1. The blueprints for the new construction projects have been completed and construction is ready
to begin. While the organization was thinking about erecting a modular structure, they decided
on a more traditional approach. The foundation will be poured and cured before the framing
begins. This is an example of:
a. Discretionary dependency
b. Mandatory dependency
c. External dependency
d. Internal dependency
2. Your project is experiencing resource constraints at certain times in the project timeline,
requiring you to adjust start and finish dates on the schedule. What tool is best to use in this
situation?
a. Resource leveling
b. Feeding buffer
c. Critical Path method
d. Resource smoothing
3. The project optimistic estimate is 10 weeks and the pessimistic estimate is 40 weeks. What is
the standard deviation of the estimate?
a. 4
b. 5
c. 6.7
d. 7.5
PMI, PMP, PMBOK and PMI-ACP are registered marks of Project Management Institute, Inc
5. Your project has produced an optimistic estimate of 25 weeks, a pessimistic estimate of 95
weeks, and a calculated PERT of 40 weeks. What is the range of completion of the project with a
95% confidence factor?
a. Between 20 weeks and 60 weeks
b. Between 23.7 weeks and 57.3 weeks
c. Between 16.7 weeks and 63.3 weeks
d. Between 16.3 weeks and 63.7 weeks
Activity Predecessor D
Start - -
A - 5
B A 4
C A 6
D B,C 1
E C 1
F D,E 5
G E 7
End F,G -
6. Create the Network Diagram using the grid above. All times in weeks. Use for the next three
questions.
8. The customer has asked that you reduce activity D by 2 weeks. What impact does this have on
the schedule?
a. None. It is not on the critical path
b. It will reduce the schedule like two weeks
c. It will only work if you also reduce activity B by two weeks
d. It will only work if you also reduce activity F by two weeks
10. Your team is reviewing the project activities and has started to estimate the durations of the
work packages identified in the WBS. Some of these work packages and activities have
significant uncertainty associated with them for which the team has created contingency
buffers. The tool and technique that is used for this process is called:
a. Expert judgment
b. Reserve analysis
c. Parametric estimating
d. Three point estimating
Answers:
1. B - This is a clear example of a mandatory dependency; The foundation must set before you can
start erecting the walls of the structure.
2. A – Resource leveling is the tool that is used in this situation. PMBOK® Guide, 5th edition, p. 179.
4. D – Additional resources shortens activity durations. PMBOK® Guide, 5th edition, p. 181
8. C – Notice the question doesn't ask you what you will do about it – it si ply asks you hat does
this ea ? What it ea s is that your project o has a egati e float of three eeks
9. B – Reserve analysis defines contingency reserves as a method for dealing with schedule
uncertainty