How To Display 4 Baselines On The Gantt Chart in Primavera P6 - Leopard Project Controls

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

 Previous Next 

Course List
HOME COMPANY SERVICES P6 TRAINING CALENDAR SHOP BLOG
Primavera P6
How to Display 4 Baselines on the Gantt chart in Professional
Fundamentals Online
Primavera P6? Training Course
CONTACT US  
Creating the baseline will help the manager analyze the efficiency of
the project’s basic requirements of threat or opportunity. A Gantt
Chart Baseline is the current plan of a project. In comparison, the Upcoming Events
Primavera P6 baseline is the screenshots or images of a project
strategy. These images consist of the real dates, period,
expenditures, and performance of the project. They help to measure
the project plan from all perspectives. Hence, the manager will be Primavera P6 CPM
able to understand the basis of the running project and analyze its Scheduling Class
achievement. (05APR2021-
16APR2021)
In Primavera P6 Proficient, the user can set up and give a project
baseline. He may also set up three user baselines for the sum of
four. He can present all four baselines on the Gantt chart at the same
time. For effective learning about the Primavera P6 efficient project Primavera P6 CPM
performance, the manager has to show different baselines on the Scheduling Class
Gantt chart. This guide article will let you know how to Display 4 (03MAY2021-
Baselines on the Gantt chart in Primavera P6.
14MAY2021)

Steps to Display 4 Baselines on the Gantt chart in


Primavera P6
Generally, there are three essential steps to create the baselines in Popular Recent
Primavera P6 Professional. They are given below;

1. Take a screenshot of the project at the time of baseline


creations Learn about
2. In the next step, assign the baseline our Primavera
3. In the last step, describe the baseline shortly P6 Courses
March 19th, 2020
Image 1 has a timetable of four required baselines.
Claims and
Disputes in
Construction
June 14th, 2020

Using Custom
User-Defined
Fields in
Primavera P6
July 17th, 2020


Removing
This image shows the baseline at the project starting. It is also Partial and All
displaying the three baselines of three development updates.Now Logic within
have a look to create all four of these baselines. the Primavera
P6 Schedule
First of all, click on the ‘project’ bar of the Primavera P6. February 1st,
Choose the ‘maintain baselines’ function. This option will create 2021
the baseline.

Now in image 3, there are four baselines.


Follow us on Twitter
HOME COMPANY SERVICES P6 TRAINING CALENDAR SHOP BLOG

Tweets by
@consultleopard

Leopard Projec
CONTACT US   @consultleopard
It's the most wonderful
night of the year! Merry
Christmas,
everyone!#christmas2020
#merrychristmas

These four baselines are taken on changed dates and are


showing four images.
You can see the data date January 7, 2021, of Construction
Project B4 baseline.
Now, it’s a step to assign the baseline.

Embed View on Twitter

Now click on the project tab and choose Assign Baselines.

Below the image five is showing that the first baseline is assigned at
the start of the Project Baseline.


HOME COMPANY SERVICES P6 TRAINING CALENDAR SHOP BLOG

CONTACT US  

All successful images are step by step assigned to Primary,


Secondary, and Tertiary User Baselines.

After creating and assigning the baselines, we will now see the
display of each baseline on the Gantt chart.

In the next step, as displayed in image 6, we have to choose


the Bar icon in the tool group panel.

In image 7, all four baseline bar’s short descriptions at the lower side
of the stack display in the bar menu.


HOME COMPANY SERVICES P6 TRAINING CALENDAR SHOP BLOG

You can see that each bar description consists of different


CONTACT US  
Timescales. On the other hand, they have identical customary
filters.

From the bar-style menu, you can choose the shape, color,
structure, and row.

If you apply the proper color and style, it will make the description
more instinctive.

If the users select a suitable row and design, it will become more
perceptive.

In image 8, the project baseline’s timescale ‘Project Baseline Bar’


has been shown.

In the bar menu, the style and display of Project Baseline’s row have
been set. You can also see that it has been set to display on row 2.
The style is normal and tall.

In image 9, the primary baseline has scheduled ‘Primary Baseline.’

But now we select a regular l width style.


Keeping in mind the importance of exact shape, we choose the
low position style.

Image 10 is describing the Secondary Baseline Bar schedule’s


‘Second Baseline’. 
HOME COMPANY SERVICES P6 TRAINING CALENDAR SHOP BLOG

Now, it will display on row 3.


CONTACT US  
In image 11, you can see the ‘third Baseline’ having the Tertiary
Baseline Bar schedule.

It is also displayed in row 3.

You can see that all the bar’s description row is normal, heavy, and
low. Hence, the row and style of all bar’s descriptions are clear. Now
try to ensure to clasp on to view all baselines.

Hence, it’s time to set the suitable rows of the baseline bar.
For this purpose, we will click on the view panel and choose the
Font and Row bar.


HOME COMPANY SERVICES P6 TRAINING CALENDAR SHOP BLOG

CONTACT US  
From the Table, Font, and Row menu, click on ‘keep current
row heights’ and set the height for all rows to 32.

Now click on the OK option.

Finally, the Gantt chart and four baseline bars are displayed.


HOME COMPANY SERVICES P6 TRAINING CALENDAR SHOP BLOG

CONTACT US  

Conclusion
From the above detail, you can see that it is possible to show all four
baselines on the Gantt chart in Primavera P6. It consists of the
project baseline; when the project starts, its primary, secondary, and
tertiary baselines, to analyze the plan developed over time. The main
point to show the four baselines depend on the selection of suitable
row and bar design. The shape consists of bar placement and its
style. Primavera P6 Professional never automatically sets the row
height. Hence, it is up to you to set the row height according to the
display of all four baselines on the Gantt chart.

How to Maintain & Importance of What's New in


Backup Primavera P6 Primavera P6 in Primavera P6 Version
Baseline Schedules Construction 19.12?
January 8, 2021 June 1, 2020 August 5, 2020
In "CPM Scheduling" In "Construction" In "Primavera P6"

By Kamran | Cost Control, CPM Scheduling, Primavera P6, Primavera P6 Training,


Project Controls

Share This Story, Choose Your Platform!

        


Related Posts

HOME COMPANY SERVICES P6 TRAINING CALENDAR SHOP BLOG

Leave a Reply

Enter your comment here...

CONTACT US  

ABOUT LEOPARD CURRENTLY CONTACT US SUBSCRIBE TO


PROJECT TRENDING TODAY BLOG VIA EMAIL
CONTROLS, LLC
 Suspending Enter your email
Project Work in  43588 Evergold
Leopard is a certified address to subscribe
Primavera P6 Terrace, Ste 201
Small and Micro to this blog and
business in the Ashburn, VA receive notifications
SWaM program of  How to Create a
20147 of new posts by
Driving
DSBSD in the State Predecessors email.
of Virginia. Report in
Headquartered in Primavera P6  (+1) 571-748-
Northern Virginia, 7635 Email Address
Leopard provides  Primavera P6
Primavera P6 CPM Constraint Types
[email protected] Subscribe
Scheduling services,
Takeoff & Estimating,  How to Display 4
and BIM services to Baselines on the
Gantt chart in
AEC firms. Primavera P6?

 Removing Partial
and All Logic
within the
Primavera P6
Schedule
Read
More  Using and
Managing
Primavera P6
Thresholds

Copyright 2020, Leopard Project Controls, LLC. All Rights Reserved. Oracle® and P6® are registered trademarks and brands of Oracle
Corporation and/or its affiliates. All other marks are the property of their respective owners.
Privacy Policy | Terms of Use | Refund Policy | Contact Us | P6 Training | Services

You might also like