Larsen & Toubro Limited: ECC Division - EDRC

This document provides a bill of quantities for two structures: 1. An inlet chamber that is 2.5m x 2.5m x 3.4m. It lists the quantities of materials needed for excavation, backfilling, concrete, reinforcement, and other items. 2. A sluice valve chamber that is 5.5m x 3m x 2.8m. Similar to the inlet chamber, it provides the quantities of various construction materials required. The document contains detailed dimensions and calculations of quantities for various construction items for the two structures. It will help estimate the costs for building the inlet chamber and sluice valve chamber.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
68 views32 pages

Larsen & Toubro Limited: ECC Division - EDRC

This document provides a bill of quantities for two structures: 1. An inlet chamber that is 2.5m x 2.5m x 3.4m. It lists the quantities of materials needed for excavation, backfilling, concrete, reinforcement, and other items. 2. A sluice valve chamber that is 5.5m x 3m x 2.8m. Similar to the inlet chamber, it provides the quantities of various construction materials required. The document contains detailed dimensions and calculations of quantities for various construction items for the two structures. It will help estimate the costs for building the inlet chamber and sluice valve chamber.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 32

LARSEN & TOUBRO LIMITED

ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. PHED -FATEHPUR PKG-6
REV. NO. DATE
DOC NO
6/9/2021
CALCULATED CHECKED
PARTICULARS Inlet Chamber 2.5m x2.5mx 3.4m

Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 1 4.65 4.65 2.00 43.25 m3
2-4m 1 4.65 4.65 1.20 25.95 m3

69.19 m3

2 Backfill 37.67 m3

3 Disposal
Longwall 2 3.05 0.275 2.80 4.70 m3
Shortwall 2 2.5 0.275 2.80 3.85 m3
Inside chamber 1 2.5 2.5 2.80 17.50 m3
Base Slab 1 3.65 3.65 0.3 4.00 m3
PCC 1.48 m3 31.53 m3

4 PCC 1 3.85 3.85 0.1 1.48 m3 1.48 m3

5 RCC M20 - Below GL


Long wall 2 3.05 0.275 2.80 4.70 m3
Short wall 2 2.5 0.275 2.80 3.85 m3
Base Slab 1 3.65 3.65 0.3 4.00 m3
Pedestal 1 0.5 0.5 0.3 0.08 m3 12.62 m3

6 RCC M20 - Above GL


Long wall 2 3.05 0.275 0.6 1.01 m3
Short wall 2 2.5 0.275 0.6 0.83 m3
Cover slab 1 2.5 2.5 0.150 0.94 m3
Beam 0 3.05 0.3 0.400 0.00 m3 2.77 m3

6 Shuttering BGL
Long wall 4 3.05 - 2.80 34.16 m2
Short wall 4 2.5 - 2.8 28.00 m2
Base Slab 1 14.6 - 0.3 4.38 m2
Pedestal 1 2 - 0.3 0.60 m2 67.14 m2

7 Shuttering AGL
Long wall 4 3.05 - 0.6 7.32 m2
Short wall 4 2.5 - 0.6 6.00 m2
Cover slab 1 2.5 2.5 - 6.25 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. PHED -FATEHPUR PKG-6
REV. NO. DATE
DOC NO
6/9/2021
CALCULATED CHECKED
PARTICULARS Inlet Chamber 2.5m x2.5mx 3.4m

Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
Beam 0 3.05 1.1 - 0.00 m2 19.57 m2

7 HYSD Reinforcement
Walls 85 10.38 - - 882.17 kg
Slab 80 4.93 - - 394.74 kg
Pedestal 100 0.08 - - 7.50 kg
Beam 150 0.00 - - 0.00 kg 1.28 MT

8 Ferro cement manhole 1.00 No

9 Structural steel 1.05 10 5.80 60.90 kg 0.06 MT

10 M.S.rungs 11.33 11.33 Nos 12.00 Nos

11 Painting outside
Longwall 2 3.05 - 0.60 3.66 m2
shortwall 2 3.05 - 0.60 3.66 m2 7.32 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. PHED -FATEHPUR PKG-6
REV. NO. DATE
DOC NO
6/9/2021
CALCULATED CHECKED
PARTICULARS Sluice valve Chamber 5.5m x3mx 2.8m

Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 1 7.8 5.3 2.00 82.68 m3
2-4m 1 7.8 5.3 0.70 28.94 m3

111.62 m3

2 Backfill 49.19 m3

3 Disposal
Longwall 2 6.1 0.3 2.30 8.42 m3
Shortwall 2 3 0.3 2.30 4.14 m3
Inside chamber 1 5.5 3 2.30 37.95 m3
Base Slab 1 6.8 4.3 0.3 8.77 m3
PCC 3.15 m3 62.43 m3

4 PCC 1 7 4.5 0.1 3.15 m3 3.15 m3

5 RCC M20 - Below GL


Long wall 2 6.1 0.3 2.30 8.42 m3
Short wall 2 3 0.3 2.30 4.14 m3
Base Slab 1 6.8 4.3 0.3 8.77 m3
Pedestal 1 0.5 0.5 0.3 0.08 m3 21.41 m3

6 RCC M20 - Above GL


Long wall 2 6.1 0.3 0.5 1.83 m3
Short wall 2 3 0.3 0.5 0.90 m3
Cover slab 1 5.5 3 0.150 2.48 m3
Beam 2 3.6 0.3 0.400 0.86 m3 6.07 m3

6 Shuttering BGL
Long wall 4 6.1 - 2.30 56.12 m2
Short wall 4 3 - 2.3 27.60 m2
Base Slab 1 22.2 - 0.3 6.66 m2
Pedestal 1 2 - 0.3 0.60 m2 90.98 m2

7 Shuttering AGL
Long wall 4 6.1 - 0.5 12.20 m2
Short wall 4 3 - 0.5 6.00 m2
Cover slab 1 5.5 3 - 16.50 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. PHED -FATEHPUR PKG-6
REV. NO. DATE
DOC NO
6/9/2021
CALCULATED CHECKED
PARTICULARS Sluice valve Chamber 5.5m x3mx 2.8m

Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
Beam 2 3.6 1.1 - 7.92 m2 42.62 m2

7 HYSD Reinforcement
Walls 85 15.29 - - 1299.48 kg
Slab 80 11.25 - - 899.76 kg
Pedestal 100 0.08 - - 7.50 kg
Beam 150 0.86 - - 129.60 kg 2.34 MT

8 Ferro cement manhole 1.00 No

9 Structural steel 1.05 28 5.80 170.52 kg 0.17 MT

10 M.S.rungs 9.333 9.33 Nos 10.00 Nos

11 Painting outside
Longwall 2 6.1 - 0.50 6.10 m2
shortwall 2 3.6 - 0.50 3.60 m2 9.70 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Fatehpur pkg 6
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED
S SCOUR VALVE CHAMBER 1.2m x 1.2m x 2.8 m
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 1 2.95 2.95 2.00 17.41 m3
2-4m 1 2.95 2.95 0.60 5.22 m3

22.63 m3

2 Backfill 16.23 m3

3 Disposal
Longwall 2 1.5 0.15 2.30 1.04 m3
Shortwall 2 1.2 0.15 2.30 0.83 m3
Inside chamber 1 1.2 1.2 2.30 3.31 m3
Base Slab 1 1.95 1.95 0.2 0.76 m3
PCC 0.46 m3 6.40 m3

4 PCC 1 2.15 2.15 0.1 0.46 m3 0.46 m3

5 RCC M20 - Below GL


Long wall 2 1.5 0.15 2.30 1.04 m3
Short wall 2 1.2 0.15 2.30 0.83 m3
Base Slab 1 1.95 1.95 0.2 0.76 m3
Pedestal 0 0.5 0.5 0.3 0.00 m3 2.62 m3

6 RCC M20 - Above GL


Long wall 2 1.5 0.15 0.5 0.23 m3
Short wall 2 1.2 0.15 0.5 0.18 m3
Cover slab 1 1.2 1.2 0.150 0.22 m3
Beam 0 1.2 0.3 0.400 0.00 m3 0.62 m3

6 Shuttering BGL
Long wall 4 1.5 - 2.30 13.80 m2
Short wall 4 1.2 - 2.3 11.04 m2
Base Slab 1 7.8 - 0.2 1.56 m2
Pedestal 0 2 - 0.3 0.00 m2 26.40 m2

7 Shuttering AGL
Long wall 4 1.5 - 0.5 3.00 m2
Short wall 4 1.2 - 0.5 2.40 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Fatehpur pkg 6
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED
S SCOUR VALVE CHAMBER 1.2m x 1.2m x 2.8 m
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
Cover slab 1 1.2 1.2 - 1.44 m2
Beam 0 1.2 1.1 - 0.00 m2 6.84 m2

7 HYSD Reinforcement
Walls 85 2.27 - - 192.78 kg
Slab 80 0.98 - - 78.12 kg
Pedestal 100 0.00 - - 0.00 kg
Beam 150 0.00 - - 0.00 kg 0.27 MT

8 Ferro cement manhole covers 1.00 No

9 Structural steel 1.05 4.8 5.80 29.23 kg 0.03 MT

10 M.S.rungs 9.333 9.33 Nos 10.00 Nos

11 Painting outside
Longwall 2 1.5 - 0.50 1.50 m2
shortwall 2 1.5 - 0.50 1.50 m2 3.00 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Fatehpur pkg 6
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED CHECKED
S SCOUR VALVE CHAMBER 1.8m x 2.1m x 2.8 m
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 1 3.65 3.95 2.00 28.84 m3
2-4m 1 3.65 3.95 0.60 8.65 m3

37.49 m3

2 Backfill 22.37 m3

3 Disposal
Longwall 2 2.2 0.2 2.30 2.02 m3
Shortwall 2 2.1 0.2 2.30 1.93 m3
Inside chamber 1 1.8 2.1 2.30 8.69 m3
Base Slab 1 2.65 2.95 0.2 1.56 m3
PCC 0.90 m3 15.11 m3

4 PCC 1 2.85 3.15 0.1 0.90 m3 0.90 m3

5 RCC M20 - Below GL


Long wall 2 2.2 0.2 2.30 2.02 m3
Short wall 2 2.1 0.2 2.30 1.93 m3
Base Slab 1 2.65 2.95 0.2 1.56 m3
Pedestal 0 0.5 0.5 0.3 0.00 m3 5.52 m3

6 RCC M20 - Above GL


Long wall 2 2.2 0.2 0.5 0.44 m3
Short wall 2 2.1 0.2 0.5 0.42 m3
Cover slab 1 1.8 2.1 0.150 0.57 m3
Beam 0 2.1 0.3 0.400 0.00 m3 1.43 m3

6 Shuttering BGL
Long wall 4 2.2 - 2.30 20.24 m2
Short wall 4 2.1 - 2.3 19.32 m2
Base Slab 1 11.2 - 0.2 2.24 m2
Pedestal 0 2 - 0.3 0.00 m2 41.80 m2

7 Shuttering AGL
Long wall 4 2.2 - 0.5 4.40 m2
Short wall 4 2.1 - 0.5 4.20 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Fatehpur pkg 6
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED CHECKED
S SCOUR VALVE CHAMBER 1.8m x 2.1m x 2.8 m
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
Cover slab 1 1.8 2.1 - 3.78 m2
Beam 0 2.1 1.1 - 0.00 m2 12.38 m2

7 HYSD Reinforcement
Walls 85 4.82 - - 409.36 kg
Slab 80 2.13 - - 170.44 kg
Pedestal 100 0.00 - - 0.00 kg
Beam 150 0.00 - - 0.00 kg 0.58 MT

8 Ferro cement manhole covers 1.00 No

9 Structural steel 1.05 7.8 5.80 47.50 kg 0.05 MT

10 M.S.rungs 9.333 9.33 Nos 10.00 Nos

11 Painting outside
Longwall 2 2.2 - 0.50 2.20 m2
shortwall 2 2.5 - 0.50 2.50 m2 4.70 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Fatehpur pkg 6
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED CHECKED
S AIR VALVE CHAMBER 1.2m x 2.1m x 2.8 m
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 1 3.1 4 2.00 24.80 m3
2-4m 1 3.1 4 0.65 8.06 m3

32.86 m3

2 Backfill 21.35 m3

3 Disposal
Longwall 2 1.6 0.2 2.30 1.47 m3
Shortwall 2 2.1 0.2 2.30 1.93 m3
Inside chamber 1 1.2 2.1 2.30 5.80 m3
Base Slab 1 2.1 3 0.25 1.58 m3
PCC 0.74 m3 11.51 m3

4 PCC 1 2.3 3.2 0.1 0.74 m3 0.74 m3

5 RCC M20 - Below GL


Long wall 2 1.6 0.2 2.30 1.47 m3
Short wall 2 2.1 0.2 2.30 1.93 m3
Base Slab 1 2.1 3 0.25 1.58 m3
Pedestal 0 0.5 0.5 0.3 0.00 m3 4.98 m3

6 RCC M20 - Above GL


Long wall 2 1.6 0.2 0.5 0.32 m3
Short wall 2 2.1 0.2 0.5 0.42 m3
Cover slab 1 1.2 2.1 0.150 0.38 m3
Beam 0 2.1 0.3 0.400 0.00 m3 1.12 m3

6 Shuttering BGL
Long wall 4 1.6 - 2.30 14.72 m2
Short wall 4 2.1 - 2.3 19.32 m2
Base Slab 1 10.2 - 0.25 2.55 m2
Pedestal 0 2 - 0.3 0.00 m2 36.59 m2

7 Shuttering AGL
Long wall 4 1.6 - 0.5 3.20 m2
Short wall 4 2.1 - 0.5 4.20 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Fatehpur pkg 6
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED CHECKED
S AIR VALVE CHAMBER 1.2m x 2.1m x 2.8 m
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
Cover slab 1 1.2 2.1 - 2.52 m2
Beam 0 2.1 1.1 - 0.00 m2 9.92 m2

7 HYSD Reinforcement
Walls 85 4.14 - - 352.24 kg
Slab 80 1.95 - - 156.24 kg
Pedestal 100 0.00 - - 0.00 kg
Beam 150 0.00 - - 0.00 kg 0.51 MT

8 Ferro cement manhole covers 1.00 No

9 Structural steel 1.05 6.6 5.80 40.19 kg 0.04 MT

10 M.S.rungs 9.333 9.33 Nos 10.00 Nos

11 Painting outside
Longwall 2 1.6 - 0.50 1.60 m2
shortwall 2 2.5 - 0.50 2.50 m2 4.10 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Fatehpur pkg 6
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED CHECKED
S Butterfly valve chamber -surge protection 1.8m x 1.4m x 2.1 m
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 1 3.6 3.2 1.90 21.89 m3

21.89 m3

2 Backfill 14.05 m3

3 Disposal
Longwall 2 2.15 0.175 1.60 1.20 m3
Shortwall 2 1.4 0.175 1.60 0.78 m3
Inside chamber 1 1.8 1.4 1.60 4.03 m3
Base Slab 1 2.6 2.2 0.2 1.14 m3
PCC 0.67 m3 7.84 m3

4 PCC 1 2.8 2.4 0.1 0.67 m3 0.67 m3

5 RCC M20 - Below GL


Long wall 2 2.15 0.175 1.60 1.20 m3
Short wall 2 1.4 0.175 1.60 0.78 m3
Base Slab 1 2.6 2.2 0.2 1.14 m3
Pedestal 0 0.5 0.5 0.3 0.00 m3 3.13 m3

6 RCC M20 - Above GL


Long wall 2 2.15 0.175 0.5 0.38 m3
Short wall 2 1.4 0.175 0.5 0.25 m3
Cover slab 1 1.8 1.4 0.150 0.38 m3
Beam 0 1.8 0.3 0.400 0.00 m3 1.00 m3

6 Shuttering BGL
Long wall 4 2.15 - 1.60 13.76 m2
Short wall 4 1.4 - 1.6 8.96 m2
Base Slab 1 9.6 - 0.2 1.92 m2
Pedestal 0 2 - 0.3 0.00 m2 24.64 m2

7 Shuttering AGL
Long wall 4 2.15 - 0.5 4.30 m2
Short wall 4 1.4 - 0.5 2.80 m2
Cover slab 1 1.8 1.4 - 2.52 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Fatehpur pkg 6
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED CHECKED
S Butterfly valve chamber -surge protection 1.8m x 1.4m x 2.1 m
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
Beam 0 1.8 1.1 - 0.00 m2 9.62 m2

7 HYSD Reinforcement
Walls 85 2.61 - - 221.79 kg
Slab 80 1.52 - - 121.76 kg
Pedestal 100 0.00 - - 0.00 kg
Beam 150 0.00 - - 0.00 kg 0.34 MT

8 Ferro cement manhole covers 1.00 No

9 Structural steel 1.05 6.4 5.80 38.98 kg 0.04 MT

10 M.S.rungs 7 7.00 Nos 7.00 Nos

11 Painting outside
Longwall 2 2.15 - 0.50 2.15 m2
shortwall 2 1.75 - 0.50 1.75 m2 3.90 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Fatehpur pkg 6
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR Non Return valve chamber -surge protection 2.5m x 1.4m x 2.1 CALCULATED CHECKED
S m
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 1 4.3 3.2 1.90 26.14 m3

26.14 m3

2 Backfill 15.87 m3

3 Disposal
Longwall 2 2.85 0.175 1.60 1.60 m3
Shortwall 2 1.4 0.175 1.60 0.78 m3
Inside chamber 1 2.5 1.4 1.60 5.60 m3
Base Slab 1 3.3 2.2 0.2 1.45 m3
PCC 0.84 m3 10.27 m3

4 PCC 1 3.5 2.4 0.1 0.84 m3 0.84 m3

5 RCC M20 - Below GL


Long wall 2 2.85 0.175 1.60 1.60 m3
Short wall 2 1.4 0.175 1.60 0.78 m3
Base Slab 1 3.3 2.2 0.2 1.45 m3
Pedestal 0 0.5 0.5 0.3 0.00 m3 3.83 m3

6 RCC M20 - Above GL


Long wall 2 2.85 0.175 0.5 0.50 m3
Short wall 2 1.4 0.175 0.5 0.25 m3
Cover slab 1 2.5 1.4 0.150 0.53 m3
Beam 0 2.5 0.3 0.400 0.00 m3 1.27 m3

6 Shuttering BGL
Long wall 4 2.85 - 1.60 18.24 m2
Short wall 4 1.4 - 1.6 8.96 m2
Base Slab 1 11 - 0.2 2.20 m2
Pedestal 0 2 - 0.3 0.00 m2 29.40 m2

7 Shuttering AGL
Long wall 4 2.85 - 0.5 5.70 m2
Short wall 4 1.4 - 0.5 2.80 m2
Cover slab 1 2.5 1.4 - 3.50 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Fatehpur pkg 6
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR Non Return valve chamber -surge protection 2.5m x 1.4m x 2.1 CALCULATED CHECKED
S m
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
Beam 0 2.5 1.1 - 0.00 m2 12.00 m2

7 HYSD Reinforcement
Walls 85 3.12 - - 265.52 kg
Slab 80 1.98 - - 158.16 kg
Pedestal 100 0.00 - - 0.00 kg
Beam 150 0.00 - - 0.00 kg 0.42 MT

8 Ferro cement manhole covers 1.00 No

9 Structural steel 1.05 7.8 5.80 47.50 kg 0.05 MT

10 M.S.rungs 7 7.00 Nos 7.00 Nos

11 Painting outside
Longwall 2 2.85 - 0.50 2.85 m2
shortwall 2 1.75 - 0.50 1.75 m2 4.60 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Fatehpur pkg 6
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED CHECKED
S Sluice valve chamber -surge protection 1.8m x 1m x 1.7 m
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 1 3.5 2.7 1.50 14.18 m3

14.18 m3

2 Backfill 9.54 m3

3 Disposal
Longwall 2 2.1 0.15 1.20 0.76 m3
Shortwall 2 1 0.15 1.20 0.36 m3
Inside chamber 1 1.8 1 1.20 2.16 m3
Base Slab 1 2.5 1.7 0.2 0.85 m3
PCC 0.51 m3 4.64 m3

4 PCC 1 2.7 1.9 0.1 0.51 m3 0.51 m3

5 RCC M20 - Below GL


Long wall 2 2.1 0.15 1.20 0.76 m3
Short wall 2 1 0.15 1.20 0.36 m3
Base Slab 1 2.5 1.7 0.2 0.85 m3
Pedestal 0 0.5 0.5 0.3 0.00 m3 1.97 m3

6 RCC M20 - Above GL


Long wall 2 2.1 0.15 0.5 0.32 m3
Short wall 2 1 0.15 0.5 0.15 m3
Cover slab 1 1.8 1 0.150 0.27 m3
Beam 0 1.8 0.3 0.400 0.00 m3 0.74 m3

6 Shuttering BGL
Long wall 4 2.1 - 1.20 10.08 m2
Short wall 4 1 - 1.2 4.80 m2
Base Slab 1 8.4 - 0.2 1.68 m2
Pedestal 0 2 - 0.3 0.00 m2 16.56 m2

7 Shuttering AGL
Long wall 4 2.1 - 0.5 4.20 m2
Short wall 4 1 - 0.5 2.00 m2
Cover slab 1 1.8 1 - 1.80 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Fatehpur pkg 6
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED CHECKED
S Sluice valve chamber -surge protection 1.8m x 1m x 1.7 m
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
Beam 0 1.8 1.1 - 0.00 m2 8.00 m2

7 HYSD Reinforcement
Walls 85 1.58 - - 134.39 kg
Slab 80 1.12 - - 89.60 kg
Pedestal 100 0.00 - - 0.00 kg
Beam 150 0.00 - - 0.00 kg 0.22 MT

8 Ferro cement manhole covers 1.00 No

9 Structural steel 1.05 5.6 5.80 34.10 kg 0.03 MT

10 M.S.rungs 5.667 5.67 Nos 6.00 Nos

11 Painting outside
Longwall 2 2.1 - 0.50 2.10 m2
shortwall 2 1.3 - 0.50 1.30 m2 3.40 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. PHED -FATEHPUR PKG-6
REV. NO. DATE
DOC NO
6/9/2021
CALCULATED CHECKED
PARTICULARS Flow meter Chamber 2.4m x2.4m x 2.5m

Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 1 4.45 4.45 2.00 39.61 m3
2-4m 1 4.45 4.45 0.35 6.93 m3

46.54 m3

2 Backfill 25.98 m3

3 Disposal
Longwall 2 2.85 0.225 2.00 2.57 m3
Shortwall 2 2.4 0.225 2.00 2.16 m3
Inside chamber 1 2.4 2.4 2.00 11.52 m3
Base Slab 1 3.45 3.45 0.25 2.98 m3
PCC 1.33 m3 20.55 m3

4 PCC 1 3.65 3.65 0.1 1.33 m3 1.33 m3

5 RCC M20 - Below GL


Long wall 2 2.85 0.225 2.00 2.57 m3
Short wall 2 2.4 0.225 2.00 2.16 m3
Base Slab 1 3.45 3.45 0.25 2.98 m3
Pedestal 1 0.5 0.5 0.3 0.08 m3 7.78 m3

6 RCC M20 - Above GL


Long wall 2 2.85 0.225 0.5 0.64 m3
Short wall 2 2.4 0.225 0.5 0.54 m3
Cover slab 1 2.4 2.4 0.150 0.86 m3
Beam 0 2.85 0.3 0.400 0.00 m3 2.05 m3

6 Shuttering BGL
Long wall 4 2.85 - 2.00 22.80 m2
Short wall 4 2.4 - 2 19.20 m2
Base Slab 1 13.8 - 0.25 3.45 m2
Pedestal 1 2 - 0.3 0.60 m2 46.05 m2

7 Shuttering AGL
Long wall 4 2.85 - 0.5 5.70 m2
Short wall 4 2.4 - 0.5 4.80 m2
Cover slab 1 2.4 2.4 - 5.76 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. PHED -FATEHPUR PKG-6
REV. NO. DATE
DOC NO
6/9/2021
CALCULATED CHECKED
PARTICULARS Flow meter Chamber 2.4m x2.4m x 2.5m

Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
Beam 0 2.85 1.1 - 0.00 m2 16.26 m2

7 HYSD Reinforcement
Walls 85 5.91 - - 502.03 kg
Slab 80 3.84 - - 307.17 kg
Pedestal 100 0.08 - - 7.50 kg
Beam 150 0.00 - - 0.00 kg 0.82 MT

8 Ferro cement manhole 1.00 No

9 Structural steel 1.05 9.6 5.80 58.46 kg 0.06 MT

10 M.S.rungs 8.333 8.33 Nos 9.00 Nos

11 Painting outside
Longwall 2 2.85 - 0.50 2.85 m2
shortwall 2 2.85 - 0.50 2.85 m2 5.70 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. PHED -FATEHPUR PKG-6
REV. NO. DATE
DOC NO
6/9/2021
CALCULATED CHECKED
PARTICULARS Chamber 2.4m x2.6mx2.5m

Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 1 4.55 4.75 2.00 43.23 m3
2-4m 1 4.55 4.75 0.38 8.10 m3

51.33 m3

2 Backfill 28.80 m3

3 Disposal
Longwall 2 2.85 0.225 2.00 2.57 m3
Shortwall 2 2.6 0.225 2.00 2.34 m3
Inside chamber 1 2.4 2.6 2.00 12.48 m3
Base Slab 1 3.55 3.75 0.275 3.66 m3
PCC 1.48 m3 22.53 m3

4 PCC 1 3.75 3.95 0.1 1.48 m3 1.48 m3

5 RCC M20 - Below GL


Long wall 2 2.85 0.225 2.00 2.57 m3
Short wall 2 2.6 0.225 2.00 2.34 m3
Base Slab 1 3.55 3.75 0.275 3.66 m3
Pedestal 1 0.5 0.5 0.3 0.08 m3 8.64 m3

6 RCC M20 - Above GL


Long wall 2 2.85 0.225 0.5 0.64 m3
Short wall 2 2.6 0.225 0.5 0.59 m3
Cover slab 1 2.4 2.6 0.150 0.94 m3
Beam 0 3.05 0.3 0.400 0.00 m3 2.16 m3

6 Shuttering BGL
Long wall 4 2.85 - 2.00 22.80 m2
Short wall 4 2.6 - 2 20.80 m2
Base Slab 1 14.6 - 0.275 4.02 m2
Pedestal 1 2 - 0.3 0.60 m2 48.22 m2

7 Shuttering AGL
Long wall 4 2.85 - 0.5 5.70 m2
Short wall 4 2.6 - 0.5 5.20 m2
Cover slab 1 2.4 2.6 - 6.24 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. PHED -FATEHPUR PKG-6
REV. NO. DATE
DOC NO
6/9/2021
CALCULATED CHECKED
PARTICULARS Chamber 2.4m x2.6mx2.5m

Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
Beam 0 3.05 1.1 - 0.00 m2 17.14 m2

7 HYSD Reinforcement
Walls 85 6.13 - - 521.16 kg
Slab 80 4.60 - - 367.76 kg
Pedestal 100 0.08 - - 7.50 kg
Beam 150 0.00 - - 0.00 kg 0.90 MT

8 Ferro cement manhole 1.00 No

9 Structural steel 1.05 10 5.80 60.90 kg 0.06 MT

10 M.S.rungs 8.333 8.33 Nos 9.00 Nos

11 Painting outside
Longwall 2 2.85 - 0.50 2.85 m2
shortwall 2 3.05 - 0.50 3.05 m2 5.90 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Fatehpur PKH 6
REV. NO. DATE
DOC NO
22/11/11
PARTICULAR CALCULATED CHECKED
S chamber -at WTP outlet channel 3m x 2.8m x 2.7m
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 0 5.15 4.95 2.00 0.00 m3
2-4m 0 5.15 4.95 0.65 0.00 m3

0.00 m3

2 Backfill -32.42 m3

3 Disposal
Longwall 2 3.45 0.225 2.20 3.42 m3
Shortwall 2 2.8 0.225 2.20 2.77 m3
Inside chamber 1 3 2.8 2.20 18.48 m3
Base Slab 1 4.15 3.95 0.3 4.92 m3
PCC 2.84 m3 32.42 m3

4 PCC 1 4.45 4.25 0.15 2.84 m3 2.84 m3

5 RCC M20 - Below GL


Long wall 2 3.45 0.225 2.20 3.42 m3
Short wall 2 2.8 0.225 2.20 2.77 m3
Base Slab 1 4.15 3.95 0.3 4.92 m3
Pedestal 1 0.5 0.5 0.3 0.08 m3 11.18 m3

6 RCC M20 - Above GL


Long wall 2 3.45 0.225 0.5 0.78 m3
Short wall 2 2.8 0.225 0.5 0.63 m3
Cover slab 1 3 2.8 0.150 1.26 m3
Beam 0 3 0.3 0.400 0.00 m3 2.67 m3

6 Shuttering BGL
Long wall 4 3.45 - 2.20 30.36 m2
Short wall 4 2.8 - 2.2 24.64 m2
Base Slab 1 16.2 - 0.3 4.86 m2
Pedestal 1 2 - 0.3 0.60 m2 60.46 m2

7 Shuttering AGL
Long wall 4 3.45 - 0.5 6.90 m2
Short wall 4 2.8 - 0.5 5.60 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Fatehpur PKH 6
REV. NO. DATE
DOC NO
22/11/11
PARTICULAR CALCULATED CHECKED
S chamber -at WTP outlet channel 3m x 2.8m x 2.7m
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
Cover slab 1 3 2.8 - 8.40 m2
Beam 0 3 1.1 - 0.00 m2 20.90 m2

7 HYSD Reinforcement
Walls 85 7.59 - - 645.47 kg
Slab 80 6.18 - - 494.22 kg
Pedestal 100 0.08 - - 7.50 kg
Beam 150 0.00 - - 0.00 kg 1.15 MT

8 Ferro cment man hole cover 1.00 No

9 Structural steel 1.05 17.6 5.80 107.18 kg 0.11 MT

10 M.S.rungs 9 9.00 Nos 9.00 Nos

11 Painting outside
Longwall 2 3.45 - 0.50 3.45 m2
shortwall 2 3.25 - 0.50 3.25 m2 6.70 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Fatehpur pkg 6
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED CHECKED
S 2m x 2.2m x 2.2 m-At pallu/sadasar
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 1 3.95 4.15 2.00 32.79 m3
2-4m 1 3.95 4.15 0.08 1.23 m3

34.01 m3

2 Backfill 19.80 m3

3 Disposal
Longwall 2 2.4 0.2 1.70 1.63 m3
Shortwall 2 2.2 0.2 1.70 1.50 m3
Inside chamber 1 2 2.2 1.70 7.48 m3
Base Slab 1 2.95 3.15 0.275 2.56 m3
PCC 1.06 m3 14.22 m3

4 PCC 1 3.15 3.35 0.1 1.06 m3 1.06 m3

5 RCC M20 - Below GL


Long wall 2 2.4 0.2 1.70 1.63 m3
Short wall 2 2.2 0.2 1.70 1.50 m3
Base Slab 1 2.95 3.15 0.275 2.56 m3
Pedestal 0 0.5 0.5 0.3 0.00 m3 5.68 m3

6 RCC M20 - Above GL


Long wall 2 2.4 0.2 0.5 0.48 m3
Short wall 2 2.2 0.2 0.5 0.44 m3
Cover slab 1 2 2.2 0.150 0.66 m3
Beam 0 2.2 0.3 0.400 0.00 m3 1.58 m3

6 Shuttering BGL
Long wall 4 2.4 - 1.70 16.32 m2
Short wall 4 2.2 - 1.7 14.96 m2
Base Slab 1 12.2 - 0.275 3.36 m2
Pedestal 0 2 - 0.3 0.00 m2 34.64 m2

7 Shuttering AGL
Long wall 4 2.4 - 0.5 4.80 m2
Short wall 4 2.2 - 0.5 4.40 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Fatehpur pkg 6
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED CHECKED
S 2m x 2.2m x 2.2 m-At pallu/sadasar
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
Cover slab 1 2 2.2 - 4.40 m2
Beam 0 2.2 1.1 - 0.00 m2 13.60 m2

7 HYSD Reinforcement
Walls 85 4.05 - - 344.08 kg
Slab 80 3.22 - - 257.24 kg
Pedestal 100 0.00 - - 0.00 kg
Beam 150 0.00 - - 0.00 kg 0.60 MT

8 Ferro cement manhole covers 1.00 No

9 Structural steel 1.05 8.4 5.80 51.16 kg 0.05 MT

10 M.S.rungs 7.333 7.33 Nos 8.00 Nos

11 Painting outside
Longwall 2 2.4 - 0.50 2.40 m2
shortwall 2 2.6 - 0.50 2.60 m2 5.00 m2
LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Muscat 135
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED CHECKED
S Diaphragm blocks-150 DN
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 1 1.45 1.45 2.00 4.21 cum

4.21 m3

2 Backfill 3.77 m3

3 Disposal
RCC 1 0.45 0.45 2.00 0.41 cum
PCC 1 0.6 0.6 0.08 0.03 cum

0.43 m3
4 PCC 1 0.6 0.6 0.08 0.03 cum
0.03 m3

5 RCC BGL
RCC 1 0.45 0.45 2.00 0.41 cum 0.41

6 RCC AGL
RCC 1 0.45 0.45 1.3 0.26 cum
Deduct pipe 0.785 0.15 0.15 0.45 0.01 cum
0.26 cum
7 Shuttering BGL
1 1.8 2.000 3.60 Sqm

3.60 Sqm
8 Shuttering AGL
1 1.8 1.30 2.34 cum
2.34 Sqm

9 HYSD
1 100 0.66 66.03 0.07 MT

10 Painting Outside 1 2.34 Sqm


LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Muscat 135
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED CHECKED
S Diaphragm blocks-200 DN
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 1 1.6 1.6 2.00 5.12 cum

5.12 m3

2 Backfill 4.36 m3

3 Disposal
RCC 1 0.6 0.6 2.00 0.72 cum
PCC 1 0.75 0.75 0.08 0.04 cum

0.76 m3
4 PCC 1 0.75 0.75 0.08 0.04 cum
0.04 m3

5 RCC BGL
RCC 1 0.6 0.6 2.00 0.72 cum 0.72 cum

6 RCC AGL
RCC 1 0.6 0.6 1.4 0.50 cum
Deduct pipe 0.785 0.2 0.2 0.6 0.02 cum
0.49 cum
7 Shuttering BGL
1 2.4 2.000 4.80 Sqm

4.80 Sqm
8 Shuttering AGL
1 2.4 1.40 3.36 cum
3.36 Sqm

9 HYSD
1 100 1.21 120.52 0.12 MT

10 Painting Outside 1 3.36 Sqm


LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Muscat 135
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED CHECKED
S Diaphragm blocks-250 DN
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 1 1.75 1.75 2.00 6.13 cum

6.13 m3

2 Backfill 4.94 m3

3 Disposal
RCC 1 0.75 0.75 2.00 1.13 cum
PCC 1 0.9 0.9 0.08 0.06 cum

1.19 m3
4 PCC 1 0.9 0.9 0.08 0.06 cum
0.06 m3

5 RCC BGL
RCC 1 0.75 0.75 2.00 1.13 cum 1.13 cum

6 RCC AGL
RCC 1 0.75 0.75 1.5 0.84 cum
Deduct pipe 0.785 0.25 0.25 0.75 0.04 cum
0.81 cum
7 Shuttering BGL
1 3 2.000 6.00 Sqm

6.00 Sqm
8 Shuttering AGL
1 3 1.50 4.50 cum
4.50 Sqm

9 HYSD
1 100 1.93 193.19 0.19 MT

10 Painting Outside 1 4.50 Sqm


LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Muscat 135
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED CHECKED
S Diaphragm blocks-300 DN
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 1 1.9 1.9 2.00 7.22 cum

7.22 m3

2 Backfill 5.52 m3

3 Disposal
RCC 1 0.9 0.9 2.00 1.62 cum
PCC 1 1.05 1.05 0.08 0.08 cum

1.70 m3
4 PCC 1 1.05 1.05 0.08 0.08 cum
0.08 m3

5 RCC BGL
RCC 1 0.9 0.9 2.00 1.62 cum 1.62 cum

6 RCC AGL
RCC 1 0.9 0.9 1.6 1.30 cum
Deduct pipe 0.785 0.3 0.3 0.9 0.06 cum
1.23 cum
7 Shuttering BGL
1 3.6 2.000 7.20 Sqm

7.20 Sqm
8 Shuttering AGL
1 3.6 1.60 5.76 cum
5.76 Sqm

9 HYSD
1 100 2.85 285.24 0.29 MT

10 Painting Outside 1 5.76 Sqm


LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Muscat 135
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED CHECKED
S Diaphragm blocks-400 DN
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 1 2.2 2.2 2.00 9.68 cum

9.68 m3

2 Backfill 6.66 m3

3 Disposal
RCC 1 1.2 1.2 2.00 2.88 cum
PCC 1 1.35 1.35 0.08 0.14 cum

3.02 m3
4 PCC 1 1.35 1.35 0.08 0.14 cum
0.14 m3

5 RCC BGL
RCC 1 1.2 1.2 2.00 2.88 cum 2.88 cum

6 RCC AGL
RCC 1 1.2 1.2 1.67 2.40 cum
Deduct pipe 0.785 0.4 0.4 1.2 0.15 cum
2.25 cum
7 Shuttering BGL
1 4.8 2.000 9.60 Sqm

9.60 Sqm
8 Shuttering AGL
1 4.8 1.67 8.02 cum
8.02 Sqm

9 HYSD
1 100 5.13 513.40 0.51 MT

10 Painting Outside 1 8.02 Sqm


LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Muscat 135
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED CHECKED
S Diaphragm blocks-600 DN
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 1 2.2 2.2 2.00 9.68 cum

9.68 m3

2 Backfill 6.66 m3

3 Disposal
RCC 1 1.2 1.2 2.00 2.88 cum
PCC 1 1.35 1.35 0.08 0.14 cum

3.02 m3
4 PCC 1 1.35 1.35 0.08 0.14 cum
0.14 m3

5 RCC BGL
RCC 1 1.2 1.2 2.00 2.88 cum 2.88 cum

6 RCC AGL
RCC 1 1.2 1.2 2 2.88 cum
Deduct pipe 0.785 0.6 0.6 1.2 0.34 cum
2.54 cum
7 Shuttering BGL
1 4.8 2.000 9.60 Sqm

9.60 Sqm
8 Shuttering AGL
1 4.8 2.00 9.60 cum
9.60 Sqm

9 HYSD
1 100 5.42 542.07 0.54 MT

10 Painting Outside 1 9.60 Sqm


LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Muscat 135
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED CHECKED
S Diaphragm blocks-600 DN
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 1 2.4 2.4 2.00 11.52 cum

11.52 m3

2 Backfill 7.42 m3

3 Disposal
RCC 1 1.4 1.4 2.00 3.92 cum
PCC 1 1.55 1.55 0.08 0.18 cum

4.10 m3
4 PCC 1 1.55 1.55 0.08 0.18 cum
0.18 m3

5 RCC BGL
RCC 1 1.4 1.4 2.00 3.92 cum 3.92 cum

6 RCC AGL
RCC 1 1.4 1.4 2.05 4.02 cum
Deduct pipe 0.785 0.7 0.7 1.4 0.54 cum
3.48 cum
7 Shuttering BGL
1 5.6 2.000 11.20 Sqm

11.20 Sqm
8 Shuttering AGL
1 5.6 2.05 11.48 cum
11.48 Sqm

9 HYSD
1 100 7.40 739.92 0.74 MT

10 Painting Outside 1 11.48 Sqm


LARSEN & TOUBRO LIMITED
ECC Division – EDRC BILL OF QUANTITIES

JOB NO SHEET
PROJECT. Muscat 135
REV. NO. DATE
DOC NO
6/9/2021
PARTICULAR CALCULATED CHECKED
S Diaphragm blocks-1100 DN
Dimensions
Sl No. Description of Work Numbers Total
No Length Breadth Height Contents or area
/Depth
1 Earthwork Excavation
0-2m 1 2.65 2.65 2.00 14.05 cum

14.05 m3

2 Backfill 8.36 m3

3 Disposal
RCC 1 1.65 1.65 2.00 5.45 cum
PCC 1 1.8 1.8 0.08 0.24 cum

5.69 m3
4 PCC 1 1.8 1.8 0.08 0.24 cum
0.24 m3

5 RCC BGL
RCC 1 1.65 1.65 2.00 5.45 cum 5.45 cum

6 RCC AGL
RCC 1 1.65 1.65 2.375 6.47 cum
Deduct pipe 0.785 1.1 1.1 1.65 1.57 cum
4.90 cum
7 Shuttering BGL
1 6.6 2.000 13.20 Sqm

13.20 Sqm
8 Shuttering AGL
1 6.6 2.38 15.68 cum
15.68 Sqm

9 HYSD
1 100 10.34 1034.29 1.03 MT

10 Painting Outside 1 15.68 Sqm