Chapter 2 - Fundamental Design and Runoff Quantity Estimation
Chapter 2 - Fundamental Design and Runoff Quantity Estimation
2.2 Concept of
Chapter Hydrology Design
2
2.4 Design Rainfall
Rainfall estimation
Routing estimation
2.2 Concept of Hydrology Design
• The design of drainage and stormwater facilities are not limited to the natural passage of
water resulting from storm events, but also in land development and the construction field.
• When clearing land for development, it is important to provide sediment control to ensure
that eroded soil does not enter into waterways and wetlands. This is depends on the area of
the land being cleared, the amount of rainfall that can be expected during the period where
the soil will be exposed to rainfall impact and site characteristics such as the slope and soil
type.
• In addition to hydrologic considerations during the land development stage, site development
must also consider drainage patterns after development.
• The main objectives of hydrologic analysis and design are to:
• estimate peak flow rates and/or flow hydrographs for the design of conveyance and
quantity control facilities
• estimate annual runoff volumes for approximating pollutant loads in the design of water
quality control facilities.
ARI & AEP
Rainfall and subsequent discharge estimates is based on the selected value of frequency or
return period, termed as the average recurrence interval (ARI). ARI is strongly recommend to be
used for the designed drainage system in minor and major stormwater quantity systems.
ARI is the average length of time between rain events that exceed the same magnitude, volume
or duration and is expressed as : 1
Tr = x100
P
Where, Tr = Average Recurrence Interval, ARI (year)
P = Annual exceedance Probability, AEP (%)
Additionally, the probability concept can be applied in determine the
N
1
i) Probability exceeds for n years: P = 1 − 1 −
Tr
N
1
ii) Probability not exceeds for n years: P = 1 −
Tr
Example 2.1 Example 2.2
Calculate the probability of a peak flow in Calculate the probability of not having a
100 years? peak flow within 100 years?
1 1
𝑇r = 𝑥100 𝑇r = 𝑥100
𝑃 𝑃
1 1
𝑃= = 0.01@1% 𝑃 =1− = 0.99@99%
100 100
Example 2.3 Example 2.4
There are differences between design floods and actual floods in flood estimation exercises.
Although the same mathematical procedures may be involved in both cases, the implications and
assumptions involved and the validity of application are quite different.
Design Flood Actual Flood
• A design flood is a probabilistic or statistical • The approach to estimating an actual flood from a
estimate, being generally based on some form of particular rainfall is quite different in concept and is
probability analysis of flood or rainfall data. of a deterministic nature.
• For the design flood, the conditions are not • All causes and effects require consideration.
known and must be assumed, often implicitly in • The actual antecedent conditions prevailing at the
the design values that are adopted. time of occurrence of the rain are very important
• The design methods given in this Manual have and must be allowed for in estimation of the
been constructed so that the ARI of the design resulting flood. No real information is given
rainfall and design runoff can be assumed to be regarding the probability of the actual flood.
equal.
Major & Minor system
Pollutant transport and settling process: In order to investigate environmental concerns, stormwater
specialists are usually called upon to study the transport, settlement and retention of various substances in
surface water and porous media.
a) Transport processes
b) Particulate settling (involve with drag force)
2.4 Rainfall design & estimation - Introduction
• Rainfall is the driving force behind all stormwater studies and designs. An understanding of
rainfall processes and the significance of the rainfall design data is a necessary pre-requisite for
preparing satisfactory drainage and stormwater management projects.
• Rainfall design methods, which have been developed in other countries, may not always be
suitable for application in Malaysia. The design calculations for these methods have been
adjusted in this Manual to suit Malaysian conditions.
• Design storm duration is an important parameter that defines the rainfall depth or intensity for a
given frequency, and therefore affects the resulting runoff peak and volume.
• Recommended practice for catchments containing storage is to compute the design flood
hydrograph for several storms with different durations equal to or longer than the time of
concentration for the catchment, and to use the one which produces the most severe effect on
the pond size and discharge for design.
2.4 Rainfall design & estimation - IDF curve
• An Intensity-Duration-Frequency curve (IDF Curve) is a graphical representation of the probability
that a given average rainfall intensity will occur or a mathematical function that relates the
rainfall intensity with its duration and frequency of occurrence.
• The data are normally presented as curves displaying two of the variables, such as intensity and
duration, for a range of frequencies.
• These curves are commonly used in hydrology for flood forecasting and civil engineering for
urban drainage design. Figure below shows an example of typical IDF curve.
4.00 10-year
Intensity (in/hr)
20-year
3.00
2.00
1.00
0.00
0 10 20 30 40 50 60 70
Duration (min)
1000
2 5 10 20 50 100
Rainfall Intensity (mm/hr)
100
10
1
1 10 100 1000 10000
Duration (min)
Empirical IDF Curve
Solution:
λ K θ η
Ampang 65.809 0.148 0.156 0.837
, i = 9.1 mm/hr
Various methods can be used to develop design rainfall temporal pattern. However, design patterns
are not derived from complete storms, but from intense bursts of recorded rainfall data for selected
durations.
Temporal Patterns Development Steps
01 Rational Method
.
02 Hydrograph Method
.
Rational Method is used to compute the peak run-off, Q, following a rainfall event. According to
MSMA (2012), this method is the most frequently used in Malaysia and other countries. The
equation gives satisfactory result for small drainage catchments and expressed as,
where;
Q = peak flow (m3/s),
C = run off coefficient,
i = average rainfall intensity (mm/hr), with the return period of Tr years and with rainfall
duration equal to tc which is derived from frequency analysis of recorded rainfall.
A = drainage area (ha)
This method is known for its simplicity, however, now that computerized procedures for
hydrograph generation are readily available and making computation/design by computerized
method or software is also simple.
Rational Method
1. peak flow occurs when the entire catchment is contributing to the flow,
2. rainfall intensity is uniform over the entire catchment area, and
3. rainfall intensity is uniform over a time duration equal to tc
tc= 𝑡o + 𝑡𝑔 + 𝑡d
Where, the overland flow time (to) and the times of travel in street gutters (tg) or roadside swales,
stormwater drains, drainage channels, small streams (td)
• Calculation of tc is subject to the catchment properties, particularly length, slope and roughness
of drainage path. Catchment roughness, length and slope affect the flow velocity and
subsequently overland flow time, to.
Alternatively, the overland
flow time can easily be
estimated using the Design
Chart
Example 2.7 – Tc
Calculate time of concentration, tc for:
• Overland: average grass surface, 100 m length and slope of 3%,
• Drain: 1000 m length, slope of 0.2% and trapezoidal shape with side slope of 1.5,
Example 2.7 – Answer
Overland flow, n = 0.045
107.n.L1/3 107x0.045x1001/3
to = 1/5
= 1/5
= 17.94min
S 3
C A
j =1
j j Cavg = average runoff coefficient,
Cavg = m
Cj = runoff coefficient of segment j,
A j
Aj = area of segment j (ha)
j =1 m = total number of segments
Table below shows recommended runoff coeficients for various landuses which can be used as a
guide for designer. The near-field runoff coefficient for any single or mixed landuse should be
determined based on the imperviousness of the area.
Example 2.8 – Coefficient of Runoff, C
Calculate runoff coefficient for 20 years ARI based on land use of catchment area.
C A
j =1
j j
[(0.95 x 8) + (0.5 x17) + (0.8 x 50) + (0.95 x10)]
Cavg = =
m
[8 + 17 + 50 + 10]
A
j =1
j
Solution
Example 2.9 - Answer
Sub-catchment 1 (example):
Applying Horton’s formula, calculate to
Time of Concentration, tc
tc = tc + tc
tc = 6.0 min
to = 4.6 min
td = 1.4 min
Example 2.9 - Answer
Sub- Length, Slope, to, min Ld A P R S, m/m td, min tc, min
Catchm Lo S
ent
1 53.5 3.74 4.6 200 0.18 1.342 0.134 0.02 1.4 6.0
2 97.67 46.1 3.4 474 0.18 1.342 0.134 0.11 1.4 4.8
3 64.82 30.85 3.2 491.2 0.18 1.342 0.134 0.15 1.2 4.4
4 98.93 50.54 3.4 1054 0.18 1.342 0.134 0.06 4.1 7.5
** assume that the channel geometry is triangular with the slope of 1:2, depth and
width of channel is 0.3m and 1.2m respectively.
Solution
Rational Hydrograph Method
• Extended version of RM to the development of runoff hydrographs. This method is
recommended for the development of inflow hydrograph on-site detention (OSD) and small
detention pond.
• Two types of hydrograph are to be used for the sub-catchment using the RHM procedure.
Each hydrograph is a function of the length of the rainfall averaging time, d, with respect to
the sub-catchment time of concentration, tc.
• Type 1 (d is greater than tc): resulting trapezoidal
hydrograph has a uniform maximum discharge Q, as
determined from the Rational Method. The linear
rising and falling limbs each has a duration of tc.
• Type 2 (d is equal to tc): resulting triangular
hydrograph has a peak discharge Q. the linear rising
and falling limbs each have a duration of tc.
• Hydrograph type in the RHM is determined by the r/ship between rainfall duration & the time
of concentration of sub-catchment. The peak discharge is determined using Rational method.
Time Area Method
• Assume that the outflow hydrograph for any storm is characterized by separable sub-
catchment translation and storage effects. Determination of direct runoff to the outlet
via drainage network can be described using channel travel time, resulting in an outflow
hydrograph that ignores storage effects.
• Catchment will be divided into a number of isochrones or lines of equal travel time to
the outlet (Figure 2.4b). Derivation of isochrones is very crucial. The area between
isochrones are then plotted against the travel time (Figure 2.4c).
• Figure 2.4a should be applied (after deducting losses) to the entire catchment, the runoff
from each sub-area reaches the outflow at lagged intervals defined by the time-are
histogram.
To determine the hydrograph
ordinates qi expressed by using
following equation;
Runoff (m3/s)
2.00
Coefficient of discharge, Cd for square-edged, ragged edged and circular edged are 0.6, 0.4
and 0.6
Orifices
Free outfall – effective head measured from the centerline of orifice to the upstream water
surface elevation
As indicated above, the value of coefficient Cscw is vary depend on ratio of H/Hc. The
following eq. can be applied if the ratio of H/Hc is less than 0.3 with the constant of Cscw is
1.84.
Broad Crested Weirs
The most common type of structure for outflow control is broad crested weir. The
transverse cross-section is trapezoidal in shape for ease of construction. Flow rate can be
determine by using following eq.
The discharge coefficient Csp varies as function of spillway base width and effective head.
Following Eq. can be used to compute the critical velocity and critical slope
For a given effective head Hp, flattening the exit slope Se to less than Sc decreases spillway
discharge, but steeping Se greater than Sc does not increase discharge. If a slope Se steeper than
Sc is used, the velocity Ve in the exit channel will increase according to the following relationship
To estimate the time it would take to drain stored water volume of a pond through orifice
system. The following Eq. may be used to check the storage does not take too long time to
empty the pond or to return to the normal water level, after the storm ends;
Where the water surface are is constant, time to empty can be simplified to
2.5 Routing estimation
The most common methods used for routing are
1. Modified puls method – pond/reservoir
2. Muskingum method – river/channel
This method begins with the continuity equation which state that the inflow minus the
outflow equals the change in storage (I - O = ΔS). The difference in storage with respect to
time can be computed as
The storage indication between any
two time steps, t1 and t2 during the
reach routing can be expressed as the
left-side quantity:
I1 + I 2 O1 + O2 S 2 − S1
− =
2 2 t
2 S1 2S2
I1 + I 2 + − O1 = + O2
t t
(3) Next, using the hydrograph and interpolation, insert the (discharge) values. For
example at 1 hour, the inflow is 30 cfs.
(4) Next, add the inflow to the inflow in the inflow in the next time step.
(5) For the first blank inflow at 0 is added to the inflow at 1 hour to obtain a value of
30. This is then repeated for the rest of the values in the column.
(6)The 2S / t + O column can then be calculated using the following
n n +1
equation: 2S 2S
I1 + I 2 + 1 − O1 = 2 + O2
t t
30 + 0 = 2 S n / t + On +1
(7) Then, using the curve provided outflow can be determined. In this case, since ,
2 S n / t + On +1 = 30
(8) To obtain the final column, 2 S n / t − On, two times the outflow is subtracted
from . Example
30 − 2 x5 = 20
(9)The same steps are repeated for the next line. First 90 +20 = 110
From the graph, 110 equals an outflow value of 18. Finally 110 – 2 x 18 = 74.
(10)This process can then be repeated for the rest of the columns. Now a list of
the outflow values has been calculated and the problem is complete.
Muskingum Method
2. Muskingum method – river/channel
• The method models the storage volume of flooding by
combination of wedge and prism storages.
• Assuming that the cross-sectional area of the flood flow is
directly proportional to the discharge at the section, the
volume of prism storage is equal to KO where K is a
proportionality coefficient, and the volume of wedge
storage is equal to KX(I − O), where X is a weighting factor
having the range 0 X 0.5.
• The total storage is therefore the sum of two components,
S = KO + KX (I − O )
which can be rearranged to give the storage function for the
linear-model Muskingum method:
S = K XI + (1 − X )O
66
Values of storage at time j and j+1 can be written, respectively as
S j = K XI j + (1 − X )O j
S j +1 = K XI j +1 + (1 − X )O j +1
The change in storage over time interval t is
S j +1 − S j = K XI j +1 + (1 − X )Q j +1 − XI j + (1 − X )O j
or from continuity equation,
S j +1 − S j =
(I j + I j +1 )
t −
(O j + O j +1 )
t
2 2
67
Combining both,
O j +1 = C1I j +1 + C2 I j + C3O j
where t − 2KX
C1 =
2K (1 − X ) + t
t + 2KX
C2 =
2K (1 − X ) + t
2K (1 − X ) − t
C3 =
2K (1 − X ) + t
also C1 + C2 + C3 = 1
Example 2.13 Muskingum Method
Route the inflow hydrograph tabulated in the table through
a river for x = 0.2 and K = 20 hours. Assume O1 = I1 and Δt =
12 hours
O j +1 = C1I j +1 + C2 I j + C3O j
2.6 Critical Storm Duration
Critical Storm Duration.
Through the critical storm duration, the highest flow rate in conveyance system
and the highest water level in the storage facilities were used in designing the
drainage system.
1. Conveyance System
1 2 3 4 5 6
1- simple calculation for catchment < 80 ha,: critical storm duration = tc with
possible check s for partial area effects, and
2- Computer model for catchment > 80 ha: run model for carious storm duration
and plotting the calculated peak flow rates for various durations to find the critical
storm duration as shown in the following figure.
Figure shows Determination of
Critical Storm Duration for
Conveyance
2. Storage System
The critical storm duration of any storage facility (OSC, Detention Pond, Wetland ,
etc) mainly depend on the event runoff volume, inflow-outflow relationship,
initial water level in the system and etc.
Runoff volume is more critical, instead of just the intensity of the rainfall. Hydrologic
and hydraulic routing of various storm duration is required to define the maximum
water level in the storage facility.
The designer must then plot the simulated highest water level in the storage
facilities against the storm duration to find the critical storm duration.
Figure shows Determination of
Critical Storm Duration for
Storage facility