PROJECT: WATER PROOFING & INSTALATION OF DOWNSPOUT

LOCATION: Poiduran DS
FROM:
AS OF:

BIDFORM

Scope of Works: HAULING WORKS,PLUMBING WORKS, PAINTING WORKS, MORTAR TOPPING & WATERPROOFING

Note:
1. Any unwanted dirt or damages and other works caused by this scope shall be subject for cleaning, repair or replacement.
2. Any damage/s on materials and fixtures furnished by the owner/company which has which has been turned over & received by the
contactor shall be subject for cleaning, repair or replacement.

DESCRIPTION QTY UNIT U-COST AMOUNT

DOWNSPOUT @ 8 MTRS IN HIGH APROXIMATE 240 SQM


DEBRIS 1 LOT
2ND FLR EXTERIOR WALL (TO BE WATERPROOF) 196.8 SQM
3ND FLR EXTERIOR WALL (TO BE PAINT FINISHED) 196.8 SQM
ROOFDECK (TO BE WATER PROOF)BITOKOTE 530 SQM
ROOFDECK (TO BE MORTAR TOPPING) 530 SQM
2 SIDE parapet to be waterproof 63.6 SQM
REAR SIDE PARAPET TO BE WATERPROOF 75 SQM

TOTAL MATERIAL COST


TOTAL LABOR COST
TOTAL DIRECT LABOR AND MATERIALS
Mobilization/Demobilization
Overhead Cost
Temporary Facilities

SUB-TOTAL COST
GRAND TOTAL COST