Biaya Vendor REPLACE DUCTING PLATE PARTIALLY OF Ducting IDF Going To Stack RB
Biaya Vendor REPLACE DUCTING PLATE PARTIALLY OF Ducting IDF Going To Stack RB
Biaya Vendor REPLACE DUCTING PLATE PARTIALLY OF Ducting IDF Going To Stack RB
Duration
No Description Quantity Unit Rate Total Amount Remarks
( Day )
I. Material
1 Pipe 8', 6' 3,000 m 567,000 1,701,000,000
2 Fitting, Support Pipe, U - Bolt, etc 1 Lot 187,110,000 187,110,000
3 Relief Valve 6" 1 ea 85,000,000 85,000,000
4 Strainer 6" 2 ea 15,395,000 30,790,000
5 Pressure Switch 1 ea 4,500,000 4,500,000
6 Pressure Gauge 1 ea 1,500,000 1,500,000
Sub Total I 2,009,900,000
II. Man Power
1 Site Manager ( Mechanical Engineer ) 60 1 Prs 700,000 42,000,000 146,000,000
2 Piping Inspector 60 1 Prs 400,000 24,000,000
3 Piping Supervisor 60 1 Prs 400,000 24,000,000
4 Fitter 60 16 Prs 250,000 240,000,000
5 TIG Welder 60 6 Prs 350,000 126,000,000
6 Painter 60 2 Prs 250,000 30,000,000 30,000,000
7 Sandblaster 60 2 Prs 250,000 30,000,000 30,000,000
8 Rigger 60 2 Prs 250,000 30,000,000
9 Schafolder 60 2 Prs 250,000 30,000,000
10 Helper 60 10 Prs 180,000 108,000,000
11 Safetty Man 60 1 Prs 250,000 15,000,000
44 Sub Total II 699,000,000 639,000,000
III. Material Scaffolding
1 1 Lot 30,000,000 30,000,000
Sub Total III 30,000,000
IV. Tool / Safety Ordinary Tool / Consumable
A. Tool / Safety Ordinary Tool
1 Welding Machine 60 6 Unit 150,000 54,000,000
2 Grinding Machine 7" 60 4 Set 15,000 3,600,000
3 Grinding Machine 4" 60 8 Set 10,000 4,800,000
4 Hand Tool ( Hammer, Adjustable Wrench, 60 3 Set 10,000 1,800,000
Measurement )
5 Cutting Touch 4 Set 60 4 Set 20,000 4,800,000
6 Personal safety Equipment 60 43 Prs 150,000 6,450,000
7 Electrical Chord c/w Cable 60 3 set 30,000 5,400,000
8 Chain Block 3 Ton 60 3 set 30,000 5,400,000
9 Chain Block 5 Ton 60 2 set 50,000 6,000,000
10 Sling Bel 2 Ton 60 4 set 15,000 3,600,000
11 Sling Bel 3 Ton 60 4 set 20,000 4,800,000
12 Cable Power Welding Machine 60 3 set 20,000 3,600,000
13 MCB Panel 60 1 set 34,000 2,040,000 106,290,000
14 Exavator 60 1 Unit 1,200,000 72,000,000 72,000,000
B. Consumable 60
1 Elektrode LB 52 / 7018 60 750 kg 40,000 30,000,000
2 Grinding Disc 7" 60 250 ea 55,000 13,750,000
3 Grinding Disc 4" 60 400 ea 25,000 10,000,000
4 Welding Masker 60 10 ea 100,000 1,000,000
5 Oksigen 60 120 Btl 200,000 24,000,000
6 Acytelane 60 Btl 230,000 13,800,000
7 Cup Brush C.S 4" 60 20 ea 100,000 2,000,000
8 Majun 60 1 lot 200,000 200,000
9 Marker 60 10 Pack 180,000 1,800,000 96,550,000
7 Wripping + Mastic 502 m2 140,000 70,280,000 70,280,000
8 Painting Jotun + Sand Blasting @ 250 Micron 1,382 m2 200,000 276,400,000 408,000,000
9 Floor ( 0,8m X 0,15m x 800m ) 96 m3 3,500,000 336,000,000 336,000,000
10 White Glaas + Black Glass Welding Masker 60 50 ea 15,000 750,000 750,000
Sub Total IV 958,270,000
VI. NDT TEST
1 X Ray 300 Film 300,000 90,000,000
2 PT 4,800 Dia Inchi 8,000 38,400,000
3 Commisioning Works 1 lot 7,930,000 7,930,000
Sub Total VI 136,330,000
VIII. Transportation and Accommodation
1 Mob and demom 126,000 kg 900 113,400,000 2,123,300,000
2 Pemodokan + uang Makan 60 43 Prs 75,000 193,500,000 32,400,000
Sub Total VIII 306,900,000 4,140,400,000
IX Sosialisasi dan Keamanan 1 lot 40,000,000 40,000,000
Sub Total IX 40,000,000
GRAND TOTAL 4,180,400,000
ROUNDED EXCLUDE VAT 10%
Prepared By Aproved By
PROJECT : DUCTING
CLIENT : PT. TANJUNG ENIM LESTARI
ITEM CODE : 528050
Unit Rate
No Description Duration Quantity Total Amount Remarks
IDR ###
I. Material
7 Rock Wall size 60 cm x 5 m x 50 mm density 100 kg/m3 50 m2 75,000 3,750,000
8 Zinc Jacketing size 95cm x 8m x 0.8 mm 55 m2 105,000 5,775,000
9 Flashing Zincalume 24 m1 50,000 1,200,000
Sub Total I 10,725,000
II. Man Power ###
Installation and Replace
4 Foreman 7 day 1 Prs 400,000 2,800,000
5 Fitter 7 day 12 Prs 300,000 25,200,000
6 Scafolder 7 day 4 Prs 300,000 8,400,000
7 Welder 7 day 4 Prs 300,000 8,400,000
8 Helper 7 day 2 Prs 220,000 3,080,000
9 Sapety Man 7 day 1 Prs 300,000 2,100,000
10 Electrical 7 day 1 Prs 300,000 2,100,000
11 Driver 7 day 1 Prs 145,000 1,015,000
12 Tool Room 7 day 1 Prs 160,000 1,120,000
27 Sub Total II.1. 54,215,000
Profite 30% 16,264,500
Total 70,479,500
Insulation
1 Foreman 5 day 1 Prs 400,000 2,000,000
2 Insulator 5 day 4 Prs 300,000 6,000,000
3 Safety 5 day 1 Prs 300,000 1,500,000
4 Electric 5 day 1 Prs 300,000 1,500,000
5 helper 5 day 2 Prs 220,000 2,200,000
9 Sub Total II.2. 13,200,000
Profite 30% 3,960,000
Total 17,160,000
Page 2
REPLACE DUCTING PLATE PARTIALLY OF DUCTING IDF GOING TO STACK RB
PROJECT : DUCTING
CLIENT : PT. TANJUNG ENIM LESTARI
ITEM CODE : 528050
I. Material 1 Ls 10,725,000
II. Man Power 1 Ls 67,415,000
III. Protective Personal Equipment 1 Ls Err:509
IV. Equipment & Supporting Tools 1 Ls Err:509
V. Consumable 1 Ls Err:509
VI. Mob Mob Demob and Accomodation 1 Ls 16,675,000
VII. Sosialisasi dan Keamanan 1 Ls Err:509
GRAND TOTAL Err:509
ROUNDED Err:509 EXCLUDE VAT 10%