Project Schedule Management Assignment For Next Class
Project Schedule Management Assignment For Next Class
1
Describe the project schedule management planning
processes and understand contents of a schedule
management plan, activity list, activity attributes,
milestone list, project schedule network diagram,
duration estimates, basis of estimates, schedule
baseline, project schedule, schedule data, and project
calendars
Understand how to find the critical path and its
implications on timely project completion
Explain the concept of critical chain scheduling and
how it can be used in organizations
2
Copyright 2017 Kathy Schwalbe LLC
3
Knowledge
Planning Process Outputs
Area
Plan schedule Schedule management plan
management
Define activities Activity list
Activity attributes
Milestone list
Change requests
4
◦ Scheduling methodology and tools used to create a schedule
model, if required
◦ Level of accuracy required for activity duration estimates
◦ Units of measure, such as staff hours, days, or weeks
◦ Organizational procedure links
◦ Project schedule model maintenance
◦ Control thresholds for monitoring schedule performance, such
as a percentage deviation from the baseline plan
◦ Rules of performance measurement, especially if earned value
management is used
◦ Formats and frequency for schedule reports
Knowledge
Planning Process Outputs
Area
Plan schedule Schedule management plan
management
Define activities Activity list
Activity attributes
Milestone list
Change requests
Project schedule management
5
The process of identifying specific actions to be
performed to produce the project deliverables.
6
Decomposition is a technique used for dividing and
subdividing the project scope and project deliverables
into smaller, more manageable parts.
Activities represent the effort needed to complete a
work package.
The process of “Define Activities” define the final
output as activities rather than deliverables (similar to
the “Create WBS” process).
Activity List
A tabulation of activities to be included on a project
schedule.
Includes the activity name, an activity identifier or number
(WBS ID), and a scope of work description of the activity in
sufficient detail to ensure that project team understands
what work needs to be completed.
7
Activity Attributes
Extend the description of the activity by identifying multiple
components associated with each activity.
Provide schedule-related information about each activity,
such as predecessors, successors, logical relationships, leads
and lags, resource requirements, constraints, imposed dates,
and assumptions related to the activity
8
Copyright 2017 Kathy Schwalbe LLC
9
Copyright 2017 Kathy Schwalbe LLC
10
Activity List and Attributes
August 1
Milestone List
A milestone is a significant point or event in a project.
It often takes several activities and a lot of work to complete a
milestone, but the milestone itself is like a marker to help
identify necessary activities.
There is no cost or duration for a milestone because it
represents a significant point or event.
Sample milestones for many projects include:
◦ Sign-off of key documents
◦ Completion of specific products
◦ Completion of important process-related work, such as awarding a
contract to a supplier
11
Milestone Initial Estimated Completion Date*
Draft survey completed 8/3
Survey comments submitted 8/8
Survey sent out by IT 8/10
Percentage of survey respondents reviewed 8/17
Survey report completed 8/22
Survey results reported to steering committee 8/24
*Note: Dates are in U.S. format. 8/3 means August 3.
Knowledge
Planning Process Outputs
Area
Plan schedule Schedule management plan
management
Define activities Activity list
Activity attributes
Milestone list
Change requests
Project schedule management
12
The process of identifying and documenting
relationships among the project activities.
13
Mandatory dependencies are inherent in the nature of the
work being performed on a project
◦ You cannot hold training classes until the training materials are
ready
14
A schematic display of the logical relationships among, or
sequencing of, project activities.
The preferred technique for showing activity sequencing.
15
Types of Network Diagrams (cont.)
16
Keep in mind that the network diagram represents
activities that must be done to complete the project;
it is not a race to get from the first node to the last
Every activity on the network diagram must be
completed for the project to finish
Not every item on the WBS needs to be on the
network diagram; only activities with dependencies
need to be shown on the network diagram
17
Copyright 2017 Kathy Schwalbe LLC
18
Copyright 2017 Kathy Schwalbe LLC
19
You might want to wait a certain period of time,
perhaps 30 days, after holding the first training class
before holding the second one (a lag of 30 days).
You might want to get started on writing a long
research report 5 days before all of your reference
materials are gathered (a lead of -5 days).
20
Copyright 2017 Kathy Schwalbe LLC 41
Knowledge
Planning Process Outputs
Area
Plan schedule Schedule management plan
management
Define activities Activity list
Activity attributes
Milestone list
Change requests
Project schedule management
21
The process of estimating the number of work periods
needed to complete individual activities with estimated
resources.
◦ The work periods are defined in the Time Management Plan (e.g. hours
of work, days, months)
22
Copyright 2017 Kathy Schwalbe LLC
23
Program Evaluation and Review Technique (PERT) is a
network analysis technique used to estimate project duration
when there is a high degree of uncertainty about the
individual activity duration estimates.
24
Some people prefer using a Monte Carlo simulation over
PERT because it accounts for various probabilities
To perform a Monte Carlo simulation, in addition to the
three-point estimate, you also collect probabilistic
information for each activity duration estimate
◦ For example, estimators must provide a probability of each
activity being completed between the optimistic and most likely
times
◦ You then run a computer simulation to find probability
distributions for the entire schedule being completed by certain
times
25
Knowledge
Planning Process Outputs
Area
Plan schedule Schedule management plan
management
Define activities Activity list
Activity attributes
Milestone list
Change requests
26
Schedule development uses the results of all the preceding
project time management processes to determine the start
and end dates of project activities and of the entire project
The resulting project schedule is often shown on a Gantt
chart, a standard format for displaying project schedule
information by listing project activities and their corresponding
start and finish dates in a calendar format
The ultimate goal of schedule development is to create a
realistic project schedule that provides a basis for monitoring
project progress for the time dimension of the project
27
Copyright 2017 Kathy Schwalbe LLC
28
Critical path method (CPM)—also called critical path
analysis—is a network diagramming technique used to
predict total project duration
A critical path for a project is the series of activities that
determine the earliest time by which the project can be
completed. It is the longest path through the network
diagram and has the least amount of slack or float
◦ Slack or float is the amount of time an activity may be delayed
without delaying a succeeding activity or the project finish date
The longest path or the path containing the critical tasks is
what is driving the completion date for the project
29
The critical path shows the shortest time in which a
project can be completed
If one or more of the activities on the critical path
takes longer than planned, the whole project schedule
will slip unless the project manager takes corrective
action
For example: Apple Computer team members put a
stuffed gorilla on top of the cubicle of whoever was in
charge of a critical task, so they would not distract him or
her
The fact that its name includes the word “critical” does not
mean that the critical path includes all critical activities
Frank Addeman, executive project director at Walt Disney
Imagineering, explained in a keynote address at the May
2000 PMI-ISSIG Professional Development Seminar that
growing grass was on the critical path for building Disney’s
Animal Kingdom theme park
This 500-acre park required special grass for its animal
inhabitants, and some of the grass took years to grow
So, growing grass was driving the completion date of the
theme park; not what most people would think of as a
critical activity!
30
Crashing is a technique for making cost and schedule trade-
offs to obtain the greatest amount of schedule compression
for the least incremental cost.
◦ If two critical tasks each take two weeks, and it will take $100 to
shorten Task 1 by a week and $1,000 to shorten Task 2 by a
week, shorten Task 1
31
Schedule Baseline
The approved version of a schedule that can be changed
only through formal change control procedures.
Used as a basis for comparison to actual results.
Presents approved and accepted baseline start dates
and baseline finish dates by the appropriate stakeholders.
Project Schedule
Presents linked activities with planned dates, durations,
milestones, and resources.
Includes a planned start date and a planned finish date
for each activity at a minimum.
May be presented in summary or detailed forms:
◦ Bar charts or Gantt charts.
◦ Milestone charts.
◦ Project schedule network diagrams.
32
Copyright 2017 Kathy Schwalbe LLC
33