Cost of Quality & Accounting For Production Losses (Theories and Problems)
Cost of Quality & Accounting For Production Losses (Theories and Problems)
Cost of Quality & Accounting For Production Losses (Theories and Problems)
Problems)
1. The quality costs that are associated with materials and products that fail to meet quality
standards and result in manufacturing losses are known as:
A. internal failure costs
B. external failure costs
C. prevention costs
D. appraisal costs
E. none of the above
2. The quality costs that are associated with designing, implementing, and maintaining the
quality system are known as:
A. appraisal costs
B. internal failure costs
C. external failure costs
D. prevention costs
E. none of the above
3. The quality costs that are incurred to ensure that materials and products meet quality
standards are known as:
A. external failure costs
B. prevention costs
C. appraisal costs
D. internal failure costs
E. none of the above
4.The quality costs that are incurred because inferior quality products are shipped to customers
are known as:
A. internal failure costs
B. external failure costs
C. prevention costs
D. appraisal costs
E. none of the above
82
The Cost of Quality and Accounting for Production Losses 83
7. A mathematical technique used to monitor production quality and reduce product variability
is:
A. the method of least squares
B. the statistical scattergraph method
C. statistical process control
D. linear programming
E. none of the above
10. All of the following accounts would be acceptable ones to credit at the time scrap is sold
except:
A. Scrap Sales
B. Cost of Goods Sold
C. Factory Overhead Control
D. Work in Process
E. all of the above would be acceptable
12. When spoilage occurs because of some action taken by the customer, the unrecoverable
cost of the spoilage should be charged to:
A. Work in Process
B. Spoiled Goods Inventory
C. Factory Overhead Control
D. Applied Factory Overhead
E. none of the above
13. When spoilage occurs because of some internal failure, the unrecoverable cost should be
charged to:
A. Work in Process
B. Spoiled Goods Inventory
C. Factory Overhead Control
D. Applied Factory Overhead
E. none of the above
14. When rework occurs because of some action taken by the customer, the cost of the rework
should be charged to:
A. Work in Process
B. Spoiled Goods Inventory
C. Factory Overhead Control
D. Applied Factory Overhead
E. none of the above
15. When rework occurs because of some internal failure, the cost of the rework should be
charged to:
A. Work in Process
B. Spoiled Goods Inventory
C. Factory Overhead Control
D. Applied Factory Overhead
E. none of the above
16. Newman Company's Job 1865 for the manufacture of 2,200 coats was completed during
August at the unit costs presented below. Due to an internal failure in the production process,
200 coats were found to be spoiled during final inspection that were sold to a jobber for $6,000.
What would be the unit cost of good coats produced on Job 1865?
A. $57.00
B. $55.00
C. $56.00
D. $58.00
E. none of the above
17. During March, Vaughan Company incurred the following costs on Job 009 for the
manufacture of 200 motors:
The rework costs were attributable to the exacting specifications of the customer. What is the
cost per finished unit of Job 009?
A. $15.80
B. $14.60
C. $14.00
D. $13.30
E. none of the above
18. Spoilage occurs as a result of an internal failure in a process cost system. Using average
costing, the number of equivalent units that production costs should be charged to would be
based upon:
A. spoiled units
B. units transferred out and spoiled units
C. units transferred out, spoiled units, and units in ending inventory
D. units transferred out and units in ending inventory
E. none of the above
19. Spoilage occurs as a result of normal production shrinkage in a process cost system.
Using average costing, the number of equivalent units that production costs should be charged
to would be based upon:
A. spoiled units
B. units transferred out and spoiled units
C. units transferred out, spoiled units, and units in ending inventory
D. units transferred out and units in ending inventory
E. none of the above
20. In a process cost system, the cost of spoilage due to an internal production failure should be
recorded as:
A. dr. Work in Process; cr. Finished Goods
B. dr. Work in Process; cr. Factory Overhead Control
C. dr. Factory Overhead Control; cr. Work in Process
D. dr. Materials; cr. Factory Overhead
E. dr. Finished Goods; cr. Work in Process
86 Chapter 7
21. Gyro Products transferred 10,000 units to one department. An additional 3,000 units of
materials were added in the department. At the end of the month, 7,000 units were transferred
to finished goods; while 4,000 units remained in work in process inventory. There was no
beginning inventory, and lost units were a result of normal production shrinkage. The
production costs for the period in this department would be effectively allocated over:
A. 12,000 units
B. 11,000 units
C. 10,000 units
D. 7,000 units
E. 13,000 units
22. In manufacturing its products for the month of March, Leo Co. incurred normal production
shrinkage of $10,000 and spoilage due to internal failure of $12,000. How much spoilage cost
should Leo charge to Factory Overhead Control for the month of March?
A. $22,000
B. $12,000
C. $10,000
D. $0
E. none of the above
23. Willis, Inc. instituted a new process in October. During October, 10,000 units were started
in Department A. Of the units started, 1,000 were lost in the process due to normal production
shrinkage, 7,000 were transferred to Department B, and 2,000 remained in work in process at
October 31. The work in process at October 31 was 100% complete as to materials costs and
50% complete as to conversion costs. Materials costs of $27,000 and conversion costs of
$40,000 were charged to Department A in October. What were the total costs transferred to
Department B?
A. $46,900
B. $53,600
C. $56,000
D. $57,120
E. none of the above
SUPPORTING CALCULATION:
24. A company that manufactures baseballs begins operations on January 1. Each baseball
requires three elements: a hard plastic core, several yards of twine that are wrapped around the
plastic core, and a piece of leather to cover the baseball. The plastic core is started down a
conveyor belt and is automatically wrapped with the twine to the approximate size of the
baseball, at which time the leather cover is sewn to the wrapped twine. Finished baseballs are
inspected, and the ones that are defective due to internal production failure are pulled out.
Defective baseballs cannot be economically salvaged and are destroyed. Cost and production
reports for the first week of operations are:
During the week, 2,100 baseballs were completed; 2,000 passed inspection. There was no
ending work in process. The cost of the spoilage charged to Factory Overhead is:
A. $33
B. $22
C. $1,100
D. $55
E. none of the above
SUPPORTING CALCULATION:
25. In a process cost system, the cost of rework usually is debited to:
A. Factory Overhead Control
B. Applied Factory Overhead
C. Spoiled Goods Inventory
D. Work in Process
E. none of the above
26. If spoilage occurs as a result of an internal failure in a process cost system, using fifo
costing, the number of equivalent units that production costs should be charged to would be
based upon:
A. spoiled units
B. units transferred out and spoiled units
C. units transferred out, beginning inventory, and units in ending inventory
D. units transferred out, spoiled units, units in ending inventory, and units in
beginning inventory
E. none of the above
88 Chapter 7
27. If spoilage occurs as a result of normal production shrinkage in a process cost system, using
fifo costing, the number of equivalent units that production costs should be charged to would be
based on:
A. spoiled units
B. units transferred out and spoiled units
C. units transferred out, beginning inventory, and units in ending inventory
D. units transferred out, spoiled units, units in ending inventory, and units in beginning
inventory
E. none of the above
28. Primo Products transferred 15,000 units to one department. An additional 5,000 units were
in beginning inventory in the department. At the end of the month, 12,000 units were
transferred to the next department, 6,000 units remained in work in process, 40% complete as
to conversion costs and the remaining units were lost at the 75% stage of conversion.
Beginning inventory was 60% complete as to conversion costs and lost units were the result of
internal failure. The equivalent units of conversion cost using fifo costing is:
A. 14,400
B. 12,900
C. 13,900
D. 13,400
E. none of the above
SUPPORTING CALCULATION:
29. Primo Products transferred 15,000 units to one department. An additional 5,000 units were
added in the department. At the end of the month, 12,000 units were transferred to the next
department, 6,000 units remained in work in process, 40% complete as to conversion costs and
the remaining units were lost at the 75% stage of conversion. Beginning inventory was 60%
complete as to conversion costs, and lost units were the result of normal production shrinkage.
The equivalent units of conversion cost using fifo is:
A. 11,400
B. 14,400
C. 12,900
D. 13,400
E. none of the above
SUPPORTING CALCULATION:
PROBLEMS
PROBLEM
1. Munoz Metal Products accumulates metal shavings from the shop floor and sells them
periodically to a nearby scrap dealer. Scrap sales, on account, for the period just ended total
$2,300.
SOLUTION
PROBLEM
2. Walker Inc. manufactures custom wood products. During the current period, an order for
2,000 workbenches was begun on Job 1994. After the job was completed, the benches were
inspected and 100 units were determined to be defective. The customer has agreed to accept
the order with only 1,900 units instead of the quantity originally ordered. The spoiled units can
be sold as seconds for $25 each. Spoiled goods are kept in a separate inventory account from
finished goods. Total costs charged to
Job 1994 follow:
Required:
(1) Assuming that the defective units were the result of an internal failure (i.e., an employee
error or a machine failure), prepare the appropriate general journal entries to record the
transfer of the defective units to a separate inventory account and the completion and
shipment of Job 1994 to the customer.
(2) Assuming that the defective units were the result of a change in design specified by the
customer after the units were completed, prepare the appropriate general journal entries
to record the transfer of the defective units to the separate inventory account and the
completion and shipment of Job 1994 to the customer.
SOLUTION
(1) Spoiled Goods Inventory (10 units x $25 salvage) .................. 250
Factory Overhead Control ...................................................... 250
Work in Process (10 units x $50* cost) ............................. 500
(2) Spoiled Goods Inventory (10 units x $25 salvage) .................. 250
Work in Process ............................................................... 250
PROBLEM
3. Albany Appliances manufactured 100 microwave ovens in a recent production run and
discovered that 10 ovens were defective and required reworking as follows:
Required:
(1) Prepare the journal entries to record (a) the normal production costs, (b) the rework
costs, and (c) the transfer of the job costs to Finished Goods assuming that rework costs
were caused by an internal failure.
(2) Prepare the same journal entries as in (1), assuming that rework costs were caused by a
change in customer specifications.
SOLUTION
Debit Credit
(1) (a) Work in Process ............................................................ 20,000
Materials.................................................................. 5,000
Payroll ..................................................................... 7,500
Applied Factory Overhead ....................................... 7,500
PROBLEM
4. Potter Paint Company manufactures paint in three departments using a process cost system
with an average cost flow assumption. Selected cost and production data for the Blending
Department, the second department in the production process, for the month just ended, are as
follows:
The paint is inspected at the end of the process in the Blending Department to detect any
spoiled batches. Ending inventory is 75% complete as to materials and 25% complete as to
conversion costs.
Required:
(1) Compute the equivalent units of production for each cost element in the Blending
Department for the month just ended.
(2) Determine the average cost per equivalent unit for each cost element.
SOLUTION
(1)........................................................ From
Preceding
Department Materials Labor Overhead
Equivalent units transferred out .............. 20,000 20,000 20,000 20,000
Equivalent units in ending inventory ....... 7,000 5,250 1,750 1,750
Equivalent units of spoilage .................... 3,000 3,000 3,000 3,000
Total equivalent units.............................. 30,000 28,250 24,750 24,750
The Cost of Quality and Accounting for Production Losses 93
(2)........................................................ From
Preceding
Department Materials Labor Overhead
PROBLEM
5. Carter Company manufactures a single product in two departments, Cutting and Finishing.
Units of a product are started in the Cutting Department and then transferred to the Finishing
Department where they are completed. Units are inspected at the 80% stage of completion in
the Finishing Department. Good units are transferred to finished goods inventory when
completed and spoiled units are transferred to a separate inventory account. Spoiled units are
inventoried at their salvage value of $3 each, and the unrecoverable cost of spoilage, which was
caused by an internal failure, should be charged to the appropriate account.
Materials are added at the beginning of the production process. At the end of June, 2,000
units were still in process in the Finishing Department, 100% complete as to materials and 60%
complete as to conversion costs. During July, 20,000 units were transferred from the Cutting
Department to the Finishing Department and 15,000 were transferred from the Finishing
Department to finished goods inventory. At the end of July, the Finishing Department still had
4,000 units in process, 100% complete as to materials and 20% complete as to conversion
costs. Cost data related to July operations in the Finishing Department follow:
Beginning Added
Costs charged to the department:....................................................... Inventory This Period
Cost from preceding department .................................................. $6,050 $54,450
Materials ....................................................................................... 3,410 30,690
Labor ............................................................................................ 1,638 14,742
Factory overhead.......................................................................... 2,184 19,656
Required: Complete the following cost of production report for the Finishing Department
based on the data presented for July, assuming the company uses a process cost system with
average costing to account for its production.
94 Chapter 7
SOLUTION
Carter Corporation
Finishing Department
Cost of Production Report
For July, 19--
% Unit Total
Cost Accounted for as Follows Units Complete Cost Cost
Transferred to
finished goods ....................... 15,000 100% $ 6.40 $96,000
Transferred to spoiled goods
inventory at salvage value ..... 3,000 3.00 9,000
Charge to factory overhead
for spoilage:
Cost from preceding
department ...................... 3,000 100% $ 2.75 $ 8,250
Materials ............................... 3,000 100% 1.55 4,650
Labor. ................................... 3,000 80% .90 2,160
Factory overhead .................. 3,000 80% 1.20 2,880
$17,940
Less salvage value of
spoiled units..................... 3,000 3.00 9,000 8,940
Work in process,
ending inventory:
Cost from preceding
department ...................... 4,000 100% $ 2.75 11,000
Materials ............................... 4,000 100% 1.55 6,200
Labor. ................................... 4,000 20% .90 720
Factory overhead .................. 4,000 20% 1.20 960 18,880
Total cost accounted for ............. $132,820
* Total number of equivalent units required in the cost accounted for section determined as
follows:
Prior
Dept. Cost Materials Labor Overhead
Equivalent units transferred out ................. 15,000 15,000 15,000 15,000
Equivalent units in ending inventory .......... 4,000 4,000 800 800
Equivalent units of spoilage ....................... 3,000 3,000 2,400 2,400
Total equivalent units................................. 22,000 22,000 18,200 18,200
96 Chapter 7
PROBLEM
6. Carrera Chemical Inc. uses a process cost system with an average cost flow assumption to
account for the production of its only product. The product is manufactured in two
departments. Units of product are started in the Cooking Department and then transferred to
the Blending Department where they are completed. Because of the intense heat applied in
the Cooking Department, some of the production volume is lost to evaporation. Labor and
overhead are treated as one element of cost in the Cooking Department (i.e., conversion cost).
Data related to May operations in the Cooking Department follow:
Beginning Added
Costs charged to the department:....................................................... Inventory This Period
Materials ....................................................................................... $4,375 $11,795
Conversion cost ............................................................................ 2,975 6,181
Required: Prepare a cost of production report for the Cooking Department based on the data
presented for May.
The Cost of Quality and Accounting for Production Losses 97
SOLUTION
Conversion
Quantity Schedule ................................................... Materials Cost Quantity
Beginning inventory ................................................. 10,000
Started in process this period .................................. 45,000
55,000
% Unit Total
Cost Accounted for as Follows Units Complete Cost Cost
Transferred to Blending
Department ........................... 40,000 100% $.54 $21,600
Work in process,
ending inventory:
Materials ............................... 9,000 100% $.33 $2,970
Conversion cost .................... 9,000 40% .21 756 3,726
Total cost accounted for ............. $25,326
* Total number of equivalent units required in the cost accounted for section determined as
follows:
Conversion
Materials Cost
Equivalent units transferred out .......................................................... 40,000 40,000
Equivalent units in ending inventory ................................................... 9,000 3,600
Total equivalent units.......................................................................... 49,000 43,600
98 Chapter 7
PROBLEM
7. School Craft Petroleum Company uses a process cost system with a fifo cost flow
assumption to account for production, which is manufactured in two departments. Units of
product are started in the Cracking Department and then transferred to the Refining Department
where they are completed. Units are inspected at the end of the production process in the
Refining Department. Good units are transferred to finished goods inventory and spoiled units
are transferred to a separate inventory account. Spoiled units are inventoried at their salvage
value of $8 each, and the unrecoverable cost of spoilage resulting from an internal production
failure is charged to the appropriate account. Data related to September operations in the
Refining Department follow:
Units in beginning inventory (60% materials, 30% labor, 30% overhead) .................. 2,800
Units received from Cracking Department this period ................................................ 8,400
Units transferred to the finished goods inventory this period ...................................... 7,600
Units transferred to special inventory account this period .......................................... 1,100
Units in ending inventory (100% materials, 50% labor, 50% overhead) ..................... 2,500
Beginning Added
Costs charged to the department:....................................................... Inventory This Period
Cost from preceding department ................................................... $17,889 $68,040
Materials ....................................................................................... 2,733 11,900
Labor............................................................................................. 7,278 30,063
Factory overhead .......................................................................... 12,350 51,016
Required: Prepare a cost of production report for the Refining Department based on the data
presented for September.
The Cost of Quality and Accounting for Production Losses 99
SOLUTION
% Unit Total
Cost Accounted for as Follows Units Complete Cost Cost
Transferred to finished goods:
From beginning inventory ........ $ 40,250
Cost to complete this
period:
Materials ....................... 2,800 40% $ 1.25 $ 1,400
Labor ............................ 2,800 70% 3.30 6,468
Factory overhead ......... 2,800 70% 5.60 10,976 $ 59,094
Started and completed
this period .......................... 4,800 100% $ 18.25 87,600
Total cost transferred to
Finishing Department ......... $ 146,694
Transferred to spoiled goods
inventory at salvage value ....... 1,100 $ 8.00 8,800
Charged to factory overhead for
spoilage:
Cost of completed spoiled
units ................................... 1,100 100% $ 18.25 $ 20,075
Less salvage value of spoiled
units ................................... 1,100 8.00 8,800 11,275
Work in process,
ending inventory:
Cost from preceding
department ........................ 2,500 100% $ 8.10 $ 20,250
Materials ................................. 2,500 100% 1.25 3,125
Labor. ..................................... 2,500 50% 3.30 4,125
Factory overhead .................... 2,500 50% 5.60 7,000 34,500
Total cost accounted for ............... $ 201,269
* Number of equivalent units of cost added during the current period determined as follows:
Prior
Dept. Cost Materials Labor Overhead
To complete beginning inventory .......... 0 1,120 1,960 1,960
Started and completed this period ........ 4,800 4,800 4,800 4,800
Ending inventory................................... 2,500 2,500 1,250 1,250
Spoiled units ......................................... 1,100 1,100 1,100 1,100
Total equivalent units............................ 8,400 9,520 9,110 9,110