P&ID Preparation Procedure
P&ID Preparation Procedure
P&ID Preparation Procedure
PREPARATION PROCEDURE
FOR
For Internal
FORM 552-1 4
DOC. No. REV.
0
SHEET 2 - 43
1. INTRODUCTION .................................................................................................................................. 3
2. GENERAL ............................................................................................................................................. 4
2.1. SHEET SIZE AND TITLE BLOCK ................................................................................................................... 4
2.2. UNIT NUMBER............................................................................................................................................ 4
2.3. CONFIGURATION OF P&IDS ....................................................................................................................... 4
2.4. DRAWING NUMBER OF P&ID ..................................................................................................................... 4
2.5. ARRANGEMENT IN P&ID ............................................................................................................................ 5
2.6. TYPICAL ARRANGEMENT FOR BATTERY LIMIT ........................................................................................... 7
2.7. NUMBERING SYSTEM ................................................................................................................................. 9
2.8. NACE MR0103-2003 APPLICATION ........................................................................................................... 9
2.9. WINTERIZATION ...................................................................................................................................... 10
2.10. OTHERS ............................................................................................................................................... 12
3. PIPING ................................................................................................................................................ 12
3.1. DRAINAGE SYSTEM .................................................................................................................................. 12
3.2. VENT AND DRAIN SYSTEM ........................................................................................................................ 13
3.3. AIR OPERATED VALVE (AOV) HOLD ...................................................................................................... 13
3.4. STEAM-OUT CONNECTION FOR PIPING ...................................................................................................... 15
3.5. TEMPORARY N2 PURGE CONNECTION ...................................................................................................... 15
3.6. UTILITY CONNECTION FOR PERMANENT USE ............................................................................................ 15
3.7. STEAM TRAP ............................................................................................................................................ 16
3.8. LINE CLASS BREAK POINT ....................................................................................................................... 16
3.9. SLOP HEADER (HOLD).............................................................................................................................. 19
3.10. UTILITY STATION ................................................................................................................................. 19
3.11. PIPING SPECIFIED BY “NO POCKET” OR “FREE DRAINING” OR “GRAVITY FLOW” OR “SLOPE” ................. 19
3.12. MISCELLANEOUS.................................................................................................................................. 20
4. INSTRUMENT..................................................................................................................................... 22
4.1. ELECTRIC SIGNAL LINE ........................................................................................................................... 22
4.2. LEVEL INSTRUMENT................................................................................................................................. 22
4.3. PRESSURE AND TEMPERATURE INSTRUMENT ............................................................................................ 23
4.4. PRESSURE DIFFERENCE INDICATOR OF TOWER AND REACTOR .................................................................. 23
4.5. SELECTION FOR DIAPHRAGM TYPE INSTRUMENT ...................................................................................... 23
4.6. CONTROL VALVE ..................................................................................................................................... 24
4.7. EMERGENCY SHUT-OFF VALVE INSTALLATION (HOLD) ............................................................................. 26
4.8. SAFETY RELIEF VALVE ARRANGEMENT ................................................................................................... 27
4.9. TANK BLANKET SYSTEM BY NITROGEN .................................................................................................... 27
4.10. LOCAL SWITCH FOR MOTOR START/STOP ............................................................................................ 28
4.11. BACKUP INSTRUMENT FOR CONTROL LOOP .......................................................................................... 28
4.12. INSTRUMENT REPRESENTATION ........................................................................................................... 28
5. EQUIPMENT ....................................................................................................................................... 28
5.1. EQUIPMENT DESIGN INFORMATION .......................................................................................................... 28
5.2. ISOLATION PHILOSOPHY .......................................................................................................................... 30
5.3. REPRESENTATION OF FLANGE .................................................................................................................. 30
5.4. PRESSURE VESSEL (COLUMN AND DRUM) ................................................................................................. 30
5.5. HEAT EXCHANGER ................................................................................................................................... 31
5.6. AIR COOLED HEAT EXCHANGER .............................................................................................................. 32
5.7. PUMP ....................................................................................................................................................... 33
5.8. COMPRESSOR........................................................................................................................................... 37
5.9. FIRED HEATER......................................................................................................................................... 37
FORM 552-2 4
DOC. No. REV.
0
SHEET 3 - 43
1. INTRODUCTION
This document covers the general criteria and procedures for the preparation and development of both Piping
and Instrument Diagram (hereinafter referred to as P&ID) and Utility Flow Diagrams (hereinafter referred to
as UFD) in ABU Project.
This document describes general rules to draft P&IDs and UFDs, therefore specific items and details in
preparing P&IDs and UFDs of individual units should be confirmed separately from this document.
The units which will be constructed in this project are composed of licensed units and non-licensed units.
However, this document is applied to the only non-licensed unit P&IDs and UFDs which will be prepared by
JGC. For the licensed unit’s P&IDs and UFDs which will be prepared by licensers, this document shall be
applied only when JGC will develop them.
FORM 552-2 4
DOC. No. REV.
0
SHEET 4 - 43
2. GENERAL
- Fluid Name
- Line Size and Class
- Requirement of Insulation and Steam Trace
DWG. No.
Notes:
(1) Legend and General Notes shall be common for all sections.
(2) XXX : Unit Number
FORM 552-2 4
DOC. No. REV.
0
SHEET 5 - 43
(2) The equipment number and service name for each major item shall be placed on the top of the sheet
and directly over the equipment as nearly as practical. The equipment number shall also be shown
alongside the equipment.
(3) P&IDs should have enough space for further detail information which will be provided in later stage.
2.5.2. Line
(1) A process line entering or leaving a unit shall be terminated at the bottom of a sheet with sheet
connection symbol which indicates the fluid name, the source or destination unit & equipment name.
Refer to (a) and (b) on the illustration below.
(2) A process line entering or leaving a sheet shall be terminated at the side of a sheet with sheet
connection symbol. If the process line is going to the sheet with greater drawing number, the process
line shall go to the right, and if it is to a lower drawing number, it shall go to the left. The fluid name,
the source or destination equipment item number and the drawing number on which it is continued
shall be indicated beside the sheet connection symbols. Continuation lines in the same unit between
sheets shall match with the heights from sheet to sheet.
(c)
(3) A utility line which is continued on a UFD may terminate at any convenient location on the sheet, with
a sheet connection symbol.
(4) An instrument signal line entering or leaving a sheet shall be the same manner with the process line
with a sheet connection symbol shown below.
(5) Flow arrow symbols shall be shown to readily indicate the direction of flow.
(6) Main process lines shall be emphasized by bold lines. Unnecessary crossover of lines shall be
avoided as far as possible. If it is unavoidable, horizontal line shall basically take precedence over
vertical line as shown below. However, if the types of the lines in crossover are different, the
following order shall take precedence over the line position.
FORM 552-2 4
DOC. No. REV.
0
SHEET 6 - 43
- Outside of a unit
Fluid Name
From/To Equip. No. XXX : Unit No. (upstream/downstream unit No.)
YYY : Contractor DWG. No. (Serial No.)
XXX-YYY
ABC
ABC : Fluid Identification Code
(UFD DWG. No. will not be indicated.)
XXX-YYY
From Inst. Tag No.
XXX : Unit No. (upstream/downstream unit No.)
YYY : Contractor DWG. No. (Serial No.)
XXX-YYY
To Inst. Tag No.
- Outside Unit
SIGNAL
From/To Inst. No. XXX : Unit No.
YYY : Contractor DWG. No. (Serial No.)
XXX-YYY
FORM 552-2 4
DOC. No. REV.
0
SHEET 7 - 43
Notes:
(*1) 1 inch bleeder shall be provided for the following service:
– VR line
– Flange rating is 1500# and greater
(*2) Butterfly valve to be applied for 6 inches and larger.
- Incoming - Outgoing
PI PI
3/4B 3/4B
B.L. B.L.
Although a local pressure gauge (PI) is shown on the above each illustration, the requirements of
gauges/instruments at B.L should be subject to the followings:
- For process line : Depend on process requirements, any instruments are usually not required.
- For utility line : Refer to Section 2.6.4.
Typical arrangement of double block isolation is as follows. The requirements of instrument at B.L should
FORM 552-2 4
DOC. No. REV.
0
SHEET 8 - 43
- Incoming - Outgoing
Note1
PI PI
3/4B 3/4B
(1) B.L. isolation valves are not required between the integrated process units which are simultaneously
operated at every time and located in the same area.
For example,
– DHU (Unit 445) / NHT (Unit 445)
1-1/2B
FL
3/4B
B.L.
(1) One set of B.L isolation facilities shall be provided at unit header, branched off from the utility
interconnection pipe.
(2) Header isolation valve (root valve) does not have to be provided on branch lines, including
sub-headers.
FORM 552-2 4
DOC. No. REV.
0
SHEET 9 - 43
○ : Required
× : Not Required
The requirement of flow instrument shall be carefully reviewed. If individual users or generators have the
respective flow meter, no flow meter is required on the B.L of process unit.
FORM 552-2 4
DOC. No. REV.
0
SHEET 10 - 43
2.9. Winterization
Winterizing protection shall be considered for the fluid which has higher pour point or solidifying point than
the lowest ambient temperature. Winterizing protection shall be considered based on 1°C of ambient
temperature for this project.
– Bare piping, in which the liquid is likely to coagulate within about 12 hours after stop the liquid
flowing shall be hot insulated.
– Hot insulated lines, in which the liquid is likely to coagulate within about 12 hours after stop of
the liquid flowing, shall be steam traced, even though the liquid operating temperature is high.
– Steam trace is not required for start up lines. Start up lines should be considered that material
in these lines will be evacuated after finishing all of start up operation.
– Every size of piping, except the lines described as above, shall be steam traced and hot
insulated regardless of operating temperature, or be designed No Pocket. Steam purge
connection shall also be provided to empty the inside completely.
Steam trace is not required because winterizing protection should be considered based on 1 deg C of
ambient temp.
– Normally no flowing lines such as instrument lead piping and control valve bypass line shall be
steam traced. Hot insulation and steam trace for winterization is not required on inlet piping
of relief valve, because free draining piping layout to suction vessel is usually applied to.
– Due to the existence of chloride in CCR Regeneration section, heavy duty steam trace shall be
provided for dead space for instruments. Since these lines will be provided at high position
where low pressure steam could condensed, special pressure for steam trace shall be
considered.
Hot insulation and steam trace provided for winterization shall be clearly distinguished from them which are
provided by process requirements in P&IDs.
FORM 552-2 4
DOC. No. REV.
0
SHEET 11 - 43
PI FI
PG PT FT
PI
PG PT
LG
LT LI LT LI
LG
The instrument located on the steam traced line to prevent condensation problem such as reciprocating
compressor inlet and fuel gas does not need to be provided with the steam trace.
Steam trace should be applied to the line up to the Steam trace should be applied to the line,
first valve up to the connection point.
FORM 552-2 4
DOC. No. REV.
0
SHEET 12 - 43
2.10. Others
3. PIPING
Plot plan will be divided into two parts, Block-I (Bottom) and Block-II (Aroma). In Block-I, closed drain
lines will be provided in the only limited area, while most of the area will be covered by closed drain lines in
Block-II. However, drainage system will not be required for the area which are relating to lighter material
than C5.
Closed drain and open drain connections shall be represented on P&ID as follows:
3/4B
The drip funnel shall be indicated on P&ID, when drainage shall be led to the oily sewer water.
The underground piping for the closed drain shall be sloped minimum 1/500 and slop symbol shall be
indicated in P&ID.
FORM 552-2 4
DOC. No. REV.
0
SHEET 13 - 43
P&ID symbol shall be followed P&ID of Legend and General Notes (6/7), D-000-1225-106
(1) For 150# and 300#, AOV shall be provided for the suction and discharge valves, if the valve size is
equal to or greater than 8 inches.
(2) For 600# and larger, AOV shall be provided for the suction and discharge valves, if the valve size is
equal to or greater than 6 inches.
(3) AOV shall be provided for the suction valve, if the pump is operated at 200˚C and larger and
“Evaluation for Pump Mechanical Seal Failure” calculated according to the Table 3.2 is over 16
points and larger.
HS
Hold for this section until discussing with client.
A IA
FORM 552-2 4
DOC. No. REV.
0
SHEET 14 - 43
1. Factor for heat of combustion ---(F) (Note 1) Note 1) The following factor
F = HL[kJ/kg] / 4200 (F) = can be selected as (F).
If pump can handle several
2. Operating Condition materials, Total Point shall
A. Operating temperature base factor be calculated for each
a. Over Flash Point 10 material and select the
b. Boiling Point 20 higher value.
c. Over 10 vol% of LPG 20
d. Over 200 deg C 25*f Material (F)
(f = Ope temp/200) Crude 10.5
Selected Factor (OT) = Light Nap. 10.8
(Select one factor from a to d) Heavy Nap. 10.6
Kerosine 10.5
B. Operating Pressure base factor LGO 10.4
a. -0.05MPa and lower (Column Press) 10 LCO 10.3
b. 0.15MPa and larger (Pump Suc Press) 5 HGO 10.3
c. 0.5MPa and larger (Pump Suc Press) 10 HCO 10.1
d. 1.0MPa and larger (Pump Suc Press) 20 SLO 10
Selected factor (OP) = RT 10
(Select one factor from a to d) DDS-P 10
RMT 10.7
C. Pump Suction Size base factor Gasoline 10.8
a. 8 inches and larger 5 C2+C3 11.4
b. 10 inches and larger 10 C3 11.3
c. 12 inches and larger 15 C4 11.2
d. 14 inches and larger 20
Selected factor (S) =
(Select one factor from a to d)
FORM 552-2 4
DOC. No. REV.
0
SHEET 15 - 43
3.4.1. Arrangements
The typical configulation of steam out connection is as follows :
1-1/2B 1"
MPS
3/4B
Optimum location of those purge connection shall be reviewed by piping engineer in consideration of the
actual piping layout.
N2 purge shall be applied to the systems which will not be allowed steam-out by process and mechanical
reasons.
An actual piping arrangement is almost same as the steam-out connection. N2 connection size is
normally used 1 inch but larger size has to be installed based on the estimation from the volume and
required pressurizing speed.
1B 1"
N2
3/4B
N2 IW MPS
1B 1-1/2B 1-1/2B
1-1/2B
1"
3/4B
3/4B
FORM 552-2 4
DOC. No. REV.
0
SHEET 16 - 43
Steam trap which is essential from the process requirements shall be specified by process engineer. They
are as follows:
– Turbine inlet
– Stripping steam to tower
– Heat exchanger outlet (Steam reboiler or steam header, etc. if required)
– Smokeless steam for Flare
– End of steam header
The other steam traps, such as steam header drain or low point drain, shall be specified by piping engineer
and not indicated in P&ID.
(1) The line class break point shall be at the final valve, if class break is required.
(2) Line class break point around control valve shall be at the bypass and block valve.
(3) For the product run down line, Unit Battery valves should be considered the valves are always
opened while Unit is operating. And the isolation valves for storage tanks should be considered
at least one rundown routing is always maintained while Unit is operating. Therefore, the line
class break is specified at the downstream of control vale at rundown line in Inside of Battery
Limit.
(4) If new line is connected the existing line, class break point will be determined, considering design
condition of the existing line.
(5) High line class due to the tube rupture of S/T type heat exchanger shall be applied to up to the
upstream and downstream first valves of the heat exchanger. Refer to the typical example below.
(6) Class break around pump should be as follows:
– If pump discharge line class is 600# and smaller, pump discharge class shall be
applied to up to the pump suction valve, when a spare pump is installed.
– If pump discharge line class is 900# and greater, pump suction line class should be
decided by upstream condition. Since pump mechanical seal can not withstand for
significant high pressure, safety relief valve should be provided for pump suction.
(7) For the licensed unit, line class break point shall be subject to the licenser’s instructions.
(8) Project Engineer will specify the break point, based on the applicable code.
- Control Valve
FORM 552-2 4
DOC. No. REV.
0
SHEET 17 - 43
SV
CSO
To Flare Header
Low Grade
1-1/2B
CSO
High Grade
1-1/2B
- Utility Connection
When Process
class is higher than
Utility class
Low Grade High Grade
Process Line
Utility from
header
FORM 552-2 4
DOC. No. REV.
0
SHEET 18 - 43
- Pump Suction
A B
M M
- Line Class governed by Tube Rupture of Heat Exchanger (line class of low pressure side shall be
upgraded by 10/13 rule application)
High
Pressure Side
10/13 rule shall be applied to the inlet and outlet nozzles and its companion flange.
- Line Junction
FORM 552-2 4
DOC. No. REV.
0
SHEET 19 - 43
M Low Grade M
Low Head High Grade Low Head
Pump Pump
A A
M M
High Head * Install check valve
High Head
Pump Pump
The line up of individual slop headers shall be considered, including the following concepts:
600# 300# 150#
CLASS CLASS CLASS
Unit Common
Class
break 3/4B 3/4B 3/4B CSO Slop Tank
3.11. Piping specified by “No Pocket” or “Free Draining” or “Gravity Flow” or “Slope”
For the piping layout for the captioned definition, refer to P&ID of Legend and General Notes (1/7),
D-000-1225-101.
FORM 552-2 4
DOC. No. REV.
0
SHEET 20 - 43
3.12. Miscellaneous
(1) Typical vent and drain size for piping shall be 3/4”, unless otherwise specified.
(2) When a valve is CS and its size is 1-1/2” or less, welding connection should be applied, while the
flange connection is applied for 2” and above. For alloy valves, whose rating is equal to or
greater than 900#, typical connection shall be by flange regardless of its size.
(3) For 1500# and greater, all of valves, including control valves, will be butt welded, regardless of
size, material, or valve type.
(4) “Min.” shall be indicated on P&ID for the following points to minimize the pipe dead end:
(5) For the lines in which two phases fluid flows and vapor pocket is not avoidable, show “Two Phase
Flow” on P&ID to provide against vibration problem and flow measurement.
(6) Weep hole shall be provided at low points in discharge line of safety relief valve, rupture disc and
silencer discharging to atmosphere. The hole diameter is 9mm and indicate “9MM WH.”
(8) Show “free drain and minimum” at the outlet line of tower feed control valve, where vibration
expects due to flash & slug.
Note “X”
Free Draining
Min.
FORM 552-2 4
DOC. No. REV.
0
SHEET 21 - 43
(9) Indicate “Symmetrical Piping” for the exchangers, which have two nozzles.
Symmetrical Piping
(10) Free draining requirement is not necessary for the non condensable gas (e.g. nitrogen) line at the
upstream of the pressure control valve, when a check valve is provided at the downstream of
control valve.
(*1)
N2 Flare
(11) When the reactor inlet line is connected on the top MH, indicate elbow connection instead of spool
piece.
S.P
(12) Flange rating shall be indicated, if nozzle rating and connecting line class is different, such as all
the nozzles in 1-1/2” and smaller connected to equipment shall be min 300# rating, even if the
equipment rating is 150#.
(13) Manual drain valves for the water boot containing LPG should be arranged to have gate and globe
valves with minimum 600 mm distance between both valves.
LPG
MIN. 600MM
(14) Side cut draw off line from column tray shall drop vertically at least 3,000mm below bottom of
draw off nozzle, before the diameter reduction and/or horizontal run.
FORM 552-2 4
DOC. No. REV.
0
SHEET 22 - 43
Min. 3000mm
(15) Personnel protection shall be provided on operating equipment when the stream temperature is 70
deg C and greater.
4. INSTRUMENT
(1) As a general rule, independent connections shall be provided for the level gauge, level controller
and level switch. Their nozzle sizes are as follows:
(2) Standpipe is provided only for installation of multiple LGs, and its size is 2B and 300# minimum.
(rating Hold) Level transmitter may share the same standpipe with level gauge, while level
transmitter or switch incorporated into emergency shut down system shall have independent direct
connection on vessel.
(4) Indicate level gauge type beside LG balloon, based on the following criteria:
(5) For level instrument for amine sump tank, vertical displacer type (top mount internal) level
instrument shall be provided on amine sump tanks located at underground. The size of the
displacer connection is 4 inches. Refer to section 5.7.3.
(6) For level instrument for Tanks of Water, Caustic and Amine Solution, use the direct mount
differential type level indicator with 3 inches diaphragm connection. Typical representation is as
follows:
FORM 552-2 4
DOC. No. REV.
0
SHEET 23 - 43
3“ LI
LT
(7) Upper side isolation valve for level instruments is not required, when vessel is open to atmosphere.
ATM
Valve is not required.
LT LG
Pressure Thermowell
– Non cladding 1” 1-1/2”
– Cladding 2” 2”
For piping, the following size will be used but not required to indicate in P & ID.
– Pressure 3/4”
– Temperature 1-1/2”
For pressure drop measurement of the full liquid reactor, strainer and treater, locate PDT meter at grade.
Delete free drain and slope requirement for full liquid service.
FORM 552-2 4
DOC. No. REV.
0
SHEET 24 - 43
– FC : failure to close
– FO : failure to open
– FLC : failure lock (last position tend to close )
– FLO : failure lock (last position tend to open )
4.6.2. CV Arrangement
Typical CV arrangement is shown below:
A drain valve (size 3/4 inches) shall be installed at the inlet of control valve. However, the control
valves with bypass which possibly cokes deposit in the valve or handle seriously hazardous fluids, shall
be installed at both inlet and outlet. They are listed as follows:
(2) Valve Size Refer to the Table 4.1, Criteria for Valve Size of both Block and Bypass
FORM 552-2 4
DOC. No. REV.
0
SHEET 25 - 43
Table 4.1 Criteria for Valve Size of both Block and Bypass (CES-I-501-02)
(Unit: Inches)
Control Valve Type of Line size
Size (Inch) Valve 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20
Block 1/2 3/4 1 1-1/2
1/2
Bypass 1/2 3/4 1 1
Block 3/4 1 1-1/2 2
3/4
Bypass 3/4 1 1 1
Block 1 1-1/2 2 3
1
Bypass 1 1-1/2 1-1/2 1-1/2
Block 1-1/2 2 2
1-1/2
Bypass 1-1/2 2 2
Block 2 3 3
2
Bypass 2 3 3
Block 3 4 4
3
Bypass 3 4 4
Block 4 6 6
4
Bypass 4 6 6
Block 6 8 8
6
Bypass 6 8 8
Block 8 10 10
8
Bypass 8 10 10
Block 10 12 12
10
Bypass 10 12 12
Block 12 14 14
12
Bypass 12 14 14
Block 14 16 16
14
Bypass 14 16 16
Block 16 18 18
16
Bypass 16 18 18
FORM 552-2 4
DOC. No. REV.
0
SHEET 26 - 43
In addition to the licenser’s standard practice, Emergency Shut-off Valves (ESV) should be provided at
the following locations for the safety purpose:
Typical arrangements shall be followed on P&ID of Legend and General Notes (4/7), D-000-1225-104.
FORM 552-2 4
DOC. No. REV.
0
SHEET 27 - 43
SV
CSO
To Flare Header
3/4B
1-1/2B
CSO
3/4B
1-1/2B
(1) SV sub-header may be provided when many SV are required at a service location.
(2) It shall be considered that SV are located on the vapor outlet line rather than direct mounting on
the vessel. Outlet vapor line size shall be reviewed with reference to API RP 521 criteria.
(3) Block valves (with CSO facilities) and bypass valves shall be provided for all SV installed to
protect pressure vessels and connected to flare header.
(4) 3/4 inches of bleed connections shall be provided on inlet and outlet line between the block valve
and SV. Bleed connection is not required for thermal relief valves provided on the lines.
(5) Discharge piping to the atmosphere shall have a 9mm diameter weep hole at the low point and
have no block valve on the discharge line.
(6) Set pressure shall be indicated adjacent to the SV. If SV is located high point of the full liquid
service, the set pressure shall be verified by taking account of the liquid head.
(7) If the bypass line is used for vessel vent, its size shall be the same as the vessel vent. Minimum
bypass line size is smaller of 1-1/2 inches or SV discharge line size.
(8) Spare SV is not necessary to be installed on stream.
(9) For the water coolers, SV is not required for cooling water line because CSO is specified for the
outlet valve on cooling water return line.
(4) Thermal Relief Valves are not required for the following case:
– Spare standby equipment is provided with SV
– The protected equipment is operated intermittently
– The protected equipment is considered to be isolated, then drained out immediately, when the
equipment is out of service.
FORM 552-2 4
DOC. No. REV.
0
SHEET 28 - 43
PG
Free Draining
PCV
Free Draining
N2
TI
SKIN
5. Equipment
5.1. Equipment Design Information
The design information for major equipment to be indicated on P&ID and UFD shall be as follows:
(2) Tanks
– Item No.
– Service Name
– Diameter x Height/ Length
– Storage Capacity (M3)
– Code
FORM 552-2 4
DOC. No. REV.
0
SHEET 29 - 43
(6) Compressors
– Item No.
– Service Name
– Type
– Design Capacity (NM3/Hr)
– Suction Pressure / Discharge Pressure
– Motor (kW) / Turbine (rpm)
– Code
(7) Pumps
– Item No.
– Service Name
– Type
– Design Capacity
– Suction Pressure / Discharge Pressure
– Motor (kW) / Turbine (rpm)
– Code
FORM 552-2 4
DOC. No. REV.
0
SHEET 30 - 43
Valves and spectacle blinds are not necessary for equipment isolation but temporary blinds shall be used.
Temporary blinds are not shown on P&ID.
If steam injection line is provided for the column, such as stripping steam, additional steamout nozzle is
not required.
5.4.5. Elevation
Elevation shall be shown in P&IDs/UFDs.
Skirt mark does not have to be indicated in P&ID/UFD, but the minimum required distance between the
base line and tangential line of the vessel shall be shown as follows:
FORM 552-2 4
DOC. No. REV.
0
SHEET 31 - 43
XXX
Min.
XXX
Min.
XXX
Min.
(Base Line) (Base Line)
CWS valve for water cooler 2 inches and smaller Gate valve
3 inches and larger Butterfly valve
CWR valve for water cooler 6 inches and smaller Globe valve
8 inches and larger Butterfly valve
FORM 552-2 4
DOC. No. REV.
0
SHEET 32 - 43
1B
1B
1”
FIC
Steam
FT
FV
Min 1500mm
Condensate
FORM 552-2 4
DOC. No. REV.
0
SHEET 33 - 43
TY
TC
VSH VSH
M M
DI DI
Hold
VAH VAH
TC
TV
M M
DI DI
5.7. Pump
5.7.1. Centrifugal Type
(1) Suction valve size shall be the same as the line, however, if pump suction nozzle is two or more
sizes smaller than the suction line, the valve may be specified one size larger than pump nozzle.
(2) Discharge valve shall be the same as the line, however, if the discharge line size is 8 inches and
larger and pump discharge nozzle is two or more size smaller then discharge line, check valve and
block valve may be specified one size smaller than line.
(3) Pressure Instrument
a. A local pressure gauge (PI) shall be installed on both pump suction and discharge lines of all
pumps.
b. A local or DCS PDI across a suction strainer shall be provided according to the licensor’s
instruction.
(4) Warm-up Line
a. Warm-up Line is installed when the fluid temperature is higher than 150 oC or when the fluid
FORM 552-2 4
DOC. No. REV.
0
SHEET 34 - 43
3/4”
PG PG RO
DI
M
PG PG PG PG
A B
DI DI
M M
Note : Signals of the respective switch to dictate trouble are transferred by DCS system, but one common
trouble alarm is shown on the DCS display.
FORM 552-2 4
DOC. No. REV.
0
SHEET 35 - 43
PG PG PG PG
A B
DI DI
M M
If licenser specifies the arrangements around LPG pump, the provisions for highly volatile liquid
shall be followed. 1” pressure equalizing line to the suction vessel shall be provided, even if
licenser does not specify.
Free Draining
1-1/2”
MPS
Vent to Flare
*2 *2
1” 1”
*2 *2
1” 3/4” 1” 3/4”
PG *1 PG PG *1 PG
3/4” 3/4”
A B
DI DI
M M
*1 Utility connection
*2 Provide Approximately min.
600mm distance between both valves
(center to center)
FORM 552-2 4
DOC. No. REV.
0
SHEET 36 - 43
Typical arrangements for the pump handling the heavy oil with high pour point, such as gas oil
and heavier, are indicated in the Attachment-2.
PG
Vendor’s
Chemical Supply M
System
DI
FORM 552-2 4
DOC. No. REV.
0
SHEET 37 - 43
LT LI
DI
M 4” 15mmφ
Vent Hole
5.8. Compressor
5.8.1. Centrifugal Type
(1) Suction strainer
Temporary strainers shall be supplied by compressor vendor in all compressor suction lines and as close
to the compressor as practical.
FORM 552-2 4
DOC. No. REV.
0
SHEET 38 - 43
FORM 552-2 4