Consolidated Quarterly Report

The documents report on government projects in Pio V. Corpus, Masbate province for 3 quarters. In the 1st quarter of 2020, a local access road project in Bunducan was 15% completed with 15.1 million pesos incurred out of a total budget of 97.7 million. In the 2nd quarter, the project was 65% completed with 63.5 million pesos incurred. In the 3rd quarter of 2019, 4 projects were reported: a water supply system and sea ambulance project were completed, a local road upgrading project was completed, and a road concreting project was 30% completed with 1 million pesos incurred out of a 5 million budget. Local officials certified the data in the reports

Uploaded by

kerwin jay
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
41 views3 pages

Consolidated Quarterly Report

The documents report on government projects in Pio V. Corpus, Masbate province for 3 quarters. In the 1st quarter of 2020, a local access road project in Bunducan was 15% completed with 15.1 million pesos incurred out of a total budget of 97.7 million. In the 2nd quarter, the project was 65% completed with 63.5 million pesos incurred. In the 3rd quarter of 2019, 4 projects were reported: a water supply system and sea ambulance project were completed, a local road upgrading project was completed, and a road concreting project was 30% completed with 1 million pesos incurred out of a 5 million budget. Local officials certified the data in the reports

Uploaded by

kerwin jay
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

FDP Form 6 - Fund Utilization

CONSOLIDATED QUARTERLY REPORT ON GOVERNMENT PROJECTS, PROGRAMS or ACTIVITIES


FOR THE 1ST QUARTER, CY 2020

Province of Masbate
MUNICIPALITY OF PIO V. CORPUS

Project Status
Target Completion No. of
Program or Project Location Total Cost Date Started Remarks
date % of Total Cost Incurred to Extension
Completion Date

Local Access Road in Bunducan 9,768,546.42 February 4, 2020 July 4, 2020 15% 1,465,281.96 On-going
Bunducan, Pio V. Corpus,
Masbate

We hereby cetify that we have reviewed the contents and hereby attest to the veracity and correctness of the data or
information contained in this document.

VERSALE L. OLIVERIO ALLAN T. LEPASANA


Local Accountant LCE
FDP Form 6 - Fund Utilization
CONSOLIDATED QUARTERLY REPORT ON GOVERNMENT PROJECTS, PROGRAMS or ACTIVITIES
FOR THE 2ND QUARTER, CY 2020

Province of Masbate
MUNICIPALITY OF PIO V. CORPUS

Project Status
Target Completion No. of
Program or Project Location Total Cost Date Started Remarks
date % of Total Cost Incurred to Extension
Completion Date

Local Access Road in Bunducan 9,768,546.42 February 4, 2020 July 4, 2020 65% 6,349,555.17 On-going
Bunducan, Pio V. Corpus,
Masbate

We hereby cetify that we have reviewed the contents and hereby attest to the veracity and correctness of the data or
information contained in this document.

VERSALE L. OLIVERIO ALLAN T. LEPASANA


Local Accountant LCE
FDP Form 6 - Fund Utilization
CONSOLIDATED QUARTERLY REPORT ON GOVERNMENT PROJECTS, PROGRAMS or ACTIVITIES
FOR THE 3RD QUARTER, CY 2019

Province of Masbate
MUNICIPALITY OF PIO V. CORPUS

Project Status
Target Completion No. of
Program or Project Location Total Cost Date Started Remarks
date % of Total Cost Incurred to Extension
Completion Date

1. Construction of Guindawahan-Cabangrayan Water Guindawahan -


12,000,000.00 February 28, 2019 July 04, 2019 100% 11,999,271.69 Completed
Supply System Level II Cabangarayan, Pio V.
Corpus, Masbate
Delivered and received by the
2. Procurement of Sea Ambulance 2,999,200.00 100% 2,999,200.00 LGU, August 2019, check issued
after date of Actual receipt

3. Local Access Road-Local Road Upgrading Labigan, Pio V. Corpus, 8,593,803.00 October 4, 2018 February 8, 2019 100%
Masbate 8,589,337.86 Completed
4. Concreting of road from junction Alegria (Provincial Alegria & Mabuhay, Pio V.
5,000,000.00 September 28, 2019 December 19, 2019 30%
road) to Barangay Mabuhay Corpus, Masbate 999,749.97 On-going

We hereby cetify that we have reviewed the contents and hereby attest to the veracity and correctness of the data or
information contained in this document.

VERSALE L. OLIVERIO ALLAN T. LEPASANA


Local Accountant LCE