A Hard Narrow Rock Mining
A Hard Narrow Rock Mining
A Hard Narrow Rock Mining
The ARM 1100 was described in a paper presented at the 6th International Symposium on Mine
Mechanization and Automation in September 2001. It started operation underground at Rowland
Shaft in early 2002. This paper covers the results of those trials that resulted in more than 1 100
square metres of UG2 being mined.
Figure 6. Assembly of the ARM 1100, launching the machine and cutting into the raise
Current Penetrat(mm)
Stall Counter []
180
150
30
0
Figure 7. Typical machine and cutting data collected for each cycle of the machine
Figure 9. Scoop arm used to load cut rock onto the belt conveyor
10
0
20 25 30 35 40 45 50 55 60 65 70 75 80 85 90
depth of cut (mm)
Chips from steel-ring cutters Chips from chisel-type cutters Chips from 20° conical buttons
Cleaning process
Roof support
From the outset the cleaning of ore away from the cutter
head was identified as a major obstacle and indeed proved Currently roof support is being installed by hand. The
to be problematic. The main issues being: necessity to have an integrated permanent roof support
system was recognized early on in the project. With the
• Cleaning of ore from the cutting path. Too much ore availability now of a drifter small enough to operate in a
remained in the cutter path after completion of the
1.1 M stoping height it was decided to start immediately
cleaning stroke. This is demonstrated in Figure 13
with design of an integrated bolting system.
below
• The ore remaining is subject to a regrinding action,
resulting in high fines content. Ore handling system
• The cleaning arm which feeds the ore into the loading
chute to the conveyor is inefficient The cleaning system behind the ARM is another problem,
• The conveyor design is inadequate and results in which requires urgent attention. At the moment a ULP
excessive breakages. This is the result of both design loader is being successfully used, this provides a flexible,
(return pulley too short) and the accumulation of fines reliable cleaning method however, a very expensive one.
under the conveyor. Other alternatives are also being perused such as:-
A number of changes was made to improve the situation, • Vacuum system
Figure 14 shows the general arrangement, and more • Mobile conveyors
changes are in the process of being made. These are: • Shuttle cars
Face scraper
Loading
Loading chute arm
Figure 13. Material left on the face after the cutter head has
completed its cleaning stroke Figure 14. Modified conveyor belt loading