Method Statement For Laying of MCC Duct and Civil Works For MCC Network
Method Statement For Laying of MCC Duct and Civil Works For MCC Network
Prepared for:
Modon Properties
P.O. Box 26866,
Abu Dhabi, United Arab Emirates
www.modon.ae
REVISION HISTORY
APPROVALS
Printed initials in the boxes confirms that the document has been reviewed and approved. Approved
records are saved on Riyadh City Program Library.
Author
Checked By Dhia Yousif
Reviewed By John Nielsen
Approved By Vimal Kumar
NAME SIGNATURE DATE
Table of Contents
DESCRIPTION PAGE NO.
Content
Rev.00
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 4 of 27
2. References................................................................................................................................7
3. Definitions................................................................................................................................9
4. Resources...............................................................................................................................10
5. HSE Requirements.................................................................................................................15
5.3 Training.....................................................................................................................16
5.4 Induction:..................................................................................................................17
6.1 Preliminaries..............................................................................................................18
6.2 Street Light and Control Cabinet Foundation Casting and Installation......................19
A. Form work.................................................................................................................20
C. Concreting of Foundation..........................................................................................20
D. Concrete Placement...................................................................................................20
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 5 of 27
6.2.4 Drilling, Excavation & Erection of Street light & Control Cabinet foundation........21
6.5.2 Excavation.................................................................................................................27
6.5.4 Routing......................................................................................................................28
6.12 Documentation:.........................................................................................................33
7. Construction Program.............................................................................................................34
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 6 of 27
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 7 of 27
The method statement shall be briefed to all appropriate operatives to ensure that they are aware of
the plan, sequence of activities & project specific requirements of Client/Consultant.
A constant monitoring and supervision duty shall be undertaken by SBD to ensure work activities
are carried out in accordance with the method statement. Any irregularities shall be immediately
took action.
2. References
2.1 Codes of Practice / Legislative Code
Document Reference No. Title
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 8 of 27
MCC Network
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 9 of 27
3. Definitions
4. Resources
4.1 Approved Material Submittal
Submittal will be prepared for the following materials to seek the Engineers approval prior to use in
permanent construction:
8.5m single & Double arm pole (4.0m)
75 mm UPVC pipe for duct.
Anchor Bolts for 8.5m single arm pole (4.0m)
Dune Sand
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 10 of 27
Not Applicable
There are numerous numbers of shop drawings related with MCC Network shall be submitted. Only
Approved shop Drawings shall be used in construction methodology.
All Field works shall be carried out as per approved Shop Drawings & Standard Project Drawings.
Contractor is responsible for all site drawings to be maintained the as-built AutoCAD drawings /
GIS drawing as per ADM requirements.
Note: Shop Drawings are subject to revision and resubmission for approval whenever a new change
or update arises.
4x4 Pick up 1
Flat Trailer. 1
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 11 of 27
Air Compressor 1
Small Generator 1
Auger machine 1
Surveying equipment’s. 1
Construction Manager
Specific responsibilities include:
- Executing project work plans. Tracking project milestones and deliverables.
Identify potential crises and devise contingency plans.
- Managing day-to-day operational aspects. Minimize exposure and risk on
project. Managing scope with respect to variations, with or without time and
cost impact. Managing delay issues, time extensions and cost claims.
- Oversee Quality, HSE, Sustainability and Environment matters on site.
- Achieving planned targets by effectively utilizing man, material and
equipment. Ensuring accurate measures of work required are being taken to
control construction cost.
- Liaising with project stakeholders and customers.
- Ensuring availability of workforce with required skills as per project plan.
Providing leadership to the project teams.
- Demonstrated commitment to improve skills and knowledge of subordinates
and self. Share and implement work-related knowledge and skills
Site Engineer(s)
Specific responsibilities include:
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 12 of 27
- Ensuring that the work execution will be performed in a safe manner and meets
the requirements of the project documentation.
- Ensuring that all shop drawings and material used in permanent works is are
issued for construction or as approved by the Engineer.
- Shall ensure that operatives comply with the relevant method statements,
Toolbox Talks and general site briefings.
- Ensuring that sub-contractors achieve the on-site required standards.
- Carrying out phased inspections as required & ensuring that completed works
are offered for inspection for approval to concerned parties within specific
dates/ programmers.
- Monitoring the close-out activities of the project and maintain a smooth hand-
over.
- Shall refer to the QA/QC Department and the HSE Department for advice and
guidance when required.
QA/QC Engineer(s)
Specific responsibilities include:
- Shall ensure that operatives comply with the relevant method statements will
be followed by initiating Toolbox Talks and general site briefings.
- Ensuring that staff is aware of their responsibilities in respect of quality
requirements.
- Ensure that all technical submittals used in construction are the current
versions & approved by the Engineer or other relevant Authority.
- Ensuring that materials are inspected when delivered to ensure they comply
with the various specifications prior to use.
HSE Officer (s)
Specific responsibilities include:
- Assisting in the production of any health, safety and environmental documents.
- Monitoring the implementation of health, safety and environmental
requirements.
- Undertaking audits and ensuring that corrective and preventive actions are
taken where required.
- Liaise with the senior site staff on health, safety and environmental related
matters.
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 13 of 27
Surveyors
Specific responsibilities include:
- Administering & guiding all assistant surveyors/ instrument men/ chainmen
within the project to complete the assigned job.
- Determining precise location, measurements/ stakeout of points, elevation,
lines, areas and contours for construction, mapmaking, land divisions etc. as
per approved shop drawings.
- Coordinating with Chief Surveyor / Engineers/ Foremen/ Chief Draftsmen for
Survey Works.
- Monitoring the calibration validity of all survey instruments in the project, their
accounting and maintenance.
- Preparing Survey Reports on daily basis to all construction activities &
maintaining all the survey records.
Foremen
Specific responsibilities include:
- To ensure that all operatives and appropriate briefed as to the content of the
method statement and the works.
- To ensure the works are undertaken in a safe manner & quality control is
implemented.
- To ensure all operatives are adequately trained in their respective works.
- Reporting any un-safe practices on site to the SBD site team.
Charge hand
Site Foreman
L D and H D Drivers
Equipment Operators
Electricians
Helpers
5. HSE Requirements
5.1 Personal Protective Equipment
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 14 of 27
Safety Jackets
Dust masks
First aiders and first aid kit also assigned at different locations
Emergency Contact Numbers as follows:
5.3 Training
This Method Statement shall be briefed to the appropriate personnel. This is essential to the safe
and successful completion of the operation. Records shall be kept of all briefings.
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 15 of 27
Prior to these works commencing, a review of the activities shall be undertaken in association with
the operatives undertaking the duties. This will identify where additional training and above
existing knowledge, or experience is required.
SBD shall evaluate and perform the followings:
Determine the necessary competence for personnel performing work affecting its
quality.
Provide training or take other actions as to satisfy those needs.
Evaluate the effectiveness of action taken.
Ensure that its personnel are aware of the relevance and importance of their
activities and how they contribute to the achievement of the product.
Toolbox talk will be given to operations.
Emergency Contact numbers to be posted in strategic areas within the project
Emergency vehicle with dedicated driver is on site
Fire extinguishers present on various locations
Emergency Procedure Shall be briefed to all Personnel in each Toolbox Talk
Assembly point in the event of fire / other emergency shall be brief to all
Personnel.
Contact numbers for the emergency services shall be provided by the Site Safety
Officer and held by the Site Engineer & foreman.
All Workers involved in activity shall strictly follow the emergency procedure.
5.4 Induction:
All Workers and Staff attend the HSE induction before commencing the work at
site
All Persons shall adhere to PPE
All Workers shall attend toolbox talk weekly (i.e. first day of the week)
Any unsafe acts or condition are to be identified and corrected immediately and
referred to respective supervisor.
Any accident or incident shall be reported immediately to take prevention measures
All relevant JSA adhered to
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 16 of 27
Before starting the all works related street lighting network to be mentioned the getting of all
NOC’s from the related authorities.
6.1 Preliminaries
Before commencing the all works related MCC network installation in any area, the followings
need to be ensured:
Site Survey shall be carried out according approved drawings.
The MCC work to be done as per the approved shop drawings. Engineers strictly
are following the approved shop drawing.
All installation works shall be carried out as per the approved schematic drawings.
All material to be used shall be approved make.
Concrete Mix Design shall be C40 and rebar type shall be BS 4449 -05 Gr B-500B
– Uncoated as per project and ADM Specifications.
Check the Machinery working condition.
All Reinforcement shall be placed according to bar bending schedule and anchor
bolts shall be approved drawings.
The route to be excavated will be checked for existing services (if any) and marked
for excavation as per shop drawing.
Dewatering to be done on the cable laying route if required.
All backfilling & Compaction works shall be as per the approved Project
specifications and compaction will be done until a satisfactory degree has been
achieved and no more settlement is going to take place. This point cab identified by
observation and level checking.
Appropriate personnel protection equipment’s shall be worn by personnel at work.
Display safety warning signs around proposed excavation area as well as warning
tape.
Excavation close to roads with traffic shall have warning traffic cones well as
“Slow down “Signs displayed on road.
6.2 MCC Pole, Pull Box and Control Cabinet Foundation Casting and Installation
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 17 of 27
A Proper concrete plat form shall be prepared. Reinforcement cage & fabricated according to bar
bending schedule and approved shop drawing will be placed with prefabricated shutters (According
to approved drawing).
Construction of foundation for MCC poles shall be done the following requirements:
A. Form work
Steel form work required as per dimensions of MCC foundation and it shall be
fixed properly.
Rebar type for street light foundation shall be BS 4449 -05 Gr B-500B – Uncoated
as per ADM specifications.
Reinforcement cage as per the drawing shall be fabricated and it shall be lowered
into the shutter assembly and aligned properly. The proper sizing of bars, correct
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 18 of 27
number of bars and spacing of the bars will be checked before lowering the cage
and proper cover shall be checked.
B. Fixing of the Anchor Bolts.
Anchor bolts assembly will be fixed tightly and securely, it shall be checked for
plumb for verticality, and dimensions shall be as per drawings.
Wooden template will securely to the anchor bolts and all the coordinates of shall
be checked before concrete.
C. Concreting of Foundation.
Concrete shall be done as per the specification and concrete shall be consolidated
using a vibrator adequate for the size of pour.
D. Concrete Placement
The concrete mix grade shall be C20/20 &C20/10 for Screed, C40/20 (SRPC+MS)
After mixing the concrete at plant it will be immediately transferred to the site or
final destination to the stipulated time
The concrete shall be placed gently in position
Before placement the fresh concrete shall be checked for quality and all relevant
quality control checks shall be completed.
Concrete shall be placed uniformly and along with structure in lifts of 30 to 40 cm
and thoroughly vibrated all along the structure care shall be taken against
segregation and honeycombs.
Curing period shall be according to specified time as Water Based curing
compound use.
Fresh concrete will be protected from weather, water and it will be covered with
polyethylene sheet or Hessian cloth.
Make sure that the fixed elbows were not moved when concrete is poured
After and when concrete is set external shutter will be de molded by carefully by
unlocking the outer shutter and anchors.
Before Lifting and transporting to the site at least 75 % strength (after 7days) shall
be obtained from testing Cube of compressive strength.
After that foundation to be lifted by using slings and D shackles to the flat bed
crane with care.
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 19 of 27
Protective coating and water proofing for the foundations shall be done after
necessary concrete repairs with approved materials.
All the PVC elbows openings shall be cleared before installation.
The Street light foundation will be transported to the site on low bed trailer with the help of crane
loading and approved slings and it will be directly placed the to the alignment and approved grade.
Proper care will be taken for safe handling of the foundation unloading.
6.21.4 Drilling, Excavation & Erection of MCC Pole & pull box
All excavation for foundations for MCC poles shall be made by drilling, boring or
sinking a casing unless otherwise indicated on the drawings.
All drilled foundation shall be installed in the presence of the Engineer.
All foundation shall be located to the lines and spacing indicated on the drawing
and shall be drilled vertically with a tolerance of one fifty.
The foundations shall be drilled with a casing being installed such that bottom of
the casing is maintained below the bottom of the excavation at all times.
Before starting of the MCC pole foundation, control cabinet foundation excavation
permit to dig notification shall be submitted and make sure that no existing services
interfere with the depth of the excavation.
Drilling shall be carried out with Auger machine and before excavation setting out
the Street light foundation and control cabinet foundation shall be done by surveyor
and it will mark clearly on the ground.
Excavation shall be carried out with true line and all the safety precautions shall be
carried out. After excavation completed the Street foundation and control cabinet
shall be lowered with crane with Approved sling & set out shall be done.
Back filling of the street light foundation will be done in layers as per project
specifications and approved shop drawing.
Back filling up duct and trench area shall be filled as per approved shop drawing
and ADM specifications.
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 20 of 27
For more details about backfilling materials layer by layer please refer attached
drawing.
6.3 Duct Construction
MCC ducts are provided to use underground conduit cross length of the road. The duct
construction procedures are given below.
Surveys and setting out for ducts
Excavation
Laying of Upvc and GRV duct pipes and Concrete surround
Duct installation and backfilling
SRPC K140 Concrete grade is using for the duct works and Uncoated steel i.e. BS 4449-05 Gr B-
500B Uncoated is using for duct.
More details please refer attached drawing ref. no. --------------------------------
6.21.6 Road Crossings
Approved type of PVC pipe for electrical use will be ordered and supplied to site.
The top surface of pipes shall be at a minimum depth of 1m from the pavement
level when laid under roads, pavements.
The pipes shall be laid preferably askew to reduce the angle of bend as the cable
enters and leaves the crossing.
The temporary re-instatements of roadways should be inspected at regular
intervals, particularly after a rain, and any settlement should be made good by
further filling as may be required.
After the subsidence has ceases, the top of the filled-up trenches in roadways or
other paved areas shall be restored to the same density and material as the
surrounding area in accordance with the relevant Specifications to the satisfaction
of the Engineer-in-Charge.
Before commencing the Street Pole Installation Work in the area, the following will be checked.
Permission to start has been given (i.e. all first fix containment signed-off).
All materials are available for the specific area of work.
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 21 of 27
The MCC poles will be checked for any damage prior to transportation from the stores compound
to where it is to be installed. When unpacking the Street Light pole from the crates, care will be
taken to avoid scratching or denting finished surfaces.
On satisfactory completion of the above, the Street light pole be loaded onto or flatbed truck using
the slings, D shackle (2 Nos.) and lifting eyes provided by the Manufacturer and positioned on
wooden battens then securely tied down to avoid any movement of the load during transportation to
the site & the insertion of pipe rollers under the base of the rollers removed accordingly. On arrival
at the location Street Light poles will be off-loaded from the truck by mobile crane using slings and
D shackle (2Nos.) & located through the access aperture into the site on wooden battens.
The loading and unloading of MCC pole shall be done using slings and D shackle with care. Each
section of the MCC pole will be lifted approximately 75mm to facilitate the removal of the wooden
battens. Good care will be taken in all these operations, to avoid scratching or denting of finished
surfaces of the Street light poles.
The MCC poles will be installed on foundations only after the Foundations are
aligned properly.
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 22 of 27
Assemble poles on ground including fixing of a bracket on top of the pole for
mounting the Lighting fixture.
The pole will be lifted with a Crane/Hi-up crane by using slings and D shackle
(2Nos.) and bolted on the foundation where the base plate of the pole has to fix on
top of foundation.
The poles will be erected under the supervision of an experienced
supervisor/Forman that has well versed experience in mounting poles.
A safe scaffolding access platform will be erected if necessary, for working at high
levels.
The elevation/Mounting height of the component parts will be checked against
relevant drawings and confirmed correct.
Measures to be implemented when closing the road to vehicles while installing the
poles.
Grounding rods made of copper shall be installed in easily accessible concrete pits
(for tiled areas) and in pulling pits or in PVC pipe with a cap in other areas.
All 10M and 14M light poles shall be numbered as required by the ADM-DOT.
Paint of numbering and the surface preparation for numbering shall meet the
Method Statement for Installation of MCC ducts and Civil works of MCC network Page 23 of 27