Time Schedule - Pfizer

The document outlines the schedule for supplying and installing a fire suppression system at Pfizer Indonesia over 214 days from July 3, 2021 to October 6, 2021. Key aspects of the project include preliminary works such as design approval, material procurement, and site preparation from March to August 2021. Services like equipment delivery and installation, piping works, and testing and commissioning are scheduled from June to October 2021. The schedule is broken down into detailed tasks with assigned durations and predecessor dependencies.

Uploaded by

Bagus Prambudi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
2K views2 pages

Time Schedule - Pfizer

The document outlines the schedule for supplying and installing a fire suppression system at Pfizer Indonesia over 214 days from July 3, 2021 to October 6, 2021. Key aspects of the project include preliminary works such as design approval, material procurement, and site preparation from March to August 2021. Services like equipment delivery and installation, piping works, and testing and commissioning are scheduled from June to October 2021. The schedule is broken down into detailed tasks with assigned durations and predecessor dependencies.

Uploaded by

Bagus Prambudi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

PROJECT SCHEDULE SUPPLY & INSTALLATION OF FIRE SUPPRESSION SYSTEM - PFIZER INDONESIA

ID WBS Task Name Duration Start Finish Predecessors Mar '21 Apr '21 May '21 Jun '21 Jul '21 Aug '21 Sep '21 Oct '21
1 1 INSTALASI FIRE FIRE FIGHTING PFIZER GANDARIA 214 days Sun 07/03/21We d 06/10/21
2 1.1 PO Received 1 day Sun 07/03/21 Sun 07/03/21
3 1.2 PRELIMINARY WORKS 161 daysMon 08/03/21 Sun 15/08/21
4 1.2.1 Design Draw ing & Approval Material (Circulating Doc) 21 day s Mon 08/03/21 Sun 28/03/21 2
5 1.2.2 Approved Draw ing & A pproval Material (Design Freeze / IFC) 7 days Mon 22/03/21 Sun 28/03/21 4FS-7 days
6 1.2.3 Purchase Installation Material (Local) 90 day s Mon 22/03/21 Sat 19/06/21 5FS-7 days
7 1.2.4 PIM (Visual & Qty Check only) 2 days Sun 20/06/21 Mon 21/06/21 6
8 1.2.5 Purchase Main Equipment 140 days Mon 29/03/21 Sun 15/08/21 5
9 1.2.6 Site Of f ic e, Warehouse, Fabrication Facility, etc Work 7 days Mon 22/03/21 Sun 28/03/21 4FS-7 days
10 1.3 SERVICES 85 days Tue 22/06/21 Tue 14/09/21
11 1.3.1 Main Equipment Internal QC Check 2 days Mon 16/08/21 Tue 17/08/21 8
12 1.3.2 Deliv ery Installation Material 50 day s Tue 22/06/21 Tue 10/08/21 7
13 1.3.3 Deliv ery Main Equipment 2 daysWed 18/08/21 Thu 19/08/21 11
14 1.3.4 FIRE PROTECT ION PIPING EXTERNAL 63 daysWe d 14/07/21 Tue 14/09/21
15 1.3.4.1 Main Pipe Installation 60 day sWed 14/07/21 Sat 11/09/21 12FS-28 days
16 1.3.4.2 Equipment Installation 10 day s Sun 05/09/21 Tue 14/09/21 15FS-7 day s
17 1.3.4.3 Fire Sprinkler Installation 45 day s Thu 29/07/21 Sat 11/09/21 15FS-45 days
18 1.3.4.4 Equipment Installation 10 day s Sun 05/09/21 Tue 14/09/21 17FS-7 day s
19 1.3.5 FIRE PROTECT ION PIPING DAT A HALL 63 daysWe d 14/07/21 Tue 14/09/21
20 1.3.5.1 Piping and Pulling Cable f or Fire Alarm & V esda 60 day sWed 14/07/21 Sat 11/09/21 12FS-28 days
21 1.3.5.2 Fire Alarm Equipment Installation 60 day sWed 14/07/21 Sat 11/09/21 12FS-28 days
22 1.3.5.3 Cable Termination 10 day s Sun 05/09/21 Tue 14/09/21 21FS-7 day s
23 1.3.5.4 Fire Sprinkler Installation 60 day sWed 14/07/21 Sat 11/09/21 12FS-28 days
24 1.3.5.5 Equipment Installation 10 day s Sun 05/09/21 Tue 14/09/21 23FS-7 day s
25 1.3.6 PROTECTION PIPING OFFICE AREA 52 days Tue 20/07/21 Thu 09/09/21
26 1.3.6.1 Piping and Pulling Cable f or Fire Alarm 45 day s Tue 20/07/21 Thu 02/09/21 12FS-22 days
27 1.3.6.2 Fire Alarm Equipment Installation 7 days Fri 27/08/21 Thu 02/09/21 26FS-7 day s
28 1.3.6.3 Piping Installation 45 day s Tue 20/07/21 Thu 02/09/21 12FS-22 days
29 1.3.6.4 Accessories Installation 7 days Fri 27/08/21 Thu 02/09/21 28FS-7 day s
30 1.3.6.5 Pump Installation 21 day s Fri 20/08/21 Thu 09/09/21 29FS-14 days
31 1.3.6.6 Cable Termination f or Pump 4 days Mon 06/09/21 Thu 09/09/21 30FS-4 day s
32 1.3.6.7 Fire Sprinkler Installation 30 day s Tue 20/07/21Wed 18/08/21 12FS-22 days
33 1.3.7 FIRE PROTECT ION PIPING GUARD HOUSE 20 days Thu 19/08/21 Tue 07/09/21
34 1.3.7.1 Piping and Pulling Cable f or Fire Alarm 20 day s Thu 19/08/21 Tue 07/09/21 32
35 1.3.7.2 Fire Alarm Equipment Installation 20 day s Thu 19/08/21 Tue 07/09/21 32
36 1.3.7.3 Fire Sprinkler Installation 20 day s Thu 19/08/21 Tue 07/09/21 32
37 1.3.7.4 Equipment Installation 20 day s Thu 19/08/21 Tue 07/09/21 32
38 1.3.8 PORTABLE FIRE EXTINGUISHER INSTALLATION 9 days Fri 20/08/21 Sat 28/08/21
39 1.3.8.1 Data Hall 3 days Fri 20/08/21 Sun 22/08/21 13
40 1.3.8.2 Of f ice A rea 2 days Mon 23/08/21 Tue 24/08/21 39
41 1.3.8.3 External Building 2 daysWed 25/08/21 Thu 26/08/21 40
42 1.3.8.4 Guard House 2 days Fri 27/08/21 Sat 28/08/21 41
43 1.4 TESTING & COM MISSIONING 29 daysWe d 08/09/21We d 06/10/21
44 1.4.1 FIRE PROTECT ION PIPING EXTERNAL 11 daysWe d 08/09/21 Sat 18/09/21
45 1.4.1.1 Hydrotest (Internal & Witness by Ow ner) 7 daysWed 08/09/21 Tue 14/09/21 17FS-4 day s
46 1.4.1.2 Trouble shooting, Internal Test & Testing FA system 4 daysWed 15/09/21 Sat 18/09/21 45
47 1.4.2 FIRE PROTECT ION PIPING DAT A HALL 7 daysWe d 15/09/21 Tue 21/09/21
48 1.4.2.1 Hydrotest (Internal & Witness by Ow ner) 7 daysWed 15/09/21 Tue 21/09/21 24
49 1.4.2.2 Trouble shooting, Internal Test & Testing FA system 7 daysWed 15/09/21 Tue 21/09/21 22
50 1.4.3 PROTECTION PIPING OFFICE AREA 14 daysWe d 08/09/21 Tue 21/09/21

Task Project Summary Inactive Summary Manual Summary External Milestone

Project: PFIZER Indonesia Split External Tasks Manual Task Start-only Progress
Date: Fri 30/04/21
Milestone External Milestone Duration-only Finish-only Deadline

Summary Inactive Milestone Manual Summary Rollup External Tasks

Created by : Approved by :
PROJECT SCHEDULE SUPPLY & INSTALLATION OF FIRE SUPPRESSION SYSTEM - PFIZER INDONESIA
ID WBS Task Name Duration Start Finish Predecessors Mar '21 Apr '21 May '21 Jun '21 Jul '21 Aug '21 Sep '21 Oct '21
51 1.4.3.1 Hydrotest (Internal & Witness by Ow ner) 7 daysWed 15/09/21 Tue 21/09/21 24
52 1.4.3.2 Trouble shooting, Internal Test & Testing FA system 7 daysWed 08/09/21 Tue 14/09/21 35
53 1.4.4 FIRE PROTECT ION PIPING GUARD HOUSE 7 daysWe d 15/09/21 Tue 21/09/21
54 1.4.4.1 Hydrotest (Internal & Witness by Ow ner) 2 daysWed 15/09/21 Thu 16/09/21 24
55 1.4.4.2 Trouble shooting, Internal Test & Testing FA system 7 daysWed 15/09/21 Tue 21/09/21 22
56 1.4.5 Onsite training 1 day Wed 22/09/21Wed 22/09/21 55
57 1.4.6 As-built draw ing and final documentation 14 day s Thu 23/09/21Wed 06/10/21 56

Task Project Summary Inactive Summary Manual Summary External Milestone

Project: PFIZER Indonesia Split External Tasks Manual Task Start-only Progress
Date: Fri 30/04/21
Milestone External Milestone Duration-only Finish-only Deadline

Summary Inactive Milestone Manual Summary Rollup External Tasks

Created by : Approved by :