Hydrosatic Presentation
Hydrosatic Presentation
• Piping
• Tanks
• Boiler
• Valves
INTRODUCTION
• Valves Procedure
• Pressure Vessels ietc Standards Pressure
Vessels
• Boilers
• Tanks
• Others Boiler
Hydrostatic testing
Piping System
Hydrostatic testing has been used to
determine and verify pipeline integrity.
Innumerable information can be obtained
through this verification process; however, Valves
it is essential to identify the limits of the Introduction
test process and obtainable results. There Parameters
are several types of flaws that can be
detected by hydrostatic testing: Procedure
Standards Pressure
Vessels
Boiler
PURPOSE OF HYDROSTATIC TEST
External corrosion:
MIC, oxidation, under
Hydrostatic test may be used to check the Internal corrosion: deposition Hydrogen induced
Pitting or uniform cracking
following: corrosion
Piping System
•The proof test involves
pressurizing the vessel
The process of or pipe with water to a
proof testing stress level above the
involves the design pressure but
Valves
below the yield
following steps. strength of the material
of construction. Introduction
Parameters
Procedure
Standards
• Hold the • Monitor for Pressure
pressure to the the drop in Vessels
required time. pressure.
Boiler
Hazards
Substandard support.
PSV failure.
Safety Precaution
1. Hydro test test Area shall be barricaded and provide warning boards to prevent personnel entry.
2. Calibrated pressure gauges and Pressure safety valves only shall be used.
3. Rating of fittings, pressure gauges, vent valves, gaskets shall be suitable for the test pressure.
4. Flanges and Plates shall be as per the line class.
5. All the temporary welding shall be performed by qualified welders and approved by Client QA/QC.
6. Ensure air vent provided at the highest elevation.
7. Gradual filling of lines shall be done keeping vent to open.
8. Ensure that the line is vented to remove air pockets before pressurization.
9. Pressure should be raised gradually under control to allow time for pipes to strain and time for personnel to check for leaks.
10. There shall be at least two pressure gauges, one at lowest point and another at the highest point in the system
11. Hydro testing crew should not stay in the direction of the blind flanges to prevent injury in case of flange rapture.
12. All hoses/ piping/gaskets and connectors/clamps shall be of adequate rating to withstand pressure.
13. Whip lash arrestor shall be provided at hose connection.
14. Personnel shall not approach the system under high Pressure.
15. Only essential and trained persons shall be allowed at the Hydro test work location
16. Access shall be free from any obstacle.
17. Supervisors shall be present at work location during hydro testing activities are done.
18. Risk assessment shall be done for any hydro test job.
PRESSURE VESSELS
ASME Section VIII DIV-1 : ASME Boiler and Pressure Vessel Code Section VIII Rules
for Construction of Pressure Vessels
PRESSURE VESSELS
Pressure tests are not normally conducted as part of routine inspection. A pressure test
is normally required after an alteration or major repair. After repairs (other than major
repairs) are completed, a pressure test
Pressure tests are typically performed on an entire vessel. However, where practical,
pressure tests of vessel components/sections can be performed in lieu of entire vessels
(e.g. a new nozzle). An engineer should be consulted when a pressure test of vessel
component/sections is to be performed to ensure it is suitable for the intended purpose.
PRESSURE VESSELS – Test Determination
When a code hydrostatic pressure test is required, the minimum test pressure should be in
accordance with the rules of the applicable code (construction code used to determine
the MAWP). 4
For this purpose, the minimum test pressure for vessels that have been rerated using the
design allowable stress published in the 1999 addendum or later of ASME Code, Section
VIII, Division I, Code Case 2290, or Code Case 2278.
• Test Pressure in psig (MPa) = 1.5 MAWP × ( temp/ temp), prior to 1999
addendum
• Test Pressure in psig (MPa) = 1.3 MAWP × ( temp/ temp), 1999 addendum
and later
• Where,
temp is the allowable stress at test temperature in ksi (MPa);
temp is the allowable stress at design temperature in ksi (MPa).
PRESSURE VESSELS – Test Preparation
Before applying a pressure test, appropriate precautions and procedures should be taken to
assure the safety of personnel involved with the pressure test.
A close visual inspection of pressure vessel components should not be performed until the vessel
pressure is at or below the MAWP.
When a pressure test is to be conducted in which the test pressure will exceed the set pressure
of the pressure-relieving device(s), the pressure-relieving device(s) should be removed.
Other appurtenances, such as gauge glasses, pressure gauges, and rupture disks, that may be
incapable of withstanding the test pressure should be removed or blanked off.
PRESSURE VESSELS - Hydrostatic Pressure Tests
Before applying a hydrostatic test, the supporting structures and foundation design should be
reviewed to assure they are suitable for the hydrostatic test load.
All instruments and other components that might experience the full hydrostatic test pressure
should be checked to ensure that they are designed for the specified pressure test; otherwise they
must be blinded off from the test.
Hydrostatic pressure tests of equipment having components of Type 300 series stainless steel
should be conducted with potable water or steam condensate having a chloride concentration of
less than 50 ppm.
The inspector should verify the specified water quality is used and that the vessel has been
drained and dried
PRESSURE VESSELS – TEST PRESSURE
Parameter Value Boiler blowdown tank
Working temperature 148 ºC
M.A.W.P 3.5
Testing temperature 148 ºC
Material SA516
This examination for leakage shall be made of all joints and connections and all regions of high
stress such as:
• knuckles in formed heads
• cone-to-cylinder junctions
• Regions around openings.
This visual examination may be waived if a suitable gas leak test is applied satisfying the
requirements
All other locations of leakage must be corrected and the vessel retested.
Similar to VIII-1, the Inspector has a right to reject a vessel if there are visible signs of
permanent distortion following the test ASME Sec-VIII
PRESSURE VESSELS – PNEUMATIC TEST
At ambient temperatures, carbon, low-alloy, and other ferritic steels may be susceptible to brittle failure.
A number of failures have been attributed to brittle fracture of steels that were exposed to temperatures below
their transition temperature and to pressures greater than 20 % of the required hydrostatic test pressure.
The potential for a brittle failure shall be evaluated prior to hydrostatic or especially prior to pneumatic testing
because or the higher potential energy involved.
To minimize the risk of brittle fracture during a pressure test, the metal temperature should be maintained at
least 30 °F (17 °C) above the MDMT or MAT for vessels that are more than 2 in.
When hydrotesting solid or clad austenitic stainless steel, the water temperature should not exceed 120 °F (50
°C) to prevent possible chloride stress corrosion cracking.
PRESSURE VESSELS - Alternatives
Appropriate NDE (e.g. RT, UT, PT, MT, etc.) shall be specified
and conducted when a pressure test is not performed after
a major repair or alteration.
PIPING
API – 570 : Piping Inspection Code
ASME B 31.1 : ASME Power Piping Code
ASME B 31.3 : ASME Process Piping Code
PIPING - INTRODUCTION
According to ASME piping system is divided into two main types:
Process Piping
It is the final check of mechanical integrity of the whole system and should be followed religiously as
after this activity the piping system has to be commissioned.
• Flow/volume demands
Test • Size and length of pipe
requirements • Total overall difference
are set by from the low to highest
considering the elevations
following: • Changes in elevation or
"high spots."
PIPING - Preparation for Testing
Exposure of Joints. Ail joints including welds not previously pressure tested shall be left uninsulated and
exposed for examination during the test.
Addition of Temporary Supports. Piping systems designed for vapor or gas shall be provided with
additional temporary supports if necessary to support the weight of the test liquid
Restraint or Isolation of Expansion Joints. Expansion joints shall be provided with temporary restraint if
required for the additional pressure load under test, or they shall be isolated during the system test.
Isolation of Equipment and Piping Not a Subjected to Pressure Test. Equipment that is not to be subjected to
the pressure test shall be either disconnected from the system or isolated by a blank or similar means.
Treatment of Flanged Joints Containing Blanks. Flanged joints at which blanks are inserted to blank off other
equipment during the test need not be tested after removal of the blank provided the requirements are
subsequently performed.
Precautions Against Test Medium Expansion. If a pressure test is to be maintained for a period of time during
which the test medium in the system is subject to thermal expansion, precautions shall be taken to avoid
excessive pressure.
PIPING - Requirements for Specific Piping Systems
Material. When permitted by the Material Specification, a system hydrostatic test may be performed in lieu of the hydrostatic
test required by the material specifications for material used in the piping subassembly or system provided the minimum test
pressure required for the piping system is met.
Provision of Air Vents at High Points. Vents shall be provided at all high points of the piping system in the position in which
the test is to be conducted to purge air pockets while the component or system is filling.
Test Medium. Water shall normally be used as the test medium unless otherwise specified by the Owner. Test water shall be
clean and shall be of such quality as to minimize corrosion of the materials in the piping system.
Check of Test Equipment Before Applying Pressure. The test equipment shall be examined before pressure is applied to
ensure that it is tightly connected. All low-pressure filling lines and all other items not subject to the test pressure shall be
disconnected or isolated by valves or other suitable means.
Required Hydrostatic Test Pressure. The hydrostatic test pressure at any point in the piping system shall not be less than 1.5
times the design pressure, but shall not exceed the maximum allowable test pressure of any non-isolated components. The
pressure shall be continuously maintained for a minimum time of 10 minutes and may then be reduced to the design pressure.
Examinations for leakage shall be made of all joints and connections.
PIPING – TEST PRESSURE
𝑃 = 1.5𝑃
2) Process Piping: (345.4.2.)
𝑆
𝑃 = 1.5 × 𝑃 × , 𝑊ℎ𝑒𝑛 𝑑𝑒𝑠𝑖𝑔𝑛 𝑡𝑒𝑚𝑝𝑒𝑟𝑎𝑡𝑢𝑟𝑒 𝑖𝑠 𝑔𝑟𝑒𝑎𝑡𝑒𝑟 𝑡ℎ𝑎𝑛 𝑡𝑒𝑠𝑡 𝑡𝑒𝑚𝑝𝑒𝑟𝑎𝑡𝑢𝑟𝑒
𝑆
Where;
𝑃 𝑖𝑠 𝑚𝑖𝑛𝑖𝑚𝑢𝑚 ℎ𝑦𝑑𝑟𝑜𝑠𝑡𝑎𝑡𝑖𝑐 𝑡𝑒𝑠𝑡 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒
S is allowable stress at component design temperature for the prevalent pipe material
𝑆 is allowable stress at test temperature for the prevalent pipe material
𝑃 𝑖𝑠 𝑑𝑒𝑠𝑖𝑔𝑛 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒
PIPING - EXAMPLE
PIPING - EXAMPLE
PIPING - Pneumatic Testing
Test Medium. The gas used as the test medium shall be nonflammable and nontoxic. Since
compressed gas may be hazardous when used as a testing medium, it is recommended that
special precautions for protection of personnel be observed when a gas under pressure is used
as the test medium.
Preliminary Test. A preliminary pneumatic test not to exceed 25 psig [I75 kPa (gage)] may be applied.
Required Pneumatic Test Pressure. The pneumatic test pressure shall be not less than 1.2 nor more
than 1.5 times the design pressure of the piping system. The test pressure shall not exceed the
maximum allowable test pressure of any non-isolated component. The pressure shall be continuously
maintained for a minimum time of 10 minutes. Examination for leakage detected by soap bubble or
equivalent method shall be made of all joints and connections.
PIPING – PNEUMATIC TEST
INTRODUCTION:
• Pneumatic testing involves the hazard of released energy stored in compressed gas so it
should be performed with extreme caution
• Permitted when hydro test can’t be done such as with the case of interior insulation and
refractory lining of pipe
• A pressure relief device shall be provided, having a set pressure not higher than the test
pressure plus the lesser of 10% of the test pressure.
• The gas used as test fluid, if not air, shall be nonflammable and nontoxic.
• Test Pressure:
PIPING – PNEUMATIC TEST
PROCEDURE:
• The pressure is to gradually increase until the lesser of 50% of the test pressure or 25 psig is
obtained
• Pressure is to be held at this level and a preliminary check of the welded and bolted
connections is to be conducted
• Pressure is then gradually increased in about 5 to 10 psig pressure increments, holding the
pressure after each increment for 5 to 10 minutes to allow for piping strains to equalize
• Then continuing in this pressure increment manner until the test pressure is reached
• Hold the test pressure at 110% of design pressure for 5 to 10 minutes
• Then lower the pressure to 100% of design pressure and examine the piping system for
leaks.
PIPING - PNEUMATIC TEST
PROCEDURE:
• Pressure gauges should be fitted at both low and high point when testing large volume
systems
• The system shall be filled from the lowest available point
• All vents and high point connections shall be open during this operation to allow the air in
the system to vent off
• After the system has been completely vented all vents and drains should be plugged or
blinded
• Maintain pressure for 10 minutes and then gradually increase pressure in steps of one tenth
of the test pressure until the test pressure is attained.
• The pressure shall be continuously maintained for a minimum time of 10 min and may then
be reduced to the design pressure and held for such time as may be necessary to conduct
the examinations for leakage.
PIPING - PNEUMATIC TEST
PROCEDURE:
• Whenever a leak is found from flanged connection, don’t perform any tightening before the
system pressure is brought down to at least 70%.
• A leak from a weld joint, piping base metal or any other location which may require hot
work shall only be addressed after de-pressurizing the piping under test.
• After any leaks have been repaired the system shall again be pressurized to the test
pressure in stages.
• After testing is completed, equipment should be thoroughly drained with all high point
vents open during draining, and dried by air blowing, swabbing, or other appropriate
means. If immediate draining and drying are not possible, hydro test water should be
circulated in the piping for at least one hour daily to reduce the possibility of pitting and
microbiologically influenced corrosion.
PIPING - PRECAUTIONS
Equipment fabricated from austenitic (300 series) and ferritic (400 series) stainless
steels and requiring hydrostatic testing should be tested with deionized water high
purity steam condensate, or potable water, in decreasing order of preference.
The hoop stress caused by the test pressure should not exceed yield.
Vents shall be provided at all high points of the piping system in the position in
which the test is to be conducted to purge air pockets while the component or system
is filling.
BOILER
NIBC – Part 3
BOILER - INTRODUCTION
On completion of annual
overhaul
Buck stays, its guides and anchors are installed as per the drawings.
DM water quality & availability as per requirement. (Minimum three (3) times of the boiler
water holding capacity shall be readily available).
Ensure that minimum three (3) numbers of calibrated pressure gauges are fitted at the
identified locations (One in the steam drum, one in the steam outlet header and the other
at the outlet of the hydraulic pump).
BOILER – TEST PRE-REQUISTES
• Chemicals – Ammonia and Hydrazine Hydrate in quantity such that water being filled shall
have 200 ppm of hydrazine and pH of 9.5 - 10
BOILER – PROCEDURE
If no leak is observed
When the pressure release the -boiler; for
If any leakage is identified
reaches the hydro-test further work. Reduce the
it is to be attended after
pressure, stop the Check for any leakage or boiler pressure gradually
draining the water and
pressurizing pump and sweating. by crack opening drain
repeat the hydro test as
observe the pressure valves till the boiler is 2
mentioned above.
drop for 30 minutes kg/ cm2 (g) and then
open all the vent valves.
BOILER – PRECAUTIONS
The DM water
and the metal
temperature of
Dial pressure
Minimum two the pressure Do not weld
Steam drum, Proper gauge used in parts should be The metal
set of spare any pressure
man holes lighting, the testing above the temperature
gaskets for parts or
and manifolds approach shall have ambient air dew shall not
the drum and attachments
inspection platforms and dials point to prevent exceed 120°F
boiler to the
caps are communicatio graduated condensate (50°C) during
important formation on pressure
properly n systems over the the close
gaskets must the pressure parts, with
joined and must be in entire range visual
be available parts being water inside
tightly sealed. place. of the hydro examination.
ready. tested, which tubes.
test pressure. interfaces with
the detection of
small leaks.
BOILER – PRECAUTIONS
DM water with oxygen scavenger added to 300ppm and PH not more than 9.5 to be used.
Boiler shall always be filled with treated water as specified in the contract. Filling the boiler
with un-treated water will cause internal damage and corrosion of pressure parts.
REPAIRED BOILER - HYDROTEST
Test pressure should be not more than 1.5 time MAWP to verify leak tightens integrity of repair
During pressure test where test pressure exceeds 90% of set pressure of the PRV, then PRV should be
removed and connection is reinstated by blinding
The metal temperature for the pressure test shall be in accordance with the original code of construction
but not less than 16C and more than 49C
Hold time for pressure test shall be minimum 10 minutes prior to examination by the inspector
The test pressure should be reduced to MAWP for close examination by the inspector.
API -653 ; Tank Inspection
TANK
and Repair.
TANK – INTRODUCTION
• Fixed Roof: Liquid filling and draining is controlled by pressure vacuum relief valve.
• Floating Roof: Liquid filling and draining is controlled by movement of roof itself.
TANK – WHY HYDROSTATIC TEST
• Final mechanical test to check mechanical strength of new storage tank. If there
are weak spots they will be evident when the tank is full of water.
• To ensure that there are no cracks, pinholes, or other discontinuities in the welds
• A reconstructed tank.
• A tank where an engineering evaluation indicates the need for the hydrostatic test
due to an increase in the severity of service. Examples of increased service severity
are an increase in operating pressure (such as storing a product with a higher
specific gravity), lowering the service temperature, and using tanks that have been
damaged.
TANK - Hydrostatic Test Procedure
Review/Approval/Authorization Requirements:
Shell Repair:
Fitness-for-Service Evaluation:
Leak Tests:
TANK -Settlement Survey During Hydrostatic Testing
Butterfly Valve
Diaphragm Valve
Back Seat
Shell
VALVES - TESTS
• Shell Test
• Back Seat
Visually detectable leakage through the pressure boundary walls and any fixed body joint is not
permitted.
Stem seals:
For adjustable stem seals, leakage from stem seals during the shell test not be the cause for
rejection at pressure rating greater than 38 ⁰C
For non-adjustable stem seals (O-rings, fixed single rings, etc), visually detectable leakage during
the shell test is not permitted.
No-Visually detectable leakage definition: If test fluid is liquid, there shall be no evidence of
drops or wetting of the external surfaces of the test
VALVES –LEAKAGE
The allowable leakage rate for closure test of valves with nonmetallic (e.g. ceramic) seat material
shall be equal to that specified in table 5 for a metal seated valve of equivalent size and type.
VALVES - PRECAUTIONS
• Paint is not applied prior to hydro test because it can mask surface defects
VALVES –PNEUMATIC TEST
• High Pressure Pneumatic Shell test: This test will be done at 110% MAWP at 38C as
• Low Pressure Closure Test: This test is recommended to be performed using gas (air/ inert
gas, etc)
• Low-Pressure Back seat Test: Recommended test fluid is gas (air / inert gas, etc)
TANK – HYDROSTATIC TEST HEIGHT
The tank shall not be filled above the level determined by the lesser value of 𝐻 . The hydrostatic test height, 𝐻 , is calculated as
follows:
𝑆 𝐸𝑡
𝐻 = +1
2.6 𝐷
Where;
𝐻 is the height from the bottom of the shell course under consideration to the hydrostatic test height when
evaluating an entire shell course in feet; or
is the height from the bottom of the length, L, for the most severely thinned area in each shell course to the
hydrostatic test height in feet.
𝑆 is the maximum allowable hydrostatic stress in pounds per square inch (psi)
The maximum liquid level for hydrostatic test shall be determined by using the actual thickness measured for each shell course,
the allowable stress for the material in each course, and the design method to be used.
HYDROSTATIC TEST PRESSURE
Duration
SYSTEM SUB-DIVISION TEST PRESSURE Acceptance Criteria
(minutes)
No deformation of foundation
𝑆 𝐸𝑡
TANK - 𝐻 = +1 24 x 60 No distortion of tank
2.6 𝐷 No leakage
EXAMPLE
Q#1 What is the minimum hydrostatic pressure for an existing vessel where the MAWP is 1000
psi and corrected stress / temperature ratio is 1.0?
Q#2: What is the minimum hydrostatic pressure for an existing vessel where the MAWP is 500
psi and corrected stress / temperature ratio is 0.8 ?
Q#3: Calculate hydrostatic leak test at 70 degree F, required for a piping system with NPS 6
ASTM A 106 Gr B pipe that operates at a maximum of 650 degrees F and 400 psi.cvQ#3:
Calculate hydrostatic leak test at 70 degree F, required for a piping system with NPS 6
ASTM A 106 Gr B pipe that operates at a maximum of 650 degrees F and 400 psi.
EXAMPLE
Q#4: A Grey Cast Iron gate valve of class 600 & NPS “6” has to be hydro tested for body as
well as its closure. Find out test pressure and duration for both tests.
Q#5: The working pressure of boiler is 104 kg/cm2 . What would be its test pressure?
Hydrostatic pressure other section of Section Viii Pressure vessel
2) For cast iron(UCI-99)
𝑃 = 2 𝑀𝐴𝑊𝑃 × 𝐿𝑆𝑅 𝑀𝐴𝑊𝑃 ≥ 30 𝑝𝑠𝑖
𝑃 = 2.5 𝑀𝐴𝑊𝑃 × 𝐿𝑆𝑅 𝑃 ≤ 400𝐾𝑃𝑎, 𝑀𝐴𝑊𝑃 ≤ 30 𝑝𝑠𝑖
Note: pressure vessel parts shall not be painted or otherwise coated either internally or externally prior to the hydrostatic
pressure test.
4) For Materials having high allowable stresses at low temperature (SS, Alloys) (ULT-99)