Unit 5 QB
Unit 5 QB
Unit 5 QB
8. State the two cost control coding system adopted at work site. (May/June 2007)
Cost control coding system at site
201 Clearing and Preparing Site
202 Substructure
202.1 Excavation and Shoring
202.2 Piling
202.3 Concrete Masonry
202.31 Mixing and Placing
202.32 Formwork
202.33 Reinforcing
PART – B
1. Write report to accompany an estimate for residential building for a executive engineer.
(Nov./Dec. 2016)
Report On Estimates for the Construction of Residential Building
The detailed estimate for construction of a residential building for the Executive Engineer at has
been prepared in compliance of S.E. letter no . dated .
There is no building for the residence of the Executive Engineer at Udaynagar and he has to live in a
rented building with meager accommodation at a very high rent. It has, therefore, been proposed to construct a
residential building for the Executive Engineer. The head of the accounts will be 50 civil original works,
building.
The estimate provides for the following accommodation:-
One drawing room, one dining room, three bed rooms, one guest room, and the necessary store kitchen,
baths, front and back verandahs and motor garage per plan enclosed. A site has already been selected having a
land of 60 m 30 m for the construction of the building having good soil and proper drainage and this much of
land has to be acquired. The building shall be oriented to face north direction
The building shall have lime concrete foundation and first class brick masonry with lime mortar up to
plinth level and the superstructure shall be of first class brick work in cement mortar, 1:6 Lintels shall be of
R.B. work and roof shall be R.C.C with lime concrete terrace finishing. The drawing and dining rooms shall
have mosaic floor and other rooms 2.5 cm c.c. floor over 7.5 cm lime concrete. Inside and outside walls shall be
12 mm cement line plastered 1:1:6, and ceiling shall be 6 mm cement plastered 1:3. Inside of drawing and
dining rooms shall be colour washed and inside of remaining rooms shall be white washed and outside wall be
colour washed. Doors and windows shall be 4.5cm 13 4 " thick teak wood with chaukhatosal wood and enamel
painted. All work shall be strictly as per detailed P.W.D. Specification.
The estimate has been prepared at P.W.D Schedule of rates, and for non-schedule items on analysis of
rates. The foundation has been designed for a safe load of 9 tonne per sq m (8 ton per sq ft) and the R.C.C roof
has been designed for a safe load of 150 kg per sq m (30 1bs per sq ft) with 1400 kg per sqcm (20000 1bs per sq
in) as sage tensile stress of steel and 50 kg sq cm (750 1bs per sq in) as safe compressive stress of concrete. All
designs and calculations have been included in the estimate. Plans and drawings and site plans are also enclosed
with the estimate.
Provision has been made for electrification and sanitary and water supply works and 20% of the
estimated cost of the building works ahs been included for these works. As there is no sewer line in the area a
septic tank shall have to be constructed for which lump sum provision of Rs.700,00 has been made in the