Management Science
Management Science
Midsayap, Cotabato
MANAGEMENT
SCIENCE
CHAPTER 5 Forecasting
5(a) Moving Average
5(b) Exponential Smoothing
5(c) Trend Projection
5(d) Measuring Forecast Accuracy
5(e) Regression Analysis
LEARNING OBJECTIVES
CHAPTER OUTLINE
1.1 Introduction
See the computation below for the point that intersects the
two constraint lines.
CORNER POINT SOLUTION METHOD
Objective function:
Minimize cost = 2X + 3Y
Subject to constraints:
5X + 10Y > 90 (assumed) (ingredient A constraint)
4X + 3Y > 48 (assumed) (ingredient B constraint)
0.5X > 1.5(assumed) (ingredient C constraint)
X,Y > 0 (non-negativity constraints)
Note: Before solving the problem, take note of the three features
that affect the solution. First, the third constraints implies
that farmer must purchase enough brand 1 feed to meet the minimum
standards for the C nutritional ingredient. Buying only brand 2
would not be feasible because it lacks C. Second, we will be
solving for the blest blend of brands 1 and 2 to buy per turkey
per month. If the ranch houses 5,000 turkeys in a given month, it
need simply multiply the X and Y quantities by 5,000 to decide how
much feed to order overall. Third, we are dealing with a series of
greater than or equal to constraints. These cause the feasible
solution area to be above the constraints.
No Feasible Region
When there is no solution to LP problem that satisfies all of
the constraints, then no feasible solution exists. Graphically, it
means that no feasible solution region exists, a situation that
might occur if the problem was formulated with conflicting
constraints. For example, if one constraints is supplied by the
marketing manager who states that at least 300 tables must be
produced (X > 300) to meet sales demand, and a second restriction
is supplied by the production manager, who insists that no more
than 220 tables be produced namely (X < 220) because of a lumber
shortage, no feasible solution region results.
Unboundedness
Unboundedness is a condition that exists when a solution
variable and the profit can be made infinite large without
violating any of the problem’s constraints in a maximization
process. It would indeed be wonderful for the company to be able
to produce an infinite number of units of product but obviously no
firm has infinite resource available or infinite product demand.
Redundancy
Redundancy is the presence of one or more constraints that
do not affect the feasible solution region.
LEARNING OBJECTIVES
CHAPTER OUTLINE
2.1 Introduction
LEARNING OBJECTIVES
CHAPTER OUTLINE
3.1 Introduction
3.8 Degeneracy
3.1
4 INTRODUCTION
Mill Demand
A. Chicago 200
B. St. Louis 100
C. Cincinnati 300
Total 600 tons
Mill
Grain Elevator Chicago St. Louis Cincinnati
Kansas City $6 $ 8 $10
Omaha 7 11 11
Des Moines 4 5 12
Notice that after all four unused routes are evaluated, there
is tie for the entering variables cells 1A and 2A. The tie can be
broken arbitrarily. We will select cell 1A to enter the solution
(because of low cost).
Now we must check to see whether the solution shown in Table
B.19 is the optimal solution. We so this by plotting the paths for
the unused routes or empty cells (1B, 2A, 2B and 3C). If one of
the solutions is $0 reduced cost, it means the solution in Table
B-19, is the optimal cost solution.
Therefore, the solution and the total minimum cost are shown
in the table below:
Route Tons Shipped Cost Per unit Total Cost
From To
1 A 25 6 $ 150
1 C 125 10 1,250
2 C 175 11 1,925
3 A 175 4 700
3 B 100 5 500
Total 600 $4,525
LEARNING OBJECTIVES
CHAPTER OUTLINE
4.1 Introduction
Both the techniques use similar terminology and have the same
purpose. PERT stands for Project Evaluation and Review Technique
developed during 1950’s. The technique was developed and used in
conjunction with the planning and designing of the Polaris missile
project. CPM stands for Critical Path Method which was developed
by DuPont Company and applied first to the construction projects
in the chemical industry. Though both PERT and CPM techniques have
similarity in terms of concepts, the basic difference is, PERT is
used for analysis of project scheduling problems. CPM has single
time estimate and PERT has three time estimates for activities and
uses probability theory to find the chance of reaching the
scheduled time.
Activity
An activity represents an action and consumption of resources
(time, money, energy) required to complete a portion of a
project. Activity is represented by an arrow, (Figure 4.1).
A
i j A is called an Activity.
Event
An event (or node) will always occur at the beginning and end
of an activity. The event has no resources and is represented
by a circle. The ith event and jth event are the tail event
and head event respectively, (Figure 4.2).
A
i j
Dummy Activity
An imaginary activity which does not consume any resource and
time is called a dummy activity. Dummy activities are simply
used to represent a connection between events in order to
maintain a logic in the network. It is represented by a dotted
line in a network, see Figure 4.5.
5. A network should have only one start event and one end event
Some conventions of network diagram are shown in Figure 4.10
(a), (b), (c), (d) below:
Step 1:
Number the start or initial event as 1.
Step 2:
From event 1, strike off all outgoing activities.
This would have made one or more events as initial
events (event which do not have incoming
activities). Number that event as 2.
Step 3:
Repeat step 2 for event 2, event 3 and till the end
event. The end event must have the highest number
4.6 CRITICAL PATH ANALYSIS
The critical path for any network is the longest path through
the entire network.
CHAPTER OUTLINE
5.1 Introduction
Quantitative methods
These types of forecasting methods are based on mathematical
(quantitative) models, and are objective in nature. They rely
heavily on mathematical computations.
5.3 TIME-SERIES MODELS
Time-series models attempt to predict the future by using the
historical data. These models make the assumption that what happens
in the future is a function of what has happened in the past.
LEARNING OBJECTIVES
CHAPTER OUTLINE
6.1 Introduction
R(x) – VC(x) – FC = P
Solution:
In unit
PROBLEM 2
CITE Black Hawks Corporation sell a product for $79.99 that
costs $11.99 per unit to produce. The firm total fixed costs is
$27,336. Determine how many units must CITE Black Hawks to sell
to break even?
Solution:
Given:
P = 79.99
V = 11.99
FC = 27,336
x = FC / (P –V)
= 27,336 / (79.99 – 11.99)
= 402 units
PROBLEM 3
NDMC Kudos Corporation is a small but growing manufacturer of
telecommunications equipment. The company has no sales force of
its own; rather, it relies completely on independent sales agents
to market its products. These agents are paid a commission of 15%
of selling price for all items sold.
“They claim that after paying for advertising, travel, and the
other costs of promotion, there’s nothing left over for profit,”
replied Noel.
“I say it’s just plain robbery,” retorted Ronniel. “And I also
say it’s time we dumped those guys and got our own sales force.
Can you get your people to work up some cost figures for us to
look at?”
“It’s even better than that,” explained Noel. “We can actually
save P75,000 a year because that’s what we’re having to pay the
auditing firm now to check out the agents’ reports. So our overall
administrative costs would be less.”
“Pull all of these number together and we’ll show them to the
executive committee tomorrow,” said Ronniel. “With the approval
of the committee, we can move on the matter immediately.”
Solutions:
1. Fixed Costs:
Overhead 2,340,000
Marketing 120,000
Administrative 1,800,000
Interest 540,000
Total 4,800,000
5. The question asked for is the indifference point. The peso sales
required to produce equal income can be easily calculated by
dividing the net increase in fixed costs by the increase in
contribution margin ratio:
Difference in CMR = 35% - 47.5 = 12.5%
Increase in fixed costs = 2,400,000 – 75,000 = P2,325,000
Indifference Point: 2,325,000 ÷ 0.125 = P18.6M
CHAPTER 7
DECISION THEORY
LEARNING OBJECTIVES
CHAPTER OUTLINE
7.1 Introduction
Example No. 4:
Find:
(i) EMV of optimal order.
(ii) Expected profit presuming certainty of demand.
7.8 USE OF SUBJECTIVE
PROBABILITIES IN DECISION
MAKING
When the objective probabilities of the occurrence of various
states of nature are not known, the same can be assigned on the
basis of the expectations or the degree of belief of the decision-
maker. Such probabilities are known as subjective or personal
probabilities. It may be pointed out that different individuals
may assign different probability values to given states of nature.
This indicates that a decision problem under uncertainty can
always be converted into a decision problem under risk by the use
of subjective probabilities. Such an approach is also termed as
Subjectivists' Approach.
Example No. 5:
The conditional payoff (in Rs) for each action-event combination
are as under:
7.9 USE OF POSTERIOR
PROBABILITIES IN DECISION
MAKING
The probability values of various states of nature, discussed
so far, were prior probabilities. Such probabilities are either
computed from the past data or assigned subjectively. It is
possible to revise these probabilities in the light of current
information available by using the Bayes' Theorem. The revised
probabilities are known as posterior probabilities.
Example No. 6: