Construction Technology of Civil Engineering Projects
Construction Technology of Civil Engineering Projects
Lecture notes
These lecture notes have been developed with due care. Comments are
however appreciated.
Please reply to [email protected]
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst
Construction Technology of Civil Engineering Projects
0 CONTENTS
0 Contents .............................................................................................................. 1
1 Introduction ........................................................................................................ 5
2 Interaction in Design ........................................................................................ 11
2.1 Interaction between design and functional requirements/ boundary
conditions ............................................................................................................. 12
2.1.1 Subsoil ................................................................................................ 13
2.1.2 Earthquake.......................................................................................... 13
2.1.3 Hurricane ............................................................................................ 13
2.1.4 Temporary nature of structures .......................................................... 14
2.1.5 Extrapolation beyond the state of the art ........................................... 14
2.2 Interaction between design and execution/maintenance ............................. 15
2.2.1 Economical aspects ............................................................................ 16
2.2.2 Boundary conditions for design imposed by execution aspects ........ 17
2.3 Interaction between the different engineering disciplines ........................... 27
2.4 Interaction between Design and QHSE ....................................................... 28
3 Cost Estimation ................................................................................................ 30
3.1 Cost components.......................................................................................... 30
3.2 Development of cost for labour, materials and equipment ......................... 31
3.3 Cost drivers for concrete works in civil engineering .................................. 32
3.4 Interaction between design and cost of concrete ......................................... 37
4 Design/ Construct optimization........................................................................ 45
4.1 Introduction.................................................................................................. 45
4.2 Integration within the project environment ................................................. 47
4.2.1 The increasing specification phenomenon ......................................... 48
4.2.2 Cyclic and Linear approach ............................................................... 49
4.2.3 Serial versus Concurrent engineering ................................................ 52
4.2.4 Process management aspects (engineering oriented)......................... 53
4.3 Tender phase ................................................................................................ 58
4.3.1 Tender strategy ................................................................................... 58
4.3.2 Risk management ............................................................................... 61
4.3.3 Level of Specification ........................................................................ 62
4.3.4 The solution versus a solution ............................................................ 63
4.4 Construction Phase/ Realization Phase ....................................................... 63
4.4.1 Integrated planning schedule ............................................................. 63
4.4.2 Value engineering .............................................................................. 64
4.4.3 Risk Management............................................................................... 64
4.4.4 As built documents ............................................................................. 65
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 1 of 199
Construction Technology of Civil Engineering Projects
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 3 of 199
Construction Technology of Civil Engineering Projects
1 INTRODUCTION
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 5 of 199
Construction Technology of Civil Engineering Projects
CONSTRUCTION TECHNOLOGY
EXECUTION STRUCTURAL
TECHNOLOGY DESIGN
CONSTRUCTION
DESIGN ENGINEERS
PEOPLE AT SITE
Construction people at site actually execute the scheme. Design engineers will, as
part of the design, optimize the cost drivers of the scheme: manpower required,
equipment needed, material demand and, if applicable, cost related to maintenance
and repair.
The optimization in this respect is the effort to reach a structurally and
economically justified scheme that complies with the functional requirements in a
most effective way.
During the development of the design, alternatives will be generated and
considered. The alternatives may be fundamentally different in the way they cope
with the structural and execution aspects of the scheme. The choice between
alternatives is, apart from cost, also influenced by following considerations:
Reliability and risk management
Constructability
Redundancy aspects
Maintenance cost
Durability aspects
Sustainability aspects
Future extension capability
Design aspects: shape, repetition, planning etc.
And again, interaction between all aspects involved is the decisive success factor
and may lead to unconventional solutions.
An example in the Netherlands is the Euromax quay wall (fig. 1.4), where a whole
life cycle approach resulted in a diaphragm wall (a concrete slurry wall).
Traditional solutions would result in a steel sheet pile wall.
To support the interaction between design and execution aspects, the lecture will
also address:
• Special execution methods/ techniques which may lead to cost effective
solutions such as movable formwork and to highlight the importance of
repetition.
• Planning aspects and how planning aspects may have an impact on the
development/ choice of alternatives.
• Cost estimation, to create awareness of the economical impact of design
choices and to support the selection of alternatives.
• It should be realized that all prices are indicative and for teaching purposes
only. Actual prices will vary pending market conditions and geographical
spread.
Bibliography:
Uitvoering van Betonconstructies, (in Dutch), issued by Stichting ENCI Media, ‘s-
Hertogenbosch, The Netherlands, ISBN 90-71806-26-X
Handboek Ondergronds Bouwen, Bouwen vanaf het Maaiveld, part 2 (in Dutch),
issued by Balkema, Rotterdam, The Netherlands, ISBN 90 5809 313 1
Installation of steel sheet piles, (in English), issued by the technical European Sheet
Piling Association (TESPA)
British Standard, BS-5973. Code of practice for access and working scaffolds and
special scaffold structures in steel, 1993.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 9 of 199
Construction Technology of Civil Engineering Projects
J. Martín Palanca. Presiones del hormigón fresco. Instituto Eduardo Torroja c.c.
1982. (“Pressures of fresh concrete”, in Spanish.)
2 INTERACTION IN DESIGN
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 11 of 199
Construction Technology of Civil Engineering Projects
The functional requirements and in particular the primary function will lead to a
basic concept of the scheme: for a building the basic concept is a box with
columns/ walls in between the floor slab and the roof slab, for a viaduct it is a box
type superstructure on piers, for a jetty it is a deck structure on piles (fig. 2.1).
Boundary conditions will in general influence the choice of basic concept (or parts
thereof) right from the start:
2.1.1 Subsoil
The subsoil conditions will generally indicate the type of foundation: a piled
foundation or a spread foundation. Pending the concept this will have a major or
minor impact: for a viaduct the superstructure is not significantly influenced by the
choice of foundation (except for integral viaducts). But for a quay wall it has a
major impact: a sheet pile wall or a deck on piles versus a gravity structure. And
even within the group of gravity structures the subsoil may lead to different basic
concepts: soils with less strength may allow caissons, but not block walls as block
walls will lead to higher foundation stresses compared to caissons. From this
interaction it can easily be concluded that there is a direct correlation between the
reliability of the soils data and the reliability of the concluded concept.
2.1.2 Earthquake
Earthquake conditions will generally lead to an adjustment of the normally applied
static schemes: multi span structures often have one strongpoint to stabilize in the
longitudinal direction. Under earthquake conditions this would lead to a significant
load on the strongpoint as the earthquake is generally applied as an equivalent
horizontal load with a magnitude equal to a certain percentage of the vertical
weight. As the strongpoint stabilizes the entire length, it would receive a fixed
percentage of the overall weight as horizontal load. To avoid such condition the
multi span system is often separated into a number of single span units, each taking
the earth quake load independently.
2.1.3 Hurricane
Hurricanes result in high water levels and big waves. This will specifically
influence the deck levels of platforms and elevations of quay walls. The levels
concluded from the hurricane circumstances may however conflict with the levels
concluded from operational conditions. To solve such conflict unconventional lay-
outs or special provisions such as relieve systems are applied. Typical relieve
systems for piled deck concepts for quay walls, consist of deck slab units which
will be lifted at a specific overpressure. Chains are used to secure the global
position of the slabs relative to the deck.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 13 of 199
Construction Technology of Civil Engineering Projects
Fig 2.3 Ramspol, ICT tools to support design (FEM calculation) and work
preparation (3D CAD modeling). Courtesy: BAM Infraconsult bv
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 15 of 199
Construction Technology of Civil Engineering Projects
Initial cost corrected for the value of changes in construction time: from the
client’s perspective, an acceleration of completion could have a value
because of overall project optimization or an earlier start of revenues
generated by the project. The value per unit of time may have a significant
impact on alternatives and/ or construction methods as a balance must be
found between initial cost and the value of time.
Initial cost corrected for the cost of quality: quality in this respect is meant
as aesthetics, appearance, reputation, maintenance demand etc. Basic
requirements related to safety, reliability and serviceability shall always be
met.
Initial cost plus capitalized cost for maintenance, repair and demolition:
The integral approach to consider the net present value of all cost over the
entire service life of the project.
On-shore site conditions may limit the crane capacity which can be used at site.
The hoisting capacity, always to be considered in combination with the reach,
should be considered in design. For waterfront/ off-shore projects, environmental
conditions like waves and swell will generally dictate the choice between floating
spread (pontoons and barges), and self elevating platforms (jack-up barges). The
characteristics of both are rather different in lifting capacity and reach as well as in
cost. To optimize cost, such choice should have an impact on the design/concept:
generally, design/concepts will make an optimal use of the cranes available. A
typical example of the interaction at structural element level is a block wall (fig
2.4): outside the Netherlands a block wall is often used as quay wall (if subsoil
conditions allow). To provide adequate stability, the wall requires a certain weight.
The weight comes from the blocks. But to provide internal stability, each individual
block needs a certain weight as well. And as such there is a direct link between the
design of the wall, the design of the individual block and the lifting
capacity/equipment required.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 17 of 199
Construction Technology of Civil Engineering Projects
Fig 2.5 heavy lifting capacity and preassembly of major components applied
at a remote site. Courtesy Interbeton BV
Boundary conditions may impose the use of special formwork and supporting
structures (falsework):
They all have in common that the span is built from a limited number of
positions, mainly independent from the area to be crossed.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 19 of 199
Construction Technology of Civil Engineering Projects
a prismatic beam as basic concept: the dead weight would simply be too big to
carry. Nevertheless economic concepts can be developed by a curved bottom chord
of the beam: the weight is reduced and through a smart design of the formwork,
repetition can be incorporated. This method can be used for both in-situ
construction (fig. 2.10) as well as for prefabrication (fig 2.11).
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 21 of 199
Construction Technology of Civil Engineering Projects
2.2.2.4 Constructability.
A method statement is a document which clearly presents how the scheme can or
should be built: all phases of the execution must be addressed: required equipment,
impact of phasing on formwork , falsework and reinforcement details, prestressing
procedures, interference with the surrounding environment, adverse environmental
conditions, logistics, permits, approvals etc. Special attention s required for design
choices that influence the time schedule for the execution of the scheme: time is a
cost factor on its own, but changes in the completion data might have a significant
commercial value to the client. Method statements may have various levels of
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 23 of 199
Construction Technology of Civil Engineering Projects
detail: from global (for the scheme as a whole) to detail (parts of the scheme,
components and details). Method statements should be (globally) developed during
the conceptual development of the scheme to demonstrate feasibility of the scheme
and should be further detailed during the subsequent phases. Method statements
also serve as an interface document between design and construction to secure the
transfer of critical information but also to facilitate interaction between design and
construction (fig 2.12). Finally, during construction, method statements are an
important tool to assure quality.
Stability, strength, stiffness must be checked for all phases and special attention is
required for the change in static schemes that can occur as execution proceeds. An
example of this aspect is given in fig. 2.13 for a concrete block wall: to optimize
the material demand, blocks are placed eccentrically to each other to keep the
resultant load within the middle third of the bottom block- foundation interface.
The overturning stability during construction must be checked at all levels of the
block- block interfaces: the wall leans backwards, is subjected to wave loads and
not yet backfilled. Such case could be governing and additional measures (partly
backfilling during construction) might be required. Pending consequences on time
schedule, logistics and equipment required, a redesign might be required.
The execution process will generate deviations from theoretical positions and
dimensions. Tolerances, as such accepted deviations, are given in codes (both Euro
codes and National codes). Design codes have allowed for these tolerances also.
However, civil engineering structures do not always fall within the validity area of
the specific building codes. Project specific tolerances must be addressed and
agreed in such case, and subsequently be incorporated in design (if beyond the
values incorporated in design codes). Specific examples are driving tolerances of
piles in open waters (typical position tolerance 50 mm.) and prepared foundation
bed tolerances in open water (typically 25 mm.). Smart design will anticipate on
tolerances and develop a phasing schedule, a choice of materials (prefab/ in-situ
concrete or a mix of both) and details, to eliminate the effect of individual
contributions and as such avoiding an accumulation of deviations. A typical
example is the connection between steel piles, concrete pile caps and concrete deck
elements as frequently applied in port construction for jetties (fig. 2.14) : the
driving of the piles will result in a deviation from the nominal position (but should
be within specified tolerances). The cutting of the piles will result in levels around
the nominal level as well (and should also be within the specified levels). A
prefabricated pile- cap, made as a hollow, U-shaped, box is lowered over the piles.
The box has oversized holes in the bottom slab to pass the piles and to allow for
tolerances (horizontal control). Vertical control is assured by the application of
shim plates (filling plates) between the piles and the supporting beams inside the
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 25 of 199
Construction Technology of Civil Engineering Projects
box. By these, simple, measures, tolerances have been decoupled and positional
control of the box is assured. The deck structure can now easily be constructed by
prefabricated deck slabs (with a thickness of approximately half the depth of the
deck) and an in-situ concrete topping. By the application of an in-situ topping,
vertical control of the finished deck is relatively easy.
Eccentricities can be the consequence of tolerances but may originate from a
different mechanism also: the, literally, gap between the theoretical scheme and
reality. Not due to construction, but from the consequence that structural members
have dimensions or from optimizations. An example is a pile- system of raker piles,
schematically taken as single lines with a discrete point of intersection. From an
optimization consideration it may make sense to space both legs of the rake system
(out of plane), but an eccentricity (and as such secondary moments) will be the
consequence.
2.2.2.5. Reliability
The design and the design choices should allow a strict control (management) of
the construction phase (and if applicable the service life): the prediction of material
demand, concluded man-hours, required equipment, time demand and, if
applicable, maintenance and repair efforts, should be reliable throughout the
subsequent phases. Reliability in this respect is heavily influenced by the
correctness of input data, properly selected tools for analysis (level of
sophistication) and significance of the criteria. It requires thorough experience and
engineering judgment to realize and quantify the uncertainty in output due to a
limitation of available input data, the limited quality of input data and the limited
level of sophistication of analysis tools in early stages of concept development.
Nevertheless, reliability of the process as a whole requires engineers to quantify the
effects and to incorporate them in results as calculated.
An effective tool to meet this objective is to structure the design process through a
number of phases (cycles), with target budget accuracy criteria for each phase. A
suggested approach is given in Appendix A.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 27 of 199
Construction Technology of Civil Engineering Projects
More than in the past, there is an interaction between Design and QHSE (quality,
health, safety and environmental care). The interaction can have an impact on the
choice of materials, method statements for construction, reinforcement details,
construction details, equipment to be used, monitoring during construction and
temporary provisions.
Examples of this interaction are:
Secured, dedicated, walkways for site personnel: not only for elevated sites
(high rise buildings, off-shore platforms, bridges and silo’s ), but also for rail
tunnel projects: starter bars from the bottom slab for the rail supporting
blocks will stand upright over a significant length and for a significant time.
Site logistic requires personnel to cross these areas regularly. The provision
of an elevated pass-over at dedicated positions is an effective way to avoid
people falling over starter bars (which could lead to fatal consequences).
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 29 of 199
Construction Technology of Civil Engineering Projects
3 COST ESTIMATION
Indirect Cost:
Site office, including man-hours for management and supporting staff.
Site facilities for storage, repair and maintenance
Site preparation: leveling, roads and fences
Auxiliaries: oil, gas, water and electrical supply.
Small tools: positioning/ survey tools (total stations), compressor, compactors
etc.
Design and site- engineering
General overhead
Risk, profit, general cost
Note: Indirect cost can amount some percent of total cost for construction, also for
the bigger project. General overhead is normally a percentage of the sum of direct
and indirect cost. General cost for civil engineering projects is around 12% of the
direct cost. Although driven by geographical area, market situation and commercial
considerations, 20% can be used as percentage of direct plus indirect cost for
general overhead for budget estimate purposes, (for Design/ Construct type
projects)
Due to the development of cost components, there has been a significant change in
the ratio between the components formwork/ falsework, reinforcement and
concrete: for concrete structures in the building industry (offices etc.) the
contribution of formwork/ falsework has significantly increased and is now a
dominant factor. To influence construction cost, quite a focus is required on
formwork/ falsework.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 31 of 199
Construction Technology of Civil Engineering Projects
Concrete per m3
Reinforcement per kg, ton
Formwork/ falsework per m2
An integrated, fixed, price for 1 cubic meter of concrete for universal applications
doesn’t exist. As will be explained in this chapter, the cost components as
mentioned above are significantly influenced by project specific (local) conditions
and conceptual choices made by engineers.
Nevertheless integrated, overall prices for 1 cubic meter of concrete are sometimes
used as a working tool to judge alternatives: overall project cost is divided by the
total volume of concrete of the scheme. In that case also cost for equipment
(pontoons, lifting equipment) and special provisions (dry dock) are included.
Within such context the overall price per cubic meter can be a useful indicator to
identify trends and to support the selection of alternatives.
To further investigate and clarify cost drivers for reinforced, cast in place, concrete,
focus will be given to each of the 3 main components given above. As formwork
could result in a substantial variation in cost per cubic meter of concrete, first
material cost of concrete and the effect of reinforcement will be discussed. After
that, formwork will be discussed separately.
Basic components of cost for concrete (material), reinforcement and some
formwork principles are as follows:
Concrete:
• Materials: cement, sand, gravel and water; quantities based on the
mix design.
• Batching plant: depreciation, maintenance and interest.
• Transport: dependent of distance
• Man-hour demand: dependent of dimensions, shape and complexity.
• Cost for concrete only may vary a factor 2-3.
Reinforcement:
• Procurement of steel: market effect and dependent of distance.
• Cutting/ bending and placement, fixing: dependent of diameter and
shape.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 33 of 199
Construction Technology of Civil Engineering Projects
In the Netherlands large volumes of gravel and sand are available at relatively short
distances: the large rivers have transported these materials in the past from the
mountains to the Low Lands.
Therefore, variations in cost for transportation will be small. Abroad, the situation
can be significantly different. Transportation cost may vary considerably, pending
location of quarries for rock, dredging areas for gravel and/ or sand and the
available infrastructure for transportation.
The effect is illustrated by multiplying the cost for transportation (sand and gravel)
as listed in the nominal case above by a factor of 10.
Increased cost for transportation of sand and gravel: 10 times nominal cost
Material cost: (typical 1:2:4 mix)
Cement: 320 kg/m3 @ € 80 / ton € 25,60
Sand: 605 kg/m3 @ € 150/ ton € 91,00
Gravel 1350 kg/m3 @ € 170/ ton € 230,00
Water 125 kg/m3 @ € 0,55 / ton € 0,10
Total cost of 1 m3 of material € 346,70
Batching plant
Depreciation, maintenance, interest,
transportation from plant to site/ m3 € 48,00
Casting at site 1mh @ € 38,00 € 38,00
1 m3 of concrete in place € 432,70
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 35 of 199
Construction Technology of Civil Engineering Projects
The choice of bar diameter is influenced by quite some considerations: crack width
control, spacing between bars, cover and diameter dependant cost per ton.
The effect of diameter on cost is illustrated as follows:
Diameter in mm Material in Transport, Bending Cost in €/ kg
€ / ton Cutting, placing Mh/ ton
Mh/ ton
10 840 29 5 2,13
12 810 20 3 1,65
≥ 16 790 13 2 1,36
The structural engineer should make a balanced choice taking into account the
considerations mentioned above.
consequences for formwork and false work, dimensions of the section and the
consequence on reinforcement, choice to apply prestressing, reinforcement or a
combination, in-situ construction and/ or prefabrication etc.
All variables have an impact on cost. Apart from the cost of concrete, cost of the
overall scheme are also influenced by cost of foundations, earth works, dewatering,
temporary sheet piles etc.
As an example: a massive plate structure is a simple structure to construct and
could be cheaper compared to the cost of a box girder. But the box girder
alternative will result in less dead weight which will lead to less foundation piles.
Furthermore (and as will be discussed later in chapter 5, design considerations) it is
not just the cost that will (completely) govern the choice between alternatives:
Complexity of a concept will be an important consideration as well as it has an
impact on the (financial) risk exposure.
From an owner’s perspective, additional considerations may be applicable:
sustainability and redundancy.
Sustainability is closely linked to environmental care: What is the ‘burden’
of materials, their maintenance over the life cycle, construction methods and
dismantling on the environment? Awareness, vision and view points,
supported by legislation, are tools to make a judgment.
In these lecture notes, costs of the concrete structure itself are subject of discussion,
not the issues additionally mentioned above.
Through a number of examples the interaction between design and cost will be
clarified. It should be mentioned that cost as given are indicative and for
clarification only!
To support the development of alternatives it is advised to visualize the relation
between (relative) cost and a scheme parameter such as height of a section, profile
etc. This will result in a graph as given in fig. 3.6
The design engineer is not bound to select the parameter value leading to the lowest
cost: there is a validity area around the minimum where selection of the parameter
may also be influenced by other considerations as discussed above.
In the next examples the interaction between design and cost will be addressed,
specifically the relation between construction height and cost.
concrete +
reinforcement
concrete 8000 8000
Notes:
In the graph the influence of formwork is excluded
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 39 of 199
Construction Technology of Civil Engineering Projects
For slabs with a thickness less than 550 mm, the compression zone is not able
to take the shear force. Costs for these consequences (stirrups, corbels) have
not been allowed for.
For the given rates, cost for concrete appear to be dominant; based on the
strategy to have the reinforcement in yielding for the ULS, the minimum
acceptable construction height is 360 mm. a further reduction would require
compression reinforcement, which would lead to a significant increase in cost.
Notes:
As was the case for the culvert of example 1, also for the floor beam it appears
that for the rates as assumed, the most economical height equals the minimum
height according the strength calculations for the floor slab. The cost of
concrete are less dominant compared to the culvert. The cost for form/ false
work strongly reduces for smaller construction heights of the floor beam.
For smaller construction heights, the floor beam concept will gradually change
into a massive slab system. Such system will generally be more economical
because of the simplicity of formwork, despite the higher material demand of
concrete. The floor slab system on the other hand will lead to less dead weight
of the building, resulting into a cheaper foundation. Total height of the
building however will increase if floor beams are applied.
Massive slabs would require special attention in terms of punching shear
capacity and stability issues.
Highly reinforced beams may cause problems at intersections with other
beams and columns. If not properly addressed in design, these intersections
will be difficult/ impossible to execute and may lead to improvisations at site.
This may result in non conformities. It is therefore recommended to select,
within the validity area OV, the beam height with the lowest reinforcement
ratio. Typical main reinforcement ratios for beams are 0.8-1.0%, for slabs with
loads of 3-4 kN/m2 , 0.4-0.7% in each direction. For these small loads,
deformation will normally be governing, and the height follows from the
deformation criteria.
A typical detail at bridges and viaducts is the finishing at the edge beam. To align
the edge of the bridge and also to hide transverse prestressing anchorages, an edge
beam is frequently applied, see fig 3.10. The finishing can vary from a cast-in-situ
beam to a prefabricated beam in architectural concrete. In a study to investigate the
influence from formwork on design and execution, 3 solutions for the edge beam
have been considered (see below).
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 41 of 199
Construction Technology of Civil Engineering Projects
Edge
beam
with tie
bars
A second option to construct the finishing is to use prefabricated panels and apply
cast-in-situ connections. The connection is only cast after final positioning of the
panel. This option is normally considered if hand railing anchors have to be
provided near the edge of the structure. A specific point of attention is the fact that
the panel is installed and positioned at the cantilevered part of the deck structure.
The vertical part of the formwork for the connection is anchored to the deck by
cast-in anchor bolts or driven nails.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 43 of 199
Construction Technology of Civil Engineering Projects
4.1 Introduction
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 45 of 199
Construction Technology of Civil Engineering Projects
(further referred to as D/C): the development of the concept and actual execution of
the scheme are both with one party. D/C gives the opportunity to achieve a most
economical solution by full integration, through interaction, of the design and
construction disciplines. A further expansion of D/C is the Design/ Build/ Operate
and Transfer type contract (DBOT) where also maintenance and operations are part
of the scope of contract. In such case, maintenance aspects should also be
considered to achieve the optimum. In case of D/C or DBOT, the focus should be
on exploring the opportunities arising from interaction between disciplines
involved. As such it is about an integral, multidisciplinary, process to be performed
and managed. And the integration, even for D/C, is more than just adding the
disciplines together:
D/C ≠ D+C
This section will present some basic principles of the optimization through
interaction, with focus on the role of engineers, from a process perspective. To link
the principles to practice, the Design/ Construct case will be used as a reference.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 47 of 199
Construction Technology of Civil Engineering Projects
To structure the design process during the tender phase (development phase)
engineers should realize the level of specification of the scheme. To submit a bid, a
scheme must be specified to such a level as required to calculate cost to a set
accuracy. The gap between the level of specification of the Invitation to Bid and the
required level of specification to submit a tender is a clear indicator of the extent
and intensity of the process to be performed during the tender phase of the project.
The level of specification can be very low: a typical example would be a traffic
capacity between A and B, full stop. This position is indicated as Type 1 in fig. 4.5.
The specification could be very high as well: the concept is given with main
dimensions, typical details and main quantities can be concluded from the
documents or calculated with relative minor efforts. This is indicated as Type 3 in
fig. 4.5
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 49 of 199
Construction Technology of Civil Engineering Projects
• The linear process will contain optimizations. The challenge is to reduce the
degrees of freedom and to create a higher level of specification as soon as
justified. In practical terms this means that choices should be made as soon
as justified. This is represented by the green line in fig 4.9. A dangerous trap
in practice is the strong drive to realize optimizations in combination with an
overoptimistic perception of the feasibility/ reliability of optimizations: if the
governing time schedule forces to make a choice, the choice should be made
and activities to be continued as planned. Such a moment in time is often
referred to as a freeze. Consequences of not respecting the freeze (indicated
in red in fig. 4.9) may have a substantial impact on management of time and
budget. It requires a strong discipline to adhere to the principles above, but at
the same time, adherence is generally concluded as a critical success factor.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 51 of 199
Construction Technology of Civil Engineering Projects
The boundary of a cluster (and as such the interface) is taken at the positions where
minimum interaction will occur: the clusters are reasonable self supporting and will
generally be multidisciplinary. A typical example of cluster approach is the team
organization for the storm surge barrier Ramspol in the Netherlands: (See fig 4.11)
The organization contained 4 clusters: The (nylon reinforced) rubber sheet, the
piled foundation and sill, the control room (as a whole) and the river training
works. Each of the clusters definitely has relations with the others, but the
interaction at these interfaces was relatively low. Each cluster was multidisci-
plinary, both from an engineering point of view (interaction between the various
engineering disciplines) as well as within the civil discipline as a whole (where
design, cost estimation, work preparation and execution were all present in each of
the relevant clusters).
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 53 of 199
Construction Technology of Civil Engineering Projects
The loading arms and other topsides are decisive input aspects for the deck design,
but are long lead projects in themselves. To delay the start of the deck design till
engineered data of the loading arms would be available, is generally not acceptable
in terms of overall running time of design, procurement, construction and
commissioning. The application of the System Engineering principles consists of
the assessment of space requirements and envelopes of the loadings (H, V, and M)
at an early stage. Not the exact values, but minimum/ maximum ranges. The space
requirements and envelopes are used for the design of the deck (and foundation).
Upon completion of topsides design and deck design, both clusters are brought
together and, if properly fixed in the beginning, will match. Upon availability of the
detailed design results of the topsides, generally, no redesign of the deck will be
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 55 of 199
Construction Technology of Civil Engineering Projects
performed as the overall schedule will commonly not allow redesign. As such sub-
optimizations with focus on minimum material demand are given up in favor of the
overall optimization (commonly minimization of time). On a growing number of
(large scale) civil engineering projects, System Engineering principles are applied
as a tool to demonstrate compliance with requirements through a structured and
standardized approach with a strong focus on validation and verification.
A key-aspect of Systems Engineering, within the context of validation and
verification, is the explicit way of recording information. This will result in a
transparent process, which is a critical success factor to manage large scale
(infrastructural) projects: Due to their scale, a great number of interfaces, both
internal and external, will occur. A high level information management approach is
of the essence to avoid non-conformities and consequential cost. Systems
Engineering provides the necessary integrated and structured methodologies. Core
elements of the approach (according ISO/IEC 15288:2002: Systems engineering-
System life cycle processes) can be summarized as follows :
• Stakeholders Requirement Definition Process
• Requirement Analysis Process
• Design Process
• Implementation Process
• Operation and Maintenance Process
• Verification and Validation Process
• System Management over the Service Life
As such, Systems Engineering provides tools to apply Life Cycle Management in
each of the phases of the Service Life.
Important aspects of System engineering are:
• The distinction between the specification process and design process
to optimize transparency: starting point of the processes is the project
problem definition. A typical example could be: a road transport capacity
between A and B must be C. The solution of the problem is the project
objective. System Engineering describes two processes right from the start:
the specification process and the design process which should be
requirements driven. Both start at the problem definition and run parallel in
cycles of increasing level of detail to such an extent that the execution phase
may follow. At such level both processes merge.
level of development) and to validate whether the design, again at each level
of development, satisfies the requirements of the stakeholder (Client). During
the execution of the project, components are realized and built together to
form the scheme. Also during this stage there is a continuous process of
verification (compliance with design) and validation (satisfaction of stake
holder’s requirements).
Fig. 4.14 Key aspects of Systems Engineering (image courtesy of Prorail and
Dutch Ministry of Transport and Public Works)
In addition, System Engineering also comprises the Work Breakdown Structure and
can be expanded with additional Breakdown Structures as appropriate, although
limitation of Breakdown Structures is strongly recommended to limit interactions.
Also a balance should be found between the level of decomposition and the number
of interfaces as all the breakdown structures are based on the top-down
decomposition of systems. Data bases are generally applied to identify and manage
relations between the various Break Down Structures.
Which approach is selected depends on a first judgment of the Invitation to Bid: if,
from a first judgment, a most likely solution can be concluded, the Base Case
approach is adopted. If there is no likely solution, a number of alternatives must be
considered and the Variants approach is selected.
In fig 4.14 acceptable alternatives are those initiated in the green area (variants 1
and 2). The red dots indicate alternatives which would result in a too short period
for development to the required level of specification, or would result in a lack of
manpower.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 59 of 199
Construction Technology of Civil Engineering Projects
The Variant approach is selected in case it is not clear which concept would be the
most likely. As such a number of alternatives will be considered. Although the
same principles as described for the Base Case apply with relation to Time and
Manpower constraints, the variant approach contains a third vital principle: the
design freeze: generally it is not possible to develop all alternatives because of
constraints. In such case a choice shall be made. And the choice shall be made
within the green zone of fig 4.16.: there should be enough time available to further
develop the selected alternative(s). The principle of design freeze appears to be a
difficult, although vital, aspect to be applied. If not properly applied, it will
endanger the reliability of alternatives because of a lack of specification. Under
such circumstances it often appears that the perception of engineers with regard to
the actual level of specification is too optimistic.
• Risk Inventory Lists: the use of Risk Inventory Lists makes the analysis more
project-specific. All disciplines concerned will develop the RIL. The
development of a RIL appears to be a powerful tool to focus on risks, to
improve awareness and to get an overview of exposures. Such overview is a
pre-requisite to allow management of risks.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 61 of 199
Construction Technology of Civil Engineering Projects
• Risk Inventory List together with Monte Carlo simulations. This approach is
selected for schemes which are considered to be exposed to substantial risks.
Both size and characteristics of the project should be considered to conclude
if this type of analysis is required. Large Design/ Construct projects or
smaller projects but with multi disciplines are generally subjected to this type
of analysis.
The reliability of the analysis is governed by the reliability of the input parameters.
The reliability of input parameters will be improved if statistical data are used. This
however requires a data bank which is gradually filled with data from practice. To
make risk management happen, such data bank is a pre-requisite. The development
of a data bank does require an effective feed back loop from actual construction to
the engineering disciplines. In (temporary) lack of a data bank expert opinions can
be asked to select mean and standard deviation values for the input parameters. It is
advised to base the input parameters on the advice of more than one expert only.
Once the exposure of risks is assessed, actual management can start. Basically there
are three options: eliminate, insure or accept. Which option is selected depends on
the actual risk and the consequences if the risk actually would occur, acceptance
thereof, whether insurance cover can be arranged etc.
Apart from reliability of the concept considered, the efforts during the tender
should result in the optimum solution for the case considered. This is frequently
referred to as MEAT (Most Economically Attractive Tender). The assessment is
based on a wide variety of value-issues: integral cost, time schedule, environmental
impact in the broadest context, sustainability, flexibility, etc.). The tender process
should develop into the MEAT. As the design process is the transformation from
freedom into specification, very many decisions will be required. This means that
many switches will have to be set, resulting into the right solution. Decomposition
as such is not a guarantee that the right decisions will be made. To support the
decision-making process, trade-off matrixes are frequently used. All relevant
aspects are listed and rated for the alternatives concerned. And again, this does
require substantial experience as statements have to be generated with limited
information and level of detail only. This is where the process does require due
attention: the margin of the supporting system should be in balance with the real
differences and margins of the option to be judged. If not, the best solution could be
shaded- away by the inaccuracy of the supporting tools.
stage. An initial version of the schedule must be made during the tender phase of
the project, prior to making commitments/ submitting a tender. A violation of this
principle may lead to unbalanced time consumption or constraints which, in turn,
will obstruct proper management, both in terms of financial, quality and time
management. The integrated planning should incorporate the principles of
concurrent engineering as earlier described.
• Value engineering should incorporate total, integral cost. In practice this often
appears to be complicated. As an example: uniform reinforcement diameters
and reinforcement patterns (not necessarily lowest material consumption)
versus savings due to efficiency.
• Top XX list: from the analysis a shortlist of risks is compiled. The list will
consist of those risks which represent a dominant part of the overall
exposure. The advantage of the shortlist is the fact that attention can be
specially focused.
• Update of the Risk Dossier: during detailed design and actual execution of
the works the insight in risks may change or events are completed without
actual occurrence of the risk. Updating the file keeps attention focused.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 65 of 199
Construction Technology of Civil Engineering Projects
• Kick-off meetings should be organized for all the phases of the project and
all disciplines involved should participate.
• Reviews should be organized with regards to engineering, cost estimation
and contractual/ commercial aspects with due attention to boundary
conditions.
• The contractual review and negotiations should be assisted/ supported by the
design discipline(s).
• An integrated planning is a must: all disciplines should be considered as
equal.
• Choices should be made according to the planning schedule. Apply design
freezes to allow proper phasing of the process.
• There should be a limited authorization to apply changes to the design. A
clear structure of authorizations is required.
• Approval procedures should be clear and should not be open ended.
• Interaction/ communication between all disciplines involved is a critical
success factor.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 67 of 199
Construction Technology of Civil Engineering Projects
5 DESIGN CONSIDERATIONS
5.1 Introduction
Civil engineering structures must have a high degree of effectivity with regard to
functional requirements and boundary conditions.
At the same time, it can be decisive that concepts are efficient, that actual execution
(and maintenance if applicable) doesn’t become too expensive. To develop a
concept that meets all functional requirements/ boundary conditions and at the
same time is an economical solution, a methodology should be followed during the
conceptual phase. This methodology should also prevent that in a later stage
surprises would occur in relation to structural performance and in economy of the
scheme (cost/ construction time/ maintenance requirements). This chapter of the
lecture notes presents such methodology.
In the western world, savings on manpower cost are more effective compared to
savings on materials, due to the development of cost (over the years) for materials
and manpower. Formwork and false work are important elements to consider as
they present a substantial part of the cost of the concrete structure. Through
rationalization and mechanization it has been possible to cope with the challenge to
be more man-hour efficient.
The methodology presented is based on the use of five design considerations to be
used:
• Shape of the structure and sections.
• Repetition: with focus on investments for formwork/ false work.
• Repetition: with focus on man-hour efficiency through learning effects.
• Planning: number of critical paths and intensity of interactions between
activities.
• Detailing: tolerances, finishing, striking of formwork.
5.2 Methodology
Chapter 2, interaction in design, extensively discussed the vital impact of
interaction in conceptual design. Also for the further development of alternatives,
interaction is vital again. The interaction is on one hand between sketches of the
structure/ dimensions and structural performance, on the other hand between these
sketches/ dimensions and execution.
Functional requirements
Boundary conditions compliance
Reliability/ Economy
Compliance Reliability
Constructability
Aspects Aspects
See section 5.3 See section 5.4
Minimum/ maximum
Preferred dimensions
dimensions
Variants
See section 5.5
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 69 of 199
Construction Technology of Civil Engineering Projects
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 71 of 199
Construction Technology of Civil Engineering Projects
Uncertainties do occur in the field of loads, static schemes and SLS aspects to be
addressed:
• Loads: loads are more frequently measured and documented than before. As
such an increasing knowledge is being build up to allow a statistical approach of
loads. Especially in the field of rail and road infrastructures, loads are rather
reliable. Also water pressures can reliably be calculated as water levels of rivers,
lakes and seas have been monitored over decades. The same applies for wind
loads as also wind data have been recorded over long periods of time. But
general loads, frequently applied as uniform distributed loads, have an
uncertainty. But can be governing at the same time. Care should be given to
these loads and validity for the case considered should be checked carefully.
• Static schemes: static schemes are reliable most of the time. But especially at
structural interfaces and at the soil- structure interface a careful consideration is
required. A typical example is the simplification, frequently applied, of the soil-
structure interface where the horizontal resistance/ deformation of the soil is
modeled by a set of independent, non- linear springs. From an interaction
between loads, structural stiffness and the spring characteristics, an equilibrium
results. But the springs have no interaction directly between themselves:
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0-November 2018
Prof. Ir. A .Q.C. van der Horst Page 72 of 199
Construction Technology of Civil Engineering Projects
For all stages (including construction stages) following aspects, either SLS or ULS,
must be checked:
• Strength/ Safety
Static schemes may change during construction: All steps of construction must
be followed on their consequences for the static scheme. If the method of
execution is not yet final, at least one, most likely, method should be taken and
checked. Such assumption must be documented for following design stages.
A typical example of a changing static scheme, is the use of prefab slabs in
deck structures: to optimize the use of man hours at site and to optimize cost for
formwork/ false work, it is quite common to apply prefabricated slabs at each
span and to provide an in-situ top layer afterwards. The static scheme changes
from a simply supported slab into a multiple span, continuous slab.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 73 of 199
Construction Technology of Civil Engineering Projects
Also the shape of cross sections may change during construction. A typical
example is the use of prefabricated U shaped beams which will, in a later stage,
be filled and connected to other components. Also fatigue aspects may be
decisive during construction: steel foundation piles in open waters may have
fatigue problems due the small wind waves during the construction stage where
the piles are standing as cantilevered beams. This condition may typically occur
from water depths above around 10 meters. The problem can easily be solved
by the application of a temporary brace between the piles.
Strength consequences should be checked for all stages.
• Stiffness
Changes in cross-sections and static schemes during construction may have a
significant impact due to stiffness related consequences and must be checked,
apart from the usual checks of the completed structure with regard to water
accumulation, vibrations, dynamic response and second order effects.
Also the soil-structure interaction must be checked: the subsoil response may
lead to an accumulation of deformations during construction with an impact on
the completed scheme, or measures to be taken during construction. A typical
example in this category is the concept of block walls as discussed in chapter 2.
If substantial deformations are likely to occur, predictions should be made on
beforehand and carefully compared to data collected from the structure during
construction. If non-conformities are noted, an analysis must be performed to
clarify the differences and conclude whether additional measures are required.
• Stability
Stability of members and the structure as a whole must be checked for stability
during all stages of realization. Stability aspects include horizontal/ vertical/
rotational stability, (local) buckling stability, overturning stability, sliding
stability, slip circle stability, up-lift stability and the bearing capacity of the
subsoil.
• Durability
A vital performance aspect is durability. The durability performance of a
structure is governed by two key influence factors: design and execution. The
influence of the actual execution of the project has a significant impact on the
ultimate durability performance of the structure and will be discussed in chapter
6, dealing with Construction for Service life. Design however creates the
circumstances under which execution will take place.
Typical design issues are: mix design (both choice of materials and quantities
of materials), including water/cement ratio and density, and the concrete cover.
But also the design of reinforcement has an impact: if compaction of the fresh
concrete (or even worse: the flow of fresh concrete) is hindered by abnormal
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0-November 2018
Prof. Ir. A .Q.C. van der Horst Page 74 of 199
Construction Technology of Civil Engineering Projects
dense reinforcement, the quality of the cover will be adversely influenced and
as such durability will not meet the required standard. Alternatives must be
considered: change of design, mix design or compaction techniques.
• Geotechnical and foundation aspects
Structural performance will be influenced by geotechnical and foundation
aspects such as strength/ deformation of the subsoil/ foundation, ground water
table (and management/ feasibility of artificial tables during construction) and
the reliability of the soils information.
Special attention should be given to the ratio of horizontal versus vertical loads
during construction as that ratio has a major impact on the capacity of spread
foundations. The reliability of the soils information depends on the density of
the investigations, scope of the investigation program, quality of the
investigations and interpretation thereof and interface management between
geotechnical and structural engineers with emphasis on how parameters should
be applied in models. Also the need of additional investigations shall be
addressed: it is quite common that at early stages of scheme development only
limited information is available. But during development stages the reliability
of the soils information should increase in a balanced way with the anticipated
accuracy target of the budget forecast.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 75 of 199
Construction Technology of Civil Engineering Projects
construction method has a decisive impact. Once the construction method is agreed
and frozen, the Method Statement can be drafted, covering all stages of
construction to complete the scheme.
In Appendix B an example is given which presents the construction plan of a
bridge at Reunion. From the example the interaction between design and
construction method can easily be concluded. (Courtesy to Jean Muller
International- France)
Tremy pipe
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 77 of 199
Construction Technology of Civil Engineering Projects
The structural concrete space (S) will be the result of interaction between the
functional/ special requirements (H), ballast requirements (B), design and execution
considerations, and serviceability aspects. Once the initial selection is done, these
practical dimensions must be checked for the ULS/ SLS limit states, including the
construction stages, and reinforcement details. Reinforcement details follow from
ULS/ SLS considerations, execution considerations (minimum spacing between
reinforcement for casting, minimum spacing between prestressing anchors,
practical diameter- spacing requirements to allow workers to climb the
reinforcement cage (typically 16mm bars-spaced 150 mm.)), and the optimum in
cost. The selection of initial values and the checks thereafter is a cyclic process:
once consequences of choices become clear it should be considered whether
adjustments are required. For water depths exceeding 25 m, the usual dimensions
of S will, most likely, not be able to take the loads. An increase in S and B may
have an adverse effect on functional requirements (alignment) and will have effects
on cost because of an increased length of approaches and increased volumes of
dredging. The application of transversal prestressing has proven to be an adequate
solution in such case.
For shallow tunnels on the other hand, and specifically small span tunnels as in use
for underground public transport, the application of vertical tension piles or anchors
will optimize the H-B-S relation.
5.5 Variants
From the interaction between design aspects and execution considerations as
discussed in sections 5.3 and 5.4, variants/ alternatives can be developed. This
section will present a methodology to support the selection between the variants/
alternatives. The scheme of the methodology is as follows:
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 79 of 199
Construction Technology of Civil Engineering Projects
The main purpose of the presented approach is to get an impression of both the
project cost and the level of complexity.
Based on cost and complexity a choice between variants can be made.
5.5.1 Shape
Starting with the conceptual plan and shape, it should be considered:
• To apply simple, straight and plane shapes
• To avoid locally required modification to formwork
• To use standard sizes of plate material for formwork through smart
selection of structural dimensions
• To apply formwork units as big as can be handled, as this will reduce the
required man hours per m2
Through these measures cost for formwork, a significant factor in overall cost, will
be reduced.
An example of some of these principles is illustrated in fig 5.11:
For small retaining walls, simple and straight surfaces as given in variant a,
will lead to more economic concepts compared to variant b, where the
application of dents will have an adverse effect on cost for formwork.
5.5.2 Repetition
Repetition can have an effect through two mechanisms:
• Depreciation value of formwork and falsework
• Learning cycle of workforce
Different type of formwork (wood, steel, formwork systems), have different cost-
repetition graphs. As such the repetition factor may help to select the appropriate
formwork, or, alternatively, the graphs help to demonstrate the savings through
repetition.
It should be noted that repairs will create discontinuities in the cost-repetition
graph. As such this may influence the choice of formwork.
If construction time would require the use of more formwork units, this will
influence the repetition per unit and as such the cost per m2. This requires an
integral consideration of cost.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 81 of 199
Construction Technology of Civil Engineering Projects
The cost- repetition graph is not a single line graph: it is an area around an average
line. Where actual cost will be relative to the average cost, is influenced by
complexity of shapes, size of the areas etc. A typical graph is given in fig 5.13
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 83 of 199
Construction Technology of Civil Engineering Projects
In fig 5.14 a graph is presented which illustrates the relation between the man-hour
demand per element ( unit) and the repetition factor n in case of a one-off
production of n elements ( En) and the development of the average in case of
multiple series of n elements ( Dn) .
The average learning cycle effect can be described with following formula:
D 2n = ф D n
in which:
D 2n = man-hour demand per element (unit) at a production of 2n units
D n = man-hour demand per element (unit) at a production of n units
Ф = factor which indicates the learning effect.
considered: the disturbance of the repetition has cost effects which should be lower
than the actual savings from the changes considered. As such it is a proven
principle that in-depth work preparation with focus on the final scheme to be built
pays more than an attitude of early start and modifications during construction.
It can be concluded from both repetition influences (depreciation and learning cycle
effects), that repetition is a major factor to consider to obtain a rational (practical,
economical) design.
The network planning will allow an analysis of the execution process. Such a
process analysis is a tool to develop a most economical execution method, with
strong emphasis on formwork and falsework. From the network planning the
completion date of the project can be concluded. The completion data is an
essential milestone: it is a contract requirement with often a high commercial value
(toll infrastructures, production platforms in the oil and gas industry, sports
stadiums). Also time-dependent cost can be concluded from the planning.
For concrete structures, a straight forward planning can be achieved by:
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 85 of 199
Construction Technology of Civil Engineering Projects
If tension occurs between time required and the week cycle, technological
measures such as optimization of the mix design and heat treatment (with
influence on strength development) can be taken to save time.
5.5.4 Details
During the design process of civil engineering structures, there will be a
development from a global focus to a more detailed focus. It is a natural process to
channel attention from an integral view to details. To support the evaluation of
alternatives, details must be considered along with aspects of shape, repetition and
planning. Formwork and false work are major aspects to consider when detailing a
concept. Of all cost components, formwork and false work take a major part.
Through a rational design/ construction method, substantial savings can be
obtained. With respect to the repetition factor, location of casting joints and
working joints (with due respect to design considerations and planning aspects)
needs full attention as this is considered as a major detailing issue of design.
Formwork and false work should not be economical only: the system must be of
adequate quality. The quality could be judged upon the compliance of the
permanent structure with requirements related to appearance, finishing, dimensions
and durability.
Within the context of this lecture following detailing aspects will be addressed:
Tolerances
Finishing
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 87 of 199
Construction Technology of Civil Engineering Projects
Striking of formwork
Some typical examples of detailing aspects are as follows:
In Fig 5.17 two options are given for a retaining wall: a sloped top surface versus a
horizontal surface. To cast a sloped slab (slopes up to 20 degrees) will require more
man hours compared to a horizontal surface. Also post-casting treatment will
require more hours. The additional man hours should be judged against the saving
in material demand.
5.5.5 Tolerances.
Strict tolerances for concrete structures and/ or formwork will lead to an increase in
cost. It is easier and more cost- effective to anticipate on tolerances. A typical
example is the capping beam of a pile foundation: it is easier and more cost-
effective to widen the beam to allow for normal, practical driving tolerances, than
to impose tolerances which are smaller than can normally be achieved. This
principle is illustrated in fig. 5.8
As dimensional control of a concrete structure is influenced by temperature, rain,
wind, creep and shrinkage, design should allow for the variations in dimensions
and positions. Especially for bearings, handrails and at connections between
members, attention should be given to dimensional control aspects.
A typical example is given in fig. 5.19 : due to creep and shrinkage of a prestressed
viaduct, there could be a mismatch in positions of the cast-in anchors and the poles
of the steel handrails. Slotted holes in the base plate and joints in the concrete
structure will eliminate the effects.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 89 of 199
Construction Technology of Civil Engineering Projects
5.5.6 Finishing
Formwork material will have an impact on the appearance of a concrete structure.
A specific texture may be specified from a esthetical or functional perspective.
Apart from the formwork material itself, special units can be placed against the
inside the formwork to realize special texture effects. Finishing requirements
should be specific before actual execution: if written specifications would have
limited significance (especially for appearance), a visual catalog could be an
appropriate tool. A typical example of such catalog is the ‘schoon beton’ brochure
as issued by ENCI (The Netherlands).
5.5.7 Striking of formwork
In case of high repetition factors, special attention should be given to the shape of
the section to allow efficient removal of the formwork. This includes rounded
edges, bevels, inclined (tapered) surfaces etc. Also the use of debonding agents is
quite effective. Fig 5.20 illustrates how the shape of a cross-section has an impact
on the number of required activities to remove the formwork and on the risk to
damage the structure at early age.
6.1 Introduction
Construction for Service Life is an aspect of the broader theme Life Cycle
Management ( LCM).
Life Cycle Management is an approach to achieve:
Optimized integral cost over the full service life of a structure and optimized
performance in compliance with (functional) requirements.
The service life of a structure covers all stages from design, execution, maintenance
and repair up to and included demolition.
The optimization of integral cost implicates a balance between cost and added
value. As such there must be an unambiguous understanding between all involved
in the process, which added value must be generated. Most commonly this is
specified in functional requirements, project/ location specific additional
requirements and criteria. The optimization also implicates that all disciplines
involved (design, execution and maintenance/repair) should have an input in the
process to reach the optimum, avoiding sub-optimizations in any one of the
disciplines. It requires a re-thinking of the construction process compared to the
traditional approach where there is a more sequential order of participation of the
disciplines. Under Life Cycle Management there should be an integral approach. In
the integral approach, consequences of choices by anyone disciple on the scheme as
a whole should be carefully examined and must be balanced. A typical example
could be the choice of concrete cover: in anticipation on practical achievable
tolerances, it could make sense to apply an increase in cover to reduce future
maintenance and repair, especially for those sections where the relative decrease in
internal lever arm can (practically) be neglected.
and support the design and construction process: System Engineering approaches,
Risk Based Quality Management, databases and data communication, and
CADCAM techniques. And, maybe less pronounced and accessible, the stronger
focus on sustainability.
The nature of Life Cycle Management is quite different for the various types of
structures:
• The Service Life of buildings is dominated by aspects related to economic
life, refurbishment, and trends in society. The service life is relatively short.
The environment the structures are exposed to is generally mild
• The Service Life of Civil Engineering structures is dominated by aspects
related to compliance with quite specific and often unique/ complicated
functional requirements. The integral costs are generally optimized over a
relatively long service life. And the structures are generally exposed to a
severe environment. As such deterioration is a factor to be carefully
considered.
These lecture notes will focus on the construction phase of Civil Engineering
structures only.
The integral approach of LCM is, as explained before, not just an extrapolation of
the present development stages of a project. As it will require a rethinking of
approach, focus should be given to following factors (which have appeared to be
critical success factors):
• Identification of drivers with regard to direct and integral cost and critical
factors to performance
• Identification of the impact of these drivers and factors on cost and
performance: understanding the mechanism
• Development of tools to quantify effects
It is especially the understanding of causality, but with a reach over the full service
life and in an integral context, that will require full attention and appears to be a
difficult point in practice: what is the consequence in future of a certain choice and
does such choice contribute to optimal cost and optimum performance at the same
time? Where is the balance? Etc.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 93 of 199
Construction Technology of Civil Engineering Projects
It was Prof. de Sitter from the Netherlands who created awareness with regard to
causality in the building industry by development of what is called ‘de Sitter’s
Law’: (units are left out as they are immaterial)
Construction for Service Life is a shackle in the Life Cycle Management chain. As
such it is part of an overall process:
The proceeding phase is the design phase: starting principles and input data
are required: see section 6.3
The following phase is the maintenance and repair phase: output data should
be documented and handed over to the next phase: see section 6.5
6.3 Starting principles and input data for Construction for Service
Life
Construction for Service Life is an approach to contribute through the construction
phase to a proper Service Life Performance within the agreed framework of the
Contract and the Specifications
To reach the objectives of Construction for Service Life it is vital that:
All phases contribute in a balanced way to LCM and comply with the agreed terms
• As optimization of integral cost is an important aspect, each phase should
be focussed on optimizing integral cost more than striving for sub
optimization of the own phase concerned. This requires knowledge and
awareness of consequences of choices.
• Once the balanced contribution is specified, each phase must comply with
the terms. This requires knowledge and awareness of the consequences of
non conformities and application of control tools
All interfaces between the phases are effectively managed.
• At the start of each phase a set of documents from the previous phase must
be available to clearly specify starting points and terms to adhere to.
To allow Construction for Service Life, Design for Service Life should:
• Deliver the Life Cycle Management File, a file with all relevant
Engineering Documents, Engineering Instructions and Specifications, as
clear starting points for the actual Construction Phase and as a basis to
further develop the document into the Birth Certificate which will form the
basis for the operational phase of the service life
• Itself be based on clear definitions of the strategy to be followed: are LCM
principles applicable or not and what is the maintenance strategy? (regular,
scheduled maintenance versus maintenance free)
The New Guide to Good Practice, under preparation in Commission 10 of FIB, will
address some critical aspects and specific points of attention for construction such
as:
• Formwork and falsework
• Concrete
• Materials supply, mixing, placing and compaction
• Curing
• Finishing
• Cover
• Prestressing
• Precast concrete
• Foundations
• Reinforcement
• Piles, diaphragm walls, barrettes and slurry walls
• Tolerances
• Quality control
• Health and Safety
• Workmanship/ staff and labour
• Management of the Construction Process
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 95 of 199
Construction Technology of Civil Engineering Projects
Notwithstanding the broader theme, 4 critical factors (the four C’s) for construction
can be distinguished in general:
• Concrete mix
• Cover to reinforcement
• Compaction
• Curing of concrete
• Reinforcement corrosion:
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 97 of 199
Construction Technology of Civil Engineering Projects
• Concrete mix
• Alkali aggregate reaction (fig. 6.5)
• Sulfate attack
• Freeze-thaw (see fig 6.6)
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 99 of 199
Construction Technology of Civil Engineering Projects
• Cover to reinforcement:
Depth of the cover has, together with the quality of the cover, a decisive
impact on the durability of the structure.
National and Regional codes give guidelines for the cover depth in relation to
the class of exposure. It is vital that prior to the placing of concrete the cover
to reinforcement is secured by inspection and, if required, correction.
Although self-control is an accepted approach under ISO 9000, it is strongly
recommended to have random, second line inspections. It should be realized
by designers that the likelihood of conformity also depends on design and
reinforcement details: tolerances shall be regarded and dense reinforcement
details, especially in combination with large diameter reinforcement bars with
curved shapes, may lead to difficulties.
It should be realized that tolerances in cover will occur despite efforts. Fig 6.8
shows the results of 18000 measurements on a major scheme, executed under
ISO 9000 procedures. The spread in results is obvious as is the non-
conformity area (shaded area in fig 6.8). Anticipation is required: under LCM
approach, engineers should specify such value that the overall cost (initial and
for repair) is minimized. That requires an understanding of tolerances as
should be anticipated but also an understanding of the consequences of non-
conformities in terms of deterioration. Deterioration models are available and
will be discussed later. Under the traditional construct-only contracts,
contractor should just comply with the specifications.
• Compaction
Proper compaction is a critical success factor to obtain a reliable and durable
structure: Compaction will bring energy into the freshly poured concrete which
will lead to reduction of voids, increase in density and a good embedment of
reinforcement. Compaction is labour-intensive (it is an important component of
the cost to place concrete) and does require skills and good workmanship. It
requires training of people and a sense of responsibility. If performed poorly, it
may have quite significant effects: poor durability, segregation, loss of cover
etc. General guidelines are given in national codes and in section 7 on practical
construction of these lecture notes.
• Curing
The freshly placed concrete should be given circumstances to develop into good
quality concrete. A major factor is the undisturbed reaction between cement and
water. This process could be disturbed by a lack of water. That might occur by
evaporation. Preventing evaporation of water from the fresh concrete is called
curing. Curing can be done in various ways: a water film on top of the concrete
surface, water spay (which leads to a high relative humidity of the air
surrounding the concrete), membranes to cover the concrete and the application
of curing compounds. Curing compounds are sprayed on the concrete, form a
layer which will prevent evaporation and will often disappear after some time.
finishers in a later stage. Properties should be checked with the supplier of the
curing compound.
Although Construction for Service Life and LCM are still under development,
some tools have been developed/ are still under development:
• Deterioration
The objective of LCM is to comply with requirements, all over the service
life. This is schematically presented in fig 6.9.
Tools to quantify the deterioration process and also to quantify the effect of
parameter variation on deterioration and needs for maintenance and repair, are
still scarce. Duracrete is such a model, developed with funding from the
European Union by an international task force. The principle of the model is
given in fig 6.10.
Pf,T=P{R−S<0}T<Ptarget=Φ(−β), in which:
Pf,T, is the probability of failure of the structure within T; and T, the intended
service period.
The mathematical model for describing the event ‘failure’, i.e. passing a limit state,
comprises a load variable S and a resistance variable R. Failure occurs if the
resistance is smaller than the load. The probability of failure within the period of
time [0;T], Pf(T) is defined as the probability of the load not exceeding the
resistance within the given period:
The client or the owner of the structure should define the requirements for quality
in terms of performance requirements and target service life, apart from further
requirements which are generally given in building codes. It should be realized that
reinforcement corrosion is related to multiple limit states (see fig. 6.11). In general,
depassivation and cracking represent serviceability limit states related to durability;
spalling and collapse represent ultimate limit states. Spalling relates to both
durability and safety.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 103 of 199
Construction Technology of Civil Engineering Projects
7.1 Introduction
The execution process of civil engineering structures has quite an impact on the
overall construction cost, the quality of concrete as building material and the
durability-performance of the structure as a whole. Contrary to steel and wood,
execution (casting, compaction, hardening, curing and quality control) together
with the selected mix-design are decisive for the properties of concrete (density,
strength and stiffness) and assurance to conformity to specifications (cover).
The execution process has been influenced over the years by developments in the
construction industry:
•Large scale projects with a strong focus on repetition
• Strong increase in cost for labour relative to cost of materials
• Less skilled labour at site
• Fast construction schedules
• Focus on Quality Management and Process Control
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 105 of 199
Construction Technology of Civil Engineering Projects
As cost for formwork/ falsework is a substantial part of the overall cost for a
concrete civil engineering structure in concrete, rational use and further
development of formwork/ falsework should get a strong focus.
The typical one week cycle will have the casting operation on Friday to allow
hardening during the weekend and striking of formwork on Monday. It should be
realized that disturbance of the week cycle could have quite some consequences on
the planning as a whole. Disturbances should be avoided by proper work
preparation and the consequences of a disturbance should be minimized by counter
measures (overtime, weekend etc).
Pending the available construction time and anticipated cycle, the number of
formwork units can be concluded. The cycle required can be reduced by:
It is obvious that the lowest integral cost can only be achieved by a careful
examination of all cost components in their interaction with each other.
• Climbing formwork and slip forming for stability shafts in high rise
buildings, bridge piers, storage tanks and off-shore platforms.
Essential for the economic use of special types of formwork is the principle
of repetition. Repetition should be an important design consideration in the
choice of shapes, position and number of joints and in the planning of
construction phases. Long or high structures do allow repetition.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 107 of 199
Construction Technology of Civil Engineering Projects
7.2.1 Introduction
The development of cost for labour and materials has led to a strong drive to make
formwork and falsework as manhour-effective as possible. In practice a wide
variation in sophistication can be distinguished: from the traditional in-situ built
wooden formwork for a foundation slab (fig 7.1) to an optimized piece of
equipment to produce prestressed girders under factory conditions (fig 7.2) and
purpose made, mobile temporary structures to make complete units of a structure
(fig 7.3).
If a system as presented in fig. 7.5 is applied, less man-hours are required to build-
up the system and given the simplicity of the system, less skilled personnel is able
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 109 of 199
Construction Technology of Civil Engineering Projects
to do the job. The system has a high degree of flexibility as height and width can
easily be amended.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 111 of 199
Construction Technology of Civil Engineering Projects
• The actual formwork, in direct contact with the fresh concrete: this part of
the temporary structure has a decisive impact on the appearance and
finishing of the concrete. Requirements will generally be specified in the
contract documents.
• A supporting structure, part of the falsework, that takes the loads from the
fresh concrete and transfers the resultant loads to the next component:
• A mechanism to take or balance the resultant loads arising from the fresh
concrete and to stabilize the temporary structure as a whole: often internal
spacers (for geometrical control) are combined with ties (see fig. 7.7) which
balance the loads on both sides of the formwork. In addition, braces are
provided to assure stability against wind loads and horizontal impacts during
casting.
• Often a working platform is provided at the top of the falsework unit to
provide access for casting operations
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 113 of 199
Construction Technology of Civil Engineering Projects
with coatings. The system of wooden beams was replaced by trusses, both in wood
and steel, provided with adjusters for geometrical control. Due to the development
of trusses with an increased bearing capacity, the number of ties could be limited.
This reduction is significant in cost as the installation and removal of ties and
finishing repair of the concrete surface is a major cost component for formwork. A
further development was the introduction of an all steel formwork/ falsework
concept (fig 7.10).
The next step in optimization, closely linked to specialist suppliers, was the
development of universal, modular systems: standardized panels (fig 7.11) with
different dimensions which can be combined to project specific demands, provided
with stability provisions and access facilities (fig 7.12 and fig 7.13). As such
complete systems.
Fig 7.12 Panel system/ Access Fig 7.13 Panel system/ Stability
Further optimization has led to impressive, large sized elements (fig 7.14)
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 115 of 199
Construction Technology of Civil Engineering Projects
Fig 7.15 traditional wooden formwork (L) and steel formwork (R) with frame to
balance pressures from fresh concrete
Fig 7.16 panel system for columns Fig 7.17 ‘Spiralo’ system
use of temporary supports or not and the overall depth of the slab, the thickness of
the prefabricated slab will vary. The prefabricated slab contains all the bottom
reinforcement required and is provided with dowel reinforcement to provide proper
bond with the in-situ concrete layer.
7.2.6 Falsework
This section will specifically address falsework for civil engineering projects as
loads are generally higher compared to applications in the building industry.
Formwork of horizontal members is generally supported by a first layer of beams
which, in turn, are supported by a second layer of beams. Supporting struts will
transfer the loads to the subsoil through a proper foundation of spreader beams or
plates. In case of weak subsoil a piled foundation should be provided or a soil
improvement should be applied instead. The principle is illustrated in fig 7.19 as
typical example of a viaduct.
Apart from the steel supports, which introduce the loads in a concentrated way,
towers have been developed. The towers consist of standardized units which can be
coupled together (fig 7.21). The tower will introduce the loads in a more uniform
way. Typical capacities of the towers range from 200kN to 2000kN, although
project specific towers can be designed tailor made. The advantage of towers is that
the beams supporting the formwork are less heavily loaded compared to the case
where concentrated supports are used.
.
Supporting beams (in combination with steel supports or towers) are available in a
wide variety (fig 7.22): traditional beams, trusses, combinations of trusses, beams
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 119 of 199
Construction Technology of Civil Engineering Projects
and ties etc. The interaction between design and execution should lead to the
optimized approach. Given the large variation in dimensions, shapes and project
specific conditions which is typical for civil engineering projects, rationalization of
falsework is less developed if compared to the building industry and project/ site
specific conditions will generally lead to alternatives to be considered. This can be
illustrated by a typical example of falsework alternatives for a viaduct with a span
of 20 meters. For the case it is assumed that the space under the viaduct does not
impose a restriction for the development of falsework alternatives. The formwork
consists of plywood, 18 mm. thickness, supported by wooden profiles 63x160 mm.,
spaced 350 mm. The second layer of beams consists of steel profiles HEB 300. In
alternative 1 and 2 (fig 7.22), these steel profiles have 4 supports. In alternative 1,
of which a cross-section is given in fig 7.23, universal steel struts have been
applied. These struts directly support the secondary layer of HEB 300 profiles. To
provide stability in transversal direction, braces are provided. The struts are
supported by a pile foundation. Between piles and struts a capping beam is applied.
In the second alternative (fig 7.24), the foundation piles are extended to a higher
elevation. They directly support the secondary layer of HEB 300 profiles. Double
U-shaped steel profiles connect the piles and provide transversal stability.
Alternative 3 (see fig 7.25) consists of another concept for falsework: the
application of towers. The towers are applied as space frames, equally spread over
the area to be supported. The number of beams required as second layer (the HEB
300 beams) is strongly reduced. The second layer is supported by a third layer of
steel beams, running in the transversal direction and which is directly supported by
the towers. The vertical members of the towers have specially been designed to
directly receive the third layer of beams. Due to the reduced weight per unit to be
transferred to the subsoil, often a spread foundation with (prefabricated) concrete
slabs is adequate. A further optimization (to reduce weight) could be the
application of beams instead of a massive slab. But consequences on cost for
formwork should be considered before making the choice.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 121 of 199
Construction Technology of Civil Engineering Projects
the size of the units applied and/ or the use of prefabricated structural components.
In addition, special formwork and falsework could be considered.
Special formwork and falsework should be considered if functional requirements
and/ or boundary conditions do prevent the use of common practices or that
common practices would lead to a strong increase of construction cost. Examples
are the crossing of rivers and valleys, and the construction of structures with
considerable height: towers, silos, tanks etc.
In the application of special formwork and falsework, it is again the principle of
maximization of repetition that is of prime importance to optimize construction
cost. But also the interaction between structural design, formwork/ falsework
design and construction should get proper attention: often limitations (which may
come from any discipline involved) do apply and may dictate the direction of
development. But also opportunities will be given by the close interaction. As such,
special formwork and falsework is generally applied on a project basis (purpose
made approach) .
To maximize repetition, relative small formwork units are applied for special
formwork/ falsework applications. But a balance must be found (and as such
investigated) between the repetition ratio, planning schedule and the cost of
working joints and equipment utilization. The high repetition ratio is applied in
combination with one of the following construction technologies:
• A central production unit where, with a more or less fixed setup of formwork
units, elements are produced: a typical example is the incremental launching
technique where bridge-units are made near the abutment and horizontally
pushed (launched) in the longitudinal direction of the bridge. But also
prefabrication of components (which will be assembled with special
techniques afterwards) at site.
• Mobile production units which travel as production proceeds. Typical
examples of this technique are climbing formwork and slipforming for
concepts with significant height, travelers for bridges (to construct complete
spans in situ or to allow incremental, cantilevered, in situ construction).
Given the specific aspects of mobile production units, following sections will
address these units. A distinction s made between vertical and horizontal travelling.
storage tanks, caissons and gravity based offshore structures (GBS). The
background/ trigger of the application is the fact that (for the examples given)
functional requirements do not allow the use/ application of intermediate horizontal
floors at regular intervals. These floors are commonly used (in traditional
construction) to support traditional formwork for walls. For climbing and
slipforming, the section just cast must provide the required support. Modern
systems of climbing and slipforming can even handle non-prismatic elements
(changing section over the height of the structure). Traditionally, box-outs and
connections with horizontal structural components are not a problem: box-outs are
made with an anchorbox or a wooden insert at the position required as follows (fig
7.26):
In fig 7.26 left, a rigid structural connection is shown, realized by the application of
a widely available anchor box: a metallic box, properly anchored in the vertical
wall, provided with a (vertical) cover. In the box reinforcement is provided. This
reinforcement will be bent after casting the concrete and removal of the cover.
In fig 7.26 right, a simple free support is made by using traditional wooden box-
outs.
The slipform system (see fig. 7.27) consists of a relative small wall section:
typically 1.20 meter high. The section moves continually during casting. Movement
is realized by hydraulic jacks, which are supported by climbing rods of 25 mm.
diameter. The climbing rods are extended by units of 3 meters. The rods are
supported by the concrete previously cast and placed in a circular box-out with a
diameter of 60mm. The inner and outer formwork are connected to each other by
external frames. These frames, at regular intervals, balance the concrete pressure on
the formwork and also provide the support of the system at the hydraulic jacks.
Generally two decks are applied: the main deck and the lower deck.
At the main deck all preparation works and casting operations take place: box-outs,
inserts, reinforcement , casting etc. At the lower deck the main activities are
checking, repair and bending of reinforcement at future connections. Common
travel performance is 4-6 meters per 24 hours at steps of 2.5- 5 cm. The steps have
a relation with the strength of the concrete leaving the formwork as this concrete is
loaded in compression by the self-weight, but in tension by the friction effects of
the formwork.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 125 of 199
Construction Technology of Civil Engineering Projects
As the slipform operation is a continuous process, well organized and proper work
preparation / execution is a must as supply of concrete, placement/ fixing of
reinforcement, placement of inserts and box-outs and finally placement of concrete
should be a continuous, uninterrupted process. This also requires labour to work in
shifts around the clock, including weekends. Especially in built-up areas this might
be problematic given inconvenience to the public as well as potential problems
with logistics. This aspect was one of the triggers why climbing formwork gained
popularity over the last decades.
In its simplest form, a climbing formwork/ falsework system (see fig. 7.28 a)
consists of two units, of which one is placed on top of the other by a (tower) crane.
Modern systems however, have climbing brackets and as such avoid the inefficient
use of the double panel (see fig 7.28 b). The unit is temporarily anchored to
previously cast concrete. This is commonly done at the ties. A even more
sophisticated system is the self climbing formwork unit (see fig 7.29): the unit is
self-supporting, cranage is not required and also the full height of the unit is
utilized for the casting operation. The traveling speed depends on the applied cycle:
the commonly applied height of 3- 3.5 meters and a cycle of one week would result
in a traveling speed (on average) of 0.5 meters a day.
The choice between both systems is commonly made by cost. But, as explained
before, other consideration may influence that choice: inconvenience to others,
logistics etc. In addition, design considerations may have a decisive influence as
well: climbing formwork will always need ties through the section and will always
have casting joints. Slipforming is a continuous process without casting joints. If
casting joints and ties are not preferred (nuclear power plants, liquid tight structures
etc), slipforming will be the preferred alternative. From practice it can be
concluded that (from an economical point of view) slipforming is preferred above
20 meters height.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 127 of 199
Construction Technology of Civil Engineering Projects
7.3 Concrete
Check whether formwork meets specifications, has the required quality and has no
defects:
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 129 of 199
Construction Technology of Civil Engineering Projects
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 131 of 199
Construction Technology of Civil Engineering Projects
Phase 5, Curing
Curing is essential to assure optimum hardening conditions. Optimum hardening
will result in optimum strength development and durability (see also section 6.4).
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 133 of 199
Construction Technology of Civil Engineering Projects
The casting procedure of concrete will influence the quality of the hardened
concrete. Apart from the quality of concrete also the cost of execution will be
influenced the casting procedure. Important factors to consider are casting
frequency and casting volume. To obtain a good quality concrete it is essential to
have the right mix design. The mix design will generally consist of following
components:
• Cement
• Sand
• Gravel/ coarse aggregates
• Water
• Additives: to retard, to plasticize, to form air bubbles, etc.
The composition (mix design) depends on the casting conditions and procedures,
environmental conditions and the concrete dimensions.
Apart from the mix design in terms of weight-relations, it is also the type of
cement that is an important factor. Under adverse conditions like the marine
environment or when larger volumes must be cast, blast furnace cement has a
preference above Portland cement (because of resistance and low heat
development).
After the components have been selected and the weighting procedure has been
completed, the mixing procedure may start.
Components will be mixed in a batching plant (fig 7.30). The supply of water
should be done carefully and must be monitored. In many countries concrete is
delivered through commercially operated, centralized batching plants. The
advantage of these centralized batching plants is that storage at site is avoided and
that quality control/ assurance is easier to implement and to manage. Site specific
batching plants are to be considered for remote sites and/ or very large volumes of
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 135 of 199
Construction Technology of Civil Engineering Projects
Apart from wheelbarrows, which will be applied for small volumes only, each
mode of transportation has its field of application. Some of the transportation
modes do require a specific consistency of the fresh concrete: conveyor belts need
a more stiff consistency; concrete pumps a more plastic consistency. Truck mixer
plus gutter are frequently applied if the actual casting level is below the level of
delivery: basements and foundations.
Concrete pumps can handle big volumes of concrete if the supply of fresh concrete
is secured. The capacity of the pumps is governed by the number of bends in the
Fig 7.33 Typical envelope of motor pump unit and typical picture of the unit
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 137 of 199
Construction Technology of Civil Engineering Projects
line and the pumping height. Modern mobile motor pump units are sophisticated
pieces of equipment. Provided with swivels, the sections can rapidly cover quite an
envelope (fig. 7.33), and labour intensive laying of the pipe sections is avoided.
The flexible hose at the end of the line also allows casting of walls and columns
without the risk of segregation. If the free falling height would be more than 1.5-2
meters, tremie pipes should be used to avoid segregation. Formwork could also be
provided with openings at different heights to allow a significant reduction in the
free falling height. In case of walls, special care should be given if a high casting
capacity is practiced: The rise of the fresh concrete level could easily exceed the
design assumption and consequential pressures could lead to collapse of formwork/
falsework.
Conveyor belts could be interesting for stretched units (locks and quay walls).
Cable ways are typically used for large volume schemes such as dams.
Durability of structural concrete not only depends on the correct mix design and
thickness of the cover, but also on the density of the cover. During the casting of
concrete, air will be trapped in the fresh concrete. This will lead to voids in the
concrete and also between concrete and formwork. The consistency as commonly
applied will not allow a release of the air by gravitation only: the internal friction
prevents self-compaction (with the exception of Self Compacting Concrete). The
internal friction can temporarily be reduced by the introduction of vibrations. This
can be done with the traditional internal vibrators (commonly used for compaction
at site) but also with formwork-vibrators, vibrator-beams (for horizontal surfaces
with limited depth only) and vibrator-tables (mainly applied in the prefab industry).
As the fresh concrete consists of components with different volumetric mass, a
lowering of the internal friction may lead to segregation: the heavy components
(gravel) will sink rapidly, the light particles tend to follow later. Compaction
should allow air to escape but shall avoid segregation: it is a delicate balance which
requires skill and experience.
The traditional internal vibrators are available in different diameters and as such
different capacities in terms of energy. The influence zone of a vibrator depends on
the consistency of the fresh concrete, vibration time and capacity. The stitch of the
vibration pattern depends on the influence zone. It is far better to apply shorter
vibration time and a smaller stitch than larger distances and longer vibration time.
To allow air to escape, fresh concrete layers should be limited to 300-400 mm. To
get a homogeneous structure, the vibrator should penetrate 100 mm. into the
previous (already compacted) layer (see fig 7.34). The vibrator should be lowered
into the fresh concrete by gravity only. As soon as the area around the vibrator gets
a glossy appearance, the vibrator should be lifted (to avoid segregation) in such a
way that the gap automatically fills. If a sloping casting front is applied, compac-
tion should start at the lowest position (see fig 7.35). Compaction is labour-
intensive and as such a substantial cost component. One worker can compact
between 3 and 12 m3 per hour, pending capacity of the vibrator.
Direct contact between vibrator and formwork must be avoided: the vibrator might
be damaged and if wooded formwork as applied, contact might damage the
formwork which will give a print in the finished surface.
Also direct contact with reinforcement must be avoided: if the reinforcement is
also embedded in concrete which is in the initial stage of hardening, contact
between the vibrator and reinforcement may destroy the bond. Also fixing wires
could fail under the acceleration with loss of geometrical control as a consequence.
After casting the concrete, optimal condition should be provided for the hardening
process. Reference is made to section 6, curing.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 139 of 199
Construction Technology of Civil Engineering Projects
8 UNDERWATER CONCRETE
8.1 Introduction
Underwater concrete has a wide variety of applications of which following two will
not be discussed within the context of this lecture:
• Injection method: first a gravel/ coarse material bed is placed under water
and levelled. Afterwards the bed is injected with a mortar.
Both methods may lead to concern with regard the quality of the completed
product:
• Level control of both the prepared bed and the top surface of the underwater
concrete is a point of attention:
The level and surface roughness of the prepared bed doesn’t depend on the
accuracy performance of equipment only, but also on water currents and mud
settlement.
The level of the top surface depends on the flow properties of the mix,
casting equipment and the operational circumstances.
The gradually increased requirements for quality and level control (the trigger of
this development will be discussed later), have led to quite a development/
improvement of casting equipment. Also concrete technology has contributed to a
better control of both quality and levels. The development of colloidal concrete has
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 141 of 199
Construction Technology of Civil Engineering Projects
led to mixes with outstanding flow properties and cohesion at the same time. Such
concrete has ideal properties for underwater applications as it will freely flow
around piles and reinforcement, will allow level control, and has no risk of
segregation. The cost of the required additives however is such that colloidal
concrete applications are limited to special cases and not for mass production. But
also the traditional, slightly modified, mixes have acceptable properties nowadays.
The gradually increased requirements for quality and level control do not just come
from economic considerations, but also from structural aspects arising from
functional requirements and applied dimensions of the underwater concrete slabs:
In the early stages of underwater concrete applications, mass concrete was applied:
thick layers which were not critical for the transfer of loads to the subsoil and the
underwater concrete counterbalanced the water pressure by dead-weight only.
Quality and geometry were of less importance. Presently, underwater concrete is
applied (generally as un-reinforced concrete) to form a foundation floor slab: the
floor is commonly cast between sheet piles to create, after emptying the water, a
dry environment to further construct a structure. Apart from the load transfer during
the service life, the underwater concrete floor slab also serves as a water barrier
during construction (advantage: no ground water lowering in the direct
environment of the site) and as a support (strut) for the sheet piles. The sheet piles
also serve as formwork for the underwater concrete slab. Vertical stability of the
system could be arranged through a massive slab by dead weight only, but is often
arranged through the application of tension piles together with a underwater
concrete slab with limited dimensions only.
The anchored system has proven to be an economic and reliable option. But the
anchored concept has consequences as well as it leads to a set of requirements:
water tightness because of the barrier functionality and strength to transfer the
upwards water pressures to the piles.
Also flow properties are important as the fresh concrete should be able to
completely surround the anchor piles as quite some shear force has to be transferred
from the slab to the piles.
• Apart from cover, also density of the placed concrete should be adequate to
provide the required durability: the consistency of the bedding layer (bed
surface) is of vital importance: soft deposits are dangerous as they can easily
lead to inclusions which will adversely affect the structural and durability
properties of the permanent structure.
As discussed before in this section, with the development from massive structures
to the structures with moderate dimensions, both level control and quality aspects
need further attention:
• Level control
• Tolerances: tolerances depend on equipment used and subsoil conditions:
• Top surface tolerances: 75 mm. for the Hopdobber and 150 mm. for
the Hydrovalve method (both methods will be discussed later)
• Bed tolerances (bottom tolerances): 150 mm. for sand and 250 mm.
for clay.
• Survey methods: methods to survey the excavation level, position of
reinforcement (if any), and top of cast concrete. Methods will be
discussed later.
• Quality of concrete
• Flow properties and avoidance of segregation: as the underwater
concrete can’t be compacted under water, good flow properties are required
to fill the space required, to flow around reinforcement (if any) and piles, to
fill the cavities of the sheet pile wall and to give a finished surface within
specifications. At the same time, segregation should be avoided. This mix of
requirements has led to typical mix designs with a big slump, high cement/
fines content and special placement techniques.
• The slump should be at least in the order of 140- 180 mm. For
Hopdobber and Hydrovalve applications, the minimum slump should
be 160 mm. In practice a slump of 200- 250 mm. is frequently used.
• To avoid segregation, fines and fillers (typically < 250 mm-3) are
required with a volume of 150- 155 litres/ m3 . Filler are also
required in case of high cement contents ( >325 kg/m3) : 60 liters/m3
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 145 of 199
Construction Technology of Civil Engineering Projects
Over the years various methods have been developed to cast underwater concrete:
In the early years a corbel was used (see fig 8.4). The corbel was lowered into the
water and the concrete was released once the corbel reached its level. The casting
front is built-up in the vertical direction. The corbel should penetrate in the
previous layer to avoid segregation. Nevertheless, the risk of non-compliance with
regard to quality is significant.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 147 of 199
Construction Technology of Civil Engineering Projects
In 1969 another method was applied for the first time: the hydro-valve method (fig
8.8). The system consists of a flexible sleeve which is located in a steel, perforated,
steel pipe. The flexible sleeve will be compressed if the supply of fresh concrete is
reduced. As such there will be no inclusions of water in the fresh concrete mass.
The increasing water pressure prevents the fresh concrete from falling too fast. The
steel pipe has a typical diameter of 0,70 m. A shield at the bottom of the steel pipe
allows levelling of the fresh concrete. The method is able to cast UWC where
obstructions occur.
Steel,perforated
pipe
Hydro valve
method
Flexible sleeve
Shield
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 149 of 199
Construction Technology of Civil Engineering Projects
Fig. 8.9 Construction of a temporary bridge for access and driving sheet piles
Anchorage of the walls may be done by external anchoring (see fig 8.10) or by
internal braces/ struts (see fig. 8.11). To make a choice between the two options,
following aspects should be considered:
• The width of the building pit: the width is an important factor as there is a
direct impact on material demand of the anchorage system if opted for
braces/ struts.
• Shape of the building pit: an irregular shape will have consequences on
corner-connections and standardization of units and is as such an important
aspect in relation to cost and efficiency of the actual construction phase. But
irregular shapes may also lead to unbalances between the walls, if braced:
differences in effective areas to be braced will lead to unbalanced driving
forces. The consequences of such unbalance will be a redistribution of forces
and will also have consequences on deformations of the walls. Alternatively,
amended strut patterns may overcome the unbalance but will have an impact
on the cost of the construction process. Anchors would avoid the problem of
unbalanced forces.
• Retaining height of the walls of the building pit: differences in the retaining
height of walls will also lead to an unbalance if braced. Same consequences
as mentioned above will apply.
• Obstructions in the surrounding soil mass: if obstructions (piled foundations,
utilities, underground structures etc) do occur in the surrounding soil mass,
internal anchorage would avoid the problems connected to the external
obstructions.
• Future utilization of the surrounding soil mass: grouted anchors are
commonly used if external anchoring is applied. The grout body near the toe
of the anchor will transfer the load to the surrounding soil. The typical length
of the grout body ranges from 5 to 10 meters. As the grout body can’t be
removed afterwards (contrary to the tie rods), it can seriously obstruct future
utilization of the surrounding soil mass. Internal braces/struts will avoid such
problem.
• Execution plan: all steps of the method statement for actually executing the
scheme should be carefully examined: excavation and hoisting of formwork
units have a strong interaction with the size and spacing of the braces/ struts:
floating equipment for excavation might be preferred and for formwork,
large units are generally more cost effective compared to small units, but
should be able to pass the internal anchorage.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 151 of 199
Construction Technology of Civil Engineering Projects
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 153 of 199
Construction Technology of Civil Engineering Projects
So called ‘hydro hammers’ are able to drive under water: the pile can be driven to
the level required. Diesel hammers do require a follower: from approximately 1
meter above water level, the pile is provided with a follower (in between the pile
head and the hammer). If driven from a traverse, extended leaders (for guidance)
must be applied given the elevation of the driving rig. If pontoons are applied,
floating stability must be checked: stability may be improved by water ballast tanks
or the application of winches.
A wide range of pile types is available: ranging from prefabricated, prestressed,
concrete piles to steel piles (I-profile and tubular) to GEWI piles (grouted, high
tensile steel anchors). And even a combination is frequently applied: Vibrocom
piles (see hereafter).
Prefabricated, prestressed concrete piles (see fig. 8.14, left and middle) are widely
applied and have a long track record. As these are displacement piles, a dense
pattern may lead to consequences as described in section 8.3.2. to overcome driving
stresses, steel piles could be considered as they can handle high driving stresses.
But steel piles are expensive. A combination has been developed, known as the
Vibrocom pile: a steel casing, provided with a separate end plate (not welded to the
casing) is driven into the soil. At the required depth, a prefabricated and prestressed
pile is lowered into the casing, and the annulus between this pile and the casing is
filled with mortar. Then the casing is lifted but in a pull/ push mode which
compacts the mortar and results in excellent bond properties both between pile and
mortar as well as between mortar and soil.
Permanent steel piles are nowadays seldom applied because of cost.
Displacement piles may cause adverse effects to the surroundings due to driving
operations (noise, shock waves, and displacements). Piles made in-situ without
driving are good alternatives in such circumstance. However, most of the in-situ
piles are less effective in taking axial loads compared to driven displacement piles.
An interesting development to take the advantage of an in-situ pile and to get good
tensile capacity at the same time is the drilled ‘GEWI’ pile: a high tensile steel
anchor provided with a grout body over the full length of the anchor, placed
vertically.
The GEWI system allows for single and double corrosion protection (see fig 8.15).
Recent projects in the Netherlands (Botlek railway tunnel and Zevenaar railway
tunnel) have demonstrated the effectiveness of this GEWI system. It must be
realized that the GEWI system, with the highly loaded steel anchor, is less rigid
compared to the displacement piles: this must be emphasized in the design of the
underwater concrete floor (stiffness ratio of the springs of tensile piles and the sheet
pile walls of the building pit and the consequences thereof for bending moments in
the floor slab).
As the piles must anchor the underwater concrete slab against uplift forces from
water pressure, a proper anchorage must be provided at the pile/ slab interface. In
case of concrete piles, the top part of the piles is provided with dents (see fig. 8.14).
These dents have traditionally been provided at the outside of the nominal section
(at 3 sides). Efficiency considerations have led to the application of dents within
the nominal section. Initially, this application has led to substantial damage to the
piles due to (reflected) driving stresses and a reduced cross-section (fig. 8.14 right).
Amended reinforcement details have solved this problem.
In case of GEWI anchors, steel anchor plates are provided (see fig 8.16).
Fig 8.14 Concrete tension piles (with dents) as anchorage/ driving damage
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 155 of 199
Construction Technology of Civil Engineering Projects
GEWI ® Pile with single corrosion protection and GEWI ® Pile with double
corrosion protection
5 - coupler
®
6 - GEWI bar
(nut with plate), see fig. 8.16. In case of concrete piles, the top part of the piles will
often be peeled-off after dewatering of the building pit (fig 8.17). Reinforcement
and prestressing strands will extend into the second layer and will provide the
anchorage. Recent trends also show successful examples where piles are not peeled
and the full section penetrates into the second layer for anchorage (fig. 8.18).
Specific reinforcement may be required for proper anchorage.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 157 of 199
Construction Technology of Civil Engineering Projects
(fig 8.19). Typical values for the filling layer are 0.15 m. for sand and 0.25 m. for
gravel.
Both options are feasible and have been applied successfully. No consensus has
been reached which option is preferred. Following considerations may help to
make the choice:
Without a filling layer both layers will be connected. The second slab will develop
tensile stresses due to restricted deformations after casting. These stresses may (and
will normally) lead to cracks. Cracks may be in conflict with the functional
requirement of water tightness of the second floor slab. By proper measures
(reinforcement details / cooling of concrete) cracks can be kept to acceptable
values. Without the filling layer care should be given to vertical geometrical control
of the reinforcement (cover) as the underwater concrete slab will not have a
straight, horizontal top surface. As the two slabs are connected, concrete piles may
extend with their full cross-section into the second floor slab to transmit vertical
loads and bending moments.
With a filling layer both slabs could deform independently (in plane). This is
specifically feasible if piles are not required for equilibrium. Tensile stresses due to
restricted deformations will be strongly reduced. With piles, the situation is
different: piles connected to the second layer will perform as a dowel and will
result in restriction of the deformation and will result in the development of tensile
stresses. Proper measures are required for crack width control (reinforcement
details/ cooling). Connection details have been developed to reduce the
effectiveness of the dowels: peeling of the piles to the level of the bottom of the
second floor slab, results in a relative weak shear transfer mechanism and will
reduce the tensile stresses. Quantification of the resulting stresses is difficult and
uncertain. Upper limit (conservative) approaches are often applied to design the
required reinforcement.
In case of a reinforced underwater concrete floor slab (see also section 8.3.4), the
pile head of a driven pile will be at 250 mm. below the anticipated top of
underwater concrete to allow for proper support of the reinforcement cage.
Fig 8.20 Design values and tolerances of bed level and concrete
Typical diameters for reinforcement are 25mm. and above. To allow a proper flow
of the concrete, bars should be spaced at least 250 mm. Given the specific
underwater circumstances, reinforcement will be prefabricated as fixing in-situ
must be avoided. For lifting, transportation, and placing, the reinforcement cage
should be provided with internal braces and supports which connect top and bottom
reinforcement (fig 8.21).
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 159 of 199
Construction Technology of Civil Engineering Projects
At the piles, the bottom net should have an opening of the pile size plus 300 mm.
(so: a free zone of 150mm. around the piles). To obtain maximum standardization
of the reinforcement, piles should be spaces as uniform as possible. Also casting
equipment has an impact on the design of the reinforcement: currently, the
application of the Hop-dobber requires an open square in the top net with 2m.
edges.
Positioning of the reinforcement can be done in different ways:
In case of piles, profiles can be provided on the piles to receive the top net, see fig.
8.21. Without piles, the cage can be lowered by wires running from the top of the
sheet pile wall. The wires will allow geometrical control. For wide building pits
this would be unpractical. Therefore, concrete tiles will generally be installed at the
bottom to receive the net and to serve as spacer. The net is more or less equally
supported by the excavated bed or soil improvement layer.
8.4 Quality assurance and quality control
The concept of underwater concrete construction has quite specific execution issues
as described in the sections above. Quality assurance and quality control should get
proper attention.
A summary of execution aspects and potential measures to be considered in view of
AQ/ QC are as follows:
• Suspended load and bed load (mud): survey of bed level and inspections by
divers especially (but not limited to) the areas near connections with piles or
sheet piles.
• Cracks:
• Cement replacement by fly ash etc.
• Cement with low hydratation heat development
• Reduction of slab thickness
• Pre-cooling of the concrete
• Joints (see fig 8.23)
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 161 of 199
Construction Technology of Civil Engineering Projects
• Strength
• Cement (type, quantity)
Additives (silica, fly ash)
Mixing temperature
Insulation
Thermo Koppel measurements (in combination with reference
samples)
• Surface
• Placement method
• Casting plan
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 163 of 199
Construction Technology of Civil Engineering Projects
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0 November 2018
Prof. Ir. A.Q.C. van der Horst Page 165 of 199
Construction Technology of Civil Engineering Projects
,,
2. Design process
The Scouting Phase is the first phase of the design process. From an The Scouting Phase is an initial feasibility scan of the scheme. Generally
abstract level of perception, global functional requirements are specified. To based on global functional/ performance requirements. A typical accuracy
support the owner in his decision process, an indicative budget must be made. target is +/- 30%
To allow the global cost estimate, with a typical accuracy level of +/- 30%, an
outline concept should be available. It is common practice to limit the design
efforts at this stage as the feasibility of the project is generally uncertain. To .
match the objectives of target accuracy and limited input, often experience is
used to copy former schemes and make them project specific with limited
efforts only. To do so, the designer should be well experienced to understand
general cost drivers and to identify project specific, decisive points of
attention/ cost drivers.
During this phase the functional requirements, basic data and design
criteria will be developed and the service criteria agreed. A conceptual design
will also be developed to support a more accurate budget estimate. Quite
some effort is required at this stage as the Basis of Design should be agreed,
fixed and frozen upon completion of this stage. A typical accuracy target is
+/- 20%. An essential part of this phase is the Service Criteria Agreement, see
1.6.3.1. Also the Birth Certificate Document should be initiated at this stage.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0 November 2018
Prof. Ir. A.Q.C. van der Horst Page 169 of 199
Construction Technology of Civil Engineering Projects
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0 November 2018
Prof. Ir. A.Q.C. van der Horst Page 171 of 199
Construction Technology of Civil Engineering Projects
Restrictions regarding the design and construction times, and the budget
limitations;
Legal aspects (laws, ordinances, directives);
Construction methods, transport and assembly techniques;
Equipment and facilities for monitoring and maintenance measures;
Maintaining the use of traffic structures and lifelines (pipelines, etc.);
Demolition approach at the end of service life
Life Cycle Cost considerations
.
The following deviations should be considered: The decisive actions and action effects as well as the sensitivity of the
deviation from the assumed values of the actions, concept for deviations from the anticipated values,
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0 November 2018
Prof. Ir. A.Q.C. van der Horst Page 173 of 199
Construction Technology of Civil Engineering Projects
In the context of the partial safety factor verification, ensuring the required the chosen structural system,
reliability level requires adequate consideration of the uncertainties regarding the important assumptions in the structural and analytical models,
actions, structural modelling and the determination of action effects. The
differentiation of the partial safety factors depending on the uncertainties in the accepted risks,
actions, material properties and applied models is addressed in chapter 4. other conditions relevant to the design.
the most important dimensions, construction material properties and
construction details,
comments on the envisaged methods of construction.
Specifications for detailed design, materials and workmanship
The extent and content of the project specification document shall be
adapted to the importance of the structure and the associated hazards and
environmental risks.
2.8 Dimensioning
2.8.1 Objectives
Detailing, limit measures and special provisions supplement the use of Dimensioning concerns the determination of the dimensions, the structural
models for various purposes, such as: materials and the detailing of a structure on the basis of structural and
to avoid superfluous calculations, execution-related considerations or numerical verifications.
CT 4170 Construction Technology of Civil Engineering Projects Version 6.0 November 2018
Prof. Ir. A.Q.C. van der Horst Page 177 of 199
Construction Technology of Civil Engineering Projects
CT 4170 Construction Technology of Civil engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 179 of 199
Construction Technology of Civil Engineering Projects
CT 4170 Construction Technology of Civil engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 181 of 199
Construction Technology of Civil Engineering Projects
CT 4170 Construction Technology of Civil engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 183 of 199
Construction Technology of Civil Engineering Projects
CT 4170 Construction Technology of Civil engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 185 of 199
Construction Technology of Civil Engineering Projects
CT 4170 Construction Technology of Civil engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 187 of 199
Construction Technology of Civil Engineering Projects
CT 4170 Construction Technology of Civil engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 189 of 199
Construction Technology of Civil Engineering Projects
CT 4170 Construction Technology of Civil engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 191 of 199
Construction Technology of Civil Engineering Projects
CT 4170 Construction Technology of Civil engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 193 of 199
Construction Technology of Civil Engineering Projects
CT 4170 Construction Technology of Civil engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 195 of 199
Construction Technology of Civil Engineering Projects
CT 4170 Construction Technology of Civil engineering Projects Version 6.0- November 2018
Prof. Ir. A.Q.C. van der Horst Page 197 of 199