Method Statement For Laying of MCC Duct and Civil Works For MCC Network

This document provides a method statement for laying MCC ducts and civil works for an MCC network in Riyadh City, Saudi Arabia. It outlines the objectives, references, resources, health and safety requirements, and detailed construction sequence for activities like foundation casting, duct construction, street light and pole installation, cable laying, and testing. The method statement was prepared by KBR Services for Modon Properties to guide the installation of the MCC network.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2K views26 pages

Method Statement For Laying of MCC Duct and Civil Works For MCC Network

This document provides a method statement for laying MCC ducts and civil works for an MCC network in Riyadh City, Saudi Arabia. It outlines the objectives, references, resources, health and safety requirements, and detailed construction sequence for activities like foundation casting, duct construction, street light and pole installation, cable laying, and testing. The method statement was prepared by KBR Services for Modon Properties to guide the installation of the MCC network.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 26

Method Statement for Laying of

MCC duct and Civil Works for


MCC Network

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Development Project Library for the current version.

Template Ref. No.: RS-01-00001-00-19-OA-KBR-FO-000002 | Rev. no.: 00


Prepared by:
KBR Services, Inc.
PO Box 127741,
Abu Dhabi United Arab Emirates
www.kbr.com

Prepared for:
Modon Properties
P.O. Box 26866,
Abu Dhabi, United Arab Emirates
www.modon.ae

This document is the property of KBR and Modon.

All rights reserved. No section or element of this


document may be removed from this document,
reproduced, electronically stored or transmitted in any
form without the written permission of KBR and Modon.

This document contains confidential or proprietary


information which may be subject to export control and
should not be copied, reproduced, republished, uploaded,
transmitted, printed or distributed in any way without prior
written authorization as required
Programme Management
Infrastructure and Streetscape
Riyadh City

Programme Name : Riyadh City South


Reference No. : RS-02-00001-05-11-SS-SBD-MT-000001[00]
Rev. No. : 00
Date : 13/12/2020

REVISION HISTORY

R00 Issued for approval

REV. NO DATE DESCRIPTION

APPROVALS
Printed initials in the boxes confirms that the document has been reviewed and approved. Approved
records are saved on Riyadh City Program Library.

Author
Checked By Dhia Yousif
Reviewed By John Nielsen
Approved By Vimal Kumar
NAME SIGNATURE DATE

Table of Contents
DESCRIPTION PAGE NO.
Content
Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 4 of 27

1. Objective and Scope.................................................................................................................7

2. References................................................................................................................................7

2.1 Codes of Practice / Legislative Code...........................................................................7

2.2 Applicable ADM Applications....................................................................................8

2.3 Specification Details....................................................................................................9

3. Definitions................................................................................................................................9

4. Resources...............................................................................................................................10

4.1 Approved Material Submittal....................................................................................10

4.2 Approved Subcontractor and Pre-Qualification Documents......................................11

4.3 Shop Drawings..........................................................................................................11

4.4 Equipment’s required and Third-Party Certificates...................................................11

4.5 Human Resource.......................................................................................................12

5. HSE Requirements.................................................................................................................15

5.1 Personal Protective Equipment..................................................................................15

5.2 Emergency Arrangements.........................................................................................15

5.3 Training.....................................................................................................................16

5.4 Induction:..................................................................................................................17

6. Detailed Construction Sequence (Methodology)....................................................................17

6.1 Preliminaries..............................................................................................................18

6.2 Street Light and Control Cabinet Foundation Casting and Installation......................19

6.2.1 Pre- cast of Concrete Control Cabinet Foundation....................................................19

6.2.2 Casting/pre casting of Concrete street light Pole foundation.....................................19

A. Form work.................................................................................................................20

B. Fixing of the Anchor Bolts........................................................................................20

C. Concreting of Foundation..........................................................................................20

D. Concrete Placement...................................................................................................20

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 5 of 27

6.2.3 Curing, storage and transportation of Street Light foundation...................................21

6.2.4 Drilling, Excavation & Erection of Street light & Control Cabinet foundation........21

6.2.5 Back filling of Surround............................................................................................22

6.3 Duct Construction......................................................................................................22

6.3.1 Road Crossings..........................................................................................................22

6.4 Street Light fittings & Pole Installation.....................................................................23

6.4.1 Preparation and Site Requirement.............................................................................23

6.4.2 Transporting and Unloading the Street Light Poles...................................................24

6.4.3 Installation of Street Light fittings and accessories:..................................................24

6.4.4 Installation of Street Light poles:...............................................................................25

6.4.5 Procedure for testing verticality of Poles:..................................................................26

6.4.6 Procedure for Grouting of Poles:...............................................................................26

6.4.7 Earthing for Street Light Poles & Control Cabinet....................................................26

6.4.8 Numbering of Street Light Poles...............................................................................26

6.5 CABLE LAYING WORKS.......................................................................................26

6.5.1 Preparation of Site requirement.................................................................................26

6.5.2 Excavation.................................................................................................................27

6.5.3 Transportation of Cable Drums.................................................................................27

6.5.4 Routing......................................................................................................................28

6.5.5 Cable Laying.............................................................................................................28

6.5.6 Back filling and Reinstatement..................................................................................30

6.6 Terminations works...................................................................................................31

6.7 Construction Programme...........................................................................................31

6.8 Inspection and Testing...............................................................................................31

6.9 Inspection of delivered cables....................................................................................32

6.10 Control Cabinet Inspection........................................................................................32

6.11 Site acceptance tests..................................................................................................33

6.12 Documentation:.........................................................................................................33

7. Construction Program.............................................................................................................34

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 6 of 27

8. Quality Control ITP & Inspection Check List........................................................................34

9. Quality Risk Assessment........................................................................................................35

10. Risk Assessment / Hazzard Assessment.................................................................................35

11. Third Party Certificate Requirements, if any..........................................................................35

12. Attachment (Shop drawings/Forms/sketches/certificates etc. as required.)............................36

12.1 Standard Drawings....................................................................................................36

12.2 Inspection & Test Plan..............................................................................................36

12.3 Hazard / Impact Assessment......................................................................................36

12.4 Quality Inspection Check list.....................................................................................36

1. Objective and Scope


The Objective of this Method of Statement is to describe the Method of the working procedures for
the installation of MCC NETWORKS and all other related civil works activities. in addition to
outline the materials, labor and workmanship required to undertake the works in a safe and
controlled manner, compiling with all relevant legislation, Standards and Codes of practice within
the limits of project Riyadh City South Phase 5 – Infrastructure and Streetscape.
The scope of works consists of Installation MCC Network – Civil works

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 7 of 27

The method statement shall be briefed to all appropriate operatives to ensure that they are aware of
the plan, sequence of activities & project specific requirements of Client/Consultant.
A constant monitoring and supervision duty shall be undertaken by SBD to ensure work activities
are carried out in accordance with the method statement. Any irregularities shall be immediately
took action.

2. References
2.1 Codes of Practice / Legislative Code
Document Reference No. Title

OSHAD Cop 1.0 Hazardous Material

OSHAD Cop 2.0 PPE

First Aid and Medical Emergency


OSHAD Cop 4.0
Management

OSHAD Cop 11.0 Safety in Heat

OSHAD Cop 14.0 Manual Handling and ergonomics

OSHAD Cop 15.0 Electrical safety

OSHAD Cop 17.0 Safety Signage and Signals

OSHAD Cop 21.0 Permit to Work

OSHAD Cop 22.0 Barricade of the Hazards

OSHAD Cop 23.0 Working at height

OSHAD Cop 25.0 Transport safety

OSHAD Cop 26.0 Scaffolding

OSHAD Cop 29.0 Excavation

OSHAD Cop 33.0 Working in Over or adjacent and road

OSHAD Cop 34.0 Safe use of lifting equipment

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 8 of 27

OSHAD Cop 35.0 Portable Power Tools

OSHAD Cop 36.0 Plant and Equipment

OSHAD Cop 37.0 Ladder

OSHAD Cop 44.0 Traffic management and logistics

OSHAD Cop 54.0 Waste Management

2.2 Applicable ADM Applications

Document Reference No. Title

MCC Network

Accessories of Street Lighting Cables

2.3 Specification Details

Document Reference No. Title

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 9 of 27

3. Definitions

DOCUMENT NO. DESCRIPTION

Employer MODON Properties PJSC

KBR Project Management Consultant

ARCADIS Engineer/ Lead Consultant

SBD Contractor: Saif Bin Darwish

PEMS Project Execution Method Statement

ITP Inspection and Test Plan

WIR Work Inspection Request

HIRA Hazard Identification Risk Assessment

NOC No Objection Certificate

ADM Abu Dhabi Municipality

UPVC Unplasticized Polyvinyl Chloride

4. Resources
4.1 Approved Material Submittal

Submittal will be prepared for the following materials to seek the Engineers approval prior to use in
permanent construction:
 8.5m single & Double arm pole (4.0m)
 75 mm UPVC pipe for duct.
 Anchor Bolts for 8.5m single arm pole (4.0m)
 Dune Sand

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 10 of 27

 Concrete mixer Grade SRPC K140


 BS 4449-05 Gr B-500B Uncoated steel
 Pull box cover and frame
 PVC Tapes, Nylon role
All Materials relevant to this Method statement will be used, constructed or installed following the
manufacturer’s technical recommendation / project specification, or as per agreed recommendation
by the engineer

4.2 Approved Subcontractor and Pre-Qualification Documents

Not Applicable

4.3 Shop Drawings

There are numerous numbers of shop drawings related with MCC Network shall be submitted. Only
Approved shop Drawings shall be used in construction methodology.
All Field works shall be carried out as per approved Shop Drawings & Standard Project Drawings.
Contractor is responsible for all site drawings to be maintained the as-built AutoCAD drawings /
GIS drawing as per ADM requirements.
Note: Shop Drawings are subject to revision and resubmission for approval whenever a new change
or update arises.

4.4 Equipment’s required and Third-Party Certificates

Listed Equipment below are required to execute the work

Equipment Number Required

Hi-up crane / Manitex crane. 1

4x4 Pick up 1

Flat Trailer. 1

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 11 of 27

Air Compressor 1

Small Generator 1

Auger machine 1

Surveying equipment’s. 1

All the materials used in this work shall be of good quality.

4.5 Human Resource

 Construction Manager
Specific responsibilities include:
- Executing project work plans. Tracking project milestones and deliverables.
Identify potential crises and devise contingency plans.
- Managing day-to-day operational aspects. Minimize exposure and risk on
project. Managing scope with respect to variations, with or without time and
cost impact. Managing delay issues, time extensions and cost claims.
- Oversee Quality, HSE, Sustainability and Environment matters on site.
- Achieving planned targets by effectively utilizing man, material and
equipment. Ensuring accurate measures of work required are being taken to
control construction cost.
- Liaising with project stakeholders and customers.
- Ensuring availability of workforce with required skills as per project plan.
Providing leadership to the project teams.
- Demonstrated commitment to improve skills and knowledge of subordinates
and self. Share and implement work-related knowledge and skills
 Site Engineer(s)
Specific responsibilities include:

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 12 of 27

- Ensuring that the work execution will be performed in a safe manner and meets
the requirements of the project documentation.
- Ensuring that all shop drawings and material used in permanent works is are
issued for construction or as approved by the Engineer.
- Shall ensure that operatives comply with the relevant method statements,
Toolbox Talks and general site briefings.
- Ensuring that sub-contractors achieve the on-site required standards.
- Carrying out phased inspections as required & ensuring that completed works
are offered for inspection for approval to concerned parties within specific
dates/ programmers.
- Monitoring the close-out activities of the project and maintain a smooth hand-
over.
- Shall refer to the QA/QC Department and the HSE Department for advice and
guidance when required.
 QA/QC Engineer(s)
Specific responsibilities include:
- Shall ensure that operatives comply with the relevant method statements will
be followed by initiating Toolbox Talks and general site briefings.
- Ensuring that staff is aware of their responsibilities in respect of quality
requirements.
- Ensure that all technical submittals used in construction are the current
versions & approved by the Engineer or other relevant Authority.
- Ensuring that materials are inspected when delivered to ensure they comply
with the various specifications prior to use.
 HSE Officer (s)
Specific responsibilities include:
- Assisting in the production of any health, safety and environmental documents.
- Monitoring the implementation of health, safety and environmental
requirements.
- Undertaking audits and ensuring that corrective and preventive actions are
taken where required.
- Liaise with the senior site staff on health, safety and environmental related
matters.

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 13 of 27

 Surveyors
Specific responsibilities include:
- Administering & guiding all assistant surveyors/ instrument men/ chainmen
within the project to complete the assigned job.
- Determining precise location, measurements/ stakeout of points, elevation,
lines, areas and contours for construction, mapmaking, land divisions etc. as
per approved shop drawings.
- Coordinating with Chief Surveyor / Engineers/ Foremen/ Chief Draftsmen for
Survey Works.
- Monitoring the calibration validity of all survey instruments in the project, their
accounting and maintenance.
- Preparing Survey Reports on daily basis to all construction activities &
maintaining all the survey records.
 Foremen
Specific responsibilities include:
- To ensure that all operatives and appropriate briefed as to the content of the
method statement and the works.
- To ensure the works are undertaken in a safe manner & quality control is
implemented.
- To ensure all operatives are adequately trained in their respective works.
- Reporting any un-safe practices on site to the SBD site team.
 Charge hand
 Site Foreman
 L D and H D Drivers
 Equipment Operators
 Electricians
 Helpers

5. HSE Requirements
5.1 Personal Protective Equipment

 Hard Hat (Helmet)


 Cover hall
 Hand Gloves
 Safety glasses
 Safety Shoes

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 14 of 27

 Safety Jackets
 Dust masks

5.2 Emergency Arrangements

 First aiders and first aid kit also assigned at different locations
 Emergency Contact Numbers as follows:

Contact Contact Number


SBD Sr. Project Manager 050 6168203
Construction Manager 0501061847
SBD Safety Manager 050 1067152
SBD Site Engineer 0501061847
Police 999
Ambulance 998
Abu Dhabi Municipality 993
Fire 997
Electricity 991
Water 992
Etisalat 8005500
Mafraq Hospital 02-5011111

 Emergency Contact numbers to be posted in strategic areas within the project


 Emergency vehicle with dedicated driver is on site
 Fire extinguishers present on various locations
 Emergency Procedure Shall be briefed to all Personnel in each Toolbox Talk
 Assembly point in the event of fire / other emergency shall be brief to all
Personnel.
 Contact numbers for the emergency services shall be provided by the Site
 Safety Officer and held by the Site Engineer & Foreman.
 All Workers involved in activity shall strictly follow the emergency procedure.

5.3 Training

This Method Statement shall be briefed to the appropriate personnel. This is essential to the safe
and successful completion of the operation. Records shall be kept of all briefings.

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 15 of 27

Prior to these works commencing, a review of the activities shall be undertaken in association with
the operatives undertaking the duties. This will identify where additional training and above
existing knowledge, or experience is required.
 SBD shall evaluate and perform the followings:
 Determine the necessary competence for personnel performing work affecting its
quality.
 Provide training or take other actions as to satisfy those needs.
 Evaluate the effectiveness of action taken.
 Ensure that its personnel are aware of the relevance and importance of their
activities and how they contribute to the achievement of the product.
 Toolbox talk will be given to operations.
 Emergency Contact numbers to be posted in strategic areas within the project
 Emergency vehicle with dedicated driver is on site
 Fire extinguishers present on various locations
 Emergency Procedure Shall be briefed to all Personnel in each Toolbox Talk
 Assembly point in the event of fire / other emergency shall be brief to all
Personnel.
 Contact numbers for the emergency services shall be provided by the Site Safety
Officer and held by the Site Engineer & foreman.
 All Workers involved in activity shall strictly follow the emergency procedure.

5.4 Induction:
 All Workers and Staff attend the HSE induction before commencing the work at
site
 All Persons shall adhere to PPE
 All Workers shall attend toolbox talk weekly (i.e. first day of the week)
 Any unsafe acts or condition are to be identified and corrected immediately and
referred to respective supervisor.
 Any accident or incident shall be reported immediately to take prevention measures
 All relevant JSA adhered to

6. Detailed Construction Sequence (Methodology)

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 16 of 27

Before starting the all works related street lighting network to be mentioned the getting of all
NOC’s from the related authorities.

6.1 Preliminaries

Before commencing the all works related MCC network installation in any area, the followings
need to be ensured:
 Site Survey shall be carried out according approved drawings.
 The MCC work to be done as per the approved shop drawings. Engineers strictly
are following the approved shop drawing.
 All installation works shall be carried out as per the approved schematic drawings.
 All material to be used shall be approved make.
 Concrete Mix Design shall be C40 and rebar type shall be BS 4449 -05 Gr B-500B
– Uncoated as per project and ADM Specifications.
 Check the Machinery working condition.
 All Reinforcement shall be placed according to bar bending schedule and anchor
bolts shall be approved drawings.
 The route to be excavated will be checked for existing services (if any) and marked
for excavation as per shop drawing.
 Dewatering to be done on the cable laying route if required.
 All backfilling & Compaction works shall be as per the approved Project
specifications and compaction will be done until a satisfactory degree has been
achieved and no more settlement is going to take place. This point cab identified by
observation and level checking.
 Appropriate personnel protection equipment’s shall be worn by personnel at work.
 Display safety warning signs around proposed excavation area as well as warning
tape.
 Excavation close to roads with traffic shall have warning traffic cones well as
“Slow down “Signs displayed on road.
6.2 MCC Pole, Pull Box and Control Cabinet Foundation Casting and Installation

6.21.1 Pre- cast of Concrete pull box

Reinforcement - Cutting, bending, prefabrication & fixing

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 17 of 27

 The reinforcement will be delivered in line with the programmed requirement by


the approved supplier with appropriate mill certificate and according to the general
specification
 Only approved source and supplier /Manufacturer shall be used
 All reinforcement steel shall be protected from mechanical injury or surface
deterioration from rusting or other causes from shipment to delivery
 Care shall be taken for reinforcement laid on wooden floors and suitably spaced
and in no case, it shall be contact with ground
 It will be protected from weather corrosion and water proofing.
 All delivery will be checked according to the scheduled and specified grade and
mill certificate will be checked against delivery and if any discrepancies it will be
informed to supplier within 48 hrs.
 Only verified and approved reinforcement shall be used for construction
 As per as possible prefabricated reinforcement shall be used and amount of onsite
fixing will be minimized
 The reinforcement will be fixed with approved tie wire.
 The binding will be done tightly with proper tools, and care shall be taken to ensure
that projection of ties remain within the minimum concrete cover.
 Before placing of concrete reinforcement shall be inspected with the Engineer.

6.21.2 Casting/pre casting of Concrete MCC Pole foundation

A Proper concrete plat form shall be prepared. Reinforcement cage & fabricated according to bar
bending schedule and approved shop drawing will be placed with prefabricated shutters (According
to approved drawing).
Construction of foundation for MCC poles shall be done the following requirements:
A. Form work
 Steel form work required as per dimensions of MCC foundation and it shall be
fixed properly.
 Rebar type for street light foundation shall be BS 4449 -05 Gr B-500B – Uncoated
as per ADM specifications.
 Reinforcement cage as per the drawing shall be fabricated and it shall be lowered
into the shutter assembly and aligned properly. The proper sizing of bars, correct

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 18 of 27

number of bars and spacing of the bars will be checked before lowering the cage
and proper cover shall be checked.
B. Fixing of the Anchor Bolts.
 Anchor bolts assembly will be fixed tightly and securely, it shall be checked for
plumb for verticality, and dimensions shall be as per drawings.
 Wooden template will securely to the anchor bolts and all the coordinates of shall
be checked before concrete.
C. Concreting of Foundation.
 Concrete shall be done as per the specification and concrete shall be consolidated
using a vibrator adequate for the size of pour.
D. Concrete Placement
 The concrete mix grade shall be C20/20 &C20/10 for Screed, C40/20 (SRPC+MS)
 After mixing the concrete at plant it will be immediately transferred to the site or
final destination to the stipulated time
 The concrete shall be placed gently in position
 Before placement the fresh concrete shall be checked for quality and all relevant
quality control checks shall be completed.
 Concrete shall be placed uniformly and along with structure in lifts of 30 to 40 cm
and thoroughly vibrated all along the structure care shall be taken against
segregation and honeycombs.
 Curing period shall be according to specified time as Water Based curing
compound use.
 Fresh concrete will be protected from weather, water and it will be covered with
polyethylene sheet or Hessian cloth.
 Make sure that the fixed elbows were not moved when concrete is poured

6.21.3 Curing, storage and transportation of Street Light foundation

 After and when concrete is set external shutter will be de molded by carefully by
unlocking the outer shutter and anchors.
 Before Lifting and transporting to the site at least 75 % strength (after 7days) shall
be obtained from testing Cube of compressive strength.
 After that foundation to be lifted by using slings and D shackles to the flat bed
crane with care.

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 19 of 27

 Protective coating and water proofing for the foundations shall be done after
necessary concrete repairs with approved materials.
 All the PVC elbows openings shall be cleared before installation.

The Street light foundation will be transported to the site on low bed trailer with the help of crane
loading and approved slings and it will be directly placed the to the alignment and approved grade.
Proper care will be taken for safe handling of the foundation unloading.

6.21.4 Drilling, Excavation & Erection of MCC Pole & pull box

 All excavation for foundations for MCC poles shall be made by drilling, boring or
sinking a casing unless otherwise indicated on the drawings.
 All drilled foundation shall be installed in the presence of the Engineer.
 All foundation shall be located to the lines and spacing indicated on the drawing
and shall be drilled vertically with a tolerance of one fifty.
 The foundations shall be drilled with a casing being installed such that bottom of
the casing is maintained below the bottom of the excavation at all times.
 Before starting of the MCC pole foundation, control cabinet foundation excavation
permit to dig notification shall be submitted and make sure that no existing services
interfere with the depth of the excavation.
 Drilling shall be carried out with Auger machine and before excavation setting out
the Street light foundation and control cabinet foundation shall be done by surveyor
and it will mark clearly on the ground.
 Excavation shall be carried out with true line and all the safety precautions shall be
carried out. After excavation completed the Street foundation and control cabinet
shall be lowered with crane with Approved sling & set out shall be done.

6.21.5 Back filling of Surround

 Back filling of the street light foundation will be done in layers as per project
specifications and approved shop drawing.
 Back filling up duct and trench area shall be filled as per approved shop drawing
and ADM specifications.

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 20 of 27

 For more details about backfilling materials layer by layer please refer attached
drawing.
6.3 Duct Construction

MCC ducts are provided to use underground conduit cross length of the road. The duct
construction procedures are given below.
 Surveys and setting out for ducts
 Excavation
 Laying of Upvc and GRV duct pipes and Concrete surround
 Duct installation and backfilling
SRPC K140 Concrete grade is using for the duct works and Uncoated steel i.e. BS 4449-05 Gr B-
500B Uncoated is using for duct.
More details please refer attached drawing ref. no. --------------------------------
6.21.6 Road Crossings

 Approved type of PVC pipe for electrical use will be ordered and supplied to site.
 The top surface of pipes shall be at a minimum depth of 1m from the pavement
level when laid under roads, pavements.
 The pipes shall be laid preferably askew to reduce the angle of bend as the cable
enters and leaves the crossing.
 The temporary re-instatements of roadways should be inspected at regular
intervals, particularly after a rain, and any settlement should be made good by
further filling as may be required.
 After the subsidence has ceases, the top of the filled-up trenches in roadways or
other paved areas shall be restored to the same density and material as the
surrounding area in accordance with the relevant Specifications to the satisfaction
of the Engineer-in-Charge.

6.4 Street Light fittings & Pole Installation

6.21.7 Preparation and Site Requirement

Before commencing the Street Pole Installation Work in the area, the following will be checked.
 Permission to start has been given (i.e. all first fix containment signed-off).
 All materials are available for the specific area of work.

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 21 of 27

 Any standing scaffolding is safe and suitable for purpose.


 All hand tools are in safe working order and extension leads are not damaged.
 There is adequate temporary lighting.
 Temporary power source is available in the locality and protection settings are
correct.
 Water proofing shall be provided.
 Grid lines and benchmarks have been clearly marked.
 Ensure that all client requirements with respect to HSE are and will be met.
 Ensure that all safety equipment provided is available and in good working order.
 Ensure that all persons carrying out the work is fully aware of the requirements for
safe working as specified in this safe system of work.
 All team members are equipped with PPE.

6.21.8 Transporting and Unloading the MCC Poles

The MCC poles will be checked for any damage prior to transportation from the stores compound
to where it is to be installed. When unpacking the Street Light pole from the crates, care will be
taken to avoid scratching or denting finished surfaces.
On satisfactory completion of the above, the Street light pole be loaded onto or flatbed truck using
the slings, D shackle (2 Nos.) and lifting eyes provided by the Manufacturer and positioned on
wooden battens then securely tied down to avoid any movement of the load during transportation to
the site & the insertion of pipe rollers under the base of the rollers removed accordingly. On arrival
at the location Street Light poles will be off-loaded from the truck by mobile crane using slings and
D shackle (2Nos.) & located through the access aperture into the site on wooden battens.
The loading and unloading of MCC pole shall be done using slings and D shackle with care. Each
section of the MCC pole will be lifted approximately 75mm to facilitate the removal of the wooden
battens. Good care will be taken in all these operations, to avoid scratching or denting of finished
surfaces of the Street light poles.

6.21.9 Installation of MCC poles:

 The MCC poles will be installed on foundations only after the Foundations are
aligned properly.

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 22 of 27

 Assemble poles on ground including fixing of a bracket on top of the pole for
mounting the Lighting fixture.
 The pole will be lifted with a Crane/Hi-up crane by using slings and D shackle
(2Nos.) and bolted on the foundation where the base plate of the pole has to fix on
top of foundation.
 The poles will be erected under the supervision of an experienced
supervisor/Forman that has well versed experience in mounting poles.
 A safe scaffolding access platform will be erected if necessary, for working at high
levels.
 The elevation/Mounting height of the component parts will be checked against
relevant drawings and confirmed correct.
 Measures to be implemented when closing the road to vehicles while installing the
poles.

6.21.10 Procedure for testing verticality of Poles:

 After installation of poles before grouting check the verticality of poles.


 If poles are not vertical, then adjust by levelling the nuts in bottom of poles.

6.21.11 Procedure for Grouting of Poles:

 After verticality of poles is approved by the consultant then advice Main


Contractor Engineer representative for grouting.
 Apply Denso Tape on each bolt of Street Lighting Poles.

6.21.12 Earthing for MCC Poles & Control Cabinet

 Grounding rods made of copper shall be installed in easily accessible concrete pits
(for tiled areas) and in pulling pits or in PVC pipe with a cap in other areas.

6.21.13 Numbering of MCC Poles

 All 10M and 14M light poles shall be numbered as required by the ADM-DOT.
Paint of numbering and the surface preparation for numbering shall meet the

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 23 of 27

applicable requirements of section on metal works of these standards specifications


unless otherwise directed by the Engineer.

6.21.14 Back filling and Reinstatement

 Prior to backfilling, it is necessary to carry out a visual inspection in the presence


of engineer and items that need to be checked are.
 The cables have suitable bedding such as sieve sand. Stone chips and other sharp
objects in the cable route should be removed.
 Thickness of first and second layer of soft sand to be checked and excavation to be
checked randomly.
 Pulling equipment is carefully removed.
 The cable is free from oblivious damage caused during the installation. A very high
proportion of cable failures in service are due to such damage.
 It is very important that any damage to the over sheath should be taken to notice of
the engineer prior to repair before backfilling is commenced.
 The cable conduit should firstly be surrounded and covered with appropriate
bedding material to give a compacted cover the conduit.
 Trench will be backfilled up to a level as per the approved trench sectional
drawings.
 Trench will be backfilled to the ground level and leveled properly. Subsequent
material may be placed and compacted with mechanical equipment.

6.5 Construction Programme

Laying of MCC network shall be as per Approved construction Programme.


7. Construction Program
The Method Statement is divided into following parts:
 Survey and setting out.
 Pre-start checklist.
 Material inspection.
 Preliminaries
 Trench excavation for street light Cable.
 Transportation of street light Cable Drum.

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 24 of 27

 Road crossing & street light Cable Laying.


 Delivery and Storage.
 Delivery to site
 Preparation for Pulling
 Installation/ Laying of street light Cable
 Back filling and Reinstatement.
 Termination of street light Cable.
 Documentation
 Inspection and Testing.
Installation of street light Cable shall be as per Approved Detailed construction program
submitted earlier.

8. Quality Control ITP & Inspection Check List

 All activities & arrangement will be in strict compliance to the precautionary


measures / practices & procedures established by the project management to
address the COVID-19. Refer to attached HIRA for the controls.
 All equipment’s to be used during the construction phase shall be that compatible
with the program of works as specified & acceptable to the Engineer.
 All Survey equipment’s & Laboratory Testing Equipment’s to be used are in good
condition & calibrated.
 All work inspection requests related to this method statement (preparation, Material
Sampling & Testing,) shall be submitted to the Engineer, attached with the relevant
standard check sheet use at site during actual verification.
 Note: Inspection check sheet as per project requirement will be the approval
summary as defined by consultant and will be agreed with the inspectors.
 All materials received on site & to be used for permanent construction shall be
verified for conformance & tested in site laboratory or by third party as required in
project specification prior to use.
 Material Inspection Request & Work Inspection Request related to Street Light
Cable Works Installation activities will be submitted to the Engineer for
verification & approval.
 Refer to attached Inspection & Test Plan.

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00


Rev.00

Method Statement for Installation of MCC ducts and Civil works of MCC network Page 25 of 27

9. Quality Risk Assessment


# Quality risk Consequence Mitigation Measure
1 Use of unapproved  Work may lead to wrong  Proper distribution of
drawings details. approved drawings
 Delaying of work  Proper disposition of
progress due to obsolete and
rectification unapproved drawings.
 Higher cost
 May lead to NCR
issuance

2 Use of not approved  Work may lead to wrong  No materials shall be


materials details. ordered without proper
 Delaying of work documented approval.
progress due to  Ensure all materials
rectification delivered on site shall
 Higher cost be approved prior to
 May lead to NCR use.
issuance

9. Risk Assessment / Hazzard Assessment


Risk assessments attached.
10. Third Party Certificate Requirements, if any.
None
11. Attachment (Shop drawings/Forms/sketches/certificates etc. as required.)
11.1 Standard Drawings
11.2 Inspection & Test Plan
11.3 Hazard / Impact Assessment
11.4 Quality Inspection Check list

All Paper copies of this document are UNCONTROLLED.


Please refer to Riyadh City Programme Library for the current version.

Template Ref. No.: RS-02-00001-05-11-SS-SBD-MT-000001 | Rev. 00