Background and Purpose of The Guide: (Ia Cop)
Background and Purpose of The Guide: (Ia Cop)
Introduction
2
See Chapter 3
2
December 21 2013
Draft Audit planning and risk assessment guide
3
December 21 2013
Draft Audit planning and risk assessment guide
4
December 21 2013
Draft Audit planning and risk assessment guide
managers (a) examine likely future events and the risks and opportunities
these represent to the achievement of their objectives; and (b) determine
and implement risk mitigation actions (e.g. control activities).
Audit risk assessment is part of planning and a process where auditors
consider both (i) individual events and the risks and opportunities these
represent to the achievement of the objectives of elements of the audit
universe and (ii) generic risk factors that help prioritize work to areas of
highest risk. The purpose of audit risk assessment is to ensure that audit
resources are addressed to the audit of areas of highest risk to the
Organisation.
No one can consider risk, if objectives are not clear. If it is not clear
what an element of the audit universe is trying to achieve you cannot
carry out a risk assessment. Be sure you understand the objectives of
different elements of the audit universe before trying to identify likely
events that impact these objectives and the inherent and residual risks
involved.
13. The auditing standards state clearly that where management has a functioning
risk management system in place auditors should use this as a basis for
carrying out their own risk assessment.
14. While risk management is a logical process, many public sector organisations
do not address risk management in a consistent and structured way and do
not have effective internal control. In this situation auditors must make their
own judgements about risk within the organisation. In other words: the
auditor must assess risks to the achievement of the organisation’s objectives
even if management do not.
Even where IA have to carry out their own risk assessment seek
management input on such things as the organisation’s appetite for risk.
4
See the guidance in internal control produced by the Committee of Sponsoring Organisations of the
Treadway Commission (COSO) for more information on the link between risk management and
internal control.
5
December 21 2013
Draft Audit planning and risk assessment guide
6
December 21 2013
Draft Audit planning and risk assessment guide
19. From the table it is clear that there is a significant overlap between the
first two stages of risk management and the second and third stages of
audit planning risk assessment.
20. The main difference is that managers need to assess inherent risks so that
they can determine and put in place risk mitigation actions (including
controls). The auditor however needs to assess residual risk (which is the risk
that remains after the effectiveness of internal controls are taken into account)
to determine areas that are high priority for examination.
21. A simple example illustrates the relationship between inherent risk control
activities and residual risk. If you cross the street, there are a nearly infinite
number of inherent risks. One of the inherent risks with a high probability and
large impact would be getting hit by a car. So to mitigate this risk we implement
the control of looking left and right to check for oncoming traffic before crossing
the road. But this will not eliminate every possible risk and residual risks remain.
For example, you could still be hit by a meteor because you did not look up!
22. The reason for this is obvious. With limited resources the auditor wants to
concentrate audit work on areas where the risk exposure to the Organisation
7
December 21 2013
Draft Audit planning and risk assessment guide
is highest. If inherent risk is very high but there are good controls in place then
the residual risk may be low and not therefore worthy of examination.
8
December 21 2013
Draft Audit planning and risk assessment guide
9
December 21 2013
Draft Audit planning and risk assessment guide
10
December 21 2013
Draft Audit planning and risk assessment guide
29. There is a high degree of commonality in the way that IA units in Government
typically cut up or categorize the audit universe (see best practice examples).
Best Practice example on categorisation of the audit universe
From IIA Government survey
1. Almost all IA units have a formally documented audit universe (97%).
2. The most common categorisations used are:
Departments – 97%
Processes – 97%
Organisational unit or location 81%
Operational programmes – 75%
Service Lines – 58%
ERM risk portfolio – 28%
Other – 22%
30. Ultimately it is for the head of the Internal Audit Unit to decide how to
categorize the audit universe and how many slices it makes sense to use. Most
internal audit units will therefore want to consider the following as the
minimum categorizations needed:
By organisational structure (Departments, Divisions, Units, Stand-alone
Projects);
By common processes (Payments, Receipts, Asset Management,
Procurement, Contracting, Inventory, Human Resource Management);
By location (Headquarters, Regional offices, Local offices)
By operational programmes (In a transport agency or department these
could include: construction of new roads, maintenance of roads, issue of
licences for drivers, collection of speeding fines, etc.);
By service lines (In a social security Department these could include:
services for the elderly, services for the handicapped; services for the care
of children which may be handled by a number of different departments or
units.)
The audit universe of the office consists of some 100 auditable entities that are divided
into 14 categories: 1) Governance, 2) Reforms, 3) Strategic Management, 4)
Special Initiatives/Projects, 5) Planning and Budgeting, 6) Field Programme
Cycle, 7) Decentralized offices, 8) Information Systems and Technology, 9)
Knowledge and communication, 10) Safety and Security, 11) Human Resources,
12) Financial Management, 13) Procurement, Property and Facilities
management, and 14) Administrative and Other Services.
11
December 21 2013
Draft Audit planning and risk assessment guide
12
December 21 2013
Draft Audit planning and risk assessment guide
Carry out risk assessment in two clear stages. Use stage one to identify
risks and stage 2 to assess (score) risks in terms of impact and probability.
13
December 21 2013
Draft Audit planning and risk assessment guide
residual risks; and (d) identify high levels of residual risk that need to be
factored into strategic and annual work plans.
Where no risk management process is in place Internal Audit will need
to carry out a separate exercise to identify events that give rise to risks and
opportunities. This is more difficult and time consuming than reviewing
management’s own risk assessments. It is important that the process
includes interaction with management to obtain their views on key events
and risks impacting the Organisation. It will also be necessary to score
events identified in terms of probability and impact to create an overall
risk score.
35. The process of identifying events and scoring risks as part of a separate
exercise is considered in more detail in the sections that follow.
Identifying risks
36. Even where management has not carried out formal risk assessments there
will often be other documentary sources that can help internal audit unit to
identify individual risks. These include:
Operational plans for the Organisation;
Earlier reports by internal or external audit;
Annual report of the Organisation;
Major reviews of functions or activities carried out by management or by
external bodies (e.g. World Bank or EU review missions).
37. The most common method of identifying risks will be by interview and
discussions with management. This should always be done, as management’s
views on risk are very important.
The second part of the workshop would assess (score) identified risks
for impact and probability.
38. To identify risks it can be useful to brainstorm the different types of events
that may generate risks for the organisation. An example is provided below of
common types of events that generate risk.
14
December 21 2013
Draft Audit planning and risk assessment guide
39. Once all relevant events (risks) have been identified they need to be assessed
and scored. Inherent Rrisk should be assessed in terms of impact and
probability. The impact defines the financial or non-financial consequences
for the Organisation should the risk occur. The probability defines the chances
that the risk may occur. Assessing impact of risks is more complex than
assessing probability but both are important elements of a risk assessment.
40. It is recommended not to score the risks in a pure mathematical way. It is
more practical to assess and score them according to a predetermined criteria
for impact and probability. Best practice often suggests using three scoring
levels, but this may lead to an over-scoring in the middle category. A four point
scales may therefore be the most appropriate (particularly for assessing
impact). Note that there is no rule here. Auditors are free to choose whichever
scoring system they feel is more appropriate. The example below uses four
categories but three could also be used.
15
December 21 2013
Draft Audit planning and risk assessment guide
Financial impact is less Unplanned loss of several Limited and minimal loss
than xxx,xxx. employees within a unit of operations.
Low that may cause some
disruption to the unit's Promptly recoverable
(1) operations. service interruption.
16
December 21 2013
Draft Audit planning and risk assessment guide
43. Annex A provides an example of risk impact criteria used an internal audit unit
in a UN Agency.
17
December 21 2013
Draft Audit planning and risk assessment guide
1 2 3 4 5
18
December 21 2013
Draft Audit planning and risk assessment guide
Note that inherent risk can be a generic risk factor. The work done
under chapter 3 to identify and score risks can be used to identify areas of
high inherent risk. .
Best Practice example - common risk factors used by Internal Audit units
From IIA Government survey
The most common categorisations used are:
Degree of financial materiality - 100%
Complexity of activities - 94%
Control environment - 94%
Reputational sensitivity – 92%
20
December 21 2013
Draft Audit planning and risk assessment guide
54. The decision on which risk factors to use is important and should include at
least some of the main risk factors used in general by Internal Auditors.
Keep the number of risk factors to between 4 and 8. Too few risk
factors will limit the effectiveness of the exercise; too many will increase
the time it takes to and will not produce substantially better results.
Remember you have to develop criteria to assess each factor and score
them.
Choose risk factors that make the most sense for the Organisation
you are auditing. Don’t only use the list above if there are other factors
that are more relevant.
21
December 21 2013
Draft Audit planning and risk assessment guide
22
December 21 2013
Draft Audit planning and risk assessment guide
It would be relatively easy to modify this system for use with a wider range of risk
factors. More or fewer risk factors would require a different risk index score for
high medium and low categories.
57. All risk-scoring systems by definition produce exact numbers. This can add a
false level of accuracy to the assessment process. It is important to recognise
that many risk factors are judgemental and are not based on absolute values. A
major exception is materiality, which is also one factor that will usually be
highly weighted. (Note: There are many ways of determining materiality but
the simplest models usually use a percentage of total expenditure or income.)
Make sure that risk index scores and priorities are reasonable.
(a) Calculate the theoretical maximum before setting the index priorities
and (b) be prepared to change the index priorities if the results are
obviously unrealistic (for example if every audit is show as high priority).
23
December 21 2013
Draft Audit planning and risk assessment guide
Strategic plan
59. The purpose of the strategic plan is to document the judgements made about
“audit needs” – the internal auditor’s judgement of the systems, activities and
programmes that should be subject to audit to provide reasonable assurance
to management about risks and the effectiveness of internal control. The plan
must contain:
Clearly expressed objectives and performamce indicators for what the IA
function will achieve in the next 2-4 years, linked as appropriate to the
strategy for the organisation
The methodology used to prepare the strategy and how the IA unit has
assessed risks that impact the entity’s objectives.and how the IA unit has
assessed risks that impact the work.
How the IA unit will address the areas of most significance over a period
of years. It will usually be necessary to identify cycles of coverage for
different elements of the audit universe. Some systems and processes
may need to be examined every year. Others may only need to be
examined every three to five years and so on.
The resources required and available to meet these needs and t.he impact
of resource constraints on the ideal level of audit coverage
An internal risk assessment of those events which may impact the
achievement of objectives in the audit strategy and mitigating actions to
address such risks. (For example, staffing shortfalls; skills shortages and
training and other actions needed to address these risks.).
Plans for the coordination of work with other sources of assurance (e.g.
external audit).
The approach for following up recommendations made.
The impact of resource constraints on the ideal level if audit coverage.
The higher or longer-term goals the IA function wants to achieve but may
not achieve in the short term. .
24
December 21 2013
Draft Audit planning and risk assessment guide
Allow sufficient time for planning and reporting the audit work
completed.
25
December 21 2013
Draft Audit planning and risk assessment guide
26
December 21 2013
Draft Audit planning and risk assessment guide
27
December 21 2013
Draft Audit planning and risk assessment guide
Criteria
Level
(score) Achievement Reputation (integrity,
Financial Personnel Operations
of objectives accountability)
28
December 21 2013
Draft Audit planning and risk assessment guide
Risk Assessment: Criteria for Risk Probability (example from IA unit of FAO)
29
December 21 2013
Draft Audit planning and risk assessment guide
74. Each of the risk factors is also given weighting using judgement of the relative
significance of each of the factors. This will vary between different types of
entity. An example of weights that may be applied:
Element Weighting
A Materiality 3
B Control Environment /Vulnerability 2
30
December 21 2013
Draft Audit planning and risk assessment guide
C Sensitivity 2
D Management concerns 4
75. The factor score and weightings are then combined into a formula which can
be used to calculate the risk index. For example
Risk index = (A x 3) + (B x 2) + (C x 2) + (D x 4)
76. The formula is then applied to each system to produce a risk index for each
system. Each system is then categorised as High Medium or Low risk based on
the following matrix:
Risk Index Risk Category
Over 49 High
30-49 Medium
Less than 30 Low
77. It would be relatively easy to modify this system for use with a wider range of
risk factors. More risk factors would require a different risk index score for
high medium and low categories.
78. All risk-scoring systems by definition produce exact numbers. This can add a
spurious air of accuracy to the assessment process. It is important however to
bear in mind that many risk factors are judgemental and are not based on
absolute values. A major exception is materiality, which is one factor that
should always be highly weighted.
31
December 21 2013
i