Calculation Sheet-Footing of SCM-160
Calculation Sheet-Footing of SCM-160
Calculation Sheet-Footing of SCM-160
885
RB 09 mm. 0.636 2.827
DB 12 mm. 1.131 3.770
DB 16 mm. 2.011 5.027
DB 20 mm. 3.142 6.283
DB 25 mm. 4.909 7.854
DB 32 mm. 8.042 10.053
As åo
Project :THE SEED Memories Siam , Bangkok
Subject : Design Foundation of SCM - D160
DESIGN CRITERIA
fc' = 240 ksc
fc = 90 ksc
Round Bar : fy = 2,400 ksc
fs = 1,200 ksc
n = 9.00
k = 0.40
j = 0.87
R = 15.70 ksc
Deform Bar : fy = 4,000 ksc
fs = 1,700 ksc
n = 9.00
k = 0.32
j = 0.89
R = 12.97 ksc
Wall covering = 10.00 cm.
Page 2 - 16 527616152.xlsCriteria
Project :THE SEED Memories Siam , Bangkok
Subject : Design Foundation of SCM - D160
5.00
0.60 1.80 0.60
Jib Direction
0.60
P1 P2
P5
5.00
1.80
2.00
P4 P3
0.60
2.00
PICTURE 01
D C
P M
A C
2.00
Di
REACTION A-C (JIB at 45°)
45°
A B
2.00
B. LOAD ON PILE
Assume size of footing WxLxH = 5 x 5 x 1.5
Weight of Footing = 90 Ton
No. of Pile = 5
Load from footing transfer to pile = 90 / 5
= 18 Ton
P1 P2
P5 Jib 0°
P4 P3
Ptotal
P1+P4 P5 P2+P3
1.90 1.90
= -P/N ± M di/ådi
2
Pi
P1,P4 = -156/5 +629.33 x 1.9 / 14.44
= 51.61 Ton ( ¯T ) for Tension
P5 = -156/5
= -31.20 Ton ( C ) for Compression
P2,P3 = -156/5 -629.33 x 1.9 / 14.44
= -114.01 Ton ( C ) for Compression
P1 P2
P5
P4 P3
Ptotal
P4 P1+P3+P5 P2
2.69 2.69
= -P/N ± M di/ådi
2
Pi
P2 = -156/5 -629.33 x 2.69 / 14.44
= -148.31 Ton ( C ) for Compression
P1,P3,P5 = -156/5
= -31.20 Ton ( C ) for Compression
P4 = -156/5 +629.33 x 2.69 / 14.44
= 85.91 Ton ( ¯T ) for Tension
Max. Compression Load on Pile = - 148.31 Ton ( C ) for Compression Jib 45°
Max. Tension Load on Pile = 85.91 Ton ( ¯T ) for Tension Jib 45°
C. BENDING MOMENT
5.00
0.60 1.80 0.60
0.60
P1 P2
d c
P5
5.00
1.80
2.00
a b
P4 P3
0.60
2.00
P
M
1.50
P1,P4 P5 P2,P3
0.60 0.90 0.90 0.60
d2 = M/Rb
= 22.81x1000 / (12.97 x 5 x 100 )
d = 18.75 cm. < 140.00 cm. OK.
Jib at 45°
c
Fixing Angle P2
-0.14
d2 = M/Rb
= 20.98x1000 / (12.97 x 5 x 100 )
d = 17.98 cm. < 140.00 cm. OK.
D. DESIGN OF REINFORCEMENT
As = M / fsjd
= ( 22.81 x 1000) / (1700 x 0.892 x 1.4 )
= 10.75 sq.m.
UESD 18 - DB 16 mm.
m = 3.23Sfc' / f
= 31.28 ksc.
åo = V / ujd
= 58.37 cm.
UESD 18 - DB 16 mm.
As = 24.13 sq.m. åo = 60.324 cm.
As = 36.2 sq.m. åo = 90.432 cm.
18 - DB 16mm.# TOP
1.50
18 - DB 16mm.# BOTTOM
0.60 0.90 0.90 0.60
PUNCHING SHEAR
Vp = 2 x 114.01
= 228.02 ksc.
vp = Vp / bd
= 3.26 ksc.
Allowable ; vp = 0.53 Sfc'
= 8.22 ksc. > 3.26 ksc. OK.
BORE PILING
Max. load on pile = 148.31 Ton
SPIRAL REINFORCEMENT
Ps = 0.45 [ Ag/Ac - 1 ] fc'/fy
= 0.45 [ ( 2827.44 / 1963.5 ) - 1 ] x 240 / 4000
= 0.012
Volume of Spiral Rebar ; Vs = Ps Ac
= 0.012 x 1963.5 x 100
= 2,332.64 cu.cm.
BOND LENGTH
u = (2.29 Sfc')/D
D = 16.00 mm.
u = 22.17
Ld = P/4u
= (85.91 x 1000) / (4 x 22.18 x 68 )
= 14.24 cm.
BORE PILING
Max. load on pile = 148.31 Ton
SPIRAL REINFORCEMENT
Ps = 0.45 [ Ag/Ac - 1 ] fc'/fy
= 0.45 [ ( 2827.44 / 1963.5 ) - 1 ] x 240 / 4000
= 0.012
Volume of Spiral Rebar ; Vs = Ps Ac
= 0.012 x 1963.5 x 100
= 2,332.64 cu.cm.
BOND LENGTH
u = (2.29 Sfc')/D
D = 16.00 mm.
u = 22.17
Ld = P/4u
= (85.91 x 1000) / (4 x 22.18 x 68 )
= 14.24 cm.