WMS INFINEON PROJECT TOWER (MSB, SSB AND DBs INSTALLATION) - REV-1
WMS INFINEON PROJECT TOWER (MSB, SSB AND DBs INSTALLATION) - REV-1
WMS INFINEON PROJECT TOWER (MSB, SSB AND DBs INSTALLATION) - REV-1
CONTENTS
SECTION DESCRIPTION Page
1.0 PURPOSE 2
2.0 RESPONSIBILITY 2
3.0 SCOPE 2
4.0 WORK STANDARDS 2
5.0 TOOLS AND EQUIPMENT USED 3
6.0 MATERIALS USED 3
7.0 INSTALLATION METHOD 4
8.0 TESTING 5
9.0 SAFETY & SECURITY REQUIREMENT 5
10.0 HOUSEKEEPING 5
11.0 PERSONAL PROTECTIVE EQUIPMENT (PPE) 5
12.0 INSPECTION FORM 5
1. PURPOSE
1.1. To define the procedural steps to ensure that installation of Electrical panel / Switch
Board as per approved panel/Switchboard layout drawing/document.
2. RESPONSIBILITY
Page 1 of 5
2.1. It is responsibility of the Project Manager, together with Site Supervisor, Site Engineer,
QA/QC, Lifting supervisor and Safety team to establish successful implementation and
maintenance of these procedures.
3. SCOPE
4. WORK STANDARDS
Page 2 of 5
6. MATERIALS USED
6.1. The materials used for the installation works shall be in compliance to those approved
in material schedule. The following are the materials used for the Electrical
Panel/Switchboard installation:-
6.1.1. Unistruct channel
6.1.2. U channel or Angle bar.
6.1.3. Bolt, Nut, Washer, etc
6.1.4. Anchored bolt
6.1.5. Fitting and Screw
7. INSTALLATION METHOD
7.1. Check level and location of Electrical panel as per below equipment list
7.2.2 After install Stage of panel, civil contractor will install Free Access floor prior to bring
in panel .
7.3. Moving in panel/Switchgear from Store. Using lorry crane to unload panel from lorry to
Panel room access .
7.6 After completed put panel to correct position, start next panel to bring in.
7.7 To install frame support as per approved exact location by Client representative
Check alignment as per approved method of statement.
7.8 Check the panels as per requirement of project specification.
7.9 To ensure that access maintenance of Electrical Panels/Switchboard are within
acceptable range.
7.10 All other small lighting and power panels shall be installed as per plant DB layout
Page 3 of 5
drawings.
8. TESTING
8.1. The incoming supply of the LV switchgear shall be measured for current ,voltage
,frequency & phase sequence .
8.2. The outgoing feeders shall be energized one by one & the supply shall be measured for
current, voltage ,phase & frequency .
8.3. Check the metering functions for proper operation & correct readings .
8.4. Check the earth leakage trip setting .
8.5. Check the tripping operation of ELCB
8.6. Check the incomer trip setting
8.7. Check the circuit breakers on/off function
8.8. Check overload relay setting
8.9. Check timer setting
8.10. Check the interlocking is as specified
Page 4 of 5
10. HOUSEKEEPING
10.1. Ensure all materials are placed in designated area.
10.2. Good housekeeping shall be maintained at site all times-before, during and after.
10.3. All place of work shall be free from obstruction and any tripping hazards
10.4. Waste materials shall be collected and dispose off at the end of every working
day with appropriate approval from NCSB.
Page 5 of 5