Chart of Accounts
Chart of Accounts
Chart of Accounts
As of Apr 30, 2011
2 First Payment (50% of Contract Amount) Aug. 12, 2011 127,693.13 19,153.97 146,847.10
PREPARED BY APPROVED BY
October 10, 2011
CASH STATEMENT
3 Soil test service fee initial 50% payment 12-Aug-11 146,847.10 699,087.92
4 Soil test service fee final 50% payment 7-Sep-11 146,847.10 552,240.83
PREPARED BY APPROVED BY
513,549.95
359,484.97
October 10, 2011 - October 16, 2011
Week No. 27
CASH STATEMENT
TOTAL - 70,878.86
PREPARED BY APPROVED BY
July 1, 2011 - October 23, 2011
Week No. 1 - 16
CASH STATEMENT
1 Total cash inflow July 1, 2011 - October 23, 2011 11,000,000.00 11,000,000.00
2 Total cash outflow July 1, 2011 - October 23, 2011 1,973,917.35 9,026,082.66
PREPARED BY APPROVED BY
Oct. 31, 2011 - Nov. 06, 2011
Week No. 18
CASH STATEMENT
1 Total cash inflow & outflow July 1, 2011 - Oct. 30, 2011 11,000,000.00 1,973,917.35 9,026,082.66
PREPARED BY APPROVED BY
Nov. 07, 2011 - Nov. 13, 2011
Week No. 19
CASH STATEMENT
1 Total cash inflow & outflow July 1, 2011 - Nov. 06, 2011 11,000,000.00 1,973,917.35 9,026,082.66
2 Total cash outflow Nov. 07, 2011 - Nov. 13, 2011 74,402.63 8,951,680.03
PREPARED BY APPROVED BY
Nov. 14, 2011 - Nov. 20, 2011
Week No. 19
CASH STATEMENT
1 Total cash inflow & outflow April 11, 2011 - Nov. 13, 2011 11,000,000.00 2,048,319.98 8,951,680.03
PREPARED BY APPROVED BY
Nov. 28, 2011 - Dec. 04, 2011
Week No. 21
CASH STATEMENT
1 Total cash inflow & outflow April 11, 2011 - Nov. 13, 2011 11,000,000.00 2,048,319.98 8,951,680.03
PREPARED BY APPROVED BY
Dec. 05, 2011 - Dec. 11, 2011
Week No. 22
CASH STATEMENT
1 Total cash inflow & outflow April 11, 2011 - Nov. 13, 2011 11,000,000.00 2,048,319.98 8,951,680.03
PREPARED BY APPROVED BY
Dec. 12, 2011 - Dec. 18, 2011
Week No. 23
CASH STATEMENT
1 Total cash inflow & outflow April 11, 2011 - Nov. 13, 2011 11,000,000.00 2,048,319.98 8,951,680.03
PREPARED BY APPROVED BY
Dec. 19, 2011 - Dec. 25, 2011
Week No. 24
CASH STATEMENT
1 Total cash inflow & outflow April 11, 2011 - Dec. 25, 2011 11,000,000.00 2,048,319.98 8,951,680.03
PREPARED BY APPROVED BY
Dec. 26, 2011 - Jan. 01, 2012
Week No. 25
CASH STATEMENT
1 Total cash inflow & outflow April 11, 2011 - Jan. 01, 2012 11,000,000.00 2,048,319.98 8,951,680.03
PREPARED BY APPROVED BY
Jan. 02, 2012 - Jan. 08, 2012
Week No. 26
CASH STATEMENT
1 Total cash inflow & outflow April 11, 2011 - Jan. 08, 2012 11,000,000.00 2,048,319.98 8,951,680.03
PREPARED BY APPROVED BY
Jan. 02, 2012 - Jan. 08, 2012
Week No. 27
CASH STATEMENT
1 Total cash inflow & outflow April 11, 2011 - Jan. 08, 2012 11,000,000.00 2,048,319.98 8,951,680.03
PREPARED BY APPROVED BY
CASH STATEMENT
15 Payment for bulk excavation and cart away works 27-Feb-12 1,016,600.00
Amount in Birr
Balance
1,000,000.00
845,935.02
699,087.92
552,240.83
10,552,240.83
9,577,270.83
9,555,160.83
9,282,218.18
9,096,961.52
9,026,082.66
8,951,680.03
18,951,680.03
3,984,805.47
3,585,822.04
2,569,222.04
12,569,222.04
5,992,748.96
1,127,582.40
1,127,582.40
Week No. 07
17-Aug-12
CASH STATEMENT
3 Soil test service fee initial 50% payment 12-Aug-11 146,847.10 699,087.92
4 Soil test service fee final 50% payment 7-Sep-11 146,847.10 552,240.83
15 Payment for bulk excavation and cart away works 27-Feb-12 1,016,600.00 2,569,222.04
18 Form work, cement and other materials purchase 15-Mar-12 4,865,166.56 1,127,582.40
22 Payment for Bulk Excavation & Selected Material 2-May-12 1,504,408.79 9,623,173.61
23 Advance payment for purchase various cons. Materials 23-May-12 5,958,932.00 3,664,241.61
3 Soil test service fee initial 50% payment 12-Aug-11 146,847.10 699,087.92
4 Soil test service fee final 50% payment 7-Sep-11 146,847.10 552,240.83
15 Payment for bulk excavation and cart away works 27-Feb-12 1,016,600.00 2,569,222.04
18 Form work, cement and other materials purchase 15-Mar-12 4,865,166.56 1,127,582.40
22 Payment for Bulk Excavation & Selected Material 2-May-12 1,504,408.79 9,623,173.61
23 Advance payment for purchase various cons. Materials 23-May-12 5,958,932.00 3,664,241.61
3 Soil test service fee initial 50% payment 12-Aug-11 146,847.10 699,087.92
4 Soil test service fee final 50% payment 7-Sep-11 146,847.10 552,240.83
15 Payment for bulk excavation and cart away works 27-Feb-12 1,016,600.00 2,569,222.04
18 Form work, cement and other materials purchase 15-Mar-12 4,865,166.56 1,127,582.40
22 Payment for Bulk Excavation & Selected Material 2-May-12 1,504,408.79 9,623,173.61
23 Advance payment for purchase various cons. Materials 23-May-12 5,958,932.00 3,664,241.61
3 Soil test service fee initial 50% payment 12-Aug-11 146,847.10 699,087.92
4 Soil test service fee final 50% payment 7-Sep-11 146,847.10 552,240.83
15 Payment for bulk excavation and cart away works 27-Feb-12 1,016,600.00 2,569,222.04
18 Form work, cement and other materials purchase 15-Mar-12 4,865,166.56 1,127,582.40
22 Payment for Bulk Excavation & Selected Material 2-May-12 1,504,408.79 9,623,173.61
23 Advance payment for purchase various cons. Materials 23-May-12 5,958,932.00 3,664,241.61
3 Soil test service fee initial 50% payment 12-Aug-11 146,847.10 699,087.92
4 Soil test service fee final 50% payment 7-Sep-11 146,847.10 552,240.83
15 Payment for bulk excavation and cart away works 27-Feb-12 1,016,600.00 2,569,222.04
18 Form work, cement and other materials purchase 15-Mar-12 4,865,166.56 1,127,582.40
22 Payment for Bulk Excavation & Selected Material 2-May-12 1,504,408.79 9,623,173.61
23 Advance payment for purchase various cons. Materials 23-May-12 5,958,932.00 3,664,241.61
30 Contract Administration & Supervision Fee June - Oct. 2012 11-Dec-12 124,775.00 1,816,036.81
53
NB. Week number is counted from the day the 1st payment is released for construction of site office.
Dec. 11, '12
CASH STATEMENT
TOTAL 92,921,905.08
Week No. 85*
02-Apr-13
Amount in Birr
Out Balance
1,000,000.00
146,847.10 699,087.92
154,064.99 845,935.02
146,847.10 552,240.83
10,552,240.83
974,970.00 9,577,270.83
22,110.00 9,555,160.83
272,942.65 9,282,218.18
185,256.66 9,096,961.52
70,878.86 9,026,082.66
74,402.63 8,951,680.03
18,951,680.03
14,966,874.56 3,984,805.47
398,983.43 3,585,822.04
1,016,600.00 2,569,222.04
12,569,222.04
6,576,473.08 5,992,748.96
4,865,166.56 1,127,582.40
7,704,055.48
6,576,473.08 1,127,582.40
11,127,582.40
1,504,408.79 9,623,173.61
5,958,932.00 3,664,241.61
99,820.00 3,564,421.61
3,080,300.00 484,121.61
10,484,121.61
9,770,072.00 714,049.61 3,246,759.74
10,714,049.61
8,773,237.80 1,940,811.81
124,775.00 1,816,036.81
6,476,036.81
4,660,000.00 1,816,036.81
1,800,000.00 16,036.80
4,371,896.81
4,355,860.00 16,036.80
5,256,036.81
5,240,000.00 16,036.80
3,655,536.81
3,639,500.00 16,036.80
2,986,608.81
2,820,842.00 165,766.81
149,730.00 16,036.80
3,000.00 13,036.80
4,492,536.81
4,479,500.00 13,036.80
92,908,868.28 13,036.80
Payment Released to HUDA for the Stadium Project
For the Period September 21, 2011 - September 15, 2014
Ser.
Particulars Date Out
No
3 Payment for bulk excavation and cart away works 27-Feb-12 1,016,600.00
9 Working Capital, Selected Materials Purchase & Form Work Moodification 24-Aug-12 3,080,300.00
25
26
27
TOTAL 154,657,156.56
15-Sep-14
Remarks
25-Aug-14
Payment Released for the Stadium Project
Site Office, Fence & Ware House Construction
For the Period August 12, 2011 - February 27, 2012
Ser. No Particulars Date Out
1 Construction of Site Office Initial 30% payment 12-Aug-11 154,064.99
2 Final payment for site office, store, toilet & fence construction 27-Feb-12 398,983.43
TOTAL 553,048.42
9 Contract Administration & Supervision Fee June - Oct. 2012 11-Dec-12 124,775.00
10 Contract Administration & Supervision Fee ( November 2013 - April 2013) 22-May-13 149,730.00
15 Contract Administration & Supervision Fee (May 2013 - August 2013) 23-Oct-13 99,820.00
TOTAL 1,813,889.99
TOTAL 3,246,759.74
25-Aug-14
Remrks
Remrks
Remrks
15-Sep-14
Payment Released for the Stadium Project
Site Office, Fence & Ware House Construction
For the Period August 12, 2011 - February 27, 2012
Ser. No Particulars Date Out
2 Final payment for site office, store, toilet & fence construction 27-Feb-12 398,983.43
TOTAL 553,048.42
9 Contract Administration & Supervision Fee June - Oct. 2012 11-Dec-12 124,775.00
10 Contract Administration & Supervision Fee ( November 2013 - April 2013) 22-May-13 149,730.00
15 Contract Administration & Supervision Fee (May 2013 - August 2013) 23-Oct-13 99,820.00
17 Contract Administration & Supervision Fee (Sept. 2013 - Nov. 2013) 19-Dec-13 74,865.00
20 Contract Administration & Supervision Fee (Dec. 2013 - Feb. 2014) 25-Apr-14 74,865.00
23 Contract Administration & Supervision Fee (March. 2014 - May 2014) 30-Jun-14 74,865.00
27
TOTAL 1,813,889.99
TOTAL 3,246,759.74
15-Sep-14
Remrks
Remrks
Remrks
Remrks
24-Oct-13
A. Sub-Structure
3 Masonry Works -
B. Super-Structure
9 Running Truck, Football Field and Other Stadium Facilities 15,099,121.08 17,363,989.24
2 Final payment for site office, store, toilet & fence construction 27-Feb-12 398,983.43
TOTAL 553,048.42
9 Contract Administration & Supervision Fee June - Oct. 2012 11-Dec-12 124,775.00
14
15
16
17
18
TOTAL 1,323,609.99
TOTAL 3,246,759.74
20-Oct-14
Summary of Payment Released for the Stadium Project
For the Period September 21, 2011 - October 20, 2014
2 Payment for executed works to HUDA less 5% retention (Payment certificate # 1) 44,065,277.17
3 Payment made for site office, fence & ware house construction 553,048.42
TOTAL 160,270,854.71
25-Aug-14
Summary of Payment Released for the Stadium Project
For the Period September 21, 2011 - August 25, 2014
2 Payment made for site office, fence & ware house construction 553,048.42
TOTAL 160,270,854.71
25-Aug-14
CASH STATEMENT
3 Soil test service fee initial 50% payment 12-Aug-11 146,847.10 699,087.92
4 Soil test service fee final 50% payment 7-Sep-11 146,847.10 552,240.83
15 Payment for bulk excavation and cart away works 27-Feb-12 1,016,600.00 2,569,222.04
18 Form work, cement and other materials purchase 15-Mar-12 4,865,166.56 1,127,582.40
22 Payment for Bulk Excavation & Selected Material 2-May-12 1,504,408.79 9,623,173.61
23 Advance payment for purchase various cons. Materials 23-May-12 5,958,932.00 3,664,241.61
30 Contract Administration & Supervision Fee June - Oct. 2012 11-Dec-12 124,775.00 1,816,036.81
68 Salary for the month of June, July, & August, 2014 25-Aug-14 9,000.00 188,631.81
75
76
77
78
NB. Week number is counted from the day the 1st payment is released for construction of site office.
20-Oct-14
Total 160,381,621.51
2. Payment made for site office, fence & warehouse construction 553,048.42
Total 146,313,878.50
2. Payment made for site office, fence & warehouse construction 553,048.42
Ser. No Particulars
Ser. No Particulars
Ser. No Particulars
Ser. No Particulars
A. Construction
Construction Cost 16,381,834.75 9,624,484.78 3,861,708.68 1,747,502.48 31,615,530.69
Overhead (35%) 5,733,642.16 3,368,569.67 1,351,598.04 611,625.87 11,065,435.74
Profit (8%) 1,310,546.78 769,958.78 308,936.69 139,800.20 2,529,242.46
Sub Total 23,426,023.69 13,763,013.24 5,522,243.41 2,498,928.55 45,210,208.89
B. Design
Design Fee 182,325.81 117,098.39 28,224.80 19,158.45 346,807.45
Overhead (15%) 27,348.87 17,564.76 4,233.72 2,873.77 52,021.12
Profit (20%) 36,465.16 23,419.68 5,644.96 3,831.69 69,361.49
Sub Total 246,139.84 158,082.83 38,103.48 25,863.91 468,190.06
C. Supervision
Monthly Fee = 18,500 Birr / month 407,000.00 203,500.00 111,000.00 55,500.00 777,000.00
Sub Total 407,000.00 203,500.00 111,000.00 55,500.00 777,000.00
A. Construction
Construction Cost 16,381,834.75 1,747,502.48 3,861,708.68 21,991,045.91 9,624,484.78 31,615,530.69
Overhead (35%) 5,733,642.16 611,625.87 1,351,598.04 7,696,866.07 3,368,569.67 11,065,435.74
Profit (8%) 1,310,546.78 139,800.20 308,936.69 1,759,283.67 769,958.78 2,529,242.46
Sub Total 23,426,023.69 2,498,928.55 5,522,243.41 31,447,195.65 13,763,013.24 45,210,208.89
B. Design
Design Fee 182,325.81 19,158.45 28,224.80 229,709.06 117,098.39 346,807.45
Overhead (15%) 27,348.87 2,873.77 4,233.72 34,456.36 17,564.76 52,021.12
Profit (20%) 36,465.16 3,831.69 5,644.96 45,941.81 23,419.68 69,361.49
Sub Total 246,139.84 25,863.91 38,103.48 310,107.23 158,082.83 468,190.06
C. Supervision
Monthly Fee = 18,500 Birr / month 407,000.00 55,500.00 111,000.00 573,500.00 203,500.00 777,000.00
Sub Total 407,000.00 55,500.00 111,000.00 573,500.00 203,500.00 777,000.00
A. Construction
Construction Cost 16,381,834.75 1,747,502.48 3,861,708.68 21,991,045.91
Overhead (35%) 5,733,642.16 611,625.87 1,351,598.04 7,696,866.07
Profit (8%) 1,310,546.78 139,800.20 308,936.69 1,759,283.67
Sub Total 23,426,023.69 2,498,928.55 5,522,243.41 31,447,195.65
B. Design
Design Fee 182,325.81 19,158.45 28,224.80 229,709.06
Overhead (15%) 27,348.87 2,873.77 4,233.72 34,456.36
Profit (20%) 36,465.16 3,831.69 5,644.96 45,941.81
Sub Total 246,139.84 25,863.91 38,103.48 310,107.23
C. Supervision
Monthly Fee = 18,500 Birr / month 407,000.00 55,500.00 111,000.00 573,500.00
Sub Total 407,000.00 55,500.00 111,000.00 573,500.00
A. Construction
Construction Cost 16,381,834.75 9,624,484.78 3,861,708.68 1,747,502.48 31,615,530.69
Overhead (10%) 1,638,183.48 962,448.48 386,170.87 174,750.25 3,161,553.07
Profit (1%) 163,818.35 96,244.85 38,617.09 17,475.02 316,155.31
Sub Total 18,183,836.57 10,683,178.11 4,286,496.63 1,939,727.75 35,093,239.07
B. Design
Design Fee -
Overhead (%) - - - - -
Profit (%) - - - - -
Sub Total - - - - -
C. Supervision
Monthly Fee = 18,500 Birr / month 407,000.00 203,500.00 111,000.00 55,500.00 777,000.00
Sub Total 407,000.00 203,500.00 111,000.00 55,500.00 777,000.00
A. Construction
Construction Cost 16,381,834.75 9,624,484.78 3,861,708.68 1,747,502.48 31,615,530.69
Overhead (10%) 1,638,183.48 962,448.48 386,170.87 174,750.25 3,161,553.07
Profit (1%) 163,818.35 96,244.85 38,617.09 17,475.02 316,155.31
Sub Total 18,183,836.57 10,683,178.11 4,286,496.63 1,939,727.75 35,093,239.07
B. Design
Design Fee -
Overhead (%) - - - - -
Profit (%) - - - - -
Sub Total - - - - -
C. Supervision
Monthly Fee = 18,500 Birr / month 407,000.00 407,000.00
Sub Total 407,000.00 - - - 407,000.00
A. Construction
General Excavation & Earth Works 876,107.01 1,382,718.08 387,031.40 225,048.61 2,870,905.10
Masonry Works 186,608.00 164,138.00 72,080.00 65,720.00 488,546.00
Concrete Works 4,191,117.84 4,520,789.93 566,086.15 108,409.13 9,386,403.05
Block Works 986,849.67 167,304.90
Construction Works & Facilities 455,418.00 351,292.00 806,710.00
Roofing 392,752.34 100,698.22
Carpentry & Joinery 1,526,516.80 181,253.25
Tennis Court Fencing 198,400.00
Ditch Construction Works 66,000.00 66,000.00
Steel Structure 43,349.51
Metal Works 1,736,542.79 90,855.90
Finishing Works 2,594,835.52 2,016,525.35
Painting 391,330.97 75,902.86
Spectator Seating 1,288,266.09 470,919.94 322,002.20 213,589.08 2,294,777.31
Electrical Installation 1,932,399.14 1,040,848.94 2,374,996.10 933,964.45 6,282,208.63
Sanitary Installation 1,414,281.64 727,375.00 2,141,656.64
TOTAL Excluding VAT 16,103,326.17 11,669,586.52 4,970,988.85 2,096,423.27 34,840,324.81
VAT 2,415,498.93 1,750,437.98 745,648.33 314,463.49 5,226,048.72