INTERNAL TEST REPORT

Page 1 of 2
W.O. No. : C-2899 T.R. No : BD/QC/C-2899/2021

Date : 18.06.2021

Customer/Project : M/s COBRA, SPAIN


MARLIM AZUL 565 MW CC EPC PROJECT, BRAZIL
Project No. : C-2899

Material Equipment Tested : 22 Kv. 17967A. IPB - MAIN RUN / 22kV. 935A. IPB – TAP-OFF RUN

Description of Sample(s) : Same As Above

No. of Samples Tested : 27 ELEMENTS

Applicable Specification : ANSI / IEEE C37.23

Reference Drawing : GA – C-2899-1120-29145 REV-02, LAYOUT – C-2899-1120-29154 REV-04


EKD – C-2899-1120-29162 REV-01, TERMINATION – C-2899-1120-29155 REV-04

Tests Conducted : (01) One Minute Dry Power Frequency Voltage Test Withstand At 60 kV (rms).
: (02) Insulation Resistance Measurement Test.

Test Procedure : As Per ANSI / IEEE C37.23

Test Results : (01) All elements Withstood at 60 kV. (rms) for one minute between phase and earth.

: (02) I.R value measured with 5000 V meggar before & after HV test, The value
found more than 250 G ohms.

Remarks : Above elements are also checked for visual,dimension,marking,electrical clearances,


: painting(shade,finish,adhesion ) & general arrangement and found to be in order.

Test Engineer (QA) AGM – QA


C&S Electric Ltd. C&S Electric Ltd.

C & S Electric Ltd .


Plot No.1C , Sector 8C , IIE ( Integrated Industrial Estate ) Ranipur Haridwar ( Uttrakhand )-2412933
Regd. Office : 222, Okhla Industrial Estate,
NEW DELHI - 110020

QAFQC : 07
REV-00
INTERNAL INSPECTION REPORT
Page 2 of 2
Ref. : BD / QC / C-2899 / IPBD / IR 01 Date of Inspection : 18.06.2021

Order No. : C-2899 Customer : M/s COBRA, SPAIN

Project : MARLIM AZUL 565 MW CC EPC PROJECT, BRAZIL

Specified Value Observed Value


Sl. No. Description Quantum of check Result Code
( mm) (mm)
A-1 Main Run For 22 KV, 17967A. IPBD
1 Enclosure Sheet Thickness ( AL ) Sample 9 9 A
2 Diameter of Enclosure 100% 1120 1120 A
3 Conductor Sheet Thickness (AL) 100% 11 11 A
4 Diameter of Conductor (AL) 100% 650 650 A
2 U PHASE (Length Main Run = 27 ELEMENTS)
2.1 IPM8U 100% 3695+685 3695+685 A

2.2 IPM9U 100% 4180+685 4180+685 A

2.3 IPM10U 100% 9880 9880 A

2.4 IPM11U 100% 10120+685 10120+685 A

2.5 IPM12U 100% 4810 4810 A

2.6 IPM13U 100% 10120 10120 A

2.7 IPM14U 100% 10120 10120 A

2.8 IPM15U 100% 10120+685 10120+685 A

2.9 IPM16U 100% 685+2124 685+2124 A

V PHASE
2.10 IPM8V 100% 3695+685 3695+685 A

2.11 IPM9V 100% 2480+685 2480+685 A

2.12 IPM10V 100% 8180 8180 A

2.13 IPM11V 100% 10120+685 10120+685 A

2.14 IPM12V 100% 4810 4810 A

2.15 IPM13V 100% 10120 10120 A

2.16 IPM14V 100% 10120 10120 A

2.17 IPM15V 100% 10120+685 10120+685 A

2.18 IPM16V 100% 685+2124 685+2124 A

W PHASE
2.19 IPM8W 100% 3695+685 3695+685 A

2.20 IPM9W 100% 780+685 780+685 A

2.21 IPM10W 100% 6480 6480 A

2.22 IPM11W 100% 10120+685 10120+685 A

2.23 IPM12W 100% 4810 4810 A

2.24 IPM13W 100% 10120 10120 A

2.25 IPM14W 100% 10120 10120 A

2.26 IPM15W 100% 10120+685 10120+685 A

2.27 IPM16W 100% 685+2124 685+2124 A


EXTERIOR- RAL- 7035 &
3 Paint Shade for Enclosure 100% Found OK A
INTERIOR - MATT BLACK
3.1 Paint Thickness (DFT) Random Min. 50 microns > 50 Microns A

3.2 Paint Adhesion Test & Surface finish Random No peel off Found OK A

4 Cutting of Material 100% As per fab. Drawings Found OK A

5 Rolling of Material 100% As per fab. Drawings Found OK A

6 Busbar Mounting Arrangement 100% As per Approved Drawings Found OK A

7 Identification Marking 100% Found OK. A

8 Sequential Operation Test 100% As per Approved Drawings Found OK A


Result Code :

A : Accepted ü Test Engineer QA AGM - QA


AD : Accepted with Deviation C&S Electric Ltd. C&S Electric Ltd.
RW : Rework
R : Reject
QAF : QC : 04
Rev. 01