100% found this document useful (1 vote)
317 views35 pages

Provisional Acceptance Test: DWDM: OSN9800 4238 Pakistan

The document is a provisional acceptance test template for a CMPAK 2018 bidding project involving the installation of DWDM equipment, including an OSN9800, at site 4238. It details an 11-step testing process to verify the system's power redundancy, mean launched power, receiver sensitivity, central wavelength and deviation, side-mode suppression ratio, -20 dB spectrum width, channel gain, insertion loss of multiplexers, demultiplexers and DCMs, OSNR, 24-hour bit error test, and includes tables to record test results. The tests are to be conducted by Huawei and Zong representatives to certify the system meets specifications before provisional acceptance.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
317 views35 pages

Provisional Acceptance Test: DWDM: OSN9800 4238 Pakistan

The document is a provisional acceptance test template for a CMPAK 2018 bidding project involving the installation of DWDM equipment, including an OSN9800, at site 4238. It details an 11-step testing process to verify the system's power redundancy, mean launched power, receiver sensitivity, central wavelength and deviation, side-mode suppression ratio, -20 dB spectrum width, channel gain, insertion loss of multiplexers, demultiplexers and DCMs, OSNR, 24-hour bit error test, and includes tables to record test results. The tests are to be conducted by Huawei and Zong representatives to certify the system meets specifications before provisional acceptance.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 35

HUAWEI TECHNOLOGIES PAKISTAN

PROVISIONAL ACCEPTANCE TEST TEMPLATE


CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

PROVISIONAL ACCEPTANCE TEST

Project No
Project Name CMPAK 2018 BIDDING Project

Equipment
DWDM: OSN9800
(Name & Model)

Site ID/Name 4238


CM PAK Region Pakistan
Name of Contractor M/s Huawei Technologies Pakistan (Pvt.) Ltd.
Date of Installation
Date of Acceptance Testing
Total Pages 32

Huawei Technologies Pakistan Pvt. Ltd 1


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

TABLE OF CONTENTS

1. Power Redundancy Check------------------------------------------------------------------------------------------------------------------- 5 -


2. Mean Launched Power----------------------------------------------------------------------------------------------------------------------- 6 -
3. Receiver Sensitivity--------------------------------------------------------------------------------------------------------------------------- 8 -
3.1. Test on Optical Transponder Unit------------------------------------------------------------------------------------------------------------ 8 -
3.2. Test on Optical Supervisory Channel------------------------------------------------------------------------------------------------------ 10 -
4. Central Wavelength and Deviation----------------------------------------------------------------------------------------------------- 12 -
5. Side-Mode Suppression Ratio------------------------------------------------------------------------------------------------------------ 15 -
6. -20 dB Spectrum Width--------------------------------------------------------------------------------------------------------------------- 17 -
7. Channel Gain---------------------------------------------------------------------------------------------------------------------------------- 20 -
8.1 Insertion Loss of Multiplexer----------------------------------------------------------------------------------------------------------------- 23 -
8.2 Insertion Loss of Demultiplexer------------------------------------------------------------------------------------------------------------- 25 -
8.3 Insertion Loss of DCM-------------------------------------------------------------------------------------------------------------------------- 27 -
9. OSNR Test------------------------------------------------------------------------------------------------------------------------------------- 29 -
10. 24-Hour Bit Error Test--------------------------------------------------------------------------------------------------------------------- 31 -
11. Site Deficiency List:------------------------------------------------------------------------------------------------------------------------ 33 -
12. Nill Deficiency Certificate---------------------------------------------------------------------------------------------------------------- 34 -
13. BOQ List:------------------------------------------------------------------------------------------------------------------------------------- 35 -

Huawei Technologies Pakistan Pvt. Ltd 2


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

1. Power Redundancy Check


1. On the top of the cabinet; Switch off Power Supply 1.
Result: NE should be in normal Running state.
2. On the top of the cabinet; Switch on power supply 1 and Switch off Power Supply 2
Result: NE should be in normal Running state

Power Supply Test Record Table


Power supply Power supply 2 Power Power
Node ID
1 (V1) (V2) Redundancy 1 Redundancy 2

2. Mean Launched Power

Huawei Technologies Pakistan Pvt. Ltd 3


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

1. Test Configuration

Configuration for testing mean launched power


 
2. Test Procedure
Step 1 Turn on the optical power meter.
Step 2 Set up the optical path according to the figure above.
Step 3 Wait until the numerical reading of the optical power meter is stable; read this
value.

Mean Launched Power Test Record Table

Huawei Technologies Pakistan Pvt. Ltd 4


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

Test sub-item Mean launched power


Node Slot Board Optical Rate Test result Conclusion
No. type interface No. (dBm)

Note: Each PAT member must sign each test result on site

Remarks:

Test instruments: Tested by: Date:

HUAWEI’S REPRESENTATIVE ZONG REPRESENTATIVE

Huawei Technologies Pakistan Pvt. Ltd 5


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

3. Receiver Sensitivity
3.1. Test on Optical Transponder Unit
1.  Test configuration

OTU

TX Variable
Optical
attenuator1
Variable O
Optical T
attenuator2
U
R
RX

Optical
power
meter
Configuration diagram for test on receiver sensitivity
 2.  Test procedure
Step 1 Connect the test optical line according to the above diagram. Optical attenuator 1 can employ a
non-adjustable 10 dB fixed optical attenuator. Ensure the input power at IN end of SDH tester
within the permitted range.
Step 2 Adjust the adjustable optical attenuator 2 to ensure that there is no alarm found on the board.
Step 3 The sensitivity can be tested by the self-loop alarm of the board. Use the self-loop fiber to self
loop other channels, so as to prevent the board from generating alarms.
Step 4 Adjust the tunable attenuator to increase the attenuation value to the critical point of the board
alarm; disconnect the receiving end of OTU; measure the input optical signal power with the
optical power, which is right the receiver sensitivity of OTU.

Receiver Sensitivity Test Record Table

Huawei Technologies Pakistan Pvt. Ltd 6


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

Test sub-item Receiver sensitivity

Node No. Slot Board type Optical interface No. Test result (dBm) Conclusion

Note: Each PAT member must sign each test result on site

Remarks:

Test instruments: Tested by: Date:

HUAWEI’S REPRESENTATIVE ZONG REPRESENTATIVE

Huawei Technologies Pakistan Pvt. Ltd 7


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

3.2. Test on Optical Supervisory Channel

(Note: The test will be performed on SC2/SC1 per Site)

1.  Index requirement

Receiver sensitivity: -35dBm

2.  Test configuration

Configuration diagram for test on receiver sensitivity

3.  Test procedure

Step 1 Connect the test configuration according to the above diagram.

Step 2 Because there is no related test on the instruments, the sensitivity can be tested by the self-
loop alarm of the monitored board. Use the self-loop fiber to self loop other channels, so as to
prevent the board from generating alarms.

Step 3 Adjust the tunable attenuator to increase the attenuation value to the critical point of the board
alarm; disconnect the receiving end of OSC; measure the input optical signal power with the
optical power, which is right the receiver sensitivity of OSC.

.Receiver Sensitivity Test Record Table

Huawei Technologies Pakistan Pvt. Ltd 8


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

Test sub-item Receiver sensitivity

Node No. Slot Board type Optical interface No. Test result (dBm) Conclusion

Note: Each PAT member must sign each test result on site

Remarks:

Test instruments: Tested by: Date:

HUAWEI’S REPRESENTATIVE ZONG REPRESENTATIVE

4. Central Wavelength and Deviation

Huawei Technologies Pakistan Pvt. Ltd 9


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

1.  Index requirement

The frequency and wavelength of 40-channel (100 GHz interval) of C band is shown in the following table.

Central frequency Central wavelength Central frequency Central wavelength


(THz) (nm) (THz) (nm)
196.00 1529.55 194.00 1545.32

195.90 1530.33 193.90 1546.12

195.80 1531.12 193.80 1546.92

195.70 1531.90 193.70 1547.72

195.60 1532.68 193.60 1548.51

195.50 1533.47 193.50 1549.32

195.40 1534.25 193.40 1550.12

195.30 1535.04 193.30 1550.92

195.20 1535.82 193.20 1551.72

195.10 1536.61 193.10 1552.52

195.00 1537.40 193.00 1553.33

194.90 1538.19 192.90 1554.13

194.80 1538.98 192.80 1554.94

194.70 1539.77 192.70 1555.75

194.60 1540.56 192.60 1556.55

194.50 1541.35 192.50 1557.36

194.40 1542.14 192.40 1558.17

194.30 1542.94 192.30 1558.98

194.20 1543.73 192.20 1559.79

194.10 1544.53 192.10 1560.61

 2.  Test configuration

Huawei Technologies Pakistan Pvt. Ltd 10


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

Configuration diagram of test on central wavelength

3.  Test procedure

Step 1 Start the multi-wavelength meter and wait till preheating is over.

Step 2 Connect the optical line according to the above diagram.

Step 3 Set the multi-wavelength meter in test mode, and press the AUTO key to start automatic test.

Step 4 Get the reading of the central wavelength value from the multi-wavelength meter.

4.  Note

For the test on the central wavelength, a multi-wavelength meter is recommended. If the meter is
unavailable, the test can be fulfilled with the optical spectrum analyzer, but it should be calibrated before
the test.

Central Wavelength and Deviation

Huawei Technologies Pakistan Pvt. Ltd 11


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

The central wavelength (frequency)of


Test sub item
the optical carrier
Test Standard Wavelength(frequ
Sub rack name Slot number Board type
value nm wavelength(nm) ency) offset (nm)

Note: Each PAT member must sign each test result on site
Remarks

Test instruments: Tested by: Date:

HUAWEI’S REPRESENTATIVE ZONG REPRESENTATIVE

5. Side-Mode Suppression Ratio

Huawei Technologies Pakistan Pvt. Ltd 12


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

1.  Test configuration

Configuration diagram of test on side mode suppression ratio

2.  Test procedure

Step 1 Turn on the optical spectrum analyzer, and connect the test configuration according to the
above diagram.

Step 2 Set the optical spectrum analyzer as DFB test mode.

Step 3 Press "AUTO" button of the optical spectrum analyzer to start the automatic test.

Step 4 Read the side mode suppression ratio (SMSR) directly from the optical spectrum analyzer.

Side Mode Suppression Ratio

Huawei Technologies Pakistan Pvt. Ltd 13


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

Test subitem Side mode suppression ratio

Subrack name Slot number Board type Test value(dB) Test conclusion

Note: Each PAT member must sign each test result on site
Remarks

Test instruments: Tested by: Date:

HUAWEI’S REPRESENTATIVE ZONG REPRESENTATIVE

6. -20 dB Spectrum Width

Huawei Technologies Pakistan Pvt. Ltd 14


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

1. Test Configuration

Optical
Integrated Spectrum
Transmitter Analyzer

Configuration for testing –20 dB spectrum width

2. Test Procedure

Step 1 Select a proper spectrum analyzer and turn it on for preheating. Set up the optical path
according to the figure above.

Step 2 Set the spectrum analyzer to the DFB test mode.

Step 3 Press the AUTO button on the spectrum analyzer to start an automatic test.

Step 4 Read the –20 dB spectrum width value displayed on the spectrum analyzer.

–20 dB Spectrum Width


Test subitem –20 dB spectrum width

Huawei Technologies Pakistan Pvt. Ltd 15


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

Subrack name Slot number Board type Test value nm Test conclusion

Note: Each PAT member must sign each test result on site
Remarks

Test instruments: Tested by: Date:

HUAWEI’S REPRESENTATIVE ZONG REPRESENTATIVE

Huawei Technologies Pakistan Pvt. Ltd 16


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

LSX Board Specifications

Optical Module at the Client Side


Item Unit Value
Optical Module Type 10 Gbit/s 10 Gbit/s 10 Gbit/s 10 Gbit/s Multi-
Multi-rate -10 Multi-rate -40 Single-rate rate -80 km
km km -0.3 km
Transmitter parameter specifications at point S

Maximum mean launched power dBm –1 2 –1.3 4

Minimum mean launched power dBm –6 –4.7 –7.3 0

Receiver parameter specifications at point R

Receiver sensitivity dBm –13.4 –14 –7.5 –24.0

DWDM Optical Module at Line Side


Item Unit Value
Optical Module Type 800 1600 1100 ps/nm- 1100 ps/nm- 4800
ps/nm ps/nm tunable- tunable- ps/nm
PIN APD -tunable
Transmitter parameter specifications at point S

Maximum mean launched power dBm 2 4 4 4 4

Minimum mean launched power dBm –3 0 0 0 0

Central frequency THz 192.10 to 196.00

Central frequency deviation GHz ±10

Maximum –20 dB spectral width nm 0.3 0.3 0.3 0.3 0.3

Sidé mode suppression ratio dB 35 35 35 35 35

Receiver parameter specifications at point R

Operating wavelength range nm 1200 to 1650

Receiver sensitivity dBm –14 –25 –16 –25 –27

Huawei Technologies Pakistan Pvt. Ltd 17


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

7. Channel Gain

1. Test configuration

Optical
Power Meter

1
Configuration diagram for gain test
2. Test procedure

2
Step 1 The input signal of the optical amplifying board comes from the multiplexer unit. Connect the test
configuration according to the above diagram.

Step 2 Adjust the tunable attenuator, to make the input power of the optical amplifying unit to be tested
within its permissible input range. Employ the optical power meter to measure the optical power at the
input end of the amplifier, and save the result.

Step 3 Employ the optical power meter again to measure the optical power at the output end of the amplifier.
And save the result.

M40
... ...

Step 4 Subtract the input optical power of the amplifier from the output optical power of the amplifier, the
result of subtracting is just the gain of each channel and the optical amplifier.

Note:
When the gains of the optical amplifier are measured, the optical spectrum analyzer should be applied.
The ASE noise will be significant after the amplification, when the input of amplifier is small signal. Thus,
the significant ASE noise will induce relatively significant error when using the optical power meter to fulfill
the gain test.

40
Huawei Technologies Pakistan Pvt. Ltd 18
HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

3. Specifications
OBU1 Board Specifications
Item Unit Value
TN11OBU101/T TN11OBU103/TN TN11OBU104/T
N12OBU101 12OBU103 N12OBU104
Operating wavelength range nm 1529-1561 1529-1561 1529-1561
Nominal input power range dBm -32 to -4 -32 to -3 -32 to -1
Input power range per 40 channels dBm -32 to -20 -32 to -19 -32 to -17
channel 80 channels -32 to -23 -32 to -22 -32 to -20
Typical input power of a 40 channels dBm -20 -19 -17
single wavelength 80 channels -23 -22 -20
Nominal gain dB 20 23 17
Channel gain dB 20±1.5 23±1.5 17±1.5
a: The items are supported on the TN12OBU1.

OBU205 Board Specifications:

Item Unit Value


OBU205
Operating wavelength range nm 1529-1561
Nominal input power range dBm -24 to 0
Input power range per channel 40 channels dBm -24 to -16
80 channels -24 to -19
Typical input power of a single wavelength 40 channels dBm -16
80 channels -19
Nominal gain dB 23
Channel gain dB 23±1.5

Huawei Technologies Pakistan Pvt. Ltd 19


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

Channel Gain
Test subitem Input/output optical power and gain of each channel
Subrack Slot Board Input optical Output optical Channel Test
name number Type power (dBm) power (dBm) gain (dB) conclusion

Note: Each PAT member must sign each test result on site
Remarks:

Test instruments: Tested by: Date:

HUAWEI’S REPRESENTATIVE ZONG REPRESENTATIVE

8. Insertion Loss Tests:

Huawei Technologies Pakistan Pvt. Ltd 20


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

8.1 Insertion Loss of Multiplexer


1.  Index requirement

Insertion loss of TN11M40: 6.5 dB

2.  Test configuration

Power
Meter

Power
Meter

Configuration diagram for test on insertion loss of multiplexer


3.  Test procedure

Step 1 Connect the test meters according to the figure above. For the M40, if the M40 has an EXT
optical port, the EXT port can be used to be connected with the OUT port of the M08 to test the
specifications of the M08. 

Step 2 Test the output optical power W1 of ASE broadband optical source with the optical power
meter, and save it in Channel A.

Step 3 Test the power Wi of the input port of No.i channel of the multiplexer with the optical power
meter, and save it in Channel B. Fulfill the coverage storage for Channel B.

Step 4 Calculate the difference between the input and output powers: W (dB) = W1 (dBm)-Wi (dBm),
which is just the insertion loss IL of No.i channel.

(Note: The test will be performed on 1 port on 1*M40 Per site)

Insertion Loss of Multiplexer M40

Huawei Technologies Pakistan Pvt. Ltd 21


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

Test subitem Insertion loss of multiplexer OMU


Subrack name Slot number Board type Test value (dB) Conclusion
         

         

         

         

         

         

         

         

         

         

         

         

         

Note: Each PAT member must sign each test result on site

Remarks
 
 

Test instruments: Tested by: Date:

HUAWEI’S REPRESENTATIVE ZONG REPRESENTATIVE

8.2 Insertion Loss of Demultiplexer


1.  Index requirement

Huawei Technologies Pakistan Pvt. Ltd 22


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

TN11D40 Insertion loss 6.5dB

2.  Test configuration

Power
Meter

Configuration diagram for test on insertion loss of multiplexer


3.  Test procedure

Step 1 Connect the test meters according to the figure above. For the D40, if the D40 has an EXT
optical port, the EXT port can be used to be connected with the IN port of the D08 to test the
specifications of the M08.

Step 2 ASE broadband optical source can be substituted by an optical amplifying board, that is, when
the optical amplifying board has no input, open the pump laser, and what will be outputted is
just ASE broadband optical source.

Step 3 Employ the optical power meter to test the output optical power W1 of ASE broadband optical
source, and save it in Channel A.

Step 4 Then employ the optical power meter to test the power Wi of the input port of NO.i channel of
the multiplexer once again, and save it in Channel B. Overlay storage is implemented in
Channel B.

Step 5 Calculate the difference W of the input and output powers: W (dB) = W1 (dBm) - Wi (dBm),
which is just the insertion loss IL of channel i.

Step 6 Repeat steps of (4) and (5) to test separately the insertion loss of each channel, and record the
result.

(Note: The test will be performed on one port on 1*D40 per Site)

Insertion Loss of Demultiplexer D40

Huawei Technologies Pakistan Pvt. Ltd 23


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

Test subitem Insertion loss of demultiplexer ODU


Subrack name Slot number Board type Port name Test value (dB) conclusion
           

           

           

           

           

           

           

           

           

           

           

           

           

Note: Each PAT member must sign each test result on site

Remarks
 
 

Test instruments: Tested by: Date:

HUAWEI’S REPRESENTATIVE ZONG REPRESENTATIVE

8.3 Insertion Loss of DCM


1.  Test configuration

Huawei Technologies Pakistan Pvt. Ltd 24


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

Power
Meter
Configuration diagram for test on insertion loss of DCM board
 2.  Test procedure

Step 1 Refer to the above diagram to connect the test configuration.


Step 2 The ASE broadband optical source can be replaced by an optical amplifier unit. When the
optical amplifier has no input, you can turn on the pump laser to output the ASE broadband
optical source.
Step 3 Use an optical power meter to test the output optical power Win of the ASE broadband optical
source, and save Win to channel A.
Step 4 Use an optical power meter to test the output port power Wout of the DSE board, and save
Wout to channel B.
Step 5 Difference between the input and output powers W (dB): W (dB) = Win (dBm) - Wout (dBm),
constitutes the insertion loss curve of the DCM. The maximum insertion loss of the
corresponding bandwidth is the fixed insertion loss of the DCM.
Specifications
Performance requirement of dispersion compensation optical fiber of C-band (G.652 fiber)
Item Max. Insertion PMD PDL Max. Allow Power Operation Wavelength
Distance
Type Loss(dB) (ps) (dB) (dBm) (nm)

DCM(T) 10 km 2.8 0.3 0.1 20

DCM(A) 20 km 3.3 0.4 0.1 20

DCM(B) 40 km 4.7 0.5 0.1 20

DCM(C) 60 km 6.4 0.6 0.1 20 1528-1568

DCM(D) 80 km 8 0.7 0.1 20

DCM(E) 100 km 9 0.8 0.1 20

DCM(F) 120 km 9.8 0.8 0.1 20

Huawei Technologies Pakistan Pvt. Ltd 25


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

The Insertion Loss of the DCM


Test subitem Insertion Loss

Subrack name. Slot number Board type Insertion loss Test conclusion

         

         

         

         

         

         

         

         

         

         

         

         

         

Note: Each PAT member must sign each test result on site

Remarks
 
 

Test instruments: Tested by: Date:

HUAWEI’S REPRESENTATIVE ZONG REPRESENTATIVE

Huawei Technologies Pakistan Pvt. Ltd 26


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

9. OSNR Test

1.  Test configuration

Configuration diagram for test on optical signal-to-noise ratio


 
2.  Test procedure
Step 1 Use the OSA to test the OSNR of the current system.
Step 2 Note down the result.

3.  Expected results

OSNR should not be less than 18 dB

Huawei Technologies Pakistan Pvt. Ltd 27


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

OSNR Test
Test subitem OSNR Precision
Subrack name Slot number Board type Port Test value(dB) Test conclusion
           

           

           

           

           

           

           

           

           

           

           

           

           

           

           

Note: Each PAT member must sign each test result on site

Remarks
  
 

Test instruments: Tested by: Date:

HUAWEI’S REPRESENTATIVE ZONG REPRESENTATIVE

10. 24-Hour Bit Error Test

Huawei Technologies Pakistan Pvt. Ltd 28


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

1.  Test Name: 24 hour bit error

For the specifications, see ITU-T G.826, ITU-T G.828, ITU-T M.2101, ITU-T M.2110 and ITU-T M.2120.

2.  Test Configuration

OTU board OTU board

Site A Site B Site C Site D Site E Loop


TM ADM ADM ADM TM
10G Analyzer

Loopback test
Note:

(1) The loopback (bidirectional) test is usually conducted, while the unidirectional test is also acceptable.

(2) In compliance with ITU-T M.2110, the observing time is 24 hours.

3.  Test Procedures

Step 1 Connect the circuit as shown in figure above

Step 2 According to the rate of interface and Table A-5 in the appendix, select proper PRBS for the
pattern generator to send test signals to the input port of the tested system.

Step 3 When the system works normally, perform the 24-hour BER test, set the printing time, start the
test and lock the instrument.

Step 4 After 24 hours, read (by printing) the test results from the test meter.

24-Hour System Bit Error Test

Huawei Technologies Pakistan Pvt. Ltd 29


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

Ring No. NE List 24 Hour Observation Test Result

Passed           Failed

Passed           Failed

Passed           Failed

Passed           Failed

Passed           Failed

Passed           Failed

Passed           Failed

Passed           Failed

Passed           Failed

Passed           Failed

Note: Each PAT member must sign each test result on site

Remarks:

Test instruments: Tested by: Date:

HUAWEI’S REPRESENTATIVE ZONG REPRESENTATIVE

11. Site Deficiency List:


Site Name: _______________

Huawei Technologies Pakistan Pvt. Ltd 30


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

The following deficiencies/ discrepancies were observed during the PAT and are subject to rectification or logical
justification, as the case may be.
Rectified By
S. No Test Reference Deficiency description
Huawei CM PAK
01
02
03
04
05
06

HUAWEI’S REPRESENTATIVE: ZONG REPRESENTATIVE:

12. Nill Deficiency Certificate


Site Name: _______________

Huawei Technologies Pakistan Pvt. Ltd 31


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

This is to acknowledge that we have jointly tested and confirmed that the following technical problems noted at the
time of acceptance testing have been resolved.
Rectified By
S. No Test Reference Deficiency description
Huawei CM PAK
01
02
03
04
05
06

HUAWEI’S REPRESENTATIVE: ZONG REPRESENTATIVE:

13. BOQ List:

Model Description Total Quantity Installed QTY

Huawei Technologies Pakistan Pvt. Ltd 32


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

OptiX OSN 8800(V100R006)    


Main Equipment    
Rack    

N63B Type ETSI Rack(2200*600*300mm)Without


TN1B6RACK02
SubRack(OSN 8800 T16&OSN 8800 T32 Mixed)

Subrack
TN5K2AFB Assembly Subrack(OSN 8800 T32)

SSC-DCM-CAGE-D Double-DCM CAGE(ETSI Rack)

Common Unit
TN51PIU Power Interface Board
TN51AUX System Auxiliary Interface Board
TN52SCC01 System Control and Communication Board

TN51ATE Interface Board of Alarm & Timing & Expanding

TN51EFI1 EMI Filter Interface Board


TN51EFI2 EMI Filter Interface Board
TN13FIU01 Fiber Interface Board

TN12SC201 Bi-direction Optical Supervision Channel Board

Multiplexer Unit

40-channel Multiplexing Board(C_


TN11M4001
Even,196.00THz~192.10THz,100GHz,Thermal AWG,LC)

40-channel Demultiplexing Board(C


TN11D4001
Even,196.00THz~192.10THz,100GHz,Thermal AWG,LC)

Amplifier Unit
C-BAND Optical Booster Unit(MAX -3dBm IN and 20dBm
TN12OBU103
OUT,Gain 23dB)
Dispersion Compensation Module

Dispersion Compensation Module,1525~1568nm(compensate


SSE-DCM(A)-C- G.652 fiber),-319~-337ps/nm@1545nm(compensate
652(20km) 20km),<=3.6dB,<=0.1dB,<=0.46ps,LC/UPC Interface,no
fiber,two package

DWDM Transponder
Transponder LSX
10Gbit/s Wavelength Conversion Board
TN13LSX(1*192.10
-10.71G- 10G bit/s wavelength conversion board(1*192.10-10.71G-
40km,1*1310nm-I- 40km,1*1310nm-I-64.1-10km)
64.1-10km)

TN13LSX(1*192.20
-10.71G- 10G bit/s wavelength conversion board(1*192.20-10.71G-
40km,1*1310nm-I- 40km,1*1310nm-I-64.1-10km)
64.1-10km)

Huawei Technologies Pakistan Pvt. Ltd 33


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

TN13LSX(1*192.30
-10.71G- 10G bit/s wavelength conversion board(1*192.30-10.71G-
40km,1*1310nm-I- 40km,1*1310nm-I-64.1-10km)
64.1-10km)

TN13LSX(1*192.40
-10.71G- 10G bit/s wavelength conversion board(1*192.40-10.71G-
40km,1*1310nm-I- 40km,1*1310nm-I-64.1-10km)
64.1-10km)

TN13LSX(1*192.50
-10.71G- 10G bit/s wavelength conversion board(1*192.50-10.71G-
40km,1*1310nm-I- 40km,1*1310nm-I-64.1-10km)
64.1-10km)

TN13LSX(1*192.60
-10.71G- 10G bit/s wavelength conversion board(1*192.60-10.71G-
40km,1*1310nm-I- 40km,1*1310nm-I-64.1-10km)
64.1-10km)
Installation Material
Power Cable

External Cable Set,On-site Processing 25mm^2 Power Cable Pack

External Cable Set 227IEC02(RV),25mm^2(Blue,Black,Red,Yellow/Green)

Wire,450/750V,60227 IEC 02(RV)25mm^2,blue,110A,With a


C1025BL00
package exempted from fumigating(per meter)

Wire,450/750V,60227 IEC 02(RV)25mm^2,black,110A,With a


C1025BK00
package exempted from fumigating(per meter)

Wire,450/750V,60227 IEC 02(RV)25mm^2,yellow


C1025YG00 green,110A,With a package exempted from fumigating(per
meter)

Patch Cord
F000FSL00 Optical Patch Cord(PCS)
Attenuator/Adapter
OFOAPCS00 Fixed Optical Attenuator(PCS)
Software Charge
Quotation & Charge Item Collection
OptiX OSN 8800 T32-Basic Software Package,V100R006 (Per
TN5S0000SW61
Subrack)

1.1.1 14. Installation Quality Check

No. Test Item Specified Value/ Requirement and Observation Test


Test Procedure. /Meas.Value Result
         
1.1 Front door Check door can open/close smoothly □Pass
      □Fail

Huawei Technologies Pakistan Pvt. Ltd 34


HUAWEI TECHNOLOGIES PAKISTAN
PROVISIONAL ACCEPTANCE TEST TEMPLATE
CMPAK 2018 BIDDING PROJECT
Date:__ /__ / _____ Site 4238-OSN9800-NEW-
P Name:__________________

      □NA
       
       
         
1.2 Marks and a) Cables should be marked. □Pass
label
      □Fail
    b) Labels should be stick properly on □NA
cables
       
         
1.3 Alarm a) Normal (green light) □Pass
Indicator
    b) Minor (Light yellow color) □Fail
    c) Major (Orange color) □NA
    d) Critical (Red color)  
         
1.4 Overall Check proper installation, wiring condition, □Pass
installation labeling & tidiness of power system
condition cabinets.
      □Fail
      □NA
Remarks: