Project EBTM3103 Assignment 2
Project EBTM3103 Assignment 2
< JANUARY/2018>
< EBTM3103>
MATRICULATION NO : <>
IDENTITY CARD NO. : <>
TELEPHONE NO. : <>
E-MAIL : <>
LEARNING CENTRE : <>
INSTRUCTIONS
Do not copy the assignment question and instructions to your answer.
Prepare your assignment answer following the layout of the ASSESSMENT
CRITERIA shown in the RUBRICS provided for the course. Where RUBRICS are
not provided, follow the instructions/guidelines specified by the Faculty for the
assignment concerned.
Your assignment should be between 3000 to 5000 words (depending on number
of words outlined in the assignment instruction) EXCLUDING references.
Type your answer using 12 point Times New Roman font and 1.5 line spacing.
Show the number of words at the end of your assignment.
Tables and figures where provided, should be appropriately titled.
List your references separately in the APPENDIX page.
1
QUESTION 1
A)
i) Netwowork Diagram
A
G H I
J
D
B
2
ii) CPM Analysis
75 I 80
0 A 20 Move/relocate
20 G 65
Plan move 75 5 80
Complete internal
0 20 20 construction
20 45 65
21 C 45
Select furniture
40 25 65
20 B 21 21 D 41
Kickoff Prepare office
meeting 55 20 75
39 1 40
3
iii) Calculation of LS, EF, ES, LF, and TF based on Table 1
Activity Duration ES EF LS LF TF
A 20 0 20 0 20 0
B 1 20 21 39 40 19
C 25 21 46 40 65 19
D 20 21 41 55 75 34
E 30 20 50 45 75 25
F 15 21 36 65 80 44
G 45 20 65 25 65 0
H 10 65 75 65 75 0
I 5 75 80 75 80 0
J 5 80 85 80 85 0
4
B)
Duration / Tempoh
Activity PV / BCWS BCWS / day
(days/hari)
A 5,000 20 250
B 2,000 1 2000
C 3,000 25 120
D 20,000 20 1000
E 30,000 30 1000
F 3,500 15 233
G 5,000 45 111
H 80,000 10 8000
I 50,000 5 10000
J 1,500 5 300
BAC 200,000
5
(B)
Duration /
Current Actual Cost / Earned Value
Tempoh
Planned status / Kos sebenar / Nilai Earn ACWP BCWP
Activity (for
finished Status (AC) (EV) / day / day
ACWP n
Terkini (ACWP) (BCWP)
BCWP)
Completed /
A 10-May 5,000 5,000 20 250.0 250.0
Siap
Completed /
B 14-May 1,800 2,000 4 450.0 500.0
Siap
Completed /
C 15-Jun 3,000 3,000 32 93.8 93.8
Siap
60%
D 24-Jun Completed / 11,000 12,000 41 268.3 292.7
Siap
Completed /
E 1-Jul 36,700 30,000 52 705.8 576.9
Siap
Completed /
F 15-Jul 3,500 3,500 62 56.5 56.5
Siap
90%
G 5-Jul complete / 4,000 4,500 56 71.4 80.4
Siap
H 20-Jul 0 0 0
I 28-Jul 0 0 0
J 1-Aug 0 0 0
6
(B) i S curve
CV = BCWP – ACWP
SV = BCWP – BCWS
On 05 July 2018 (given the date from question, so assume it is the date of evaluation)
7
BCWS = 158,500
ACWP = 64,435
BCWP = 59,435
1) The project CPI and SPI are 1.00 until 10 May 2018, means that the value of work
done (CPI) is as planned and so does the schedule of work done.
2) Start from 10 May 2018, the graph shows the CPI and SPI are less than 1.00. CPI
less than 1.00 means that the value of work done are less than the amount of
money spent @ cost overrun. SPI less than 1.00 means it is behind the schedule.
8
C) Risk management is a four step process there is
Step 1- Risk Identification
Step 2- Risk Analysis
Step 3- Risk respornse
Step 4- Risk Review
After we analysis the risk we need to provide a sutiable responses to them these included
a) Reducing risk
Reduce the likehood
Reduce the consequence
b) Transferring the risk
c) Avoiding the risk
d) Accepting the risk
Reducing the risk usually the first alternative consideration there are basically two ways
to do this that is redusing the likehood that will accour and or reducing the impact the
adverse event would have in the project.
9
Project managers can also can consider transfering the risk by passing the work to other
person.This transfer does not change the risk its still remain in the same place and risk
will be handled by the different person.
Question 2
(https://www.youtube.com/watch?v=TkOPdhVbeE0&feature=youtu.be)
10