore to the product platforms. These access bridges are founded
on concrete platforms and steel piles. The length of the bridges is 37.5 m each.
Cross section and side view of the access bridge is shown in figures 7.2 and 7.3.
10/29/2007
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A
Overview finger pier
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A
Cross section standard trestle bridge
M.U.C. Engineering
Project Title: Figure no:
Masterplan for the port of Fujairah Expansion Project
Figure Title A
Side view standard trestle bridge.
M.U.C. Engineering
A8 Annex 8 Layout evaluation
10/29/2007 A8 - 1
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
Contents
List of tables
10/29/2007 A8 - 2
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
10/29/2007 A8 - 3
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
A 8.1 Introduction
In this annex to the report Masterplan for the Port of Fujairah, several layout alternatives for the
expansion of this port will be analyzed. These layouts, including intermediate phasing and are shown in
Annex 2 to the masterplan report.
The objective of this evaluation is to asses the feasibility of several proposed layout alternatives based on
monetary and other criteria.
In the masterplan report, several scenarios are composed for the demand in throughput capacity for
different commodities. Not all layouts are capable of supplying for the required capacity for the highest
growth scenario. This obstructs a straightforward monetary evaluation or multi criteria analysis. The
capability of realizing the required throughput capacity is assumed to be so important, that a separate
evaluation is carried out for the different scenarios. This means that first the layouts are separately
evaluated that are capable of supplying for the highest growth scenario. Subsequently the layouts are
tested that can supply for the demand according to scenario 2 and for scenario 3.
A 8.2.1 Introduction
In this paragraph the construction cost of the layouts are estimated. These construction cost are estimated,
based on project cost of other comparable projects in the Fujairah region. The cost estimations are rough
and not suitable for tendering phase.
The costs of four main parts of the port expansion construction works are taken into account. These are:
- Dredging and reclamation
- Construction of quay walls
- Coastal protection
- Construction of the Open Sea Tanker Terminal
For the proposed layouts, dredging and land fill volumes have been determined. Detailed results of this
study are shown in Annex 6 “Dredging quantities”. For several layout alternatives there is a dredging
surplus. Although a dredging surplus would increase the total project cost of the Port Expansion Project,
it would be favorable to reduce the project cost of the reclamation project, north of the Port expansion.
This project is not owned by the Port of Fujairah Authorities but by the Fujairah Municipality. Both
projects however are on behalf of His Highness Sheikh Saleh bin Mohammad Al Sharqi and the
Government of Fujairah. For further cost estimations it is assumed that a possible dredging surplus, soil
material can be sold to the Municipality of Fujairah for reclamation purposes.
Dredging costs are estimated by using a fixed price per m3 in situ to be dredged, based on other
comparable dredging projects in the region. The price of quarry run is based on several comparable
reclamation projects in the region.
10/29/2007 A8 - 4
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
The depth of the new harbour basin does not make it necessary to use very large dredging equipment. In
fact the equipment that it is necessary for dredging the harbour basin to the desired depth is currently
presently in the region. In the pricing assumptions it is not taken into account that the dredging can be
executed in combination with the gaining of the material for the Fujairah Land Reclamation Project.
Combining these projects would further decrease the dredging price since mobilization and
demobilization costs are less. It is however unsure if both projects can be executed simultaneous.
Further a net bulking factor of 10% is assumed. This factor represents the volume gain of soil, subtracted
from the sea bottom compacted used for landfill.
The design of the quay wall is described in Annex 4 “Design of quay wall” to this report. In this annex,
the conclusions was drawn that the most favorable type of quay wall cost as well as construction time
wise is a combi sheet pile wall. In this paragraph several pricing assumptions will be made. These
assumptions are given in table A 8.2.
These assumptions where used to estimate the cost of a 1,000 m quay wall. This resulted in a price per m
which is used for estimation of construction cost for quay walls per m.
price per
Piles quantity unit unit cost
Purchase of material
Purchase of tubes 375 pc $ 18,200 $ 6,824,989
Purchase of sheet piles (infill) 374 pc $ 5,984 $ 2,238,141
Cathodic protection (purchase and installation) 375 pc $ 250 $ 93,750
Transport
Transport of tubes 375 pc $ 6,256 $ 2,345,881
Transport of infill elements 374 pc $ 610 $ 228,030
Local transports 749 pc $ 176,000
Installation
Installation of tubes 375 pc $ 3,395 $ 1,273,002
Installation of infill 374 pc $ 905 $ 338,562
Additional time, startup, unworkable weather,
cool down 5 wks $ 81,472 $ 407,361
Mobilization and demobilization $ 147,800
Lump sum items pile installation $ 75,000
Total $ 14,148,515
Anchoring
Purchase of anchor material 750 pc $ 5,513 $ 4,134,375
Transport of anchor material 750 pc $ 135 $ 101,501
10/29/2007 A8 - 5
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
Additionals
Filling of piles with sand 4157 m3 $ 10 $ 41,572
Concrete plugs 1366 m3 $ 350 $ 478,072
Concrete copping beam 13400 m3 $ 235 $ 3,149,000
Fenders (purchase and installation) 42 pc $ 10,127 $ 425,351
Bollards (purchase and installation) 42 pc $ 5,051 $ 212,140
Stairs (steel purchase) 6.3 ton $ 2,451 $ 15,439
Stairs installation 21 pc $ 154 $ 3,226
Front rail purchase 1000 m $ 512 $ 511,875
Front rail installation 1000 m $ 18 $ 17,739
Total $ 4,854,414
10/29/2007 A8 - 6
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
The price assumptions from table A 8.2 lead to a quay wall price per 1,000 m of $ 35,280,494 and a price
per m quay wall of $ 35,280
The technical design of coastal protection is discussed in Annex 5 “principle design coastal protection
works”. This annex gives a principle design for five main parts of the coastal protection of the port
project. These parts are:
- Revetment section exposed
- Revetment section sheltered
- Breakwater section
- Breakwater round head.
- Coastal protection inside the harbour basin
The proposed coastal protection is carried out as rubble mound with large rock armour layer on a slope of
1:2. Since Fujairah is an important producer of rock in the region, it seems obvious that rock is used as
armour on the coastal protection. The proposed revetments have a concrete crown wall to reduce
overtopping discharges.
In 0 unit price assumptions are used to estimate costs per m coastal protection works for the different
parts. Additional to these costs are general overhead and preliminaries and cost for survey and inspection
works.
A constant water depth representative for the specific part of the coastal protection is assumed.
Revetment sheltered
Armour rock $34 69 $2,346 $3,085
Under layer $19 58 $1,102 $1,449
Core Material $16 688 $11,008 $14,476
Crown wall $850 7 $5,950 $7,824
Total $26,834
Breakwater
Armour rock $34 122 $4,148 $5,455
Under layer $19 114 $2,166 $2,848
Core Material $16 1391 $22,256 $29,267
Total $37,570
Breakwater roundhead
10/29/2007 A8 - 7
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
The technical design of the open sea tanker terminal is discussed in Annex 7 “design liquid bulk
terminal” to this report. The onshore part of the OSTT consists of a manifold and a pipe rack between the
manifold and the jetty. The jetty is build op from steel trestle bridges founded on concrete footings on
steel piles. Standard trestle bridges are used for all offshore parts of the OSTT.
In table A 8.4 pricing assumptions are given that are used for cost estimation of the various layouts of the
liquid bulk terminal.
price per
Piles per 100 quantity unit unit cost
Purchase of tubes 100 pc $24,563 $2,456,286
Cathodic protection (purchase and installation) 200 pc $250 $50,000
Transport of tubes 100 pc $6,256 $625,568
Local transports $300,000
Installation of tubes 100 pc $11,991 $1,199,143
Additional time, startup, unworkable weather,
cool down. 6 wks $162,550 $975,303
Mobilisation and demobilsation $292,800
Lump sum items pile installation $400,000
Total $18,147,011
Price per pile $181,470
10/29/2007 A8 - 8
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
Piperack per m
Steelworks for onshore piperack 0.5 ton $2,451 $1,225
Concrete sleepers for onshore piperack 0.7 m3 $500 $350
Total $1,575
Piping
Purchase and installation 16" piping per m $175
Trestle abutment
Trestle abutment $150,000
10/29/2007 A8 - 9
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
The design of the chemical berths is not discussed in detail in this document. The berths consist of a
concrete platform connected to the shore by a concrete bridge. An overall impression is given in Annex 7
to this report. The berths will be equipped with four 10” loading arms.
A price of $ 16 M is assumed for these berths. Including overhead this is $ 18.3 M. Since all layouts have
two chemical berths, operating under comparable conditions, these costs are of minor importance.
Costs are given in American Dollars. Since November 1997, the dirham has been pegged to the U.S.
dollar (1 US dollar is 3.6725 dirhams, which translates to approximately 1 dirham = 0.272294 dollar).
Cost estimations of the proposed layouts combinations are based on pricing assumptions described in the
previous paragraph and quantity calculations. In this paragraph, quantities and costs of the different
layouts are summarized per construction phase.
First quantities for each layout and phase are determined, subsequently construction are determined.
The area south of the existing port was planned to be leased out for other developments. The proposed
lease price per m2 for this area would be 25 Dhs/m2 year which is $ 6.08. The specific area that is used for
the container terminal is 164. This means that the yearly loss of income due to the unavailability of this
area would be $ 10 M.
10/29/2007 A8 - 10
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
A 8.3.1 Quantities
Dredging A1-B1 A2-B2 A2-B1 A3-B1 A4-B3 A4-B4 A5-B1 A5-B3 A5-B4
Dredging m3 4,922,732 8,990,487 8,990,487 19,243,054 21,403,968 21,403,968 21,403,968 21,403,968 21,403,968
Quarry run fill m3 7,867,199 0 0 0 0 0 0 0 0
Reclamation red. m3 0 5,149,785 5,149,785 12,673,843 15,050,848 15,050,848 16,097,866 16,097,866 16,097,866
Quay wall
Quay wall m 1935 1750 1750 2750 2750 2750 2750 2750 2750
Coastal protection
Revetment exposed m 330 430 430 430 631 631 631 631 631
Rvtm. sheltered m 0 0 0 0 830 0 0 0 0
Breakwater m 0 0 0 3775 3775 3775 3775 3775 3775
Brkw. roundhead - 1 1 1 2 2 2 2 2 2
Harbour basin m 0 0 0 0 1,700 1,300 0 0 0
OSTT
Berths - 2 2 2 2 2 2 2 2 2
Trestle bridges m 350 0 270 270 400 200 270 1150 620
Trestle abutment - 1 0 1 1 2 2 1 1 1
Piperack m 1460 950 960 960 1550 1400 960 650 750
Piping m 11680 4640 9840 9840 12195 10744 9840 12195 10744
table A 8.5 Quantities proposed layouts phase 1
10/29/2007 A8 - 11
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
Dredging A1-B1 A2-B2 A2-B1 A3-B1 A4-B3 A4-B4 A5-B1 A5-B3 A5-B4
Dredging m3 0 0 0 0 0 0 0 0 0
Quarry run fill m3 12,606,141 6,719,426 2,057,104 0 2,394,212 2,394,212 671,262 671,262 671,262
Reclamation red. m3 0 0 0 0 0 0 0 0 0
Quay wall
Quay wall m 1150 1020 400 1295 1295 1295 1295 1295 1295
Coastal protection
Revetment exposed m 670 445 0 0 750 750 750 750 750
Rvtm. sheltered m 1520 940 760 0 0 830 0 0 0
Breakwater m 750 750 750 750 0 0 0 0 0
Brkw. roundhead - 2 1 1 1 1 1 1 1 1
Harbour basin m 0 0 0 0 0 732 500 500 500
OSTT
Berths - 2 1 2 2 2 2 2 2 2
Trestle bridges m 250 0 250 250 120 260 250 760 970
Trestle abutment - 1 0 1 1 1 2 1 0 0
Piperack m 275 0 500 500 380 350 500 0 0
Piping m 16280 0 14640 14640 12200 12316 14640 13984 12316
Chemical berths - 1 1 1 1 1 1 1 1 1
table A 8.6 Quantities proposed layouts phase 2
10/29/2007 A8 - 12
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
Dredging A1-B1 A2-B2 A2-B1 A3-B1 A4-B3 A4-B4 A5-B1 A5-B3 A5-B4
Dredging m3 0 0 0 0 0 0 0 0 0
Quarry run fill m3 1,730,911 0 4,662,322 0 0 0 0 0 0
Reclamation red. m3 0 0 0 0 0 0 0 0 0
Quay wall
Quay wall m 525 0 620 0 0 0 0 0 0
Coastal protection
Revetment exposed m 525 0 440 0 160 160 0 0 0
Rvtm. sheltered m 0 0 840 0 380 380 0 0 0
Breakwater m 0 0 0 0 0 0 0 0 0
Brkw. roundhead - 0 0 1 0 0 0 0 0 0
Harbour basin m 0 0 0 0 380 380 0 0 0
OSTT
Berths - 1 0 1 1 1 1 1 1 1
Trestle bridges m 250 0 250 250 290 130 250 0 480
Trestle abutment - 1 0 1 1 1 1 1 0 0
Piperack m 500 0 500 500 495 352 500 0 0
Piping m 23080 0 21440 21440 8210 1890 21440 8140 7500
2
Chemical berths - 2 2 2 2 2 2 2 2 2
table A 8.7 Quantities proposed layouts phase 3
10/29/2007 A8 - 13
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
Dredging A1-B1 A2-B2 A2-B1 A3-B1 A4-B3 A4-B4 A5-B1 A5-B3 A5-B4
Dredging $27,075,026 $49,447,679 $49,447,679 $105,836,797 $117,721,824 $117,721,824 $117,721,824 $117,721,824 $117,721,824
Quarry run fill $70,804,791 $0 $0 $0 $0 $0 $0 $0 $0
Reclamation red. $0 -$20,599,142 -$20,599,142 -$50,695,372 -$60,203,393 -$60,203,393 -$64,391,464 -$64,391,464 -$64,391,464
Total $97,879,817 $28,848,537 $28,848,537 $55,141,425 $57,518,431 $57,518,431 $53,330,360 $53,330,360 $53,330,360
Quay wall
Quay wall $69,273,000 $62,650,000 $62,650,000 $98,450,000 $98,450,000 $98,450,000 $98,450,000 $98,450,000 $98,450,000
Coastal protection
Revetment exposed $9,938,323 $12,949,936 $12,949,936 $12,949,936 $19,003,278 $19,003,278 $19,003,278 $19,003,278 $19,003,278
Rvtm. sheltered $0 $0 $0 $0 $22,272,129 $0 $0 $0 $0
Breakwater $0 $0 $0 $141,825,051 $141,825,051 $141,825,051 $141,825,051 $141,825,051 $141,825,051
Brkw. roundhead $2,756,240 $2,756,240 $2,756,240 $5,512,480 $5,512,480 $5,512,480 $5,512,480 $5,512,480 $5,512,480
Harbour basin $0 $0 $0 $0 $25,583,062 $19,563,518 $0 $0 $0
Total $12,694,563 $15,706,176 $15,706,176 $160,287,467 $188,612,938 $166,340,809 $166,340,809 $166,340,809 $166,340,809
OSTT
Berths 1 0 1 1 1 1 1 1 1
Trestle bridges 250 0 250 250 290 130 250 0 480
Trestle abutment 1 0 1 1 1 1 1 0 0
Piperack
Piping
Lump sum
Overhead 500 0 500 500 495 352 500 0 0
Total 23080 0 21440 21440 8210 1890 21440 8140 7500
TOTAL $229,132,528 $114,066,449 $153,895,981 $360,570,161 $395,133,978 $368,969,448 $364,812,438 $379,404,284 $370,454,499
table A 8.8 Cost estimation phase 1
10/29/2007 A8 - 14
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
Dredging A1-B1 A2-B2 A2-B1 A3-B1 A4-B3 A4-B4 A5-B1 A5-B3 A5-B4
Dredging $0 $0 $0 $0 $0 $0 $0 $0 $0
Quarry run fill $113,455,269 $60,474,834 $18,513,938 $0 $21,547,908 $21,547,908 $6,041,354 $6,041,354 $6,041,354
Reclamation red. $0 $0 $0 $0 $0 $0 $0 $0 $0
Total $113,455,269 $60,474,834 $18,513,938 $0 $21,547,908 $21,547,908 $6,041,354 $6,041,354 $6,041,354
Quay wall
Quay wall $41,170,000 $36,516,000 $14,320,000 $46,361,000 $46,361,000 $46,361,000 $46,361,000 $46,361,000 $46,361,000
Coastal protection
Revetment exposed $20,177,807 $13,401,678 $0 $0 $22,587,098 $22,587,098 $22,587,098 $22,587,098 $22,587,098
Rvtm. sheltered $40,787,513 $25,223,857 $20,393,756 $0 $0 $22,272,129 $0 $0 $0
Breakwater $28,177,163 $28,177,163 $28,177,163 $28,177,163 $0 $0 $0 $0 $0
Brkw. roundhead $5,512,480 $2,756,240 $2,756,240 $2,756,240 $2,756,240 $2,756,240 $2,756,240 $2,756,240 $2,756,240
Harbour basin $0 $0 $0 $0 $0 $11,015,766 $7,524,430 $7,524,430 $7,524,430
Total $94,654,962 $69,558,937 $51,327,159 $30,933,403 $25,343,338 $47,615,466 $25,343,338 $25,343,338 $25,343,338
OSTT
Berths $33,135,424 $1,950,000 $33,135,424 $33,135,424 $33,135,424 $33,135,424 $33,135,424 $33,135,424 $33,135,424
Trestle bridges $3,674,002 $0 $3,674,002 $3,674,002 $1,763,521 $3,820,962 $3,674,002 $11,168,965 $14,255,126
Trestle abutment $150,000 $0 $150,000 $150,000 $150,000 $300,000 $150,000 $0 $0
Piperack $433,221 $0 $787,675 $787,675 $598,633 $551,373 $787,675 $0 $0
Piping $2,849,000 $0 $2,562,000 $2,562,000 $2,135,000 $2,155,300 $2,562,000 $2,447,200 $2,155,300
Lump sum $975,000 $975,000 $975,000 $975,000 $975,000 $975,000 $975,000 $975,000 $975,000
Overhead $5,564,247 $394,875 $5,573,354 $5,573,354 $5,232,273 $5,526,638 $5,573,354 $6,443,089 $6,820,315
Total $46,780,894 $3,319,875 $46,857,454 $46,857,454 $43,989,851 $46,464,696 $46,857,454 $54,169,678 $57,341,165
Chemical berths $18,250,000 $18,250,000 $18,250,000 $18,250,000 $18,250,000 $18,250,000 $18,250,000 $18,250,000 $18,250,000
TOTAL $314,311,126 $188,119,646 $149,268,551 $142,401,857 $155,492,096 $180,239,070 $142,853,145 $150,165,369 $153,336,856
table A 8.9 Cost estimation phase 2
10/29/2007 A8 - 15
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
Dredging A1-B1 A2-B2 A2-B1 A3-B1 A4-B3 A4-B4 A5-B1 A5-B3 A5-B4
Dredging $0 $0 $0 $0 $0 $0 $0 $0 $0
Quarry run fill $15,578,199 $0 $41,960,896 $0 $0 $0 $0 $0 $0
Reclamation red. $0 $0 $0 $0 $0 $0 $0 $0 $0
Total $15,578,199 $0 $41,960,896 $0 $0 $0 $0 $0 $0
Quay wall
Quay wall $18,795,000 $0 $22,196,000 $0 $0 $0 $0 $0 $0
Coastal protection
Revetment exposed $15,810,968 $0 $13,251,097 $0 $4,818,581 $4,818,581 $0 $0 $0
Rvtm. sheltered $0 $0 $22,540,468 $0 $10,196,878 $10,196,878 $0 $0 $0
Breakwater $0 $0 $0 $0 $0 $0 $0 $0 $0
Brkw. roundhead $0 $0 $2,756,240 $0 $0 $0 $0 $0 $0
Harbour basin $0 $0 $0 $0 $5,718,567 $5,718,567 $0 $0 $0
Total $15,810,968 $0 $38,547,805 $0 $15,015,459 $15,015,459 $0 $0 $0
OSTT
Berths $33,135,424 $0 $33,135,424 $33,135,424 $33,135,424 $33,135,424 $33,135,424 $33,135,424 $33,135,424
Trestle bridges $3,674,002 $0 $3,674,002 $3,674,002 $4,261,842 $1,910,481 $3,674,002 $0 $7,054,083
Trestle abutment $150,000 $0 $150,000 $150,000 $150,000 $150,000 $150,000 $0 $0
Piperack $787,675 $0 $787,675 $787,675 $779,798 $554,523 $787,675 $0 $0
Piping $4,039,000 $0 $3,752,000 $3,752,000 $1,436,750 $330,750 $3,752,000 $1,424,500 $1,312,500
Lump sum $650,000 $0 $650,000 $650,000 $650,000 $650,000 $650,000 $650,000 $650,000
Overhead $5,941,054 $0 $5,900,874 $5,900,874 $5,657,934 $5,142,365 $5,900,874 $4,929,389 $5,901,281
Total $48,377,155 $0 $48,049,975 $48,049,975 $46,071,748 $41,873,543 $48,049,975 $40,139,313 $48,053,288
Chemical berths $36,500,000 $36,500,000 $36,500,000 $36,500,000 $36,500,000 $36,500,000 $36,500,000 $36,500,000 $36,500,000
TOTAL $135,061,322 $36,500,000 $187,254,675 $84,549,975 $97,587,207 $93,389,002 $84,549,975 $76,639,313 $84,553,288
table A 8.10 Cost estimation phase 3
10/29/2007 A8 - 16
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
Dredging A1-B1 A2-B2 A2-B1 A3-B1 A4-B3 A4-B4 A5-B1 A5-B3 A5-B4
Phase 1 $229,132,528 $114,066,449 $153,895,981 $360,570,161 $395,133,978 $368,969,448 $364,812,438 $379,404,284 $370,454,499
Phase 2 $314,311,126 $188,119,646 $149,268,551 $142,401,857 $155,492,096 $180,239,070 $142,853,145 $150,165,369 $153,336,856
Phase 3 $135,061,322 $36,500,000 $187,254,675 $84,549,975 $97,587,207 $93,389,002 $84,549,975 $76,639,313 $84,553,288
TOTAL $678,504,975 $338,686,095 $490,419,208 $587,521,993 $648,213,282 $642,597,520 $592,215,558 $606,208,966 $608,344,642
table A 8.11 Summary cost estimation per phase
10/29/2007 A8 - 17
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
Dredging A1-B1 A2-B2 A2-B1 A3-B1 A4-B3 A4-B4 A5-B1 A5-B3 A5-B4
Dredging $27,075,026 $49,447,679 $49,447,679 $105,836,797 $117,721,824 $117,721,824 $117,721,824 $117,721,824 $117,721,824
Quarry run fill $199,838,259 $60,474,834 $60,474,834 $0 $21,547,908 $21,547,908 $6,041,354 $6,041,354 $6,041,354
Reclamation red. $0 -$20,599,142 -$20,599,142 -$50,695,372 -$60,203,393 -$60,203,393 -$64,391,464 -$64,391,464 -$64,391,464
Total $226,913,285 $89,323,371 $89,323,371 $55,141,425 $79,066,339 $79,066,339 $59,371,713 $59,371,713 $59,371,713
Quay wall
Quay wall $129,238,000 $99,166,000 $99,166,000 $144,811,000 $144,811,000 $144,811,000 $144,811,000 $144,811,000 $144,811,000
Coastal protection
Revetment exposed $45,927,098 $26,351,614 $26,201,033 $12,949,936 $46,408,956 $46,408,956 $41,590,376 $41,590,376 $41,590,376
Rvtm. sheltered $40,787,513 $25,223,857 $42,934,224 $0 $32,469,007 $32,469,007 $0 $0 $0
Breakwater $28,177,163 $28,177,163 $28,177,163 $170,002,214 $141,825,051 $141,825,051 $141,825,051 $141,825,051 $141,825,051
Brkw. roundhead $8,268,720 $5,512,480 $8,268,720 $8,268,720 $8,268,720 $8,268,720 $8,268,720 $8,268,720 $8,268,720
Harbour basin $123,160,494 $85,265,113 $105,581,140 $191,220,870 $228,971,734 $228,971,734 $191,684,147 $191,684,147 $191,684,147
Total $45,927,098 $26,351,614 $26,201,033 $12,949,936 $46,408,956 $46,408,956 $41,590,376 $41,590,376 $41,590,376
OSTT
Berths $99,406,272 $5,037,000 $99,406,272 $99,406,272 $99,406,272 $99,406,272 $99,406,272 $99,406,272 $99,406,272
Trestle bridges $12,491,605 $0 $11,315,925 $11,315,925 $11,903,765 $8,670,644 $11,315,925 $28,069,372 $30,420,733
Trestle abutment $450,000 $0 $450,000 $450,000 $600,000 $750,000 $450,000 $150,000 $150,000
Piperack $3,520,907 $1,496,583 $3,087,686 $3,087,686 $3,820,224 $3,311,386 $3,087,686 $1,023,978 $1,181,513
Piping $8,932,000 $812,000 $8,036,000 $8,036,000 $5,705,875 $4,366,250 $8,036,000 $6,005,825 $5,348,000
Lump sum $2,275,000 $1,625,000 $2,275,000 $2,275,000 $2,275,000 $2,275,000 $2,275,000 $2,275,000 $2,275,000
Overhead $17,367,411 $1,211,029 $17,027,815 $17,027,815 $16,903,072 $16,218,895 $17,027,815 $18,661,660 $18,946,265
Total $144,443,196 $10,181,611 $141,598,698 $141,598,698 $140,614,208 $134,998,447 $141,598,698 $155,592,106 $157,727,782
TOTAL $678,504,975 $338,686,095 $490,419,208 $587,521,993 $648,213,282 $642,597,520 $592,215,558 $606,208,966 $608,344,642
table A 8.12 Cost estimation total project
10/29/2007 A8 - 18
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
The capacity of the proposed layouts is determined by using the simulation models that are described in annex 3 to the masterplan report. The first objective of this
simulation study was to determine the required quay length and number of berths for the composed scenarios. The second objective is to test the capacity of the proposed
layout alternatives. The results of the last study are given in the following tables.
For layouts A1 – B1, there are two options proposed. In the first option, the full quay length of the dry bulk terminal is utilized for loading of aggregates. In this way it is
possible to reach the throughput as required for scenario 1. In the second option, this layout has two berths for import of dry bulk.
Phase 1
A1B1 - A A1B1 - B A2B2 A2B1 A3B1 A4B3 A4B4 A5B1 A5B3 A5B4
No of cranes /
No of cranes /
No of cranes /
No of cranes /
No of cranes /
No of cranes /
No of cranes /
No of cranes /
No of cranes /
No of cranes /
Quay length /
Quay length /
Quay length /
Quay length /
Quay length /
Quay length /
Quay length /
Quay length /
Quay length /
Quay length /
loading arms
loading arms
loading arms
loading arms
loading arms
loading arms
loading arms
loading arms
loading arms
loading arms
berths
berths
berths
berths
berths
berths
berths
berths
berths
berths
Aggregates 1050 3 725 2 325 1 1050 3 910 3 910 3 910 3 910 3 910 3 910 3
Other dry bulk 0 0 325 1 0 0 0 0 280 1 280 1 280 1 280 1 280 1 280 1
Oil 2 8 2 8 725 8 725 8 2 8 2 8 2 8 2 8 2 8 2 8
Containers 880 12 880 12 700 9 700 9 1450 19 1450 19 1450 19 1450 19 1450 19 1450 19
Chemicals - - - - - - - - - - - - - - - - - - - -
table A 8.13 Available quay length, phase 1
It can be seen that the quay lengths and number of berths do not differ for layouts A3, A4 and A5. These layouts supply for the highest growth scenario.
10/29/2007 A8 - 19
Oil
Oil
10/29/2007
table A 8.15
table A 8.14
Chemicals
Chemicals
Containers
Containers
Aggregates
Aggregates
2
6
1
4
0
0
2030
1575
2030
1050
No of cranes / No of cranes /
A1B1 - A
Phase 1
Phase 2
A1B1 - A
loading arms loading arms
0
0
0
0
3
Quay length / Quay length /
berths berths
2
6
1
4
0 525
325
30 2030
5 1050
30 2030
725
A1B1 - B
loading arms loading arms
0
0
0
0
2
1
30
3
30
2
A2B2
A2B2
1055
2
2
0
0
0
1050
1022
1022
700
No of cranes / No of cranes /
loading arms loading arms
3
0
0
0
0
0
15
3
15
2
2
6
0
525
0
1050
1022
700
1050
No of cranes / No of cranes /
loading arms loading arms
0
0
0
0
2
0
15
3
15
3
2
6
1
525
525
1435
2110
2110
1395
No of cranes / No of cranes /
loading arms loading arms
0
0
0
2
2
40
40
5
berths berths
A4B3
A4B3
2
6
1
525
525
1435
2110
1395
2110
No of cranes / No of cranes /
loading arms loading arms
0
0
0
2
2
40
40
5
2
6
525
1
1435
525
1395
2110
2110
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
No of cranes / No of cranes /
loading arms loading arms
0
0
2
0
5
2
40
5
40
2
6
525
1
1435
525
1395
2110
2110
No of cranes / No of cranes /
loading arms loading arms
0
0
2
0
5
2
5
40
40
525
2
6
1435
1
525
1395
2110
2110
A8 - 20
No of cranes / No of cranes /
loading arms loading arms
2
0
0
5
0
2
5
40
40
525
1435
5
525
1395
2
6
2110
1
2110
No of cranes / No of cranes /
loading arms loading arms
2
5
2
5
0
40
0
0
40
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
The capacity of the proposed layouts is determined by using the simulation models that are described in annex 3 to the masterplan report. The first objective of this
simulation study was to determine the required quay length and number of berths for the composed scenarios. The second objective is to test the capacity of the proposed
layout alternatives. The results of the last study are given in the following tables.
Phase 1
A1B1 - A A1B1 - B A2B2 A2B1 A3B1 A4B3 A4B4 A5B1 A5B3 A5B4
Aggregates 50 30 15 50 50 50 50 50 50 50 [M ton/yr]
Other dry bulk 0 4 0 0 4 4 4 4 4 4 [M ton/yr]
Oil 30 30 30 30 30 30 30 30 30 30 [M ton/yr]
Containers 0.75 0.75 0.5 0.5 1.5 1.5 1.5 1.5 1.5 1.5 [M TEU/yr]
Chemicals - - - - - - - - - - [M ton/yr]
table A 8.16 Maximum throughput phase 1
Phase 2
A1B1 – A A1B1 - B A2B2 A2B1 A3B1 A4B3 A4B4 A5B1 A5B3 A5B4
Aggregates 50 30 30 50 90 90 90 90 90 90 [M ton/yr]
Other dry bulk 0 4 0 0 8 8 8 8 8 8 [M ton/yr]
Oil 62 62 46 62 78 78 78 78 78 78 [M ton/yr]
Containers 2.5 2.5 1 0.5 3.5 3.5 3.5 3.5 3.5 3.5 [M TEU/yr]
Chemicals 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 [M ton/yr]
table A 8.17 Maximum throughput phase 2
Phase 3
A1B1 – A A1B1 - B A2B2 A2B1 A3B1 A4B3 A4B4 A5B1 A5B3 A5B4
Aggregates 100 50 50 50 100 100 100 100 100 100 [M ton/yr]
Other dry bulk 0 8 0 8 8 8 8 8 8 8 [M ton/yr]
Oil 100 100 30 100 100 100 100 100 100 100 [M ton/yr]
Containers 2.5 2.5 1 1 3.5 3.5 3.5 3.5 3.5 3.5 [M TEU/yr]
Chemicals 1 1 1 1 1 1 1 1 1 1 [M ton/yr]
table A 8.18 Maximum throughput phase 3
10/29/2007 A8 - 21
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
A3 - B1 A4 - B3 A4 - B4 A5 - B1 A5 - B3 A5 - B4
[$M] [$M] [$M] [$M] [$M] [$M]
2007 -$360.6 -$395.1 -$369.0 -$364.8 -$379.4 -$370.5
2008 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2009 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2010 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2011 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2012 -$142.4 -$155.5 -$180.2 -$142.9 -$150.2 -$153.3
2013 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2014 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2015 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2016 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2017 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2018 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2019 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2020 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2021 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2022 -$84.5 -$97.6 -$93.4 -$84.5 -$76.6 -$84.6
2023 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2024 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2025 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2026 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2027 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2028 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2029 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2030 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2031 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
2032 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
NPV -$460.5 -$506.0 -$496.6 -$464.8 -$480.6 -$477.0
table A 8.19 NPV Scenario 1
10/29/2007 A8 - 22
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
Discount rate: 7%
A1 – B1 A3 – B1
[$M] [$M]
2007 -$229.1 -$370.6
2008 $0.0 -$10.0
2009 $0.0 -$10.0
2010 $0.0 -$10.0
2011 $0.0 -$10.0
2012 -$314.3 -$10.0
2013 $0.0 -$10.0
2014 $0.0 -$10.0
2015 $0.0 -$10.0
2016 $0.0 -$10.0
2017 $0.0 -$10.0
2018 $0.0 -$10.0
2019 $0.0 -$10.0
2020 $0.0 -$10.0
2021 $0.0 -$10.0
2022 -$86.7 -$152.4
2023 $0.0 -$10.0
2024 $0.0 -$10.0
2025 $0.0 -$10.0
2026 $0.0 -$10.0
2027 $0.0 -$10.0
2028 $0.0 -$10.0
2029 $0.0 -$10.0
2030 $0.0 -$10.0
2031 $0.0 -$10.0
2032 $0.0 -$10.0
NPV -$452.9 -$503.5
table A 8.20 NPV Scenario 2
10/29/2007 A8 - 23
Masterplan for the Port of Fujairah Expansion Project, Msc Thesis
Annex 8 Layout evaluation
Discount rate: 7%
A1 - B1 A2 - B2 A2 - B1 A3 - B1
[$M] [$M] [$M] [$M]
2007 -$257.3 -$114.1 -$153.9 -$360.6
2008 $0.0 -$188.1 $0.0 -$10.0
2009 $0.0 $0.0 $0.0 -$10.0
2010 $0.0 $0.0 $0.0 -$10.0
2011 $0.0 $0.0 $0.0 -$10.0
2012 -$46.8 $0.0 -$149.3 -$46.9
2013 $0.0 $0.0 $0.0 -$10.0
2014 $0.0 $0.0 $0.0 -$10.0
2015 $0.0 $0.0 $0.0 -$10.0
2016 $0.0 $0.0 $0.0 -$10.0
2017 $0.0 $0.0 $0.0 -$10.0
2018 $0.0 $0.0 $0.0 -$10.0
2019 $0.0 $0.0 $0.0 -$10.0
2020 $0.0 $0.0 $0.0 -$10.0
2021 $0.0 $0.0 $0.0 -$10.0
2022 $0.0 $0.0 -$187.3 -$10.0
2023 $0.0 $0.0 $0.0 -$10.0
2024 $0.0 $0.0 $0.0 -$10.0
2025 $0.0 $0.0 $0.0 -$10.0
2026 $0.0 $0.0 $0.0 -$10.0
2027 $0.0 $0.0 $0.0 -$10.0
2028 $0.0 $0.0 $0.0 -$10.0
2029 $0.0 $0.0 $0.0 -$10.0
2030 $0.0 $0.0 $0.0 -$10.0
2031 $0.0 $0.0 $0.0 -$10.0
2032 $0.0 $0.0 $0.0 -$10.0
NPV -$271.6 -$270.9 -$306.7 -$470.5
table A 8.21 NPV Scenario 3
10/29/2007 A8 - 24