Project Management CPM, Pert and MSP
Project Management CPM, Pert and MSP
MANAGEMENT
CPM , PERT AND MSP
CONSTRUCTION MANAGEMENT
AISHWARYA VASANT SANAP
ROLL NO 2
FIRST YEAR M.ARCH
DR. D. Y. PATIL COLLEGE OF ARCHITECTURE, AKURDI.
What is a project ?
‘’ A project is a series of activities directed to
accomplishment of a desired objective.”
Project
Network : Provi des the basis for Provi des an estimate of the
budgeting cash flow. project’s duration.
Network Diagrams
• Uses nodes to represent the activities & • Uses arrows to represent the activities & nodes
arrows to precedence relationship. to represent events.
B 3 D
A
1 2 DUMMY 6 7 8
G H
C 4 5 F
E
GANTT CHART
Advantages Limitations
• Gantt chart are quite commonly used. • Do not clearly indicate details regarding the
process of activities.
• They provide as easy
graphical representation of when • Do not give clear indication
activities (might) take place. of interrelationship between the separate
activities.
Network Planning Techniques
PERT CPM
Program Evaluation & Review Critical Path Method
Technique
• Project management technique that • step-by-step project
shows the time taken by each component management technique
of a project, and the total time required for process planning that defines —
for its completion. critical and non-critical tasks with the goal
of preventing time-frame problems.
• PERT breaks down the project
into events and activities, and lays down • Ideally suited to projects consisting of
their proper sequence, relationships, and numerous activities that interact in a
duration in the complex manner
form of a network.
CPM
• Critical path is the sequence of activities between a project’s start & finish that takes the longest
time to complete.
• CPM was developed by Duo Pont & the emphasis was on the trade – off between the cost of
project & its overall completion time.
• Steps In Determining Critical Path :
• CPM was developed for complex but fairly routine projects with
minimum uncertainly in the project completion times.
Estimation
• EF-Earliest finish time: equals to the earliest start time for the
activity plus the time required to complete the activity. ( EF =
ES + time required to complete the activity)
in CPM • LF- Latest finish time: the latest time in which the activity can be
completed without delaying the project.
• LS- Latest Start time: equal to the latest finish time minus the
time required to
complete the activity. ( LS = LF — time required to complete the
activity)
• Forward Pass: The early start and early finish times are calculated
by moving forward through the network and considering the
predecessor activities.
• Backward Pass: The latest start and finish times are calculated by
moving backward through the network.
• Slack Time: Slack time for an activity is the difference between its
earliest and latest start time or between the earliest and latest finish
time. Critical path is the path of activities having zero Slack time.
Immediate Immediate
Activity Predecessor Predecessor A C
A - 5
Start Finish
B - 6
C A 4 B D
D A, B 2
ES Earliest Starting
( Time )
Activity ES EF EF Earliest Finishing
Slack
Time LS Latest Starting
Exp time LS LF
LF Latest Finishing
• PERT was developed by the US Navy for the planning and control of the Polaris
missile program and the emphasis was on completing the program in the shortest
possible time.
• Steps In PERT:
• While the PERT asks for the most likely, the optimistic and pessimistic
PERT in durations of a task, the CPM asks similar questions—only phrased
slightly differently. CPM uses a single time estimate for each task and
Project focuses on the analysis of the duration task sequences to estimate
the total time required to complete a project.
Management • CPM allows project managers to identify the critical activities of a
project, which are those that can’t be delayed. Using them together
within a project management software results in a more complete
analysis of the project plan and a more accurate timeline.
• PERT/CPM is used to plan the scheduling of individual activities that make
up a project.
• PERT and CPM are similar in their basic approach, they do differ in the way
activity times are
estimated.
Both CPM • For each PERT activity three times (optimistic, pessimistic and most likely
times) are combined to determine the expected activity completion time and
and PERT
its variance. Thus, PERT is a probabilistic technique: it allows us to find the
probability of the entire project being completed by any given date.
• CPM, on the other hand, is called a deterministic approach. It uses two time
estimate, the normal time and the crash time, for each activity.
• PERT and CPM have been used to plan, schedule, and control a wide
variety of projects:
• R&D of new products and processes.
• Construction of buildings and highways.
• Maintenance of large and complex equipment.
• Design and installation of new systems.
1. When will the entire project be completed?
2. What are the critical activities or tasks in the project, that is, the ones that
will
delay the entire project if they are late?
3. Which are the noncritical activities, that is, the ones that can run late
without
Questions
delaying the whole project's completion time?
answered date?
CPM 6. On any given date, is the money spent equal to, less than, or greater than
the
budgeted amount?
Management? • MSP defines programme management as, the action of carrying out
the coordinated organization, direction, and implementation of a
dossier of projects and transformational activities (i.e. the
programme) to achieve outcomes and realize benefits of strategic
importance to the business.
• Defining a programme - Once the Programme Brief is approved, it can be used to help create the ‘Programme Definition
Document’. This will summarise the documentation created at this stage of the process, helping to fully define the upcoming
program.
• Managing the tranche - This process implements the governance for the program, while also acknowledging that it may need to
be changed over time. This ‘governance’ will be made up of the processes, procedures and functions which define how the
program is set up, managed and controlled.
• Delivering the capability - This is the process of coordinating and managing project delivery. It includes starting, monitoring and
concluding projects listed in the ‘Project Dossier’, in order to deliver outputs which will enable the capabilities described in the
Blueprint.
• Realizing the benefits - This process controls the benefits and ensures their successful realization. It provides the capabilities to
enable business change and, in turn, create successful outcomes and benefits.
• Closing the program - Part of managing a successful program is realizing when to conclude it