Tolerance Manual
Tolerance Manual
PRECASTIPRESTRESSED
CONCRETE INSTITUTE
TOLERANCES
FOR PRECAST AND PRESTRESSED CONCRETE
CONSTRUCTION
MNL-135-00
prepared by
Substantial effort has been made to ensure that all data and
information in this manual are accurate. However, PCI cannot
accept responsibility for any errors or oversights in the use of
material or in the preparation of engineering plans. This publi-
cation is intended for the use by personnel competent to evalu-
ate the significance and limitations of its contents and able to
accept responsibility for the application of the material it con-
tains. Special conditions on a project may require more specif-
ic evaluation of practical engineering judgement.
ISBN 0-937040-62-2
2
Fig. 1.4.1 Relationship of Project Tolerances to Functional Requirements
rl Ty~~~~:~g:5uct
~
~ Project Des1gn
I
H ~
Typical Interface
Tolerai'"ICes
H
Product/Element
Design
I
H ~
Typical Erection
IDetermine Functional
Aequ1rements
~
Determine How to
Meet Functional
Requirements
Tolerances
Define Overall
Project Tolerance
Plan
H Fabricate Elements
I
H ~
Interface Tolerance
Details
H Erect Elements
I
H ~
Special Project
Tolerances
y Install Interface
Elements
I
y Special Project
Details
~
Owne•
I Precaster's Plant
Architect/Engineer of
Record
Precaster Design-
Build Agreement r-- Engineering Desi~ns
Project and Speci ies
Tolerances
I I Precaster 81ds
Elements to
Specified Tolerances
Precaster Erects
and Controls Project Engineer of Record
Tolerances
3
Fig. 1.4.4 Tolerance Responsibility*
Comments
Project Activity Owner Architect/ General Precast Precast Precast Erector Erection
Engineer Contractor Plant Man· Plant Plant Manage- Quality
agement Engineer- Quality ment Control
lng Control
p
Set Requirements
...
Specify Typical Erection Tolerances p I I
;------
Confirm Erection Tolerances Achieved p
r--
Confirm Interface Tolerances Achieved p
Legend: P = Prime Responsibility A/A= Review and Approval Authority I= Input Required From
* The responsibility for various activities concerning tolerances varies from region to region and from project to project depending on differences in the contractual requ'1rements.
1.5 Custom Nature of Building Construction cial attention to the overall construction tolerances of
all of the elements of the construction project.
It should be noted that tolerance determination in Careful consideration of how the overall tolerance
building design and construction is substantially dif- system (product tolerances. interface tolerances,
ferent from the practices used in machine design and joint clearances, and erection tolerances) accommo-
assembly. Modern machine design relies on the abili- dates tolerance variations is necessary. The use of
ty to incorporate completely interchangeable close tolerance accommodating details, which in some
tolerance parts into the machine assembly. To ac- instances allow very significant tolerance variations to
complish this the machine industry has developed be appropriately handled, is also necessary in some
the concept of True Position Dimensioning which al- instances.
lows close tolerance mating parts to be produced in- Building construction principally involves custom
dependently with the assurance that if specified toler- work with relatively large dimensional tolerance varia-
ances are met the parts will fit properly 100 percent of tions. Thus even after appropriate member and erec-
the time. tion tolerances are specified and appropriate inter-
Precast concrete construction has moved toward face details are incorporated in the design, the
the machine design tolerance philosophy when building team members must be vigilant in the early
compared to most other large building element identification and resolution of out of tolerance situa-
construction methods. However, design practice and tions which may develop in any aspect of the overall
economical fabrication and erection tolerance reali- building system. By doing this, tolerance related re-
ties do not allow the same assurance of the 100 per- work will be minimized.
cent fit up 100 percent of the time, without giving spe-
5
2.0 Introduction Erection Tolerances
The tolerance information contained here has Erection tolerances are defined as those toler-
been developed for use primarily by precast and pre- ances which are required for the acceptable match-
cast prestressed concrete producers, erectors, quali- ing of the precast members after they are erected. Ar-
ty control agencies, architects and engineers and re- ticle 11 .0 provides a comprehensive discussion of the
lated or interfacing trades unless other tolerances are principles and considerations relative to precast con-
noted in the project drawings or specifications. crete erection tolerances. Additional information per-
In the event that the project tolerances are set by taining to erection tolerances that should be antici-
the precast producer, rather than the architect/engi- pated in the tolerance specification review and
neer, all involved parties agree in advance of any pro- construction of precast concrete structures is pro-
duction, what the project tolerances will be. If toler- vided in Article 12.0.
ances different from PCI standard tolerances are
used on a project. the specified tolerances on that
Interfacing Tolerances
particular project should be shown on the project
shop drawings and, as applicable, on the erection Interfacing tolerances are those tolerances which
drawings. In lieu of showing tolerances on each shop are associated with other materials or building sys-
drawing, a tolerance drawing for the project can be tems in contact with or in close proximity to precast
prepared to make the production personnel aware of concrete, both before and after precast erection. Ar-
the project tolerance requirements. ticle 17.0 provides guidelines for the proper dimen-
The producer's personnel should review the con- sional specification of interfacing materials in con-
tract documents and make sure that the specified tol- junction with precast product and erection
erances are appropriate to the individual compo- tolerances.
nents. If revisions are deemed necessary by the
review the architect/engineer should be notified by
the producer so that any proposed revisions can be
2.2 Tolerance Categories
approved and/or implemented by the architect/engi- There are six categories of tolerance issues for the
neer. three tolerance groups given above. The principal
concern of each category is as follows.
2.1 Groups of Tolerance Issues
6
Tolerances more restrictive than those discussed determine the most economical approach to han-
in this document should be brought to the attention dling the project tolerance requirements.
of the architect/engineer to ascertain that they are
compatible and that the proposed restrictions can be Legal
met. For example, a requirement which states that
"no bowing, warping, or movement is permitted" is To avoid encroaching on property lines and estab-
not practical or possible to achieve. lish a tolerance standard against which the work can
be compared in the event of a dispute.
Visual It is very important to agree on the project toler-
ances in writing, particularly with special tolerances
The variations in the finished product should be or in situations with critical visual aesthetics. Similarly,
controllable and result in an acceptable appearance. it is equally important to agree in advance how and
Tolerances related to visual effects or aesthetics may when these tolerances will be verified (with due con-
be significantly more stringent than those required for sideration for measurement methods, measurement
structural or functional reasons. Tolerances which locations, number of points to measure, support con-
are critical to project aesthetics should be indicated ditions, thermal conditions, and time of measure-
as such by the Architect/Engineer. ment).
Economics Contractual
To ensure a reliable and efficient rate of production To establish a known acceptability range and as-
and erection by having a known degree of accuracy sign responsibility for developing, achieving, and
in the dimensions of precast concrete products. The maintaining mutually agreed tolerances for the proj-
cost of working to tighter than standard product toler- ect. The producer's quality control staff should under-
ances should be evaluated for cumulative cost effects stand whatthe producer's contractual obligations are
at the project level. That is, one should evaluate both regarding project tolerances. The actual project tol-
the cost increases and cost savings for member fab- erances contractually agreed to may be different from
rication, interfacing with subsystems and erection to the charted values given here.
7
3.0 Responsibility for Project Dimensional assure that noted discrepancies have in fact been
Control corrected prior to concrete placement.
8
4.0 Tolerance Acceptability Range Engineer of Record is necessary to evaluate the
consequences of out of tolerance situations.
The tolerances shown in this document are guide-
lines for acceptability. Many projects involve situa- b. The member can be brought within project tol-
tions which require variation from the published toler- erance by structurally and architecturally satis-
ances. Only the recognized and agreed upon factory means. Repair methods used to correct
"project tolerances" govern the production of the pre- tolerance problems should not compromise
cast members. structural performance or long term durability.
Not all tolerances are critical in every case, particu-
larly when the structural or architectural performance c. The total erected assembly can be modified to
is not impaired. In some circumstances, the archi- meet all structural and architectural require-
tect/engineer may accept an out of tolerance member ments.
if it conforms with any of the following:
Modification of erection activities to accommodate
a. Exceeding the project tolerances does not af- out of tolerance members requires close coordination
fect the structural integrity; or architectural per- between the producer's representative and the erec-
formance of the member. Often the input of the tor.
9
5.0 Definitions of Tolerance Related Terms Bowing-An overall out-of-planeness condition
which differs from warping in that while two edges of
The following definitions should apply to toler- the panel may fall in the same plane, the portion of the
ances tor precast and precast prestressed concrete plane between the edges is out of plane. (See Warp-
products: ing.) Bowing tolerance is usually most important in
Accuracy of measurement-Conformity with the wall panels that are exposed to view. Bowing can oc-
cur in more than one direction.
actual value of the measurement.
Accuracy is not necessarily associated with the Building survey datum-The local survey datum
notion of close conformity with the true value, which established for the global erection of the building to
is a measure of precision. the design plan layout and elevations.
Architect of Record-The individual design pro- Camber- (1) The deflection that occurs in pre-
fessional responsible for, among other things, speci- stressed concrete members due to the net bending
fying the appearance of the finished structure. It may resulting from stresses associated with the effects of
be necessary to gain the approval of the Architect of the prestress force (not including dimensional inac-
Record for any proposed tolerance repair methods curacies); and (2) a built-in curvature to improve ap-
which will be visible in the completed structure. pearance.
Camber control is generally more of a concern in
Architectural precast concrete-- A precast con-
crete product with a specified standard of uniform ap- long prestressed members where there is increased
potential for differential camber in adjacent members.
pearance, surface details, color, and texture.
Tolerances for architectural precast products are Groups and Categories of Products-The PCI
generally more stringent than for structural products Plant Certification Program is focused around four
because of the increased importance of appearance. groups of products and categories within those
This class of product generally is associated with a groups designated as indicated in Table 5.0.1.
premium cost.
10
Products in Group A are subject to architectural ishes that require uniformity and detailing more de-
tolerances. Products in groups B, C, are subject to manding than the typical requirements for structural
structural tolerances. Categories CA and BA are sub- products.
ject to structural tolerances unless they are specified The surface finish requirements for these mem-
category A1 with Special Project Tolerances which bers should be clearly specified and verified with ap-
may be a combination of specially defined structural propriate samples and mockups. Included in this
and architectural tolerances. category are parking deck structural spandrels with
a special finish. Typically these members are used on
Group A-Architectural Products. These are projects for reasons of economy. They are fabricated
products produced in accordance with the require- to structural tolerances unless Special Project Toler-
ments of MNL-117. Within Group A, products in cate- ances are specified, which may be a combination of
gories A1- architectural cladding and load bearing structural and architectural tolerances.
members, and AT- architectural trim units are gener-
ally considered subject to architectural tolerances. Group G-Giass Fiber Reinforced Concrete.
This group includes concrete building elements all of These products are reinforced with glass fibers that
which are exposed to view. are randomly dispersed throughout the products and
are made by spraying a glass fiber, cement, and sand
Category A1 is architectural cladding and load slurry mixture into molds. This produces thin walled
bearing members. This category includes concrete lightweight cladding panels. Products are manufac-
building elements such as exterior cladding, load tured according to the quality requirements of MNL-
bearing and non-load bearing wall panels, spandrels,
130.
beams, mullions, columns, column covers. Category
AT is precast concrete architectural trim units, prod- Clearance-Interface space (distance) between
ucts with a high standard of finish quality and of rela- two elements. Clearance is normally specified to al-
tively small size that can be installed with equipment low for the effects of product and erection tolerances
of limited capacity. Included in this group are sills, lin- and for anticipated movement such as deflection, vol-
tels, coping, cornices, quoins, bollards, medallions, ume change movement, etc.
benches, planters, and pavers.
Clear distance-The least distance between the
Group B Bridges-This group includes all bridge surface of the reinforcement and the referenced sur-
products. The group is subdivided into B1, B2, B3, face. The referenced surface may be the form, adja-
and B4 categories. These products are considered cent reinforcement, embedments, concrete surface,
structural products. Category B1 products are typi- or other surfaces.
cally not prestressed, B2 products are prestressed
bridge related products excluding bridge beams, B3
Concealed surface-Surface not visible during
products are superstructure members using straight normal use of the member.
prestressing strand, B4 includes all products in B1 Tolerances for concealed surfaces may not be as
through B3 plus draped strand bridge members. critical as for surfaces which are exposed to view in
Category BA includes products fabricated using the finished structure.
forms and techniques common to the production of Connection-Device for the attachment of pre-
structural members (Group B) and having specified cast concrete members to each other, to the building
surface finishes that require uniformity and detailing or to the structure. Connection design must often ac-
more demanding than the typical requirements for count for the cumulative effects of all allowed toler-
structural products. ance variations.
Group C Commercial (Structural)-This group Contract documents-General conditions, proj-
includes all commercial products. The category is ect specifications and design drawings issued on be-
subdivided into C1, C2, C3, and C4 categories. These half of the owner by the design professionals of re-
products are considered structural products. Cate- cord (architect/ engineer) and from which the project
gory C1 products are typically not prestressed, C2 shop drawings and production drawings are devel-
products are prestressed hollow-core and similar re- oped.
petitive products, C3 products are prestressed mem- It is good practice to initially review the contract
bers using straight strands, C4 are products using documents to see if tolerances for the precast mem-
draped prestressing strands. Category CA, this cate- bers have been specified. If not, amend the contract
gory includes products fabricated using forms and to include specific definition of the planned approach
techniques common to the production of structural to project tolerances. Blanket reference to this docu-
members (Group C) and having specified surface fin-
11
mentwithout specifying specific tolerances should be nal 8 ft. [2.44 m] wide double tee wall panel is de-
avoided. signed to have a nominal% in. [19 mm] wide joint on
either side, the working dimension for the member
Control surfaces-The following are several dif- width would be 7ft. 11 V. in. [4.42 m].
ferent categories of surfaces relevant to precast con-
crete tolerance control and erection. Discrepancy-Indicates the difference between
planned dimension and actual dimension. The exis-
Alignment face-The face of a precast member tence of a discrepancy frequently reveals the need for
which is to be set in alignment with the faces of adja-
closer monitoring. Less precise measurement tech-
cent members or features. The alignment face is usu-
niques tend to obscure problems that more precise
ally a primary control surface. This is the member face
techniques may reveal.
that is usually exposed to view in the final structure.
Draft-The taper given to features of a mold or
Primary control surface--A surface or feature on form to allow the precast piece to be removed from
a precast member, the dimensional location of which
the mold or form without damage. Draft can result in
is specifically set and controlled in the erection pro- different feature dimensions between the front and
cess. Primary control surfaces are generally associat- back of a piece.
ed with the key dimensional features of the structure.
(for example a column haunch support surface) Engineer of Record-The design professional le-
gally responsible for the overall structural design of a
Secondary control surface--A surface or feature building or facility, for determining and setting the
on a precast member, the dimensional location of load requirements, and for coordinating the designs
which is dependent on the location tolerance of the
performed by a speciality engineer with the overall
member primary control surfaces plus the member system. Generally this is the individual who has
feature tolerances. An example would be the eleva- sealed the contract design drawings (not the precast
tion of a second-story corbel on a multistory column shop drawings) with his or her professional engi-
whose first-story corbel elevation is selected as the neer's stamp.
primary elevation control surface.
Errors in measurement-The following are differ-
Cover-The distance between the surface of the ent types of errors in measurement which must be
reinforcement and the nearest concrete surface. considered.
Creep-Dimensional change, usually shortening Systematic error-An error that invariably has the
or camber change, which takes place as result of sus- same magnitude and the same sign under the same
tained compression loading and prestress force on given conditions. Thus a cloth tape that has been
concrete elements. The magnitude and rate of creep stretched about 5 percent by overuse will consistently
depends on various factors including concrete char- measure a 40 in. dimension as just over 38 in.
acteristics and the level of compression loading.
Natural errors-Systematic errors that arise from
Dimensions-The following are several different natural phenomena. They are really the effects of cer-
categories of dimensions relevant to precast con- tain influences that operate to prevent the observer
crete fabrication. from seeing or reading directly the quantity being
Actual dimensions-The measured dimension of sought. Two instances are the refraction of light rays
the precast member after casting. and the thermal variation of measuring devices. (for
The actual or as-built dimension may differ from example thermal length changes in metal measuring
the working dimension due to construction and mate- tapes).
rial induced variation. Instrumental errors-Are the systematic effects
Basic dimension-The dimensions shown on the of imperfections in the construction or adjustment of
contract drawings or called for in the specifications. instruments used in making measurements.
The basic dimension applies to size, location, and rel- Instances include the lack of concentricity of transit
ative location. It may also be called the "nominal" di- circles, graduation errors in scales, and maladjust-
mension. ment of the bubble tubes of levels.
12
Accidental Errors-These errors of observation Lateral alignment-The location relative to a spe-
are random; they are usually small and then have a cified horizontal line or point in a horizontal plane.
tendency to be mutually compensating. The appear-
Level alignment-The vertical location relative to
ance of discrepancies in a series of measurements is
a specified horizontal plane.
one example.
When applied to roadways, bridge decks, slabs,
Flatness-The degree to which a surface approxi- ramps, or other nominally horizontal surfaces estab-
mates a plane. See Smoothness. This tolerance is lished by elevations, level alignment is defined as the
most important in wall and slab members. vertical location of the surface relative to the specified
profile grade and specified cross slope.
Formed surface-A concrete surface that has
been cast against form work. Match casting-A precast concrete fabrication
procedure whereby a segment is cast against the pre-
Hardware-Items used in connecting precast ceding segment thereby producing a matching inter-
concrete members or attaching or accommodating face that will permit re-establishment of the cast ge-
adjacent materials or equipment.
ometry at the time of erection. Match-casting may be
Generally suppliers of hardware can provide infor- accomplished by either the short line casting method
mation regarding required placement tolerances for or the long line casting method.
their hardware products.
Hardware is normally divided into the following Short line match casting-The method of casting
three categories: segments one at a time on the casting bed utilizing a
fixed or movable bulkhead. The first segment is cast
Contractor's hardware-Items to be placed on or between bulkheads.
in the structure in order to receive the precast con- Successive segments are cast, one at a time,
crete members, e.g., anchor bolts, angles, or plates against the bulkhead on one end and the reposi-
with suitable anchors.
tioned, previously cast segments on the other end.
Since the precast members must interface with
this hardware, it is important to understand the toler- Long line match casting-The method of casting
ance to which these elements are to be installed. Con- segments on a casting bed of sufficient length to per-
firm the as-built location of this hardware in advance mit the cumulative casting of segments for the entire
of the precast erection activities. length between field closure pours without reposition-
ing the segments on the casting bed. With this meth-
Plant hardware-Items to be embedded in the od, the first segment is cast between bulkheads and
concrete members themselves, either for connec-
successive segments are cast between a movable
tions and precast concrete erector's work, or for other
bulkhead on one end and the previously cast seg-
trades, such as mechanical, plumbing, glazing, mis-
ment on the other end.
cellaneous iron, masonry, or roofing trades. The
placement tolerances for this hardware often must PCI quality manuals-MNL-116 Manual for Quali-
consider the installation requirements of the systems ty Control for Plants and Production of Precast and
the hardware must interface with. Prestressed Concrete Products. This is the docu-
ment prepared by PCI as a guideline for quality assur-
Erection hardware-All loose hardware neces- ance of all precast concrete except architectural pre-
sary for the installation of the precast concrete mem-
cast and glass fiber reinforced concrete (GFRC).
bers.
MNL-117 Manual for Quality Control for Plants and
Jig-A template or device to align parts of an as- Production Of Architectural Precast Concrete Prod-
sembly, usually for pre-assembling reinforcing steel ucts. This is the document prepared by PCI as a
and hardware cages and positioning of anchor bolts guideline for quality assurance of architectural pre-
on site, with a minimum of measurement to attain con- cast concrete. MNL-130 Manual for Quality Control for
sistent accuracy from one casting to the next. The use Plants and Production of Glass Fiber Reinforced Con-
of templates in the plant and the same or matching crete. This is the document prepared by PCI as a
template for placement of the contractor's hardware guideline for quality assurance of glass fiber rein-
in the field is a good way to assure fit-up of mating forced concrete products.
connection elements.
Post-tensioning-A method of prestressing con-
Jog in alignment-The difference in elevation of crete whereby the tendon is kept from bonding to the
the top or bottom of one wall panel relative to the adja- plastic (wet) concrete, then stressed and anchored
cent wall panel measured at the mating edges of the directly against the hardened concrete, imparting
panels. stresses through end bearing at an anchorage. Post-
13
tensioning has the effect of shortening a member in the specific project specifications and for specifying
the direction axial to the post-tensioning and may re- items not covered in this document.
sult in camber. This shortening and the effects of
camber should be included in the length tolerance Quality-The appearance, strength, durability,
considerations. and dimensional conformance which is appropriate
for the specific product, its particular application and
Precast Engineer-The person or firm who de- its expected performance requirements. Quality also
signs precast concrete members for specified loads refers to the totality of features and characteristics of
and who may also direct the preparation of the shop a product that bear on its ability to satisfy stated
drawings. The responsibility for the design of the pre- needs.
cast members and of the overall structure (including
the overall tolerance plan) is determined by contract Quality assurance (QA)- All those planned or
and should be specifically defined in the project con- systematic actions necessary to ensure that the final
tract. product or service will satisfy given requirements for
quality; and performance of intended function. Typi-
Precast linear member-Beam, column, or simi- cally, the quality assurance effort will focus on the re-
lar member. quirements of the overall project. thus identifying the
tolerance quality control requirements for member
Precast planar member-Wall panel, floor panel fabrication.
or similar member.
Quality control (QC)-Those planned actions .
Precision of measurement-A measure of the which provide a means to measure and control the
closeness of conformity with the actual value. Preci-
characteristics of members and materials to predeter-
sion is related to the degree of care and refinement
mined quantitative criteria.
employed in making a measurement.
Accuracy of measurement is descriptive of the cor- Relative alignment-The distance between two
rectness of the result of the measurement. or more elements in any plane, or the distance be-
tween adjacent elements, or the distance between an
Pre-tensioning-A method of prestressing con- element and a defined point or plane.
crete whereby the tendons are elongated, and then
anchored while the concrete in the member is cast Set-up-The process of preparing molds or forms
around the tendons. The tendons are then released for casting, including installation of materials (rein-
when the concrete is strong enough to receive the forcement and hardware) prior to the actual placing
forces from the tendon through bond. of concrete. The set-up process is second only to the
Once the prestress force is transferred to the con- mold or form construction in its importance in the
crete member the member will shorten and possibly achievement of specified member tolerances.
camber. These dimensional changes need to be con-
sidered in the product tolerances, the erection toler- Shrinkage-The volume change in precast con-
ances, and the interface tolerances. crete members caused by drying that normally oc-
curs during the curing and initial life of concrete mem-
Pre-topped systems-A construction approach, bers. The expected shrinkage must be subtracted
such as may be used for the floor system in parking from the form set up dimensions to determine the as-
garages, in which the flange for the floor member, cast dimensions of a member.
often a double tee, is constructed to its final thickness
in the plant, resulting in no cast-in-place topping be-
Shop drawings-(1) Collective term used for
erection drawings, production drawings and hard-
ing required in the field. This approach can be very ef-
ficient in that it reduces the amount of field construc- ware details; and (2) Diagrams of precast concrete
members and their connecting hardware, developed
tion work. It does however. require closer control of
tolerances such as differential camber, flange con- from information in the contract documents. Shop
drawings show information needed for both field as-
nector placement and overall member depth.
sembly (erection) and manufacture (production) of
Project specifications-The building or facility the precast concrete members.
specifications which define specific requirements for
the elements of the project. Specifications can
Erection drawings-Those drawings which show
the relationship of the precast members and their
employ PCI tolerance recommendations by refer-
connections in the erected structure and which pro-
ence to specific tolerances given in this document.
vide such information as is necessary to properly
The specifications serve as the instrument for making
erect and connect the various members.
mandatory and optional selections available under
14
Production drawings-A set of instructions in the bers is secondary to their structural requirements.
form of diagrams and text which contain all the infor- The fabrication techniques used for structural precast
mation necessary for the manufacturer to produce concrete (for example, long line casting in forms with
the precast member. These documents are usually movable bulkheads), limit some of the dimensional
produced by or under the direction of the precast precision possibilities with this type of manufacturing
plant engineering department or by a party hired by process.
the producer to do this.
Sweep-A global variation in member horizontal
Hardware details-Those drawing details which alignment. This can sometimes be caused by hori-
are used for the fabrication or procurement of hard- zontally eccentric prestress in narrow members.
ware which is used either in the production of the pre-
cast member or in its erection and connection. Tendon-A high strength steel element consisting
of one or more wires, strands, or bars or a bundle of
Smoothness-The absence of local irregularity or such elements, which are stressed and used to im-
roughness. It does not refer to the overall shape ofthe part prestress to the concrete.
member. In prestressed products the position of the ten-
dons is one of the most important of all tolerances, as
Speciality Engineer-A licensed engineer, not variation in tendon location affects the structural ca-
the Engineer of Record, who performs structural engi-
pacity of the element.
neering functions necessary for the structure to be
completed. He has shown experience and/or training Theoretical casting curve-The curve of casting
in his specialty. geometry followed at the casting bed for segmental
precast members to achieve the theoretical profile of
Specially finished structural precast con- the completed structure after final deformations have
crete-A product fabricated using forms and tech-
taken place. This calculated curve takes into account
niques common to the production of structural mem-
deformations resulting from the sequence of erection
bers and having specified surface finishes that and loads applied during erection.
require uniformity and detailing more demanding
than the typical requirements for structural members. Tolerance-Specified permissible variation from
These surface finishes and any special tolerance specified requirements such as dimensions, location
requirements for this class of member should be and alignment such as:
clearly specified and verified with appropriate sam- • the permitted variation from a basic dimension
ples and mockups. These products are defined as or quantity, as in the length, width, and depth
Groups CA or BA if they use structural tolerances and of a member.
Group A 1 if they use architectural tolerances. • The range of variation permitted in maintaining
a basic dimension, as in an alignment toler-
Statistical tolerance control concepts-A math-
ance.
ematically valid approach of sampling and monitoring • A permitted variation from location or align-
tolerances on projects which have large numbers of ment.
identical pieces made using industrial tolerance con-
trol methods. Architectural tolerances-The tolerances given
in Article 10.1 for architectural panels define architec-
Step in face-The dimensional difference be-
tural tolerances. Member finish and color are sepa-
tween the edges of the planar surfaces of two adja- rate issues which are often important in the produc-
cent wall panels measured atthe mating edges ofthe tion of architectural concrete members. Architectural
two panels. The more perfectly the panels match di-
dimensional tolerances can be applied to other prod-
mensionally at the edges the less the step in face.
uct types as special project tolerances. There is no in-
Strand-A group of wires laid helically over a cen- tent to split tolerances between structural and archi-
tral-core wire. A seven-wire strand would thus consist tectural tolerances on the basis of finish or color.
of six outer wires laid over a single wire core. High Finish and color are separate issues related to project
strength steel strand is typically used to prestress aesthetic requirements.
concrete.
Structural tolerances-The tolerances given in
Structural precast concrete-Precast concrete Article 10.0 with the exception of the architectural tol-
members that are intended to support external struc-
erances given in Article 10.1, architectural trim toler-
tural loads in addition to their own weight. They are
ances given in Articles 10.29, 10.30 and 10.31 for ar-
fabricated using methods which are optimized to eco-
chitectural trim elements and Article 10.28 for railroad
nomically produce members with specified structural
ties. These tolerances apply to structural precast
properties. Appearance requirements for these mem-
15
concrete members that are fabricated using methods Erection tolerances-Those allowable variations
designed to produce economically feasible members in dimensions of member placement in the com-
with specified structural properties. pleted structure required for acceptable matching of
Finish and color are usually less important for precast members alter they are erected.
members governed by structural tolerances. When Erection tolerances are a characteristic of how the
the finish and or color of structural members are im- individual members are positioned both globally nnd
portant to the project, this should be specifically relative to one another in the overall structure.
noted in the contract documents, as special mea-
sures may be required to achieve the desired result. Interfacing tolerances-Those allowable varia-
tions in dimensions associated with other materials or
Project tolerances-The required tolerances for systems in contact with or in close proximity to pre-
a specific project. If the specified tolerances differ cast concrete.
from the tolerances given in this document for a spe- Interface tolerances could include the tolerances
cific product group or category, it is in the interest of of cast-in-place concrete footings, structural steel or
all parties to agree in writing to the project tolerances. cast-in-place concrete frames, and subsystems like
windows, doors, heating and ventilating system ele-
Special project tolerances-Specially required ments, and the like.
tolerances, different from standard PCI tolerances
given in this publication which are required to meet True position dimensioning-A system of dimen-
specific project requirements. sioning used in the machine design industry to assure
Tolerances different from those listed in this docu- that close tolerance parts are universally interchange-
ment may be agreed to for a specific project. These able. Some of the concepts of this tolerancing system
tolerances could be either less stringent or more strin- may be of interest to the precast producer for special
gent than the tolerances listed here. situations. See the reference section for publications
It should be noted that the requirement for special which address this tolerance system.
project tolerances may have a significant impact on
project price and schedule.
Variation-The difference between the actual and
the basic dimension. Variations may be either nega-
Product tolerances-Those allowable variations tive (less) or positive (greater).
in dimensions relating to individual precast concrete
members.
Vertical alignment-The location relative to a spe-
cified vertical plane or a specified vertical line or from
Control surface tolerance-Tolerances which a line or plane reference to a vertical line or plane.
are related to element control surfaces that are set or When applied to battered walls, abutments or other
aligned to be within the specified project erection tol- nearly vertical surfaces, vertical alignment is defined
erances. as the horizontal location of the surface relative to the
specified profile.
Feature tolerance-The allowable location or di-
mensional variation of a feature, such as a corbel or Warping-Twisting of a member, resulting in over-
a blackout, with respect to overall member dimen- all out-of-plane curvature of surfaces characterized
sions. Feature tolerances are a characteristic olthe in- by non-parallel edges.
dividual precast members. Warping is most often a concern in panel mem-
bers, although it can occur in other types of members.
16
6.0 Relationships Among the Different Toler- Erection tolerances and product tolerances for
ance Groups some features of a precast concrete member may be
directly additive while others are not. This fact should
The relationship among the different tolerance be communicated to production, quality control and
groups must be consistent in order to avoid tolerance erection personnel and may be shown on the erection
related rework of building members. A careful review drawings if relevant to the erection activity. Knowing
of which tolerances are primary and which secondary which member surfaces are the primary erection con-
and a review of how product and erection tolerances trol surfaces is important to the erection effort.
relate on a particular building project will determine If special project tolerances, other than standard
which tolerances are cumulative and which are not. PCI tolerances are used, in lieu of showing the erec-
tion tolerances for each piece, a tolerance drawing for
6.1 Relationship of Product Tolerances each erection situation can be used to convey the re-
quired project tolerances to the erection personnel.
Product tolerances define the limits of the size and In instances where the tolerance of both primary
dimensional precision of the individual precast mem- and secondary control surfaces must be controlled
bers comprising the building or structure. The prod- during erection, the design should be reviewed by the
uct tolerance also controls the location of the member producer and erector to assure that the details in-
features as they relate to the overall member dimen- clude provisions for secondary control surface ad-
sions. justment. If revisions are indicated by the review, the
In lieu of showing the member tolerances on each architect/engineer should be notified, as problems in
shop drawing. a project tolerance drawing can be the tolerancing system are easier to resolve before
used to convey the required project tolerances to the the pieces are produced.
production personnel. The producer should review
project specifications and design drawings to deter·
6.3 Relationship of Interfacing Tolerances
mine if surface and feature dimensional control re-
quirements are clearly outlined. If clarifications are Interfacing tolerances are those associated with
needed the architect/engineer should be notified. other materials or systems which interface with the
precast concrete members. Interfacing tolerances
6.2 Relationship of Erection Tolerances apply whether the interfacing system is erected prior
to or following precast erection.
Erection tolerances define the location and place- For interfacing situations which involve multiple
ment of the individual precast members in the as- members, both product and erection tolerance ef-
sembled structure. The individual precast member is fects may have to be accommodated within the inter-
erected and positioned so that its primary erection face tolerance.
control surface is in conformance with the established Product tolerances, erection tolerances and inter-
erection tolerances. face tolerances together determine the dimensions of
See Articles 11.0 and 12.0 for further discussion of the completed structure. If it is critical to the project,
erection tolerances. the system tolerances which take precedence on the
During precast panel installation, priority is gener- given project should be reflected in the contract docu-
ally given to aligning the exterior face of the precast ments and should also be indicated on the project
panels to meet aesthetic requirements. This may re- shop drawings.
sult in the interior precast panel face not being in a See Article 17.0 for a discussion of interfacing tol-
true plane. erances.
Product tolerances for member primary control As written, American Concrete Institute (ACI) doc-
surfaces are not additive to the erection tolerances ument 117 "Standard Tolerances for Concrete
which govern the setting of the member primary erec- Construction and Materials" applies primarily to rein-
tion control surfaces. forced concrete construction. Similarly the American
The secondary control surfaces of a member (for Institute for Steel Construction (AISC) code of stan-
example the surfaces of a blackout) usually are not di- dard practice applies only to structural steel construc-
rectly set during the erection process. Thus, the tion. Neither of these standards addresses toler-
product tolerances for secondary control surfaces ances for buildings of composite construction (i.e.
and features of the member are additive to the erec- concrete floor slabs carried by steel columns or steel
tion tolerances for the member. To ensure a trouble frames with precast concrete cladding) Nor are toler-
free installation, generally, the product tolerances ances for fireproofing and masonry controlled by ref-
must not conflict with the erection tolerances. erencing these standards. The producer should re-
17
view the contract documents to assure that the by the producer, as these require early decisions
location of all such materials contiguous to the pre- based on overall project economics. Once these de-
cast concrete members have been controlled within cisions about forming, fabrication methods, and erec-
tolerances which are, at most, no less stringent than tion procedures have been made, they should be re-
those specified in ACI 117. Notify the architect/engi- flected on the project shop drawings.
neer if revisions to the contract documents are indi-
cated by this review.
6.5 Relationship of Form Tolerances to Prod-
uct Tolerances.
6.4 Project Economic Considerations
Product tolerances are directly dependent on form
The precedence of product and erection toler- manufacturing tolerances, the flexibility of the form,
ances raises questions of project economics. The tol- and the precision with which the variable features of
erance requirements and other costs associated with the form can be adjusted.
the connection details should be reviewed by the pro- In some cases, when long production runs of
ducer in conjunction with the erector. close tolerance members are required, the invest-
When accepted by the producer and/or erector as ment in very rigid, close tolerance premium form work
contractual requirements, special tolerance require- may be the best investment that can be made. This
ments, details, and procedures should be clearly will serve to minimize any tolerance related problems
spelled out in the project shop drawings. Special tol- and the associated costs.
erances or construction procedures should be noted
18
7.0 Product Tolerances ling authority. If a specifying agency has tolerances
more restrictive than PCI tolerances in the project
Product tolerances are a measure of dimensional specification, the more restrictive agency tolerances
accuracy of the individual members and ensure, prior will govern the production of the project members.
to delivery to the job site, the high probability that the
member will fit into the structure without requiring tol-
erance related rework. See Article 10.0 for a listing of
7.1 Specification of Product Tolerances
product tolerances. See Appendix A for sample specification language
The applicable product tolerances should be con- regarding product tolerances. Project tolerances for
sidered in the overall project tolerance plan, along
manufacturing precast members and other interfac-
with the appropriate erection tolerances and the re- ing systems are standardized throughoutthe industry
quired interfacing tolerances. and should not be made more rigid and therefore
Product tolerances are needed in any manufactur-
more costly, unless absolutely necessary. The pro-
ing process. They are determined by economics, ducer should review the contract documents to as-
practicality, function and appearance. Product toler-
sure that the architecVengineer has specified project
ances are applied to physical dimensions of precast product tolerances within a generally accepted range
members such as thickness, length, width, square- or has defined special measures to achieve a different
ness, and location and size of member features.
level of tolerance. The requirement for such special
At times, the user of a precast concrete product
measures should be defined in the project contract
will specify special project tolerances for a particular documents.
project or member type. For example railroad author- The per unit cost of the preparations and actions
ities or governmental bridge authorities may often
necessary to manufacture members to close toler-
specify the necessary tolerances for products that
ances usually decreases with increasing repetition in-
they incorporate into their infrastructure. Therefore, volved on projects which consist of many similar pre-
the designer should consider PCI tolerances in con- cast members.
junction with the tolerances specified by the control-
19
8.0 Overall Plan Dimension Tolerance Con- which should be taken into account in the selection
siderations of the types of forms to be used is the precision of di-
mensional tolerance specified for the member.
The two most important considerations in achiev-
ing specified product tolerances are the effects of
formwork and the measuring techniques used to set Effects of Rigid Forms
the forms and assess the various product dimen-
Rigid forms are those which have all the sides of
sions.
the form rigidly and permanently fixed, thus ensuring
When considering the effects of product toler-
a higher degree of dimensional accuracy than other
ances the following items are significant: When new,
form types, in both the length and width directions.
relocated, or modified forms are used, the initial mem-
Rigid forms are often used in the fabrication of cus-
ber cast should be carefully measured to assure that
tomized products such as architectural precast pan-
all features are correctly formed and that all member
els, where appearance or function dictates the need
tolerances are met. This process should be repeated
for closer tolerances. Large runs of repetitive use of
when there is any reason to believe that the condition
forms can make the higher initial cost economically vi-
of the form may have changed.
able.
Length or width dimensions and straightness of a
Side forms for rigid forms should have suitable
member will all affect the joint clearance dimensions,
draft. Draft is the slope or taper required on the forms
opening dimensions between members, and poten-
to permit stripping of the precast member from the
tially the overall length of the structure which incorpo-
form.
rates the member. Thickness variation of the precast
concrete panel member becomes critical when interi-
or surfaces are exposed to view. A non-uniform thick- Effects of Semirigid Forms
ness of adjacent members will cause offsets of the
front or rear faces of the panels. Semi-rigid forms are those which have two sides
rigidly and permanently fixed. The other sides typical-
ly are made by using end dividers for long line casting
8.1 Effect of Forms on Dimensions or removable side forms to allow dimensional differ-
ences in individual pieces.
Forms are generally one of three types: rigid, semi-
In semi rigid forms the end dividers or removable
rigid, or flexible. See Fig. 8.1.1. The tolerances to
side forms are not permanently rigidly attached to the
which the forms are made and the tolerances to which
form, and thus must be set to the proper dimension
they can reliably be adjusted are an important deter-
for each panel casting. Because they must be set with
minant of the ability to achieve specified member tol-
each new casting length, they have the potential to
erances. The proportion of the product tolerance vari-
move slightly during the placement and vibration of
ation which results from form manufacturing
the concrete. This results in a lesser degree of achiev-
tolerances or adjustment precision should be consid-
able precision in linear plan dimensions than when
ered in the plan to achieve specified member toler-
rigid forms are used.
ances. One of the most important considerations
20
Effects of Flexible Forms er modulus at release) when compared with mem-
bers cast during the week and detensioned the next
Flexible forms have no permanent rigidly fixed morning after casting (more camber because of lower
sides. The typical product using such forms is a modulus at release).
double tee with blocked-out flanges, or a flat wall pan- If particular members within a project require high
el on a project having many different sized wall pan- levels of dimensional stability over time, this require-
els. Of the three types of forms discussed here, flex- ment should be brought to the attention of the precast
ible forms result in the least degree of achievable plan designer so that the prestress can be designed tore-
dimensional precision in both length and width. duce the potential effects of creep. Since this may in-
volve the addition of more total prestress, it may have
8.2 Effects of Prestressing on Dimensions economic effects and this requirement should be
treated as a special project tolerance.
The effects of prestressing can have a significant The effects of differential temperature from one
effect on member dimensions and should be consid- side of a member to another can cause the member
ered in the plan to meet specified tolerances. The pro- to bow or camber. Similarly in long members the ef-
ducer should assure that the effects of prestressing fect of lengthening and shortening due to wide ex-
have been accounted for in determining the form set- tremes of temperature can be important to the overall
up dimensions for member casting. length tolerance of members.
It is very important to agree in advance on the con- Solar heating of members stacked in the yard may
ditions under which the tolerances of a member will cause sweep and camber variations due to differen-
be checked. (e.g. the agreed support conditions for tial temperature. These deformations may not be
measuring sweep of a long slender precast pile). In present in the completed structure if it is enclosed.
instances where stringent tolerances are required Because of this it may be important to measure cam-
make sure that the affect of prestressing on member ber and sweep in the members at times when thermal
dimensions is clear within the project team. Put this effects in the piece are minimal. The opposite can oc-
agreement in writing prior to fabrication. cur with members that are exposed to thermal effects
The prestress effects result in length changes, in the completed structure. The potential for undesir-
member camber, and end rotation all of which should able deformation due to significant thermal effects
be taken into account when determining the casting should be brought to the attention of the precast de-
length for the member. The application of prestress sign engineer for evaluation.
force to the member can affect the overall length of Shrinkage and differential shrinkage of the con-
the member in two ways. First, there is an axial short- crete members can also have an effect on the dimen-
ening of the member as result of the applied axial sional tolerances of precast concrete members. Al-
compressive force of the prestress and second, the though the great majority of the concrete shrinkage
ends of the member may rotate in elevation as a result takes place during the initial curing of the member, its
of the member camber caused by prestress eccen- effect, particularly on large members, can be signifi-
tricity. cant and should be accounted for in the tolerance
control of the member. Differential shrinkage, particu-
8.3 Effects of Time, Temperature, and Shrink- larly in members which have different mixes with dif-
age on Dimensions ferent shrinkage characteristics, can result in mem-
ber bowing, warping, or camber. Differential
Because of concrete's tendency the creep under shrinkage of face and back up concrete mixes in ar-
applied load or prestress, the shape and dimensional chitectural members or in different mixes which may
tolerance of a member has the potential to change be used for the interior and exterior wythes of insu-
over time. This is more of a concern for members lated panels is something that should be assessed
which have high levels of eccentric prestress which with regard to the effect on member bowing and
can lead to changes in member camber or sweep warping tolerances.
over time.
Since the modulus of elasticity of concrete varies 8.4 Relation of Measuring Techniques to Tol-
proportionally to its strength, the strength (and result- erances
ing modulus) of the concrete at the time of transfer of
prestress may have an effect on member camber Accurate measuring devices and methods with
which can be significant enough to consider in the the precision capability appropriate to the tolerance
overall dimensional control program. This may be no- being controlled should be used for both setting and
ticeable, for example, in differential camber of long checking product, interface, and erection tolerances.
cambered members which are cast on Friday and de- Typically, the precision of the measuring technique
tensioned on Monday (less camber because of high- used to verify a dimension, either pre or post casting,
21
should be capable of reliably measuring to a preci- tion, the architect/engineer should be notified for pos-
sion of one-third the magnitude of the specified toler- sible design revisions.
ance.
The most common measuring method used in
8. 7 Tolerances for Position of Tendons
precast plants is the use of metallic measuring tapes
graduated in feet, inches and fractions of a inch. (me- Tolerance for position of prestressing tendons is
ters and millimeters) For economic and functional one the key tolerances affecting the structural capac-
reasons, the use of more sophisticated measuring in- ity of the member. If tighter or less stringent tolerances
struments, such as surveying instruments, may be on strand location than given in this document are re-
justified in some instances. To maximize accuracy, quired by the contract documents, they should be
members should not be measured in increments in a specifically noted on the project shop drawings.
manner which creates the possibilttyof cumulative er- Strand position tolerance is usually more important in
ror. (For example, use a tape long enough to measure shallow beam members than it is in deep beam mem-
the entire length of a member.) The degree of accura- bers.
cy in using measuring tapes depends on the particu- It is common practice to use% in. [16 mm] diame-
lar dimension of the member being measured. To at- ter holes in end dividers (bulkheads, headers) for all
tain greater precision in the linear dimensions of long strand sizes Y, in., 'A' in., 'Ia in., [13, 11, and 9.5 mm
members measuring tape slope, tape sag, tape ten- diameters]. This is done because it is costly to switch
sion, and temperature effects should betaken into ac- to new end dividers for different strand diameters.
count. Thus, in most plants, more precision in strand loca-
tion is achieved when using larger diameter strands.
8.5 Tolerances for Blackouts and Openings
8.8 Tolerances for Handling Device Loca-
A tolerance, consistent with the eventual function, tions
size and location of the block out should be indicated
on the shop drawings. In lieu of showing block out tol- The relative importance of placing tolerances on
erances on each shop drawing, typical block out tol- handling device locations in different directions
erances can be shown on a tolerance drawing for the should be indicated by tolerances shown on the proj-
overall project. For example, the tolerance on a win- ect shop drawings, especially in thin or narrow sec-
dow blackout, into which a prefabricated window tions.
frame will fit, should be more precise than a block out For example, closer lateral tolerances are neces-
through which a field-installed piping system will be sary to ensure the minimum required cover around
placed. The possible need for draft on the sides of lifting devices embedded in the stems of tees. In lieu
blackouts should also be considered. of showing the tolerance for handling devices on each
Another special case which should be shown on shop drawing they may be shown on a tolerance
the shop drawings is the set of required tolerance for sheet for the project.
dimensions controlling the matching of open shaped
panels. These tolerances may have to be tighter than
8.9 Tolerances Considerations for Camber
the standard dimensional tolerances by 50 to 75 per-
and Differential Camber
cent in some cases to assure a visually acceptable
match up. The producer should review these types The importance of camber and differential camber
of situations with the architect/engineer so that any between adjacent prestressed concrete members of
anticipated tolerance problems can be solved in the similar design will vary depending on the project re-
design of the panel interfacing prior to fabrication. quirements. If differential cambers exceed recom-
mended tolerances, additional effort is often required
to erect the members in a manner satisfactory for the
8.6 Tolerances for Sweep or Horizontal intended use.
Alignment The effects of differential camber on member to
member connection details and overall function in
Horizontal alignment deviation can occur as result pretopped systems should be considered in deter-
of form tolerances and member width tolerances. It mining appropriate differential camber specifications.
can also result from the effects of prestressing which The final installed differential elevation tolerance
has a lateral eccentricity, thus causing a sweep (later- between two adjacent cambered members erected in
al camber) in the member. If prestressed induced the field may be the combined result of member differ-
sweep is noted to create an out of tolerance condi- ential cambers, variations in support elevations, and
22
any elevation adjustments made to members during c. Creep differences resulting from differing con-
erection. cretes or differing stress conditions within the
Member camber measurements should be per- member.
formed in a consistent manner in order to understand d. Shrinkage effects due to differences in expo-
the actual differences in camber. It is very important sure, humidity, or curing differences.
to maintain uniformity at the time of camber measure- e. Strand relaxation which increases somewhat
ment both with regard to member temperature and with time.
solar exposure during the day and with regard to the f. Thermal effects that vary with time.
age and support conditions of the member since g. Extent of member flexural cracking.
casting.
For example, the camber measured on the top
Effects of Curing Methods on Camber Tolerances
member of a stack of double tees in the mid afternoon
on a hot sunny day will be considerably different from If special curing methods are needed to achieve
the measured camber of the bottom member of the member camber tolerances this should be noted on
stack on the same day (or of the same top piece on the project shop drawings. Curing methods can influ-
a cold cloudy day}. Similar camber measurement dif- ence concrete strength (and consequent modulus of
ferences will occur with long wall panels with one side elasticity and resulting camber effects} at the time of
exposed to the sun and the other side in the shade. prestress transfer to the member.
The most consistent results are obtained by measur-
ing camber in the early hours of the day, before the
sun has begun to differentially heat the members. Storage Configuration Effect on Camber Tolerance
Control of differential camber of adjacent mem- If special storage configurations are required to
bers in pre-topped systems may require more strin-
achieve product camber tolerances this should be
gent tolerances to meet functional requirements.
noted on the project shop drawings.
When this is the case, special design and production The following storage related issues can have an
measures may be required to achieve special project
effect on member camber.
tolerances for differential camber. Some adjustment
a. Member support locations while in storage.
to design floor elevations may be necessary when
b. Member position with respect to the sun.
working with pre-topped systems.
c. Member position in the storage stack and its ef-
If variation in camber in excess of the specified tol-
fect on the storage loading of the member.
erance is observed, the plant quality control inspector
should look for the cause and inform the architect/en-
gineer, who will determine the effects of the variation 8.1 0 Tolerances for Squareness of Ends or
on member performance. Note that variations from Variation From Specified End Skew
expected design camber may indicate strand slip-
page after release of prestress. The type of forms selected for a project should
consider the tolerance precision requirements for the
Some of the factors affecting camber variation and
subsequent differential camber are: of squareness of member ends. Out of square panels
and other members can cause tapered joints be-
tween adjacent panels and make the adjustment of
Time-Dependent Effects on Camber adjacent members difficult.
A member end skew which is not 90 degrees will
Since member camber can vary over time, the require special procedures during form set-up and
point in the life of the camber critical member to which during as-built measurement verification to assure
the camber tolerance applies to should be defined in
that tolerances are met.
the contract documents.
Checking all members at the same prescribed age
since casting is important for consistent camber mea- 8.11 Tolerances for Position of Weld Plates
surement results.
When selecting the positioning and installation
The following are time related influences on cam-
ber. methods for weld plates, consider the tolerance re-
quirements on these items. In general, plates can be
a. Modulus of elasticity variations due to curing
positioned to closer tolerances when the plates are
duration differences can result in different cam-
embedded in the bottom of the member (or against
bers for members of similar design.
b. Different age at release, ages of adjacent mem- the side form} than can plates cast into the top of the
member.
bers, age at time of erection, age at addition of
superimposed load.
23
The main reason for this difference in placement 8.15 Tolerance on Reinforcing Steel Bending
precision is that bottom and side plates can be held and Placement
in position by fastening directly to the form, and hence
are less susceptible to movement which may be Reinforcing steel placement tolerances should be
caused by the placement and vibration of the con- shown on the project shop drawings. Similarly, rein-
crete. Plates cast into the top of the member are usu- forcing bar bend tolerances should be shown on the
ally supported by some type of frame which must be bar list for the precast members. In lieu of showing
positioned on the form before casting. these tolerances on each shop drawing, they may be
given on a project tolerance drawing.
Reinforcing steel used in precast prestressed
8.12 Tolerance on Tipping and Flushness of
products is controlled by two tolerances. The first is
Weld Plates
the bar length and bending tolerance, and the second
The tipping and flushness tolerance is also impor- is the bar placement tolerance, which is to an extent
tant when selecting the plate positioning method also dependent on the bar bending tolerance.
Flushness is the relationship of the weld plate surface Reinforcing bar bending and length tolerances as
to the concrete surface. For the same reasons as out- well as reinforcement placing tolerances are gov-
lined above, plates cast on the top of members will erned by the American Concrete Institute standards.
tend to tip out of plane more than bottom plates. The section on concrete feature tolerances (Section
Another reason for tolerance difference between 2.2. from ACI 117-90 Standard Tolerances for Con-
top and bottom plates is that bottom plates get uni- crete Construction and Materials) is reproduced be-
form bearing from the form surface whereas top low in Table 8.15.1. See the current issue of ACI117
plates must be supported by removable positioning for reinforcement bending and placing tolerances.
fixtures which often are not an integral part of the In situations where reinforcement embedded in
form. and extending from a precast member must interface
with other members, special measures are often re-
quired when planning the tolerances for the reinforce-
8.13 Tolerances on Haunches of Columns ment and in the fabrication of the members. The
and Wall Panels achievable reinforcement bar bending tolerances
possible with available bar bending equipment
Measures taken to assure maintaining tolerance
should be taken into consideration. This is especially
on haunch location dimensions which are also prima-
important if hooked bars are used.
ry erection control surfaces should consider the toler-
The overall tolerance plan for members with em-
ance requirements of the type of connection used at
bedded reinforcement should consider the detailed
the base of the member. Since a panel or other mem-
clearances between adjacent reinforcing bars and
ber base connection often allows some positioning
the potential maximum tolerance variation possible in
flexibility, it is often more important to control dimen-
the location of the reinforcement extending from each
sions from haunch to haunch in multistory columns or
of the interfacing elements. This is necessary to as-
walls rather than to maintain tight control of actual
sure that adequate clearances exist throughout.
haunch location dimensions from the end of the
Where the reinforcement extends out from the mem-
member.
ber, be sure to evaluate the position of the reinforce-
ment relative to the features it must interface with.
8.14 Tolerances on Location of Sleeves Cast through all of the angles of motion involved in the
in Prestressed Products erection process.
In special situations where complex reinforcement
The sleeve location tolerance should be secon- patterns must be interfaced during erection, steps
dary to the location tolerance of the strands unless should be taken to assure that the proposed arrange-
otherwise noted on the project shop drawings. The ments are workable. A common error is to lay out a
tolerance on sleeves may be affected by slight reloca- reinforcement clearance plan using reinforcing bar
tion of the sleeves necessitated by the location of pre- centerline to centerline dimensions and not appropri-
stressing strands within the member. ately considering the consequences of the bar diam-
For horizontal and vertical sleeve location toler- eter or the consequences of hook bending and length
ances, consideration should be given to the location tolerances. This is more of a consideration with larg-
of both straight and deflected prestressed strands, er diameter reinforcing bars which are relatively
the function of the sleeve, and its proximity to other closely spaced.
sleeves.
24
If a producer subcontracts the reinforcing bar ACI specified bending tolerances is not suitable to
bending to an outside supplier, early and frequent meet the tolerance requirements of member fabrica-
checks of bending accuracy should be made. Addi- tion. For this reason some producers bend their own
tionally, in some instances special bar bending toler- bars or require their suppliers to work to bending tol-
ances may have to be specified in the contract with erances that are more stringent than those pre-
the bar bending fabricator. scribed by ACI.
Note that for some types of precast members, pro-
ducers find that reinforcement bent to conform with
25
8.16 Tolerance on Position of Strand Deflec-
tion Points
Fig. 8.17 .1 Warping Definitions for Panels
Strand hold-downs and other strand deflection de-
vices frequently have their positions dictated by the
requirement that they be fixed, either to the form itself
or to the form support, so that suitable strand hold-
down structural capacity is achieved. Often these
hold down locations are on a lattice grid that may
have a spacing as great as 40 in. [1020 mm] between
location points.
These casting bed structural conditions affecting
strand hold down location can frequently result in
available hold down positions being as much as ± 20
in. [±51 0 mm] from the specified location. If hold
down locations are specified closer than this, the ar- ADJACENT CORNER
chitect/engineer should be contacted prior to revision
of any specified hold down tolerance.
Special strand hold down location tolerances may
be required for cantilevers and other special condi-
tions. More precise placement of strand deflection
points will increase the cost of these members. The
vertical position of the hold-down is usually more im-
portant than the horizontal position.
26
Fig. 8.17.2 Definition of Bowing for Panels
Exposed face ~
I
Max. bowing 0)
Max. bowing 0)
Bowing
(cross section)
Exposed face
(convex)
Bowing 0)
(elevation)
Exposed face
(concave)
Length of
bow
(elevation)
Max. bowing 0)
Precast
concrete
panel
Length of bow
(cross section)
27
Fig. 8.17.3 Differential Bowing of Panels Panels which are relatively thin in cross section,
when compared to their overall plan dimensions, are
more likely to warp or bow as a result of a number of
design, manufacturing, and environmental condi-
tions.
To reduce the potential of panel warping or bowing
(i) 0 0 0 ® ® after erection, consideration should be given by the
architect/engineer for panel length, shape and the
===,== number and location of tie back connection points.
The producer and the architect/engineer should
L PRECAST
CONCRETE
collaborate in the decisions regarding maintaining or
PANELS relaxing bowing and warping tolerances. Appear-
ance requirements, the required type and spacing of
CROSS SECTION OF FACADE connections, and the experience of the local precas-
ter regarding overall economic and construction fea-
sibility of panels with various levels of bowing and
warping tolerance should be discussed with the ar-
chitect/engineer.
Similarly, panels which are manufactured using
large aggregate concrete mixes (above% in. [19 mm]
aggregate) or members which are fabricated from
non homogeneous materials such as two significant-
Surface Out of Planeness Tolerance ly different concrete mixes, special veneers, insulat-
ing mediums, etc., require more careful consideration
Surface out of planeness, which is not a character-
of all aspects of fabrication, storage, and handling
istic of the entire panel shape, is defined as a local
with regard to bowing and warping.
smoothness variation rather than a bowing variation.
Examples of local smoothness variation are shown in
Fig. 8.17.4.
The tolerance for this type of variation is usually ex- Fig. 8.17.4 Local Smoothness Variations
pressed in inches deviation from a 10ft. [3m] straight
10' (3 m )
edge. The tolerance should be checked with a 10ft. Exposed sur-
[3m] straightedge or the equivalent, as shown in Fig. face of pre-
r- Variation in local cast concrete
8.17.4 unless other methods are specified or agreed smoothness
to. Fig. 8.17.4 also shows how to determine if a sur-
/
v panel
28
9.0 Special Tolerance Considerations 9.4 Statistical Tolerance Concepts
The function of members within the building or Any special measuring or record keeping meth-
structure and the employment of special manufactur- ods specified in the contract documents should be
ing techniques used to produce certain members observed by the plant quality control personnel. An
may warrant special tolerance considerations which understanding of statistical methods as they apply to
should be discussed by the producer with the archi- dimensional control can be helpful in developing proj-
tect/engineer. ect tolerance control plans which account for mem-
For example groups of inserts or cast-in items ber product tolerances, interface tolerances, and
which must be located in close relative tolerance to erection tolerances.
each other should not be separated onto two different While statistical concepts may not be commonly
panels by a joint unless special measures are taken employed in the dimensional control of precast prod-
to achieve the desired relative tolerances. ucts, it may be advantageous for producers to con-
sider this approach in certain circumstances for at
least two reasons: First, a random sampling of specif-
9.1 Considerations for Tolerances of Archi-
tectural Members ic measurements and subsequent statistical analysis
of these measurements can create quality control re-
In the context of tolerances, "architectural panel or lated economies on projects which have a large num-
member" refers to the class of tolerances specified ber of identical pieces with stringent tolerance re-
and not necessarily to the members' use in the final quirements. Concrete railroad tie production and
structure. Article 10.1 of this document defines archi- close tolerance interlocking tunnel liner elements are
tectural tolerances for typical architectural panels. Ar- examples of such instances.
chitectural panels, for example, require more strin- Second, statistical concepts can be used as a tool
gent tolerances due to the visual considerations in developing the tolerance control requirements for
which apply to the final construction. specific production operations. By proper sampling
and analysis, one can determine more precisely
which types of member features require more atten-
tion in the fabrication process and this can be imple-
9.2 Tolerance Considerations for Visible
mented in the production and quality control pro-
Structural Members
gram. For information regarding this type of statistical
Double tees and hollow-core slabs are often used approach to dimensional control, one should refer to
for wall panels which are exposed as visible elements appropriate publications as listed in the references for
of a building. If more stringent special project toler- this document.
ances are specified and required for these products
when used as visual elements, special production
methods and tolerance verification methods will be 9.5 Tolerance Considerations for Segmental
required. The same high degree of dimensional preci- Precast
sion associated with purely architectural panels
should generally not be specified for double tee or Segmental precast projects are, by definition, spe-
hollow-core panels since the manufacturing tech- cial projects from the tolerance point of view. These
niques for the product when used as a visible element projects will have unique tolerance requirements and
is generally the same as for the structural product for will require consideration of tolerances at all levels of
which these elements are more commonly used. the project, including design, member fabrication,
erection, and sub system installation.
For precast segmental construction using short
line forming techniques, precision surveying systems
9.3 Tolerances for Structural Members
should be provided so that levels and horizontal align-
Unless otherwise specified on the shop drawings, ment are measured to the very high levels of accuracy
tolerances for structural members should be as out- unique to each project using this construction meth-
lined in Article 10.0 of this document for the members od. For all other types of segmental construction,
designated as "structural members" (excluding Ar- surveying should be provided to an accuracy of ± 1/a
ticle 10.1 and Articles 10.29, 10.30, and 10.31 which in. [3 mm].
give architectural tolerances).
29
For precast segmental construction using match- casting a new segment. In addition to the computed
cast segments, careful checks of both measure- as-built casting curves for vertical and horizontal
ments and computations of geometry should be deflections, a cumulative twist curve should be com-
made before moving segments from their casting puted using the measured cross slopes ofthe individ-
position. Dimensions from segment to segment ual units as a check on the extrapolated deflections.
should be adjusted to compensate for any deviations In computing set up elevations in the match-cast pro-
within a single segment so that the overall alignment cess, priority should be given to correcting twist er-
of the completed structure will conform to the dimen- rors by proper counter-rotation. The segment in the
sions shown on the plans. Computed as-built coordi- match cast position should not be subjected to
nates of all sections cast should be completed before stressing that would induce twist.
30
10.0 Product Tolerance Listings the location of multiple embedments should always
be measured from the appropriate control surface,
The following pages give dimensional require· rather than measuring some from a member edge
ments for a range of standard precast concrete and and others from intermediate embedments. The
precast, prestressed concrete products. These toler· member diagrams in this section show the location of
ances are guidelines only and each project may have features to which the tolerances apply. They are not
project tolerances specified which are different from intended to show the most appropriate reference lea·
those shown. Article 10.1 defines architectural panel ture for measurement. The appropriate dimensioning
member tolerances. Articles 10.2 through 10.25 de· system to achieve the desired tolerances should be
fine tolerances for structural members. Article 10.26 established by the engineer and shown on the pro·
Railroad nes, is a special product tolerance. Articles duction drawings.
10.27 through 10.29 defme tolerances for architectur· Camber tolerances have special considerations.
al trim elements. For members with a span-to-depth ratio at or exceed·
During the pre and post pour check of precast ing 25, the camber tolerance given herein may not ap·
member dimensions, the quality control inspector ply. If the application requires control of camber to the
should have the approved version of shop drawings listed tolerance in beams with high span-to-depth ra·
for reference. Any discrepancies found should be tio, special production measures may be required.
noted on the post pour record and transmitted to The precaster should be consulted regarding this re·
management or engineering for evaluation and reso- quirement.
lution, which may include design of any structural or Prediction of camber in a prestressed member is
appearance revisions which may be necessary. based on empirical formulas. The accuracy of these
Product tolerances are necessary in any manufac- estimates decreases with time. Measurement of cam·
turing process. They are normally determined by ber for comparison to predicted design values should
function and appearance requirements, and by eco- be completed within 72 hours of transfer of prestress·
nomic and practical production considerations. Toler- ing force.
ances for manufacturing precast products are stan- Temperature variation across a member section
dardized throughout the industry and should not be can have a significant impact on the measured cam·
reduced, and therefore made more costly, unless ab- ber. Camber should be evaluated under conditions
solutely necessary. that minimize the effect of temperature variation due
The tolerances listed herein are the minimum ac- to solar radiation, such as early in the morning.
ceptable criteria in the absence of other specifica- When the finished floor or deck surface is created
tions. Projects under the control of special authori- by the precast elements as erected (pretopped), the
ties, such as state highway departments for bridges, overall depth of the member becomes a primary con-
will often have a full set of tolerances specified. In trol feature and the deck surface becomes a primary
these situations, the tolerances specified by the con- control surface for both fabrication and erection. In or-
trolling authority may govern. der to achieve the desired tolerances on the overall
For products not specifically listed, select the ap· floor or deck it may be necessary to use special pro·
propriate tolerances from the listed type (or types) duction measures to control camber and differential
that most closely matches the function of the product. camber among the adjacent elements.
A dimensional layout and measurement plan is Refer to Article 8.17 for a definition and discussion
needed to control the production of precast elements of bowing, warping, and local smoothness toler·
so that the measurement process does not result in ances.
unintended accumulation oftolerances. For example,
31
Fig. 10.1.1 Architectural Wall Panels
.,
Allowable angle
~tationl 4
r- I
~
~ [/ I-:; .2
)
~+
~
'f-. I / ~
_, ~
I
I
a,
~
Arch1tet.iurally 1
exposed surface
Architectural panels
32
10.1 Architectural Wall Panels*
33
0 = Position of sleeve ............................................ . ± 1l2 in. [±13 mm]
p Position of insert .............................................. ±'12 in. [±13 mm]
q = Position of handling devices ........................... . ±3 in. [±75 mm]
r1 = Location of bearing surface from end of member . . . . . . . . . . . . . . . . . . ± 114 in. [±6 mm]
s1 = Reinforcing steel and welded wire reinforcement:
Where position has structural implications or affects concrete cover .. ±'/4 in. [±6 mm]
Otherwise .................................................... ±'12 in. [±13 mm]
s3 = Reinforcing steel extending out of member ....................... ±'12 in. [±13 mm]
s4 = Location of strand:
Perpendicular to panel........................... . . . . . . . . . . . . . . . ±%in. [±6 mm]
Parallel to panel ............................................... ±1 in. [±25 mm]
w2 Location of flashing reglets at edge of panel ....................... ±'Ia in. [±3 mm]
w3 = Size of reglets for glazing gaskets ................................ ± 11a in. [±3 mm]
z Electrical outlets, hose bibs, etc ................................. ±'12 in. [±13 mm]
* Units shall be manufactured so that the face of each unit which is exposed to view after erection
complies with the following dimensional requirements.
t Unless joint width and fit-up requirements demand more stringent tolerance.
<Applies to both panel and to major openings in panel. Tolerances apply to the difference of the two
diagonal measurements.
34
This page is intentionally left blank.
35
Fig. 10.2.1 Solid or Insulated Flat Structural Wall Panels
c, i
-------------------------.- Cj t
Cross section
w
a
q, 10'
I:
'~
!3 h~
I
- - i
----+
~~ -B-j
-~
f----
I
;0
I n2
~IL
I
I i il1 '2
+~
I -®----
I
--EJ-
I
I
L
~
r-
I
i
n,
9 4
- n,
p
Plan
,,
Elevation
36
10.2 Solid or Insulated Flat Structural Wall Panels
k1 = Location of strand perpendicular to plane of panel ................. ±'/• in. [±6 mm]
q1 Location of handling device parallel to length of panel ............. ±6 in. [±150 mm]
q2 = Location of handling device transverse to length of panel ........... ±1 in. [±25 mm]
r1 Location of haunch bearing elevation from end of panel ............ ±'/• in. [±6 mm]
r2 = Transverse distance between haunches . . . . . . . . . . . . . . . . . . . . . . . . . . ±'I• in. [±6 mm]
37
Fig. 10.3.1 Ribbed Structural Wall Panels
~L
Cross section
----a---
J
p
Plan
'I I,
/f"\.. ~
I
I
I
L
jl ,,
Elevation
38
1 0.3 Ribbed Structural Wall Panels
q1 = Location of handling device parallel to length of panel ............. ±6 in. [±150 mm]
q2 = Location of handling device transverse to length of panel ........... ±1 in. [±25 mm]
r1 Location of haunch bearing elevation from end of panel ............. ±V.in. [±6 mm]
39
Fig 10 ..
41 Hollow-core Wall Panels
I.
b
c,~
~-
CC .O.GJ.u.O.C.Ow
c:T
0.
k1 f k
k
Cross section
d
n,
ll I. 10· •
1
ht
I --1
~
-
I n,[---tffi----
I
I
I
~
I
~ --~--_1
-;T i -;J
I,
Plan
40
10.4 Hollow-core Wall Panels
i1 = Differential bowing between adjacent panels of the same design ....... %in. [13 mm]
Warp ........................................ •;,, in. per foot [1.5 mm per 300 mm]
k Center of gravity (CG) of strand group ............................ ±V• in. [±6 mm]
k1 = Location of strand perpendicular to plane of panel ................ ±V2 in. [±13 mm]
Minimum cover .................................................. '~• in. [19 mm]
*Some hollow-core production systems do not permit the incorporation of embedments. Contact
local producers for suitable alternate details if embedments are not practical.
41
Fig. 10.5.1 Brick Faced Architectural Elements
e c
=+== =4
Section A-A
42
10.5 Brick Faced Architectural Elements
b Variation in width of exposed mortar joints ......................... ±'Ia in. [±9 mm]
43
Fig 10..
61 Double Tees (Untapped & Pretopped)
l I _:1
"'"'~'
~
w
-t-----! if+.,
-t-
I
r
lr b2
b-4J
I
L
b3
Cross Section
q2
r -
I.
10'
.I
-T
h!
~
.I - - - -
~~2
I I
I
~
'
=--1
'
- -
I '
' ~
l r- +
'
~T
J p
I,
n,
Plan
12
1\= ]
I
- - I • -
I
I
m2
I
t-r ' I
J k,
a
.I 9
.I .,j J
Elevation
44
10.6 Double Tees (Untapped & Pretopped)
45
Fig 1o. 7 1 Single Tees (Untapped and Pretopped)
Cross section
n,
Plan
12
r
I~
- 12 ]
I - I + -
I
m2L I
J
II
k,
rgr T
I
I
mj t--
0
a
.I
Elevation
46
10. 7 Single Tees (Untapped and Pretopped)
47
Fig. 10.8.1 Columns
Cross section
,,
!
-------~~~~I'L_@~~PL_~-==~~hj~----~~~1
JL
I
LJ
JL
Ll z
-- I I-- 1
~ e
Plan
lr lz + 'lr
I
I
qzl o
t I
I
I
L
j
I
,T
Elevation
48
10.8 Columns
49
Fig 10..
91 Building Beams and Spandrel Beams
b, b,
:' :'
SJ t
1
n n
,---
~~~
c
k+ 1 ~-~-l3
- b,r n
-+13
c
LJ i
I. b .I
Cross sections
u
q,
0
.----
n q=-l
~-
/
I.
-
10'
"'
.I
----~
ht
t
I
~~
I
Plan
s,
I,
SJ
lr !'''
-----
!I
II--- - ~
I
I
I
~
- - r-r+ -------- ~
m, I
Jl k, .I g
m, 1J
I~ Elevation
a
50
10.9 Building Beams and Spandrel Beams
m2 = Tipping and flushness of bearing assembly ....................... ±'Ia in. [±3 mm]
0 = Location of sleeves cast in stems, in both horiz. and vertical planes .. ±1 in. [±25 mm]
p = Location of inserts for structural connections ..................... ±'12 in. [±13 mm]
q1 = Location of handling device parallel to length of member ......... ±12 in. [±300 mm]
q2 = Location of handling device transverse to length of member ........ ±'12 in. [±13 mm]
Sj Longitudinal spacing of stirrups .................................. ±2 in. [±50 mm]
s2 = Longitudinal spacing of stirrups within distance "c" from member ends
.............................................................. ±1 in. [±25 mm]
S3 = Stirrup projection from beam surface ............. + V. in., - 'l2 in. [ +6 mm, -13 mm]
51
Fig. 10.10.1 I Beams (Girders) or Bulb Tee Girders
10"
1· ~
·1 h~
I -~
/
"-- t
I q2
~- -t_~- ~~- -~-- - - - --f~
1- •J p
I. 11
.I
Plan
LJ
''
'''
' ' I
J I: ----~----~f·r-------;;, .,J_~
Elevation
52
10.10 I Beams (Girders) or Bulb Tee Girders
m2 = Tipping and flushness of bearing assembly ....................... ±'Ia in. [±3 mm]
p Location of inserts for structural connections ..................... ±'12 in. [±13 mm]
q1 = Location of handling device parallel to length of member .......... ±6 in. [±150 mm]
q2 Location of handling device transverse to length of member ......... ±1 in. [±25 mm]
s1 = Longitudinal spacing of stirrups .................................. ±2 in. [±50 mm]
s2 = Longitudinal spacing of stirrups within dist. "c" from member ends ... ±1 in. [±25 mm]
s3 Stirrup projection from beam surface ............. ±V. in., -'12 in. [±6 mm, -13 mm]
• The location of harped strand at the end of the beam may be controlled to ±'12 in. [±13 mm] provid-
ing that calculations show that such a variation will not result in unacceptable stresses at any design
load condition.
53
Fig. 10.11.1 Box Beams
•••••• ·-1---_I
c2
Cross section
.,
10"
1· ·1
~ --~- ~---~ --- ----
L.._-J/1----1--1- - + - - -~- 1' II
pc*- p
~-------
-----------1----,~--0~-0~
__ II _ _ _ _ }
J-
d I,
Plan
s,
12
s2 ~ II
T T T
I t I i I l
~-----
I -- - ~-=+-
I I I
-- -
-:J_.
I
I
-
I - -~ 02
l_:_J I
I I
gr
J .I ~r "'J~
:
k,
Elevation
54
10.11 Box Beams
a = Length ....................................................... ± 3/4 in. [±19 mm]
m2 Tipping and flushness of beam seat bearing surface ............... ± 11a in. [±3 mm]
q1 = Location of handling device parallel to length of member .......... ±6 in. [±150 mm]
q2 = Location of handling device transverse to length of member ......... ±1 in. [±25 mm]
55
Fig. 10.12.1 Poles
b, b, b,
_:1
r
c
b3
0
Sections
n p o,
t+-
I ·- J ·-
t-
I
I
t • •
I
I [g) 0 0
I
I
j
L
f t
d,J - o,
Elevations
56
10.12 Poles
f = Sweep ............................ ±V• in. per 10ft. or ± 1/2 in., whichever is greater
[±6 mm per 3m or ±13 mm, whichever is greater]
p = Location of insert for matching hardware pattern ................... ±'h in. [ +3 mm]
57
.
Fig 10 13.1 Hollow-core Slabs
I c, ~ I
f/.O.W.U.G.Q.O.~l
i cJ k,
k2
Cross section
d 10'
ll I. .I 11_
I,
- L
I
I
- - ~
~r-- I
I,
I
-t-- -
I
I
I
I ~
n
I>KI
f
+--- ~
I I_ n,
I
a
Plan
12
-- -- -
- ----- -
-
- -
--
1------ - --I
J~
Elevation
58
10.13 Hollow-core Slabs
• Some hollow-core production systems do not permit the incorporation of embedments. Contact
local producers for suitable alternate details if embedments are not practical.
59
Fig. 10.14.1 Piling (Hollow and Solid)
b b b
.I
~~
•
w
----- _ _j
J
·0·
~ bd
Cross sections
d.J L
L --
--
1. h t10'
.I
Side
60
10.14 Piling (Hollow and Solid)
• Controlling pile length to +6 in., -2 in. [+150 mm, -50 mm] is acceptable in most cases.
61
Fig. 10.15.1 Tee Joists/Keystone Joists
b
_ q,::). 'L __ L
q2 /- ~ =========-1 =====-· 4=== ·-=
'=~------E-----+-------
L ------- ~T---=_T---------~==f===
cJ 11 1J J at --,, 10" .I hT-
0
Plan
51
1/ 521
rrr___j
Elevation
62
10.15 Tee Joists/Keystone Joists
k1 = Location of harp points for harped strands from design location ... ±20 in [±510 mm]
11 = Location of embedment ........................................ ±1 in. [±25 mm]
12 = Tipping and flushness of embedment . . . . . . . . . . . . . . . . . . . . . . . . . . . . ±'I• in. [±6 mm]
m1 = Location of bearing assembly .................................. ±V2 in. [±13 mm]
m2 = Tipping and flushness of bearing assembly ....................... ±Vain. [±3 mm]
0 = Location of sleeves cast in stem, in both horiz. and vertical plane ±1 in. [±25 mm]
p = Location of insert for structural connections .................. . ±Y, in. [±13 mm]
Q1 = Location of handling device parallel to length of member .......... ±6 in. [±150 mm]
q2 = Location of handling device transverse to length of member ......... ±1 in. [±25 mm]
51 = Longitudinal spacing of stirrups .................................. ±2 in. [±50 mm]
52 Stirrupprojectionfrombeamsurface ............. +'/•in., -Y,in. [+6mm, -13mm]
63
F"IQ. 10.16 ·1 Step Units
a d
- I l
I
I
I
b I-
,, I
I
~
I
I
j I
~
I
I I, I ~
I
!
Plan
Elevation
64
10.16 Step Units
c1 Individual riser depth (not cumulative) ............................ ± 3As in. [±5 mm]
c2 = Riser variation from specified plane ................ + '18 in., -0 in. [ +3 mm, -0 mm]
e = Variation from specified elevation end squareness or skew . . . . . . . . . . ±V. in. [±6 mm]
* Local building codes may restrict the maximum height differential between risers. The building
code shall govern.
65
Fig. 10.17.1 Sheet Piling
JL
Elevation
Section
.---- ,..--~=-=-=--=------_--_--_-_--_-_--_-_-------------~..L_-_--_-_--_--_-_--_-_--_-_--_-+-.....:-=--=-=-=~.....,
•
I I
I
n 1 Stirrups
n I A
I I/
~----t-t-1~
i I
I I
I I
I I
I I
-------------------------------------------------------1-------L __ l____
I I
l
I
Plan
66
10.11 Sheet Piling
e = Variation from specified plan end squareness or skew .............. ±'I• in. [±6 mm]
q, = Location of handling device parallel to length of member .......... ±6 in. [±150 mm]
q2 = Location of handling device transverse to length of member ........ ±'12 in. [±13 mm]
67
Fig. 10.18.1 Stadium Riser
~
I
""' r 1
I
a m2 __J m 1• r--
Elevation
r Centerline of hole at
connection to support a
Plan
68
10.18 Stadium Riser
m2 Tipping and flushness of bearing assembly ....................... ±Vs in. [±3 mm]
q1 = Location of handling device parallel to length of member .......... ±6 in. [±150 mm]
q2 = Location of handling device transverse to length of member ......... ±1 in. [±25 mm]
69
Fig. 10.19.1 Multi-Stemmed Bridge Units
b
~--
c, ~ I I I i I "l
t- r. I
I
I
I'
I
I
!
I
J -i
c,
c
kL.
~~
m3L
I I
I
I
I
I
I
- I
'
b,
i il
b '--:-
I I ::_l_.JI'--
Cross section
~~
Jn, i b
I
I
I
I
- 1 -
L
Plan
q,
r---,
I I
''L - i
I
h
I
I
I I
I
I
I
i I
I
I
I
I
,f - - - - - ------ -
I
. . .
- -- -- ----o·-
.
--=~=~l~=-=:.-=-~=~=---
I
0
I
I m,l
I
L - -
I--
gi k,
i __jm, 1--
a
Elevation
70
10.19 Multi-Stemmed Bridge Units
d Variation from specified plan end squareness or skew ............. ±%in. [±19 mm]
e = Variation from specified elevation end squareness or skew ......... ±%in. [±19 mm]
k1 = Location of harp points for harped strands from design location .... ±6 in [±150 mm]
m3 = Differential elevation of bearing surface between stems ............. ±'/16 in. [±2 mm]
q2 = Handling device location transverse to member length ............. ±1 in. [±25 mm]
s = Longitudinal spacing of stirrups .................................. ±1 in. [±25 mm]
71
Fig. 10.20.1 Modular Room Unit
a a,
,--c,
'
I,
---~--t D
I
: ----r~r--=-----.-----~
I \
I I z I
c
.---~~-+~--
\ I D ~I\
I I ;-73 n
'21--q--~ :
z 1
j I n L
Elevation
I I I
r-----------, r------
-
: : 1
I
l J
--- ~~,,,
/
/
/
/
/
a ) r
I I I Recess
I I I
I I I
I b I I
,____ 1 I I
I I I
I I I
I I I
L--------------~ L------r---
________ 1_ __
a,
I- ----~~~============= -------
:r-- 12
:----=
I
/1
/ I
I
'-----L------------' L _ _ _ __ I
I
Plan Tilt
72
10.20 Modular Room Unit
b = Width (overall):
Single unit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ± 'I• in. [±6 mm]
Multiple unit .................................................. ± 1/2 in. [±13 mm]
d = Variation from specified plan end squareness or skew . . . . . . . . . . . . . . ±V. in. [±6 mm]
e = Variation from specified elevation end squareness or skew . . . . . . . . . . ±'AI in. [±3 mm]
Note: Tolerances for project specific items, such as security hardware, mechanical/electrical/
plumbing embedments, doors, and windows, should be included in the contract documents.
73
Fig. 10.21.1 Prestressed Concrete Panels for Storage Tanks
Plan
b e
11
c
e
Li'
r---------------
·1r
\
I
,,
,, ~
0
I I
0 I \
I I
0 I I
~~
I I
I I
0 I I
0 I I
I
.__0
I a
I
,--
I
0 0
I
I
I
I n, ,,
r
I I
k,
0
I
I
I
I
I
I
I
I I
0 I I n,
n,
I
I
I
I
hL k,
e
I -
L----- -- 1~.c--
Elevation Elevation
74
10.21 Prestressed Concrete Panels for Storage Tanks
h = Local smoothness:
Horizontal surface ..................................... 'Ia in. in 10ft. [3 mm in 3 m)
Vertical surface ....................................... y, in. in 10ft. [6 mm in 3m)
i1 = Differential bow between adjacent panels of the same design .......... 'Ia in. [10 mm)
75
Fig 10 22 1 Bridge Deck Units
(\ (\
_J (\ _j
k, L --1 I ~ c
I Elevation
I
I.
------
______ _j________
------
~
----; i -
I
-----1 - - - -
I
I
LJ
k2
I
!
s, -
-
b
r---t
-I-
- -
I
-
I
r--
-
-+ I
r--
----t-I f--
i - - - r--
I
f--
T
~s3L
I
_J L
Plan
76
10.22 Bridge Deck Units
d ~ Variation from specified plan end squareness or skew .............. ±V. in. [±6 mm]
k1 ~ Location of strand perpendicular to plane of panel ................. ±'Is in. [±3 mm]
k2 Location of strand parallel to plane of panel ....................... ±'I• in. [±6 mm]
51 ~
Longitudinal spacing of stirrups .................................. ±1 in. [±25 mm]
53 ~
Strand projection from end ..................................... ±'12 in. [±13 mm]
77
Fig. 10.23.1 Segmental Box Girder
e
f
Elevation
78
10.23 Segmental Box Girder
c1 ; Depth oftop and bottom slab .................................. ±3fs in. [±10 mm]
Note: The above tolerances should be compared to the specific requirements of the project toler·
ance control plan and adjusted as necessary.
79
Fig. 10.24.1 Pier Deck Units
c:_
----------------~l __________________
~--- -
t
~
I
I
I
I
v I
I
I
I /
I
I
I
J I
I
n2 I
I
I
I b
I I
I
I
I
/
l I
I
I
I L/
I
I
! q2
I a t I
Plan
r n lsi n
q,
1---
I
I
I
II 0 c
L:..
I
Elevation
80
10.24 Pier Deck Units
d Variation from specified plan end squareness or skew ............. ±'12 in. [±13 mm]
e = Variation from specified elevation end squareness or skew ......... ±'12 in. [±13 mm]
q1 = Location of handling device parallel to length of member .......... ±6 in. [±150 mm]
q2 = Location of handling device transverse to length of member ......... ±1 in. [±25 mm]
81
Fig. 10.25.1 Box Culvert
c,
l
- ±i
c,
c ~
b
c,
Cross section
~----------------------------------------
Longitudinal Section
82
10.25 Box Culvert
b Span:
Less than 48 in. [1.2 m] ........................................ ± 711s in. [±10 mm]
48 in. [1.2 m] to 96 in. [2.4 m] .................................. ±3f• in. [±19 mm]
Greater than 96 in. [2.4 m] ...................................... ±1 in. [±25 mm]
b1 = Thickness* of walls ........................... - 311s in., +1 in. [ -4.5 mm, +25 mm]
c = Rise
Less than 48 in. [1.2 m] ........................................ ± 711s in. [±10 mm]
48 in. [1.2 m] to 96 in. [2.4 m] .................................. ±%in. [±19 mm]
Greater than 96 in. [2.4 m] ...................................... ±1 in. [±25 mm]
*Refer to ASTM C 850 and ASTM C 789 for reinforcement placement tolerances.
83
Fig. 10.26.1 Prestressed Concrete Railroad Ties
b,
Y•
[pJ ""
""
" "'
""
""
/
")\/
'-
• • • •
• • • •
b,
.I
Section Detail
Y3
- I
r-....,
y,_,
,..~
I ~
' ' ''\..-J'''
'' ' I I
L_j ' ' ''\... ..---''''
...''_j'
I I
I I
I I
I
IV
Elevation
1
Centerline of
rail seat
\II! :
--- ----a+a---------------a+a---- ~---
i i
a
Plan
84
10.26 Prestressed Concrete Railroad Ties*
h = Local smoothness ............................. v,, in. over 6 sq. in. area of rail seat
[1 mm over 3870 mm 2 area of rail seat]
* Current tolerances as published by AREMA Committee No. 30 should be reviewed prior to produc-
tion.
85
Fig. 10.27.1 Sills, Lintels, Copings, Cornices, Quoins and Medallions
..--
1-T-l
I I
--
I
--
c,
c
L-..1 : : :
- - - - -~----- ----------
~
'
I
rj
b, :
b
----------~==~~------------------~
---
- -- -
t
~
- - -- --
~
' ' ~ h
a t
86
10.27 Sills, Lintels, Copings, Cornices, Quoins and Medallions
t Size and location of rustications and architectural features ........ ± 1Aa in. [±1.5 mm]
87
Fig. 10.28.1 Bollards, Benches and Planters
I I
I. b
.I
88
10.28 Bollards, Benches and Planters
89
Fig 10 29 1 Pavers
I -
I
---- --- --
3 j
90
10.29 Pavers
91
11.0 Erection Tolerances ance system as a first priority before any precast
members are cast. It is in the interest of all concerned
The text below discusses the tolerance principles that the architect/engineer and the party or parties re-
and considerations related to the erection and ac- sponsible for the tolerances of the interfacing struc-
ceptable matching of precast and prestressed con- ture agree in writing to the overall project tolerance
crete members when they are used for the entire system.
structure or in combination with other structural sys- In general, the more restrictive the erection toler-
tems. It is important to understand the relationships ances, the higher the cost of erection will be. For ex-
of product, interfacing and erection tolerances, as all ample, combining liberal product tolerances with re-
must be taken into account on each project to assure strictive erection tolerances may place a significant
satisfactory panel and member installation. Erection cost burden on the erection phase of the project. This
tolerances are used in the planning of the erection ac- can negate any cost or time saving the designer ex-
tivity to assure that the elements can be assembled pected to achieve by specifying less stringent prod-
to fit together as an integrated building structure. uct tolerances.
It should be noted that in some instances project
erection may be done by a company which may have
no direct contractual relationship with the precast 11.1 Recommended Erection Tolerances
concrete member manufacturer. If this is the case,
The recommended erection tolerance values are
the party with contractual authority over the erector is those to which the member primary control surfaces
responsible for assuring that the project erection tol- are to be set. It is the position dimensions of the pri-
erances are met by the erector. mary erection control surfaces which should be con-
Erection tolerances are determined by consider-
trolled during erection. The remaining position di-
ation of the characteristics of the building structure,
mensions of the member features and secondary
and site erection conditions. They should be devel- control surfaces of the member will be the result of the
oped to achieve uniform joint widths and planar wall combination of the erection tolerances given here
panel conditions. Important features include: individ-
and the appropriate product tolerances given in Ar-
ual member design, shape, thickness, composition ticle 10.0. Also see Article 14.0 for a discussion of
of materials, and overall scale of the member being
clearances.
erected. The specified erection tolerances may affect
Erection tolerances shall control the individual pre-
the work of several different building trades and must cast members as they are located and placed in the
be consistent with the tolerances as specified for
assembled structure. The primary control surfaces or
those trades.
features on the precast members shall be erected to
To understand the importance of erection toler- be in conformance with the established erection and
ances specified, the function of the precast concrete interfacing tolerances. Clearances are generally al-
components should be considered when specifying
lowed to vary so that the primary control surface can
erection tolerances. For example, members which be set within tolerance. Product tolerances shall not
are covered by finish materials may not need the be additive to the primary surface erection tolerances.
close tolerances required for those that are exposed Secondary control surfaces which are positioned
to view. Members used for an industrial building may
from the primary control surfaces by the producttoler-
not require tolerances as restrictive as those used for
ances are usually not directly positioned during the
a visually sensitive commercial or residential applica-
erection process but are controlled by the product tol-
tion. erances. Thus, if the primary control surfaces are
One way to foster collaboration wtth regard to di- within erection and interfacing tolerances, and the
mensional control is for those responsible for erection
secondary surfaces are within product tolerances,
to participate with plant quality control personnel in the member should be erected within tolerance. The
the development of the member dimensional inspec- result is that the tolerance limit for secondary surface
tion plan. By doing this, the plant quality control per-
may be the sum of the product and erection toleran-
sonnel will understand the product tolerances which ces. To ensure trouble-free installation, the product
are critical to the successful erection of the project. tolerances, generally, must not exceed the erection
It is recommended that the producer review pro-
tolerances. An example is the elevation of a second
posed tolerances with the architect/engineer and story corbel on a multi-story column whose first story
erectors prior to agreeing to the final project toler- corbel is selected as the primary elevation control sur-
ances. If a producer encounters project specifica-
face.
tions in which no mention is made of the tolerance to Because erection and product tolerances for
be controlled in a structure to which the precast con- some features of a precast concrete member may be
crete components are being connected, steps additive, the erection drawings should clearly define
should be taken to develop an overall project toler-
92
the primary erection control surfaces. If both primary Windows between open shape members where
and secondary control surfaces are critical, provi- they will intersect a joint between members is an ex-
sions for adjustment should be included. The accu- ample which requires interface erection tolerances. A
mulated tolerance limits may be required to be ac- similar condition often occurs where panels are inter-
commodated in the interface clearance. Surface and spersed with glass or metal curtain wall elements.
feature control requirements should be clearly out- Close tolerances are often required between the mul-
lines in the plans and specifications. lion and the glass or curtain wall. This condition de-
Final erection tolerances should be verified and mands additional tolerance flexibility that may be pro-
agreed upon before erection commences and, if dif- vided by special consideration of the tolerance
ferent from those given in this document, stated in adjustment aspects of corner details.
writing and noted on the project erection drawings. Many of the erection tolerances address the toler-
As-built precast erection tolerances are often largely ance on bearing length. Since the bearing length tol-
determined by the actual alignment and dimensional erance may have an effect on erection safety and
accuracy of the building foundation and frame (in structural integrity of the completed structure, it de-
those circumstances where the building frame is serves special attention both in member fabrication
constructed from some material other than precast and in erection. Problems in meeting bearing area re-
concrete}. The general contractor is usually the party lated tolerances should be brought to the attention of
responsible for the plumbness, level, and alignment the architect/engineer.
tolerances of the foundation and the structural frame, The bearing length and the length of the end of the
including the location of all bearing surfaces and an- member over the support are often not the same, as
chorage points for the precast concrete members. shown in Fig. 11.2.1. Bearing length should be mea-
Project specifications should be checked by the sured in the direction of the member span. Bearing
producer to assure that tolerances have been speci- width should be measured at 90 degrees to the direc-
fied for the site construction work which are compat- tion of the member span. For precastto precast erec-
ible with the requirement to erect precast on the build- tion acceptable bearing tolerance conditions which
ing frame. If discrepancies are discovered, they are required for safe erection should be shown on the
should be brought to the attention of the architect/en- erection drawings. For precast to other materials
gineer and resolved as early in the project as possible erection acceptable bearing conditions must be
and in every instance prior to the start of precast pro- shown in the contract documents.
duction. The producer may collaborate with the archi- If for any reason a member cannot be erected as
tect/engineer to provide special details to accommo- shown on the connection details, within the toler-
date the more liberal tolerances that may be ances outlined in this document, the erector should
associated with these site construction features. To notify the responsible party to check the structural
protect the project cost and schedule by minimizing adequacy of the resulting configuration.
erection problems, the dimensions and locations of For insulated wall panels where beams bear on the
in-place structures should be checked prior to start- interior wythe of the panel, it may be practical to speci-
ing precast erection. fy the beam length so that the tolerance can be taken
up in the insulation. This is one method of avoiding
bearing area deficiencies in this type of element.
11.2 Erection Tolerance Groups
11.3 Field Control of Erection Tolerances
The erection tolerances are given in three groups:
Appropriate field procedures should be followed
1 . Precast member to precast member
to ensure the erection of precast members within the
2. Precast member to cast-in-place concrete or
limits of the project erection tolerances. The general
masonry
contractor should establish (and maintain at conve-
3. Precast member to steel construction
nient locations), control points, bench marks and
Because erection is both equipment and site de- lines in an undisturbed condition until final completion
pendent, there may be good reason for the producer and acceptance of the project. Typically, panels are
and erector to work with the architect/engineer to located in the center of their nominal (basic dimen-
considerably vary some of the recommended toler- sional) location on the building. Panels may also need
ances to account for unique project conditions. This to be adjusted to accommodate erection and product
variation could involve modification of both specified tolerances and the locations of other adjacent materi-
product tolerances and specified erection tolerances. als while providing acceptable joint width.
93
F"'lg. 1121 Beanng Length
- - - - - Precast concrete member
Setback distance
lT
V//~
J Bearing length
I
Length over support
Support
Upon completion of panel alignment and before er erection of the structure to the final grade shown on
other trades interface any materials with the precast the design plans.
members the erector, in conjunction with the general Contractors on segmental bridge projects are usu-
contractor, should verify that the panels are erected ally required to submit deflection and/or camber data
within the specified tolerances. for each stage of construction as required to
No erected member should be left in an unsafe construct the structure to its final grade. The proce-
support condition. Any adjustments affecting struc- dure takes into account the effect of time dependent
tural performance, other than adjustments within the prestress losses and creep which will occur during
prescribed tolerances, should only be made after ap- the construction phase.
proval by the engineer of record. A geometric control plan should provide for regu-
lar monitoring of the superstructure deflections be-
11.4 Erection Tolerance Considerations for ginning with the addition of the first segment erected
Segmental Precast Projects and concluding with the last segment erected.
The control plan should also include the adjusting
An overall geometric control plan for the segmen- procedure to be used should the structure, as
tal project should be prepared. The plan should indi- erected, deviate from the predicted alignment by
cate in detail how the geometry control survey will be more than a specified amount.
performed and the actions proposed to assure prop-
94
12.0 Erection Tolerance Listings These tolerances should be considered guide-
lines for the development of project specific toler-
Erection tolerances for precast members are ances for erection
shown on the following pages.
95
Fig. 12.1.1 Beam Erection Tolerances
_ _ _ _ _ _ Bldg. grid
datum
--J a . c c
-·:tl~~~·~~ ----'d
Vertical primary
control ,,,,,,,;,----+--!
n
Ledge L ~=z:b="' Precast concrete
(N/A at inverted both sides '-----
beam
tee beam) at inverted
tee beam Support element
Centerline of
steel support
Precast element to: precast element, cast-in-place concrete, masonry, or structural steel
96
12.1 Beam Erection Tolerances
The primary control surfaces are usually as shown, a~hough this needs to be confirmed on a
job-by-job basis.
a Plan location from building grid datum ............................ ±1 in. [±25 mm]
e ~ Joint width:
Architectural exposed joints ..................................... ±V• in. [±6 mm]
Hidden joints ................................................. ±%in. [±19 mm]
Exposed structural joint not visually critical ......................... ± V2 in. [13 mm]
Note: When bearing pads are used at unarmored edges they should be set back a minimum of '12
in. [13 mm] from the face of the support or at least the chamfered dimension at chamfered edges.
*For precast elements on a steel frame, this tolerance takes precedence over tolerance on dimen-
sion "a".
t Or member top elevation where member is part of a frame without bearing ledges.
t This is a setting tolerance and should not be confused with structural performance requirements
set by the architect/engineer. The nominal bearing dimensions and the allowable variations in the
bearing length and width should be specified by the engineer and shown on the erection drawings.
97
Fig. 12.2.1 Floor and Roof Member Erection Tolerances
c
Hollowcore plan Double tee plan
b
To allow for
- 3/4" tolerance
antral surface
d deck w/ b To allow tor
-3f4" tolerance
! to' pretopped tee
underside _A
[-19mm] [-19mm] -f' Bearing pad by design
~ %":__ji.Q~=-
ad by design L____ 3/4"
[19mm} as req'd [19m~r- ~~Hoi dback as req'd
Bldg. elevation datum r-L-- - - - - - - - - - - - - -
Hollowcore elevation Double tee elevation
Precast element to: precast, cast-in-place concrete, masonry or structural steel support
98
12.2 Floor and Roof Member Erection Tolerances
The primary control surfaces are usually as shown. A majority of the time there is no designated
vertical primary control surface, and in some scenarios there are no primary control surfaces at all.
This needs to be determined on a job·by·job basis.
a = Plan location from building grid datum ............................ ±1 in. [±25 mm]
a1 = Plan location from centerline of steel support* ..................... ±1 in. [±25 mm]
b = Top elevation from building elevation datum at member ends:
Covered with topping ............................................ ±.%. [±19 mm]
Pretopped tee/carpet direct hollow-core .......................... ±'I• in. [±6 mm]
Untapped roof ................................................ ±%in. [±19 mm]
d = Joint width:
Oto40ft.member ............................................ ±1f,in.[±13mm]
41 to 60ft. member ........................................... ± 3/, in. [±19 mm]
61ft. plus member ............................................ ±1 in. [±25 mm]
e Differential top elevation as erected (for units of same design and length):
Field topped ..................................................... %in. [19 mm]
Pretopped tees at driving lanes/carpet direct hollow-core ............... 'I• in. [6 mm]
Untapped rooft ................................................... %in. [19 mm]
Note: When bearing pads are used at unarmored edges they should be set back a minimum of v,
in. [ 13 mm] from the face of the support or at least the chamfered dimension at chamfered edges.
*For precast concrete erected on a steel frame building, this tolerance takes precedence over toler-
ance on dimension "a".
t It may be necessary to feather the edges to ±'I• in. [±6 mm] to properly apply some roof mem-
branes.
t This is a setting tolerance and should not be confused with structural performance requirements
set by the architect/ engineer. The nominal bearing dimensions and the allowable variations in the
bearing length and width should be specified by the engineer and shown on the erection drawings.
§ Untapped installations will require a larger tolerance.
99
Fig. 12.3.1 Column Erection Tolerances
d d
: r+-
II I 'I
I I.
I
I
I I
II
Plan view
I
I II Splice
I I . _j
:~ ~
Vertical primary
~control surface
~ I
'\r- E
I
Horizontal primary
control surface
(at first corbel)
~
0
!2
I Ill
e II e
0 II
I
0 II II
~ ~
\2
II
b
/
0
I
I
Bldg. elevation ]
I
c _..;,...
-'I
datum
• a
-1
Bldg. grid
_.__ _ _c..__Jc___L_--11 Bldg. elevation I datum -----()
1 datum
Elevation Elevation
100
12.3 Column Erection Tolerances
The primary control surfaces are usually as shown, although this needs to be confirmed on a
job-by-job basis.
e = Plumb in any 10ft. [3m] of element height ............................ 'I• in. [6 mm]
101
Fig. 12.4.1 Structural Wall Panel Erection Tolerances
Horizontal
pnmary
g~r-- fi_ ~~--h
Vertical primary
control surface
control
surface t
-.--- -h1o
b E
c "-
Cast-in-place
01 0
I
foundation or
0
precast
concrete
Cast-in-place or
precast concrete suppo~--_:~=~"-~'
- ~~J~'I=IIE
~~~(= 1 __J k- Nominal joint width
ITillm=m=mlliffi~
Plan Section Elevation
Bldg. grid [
datum Horizontal
primary
control
l_,,r_+--r*==1r-
r--g
1
h
surface
-1 ~ ~ E c E
"-
~ t- ~ "- 0
0 I
I I
0
sLel
structure
-+
--1 a, £r--
of steel structure Nominal joint width
Section
Plan Elevation
102
12.4 Structural Wall Panel Erection Tolerances
The primary control surfaces are usually as shown, although this needs to be confirmed on a
job-by-job basis.
a = Plan location from building grid datum ........................... ±'!'in. [±13 mm]
a1 = Plan location from centerline of steel support ..................... ±'12 in. [±13 mm]
I = Maximum jog in alignment of matching edges ........................ 'h in. [13 mm]
g = Joint width (governs over joint taper) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ±'Ia in. [±9 mm]
h10 = Joint taper over 10ft. length ......................................... 'Ia in. [9 mm]
*For precast buildings in excess of 100ft. tall, tolerances "a" and "d" can increase at the rate of 1/s
in. [3 mm] per story to a maximum of 2 in. [50 mm].
t Refer to Article 8 for description of bowing tolerance.
103
Fig. 12.5.1 Architectural Walls/Spandrel Erection Tolerances
d d Horizontal primary
control surface .A
- r- h
v-
-rtr I IL
''
Vertical primary \ rf-1---L-,
control surface . -------.;. J
e II e h10
':"']" -
"E "E
""0
I
""0
I
-g
b b
<t of steel
~
support ~- r- -~ -~
~ II II
Support
L
member '\ "V=l-
Plan view Side view Elevation view
Walls Walls Walls
Horizontal primary
dd control surface
-rrr
'l~
Vertical primary I
control surface
"E
·'~ L
k
""0 __'j
t
I
gdFd
b
<tof steel
~
support Support
member "v
104
12.5 Architectural Walls/Spandrel Erection Tolerances
The primary control surfaces are usually as shown, although this needs to be confirmed on a
job-by-job basis.
a = Plan location from building grid datum* .......................... ±'I' in. [±13 mm]
a1 = Plan location from centerline of steel supportt ±V2 in. [±13 mm]
g Joint width (governs over joint taper) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ±V• in. [±6 mm]
h10 = Joint taper over 10ft. [3 m]length ................................... 'I• in. [6 mm]
* For precast buildings in excess of 100ft. tall, tolerances "a" and "d" can increase at the rate of Va
in. [3 mm] per story to a maximum of 2 in. [50 mm].
t For precast elements erected on a steel frame, this tolerance takes precedence over tolerance on
dimension "a".
105
Fig. 12.6.1 Single and Double Stadium Riser Erection Tolerances
Riser unit
~ Theoretical
b 1--- Cf of support
,I
Vertical primary
control surface
To allow for
-1"(-25mm) Plan view
tolerance
~1"
(25 mm) -~~1!1-o~ Holdback as required
Shims per design
c
h
p IJ_t:::===con===trolsurtace======~o~
Horlwntal primary ~ n
Elevation view
·n-a
Horizontal primary,_ _ __
control surtace n 1 ~'------ Vertical primary
j \=.. ! g or j control surtace
106
12.6 Stadium Riser Erection Tolerances
The primary control surfaces are usually as shown, although this is something that needs to
be confirmed with the contractor on job-by-job basis.
a ~ Plan location from building grid line datum ±1 in. [±25 mm]
g ~
Joint width {horizontal) at end of piece (Joint
width needs to be V. in. [6mm] minimum) ........................ ±'12 in. [±13 mm]
h ~ Joint width (Joint width needs to be 'I• in. [6 mm] minimum in either case)
90° angle .................................................... ±'/2 in. [±13 mm]
Joint width at skewed ends .................................... ±%in. [±16 mm]
~ Differential camber (at mid-span as erected) between adjacent members of the same de-
sign ......................... ± 3/ " in. [±5 mm] per 10ft. [3m] of member length.
k Differential sweep (at mid-span as erected) between adjacent members of the same de-
sign .......................... His in. [±5 mm] per 10ft. [3m] of member length.
Note: Local building codes may require more restrictive riser height tolerances which could also
affect product tolerance.
107
Fig. 12.7.1 Room Module Erection Tolerance
surface (front)
d d
Building grid or
I
datum (typ) ~---
I
I
I
lar- 1r ·~
I
I
I
l n-··
I
I
"1~J
I
I
~-
I
t I
I
I
I I '
I(
I I cl
I I I I
I
I
II
I'
II
II
I
I
I f [ I
-L
e
-
I I
I II II I I
I I II I I
I b I
I I' II I
:::t ~- - =::::1
--- - - ------=.J
L-- -
li= r- L.
J
c
Horizontal primary control
surface (door head)
108
12.7 Room Module Erection Tolerance
The tolerances listed below are used at the primary control surfaces only, and only those toler-
ances that are applicable to that surface. Normally the primary control surfaces are the front face
of the cell unit as the vertical primary control surface, and either the head of the door (as shown
in Fig. 12.7.1), top of cell, or the bottom of balcony as the horizontal primary control surface. Note:
on jobs where pre-topped balconies are cast as part of the cell unit, the horizontal primary control-
surface may be the top surface of the balcony.
a = Plan location from building grid line datum ...................... ± 112 in. [±13 mm]
109
Fig. 12.8.1 Stair Unit Erection Tolerance
_______ L _________ -o
Plan view
Intermediate landing
Line of topping
0
pan (if applicable)
b
Elevation view
110
12.8 Stair Unit Erection Tolerance
The primary control surface for stair units is the top of landing at floor levels. Tolerances listed
below are the same whether landings are monolithic or separate pieces.
a = Plan location from building grid line datum ........................ ±'12 in. [±13mm]
Note: Local building codes may require more restrictive riser height tolerance which could also af-
fect product tolerance.
*At stair units that have pre-topped precast landings, the maximum jog between stair units as well
as from stair unit to finish floor can not exceed V. in. However, units which have landings that are
topped have more leeway. This needs to be discussed and agreed upon with the general contrac-
tor.
111
..
Fig 12 9 1 Segmental Bridge Element Erection Tolerance
r Precast segment
~
v)
---,.+
Plan
,..A
t_ __[_
I
'
\ 7·
~~·
Elevation
I
o·
~=7
_jb
IT
Section A-A
112
12.9 Segmental Bridge Element Erection Tolerance
c = Longitudinal angular deviation from the theoretical slope change between two successive
segments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . not to exceed 0.003 radians
113
Fig 12.10.1 Circular Storage Tank Erection Tolerances
Precast panel
Cast-in-place pilaster
Plan
Tendon ducts
e
0
o I
0
Section A·A
114
12.10 Circular Storage Tank Erection Tolerances
a = Variation from the nominal tank radius ... ±'12 in. per 50 ft. of radius [±13 mm I 15.2 m]
(Not to exceed ±1 in. [±25 mm])
• In applications which involve an internal surface wiper on the sides of the tank it may be required
that this tolerance be made more stringent.
115
Fig 12.11.1 Pier Deck Erection Tolerances
Bearing strip
Elevation
~ e f ~r /
1' :
': I
v
I ::L
I Welded connections
_l
I .
I 1/
I
I I
CL_ T
,----- I Adjacent deck panel
I I :
:I
Plan
116
12.11 Pier Deck Erection Tolerances
c = Variation in width of panel to panel grout joint . . . . . . . . . . . . . . . . . . . . . ± 1/a in. [±3 mm]
e = Variation in alignment of adjacent panel edges .................... ± 1!8 in. [±3 mm]
117
Fig 12.12.1 Erection Tolerances for Bridge Deck Units
Plan
Elevation
118
12.12 Erection Tolerances for Bridge Deck Units
b = Top surface elevation from nominal top surface elevation .......... ±%in. [±19 mm]
Note: These tolerances should be compared against those specified by the controlling bridge au-
thority. If the specified project tolerances are more stringent than these, the specified tolerances
shall govern the erection of the project.
119
13.0 Erection Tolerances for Mixed Building precast to other materials, erection acceptable bear-
systems ing conditions must be shown in the contract docu-
ments.
A mixed building system is one which uses precast
If for any reason a member cannot be erected as
and prestressed concrete with other materials, usual-
shown on the connection details within the tolerances
ly cast-in-place concrete or structural steel. Mixed
outlined in this document, the erector should notify
building systems subject erection tolerances to even
the architect/engineer to check the structural ade-
more variables than do single system buildings. Each
quacy of the resulting connection configuration and
industry has its own specified erection tolerances
modify the connection if necessary. The connection
which apply when its products are used exclusively.
design should be reviewed by the erector to assure
Because the industry standard tolerances for differ-
that space has been provided so that adequate mate-
ent materials are not necessarily compatible, it is in
rial, tools and equipment can be used to complete the
the interest of the producer and erector to verify the
connections. Verify that tools and equipment can be
compatibility of each industry's erection tolerances
utilized in the intended manner under the most ad-
with the precast tolerances. Compatibility of toler-
verse combination of possible tolerances.
ances is achieved by connection design and/or by
For a cast-in-place concrete frame the maximum
modification of standard tolerances of one or more of
tolerances that should be permitted, unless other-
the involved building systems.
wise stated in the project specifications, are those gi-
Note that any modification of standard tolerances
ven in the current revision of ACI117 Standard Toler-
on the non-precast portion of the work must be
ances for Concrete Construction and Materials. The
brought to the attention of the architect/engineer so
tolerances given in ACI117 are quite optimistic for tall
the modifications can be coordinated throughout the
buildings when compared to the American Institute of
project design and construction to assure that the
Steel Construction tolerances and to as-built mea-
modified tolerances are, in fact, achieved.
surement of tolerances obtained from measurements
of tall buildings.
13.1 Connection Tolerances for Mixed Build-
Variations in height of floors in excess of the ACI
ing Systems
117 tolerances are more prevalent in cast-in-place
Special attention should be given to assuring that construction than in other types of structures when
the responsible project team member has appropri- compared to published tolerances for example in
ately considered the connection tolerance require- steel frame buildings. This will affect location or mat-
ments when mixed building systems are involved. ing of the inserts in the precast panels with the cast -in
The manner in which precast concrete members are connection devices.
connected to each other or to members fabricated of The producer and erector should be aware that tol-
other materials should be reviewed by the producer erances for cast-in-place structures may have to be
and erector in the context of the specified erection tol- increased even further beyond the values given in ACI
erances. The erector should review the design docu- 117 to account for local trade practices, the complex-
ments to assure it is practical to physically construct ity of the structure, and climatic conditions which will
the connections. exist at the time of construction. For these reasons lo-
For precast to precast erection acceptable bearing cal producers should collaborate with the architect/
tolerance conditions which are required for safe erec- engineer early in the project providing their input on
tion should be shown on the erection drawings. For overall project tolerances.
120
14.0 Clearance Considerations in Product When a project involves particular features sensi-
Manufacture tive to the cumulative effect of generally accepted tol-
erances on individual members, the producer's and
The entire building team should collaborate and erector's review should assure that the architect/en-
cooperate throughout the project to allow the project gineer has provided for this effect by setting a cumula-
to be satisfactorily built using practical tolerances and tive allowance or by providing appropriate clearances
clearances. Clearance is the space provided be- where accumulated tolerances can be absorbed.
tween adjacent precast members and is one of the
most important factors to consider in the planning for
the erection. The clearance is jointly "owned" by all of
14.2 Effects of Member Type on Clearance
Considerations
the members of the building team. What this means
is that the joint clearance is used to accommodate the The type of member is partially accounted for
product tolerances, the erection tolerances, and to al- when the product tolerances are considered. Those
low adjustment for appearance. members exposed to view should be specifically re-
Exposed joint clearance determination and config- viewed with regard to clearance requirements. An ex-
uration for architectural panels is an especially impor- posed to view member requiring stringent erection
tant consideration which should be reviewed by the tolerances generally requires more clearance for ad-
producer and the erector in advance of production. If justments than does a non exposed member with a
revisions are indicated the architect/engineer should more liberal erection tolerance. Similarly, a corner
be notified. member should have a large enough clearance pro-
Tolerances in overall building width and length are vided, so it can be adjusted to line up with both of the
normally accommodated in panel joints, making the adjacent panels.
overall building size tolerance and its relationship to In practice, members exposed to view are often
building property lines important considerations in specified with less clearance than non-exposed
joint clearance design. In the architectural panel, the members. As previously noted, more stringent spe-
joint width must not only accommodate variations in cial project tolerances may be needed when narrow
the panel dimensions and the erection tolerances for clearance joints are specified.
the panel, must also provide both a good visual line
and sufficient width to allow for effective sealing. Gen-
erally the larger the panel the wider the basic dimen- 14.3 Effects of Member Size on Clearance
sion of the joint should be in order to accommodate Considerations
realistic tolerances in straightness of panel edge, in
The effect of member size on thermal motions of
edge taper and in panel width.
the member should be considered in the review of the
When all factors are combined and considered,
project clearances. Large members are more difficult
the minimum theoretical architectural panel joint
to handle than smaller ones. A large member being
width should not be less then% in. [19 mm]. Joint
erected by a crane requires more clearance than the
widths specified as less than this amount should be
small member that can be hand erected or adjusted.
discussed in detail with the project architect prior to
start of production, as they may require more strin-
gent special project tolerances to achieve the desired 14.4 Effects of Member Location on Clear-
result. ance Considerations
The following items should be reviewed by the pro-
ducer and erector in their project review to determine The requirements for erecting the member in the
that appropriate clearance has been provided in the structure should be considered in the review of the
design. project clearances. With multistory members for ex-
ample, floor members may be erected by lowering
them from the top down between the previously
14.1 Effects of Product Tolerances on Clear- erected vertical members. This process often re-
ance Considerations quires a greater clearance for erection than does a
roof member.
The product tolerance of the member or system (if
it is an interfacing situation) and the possible maxi-
mum and minimum variations in the size of the mem- 14.5 Effects of Member Movement on Clear-
ber should be considered when reviewing the speci- ance Considerations
fied joint clearance for adequacy. If revisions to the
design are indicated the architect/engineer should be The review of clearances should consider member
notified. movements caused by temperature expansion and
121
contraction, creep, shrinkage, structural deflection should be maintained. At least 1.50 in. [38 mm] of
and rotation. The clearance between vertical mem- clearance between the back of the panel and the sur-
bers and the adjacent horizontal members should al- face of the supporting steel beam should be specified
low for some movement in the horizontal member to in tall or irregular structures regardless of the structur-
prevent the vertical member from being pushed or al framing materials.
pulled out of its original alignment. This is especially The minimum clearance between column covers
critical on exposed structures such as parking decks, and columns should be 1.50 in. [38 mm], with 3 in. [76
where temperature ranges and the associated mem- mm] preferred because of the possibility of columns
ber movements are significant. being out of plumb or a larger than nominal column
The effects of support member deflection on panel dimension interfering with the completion of the col-
movement can effect the clearance specified be- umn cover connections.
tween cladding panels that are supported by structur-
al members. 14.8 Procedure For Determination of Clear-
ance
14.6 Effects of Member Function on Clear-
ance Considerations The following is a systematic approach for making
a trial selection of a clearance value and then testing
The function of a member within the building that selection to ensure that it will allow practical erec-
should be considered in the review of the specified tion to occur. This type of systematic evaluation of all
clearance. For example, allowances should be pro- specified clearances will disclose potential problems
vided for end rotation of heavily loaded beams. Like- or areas which will require special care in member
wise a minimum amount of joint width is needed to as- production and/or erection.
sure the joint can be reliably sealed when the member
must provide protection against the elements. Step 1
14.7 Effects of Erection Tolerances on Clear- Determine the maximum size of the members in-
ance Considerations volved (basic or nominal dimension plus additive tol-
erances). This should include not only the precast
Of all the factors discussed above, product toler- and prestressed members, but also other materials.
ances and member movement are the most signifi- This step includes evaluating the installation toler-
cant variations to consider when reviewing project ances of the non-precast building systems and sub-
clearances. If the clearance provided is too small, systems and the consequences of those tolerances
erection may be slow and costly because of fit-up on the precast member interface.
problems and the possible requirements for rework.
Reviews by the architect/engineer and producer
Step 2
should determine that the erection tolerances have
been considered in the development of clearance Add to the maximum member size the minimum
specifications. The clearance necessary for erection space required for member movement resulting from
of the members will depend on their geometric config- deflections, and thermal movements. Tolerances of
uration, the dimensional accuracy of the building systems installed by other trades are generally as de-
frame or other construction to which the members are fined in the standards of practice for those trades.
connected and the limits of adjustment permitted by
the connection details.
A rule of thumb is that at least 0.50 in. [13 mm] Step 3
clearance be specified between panels and precast Check to see if the selected clearance allows the
concrete panel support members with 1 in. [25 mm] member to be erected within the erection and inter-
preferred. A clearance of 1 in. [25 mm] is the mini- facing tolerances, such as plumbness, face align-
mum planned clearance between panels and cast-in-
ment, etc. If the member interfaces with other struc-
place concrete panel support members with 1.50 in. tural systems, such as steel frame or a cast-in-place
[38 mm] preferred. concrete frame, check to see if the clearance pro-
For steel structures, 1 in. [25 mm] is the minimum vides for the erection and member tolerances of the
clearance between the back of the panel and the sur- interfacing system. Adjust the clearance as required
face of the fireproofing on the steel panel support to meet all of the needs. More clearance may be
members with 1.50 in. [ 38 mm] preferred. If there is needed to accommodate interfacing with other sys-
no fireproofing required on the steel panel support tems which may have large tolerance variations.
members then 1 in. [25 mm] minimum clearance
122
Step 4 variations in subsystem interface requirements is
necessary for every project. One should not assume
Check to see if the member can physically be that by simply specifying that "PC I tolerances shall be
erected with the clearance determined above. Con- used" that everything will work out. That "everything
sider the size and location of members in the structure will work out" is something that needs to be verified
and how connections will be made. Adjust the clear- by the development of the project tolerance plan.
ance as required. An understanding of the planned This is particularly true for complex projects or pro-
erection sequence is important in reviewing the ap- jects which are substantially different from those pre-
propriateness of specified clearances. For complex viously handled by the particular building team in-
situations it is beneficial to involve the erector in this volved.
review. The following examples in Articles 14.10 through
14.12 demonstrate the thought process involved in
Step 5 forming a project tolerance plan. A judgment situation
was created to emphasize that engineering judgment
Review the clearance to see if increasing its di- must be included as part of the clearance determina-
mensions will allow easier, more economical erection tion process. Therefore, the solution shown is not the
without adversely affecting aesthetics. Adjust the only correct one for the situation described.
clearance as required. If adjusting the clearance as The project tolerance plan should not only include
required to allow fit up still results in reasonable clear- the specification of the project tolerances and details
ance widths, the design portion of the tolerance con- but should also provide the basis with which the
trol plan for this element of the building is complete. construction team can verify the accomplishment of
the tolerance objectives leading up to the erection ef-
fort.
Step 6
Review structural considerations such as types of 14.10 Roof Member Clearance Example (Refer
connections involved, sizes required, bearing area re- to Figure 14.10.1)
quirements, and other structural issues. Check struc-
tural adequacy. The structural requirements for bear- Given: A double-tee roof member bearing on
ing areas and connection eccentricities should be ribbed wall panels.
available as input to the review of the project toler- Find: The minimum acceptable joint clearance.
ance plan. See Articles 10.3 and 10.6.
A project tolerance plan incorporating all possible Maximum double tee length = +1 in. [ +25 mm]
product tolerance variations, erection tolerance varia- Maximum wall thickness = + 'I• in. [ +6 mm]
tions, setting of joint clearances, selection of toler- Initial clearance chosen= 3/. in [19 mm] each end
ance accommodating connection details, and the
123
Fig. 14.10.1 Roof Member Clearance Determination (Example 14.1 0)
r
I (
Detail
)
L Double tee roof member
(long term shortening, - %")
\; lJ
25'·0 " I--- Plumb tolerance
~ I--- Wall thickness tolerance ( + 114'', - 1; 8 ~) (1/4" p er 10')
Detail
Step 2 - Evaluate effects of member movement ance should be increased by '12 in. [13 mm]. If the
panel is erected out of plumb outward y, in. [13 mm]
Required clearance adjustment as a result of no clearance adjustment is needed.
member movement = none
Clearance chosen = % in. [19 mm] (from Step 1) Clearance adjustment required to account for
The long term shrinkage and creep movement will erection tolerances = none
increase the clearance, so this movement can bene· Clearance chosen = % in. [19 mm] (from Step 1)
glected in the initial clearance determination, al·
though it must be considered structurally.
Step 4 - Erection Considerations
Step 3 - Evaluate effects of erection tolerances If all members are fabricated perfectly, then the
joint clearance is% in. [19 mm] at either end of the
If the wall panel is set inward toward the building double tee (1.5 in. total) [38 mm]. This is ample space
interior '/, in. [13 mm] and erected plumb, the clear·
124
for erection of this member. If all members are at max- Step 8 - Determine final clearance
imum size variance, maximum inward plan variance,
and maximum inward variance from plumb, the total Minimum clearance to be used = % in. [19 mm]
clearance is zero. This situation is undesirable, as it This clearance satisfies all conditions considered.
would likely require some rework during erection.
However, there is opportunity to directly measure the Note: For simplicity in this example, beam end
span length of the roof member and adjust the wall rotation, flange skew, and global skew tolerances
members upon erection. have not been considered. In an actual situation,
these factors should also be taken into account.
Clearance chosen = % in. [19 mm] (from step 1)
14.11 Bearing Wall Panel Joint Clearance Ex-
A judgment should be made as to the likelihood of ample (Refer to Figure 14.11.1)
maximum product tolerances all occurring in one
location. If the likelihood is judged to be low, the % Given: Bearing wall panel, 18 ft. [5.5 m] high
in. [19 mm] clearance needs no adjustment, but, ifthe erected on a cast-in-place concrete footing.
likelihood is high and the opportunity for adjustment Find: The minimum acceptable clearance be-
upon erection is judged to be low, the tolerance sys- tween the base of the wall panel and the top of the
tem designer might increase the clearance to 1 in. [25 footing.
mm]. In this instance the likelihood has been judged
to be low; therefore no adjustment has been made. For simplicity, it is assumed that the plane of the
top elevation of the wall panels will be set at exactly
the basic elevation.
Step 5 Evaluate the economy of this clearance
Minimum space for proper grouting beneath the
In single-story construction, increasing the clear- wall panel is judged in this case to be '12 in. [13 mm].
ance beyond% in. [19 mm] is not likely to speed up
erection as long as product tolerances remain within Procedure:
allowed variances. No adjustment is required for eco-
nomic considerations.
Step 1 Determine maximum member sizes
Step 6 Review structural considerations Maximum panel height= +'12 in. [+13 mm]
Highest footing top elevation = + '12 in. [ + 13 mm]
Allowing a setback from the edge of the corbel, as- Refer to Product Tolerances Article 10.3
suming in this instance to have be set by the engineer Initial clearance chosen = 1.5 in. [37 mm]
at 1.25 in. [32 mm] plus the clearance, the bearing is This results in '12 in. [13 mm] clearance in the maxi-
4 in. [102 mm] and there should be sufficient space mum member size condition.
to allow expected member movement. The tolerance
designer judges this to be acceptable from structural
and architectural viewpoints and no adjustment to the Step 2 Evaluate effects of member movement
clearance is required for structural considerations.
Bottom of member will be fixed once member is
grouted. No adjustment is required for member
Step 7 Check for effects of minimum member sizes movement.
125
Fig. 14.11.1 Bearing Wall Clearance Determination (Example 14.11)
E
E 1----- Precast concrete
"' bearing wall member
~
tl
/Clearance
.-cv ~
j Footing elevation ±Vi' (13 mm)
~
Cast-in-place foundation ----:"+--•
~
Step 5 Evaluate economic considerations mm] standard grout bed with a 2'12 in. [64 mm] thick
possible grout bed is expensive. As a general rule, for
Varying the clearance above 1.5 in. [37 mm] will normal contracting conditions, it is desirable to pro·
make the grouting operation more costly, as more vide at least 1'12 in. [38 mm] of clearance for a detail
grout will be required. The cost of the additional vol· such as this .
ume of grout required can be computed. If special attention to detail in setting and finishing
the tops of the footings is agreed upon with the con·
Step 6 Structural considerations tractors involved, one might reduce the nominal
clearance to 1 in. [25 mm].
Clearance chosen = 1.5 in. [37 mm]
Minimum depth of grout bed= '12 in. [13 mm] Step 8 - Determine final clearance
1.5 in. [37 mm] clearance is acceptable.
Minimum clearance used = 1 in. [25 mm]
Step 7 Check effects of minimum member sizes.
The designer judges that with care to assure foot·
Refer to Product Tolerances Article 10.3 ings are set on the low side of their top elevation
Clearance determined (Step 6) = 1.5 in. [37 mm] construction tolerance. This will likely satisfy all of the
Minimum panel length= '12 in. [13 mm] short conditions considered and provide an economical
Minimum footing elevation = '12 in. [13 mm]low connection.
Maximum clearance calculated = 2'12 in. [64 mm] Note: Alert contractor and erection crews to
instances which may require isolated rework in order
A judgment condition now exists. A 1.5 in. [38 to provide minimum required grout space.
126
14.12 Cladding for High Rise Steel Frame Step 6 Structural considerations
Building Clearance Example (Refer to
Figure 14.12.1) Clearance chosen ~ 23!• in. [70 mm] (From Step
3)
Given: A thirty six story steel frame building is de- This results in an expensive cladding connection,
signed with precast concrete cladding. The steel but it is possible to construct. No adjustment re-
structure is erected to tolerances per AISC. Assume quired.
that member movements have been calculated to be
negligible. In this example, precast tolerance for vari- Step 7 Check minimum member sizes at 36th story
ation in plan is specified as ±'I• in. [6 mm].
Refer to product tolerances Article 10.3
Find: Determine whether or not the panels can be Clearance chosen ~ 2% in. [70 mm] (Step 3)
erected plumb and determine the minimum accept- Minimum cladding thickness ~ - 1/a in. [ -3 mm]
able clearance at the 36th story. Minimum steel beam width ~ - 311s in. [ -4.5 mm]
Procedure: Steel support beam sweep~ -'/• in. [ -6 mm] (to-
ward building interior)
Minimum size of steel variation in plan ~ -3 in.
Step 1 - Product tolerance [ -75 mm]
Clearances calculated~ 6511s in. [156 mm]
Refer to product tolerances Article 10.1 2% + Va + 311s + '!. + 3 ~ 6511s in.
When the minimum condition exists, the resulting
Precast cladding thickness ; + v. in. [ +6 mm] clearance of6'11s in. [156 mm] produces a connection
-Vain. [-3 mm] judged by the designer to be too costly for the precast
Steel member width ~ + V. in. [ +6 mm] - 311s in. concrete cladding on this project. In addition it pro-
[-4.5 mm] duces a high torsional force on the supporting struc-
Steel member sweep (varies) ±V. in. [±6 mm] as- tural steel that must be considered in the design of
sumed. any horizontal steel supporting members.
For simplicity, assume this can be neglected in this Minimum clearance used ~ 23/• in. [70 mm]
example.
The 6511a in. [156 mm] clearance is judged not
Step 3 - Other erection tolerances practical, although the 2% in. [70 mm] minimum initial
clearance is still needed for erection. Therefore the
Maximum steel variation in plan ~ 2 in. [50 mm] initially specified erection tolerances need to be ad-
Minimum clearance~% in. [19 mm] justed.
This is the minimum clearance needed to com- Either the precast cladding members should be al-
plete the connection in the field. lowed to follow the steel frame tolerances and be
Clearance chosen ~ 2% in. [70 mm] erected out of the standard plumb tolerances for pre-
cast panels or the steel frame erection tolerances
need to be made more stringent. The likely most eco-
Step 4 - Erection considerations nomical and recommended solution will be for the
Adjustment required ~ none precast cladding members to follow the steel frame
as the variation in plumb in a building of this height will
not be noticeable.
Step 5 - Economic considerations Another solution which has proven to be both
practical and economical in some instances is to
Clearance chosen ~ 23/• in. [70 mm] (From Step
specify the more stringent AISC elevator column
3) erection tolerances for steel columns in the building
Increasing clearance will not increase economy. facade which will receive the precast cladding panels.
Nv adjustment needs to be made for economic con-
This type of solution should be agreed to as part of the
siderations.
design and specification process.
127
Fig. 14.12.1 Determinate of cladding connection tolerances-high rise steel frame (Example 14.12)
I
Theoretical centerline of column
Maximum displacement from theoretical ,I
column center line: "toward" building line ----j ~- 2"
Possible position of
precast facade
J V4"
If
:. j,I '
Actual position of colum
' 1! I
·I
1"-
r- I
·-+-
2"-
\1 I
20 stories
tacade-"building lineH
,fI,
' Steel framing
}, constructed as per AISC
Code of Standard
' Practice
H
Detail
(
~ :.r '
1/
v
2 3/4"-
(Clearance)
~ '',
·.'
'
~
1\
~ \
DETAIL
Precast ''' .
facade ; '.
,-
':::'::::
r-:-
..
Steel
framing
"
,.
)
128
15.0 Interfacing Tolerances dependent of site work, tolerances should closely
match the normal manufacturing tolerances for the
The purpose of this section is to help the designer materials to be joined plus an appropriate allowance
and producer deal with the problem of designing for (clearance) for differential volume changes between
interface tolerances. As with product and erection tol- the materials.
erances, the party to be responsible for assuring that Following is a partial checklist for the review of in-
interfacing tolerances are appropriately accounted terfacing tolerance requirements. If revisions to clear-
for in the project tolerance plan should be agreed to ances or tolerances are indicated, the architect/engi-
in writing at the start of the project. neer should be notified.
A comprehensive discussion of interfacing toler-
ances is presented and a number of typical details
and examples are given as illustrations. With interfac-
15.1 Structural Requirements
ing tolerances, it is important to note that the toler- a. The potential for introducing unintended struc-
ances associated with the system to be interfaced tural loads from the precast into the interfacing
may be very dependent on the specific system (e.g. subsystems should be evaluated. Does the be-
window system) ultimately procured for the proJect. havior of the structure require that the interfac-
The fact that the specific systems to be interfaced with ing system be isolated from primary or secon-
may not be known until late in the project make this dary structure loads?
issue one which is very important to deal with to as- b. Does the interface perform a structural function
sure a successful installation. in the structure (e.g. load transfer)?
Unusual requirements or allowances for interfac- c. In the determination of erection tolerances
ing should be in the contract documents. It is in the attention should be given to expected deflec-
interest of all parties on the project team to identify tions and/or rotations of structural members
and take steps to accommodate unusual interfacing supporting precast concrete panels.
tolerance requirements as soon as they are identified. d. How are building motions, dimensional
Accommodation of interfacing tolerances may in-
changes, and vibrations taken into account
volve contractual changes, if the interface require- structurally, and how do they collectively affect
ments are not initially defined in the contract, or if
interfacing tolerances?
these requirements change as result of procurement e. If the deflection of the structural frame is sensi-
decisions made alter the precast contract has been
tive to the location or eccentricity of the connec-
finalized.
tion, limits on connection eccentricity should be
In practice the interfacing requirements may not given on the erection drawings. This is particu-
be in the contract documents. It should be noted that
larly important for heavy members bearing on
building systems and hardware are often specified light members, such as open web joists, or can-
and procured by a company which may not have a
tilevered structural members.
contractual relationship with the precast member
f. Consideration should be given to both initial
manufacturer. If this is the case, the party with the
deflections and to expected long term deflec-
necessary contractual authority is responsible for as-
tions caused by creep of the supporting struc-
suring that the project interfacing tolerance require-
tural members.
ments are appropriately coordinated and met.
g. Allowances must be made when detailing con-
For example, windows fabricated by Company A
nections of precast concrete panels to steel
may have a quite different interface tolerance require-
structures for effects of sway in tall, slender
ment than windows fabricated by Company B. On
steel structures.
fast track projects the fact that the precast fabrication
takes place early in the project may drive the installa-
tion and tolerance requirements of the interfacing 15.2 Volume Change
systems and may influence subsystem procurement
choices. If material or component substitutions are a. The potential for volume change effects in the
made for any reason alter the initial design is com- precast or in the interfacing subsystem to
plete, the interfacing design should be reviewed by introduce unintended loads into the interfacing
the producer as well as by the architect/engineer for sub systems should be evaluated.
the new system tolerance requirements to assure b. Does the primary structure or the interfacing
compatibility of tolerances. system undergo mutually incompatible volume
Where matching of the different materials is de- changes that need to be considered? (e.g.,
pendent on work executed at the construction site, in- openings for aluminum windows should allow
terface tolerances should also be related to erection clearance for the expected thermal expansion
tolerances. Where the execution of the interface is in- of the sash.
129
c. In tall buildings global movements of the build- face between precast concrete and other mate-
ing due to solar heating on one side and sea- rials?
sonal thermal expansions and contractions c. What are the consequences of dimensional tol-
should be considered in the design of panel erance to the drainage system?
clearances and connections.
15.6 Architectural Requirements
15.3 Exposure and Corrosion
a. Which portions of the structure exterior and in-
a. lstheinterfaceexposedtoweather? If so, what terior are exposed to view? On projects where
dimensional requirements result from the need precast members have a primarily architectur-
to provide protection from moisture and the ele- al/visual function architectural requirements
ments? may require special interfacing measures.
b. How do the proposed precast concrete details b. What are the architectural treatments proposed
enhance or detract from the ability of the struc- for the various interfaces? How do the treat-
ture to remain serviceable and durable over ments relate to interfacing tolerance require-
time? To assure the long term durability of pre- ments?
cast members, it must be assured that toler- c. Tolerances for the planeness of concrete sur·
ancing of interfacing subsystems do not pro- faces at the interface with glass or curtain wall
vide a path for corrosion of metallic elements or face should be developed in conjunction with
contribute to unacceptable corrosion staining. the curtain wall installation requirements.
d. The requirement to align architectural panels in
three dimensions may result in special interfac-
15.4 Waterproofing Requirements
ing clearance requirements, even on the non-
a. Interfacing tolerances and clearances should visible faces of the member.
be evaluated for the ability to properly support e. It is important that the project design provides
the installation of weatherproofing materials. adequate clearance between the nominal face
b. What are the waterproofing requirements of the of the supporting structure and the back face of
roofing details, exterior penetrations, and the attached concrete panel. Adequate space
drainage schemes. How do they apply to the must be provided here to allow an efficient and
interface between the precast concrete and the economical erection operation.
other materials?
c. A minimum clearance joint width is typically re· 15.7 Dimensional Considerations
qui red to allow proper installation of water-
proofing sealant systems. Manufacturer's rec- a. How closely can the dimensions of the interfac-
ommendations for minimum joint width for the ing materials be controlled? It is important to
waterproofing sealant system to be used note than unless specifically controlled during
should be considered. the construction process, the industry pub-
d. Cast in grooves, reglets, or lugs that are to re· lished tolerances for the installation of materials
ceive glazing gaskets may require a higher lev- by other trades may or may not be met.
el of precision than other aspects of panel b. What are the dimensional considerations in
construction in order to allow proper installation relation to the proper function of the interfacing
and function. Reference should be made to systems? If the precast installation has specific
gasket manufacturers' tolerances on the interface tolerance needs, it is important to
groove width and surface smoothness neces· communicate these to all levels of the project
sary to obtain a proper moisture seal. design team and follow up with the construc-
tion team. This communication should be
through the party having contractual authority
15.5 Drainage Requirements
over the involved trades.
a. Interfacing tolerances which have an effect on c. The following tolerances, in addition to ACI117
the proper draining of the roof or other features requirements, should be specified for the cast-
which could retain or pond water should be re· in-place concrete construction when precast
viewed to assure that positive drainage is pos- concrete members are to be connected to cast-
sible. in-place structures. It should be noted that spe-
b. Where are the areas to be drained and how cial measures and attention to detail are likely
does the drainage requirement affect the inter- to be required to achieve these more stringent
130
than usual tolerances in the cast-in-place con- 15.8 Vibration Considerations
crete construction. Following up to assure that
the requested tolerances have actually been a. Does the mechanical subsystem have vibration
achieved has proven to be an important activity considerations which must be accounted for in
in assuring that the construction/precast erec- the interface between it and the precast con-
tion activity proceeds smoothly. crete?
b. If vibrations result in deflections of members,
1. Footings, caisson caps, and pile caps contact between members as result of vibration
aa. Variation of bearing surface for precast mem- should be avoided.
bers from specified elevation:
±0.50 in. [±13 mm] 15.9 Fire-Rating Considerations
2. Piers, columns, and walls. a. Does the need for fire resistance of the system
aa. Variation in plan from straight lines parallel to impose any tolerance requirements on the na-
specified linear building lines: 0.025 in. per foot ture of the interface such as maximum allow-
[2 mm per m] for adjacent members less than able gaps? Code requirements relating to fire
20feet [6 m] apart or any wall or bay length less ratings often require that gaps beyond a certain
than 20 feet [6 m]. size be sealed in a fire proof manner.
0.50 in. [13 mm] maximum for adjacent mem-
bers 20 feet [ 6 m] or more apart or any wall or
bay length of 20ft. [6 m] or more. 15.10 Acoustical Considerations
bb. Variation in elevation from lines parallel to spe-
cified grade lines: a. Does the acoustic environment place any spe-
0.025 in. per foot [2 mm per m] for adjacent cial requirements on the interface between pre-
cast concrete and interfacing systems? Clear-
members less than 20ft. [6 m] apart or any wall
or bay length less than 20ft. [6 m]. ance gaps can sometimes provide a route for
0.50 in. [13 mm] maximum for adjacent mem- unwanted transmission of sound from one
bers 20 feet [6 m] or more apart or any wall or room to another.
bay length of 20ft. [6 m] or more.
15.11 Economics
3. Anchor bolts
Special coordination with the cast-in-place a. Does the chosen interface design alternative
concrete contractor and the use of erection bolt place any unusual or costly demands on either
setting templates common to both the precast the precast or the interfacing system?
and cast-in-place construction effort will likely b. Has the most economical interfacing design al-
be required to achieve anchor bolt tolerances ternative been used? In some cases the cost of
which will allow trouble free erection. accommodating a tolerance sensitive interfac-
aa. Variations from specified location in plan: ing system may be a significant percentage of
±0.25 in. [±6 mm] the total costofthe installed interfacing system.
bb. Variation center to center of any two bolts within c. Has the cost trade-off between in-plant work
an anchor bolt group: ±0.125 in [±3 mm] and field work been considered?
cc. Variations from specified elevation: ±0.50 in
[±13 mm]
dd. Anchor bolt projection: - 0.25 in., +0.50 in. 15.12 Manufacturing/Erection Considerations
[-6mm, +13mm] a. Does the interfacing method consider practi-
ee. Plumbness of anchor bolts: ±0.062 in. [±2
calities of manufacturing? The manufacturing
mm]
and erection work necessary to accommodate
4. Tolerances for structural steel framing should an interfacing tolerance should be objectively
be specified to conform with the American Insti- evaluated. Viable methods of attaining the re-
tute of Steel Construction (AISC) "Code of quired interfacing tolerances should be defined
Standard Practice for Steel Buildings and before the producer agrees to provide them.
Bridges". b. Is the time required to manufacture the inter-
Particular attention is directed to the "Commen- face consistent with factory production?
tary" included with the AISC code. The commentary c. Can the interfacing parts of the structure be
provides a detailed explanation of the specified steel erected together safely and economically?
erection tolerances.
131
16.0 Design Approach for Two Interfacing Tol- tems which must be precisely installed to stringent
erance Systems tolerances in the completed structure.
Another example of functional requirements is the
Unless the design and construction team has a building drain line that must have a flow line slope
significant background of successful experience with which allows adequate drainage. This will place func-
a particular building system type, and the handling of tional limits on where the line must penetrate m<:>m-
all of the interfaces, the only way to assure the pro- bers. Consider a tee beam that has harped prestress-
posed approach to handling interfacing tolerances ing strands in the stems, making the end areas of the
will be viable is to systematically and numerically re- beam potentially difficult locations to interface with
view the proposed tolerances and interfacing require- the prestressing strands for the drain line penetra-
ments. tions.
The following approach is one suggested method
of organizing the task of systematically reviewing the
interface specified between two tolerance systems. It Step 3 Review the dimensional tolerances of each
interfacing system.
is in the interest of the producer to confirm that some-
one on the project team is responsible for and has in- For example, determine from the manufacturer's
fact reviewed the project interface tolerances. specifications what the external tolerances on the
The nominal clearance dimensions shown on the specified prefabricated metal door jamb are. Deter-
erection drawings should be equal to the actual clear- mine from the precast/prestressed concrete product
ance required plus the outward tolerance permitted tolerances what the tolerance on a large panel door
for the adjacent construction. The clearances should opening will be. For the door installation, determine
be evaluated on the assumption that the precast pan- what the floor surface tolerance requirement will be in
el will be as far out of the nominal position as is al- the area of the door and its swing path.
lowed, in the direction which creates the requirement
for the largest clearance. Special attention should be
given to complex geometric interfaces. Drawing the Step 4 Review the operational clearance specified.
interface to scale showing the possible local and
The most significant tolerance interface problems
global variations is one way to evaluate an interface
result when the members of the project team don't
situation.
understand or are unaware of special operational re-
quirements of interfacing subsystems. For example,
Step 1 Review the interface between the two sys- determine the magnitude of operational clearances
tems. which are needed to align the specified door to func-
tion properly. Then, review the nominal dimensional
a. Has the architect/engineer graphically defined
choices to assure they include an allowance for nec-
the interface to show its shape, location, and
essary clearances.
any split of contractual responsibility?
b. Has the architect/engineer shown the material
furnished by the different contracting parties? Step 5 Review compatibility of the interface toler-
For example, one might indicate the precast panel ances.
furnished by the precaster, the window furnished and
Interface tolerance incompatibility problems re-
installed by the general contractor, and the sealant
solved in the design phase of the project do not be-
between the window and the precast concrete fur-
come member fabrication problems or erection prob-
nished and installed by the general contractor. On fast
lems.
track projects it may be necessary for the window
Starting with the least precise specified system, re-
suppliers to measure the as-built window openings in
view the minimum and maximum tolerance condi-
the precast members prior to fabricating the win-
tions and compare the precast dimensions against
dows.
the minimum and maximum dimensions of the inter-
facing system. If interferences result, notify the archi-
Step 2 Review the functional requirements of each tect/engineer. For example, it is usually more eco-
interfacing system. nomical to make a larger window opening to provide
more clearance than to specify a prefabricated win-
Functional requirements which require close toler- dow system with either nonstandard sizes or toler-
ances, such as justice facility locking mechanisms, ances more stringent than standard. It is important to
require special attention. Often tolerance friendly in- understand how a close tolerance interface is ad-
terface details which can accommodate significant justed upon installation and how much adjustment
tolerance variations can be used to economically in- capability is required.
terface the precast members with interfacing subsys-
132
Step 6 Review procedures for compatibility. tolerances have been made. If project specifications
are silent on the topic of interface tolerances, it is in
Review assembly and installation procedures for the producer's interestto requestthat additional infor-
the interfacing systems to assure compatibility. Re- mation be provided regarding interfacing tolerance
view the installation procedure to assure that the pre- requirements of specified subsystems.
ferred adjustments to accommodate the tolerances
of the interfacing systems have been indicated. Re-
Step 7 Review final project specifications
view such items as minimum allowable bearing
areas, minimum and maximum joint gaps, and other Review the final project specifications as they re-
features which will vary in dimensions as a result of late to interfacing. Be especially aware of changes
the interface tolerances. which may be required as a result of possible subsys-
Review that appropriate economic trade-{)tf con- tem substitutions made during the final bidding and
siderations such as in-plant work versus field work, procurement activities.
and minor fit-up rework versus specification of tighter
133
17.0 Defining the Characteristics of a Toler- 17.1 Windows and Doors
ance Interface
a. No load transfer through window element
The following list of questions should be consid· b. Compatible with air and moisture sealant sys-
ered in the producer's review olthe nature olthe inter- tem
face between the precast member and an interlacing c. Open/close characteristics (swing or slide).
system: Windows that must open and close may have
1. What specifically is to be interlaced? more stringent interlace requirements than
2. How does the interface function? those which do not.
3. Is there provision for adjustment upon installa· d. Compatibility with door locking mechanisms
lion? Some interfacing subsystems have adjustment
capability within the subsystem. Others may have 17.2 Mechanical Equipment
zero adjustment capability built in.
4. How much adjustment can occur without re- a.Duct clearances for complex prefabricated
work? It is important to understand who will be re- duct work.
sponsible for any tolerance related rework that may b. Large diameter prefabricated pipe clearance
be required. requirements.
5. What are the consequences of an interlace tol- c. Deflection clearance requirements for deflec-
erance mismatch? tion associated with large-diameter piping and
a. rework requirements (labor and material) valves.
b. rejection limits (when a will a remake be re- d. Expansion and contraction allowances for hot
quired?) and cold piping. Large diameter piping with
6. What are the high material cost elements of the significant thermal differentials may be associ·
interlace? It is important to understand who is ated with significant forces if the piping is not
responsible for the cost of materials and labor appropriately isolated from the structure.
required to complete the different interfaces. e. Vibration isolation/transfer considerations.
7. What are the high labor cost elements of the in· 1. Acoustical shielding considerations.
terlace? This is especially important for field g. Hazardous gas/fluids containment require-
installed interlacing subsystems. ments. Hazardous materials applications may
8. What are the normal tolerances associated with result in special gap sealing requirements
the system to be interlaced? Different types of unique to this type of installation.
systems may have substantially different inter-
facing requirements.
9. Are the system interlace tolerances simple pia·
17.3 Electrical Equipment
nar tolerances or are they more complex and a. Coordination of multiple mating conduit runs.
three dimensional? For example, mechanical b. Prefabricated cable trays that must align.
piping for on-site fabrication in primarily straight c. Embedded conduits and outlet boxes. Visible
runs may have different interlacing tolerance outlet boxes or switch boxes embedded in pre·
requirements than do complex prefabricated cast walls may require special angular align-
mechanical piping systems which have bends ment tolerances for visual reasons.
occurring at penetration locations. d. Corrosion considerations related to DC power.
10. Do all of the different products of the type being e. Special insert placement requirements for e\ec·
interlaced with have the same interlace toler- trical isolation and potential for adverse reac·
ance requirements? tion with galvanized materials.
11. Does the designer of the precast system have f. Location requirements for embedded ground·
control over all aspects of the interlaces in·
ing cables.
valved? If not, what actions need to be taken g. Shielding clearance for special "clean" electri·
to accommodate this fact? cal lines.
If the answers to these questions indicate the need
for revision to interfacing tolerances or details, the ar·
chitect/engineer should be notified. 17.4 Elevators and Escalators
Listed below are some common characteristics
a. Elevator guide location requirements. Different
and considerations which are typical of most sys·
manufacturers of elevators and escalators.
tems:
134
have specific interface tolerance requirements b. Detailing to assure desired contact bearing be-
which may be different. tween masonry and precast members.
b. Electrical conduit location requirements. c. Detailing to assure desired transfer (or isola-
c. Elevator door mechanism clearances. Floor tion) of load between masonry shear wall and
slope tolerances at elevator door locations may precast frame elements.
require special consideration.
d. Special insert and control switch placement re- 17.8 Roofing
quirements.
The tolerance requirements for interfacing with
17.5 Architectural Cladding unique roofing systems should be reviewed as part of
the project tolerance plan.
The three dimensional interface requirements of a. Roof camber, both upon erection and long
architectural cladding systems, especially at corners, term, as it relates to roof drain placement.
locations of unique geometry, and areas of interface b. Fit-up of prefabricated flashing.
from one cladding type to another should be ac- c. Dimensional effects of increased deflections re-
counted for in the project tolerance plan. sulting from added material during re-roofing.
a. Joint tolerances for the specified caulking sys- d. Coordination of structural control joint locations
tem. with roofing system expansion/contraction pro-
b. Flashing and reglet fit-up (Lining up reglets visions.
from panel to panel is very difficult and often e. Location of embedded HVAC unit supports.
costly. Surface-mounted flashing or field cut re- f. Deflections due to live loads and added equip-
g lets should be considered.) ment dead loads.
c. Expansion and contraction provisions for dis-
similar materials. 17.9 Waterproofing
d. Effects of differential thermal gradients.
The party with primary responsibility for interface
17.6 Structural Steel and Miscellaneous Steel coordination of waterproofing details at the shop
drawing stage should be defined in writing for the
The party with primary responsibility for interface project.
coordination of structural steel shop drawings with a. Location and dimensions of flashing reglets.
precast concrete shop drawings should be defined in b. Location and shape of window gasket grooves.
writing for the project. c. Coordination of waterproofing system require-
a. Details to prevent rust staining of concrete. ments with structural system expansion provi-
b. Details to minimize potential for corrosion at sions.
field connections between steel and precast d. Special details around special penetrations.
concrete.
c. Coordination of structural steel expansion/con-
traction provisions with those of the precast
17.1 0 Interior Finishes-Floors, Walls, and
system. Ceilings
d. Special provisions for weld plates or other at-
tachment features for steel structures. Different interior finishes require different levels of
e. Consideration of thermal insulation and fire tolerance on substrata to which they are applied.
proofing requirements. Thus the interface tolerance requirements of the finish
types specified for the project are a consideration to
17.7 Masonry be addressed in the project tolerance plan.
a. Joints between plank members for direct car-
The party with primary responsibility for interface pet overlay.
coordination of masonry shop drawings with precast b. Visual appearance of joints for exposed ceil-
concrete shop drawings for the project should be de- ings.
fined in writing. c. Fit-up details to assure acceptable appearance
a. Coordination of masonry expansion/contrac- of interior corners.
tion provisions with those of the precast sys- d. Appearance of cast-in-place to precast con-
tem. crete interfaces.
135
17.11 Interior Walls and Partitions c. Effects of thermal bowing of wall panels.
The potential for thermal bowing to result in gaps
a. Clearance for prefabricated cabinetry and oth- between floors and walls should be evaluated.
er prefabricated finish elements.
b. Interfacing of mating embedded conduit runs
and switch boxes.
136
18.0 Typical Tolerance Related Details concerned with tolerance related considerations,
therefore structural design and aesthetics, while of
The following pages illustrate assemblies and de- great importance, are not generally emphasized.
tails often used in precast concrete structures. In Note that in all details showing weld plates, an-
some instances, precast to precast details are chors and auxiliary reinforcing are not shown to avoid
shown. However, many of the details are also applica- confusion in the graphics. These elements, should be
ble to interfacing with other materials. properly designed and included in the actual
Detailing suggestions are given with each assem- construction details as appropriate.
bly shown in this section. This section is primarily
137
Fig 18.1.1 Detailing Suggestions for Column to Footing Connection Using Anchor Bolts
- - Corner pocket
Dry pack or
non-shrink ,----- Top of footing
grout
138
Fig 18.2.1 Detailing Suggestions for Column to Footing Connection Using Footing Sleeves
J,v
Precast concrete column
I
c,c
Shims I
~
Dry pack Alternate form for
I use with flowable
4
non~shrink grout
' I' l
A/ i==:I::::
t I Interlocking conduit
sleeve
<
I >
Flowable
non-shrink
grout ~~~-B 'W
' t
"'IV
139
Fig 18.3.1 Detailing Suggestions for Column to Footing Connection Using Splice Sleeves
j ___
Precast concrete column
cl c
Splice sleeves
~
I
· - Column reinforcement
I
'
'u
~/
Dry pack
I
Top of footing
( ',u
sL/ n .
I (n f
' y
t
A
I f
Footing dowels
:
> <>
~ '
"
r
1. Use matching templates for the location of column reinforcement and splice
sleeve placement within the footing to control critical dimensions "C" and
"C 1 " which should be identical.
2. Provide clearance "/'\' large enough to accommodate tolerances required as
a result of the combination of column length and footing elevation toler-
ances. Also, this clearance must be adequate to allow access for the proper
grouting of the reinforcing bar sleeves.
3. Consult manufacturer of reinforcing bar sleeves for proper dimensions "B"
and "D" and for the tolerance on these dimensions.
4. Before executing splice sleeve assemblies always seek installation recom-
mendations from the manufacturer of the reinforcing bar splice sleeve used.
Note: Some producers have reported good success with splice sleeve connec-
tions where the sleeve portion of the connection is placed within the footing.
140
Fig 18.4.1 Detailing Suggestions for Wall Panel to Footing Connection
[----
---,----' ,v
Centroid
Precast concrete B
wall panel
~
grout if required
~
Top of footing
l
\ L l \ t:
-
v
/1
A/ ~
<1 I~
>
f
<1
- c
<1
l >
~I
~
Shims
d
.d ~
)1~
I v
141
Fi 18.5.1 Detailing Suggestion for Column to Column Connection
--- ;------
-
n
r-- ,---
Precast concrete column
B
vm -',
~Shims
Non-shrink grout / ~I I
T'i'
II
II _j
I I I I
I I I I
I I I I
I I I I
Column anchor bolts -1 I I I
~ ~
I. c .I
v
142
Fig 18.6.1 Detailing Suggestion for Composite Beam Supporting Double Tees
Cast-in-place concrete
integration pour
I
I l
I I
I I I
> I I
I I
I
I
Precast concrete I I I
double tee
L 1 r
Shear reinforcement
Precast concrete
support beam
143
Fig 18.7.1 Detailing Suggestion for Beam to Column Connection
I
material
ll
with compressive
~--~--~:~: !~~:·:----r-~
: : !: :
I1n1I I'1n1I I I
1n1 1n1
I' L
~ ~
Top of column -----~_jj f-'1
Threaded inserts
b i
1
b L Precast concrete
beam
c c
Precast concrete --~r--~,--j
column 11
IV
144
Fig 18.8.1 Detailing Suggestion for Exterior Spandrel Beam to Double Tee Connection
Add concrete
to gain cover
Concrete topping
L
---.__
'
~ ..Jl
Refer to product
>
tolerances for <
location tolerance
on insert _a
~
Dapped end
L i
~
A
i
tees
Precast concrete
spandrel beam
145
Fig 18.9.1 Detailing Suggestions for Load Bearing Wall Panel to Tee Connection
Precast concr ee
t
+
- t double tee
B
r::::: 7
~
l
~ '>
-2 ~ ~ ~ ~
Haunch
elevation
r-
Precast concrete
wall panel
1. To create a visually pleasing line at the top of the panel and ease the erection
of the roof elements, the haunch elevation of precast concrete wall panel
should be set as a primary control surface. Tolerances for wall length and
footing elevation should be absorbed at the panel bottom connection by
varying the grout pad thickness.
2. Provide adequate clearance "/'\' to accommodate the following tolerances:
beam length, beam end squareness in elevation and beam flange square~
ness in plan.
3. Provide weld plate in tee flange and in the wall panel of sufficient size to pro~
vide adequate projection "B" beyond the clip angle to accommodate toler-
ances in beam length, beam depth, and weld plate placement while allowing
space for proper welding.
146
Fig 18.10.1 Wall Panel to Tee Flange Connection
Precast concrete
wall panel
147
Fig. 18.11.1 Fascia Beam to Tee Connection
Add concrete to
gain cover
Topping
Precast concrete - I
fascia panel
l B
148
Fi . 18.12.1 Scu er Blockout in Wall Panels
-
- ,.-
------ t---c Scupper blackout
B
IX t
A
Downspout
1-- ..-c
--
.---
i
Double tee
Precast concrete
wall panel
v
149
Fig. 18.13.1 Wall Panel to Bar Joist Connection
- Ledger angle
Section A-A
150
Fig. 18.14.1 Masonry Wall to Tee Connection
.. ~.
c Precast concrete
double tee
Bearing
Precast concrete
double tee
plate
151
Fig 18.15.1 Typical Hollow-core Floor Joints
>
L\___________ _
Grout
Joint tolerance (ceiling)
1. Use leveling devices to level the bottom edges of hollow core slabs at the
joint location to minimize the effects of any differential camber when the ceil-
ing is to be exposed or planned to receive direct acoustical treatment on the
ceiling.
2. Do not release the leveling devices used to level the joints until the grout has
attained adequate strength to hold the planks in the leveled position relative
to one another.
3. Consider use of joint fairing materials for direct carpet applications.
152
Fig 18 16 1 Tee Flange to Flange Connection
.....
I\__
I I ~ I I
~ ~----~
'< ~ ~------=?
~
' '
--- rt
---
r \ I I ( I
' ( \ '
L__ Weld bar
I Weld plates -
I
I Double tee I
'
I
L:._j ~
I I
153
Fig. 18.17.1 Typical Pretopped Double Tee Joints for Parking Structures
l
----1
----~
't Joint
Detail A Detail B
1. Tool edges of tee flange at weld plate locations as shown to assure that there
is not a thin section of concrete directly above the weld plate that will be
prone to cracking because of thermal expansion of the plate during welding.
This can result in failure of the sealant system.
2. Tool edges of tees to provide the proper shape to the joint to accept the seal-
ant specified for the project. Consult sealant manufacturer for recommenda-
tions when defining the edge tooling to produce the sealant cross section
of the joint to be sealed.
3. Provide adequate clearance gap "'/>!.' to accommodate tee flange edge
smoothness tolerances and still provide the minimum joint width necessary
for proper sealing. Tolerance for alignment and smoothness of flange edges
in pre-topped systems may require more stringent special project toler-
ances to accommodate some sealant systems. Consult sealant manufactur-
er recommendations for sealant joint geometric requirements and toler-
ances.
4. Do not weld flange connectors until the tees are adjusted in such a manner
that acceptable matching of the tee flange top surfaces has been attained.
154
Fig. 18.18.1 Conduits Embedded in Double Tee Stems
I
I
Double tee
Span
1. Locate embedded conduits above the level of the top strands or establish
special project tolerances for lower conduit placement to accommodate the
interface of the conduit with the draped strands.
2. Consider the tolerances associated with the placement of shear reinforce-
ment when locating or setting location tolerances for conduits embedded in
tee stems. If functionally acceptable, conduit tolerances should allow for re-
location of embedded conduits by one conduit diameter plus one shear rein-
forcing bar diameter to avoid relocating shear steel to accommodate conduit
placement.
3. Provide positive support to embedded conduits during casting to assure
that placement tolerances are attained.
4. If conduit centerline alignment tolerances are important for embedded con-
duit in tee stems this should be specified as a special project tolerance.
155
Fig. 18.19.1 Typical Bearing Wall System Joint
tt
I
-
IV
~ Grout
I
Ir Topping
~--~~~~~~~~--~
~> Precast concrete
I hollow-core slab
~Grout
Bearing pads
Leveling device
Precast
concrete
wall panel
1. Require tighter tolerances than standard for the slab length due to the very
small bearing width usually available in the panel framing system for such
structures.
2. Provide leveling devices which allow adjustment for wall plumbness at each
floor to assure that the tolerances required for vertical plumbness are not ex-
ceeded. The main reason for careful attention to wall plumbness tolerances
is the availability of only a small bearing area.
156
Fi . 18.20.1 Staggered Architectural Wall Panels
llllll
\ ~
Shadow lines
1!llllJ
17
""""U'.IJl iJllll"' "-UlUll ~
~
\ aiiijijjji
Staggered architectural panels
1. Check design of panels to assure that excessive thermal bowing will not be
a problem. As shown in the drawing bowing of staggered panels can result
in unwanted shadow lines at certain times of the day.
2. Consider joint configurations and joint tolerances to minimize unwanted
shadow effects.
157
Fig. 18.21.1 Typical Architectural Panel Joints
r
Joint width (clearance)
~:q
I
~ ~J
I L Precast
{
concre~e panel
~ ~ Reveal joint
l
t!------,-------,/
to thos wodth
~1---------'ljr----------11
1
f-1------------') i . ~
~ ~
1
1. Specify either a chamfered or reveal joint, since these types of joints can ac-
commodate the tolerance required for panel thickness and the shadows
formed within these joints will minimize any adverse effects on the aesthetic
appearance of the joint system.
2. As a general rule, the minimum design joint width should not be less than
%in. [19 mm]. When panel production and erection tolerances are applied
to joints which are designed narrower than this, the joints may become too
narrow to allow effective caulking.
3. Avoid the use of butt joints, as the tolerance variations in panel thickness
may result in the formation of unwanted shadow lines directly over the pan-
els rather than within the joint area. This may impair the aesthetic appear-
ance of the panel assembly.
158
Fig. 18.22.1 Precast Column Near a Previously Constructed Wall Corner
Column
Precast
concrete
panel
1. Provide pockets in the walls at either of the locations as shown above. Pock-
ets should be sized and oriented to allow execution of bolted connections
marked "X". Alternatively provide adequate clearance "/li' to provide wrench
access necessary to complete the connection at "X".
2. Unless adequate access is provided for bolt tightening, it is likely that the
bolted connection "X" will not be completed.
159
Fig 18.23.1 Fascia Panel Connection to Cast-in-Place Slab
L Cast·in·place floor
160
Fig. 18.24.1 Typical Fascia Beam to Tee Connection
v-~ -~-
Fascia beam~
f-.-
v Cut back flange
l.o
A f
A- J:
L
I
I
I
I
>
f-.-
Rectangular beam
'v -~
1. Allow adequate clearance "Pi' at the fascia end of the double tee to assure
that the tee stems can be easily slid into the pockets provided in the fascia
beam.
2. Provide a sufficiently wide cut back of the double tee flange to assure that
the tee flanges have adequate clearance from the inside surface of the fascia
beam. The clearance needs to be set sufficiently large so thatthe tee's flange
does not contact the fascia beam when the tee is slid into the pockets at an
angle as is required for erection. The maximum dimension of the cut back
clearance should consider the requirements for erection, ease offorming for
the cast-in-place floor, and fire resistance considerations.
161
Fig. 18.25.1 Window Openings in Wall Panels
1\
v v v
A A
Window B
B
opening
1\ 1\ 1\
v v v
~
Panel ~
1. Consider the tolerance variations in window width and the minimum re-
quired caulking width between the window jambs and the wall panel to de-
termine blackout dimension ''Pi' and the tolerance on the "/>\' dimension.
2. Consider the tolerance variations in window height and the minimum re-
quired caulking width between the window heads and the wall panel to de-
termine blackout dimension "B" and the tolerance on the "B"' dimension.
3. Avoid locating window blackouts across a wall panel joint (see above). This
introduces the erection tolerances for panel location and plumbness com-
bined with the tolerance for panel width and joint width into the interfacing
requirements for the window system. This is much more difficult to success-
fully execute than the window blackout which is wholly contained with a
single panel.
162
Fig 1B 26 1 Precast Concrete Wall Beam to Column Connection
-+-~\,--~---+
v
____;/\\ ~-----
<
> <
I \r--\-------_ _i_--f--1/ I
I
.I \
\_____ Dry pack over columns
__/ I L 1
-Lv-~ -Lrv--
163
Fig. 18.27.1 Slab on Grade Connection to Precast Wall
1. When panel lifting device embedments are used as a tie to the floor, use a
placement tolerance of ±'/,in. [ ± 13 mm] rather than the larger standard PCI
tolerance given for embedded lifting devices when they are only used for lift-
ing.
2. Use added concrete in the floor as shown by the crosshatched area to ac-
commodate tolerances required to place lifting devices as well as to provide
adequate concrete cover "Pi'.
164
Fig. 18.28.1 Insulated Slender Wall Panels-Corner Detail
Corner joint
1. Consider the potential for opening of the corner joint as result of thermal
bowing of these adjacent panels in different directions. Assure that any cal-
culated joint opening does not exceed the motion capabilities of the speci-
fied joint sealant and joint sealant detail.
3. Allow adequate clearance "N between the columns and the inside face of
the panels so that the tolerances required for the placement of the em-
bedded hardware, tolerances for erection of the panels and the completion
of the connection welding can be easily accommodated.
165
19.0 Examples of Tolerance Detailing Related If this tolerance situation exists:
Calculations
A detailed numerical approach to designing de- e = 2.5 in. + 0.25 in. + 0.38 in.
tails for tolerances is illustrated here. Examples illus- = 3.63 in. [92 mm]
trating the consequences of certain tolerance condi-
tions shown. These examples only address tolerance
Therefore, increase the size of the angel to:
related issues and do not represent a complete con-
sideration of all of the elements which must be consid-
ered in a comprehensive design of connections. 6 in. x 4 in. [152 mm x 102 mm]
Fi .19.1.1
Panel location
+ W' higher
Insert location f--- than nominal
%"higher
than nominal L6 X 4"
Insert L4 x 4"
Insert -
Slot in angle
p"
upport
t "" 4 "
location %'
lower than
"t'
4 nominal
Precast Precast
Concrete Concrete
Panel Cast~in-place con- Panel Cast-In-place con-
crete support crete support
Theoretical tolerances; all dimensions nominal Possible condition with all tolerances combined
(a) (b)
166
19.2 Clip Angle Supporting a Precast Con- To keep the eccentric load ofthe angle at 5 in. [127
crete Panel mm], the shims must be shifted toward the precast
panels as shown. This results in torsion in the support
In this case, the designer has determined that the beam, which may not be accounted for in its original
line of load is desired to be at the center line of the design.
supporting beam to avoid torsion in the beam. If all If Condition No. 2 shown in Fig. 19.2.1 (c) exists, to
dimensions are basic or nominal as shown in Fig. keep from eccentrically loading the support beam,
19.2.1 (a}, no torsion in the supporting beam results the eccentricity of the loading of the angle increases
from the connection and the angle is designed with to 6.25 in. [159 mm]. This results in a requirement to
an eccentricity equal to 5 in. [126 mm]. increase the thickness of the support angle.
Possible Condition No. 1, shown in Fig. 19.2.1 (b) The conclusion is generally the same as example
may exist because the beam sweep tolerance is 1 in. 19.1. It will likely be more economical to use a heavier
[25 mm] away from the panel (AISC Code of Standard angle and load the steel support beam though its cen-
Practice) and the panel is located 0.25 in. [6 mm] troid.
away from its nominal position (see Article 12).
Fi . 19.2.1
Steel
' -1"Beam
support I I sweep
Line of
Precast load
concrete
panel
167
19.3 Precast Corbel withSteelto Steel Bearing lion of tolerances.
It should be noted that corbels designed for ulti·
If all of the dimensions are nominal as shown in mate loads will support beams experiencing ultimate
Fig. 19.3.1 (a), or if a favorable tolerance condition ex- deflections. This may result in a condition similar to
ists as shown in 19.3.1 (c), a corbel designed for an that shown in Fig. 19.3.1(d). This will occur even
eccentricity equal to 41/, in. [114 mm] would be ade- when all of the feature dimensions of both the beam
quate. and the column haunch were originally at nominal val·
If the situation shown in Fig. 19.3.1 (b) exists due ues. The use of bearing pads is encouraged to en-
to the slope of the haunch bearing (Reference Article sure better load distribution.
10), or if the situation shown in Fig. 19.3.1 (d) exists The use of properly designed beam end armors as
due to tipping of the bearing plate, the corbel must be shown in Fig. 19.3.1 (e) is another way of addressing
designed for an eccentricityof8.0 in. [200 mm], an in- this situation. The column haunch armor design must
crease of 78 percent. take into account the higher concentrated load asso-
It is very unlikely that the nominal zero tolerance ciated with this detail. The joint must be detailed to
condition shown in Fig. 19.3.1 (a) will occur and it is assure that the unarmored concrete on the beam sof-
quite possible that the condition shown in Fig. fit does not bear on the haunch armor plate. This de-
19.3.1 (b) or (d) will occur. Therefore, the corbel tail can be less tolerance critical than the detail shown
should be designed for the most adverse configura- in Fig. 19.3.1(a) through 19.3.1(d).
168
Fig 19.3.1 Precast Corbel with Bearing
Precast Precast
concrete concrete
beam beam
s"
Precast Precast
concrete concrete
column column
Theoretical tolerances; all dimensions nominal Haunch plate tipped: maximum haunch eccentricity
(a) (b)
Precast
concrete
beam
r!
I
<
<4''~ L
Precast
concrete
column
169
19.4 Effects of Beam Camber in the example shown has been finished level, without
regard to the cambered position ofthe beam finished
Prestressed floor and roof members usually exhib- surface.
it camber as a result of eccentric prestress force. The The reduced topping thickness at the mid-span
camber is a function of the design of the product and location may cause problems if not anticipated in de·
since it is subject to product tolerances, may not be sign, or excess topping may be required if the design
"built-in" to the desired levels. mid-span topping thickness is to be maintained and
If the effect of camber is neglected, the situation the top of the topping elevation is raised. This condi-
shown in Fig. 19.4.1 (a) may be the condition that the tion also leads to variations in topping dead load
designer expects. which may differ from design assumptions.
In actual fact, however, the real condition may re· The dimensional effects of design camber, espe-
semble Fig. 19.4.1 (b), where a long-span member cially of long-span members, should be evaluated as
may have several inches of camber. The floor topping part of the design process.
r- Topping ["""Topping
- I .I
7
'
I
'------- Double tee
L· Double tee
-lrv
(a) (b)
170
19.5 Effects of Camber Variation on Top Since welded diaphragm connections between
Flange Connections members of this type are common, the designer
should consider how the connections will be made
under conditions of adverse combinations of product
Camber variations between adjacent beam mem- and erection tolerances. This condition can also lead
bers can create significant dimensional discontinui- to excessive topping on one member while the adja-
ties which may make the completion of important cent member may receive too little topping.
connections difficult. Specifications for erection should address the
In the section shown in Fig. 19.5.1, a step of 0.75 maximum allowable difference in adjacent member
in. [19 mm] between the flanges is possible, even if top elevations if this is a design consideration for ei-
both of the long span roof or floor members are within ther connection effectiveness or topping thickness.
the differential camber tolerance.
Fi . 19.5.1 e Connections
r
Mismatch that connection
must accommodate
Topping
) I
.
.
171
19.6 Deflection of Supporting Elements Loading from other sources may also cause
deflection related problems. For example, if precast
II support member deflection is neglected when a concrete is erected prior to floor slab construction, the
series of small architectural panels are supported on weight of the floor may deflect the support beams and
a long span beam, the designer may expect that the cause a problem similar to that shown in Fig.
condition will be as shown in Fig. 19.6.1 (a). 19.6.1 (b).
In actual fact, if the supporting beam is very flex- This effect can be avoided by either determining
ible, the final condition may be as shown in Fig. the beam intermediate and final deflections, and set-
19.6.1 (b). The support beam will deflect in incre- ting the precast concrete panels such that the final
ments as each panel is erected, resulting in an in- deflected condition of the support beam will bring
plane rotation of the panels previously erected. This them into alignment. Alteratively, adjustments can be
rotation can result in variations in joint widths as illus- made to the panels alter they have all been erected.
trated in Fig. 19.6.1 (b).
Uv lv
Assumed condition neglecting support member deflection
(a)
Lv Ly.._
Possible condition resulting from support member deflection
(b)
172
19.7 Panel Supported by a Cantilever movement of the panel, but also in rotation as shown
in Fig. 19.7.1 (c).
Panels supported by cantilever construction re· Of particular note is the condition when panels
quire extremely careful consideration because of the supported on cantilever supports are adjacent to
tendency of cantilevers to deflect and rotate signifi· panels supported in a different manner. This may re-
cantly. Often, the best way to solve this problem is to sult in unwanted joint tapers and jogs in alignment.
use a support scheme that does not rely on cantilever The possibility of increased deflection and rotation of
action. Such a solution is shown in Fig. 19.7.1 (a). If the panel over time, resulting from creep off the sup-
the detail shown in Fig. 19.7.1 (b) is used, any deflec· porting cantilever, must also be considered.
lion of the cantilever will not only result in vertical
c~~~~=~:
panel
---llu~~===::;::===? Support member
Auxiliary
strut
support
Precast ~
Cantilever
support
member
r Deflected cantilever
support member
173
20.0 References 15. Spotts, M.F. "Simple Guide to True Position
Dimensions." Machine Design Magazine
1. Precast/Prestressed Concrete Institute. Ar- (January 22, 1976).
chitectural Precast Concrete. Chicago: Pre· 16. Latta, J.K. "Inaccuracies in Construction."
cast/Prestressed Concrete Institute, 1973. Canadian Building Digest 4 (April 1975).
2. Precast/Prestressed Concrete Institute. PC/ 17. Holbek, K., and PAndersen. "European Con-
Design Handbook - Precast and Pre- cepts of Construction Tolerances." ACI Jour-
stressed Concrete. 5th ed. Chicago: Precast/ na/74, no 3 (March 1977): 101-108.
Prestressed Concrete Institute, 1999. 18. American Institute of Steel Construction.
3. Barry, Austin B. "Errors in Practical Measure- Code of Standard Practice for Steel Buildings
ment." In Science, Engineering and Technol- and Bridges. Chicago: American Institute of
ogy New York: John Wiley & Sons, 1978. Steel Construction, 1992.
4. Spots, M.F. "Fast Dimensional Check With 19. Foster, Cowell W. A Treatise on Geometric Di-
Statistics." Machine Design Magazine (Octo- mensioning and To/erancing. Minneapolis:
ber 12, 1978). The Honeywell Company, 1966.
5. Duster, J.A. "Are Your Tolerances Really Nec- 20. Amrhein, J.A. Reinforced Masonry Engineer-
essary?" Precast Concrete Magazine (June ing Handbook, Clay and Concrete Masonry
1971 ). 5th Edition. Los Angeles, California: Masonry
6. Griffiths, T.J. Standardization and Tolerances Institute of America, 1994.
in Precast Concrete Construction. CP 88/68. 21. Laursen, F. Brink. "Tolerances for the Main Di-
Building Research Station. United Kingdom: mensions of Concrete Components." Build
Ministry of Public Works, 1967. International (May-June 1971).
7. American Concrete Institute. "Standard Tol- 22. Federation lnternationale de Ia Precontrainte.
erances for Concrete Construction and Mate- "Tolerances for Concrete Structures." FIP
rials." ACI 117-90. Part 5 of ACI Manual of Joint Committee Report presented at the Fe-
Concrete Practice. Farmington Hills, Michi- deration lnternationale de Ia Precontrainte,
gan: American Concrete Institute, 1998. London, United Kingdom, November 15,
8. Canadian Standards Association. Precast 1977.
Concrete Materials and Construction National 23. American Concrete Institute Committee 315.
Standard of Canada. CAN3-A23.4-M78. Can- Details and Detailing of Concrete Reinforce-
ada: Canadian Standards Association, 1978. ment. ACI 315-92. Farmington Hills, Michi-
9. Speyer, Irwin. "Considerations for the Design gan: American Concrete Institute, 1992.
of Precast Concrete Bearing Wall Buildings to 24. Birkeland, Philip W., and Leonard J. Westhoff.
Withstand Abnormal Loads." PC/ Journa/21, "Dimensional Tolerances in a Tall Concrete
no 2 (March-April 1976). Building." GB-53. ACI Journal 68, no 8 (Au-
10. Norges Bygg Forkin·1ngs Institute. To/eranser gust 1971): 600-607.
i Bygg (Tolerances in the Building Industry). 25. American Concrete Institute. Recommended
Report No. 79. Norway: Norges Bygg Forkin- Practice for Concrete Formwork. ACI
ings Institute, 1973. 347R-94. Farmington Hills, Michigan: Ameri-
11. ''AISC Erection Tolerances for Columns." can Concrete Institute, 1994.
Modern Steel Construction, Third Quarter 26. Walker, H. Carl, and Marvin L. Vender, Wal.
(1975). "Tolerances for Precast Concrete Struc-
12. Fisher Ill, A. Ernest. "Tolerances Involving Re- tures." PC/ Journal 21, no. 4 (July-August
inforcing Bars." ACI Journa/74, no. 2 (Febru- 1986): 44-57.
ary 1977): 61-70. 27. PCI Committee on Tolerances. "Tolerances
13. Connally, J.P. and D. Brown. "Construction for Precast and Prestressed Concrete." PC/
Tolerances in Reinforced Concrete Journa/26, no. 2 (March-April1981): 40-72.
Beam-Joists." ACI Journal 73, no. 11 (No- 28. PCI Committee on Tolerances. Discussion of
vember 1976): 613-617. Tolerances for Precast and Prestressed Con-
14. Stephan, D.E., and A. Murk. "Establishing crete, by PCI Committee on Tolerances. PC/
Tolerances in Concrete Construction." ACI Journal 27, no. 4 (July-August 1982):
Journa/74, no. 5 (May 1977): 208-211. 140-142.
174
29. PCI Committee on Tolerances. "Tolerances 31. Precast/Prestressed Concrete Institute.
for Precast and Prestressed Concrete." PC/ Manual for Quality Control for Plans and Pro-
Journal 30, no. 1 (January-February 1985): duction of Architectural Precast Concrete
26-112. Products. MNL-117 -96. 3rd ed. Chicago: Pre-
30. Concrete Reinforcing Steel Institute. Manual cast/Prestressed Concrete Institute, 1996.
of Standard Practice. 26th Ed. Chicago: Con- 32. Precast/Prestressed Concrete Institute.
crete Reinforcing Steel Institute, 1997. Manual for Quality Control for Plants Produc-
ing Precast/Prestressed Concrete Products.
MNL 116-99. Chicago: Precast/Prestressed
Concrete Institute, 1999.
175
Appendix A-Sample Specification Language
Element tolerances for architectural precast concrete members shall be per Tolerances for Precast and Pre-
stressed Concrete Construction, MNL 135-00, by the Precast/Prestressed Concrete Institute, Article 10.1 and as
amended with the special project tolerances listed below.
Element tolerances for architectural concrete trim members shall be per Tolerances for Precast and Prestressed
Concrete Construction, MNL 135-00, by the Precast/Prestressed Concrete Institute, Articles 10.29, 10.30 and
10.31 and as amended with the special project tolerances listed below.
176
A.J To Specify Tolerances for Structural Precast Concrete Elements
Element tolerances for structural concrete members shall be per the applicable element type as described in
Tolerances for Precast and Prestressed Concrete Construction, MNL 135-00, by the Precast/Prestressed Concrete
Institute, Article 10.0 with Articles 10.1, 10.29, 10.30 and 10.31 specifically deleted and as amended with the special
project tolerances listed below.
A.4 To Specify Tolerances for Group CA/BA Structural Elements with Special Surface Finishes
Element tolerances for Group CNBA structural concrete members shall be per the applicable element type as
described in Tolerances for Precast and Prestressed Concrete Construction, MNL 135-00, by the Precast/Pre-
stressed Concrete Institute, Article 10.0 with Articles 10.1, 10.29, 10.30 and 10.31 specifically deleted and as
amended with the special project tolerances listed below.
177
A.S To Specify Erection Tolerances for Architectural Precast Concrete Elements
Erection tolerances for architectural precast concrete members shall be per Tolerances for Precast and Pre-
stressed Concrete Construction, MNL 135-00, by the Precast/Prestressed Concrete Institute, Article 12.5 and as
amended with the special project tolerances listed below.
Erection tolerances for structural precast concrete members shall be per Tolerances for Precast and Prestressed
Concrete Construction, MNL 135-00, by the Precast/Prestressed Concrete Institute, Article 12.0with Article 12.5
specifically deleted and as amended with the special project tolerances listed below.
178
A. 7 To Specify Erection Tolerances for Group CA/BA Structural Precast Concrete Elements
Erection tolerances for Group CA/BA structural precast concrete members shall be per Tolerances for Precast
and Prestressed Concrete Construction, MNL 135-00, by the Precast/Prestressed Concrete Institute, Article 12.0
with Article 12.5 specifically deleted and as amended with the special project tolerances listed below.
179
Appendix B-Sample Contract Language - Responsibility for Project Tolerances
The responsibility for the development of the project tolerance plan in the project lies with the following party:
Owner
Architect of Record
_ _ Engineer of Record
Precast Producer
General Contract
Owner
Architect of Record
_ _ Engineer of Record
Precast Producer
General Contract
The responsibility for tolerances on this project are further defined on the attached matrix title "Responsibility
for Tolerances" which has been prepared specifically for this project.
180
Fig. 8.1 Tolerance Responsibility
Comments
Project Activity Owner Architect/ General Precast Precast Precast Erector Erection
Engineer Contractor Plant Man- Plant Plant Manage- Quality
agement Engineer- Quality ment Control
lng Control
Set Requirements
-----
Specify Typical Product Tolerances
CD
~
Select Interface Tolerance Details
Legend: P = Prime Responsibility A/A= Review and Approval Authority I = Input Required From