Technical Specification: Ection
Technical Specification: Ection
Technical Specification: Ection
SECTION 07
TECHNICAL SPECIFICATIONS OF
16/20mva_x-former_spc_ajgar_design2 1
7.0 Technical Specification of 33/11 KV, 16/20 MVA Power Transformer
7.1 GENERAL
This section of the document includes the design, manufacture, testing & inspection of
33/11KV, 16/20 MVA, Power transformers as specified.
The information is given solely as a guide for Tenders and no responsibility for its, accuracy
will be accepted nor will any claim based on the above be entertained.
Transformer supplied under this contract will be installed in tropical locations that can be
considered hostile to its proper operation. Particular problems that shall receive special
consideration relate to operation in a hot environment and presence of the insects and vermin.
7.4 STANDARDS
The equipment specified in this Section of the contract shall conform to the latest edition of the appropriate
IEC specifications and other recognized international standard. In particular:
On Load Tap changer with motor drive unit MR, Germany/ABB, Sweden
manufacturer’s name & country
Tapping Range :
a) HT 17 Tapping ± 10% in steps of 1.25% i.e. 33 KV ± 8 x
1.25%
b) LT Nill
31. Bushing CT for differential protection 400/5A on HV, 1200/5A on LV of accuracy class
5P20, burden 20 VA.
32. Neutral Bushing CT for Standby Earth Fault (SEF) 1200/5-5A on LV neutral of accuracy class 5P20,
& Restricted Earth Fault (REF) protection burden 20 VA.
d) Satisfactory Performance certificates (SPC) issued within the last 5 years from at
least 2 End users depicting that the offered type 33/11kV, 16/20 MVA Power
Transformers or higher MVA rating of same voltage class, has been in service for
at least 3 years. End user must be an Electricity Utility Service.
e) Guaranteed Technical Particulars (GTP) shall be properly filled up with submission
of related supporting documents & signed by the Manufacturer & Tenderer.
f) Outline and General Arrangement drawings of the offered type Power Transformer.
g) Cross-section Drawing showing the arrangement of core and windings of the
offered type Transformer.
h) Manufacturer’s Printed Catalogue describing specification and technical data for
crucial components (i.e. Bushings, OLTC, PRD, Buchholz, Dial type Temp. Meters,
etc.) of offered type equipment.
i) Submission of Special & Type Test Reports as stated in Clause 7.8.2. & 7.8.3. and
GTP, as per relevant IEC or other equivalent Standards from KEMA, Netherlands;
CESI, Italy; CPRI, India; China National Transformer Quality Supervision Testing
Center (CTQC), China; China Electric Power Research Institute (CEPRI), China;
BRTC, BUET..
j) Bidder shall declare guaranteed No Load Loss and Full Load Loss value in GTP.
Any Tenderer quoted the No Load Loss & Full Load Loss above the upper limit of
the loss as mentioned in GTP (Section 8, Clause 8.01, Sl No.3.9) in Tender
Document will not be considered for further evaluation & treated as non-
responsive. The Tenderer who will quote the No Load Loss & Full Load Loss below
the lower limit of No Load Loss & Full Load Loss as mentioned in GTP (Section 8,
Clause 8.01, Sl No.3.9) In that case during evaluation Capitalization cost will be
calculated only on the basis of the lower limit of No Load Loss & Full Load Loss.
Their quoted loss will not be considered for evaluation of capitalization cost.
Tenderer who quoted No Load Loss & Full Load Loss do not support with loss
calculation & type test report will also be treated as non- responsive.
k) Bidders declared/ guaranteed Percentage Impedance value shall be within the
specified value.
L) Local manufacturers, who have supplied the same offered item to BPDB within
the last 5 (five) years from the date of opening, need not to submit any Manufacturer's
Supply Record, Satisfactory Performance Certificate & Type Test report with the
tender proposal. In that case, they have to submit Satisfactory Performance Certificate
(taken at a date after the tender invitation) from Director, Purchase, BPDB, Dhaka, for
the same offered item.
16/20 mva x-former_spec & gtp_ajgar_design2 6
7.8 TEST REPORTS:
The following test reports/certificates including their test results for the routine and type
tests prescribed in "relevant IEC Standard" for the offered type rating transformer of
same voltage Class are to be furnished with the Bid, otherwise the bid will be treated
as non-responsive and will not consider for further evaluation.
7.8.1 ROUTINE TESTS
a) Measurement of insulation resistance.
b) Measurement of Voltage ratio test.
c) Measurement of winding resistance at Each Tap position.
d) Vector group test.
e) Measurement of no-load loss & current.
f) Measurement of short circuit impedance and load loss.
g) Power frequency (Separate source voltage) withstands test.
h) Transformer oil test.
7.8.2 TYPE TESTS
a) Temperature Rise Test
b) Lightning Impulse Test
7.8.3 SPECIAL TESTS
a) Short circuit withstands test report of HV-LV.
Note:
l) Type Tests and Special Tests Reports as per relevant IEC shall be submitted from KEMA,
Netherlands; CESI, Italy; CPRI, India; China National Transformer Quality Supervision Testing Center
(CTQC), China; China Electric Power Research Institute (CEPRI), China; BRTC, BUET. otherwise
the bid will be rejected. Evidences of accredited laboratory are to be submitted with the bid.
The design of the magnetic circuit shall be such as to avoid static discharge development of short circuit
paths internally or to the earthed clamping structure and the production of flux components normal to the
plane of the laminations. Each lamination shall be insulated with a material stable under the action of
pressure and hot oil.
16/20 mva x-former_spec & gtp_ajgar_design2 8
The winding structure and major insulation shall be designed to permit an unobstructed flow of cooling oil
through core cooling oil ducts to ensure efficient core cooling.
The magnetic circuit shall be insulated from all structural parts and shall be capable of withstanding a test
voltage to core bolts and to the frame of 2000 volts rms for one minute.
Cores shall constructed from clod rolled grain oriented steel sheets. Provided the contractor can provide
adequate evidence that there will be no adverse effects due to stray flux heating of core with the quality of
steel employed, designs may be offered such that when operating under the most onerous conditions, flux
density in any part of the magnetic circuit does not exceed 1.7 Tesla.
The Contractor shall determine the operating conditions under which the maximum flux density will be
attained within the following simultaneously applied limits.
- Frequency : 50 Hz
- LV and HV Voltage : Up to but not exceeding the specified maximum System voltage.
- Load : The transformer may be subjected to intermittent overloading of 150%
rated MVA at 0.8 power factor lagging in accordance with IEC-60035.
The maximum flux densities anticipated under these conditions are to be stated in Technical Schedules
(GTP).
7.19 WINDINGS:
The transformer windings shall have uniform insulation as defined in the latest revision of IEC standard.
The transformers shall be designed to withstand the impulse voltage levels and the power frequency
voltage tests specified in the Technical Schedules.
The winding shall be located in a manner which will ensure and that they remain Electro-statically
balanced and that their magnetic centers remain coincident under all conditions of operation.
The winding shall also be thoroughly seasoned during manufacture by the application of axial pressure at
a high temperature for such length of time as will ensure that further shrinkage is unlikely to occur in
service.
All electrical connections within windings shall be brazed to withstand the shocks, which may occur
through rough handling and vibration during transport switching and other transient service conditions.
Coil clamping rings shall be of the on on-magnetic steel or insulating materials built up from flat
laminations. Auxiliary laminated material other then Bakelite paper is not to be used.
Where Bakelite paper rings are used with the layers of paper lying in the axial direction, the rings may be
relied upon to provide the major insulation between the windings and frame subject to there being
adequate creepage distance.
Any metal pieces in contact with laminated rings shall be designed and secured so that they do not
weaken the electrical or the mechanical properties of the rings.
If the winding is built up of section or of disc-coils separated by spacers, the clamping arrangement shall
be ensure that equal pressure are applied to all columns of spacers.
All metal parts of the transformer with the exception of the individual core lamination, core bolts
and associated individual clamping plates, shall be maintained at some fixed potential.
The top main core clamping structure shall be connected to the tank body by a copper strap and the
bottom main core clamping structure shall be earthen by one or more of the following methods:
- by connection through vertical tie rods to the top structure.
- by direct metal-to-metal contact with the tank base maintained by the weight of the core and
windings.
- by connection to the top structure on the same side of the core as the main earth connection to
the tank.
The magnetic circuit shall be earthed to the clamping structure at one point through a removable link
placed in an accessible position just beneath an inspection opening in the tank cover and which, by
disconnection, will enable the insulation between the core and clamping plates, etc. to be tested at
voltages up to 2 KV for the purpose of checking deterioration during service. The connection to the link
shall be on the same side of the core as the main earth connection. These requirements are mandatory.
16/20 mva x-former_spec & gtp_ajgar_design2 9
Magnetic circuits having an insulated sectional construction shall be provided with a separate link for each
individual section and the arrangement of the connections shall be subject to the approval of the
Engineer.
Where oil ducts or insulated barriers parallel to the plane the laminations divide the magnetic circuits into
two or more electrically separates parts, the ducts and insolating barriers which have the thickness
greater than 0.25, mm are to be bridged with tinned copper strips so inserted as to maintain electrical
continuity.
Where coil-clamping rings are of metal at each potential, each rings shall be connected to the adjacent
core clamping structure on the same side of the transformer as the main earthing connection.
Main earthing connections shall be a cross-sectional area of not less than 100mm2 but connections
inserted between laminations may have cross sectional areas reduced 20mm2 when in close thermal
contact with the core.
7.22 OIL
All transformers shall be filled to the required level with new, unused, clean, standard mineral oil after
treatment in compliance with IEC 60296 & BS 148.
7.23 GASKETS
Any gaskets provided with the transformers shall be suitable for making oil tight joints, and there shall be
no deleterious effects of either gaskets or oil when the gaskets are continuously in contact with hot oil. No
gaskets shall be used in which the material of the material of the gasket is mounted on a textile backing.
Exterior gaskets shall be weatherproof and shall not be affected by strong sunlight.
7.24 EVALUATION CRITERIA
a) The Tenders will be evaluated on the basis of the capitalized cost of the Transformer losses.
b) Bidder will declared/ guaranteed No-Load loss and Full load loss value, otherwise the bid will be
rejected.
c) Bidders declared/ guaranteed percentage impedance value shall be within the specified value,
otherwise the bid will be rejected.
%MT (Percentage of Monetized Transformer) = % of the Monetized Transformer found during factory test witness
by BPDB's inspection team whose measured loss(s) (No load loss or Full load loss or Both) exceed the offered
loss (No load loss or Full load loss or Both) but remain within acceptable limit. For example : If total no. of
transformers to be inspected is 80 and the no. of selected transformers during QAT/pre-delivery inspection is 8, 6
nos. are found within the offered losses and 2 nos. are found exceeding the offered losses then the %MT will be
(2/8)x100=25%
* 1Measured Average No Load Loss = [Sum of the measured No-load losses of the tested
transformer(s) exceeding the offered No-load loss ÷ Nos.
of tested transformer(s) which exceeds the offered No-
load loss]
* 2Measured Average Full Load Loss = [Sum of the measured Full-load losses of the tested
transformer(s) which exceeding the offered Full-load loss
÷ Nos. of tested transformer(s) which exceeds the offered
Full-load loss
The purchaser can carryout the testing of any no. of transformers during Quality Test Witness. But, the
testing of transformers during Quality Test Witness will not be less than 10% at random basisofthe
transformer ready for inspection but in any case it will not be less than 3 nos. The manufacturer will
provide all arrangements for the testing of transformers desired by the purchaser in his factory.
The Supplier shall, after consulting the purchaser, give the Purchaser reasonable notice in writing of the
date on and the place at which any material or equipment will be ready for testing as provided in the
contract and unless the purchaser shall attend at the place so named on date, which the supplier has
stated in his notice, the supplier may proceed with the tests, which shall be deemed to have been made in
the purchaser’s presence, and shall forth with forward to the purchaser duly certified copies of test
readings.
When the purchaser intends to attend the test he shall promptly inform the supplier accordingly in writing,
so that he can take action. The purchaser shall give the supplier timely notice in writing of his intention to
attend the test.
Where the supplier provides for tests on the premises of the supplier or of any manufacturer of the
supplier, except where otherwise specified, shall provide free of charge such assistance, labor, materials,
electricity, fuel, stores, apparatus and instruments as may be requisite and as may be reasonably
demanded to carry out such test efficiently. These test shall be performed as per relevant IEC/BS
Standard or equivalent and only routine tests as agreed upon, will be performed.
As and when the purchaser is satisfied that any materials/equipment shall have passes the tests referred
to in this clause, purchaser shall notify the contractor in writing to that effect.
Should any inspected/tested goods fail to conform to the specification, the Purchaser shall have the right
to reject any of the item or complete batch if necessary. In that case Supplier have to replace the
Equipment and to make good of them without any financial involvement to the Purchaser. In case any of
the Equipment found not conforming with the specification at the time of post landing Inspection, the
supplier will in no way be relieved from the responsibility of replacing them on making them good at their
own cost, despite the Equipment were found good at the time of Factory Acceptance Test. Nothing in this
clause shall in any way release the supplier from any warranty or other obligations under the contract.
BPDB’s Inspection Team of at least 03(Three) Engineers shall have to conduct Technical Orientation
and Quality Test Witness at the manufacturer’s factory premises. The cost incurred for this purpose shall
be borne by the contractor and shall be deemed the cost in this regard is included in the offered price.
Post landing inspection shall be done immediately after arrival of the goods/materials at the designated
store of BPDB; the Engineer & representative from consignee shall conduct Post Landing Inspection in
presence of the representative of Supplier. The program of such inspection shall be intimated to the
representative of Supplier by BPDB upon arrival of the materials at BPDB store of the Inspector(s) to be
selected for test witnessing. Any defect or damage have been found at post-delivery inspection, the
defective or damaged panels/ materials/ goods to be repaired/ replaced by the Bidder/ supplier at his own
cost.
2.2 OLTC, MDU & AVR Manufacturer's name & country - MR Germany/ ABB,
Sweden
2.3 Nos. of tapping - 17
2.4 Tapping steps - +10% in steps of
1.25% 17 tapping (i.e.
33+8x1.25%)
2.5 HV or LV winding - HV winding
2.6 Power Frequency withstand test voltage between first kV 75
and last contracts of the selector switch between
diverter and switch contract.
3. G ENERAL
3.1 Manufacturer’s Name & Address To be mentioned
3.2 Material of core & grading To be mentioned
3.3 Core Loss/ Kg, supported by Characteristic Curve (to To be mentioned
be submitted )
3.4 Thickness of core, mm To be mentioned
3.5 Core Dia, mm To be mentioned
3.6 Total weight of core, Kg To be mentioned
3.7 Maximum flux density in iron at normal voltage and
frequency and at normal ratio (ONAF condition)
a) Cores Tesla < 1.7
b) Yokes Tesla To be mentioned
3.8 Magnetizing current (approx.) % To be mentioned
The Bidder shall indicate the standard to which the materials offered by him conform to.
Should these standards differ from the specified standard in any respect the Bidder shall detail
the differences between the proposed and specified standard.
DRAWINGS
To be submitted by the Bidder