Assignment Adik Ir Izzati

The document outlines a 50-day construction project to build houses on land in Kuala Trong, Perak, Malaysia. The project involves laying the foundation, base slab, columns, beams, brick walls, plaster, roof, and finishing by June 30th. Key tasks include formwork, reinforcement, concrete pouring, bricklaying, plastering, and roof installation requiring general workers, bar benders, bricklayers, roof installers and M&E workers.

Uploaded by

Sheikh Bajunaid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
104 views2 pages

Assignment Adik Ir Izzati

The document outlines a 50-day construction project to build houses on land in Kuala Trong, Perak, Malaysia. The project involves laying the foundation, base slab, columns, beams, brick walls, plaster, roof, and finishing by June 30th. Key tasks include formwork, reinforcement, concrete pouring, bricklaying, plastering, and roof installation requiring general workers, bar benders, bricklayers, roof installers and M&E workers.

Uploaded by

Sheikh Bajunaid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

HOUSING PROJECT IN KUALA TRONG, PERAK

ID Task WBS Task Name Baseline Duration Baseline Start Baseline


Apr Finish
'21 May '21 Jun '21 Jul '21
Mode 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19
1 1 Cadangan Membina 50 days Fri 30/4/21 Wed 30/6/21
Rumah Di Atas Tanah Lot
2011 Di Mukim 5, Trong,
2 1.1 Perak
Start 0 days Fri 30/4/21 Fri 30/4/21 30/4
3 1.2 Foundation 14 days Fri 30/4/21 Wed 19/5/21
4 1.2.1 Formwork 10 days Fri 30/4/21 Wed 12/5/21 General Worker[3]
5 1.2.2 Reinforcement 10 days Wed 5/5/21 Tue 18/5/21 Bar bender[3],General Worker[3]
6 1.2.3 Concrete 1 day Wed 19/5/21 Wed 19/5/21 General Worker[4]
7 1.3 Base Slab 4 days Thu 20/5/21 Mon 24/5/21
8 1.3.1 Formwork 3 days Thu 20/5/21 Sat 22/5/21 General Worker[3]
9 1.3.2 Reinforcement 3 days Thu 20/5/21 Sat 22/5/21 Bar bender[3],General Worker[3]
10 1.3.3 Concrete 1 day Mon 24/5/21 Mon 24/5/21 General Worker[4]
11 1.4 Column 12 days Tue 25/5/21 Mon 7/6/21
12 1.4.1 Formwork 8 days Tue 25/5/21 Wed 2/6/21 General Worker[3]
13 1.4.2 Reinforcement 7 days Sat 29/5/21 Sat 5/6/21 Bar bender[3],General Worker[3]
14 1.4.3 Concrete 1 day Mon 7/6/21 Mon 7/6/21 General Worker[4]
15 1.5 Beam 8 days Tue 8/6/21 Wed 16/6/21
16 1.5.1 Formwork 4 days Tue 8/6/21 Fri 11/6/21 Bricklayer[3]
17 1.5.2 Reinforcement 4 days Fri 11/6/21 Tue 15/6/21 General Worker[3],Bar bender[3]
18 1.5.3 Concrete 1 day Wed 16/6/21 Wed 16/6/21 General Worker[4]
19 1.6 Brick 14 days Tue 8/6/21 Wed 23/6/21
20 1.6.1 North 5 days Tue 8/6/21 Sat 12/6/21 Bricklayer[3]
21 1.6.2 East 5 days Thu 10/6/21 Tue 15/6/21 Bricklayer[3]
22 1.6.3 South 5 days Wed 16/6/21 Mon 21/6/21 Bricklayer[3]
23 1.6.4 West 5 days Fri 18/6/21 Wed 23/6/21 Bricklayer[3]
24 1.7 Plaster 2 days Thu 24/6/21 Fri 25/6/21
25 1.7.1 North 1 day Thu 24/6/21 Thu 24/6/21 Bricklayer[3]
26 1.7.2 East 1 day Thu 24/6/21 Thu 24/6/21 Bricklayer[3]
27 1.7.3 South 1 day Fri 25/6/21 Fri 25/6/21 Bricklayer[3]
28 1.7.4 West 1 day Fri 25/6/21 Fri 25/6/21 Bricklayer[3]
29 1.8 Roof 4 days Sat 26/6/21 Wed 30/6/21
30 1.8.1 North 2 days Sat 26/6/21 Mon 28/6/21 Roof Installer[3],M&E[3]
31 1.8.2 East 2 days Sat 26/6/21 Mon 28/6/21 Roof Installer[3],M&E[3]
32 1.8.3 South 2 days Tue 29/6/21 Wed 30/6/21 Roof Installer[3],M&E[3]
33 1.8.4 West 2 days Tue 29/6/21 Wed 30/6/21 Roof Installer[3],M&E[3]
34 1.9 Finish 0 days Wed 30/6/21 Wed 30/6/21 30/6

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Project Kuala Trong
Milestone Inactive Summary Start-only Critical
Date: Mon 17/5/21
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 1
HOUSING PROJECT IN KUALA TRONG, PERAK

Aug '21 Sep '21 Oct '21 Nov '21 Dec '21 Jan '22 Feb '22
19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31

3]

,M&E[3]
,M&E[3]
[3],M&E[3]
[3],M&E[3]

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Project Kuala Trong
Milestone Inactive Summary Start-only Critical
Date: Mon 17/5/21
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress