NESIS Regulations
NESIS Regulations
REGULATION NO: XXXX
In exercise of the powers to develop Standards and make Regulations conferred by Sections 81 and
96(1) of the Electric Power Sector Reform Act 2005 (Act No. 6 of 2005) respectively, and all other
powers enabling it in that behalf, the Nigerian Electricity Regulatory Commission makes the following
Regulations for Engineering Designs, Installations, Commissioning and Maintenance of electric power
systems in the Nigerian Electricity Supply Industry.
Page 1 of 282
Table of Contents
NIGERIAN ELECTRICITY SUPPLY AND INSTALLATION STANDARDS REGULATION 2014 ............................................1
1.1 Introduction ........................................................................................................................................... 10
1.2 Scope ..................................................................................................................................................... 10
1.3 Normative References ........................................................................................................................... 10
1.4 Definition of Terms ................................................................................................................................ 16
1.5 General Provisions ..................................................................................................................................... 21
1.5.1 Compliance with the Nigerian Electricity Supply and Installation Standards Regulations ................ 21
1.5.2 Qualification of Engineering Personnel ............................................................................................. 21
1.5.3 Inspection of Electrical Facilities........................................................................................................ 21
1.5.4 Documentation and Reporting Obligations ....................................................................................... 21
1.5.5 Enforcement and Penalty for non‐compliance ................................................................................. 21
1.5.6 Environmental Impact Assessment (EIA) Report ............................................................................... 22
1.5.7 Amendment or Repeal of NESIS ........................................................................................................ 23
1.5.8 Constitution of NESIS Review Panel .................................................................................................. 23
1.5.9 Derogation ......................................................................................................................................... 24
Chapter 2: Transmission Substations .............................................................................................................. 26
2.1 Overview ................................................................................................................................................ 26
2.2 Civil Works ............................................................................................................................................. 26
2.2.1 Civil Design ..................................................................................................................................... 28
2.2.2 Site Preparation ............................................................................................................................. 29
2.2.3 Property Blockwall Fencing ........................................................................................................... 30
2.2.4 Substation Control Building ........................................................................................................... 31
2.2.5 Equipment Plinth ........................................................................................................................... 32
2.2.6 Water Supply, Sewage & Drainage System ................................................................................... 33
2.2.7 Drainage ......................................................................................................................................... 33
2.2.7.1 Design of Drainage: ....................................................................................................................... 33
2.2.7.2 Slope of Drainage System: ............................................................................................................. 33
2.2.8 Cable Trench .................................................................................................................................. 34
2.2.9 Gravelling ....................................................................................................................................... 34
2.2.10 Landscaping ................................................................................................................................... 34
2.3 Electromechanical Works ...................................................................................................................... 35
Page 2 of 282
2.3.1 Substation Design .......................................................................................................................... 35
2.3.2 Equipment Layout.......................................................................................................................... 35
2.3.3 Bus bar Arrangement .................................................................................................................... 35
2.3.4 Major Transmission Equipment..................................................................................................... 36
2.3.5 Secondary Equipment .................................................................................................................... 40
2.4 SCADA System and Installation ............................................................................................................. 44
2.4.1 SCADA Control Room ..................................................................................................................... 44
2.4.2 Remote Terminal Unit (RTUs) ........................................................................................................ 45
2.4.3 Communications ............................................................................................................................ 45
2.5 Health, Safety and Environment............................................................................................................ 45
Chapter 3: Transmission Lines ......................................................................................................................... 46
3.1 Right‐of‐Way ......................................................................................................................................... 46
3.2 Overhead Transmission Conductors ...................................................................................................... 46
3.2.1 Properties of Electrical Conductors ............................................................................................... 47
3.2.2 Load on Overhead Transmission Conductors and Safety Factor ................................................... 48
3.2.3 Jointing and Branching of Electrical Conductors ........................................................................... 48
3.2.4 Aviation Requirements and Warning Signals: ............................................................................... 49
3.2 Insulator for Overhead Transmission Lines ........................................................................................... 49
3.2.1 Mechanical Strength of Insulators for Overhead Transmission Lines ........................................... 49
3.3 Dielectric Strength of Overhead Transmission Lines ............................................................................. 51
3.3.1 Clearance between Supporting Structures and Electrical Conductors ......................................... 51
3.3.2 Dielectric Strength of Overhead Transmission Lines ..................................................................... 51
3.4 Supporting Structures ............................................................................................................................ 51
3.4.1 Steel Structural Members of Supporting Structures ..................................................................... 51
3.4.2 Loads on Supporting Structures and Safety Factor ....................................................................... 55
3.4.3 Loads on Foundations of Supporting Structures and Safety Factor .............................................. 62
3.4.4 Reinforcement of Overhead Transmission Lines ............................................................................... 63
3.5 Regulations for Installation ................................................................................................................... 64
3.5.1 Clearance between Overhead Ground Wires and Electrical Conductors ...................................... 64
3.5.2 Height of Overhead Transmission Conductors and Limitation of Span ........................................ 65
3.5.3 Clearance between Plants and Overhead Transmission Conductors ............................................ 66
3.5.4 Restrictions in Urban Areas ........................................................................................................... 66
3.5.5 Regulations for Side‐by‐side Installation and at Adjacency to and Crossing with Other Objects . 68
Page 3 of 282
3.6 Particulars of Installation for Side‐by‐side Use and at Adjacency to and Crossing with Other Objects 69
3.6.1 Side‐by‐side Use Installation with Other Objects .......................................................................... 69
3.6.2 Installations at Adjacency to and Crossing with Other Objects .................................................... 73
3.7 Protection from Lightning and Falling Trees ......................................................................................... 83
3.7.1 Protection from Lightning ............................................................................................................. 83
3.7.2 Protection from Falling Trees ........................................................................................................ 83
3.7.3 Protection from Intrusion .............................................................................................................. 84
3.7.4 Protection from Mechanical Damage ............................................................................................ 84
3.7.5 Numbering and Danger Notices .................................................................................................... 84
3.8 Underground Transmission Lines .......................................................................................................... 85
3.8.1 Dielectric Strength of Underground Transmission Lines ............................................................... 85
3.8.2 Cables of Underground Transmission Lines .................................................................................. 85
3.8.3 Underground Installation of Cables ............................................................................................... 89
3.8.4 Particulars of Prevention against Underground Electrical Inductive Interference ....................... 92
3.8.5 Underground Installations at Adjacency to and Crossing with Other Objects .............................. 92
3.9 Special Transmission Lines .................................................................................................................... 99
3.9.1 Underwater Transmission Lines .................................................................................................... 99
3.9.2 Transmission Lines Over Bridges and Others ................................................................................ 99
Chapter 4: Injection Substation Installations ................................................................................................ 102
4.1 Civil Works ........................................................................................................................................... 102
4.1.1 Civil Design ................................................................................................................................... 102
4.1.2 Site Preparation ........................................................................................................................... 102
4.1.3 Control Room Building ................................................................................................................. 105
4.1.4 Equipment Plinth ......................................................................................................................... 106
4.2 Electromechanical Works .................................................................................................................... 108
4.2.1 Substation Design ........................................................................................................................ 108
4.2.2 Equipment Layout........................................................................................................................ 109
4.2.3 Busbar/Bay Arrangements .......................................................................................................... 109
4.2.4 Primary Equipment ...................................................................................................................... 110
4.2.5 Secondary Equipment .................................................................................................................. 116
4.3 Health, Safety and Environment.......................................................................................................... 118
4.3.1 Conveniences and Bathrooms ..................................................................................................... 118
4.3.2 Water Supply ............................................................................................................................... 118
Page 4 of 282
4.3.3 Emergency and Standby Systems ................................................................................................ 118
4.3.4 Disposal of Pollutants .................................................................................................................. 119
4.3.5 Switchyard Illumination ............................................................................................................... 119
4.3.6 Electrical Hazards ......................................................................................................................... 119
4.3.7 Fire Fighting and Protection Equipment ...................................................................................... 119
Chapter 5: Distribution Network ................................................................................................................... 120
5.1 General ................................................................................................................................................ 120
5.1.1 Allowable Voltages for Distribution Network .............................................................................. 121
5.1.2 Insulation Requirements for Distribution Network ..................................................................... 122
5.1.3 Earthing of Distribution Network ................................................................................................ 122
5.1.4 Equipment and Installation Devices for Distribution Network ................................................... 122
5.2 Overhead Distribution Lines ................................................................................................................ 123
5.2.1 General ........................................................................................................................................ 123
5.2.2 Routing of Overhead Lines .......................................................................................................... 123
5.2.3 Highway Routes ........................................................................................................................... 123
5.2.4 Overhead Lines with Bare Conductors ........................................................................................ 123
5.2.5 Vehicular Access .......................................................................................................................... 124
5.2.6 Line Conductors ........................................................................................................................... 124
5.2.7 Handling of Electric Supply Lines and Apparatus:‐ ...................................................................... 125
5.2.8 Strength of Material .................................................................................................................... 125
5.2.9 Arrangements .............................................................................................................................. 126
5.2.10 Properties of Distribution Conductors ........................................................................................ 126
5.2.11 Load Bearing Capacity for Overhead Distribution Lines and Safety Factors ............................... 126
5.2.12 Jointing Requirements for Overhead Distribution Conductors ................................................... 128
5.2.13 Dielectric Strength of Insulators of Overhead Distribution Lines ................................................ 128
5.2.14 Guard Lines, Guard Nets and Protective Devices ....................................................................... 129
5.2.15 Electric Lines Crossing Waterways .............................................................................................. 129
5.2.16 Commission’s Decision as Final ................................................................................................... 129
5.2.17 Proximity to Railway Lines ........................................................................................................... 129
5.2.18 Proximity to Telecommunication Lines ....................................................................................... 130
5.2.19 Proximity To Airfield .................................................................................................................... 131
5.2.20 Proximity to Radio, Television, or Telecommunication Aerials ................................................... 131
5.3 Basic Clearances for Installation on Distribution Lines ....................................................................... 137
Page 5 of 282
5.4 Service Drop Lines ............................................................................................................................... 140
5.5 Underground Distribution ................................................................................................................... 149
5.6 Special Distribution Lines .................................................................................................................... 154
Chapter 6: Distribution Substations .............................................................................................................. 157
6.1 Civil Works ........................................................................................................................................... 157
6.2 Basic Distribution Substation Components ......................................................................................... 157
6.2.1 Distribution Transformers ........................................................................................................... 157
6.2.2 Connection Cables ....................................................................................................................... 157
6.3 LV Distribution (Feeder Pillar) Panels .................................................................................................. 158
6.3.1 Structural and Mechanical Specifications ................................................................................... 158
6.3.2 Electrical Insulations .................................................................................................................... 158
6.3.3 Metering ...................................................................................................................................... 158
6.4 Compact Distribution Substation ........................................................................................................ 158
6.5 Pole Mounted Distribution Substation ................................................................................................ 159
Chapter 7: User’s Sites Electrical Installations .............................................................................................. 160
7.1 General Provisions ............................................................................................................................... 160
7.2 Indoor Installation ............................................................................................................................... 160
7.2.1 Electrical Design ........................................................................................................................... 160
7.2.2 Restriction of Indoor Lines Voltage ............................................................................................. 160
7.2.3 Indoor Wiring Cables ................................................................................................................... 161
7.2.4 Utilization and Restriction of Bare Conductors for Indoor Wiring .............................................. 192
7.2.5 Electrical Conductors Used for Indoor Wiring ............................................................................. 194
7.2.6 Allowable Current of Indoor Wirings ........................................................................................... 195
7.2.7 Indoor Wiring Works ................................................................................................................... 197
7.2.8 Installation of Mains for Electrical Circuits .................................................................................. 200
7.2.9 Installation of Branch Circuits ...................................................................................................... 201
7.2.13 Switching Devices at the Indoor Main Lines ................................................................................ 203
7.2.14 Control of Supply to User Site Installation .................................................................................. 205
7.2.15 Appliances.................................................................................................................................... 220
7.2.16 Preventions of Interferences Caused By High Frequency Current, Voltage Flickers And Dips ... 223
7.2.17 User’s Site Protection and Over Current Circuit Breakers for Electric Motors ............................ 224
7.2.18 Indoor Electrical Equipment and Appliances ............................................................................... 226
7.3 Special Installation ............................................................................................................................... 227
Page 6 of 282
7.3.1 Traffic Signals ............................................................................................................................... 227
7.3.2 Public Street lamps ...................................................................................................................... 228
Chapter 8: Protection, Control and Metering .............................................................................................. 230
8.1 Protection Systems Installations ......................................................................................................... 230
8.1.1 Transmission Systems Protection ....................................................................................................... 230
8.2 Power Systems Metering Installations ................................................................................................ 232
8.3 Digital Events Recorders ...................................................................................................................... 232
8.4 SCADA Systems Installations ............................................................................................................... 232
8.4.1 SCADA Control Room ................................................................................................................... 233
8.4.2 Remote Terminal Unit (RTUs) ...................................................................................................... 233
8.4.3 Communications .......................................................................................................................... 233
8.4.4 Geographic Information Systems (GIS) ....................................................................................... 233
Chapter 9: Classification of Equipment and Types of Tests ......................................................................... 234
9.1 Power and Distribution Transformers ................................................................................................. 235
9.1.2 Continuity Test ............................................................................................................................. 236
9.1.3 Vector Group ............................................................................................................................... 236
9.1.4 Ratio Test ..................................................................................................................................... 236
9.1.5 Magnetic Balance Test ................................................................................................................. 236
9.1.6 D.C. Winding Resistance Check ................................................................................................... 236
9.1.7 Insulation Resistance Test ........................................................................................................... 237
9.1.8 Phasing and Polarity .................................................................................................................... 238
9.1.9 Continuity Tests ........................................................................................................................... 238
9.1.10 Vector group ................................................................................................................................ 238
9.2 Earth Resistance Tests ......................................................................................................................... 239
9.2.1 Transmission and Distribution Requirements ............................................................................. 239
9.2.2 Soil Resistance Tests .................................................................................................................... 240
9.2.3 Current Transformers .................................................................................................................. 240
9.2.4 Excitation Tests ............................................................................................................................ 240
9.2.5 Primary Injection/Ratio Tests ...................................................................................................... 240
9.2.6 Voltage Transformers .................................................................................................................. 240
9.3 High and Medium Voltage Cables ....................................................................................................... 241
9.4 Circuit Breakers ................................................................................................................................... 241
9.5 Lightning Arresters .............................................................................................................................. 242
Page 7 of 282
9.6 Substation D.C Supply (Batteries and Battery Charger System) .......................................................... 244
9.7 Relays ................................................................................................................................................... 245
9.7.1 Standards and Specifications ....................................................................................................... 245
9.7.2 Relay Tests ................................................................................................................................... 246
9.7.3 Adverse Conditions ...................................................................................................................... 246
9.7.4 Tests on Relay Circuits ................................................................................................................. 246
9.7.5 Primary Injection Tests ................................................................................................................ 246
9.7.6 Secondary Injection Tests ............................................................................................................ 246
9.7.7 Pick –up Current .......................................................................................................................... 246
9.7.8 Calibration of Relays .................................................................................................................... 246
9.7.9 Relay Application Tests ................................................................................................................ 247
9.7.10 Maintenance ................................................................................................................................ 247
Chapter 10: Inspection Checks and Preventive Maintenance ........................................................................ 248
10.1 Transmission Installation ..................................................................................................................... 248
10.2 Distribution Installation ....................................................................................................................... 248
10.3 Consumer Installation.......................................................................................................................... 249
10.3.1 Inspection Checks of User’s Site Electrical Installations .............................................................. 249
10.3.2 Testing of Low Voltage Installations ............................................................................................ 250
Chapter 11: Earthing ....................................................................................................................................... 254
11.1 General provisions ............................................................................................................................... 254
11.7 Earthing in Commercial Premises .................................................................................................... 261
11.7.1. Earth leakage ........................................................................................................................... 261
11.8 Earthing in Industrial Premises ........................................................................................................ 262
11.9 Earthing in Construction Sites ......................................................................................................... 263
11.10 Earthing in Mobile Sites ................................................................................................................... 263
11.11 Stand‐by Generator Installation ...................................................................................................... 263
11.12 Steel Poles and Street Lighting Columns ......................................................................................... 265
11.13 Tower Earthing ................................................................................................................................ 266
11.14 Equipment Earthing ......................................................................................................................... 267
11.4.1 Substations .................................................................................................................................. 267
Chapter 12: Generation ................................................................................................................................... 268
12.1 Site Requirements ............................................................................................................................... 268
12.1.1 Site Approval ............................................................................................................................... 268
Page 8 of 282
12.1.2 Documentation ............................................................................................................................ 268
12.1.3 Geotechnical Investigations ........................................................................................................ 268
12.1.4 Hydrology .................................................................................................................................... 268
12.1.5 Water Permit ............................................................................................................................... 268
12.1.6 Environmental Impact Assessment (EIA) ..................................................................................... 268
12.2 Plant Design ......................................................................................................................................... 269
12.2.1 Fuel Handling ............................................................................................................................... 269
12.2.1 Technical Documentation ............................................................................................................ 270
12.3 Construction of Power Plants .............................................................................................................. 270
12.3.1 Responsibilities of the Licensee or Contractor ............................................................................ 270
12.3.2 Responsibilities of the Project Manager ...................................................................................... 270
12.3.3 Pre‐Requisites For Commencement Of Construction ................................................................. 271
12.3.4 Pre‐Construction Site Meeting .................................................................................................... 272
12.3.5 Environmental Health and Safety Induction ............................................................................... 273
12.3.6 Site Health and Safety Plan.......................................................................................................... 274
12.3.7 Water Management .................................................................................................................... 275
12.3.8 Emission and Effluent Limitations ............................................................................................... 276
12.3.9 Solid Wastes ................................................................................................................................ 278
12.3.10 Ambient Noise ......................................................................................................................... 278
12.3.11 Record Keeping ........................................................................................................................ 279
12.4 Power Evacuation ............................................................................................................................ 280
12.4.1 Voltage Levels: ............................................................................................................................. 280
12.4.2 Voltage Variations: ...................................................................................................................... 280
12.4.3 Frequency Level: .......................................................................................................................... 280
12.4.4 Frequency Variations: .................................................................................................................. 280
12.4.5 Technical Criteria for Plant and Apparatus at the Inter ‐ Connection Point ............................... 280
12.4.6 Performance Requirements for Power Stations: ........................................................................ 281
12.5 Penalties for Non Compliance. ............................................................................................................ 282
Page 9 of 282
1.1 Introduction
This introduction does not form part of these Regulations. The Regulations is a compendium of
standards for the design, construction and commissioning of electrical infrastructure in the Nigeria
Electricity Supply Industry approved by the Nigerian Electricity Regulatory Commission to replace the
Electricity Supply (S. I. 5) Regulations and the Electrical Installation Regulations (S.I.6) of 1996 issued
under the repealed Electricity Act. The Commission derived its power to repeal these regulations from
Section 98 of the Electric Power Sector Reform Act 2005. The new regulations is named “Nigeria
Electric Supply and Installation Standards Regulations”
These Regulations include areas on design, construction, and commissioning of the power system in
Nigeria through the value chain of electricity generation, transmission, distribution and utilisation not
covered in Grid Code, Distribution Code, Metering Code and Health & Safety Code as amended.
Fundamentally it covers standards of materials, equipment and process with normative references to
the EPSR Act, NERC technical Codes, IEC standards, and more as enumerated in the Normative
Reference.
A Technical Working Group (TWG-NESIS Regulations) under the leadership of the Nigerian Society of
Engineers (Nigeria Institution of Electrical Electronics Engineers-A Division of the Nigerian Society of
Engineers) was formed with the sole responsibility of producing a draft regulation to replace the S.I.5
and S. I. 6 Regulations. The complete list of membership and organisation represented is in Section
1.5. Four subcommittees of the TWG-NESIS Regulation produced the draft in five sessions over a
period of fifteen months. The subcommittees are Transmission, Distribution, User’s Site and
Generation committees.
1.2 Scope
This document describes the requirements regulating the generation, transmission, distribution, and
user’s site standards, guides, and recommended practices for use in the Nigeria Electricity Supply
Industry (NESI).
The following normative documents contain provisions, which, through reference in this text constitute
provisions of this International Standard. At the time of publication, the editions indicated were valid.
All normative documents are subject to revision, and parties to agreements based on these
International Standards are encouraged to investigate the possibility of applying the most recent
editions of the normative documents indicated below. Members of IEC and ISO maintain registers of
currently valid International Standards.
Distribution Code
Grid Code
Metering Code
Page 10 of 282
Reporting Compliance Regulations 2009
IEC 60076 – 2: Power transformers – Part 2: Temperature rise for liquid-immersed transformers
IEC 60076 – 3, Power transformers - Part 3: Insulation levels, dielectric tests and external clearances
in air
IEC 60076 – 4, Power transformers-Part 4: Guide to the lightning impulse and switching impulse
testing-power transformers and reactors
IEC 60076 – 7, Power transformers – Part 7: Loading guide for oil immersed power transformers
IEC 60076 – 10, Power transformers – Part 10-1: Determination of sound levels – Application guide
IEC 60076 – 13, Power transformers – Part 13: Self-protected liquid-filled transformers
IEC 60076 – 14, Power transformers – Part 14: Design and application of liquid-immersed power
transformers using high-temperature insulation materials
IEC 60296: Fluids for electrotechnical applications - Unused mineral insulating oils for transformers
and switchgear
IEC 60273: Characteristic of indoor and outdoor post insulators for systems with nominal voltages
greater than 1000 V
NIS IEC 61850: Communication networks and systems in substations - ALL PARTS s
IEC 61089: Round wire concentric lay overhead electrical stranded conductors
IEC 60028: International standard of resistance for copper
IEC 60104: Aluminium-magnesium-silicon alloy wire for overhead line conductorsIEC 60383-1:
Insulators for overhead lines with a nominal voltage above 1000 V - Part 1: Ceramic or glass insulator
units for a.c. systems - Definitions, test methods and acceptance criteria
IEC 60840: Power cables with extruded insulation and their accessories for rated voltages above 30
kV (Um = 36 kV) up to 150 kV (Um = 170 kV) - Test methods and requirements
IEC 60502-2: Power cables with extruded insulation and their accessories for rated voltages from 1
kV (Um = 1,2 kV) up to 30 kV (Um = 36 kV) – Part 2: Cables for rated voltages from 6 kV (Um = 7,2 kV)
up to 30 kV (Um = 36 kV)
IEC 60364-5-54: Low-voltage electrical installations - Part 5-54: Selection and erection of electrical
equipment - Earthing arrangements and protective BS 8004: Foundations for the Design and
construction of Injection Substation foundations
BS 5950:Structural use of steelwork in building code of practice for design rolled and welded sections
Page 12 of 282
BS 8007:Code of practice for design of concrete structures for retaining aqueous liquids
IEC 60335-2-76: Household and similar electrical appliances - Safety - Part 2-76: Particular
requirements for electric fence energizers
IEC 60694: Common clauses for high-voltage switchgear and controlgear standards.
IEC 62271-200: High‐voltage switchgear and controlgear ‐ Part 200: AC metal‐enclosed switchgear and
controlgear for rated voltages above 1 kV and up to and including 52 kV
IEC 60529: Degrees of protection provided by enclosures (IP Code)
IEC 60099 - Lightning or surge arrester devices for protection of all substations, intersection of
overhead lines and underground cables from lightning and switching surges
IEC 61954 Static VAr Compensator installed on medium voltage distribution for power quality
improvement of the network
IEC 61400-Dynamic Voltage Restorers or Series Voltage Booster device installed to mitigate against
voltage sags, spikes, harmonics and in-voltage variations
IEC 60871-Shunt capacitors installed in the Injection Substations-Each capacitor unit is designed,
rated, manufactured, and tested
IEC 61089-Classes and qualities of aluminium conductors applicable in distribution overhead network
Page 13 of 282
B.S. 125, 1970: for Copper or Copper Equivalent
IEC 60173: Colours of the cores of flexible cables and cords:High‐voltage switchgear and controlgear ‐ Part
202: High‐voltage/ low‐voltage prefabricated substation
IEC 60079-0: Explosive atmospheres ‐ Part 0: Equipment ‐ General requirements
IEC 60227:Polyvinyl chloride insulated cables of rated voltages up to and including 450/750 V ‐ Part 1: General
requirements
BS5266-1 -Where indoor lighting is designated for emergency purposes in such places as hospitals,
entertainment venues, schools, industrial premises, hotels amongst others
IEC 60598-2-3: Luminaires ‐ Part 2‐3: Particular requirements ‐ Luminaires for road and street lightingIEC
60092-306:Electrical installations in ships ‐ Part 306: Equipment ‐ Luminaires and lighting accessories
IEC 60364-7-704: Low‐voltage electrical installations ‐ Part 7‐704: Requirements for special installations or
locations ‐ Construction and demolition site installations
IEC 60364-7-705: Low‐voltage electrical installations ‐ Part 7‐705: Requirements for special installations or
locations ‐ Agricultural and horticultural premises
IEC 60364-7-701:Low‐voltage electrical installations ‐ Part 7‐701: Requirements for special installations or
locations ‐ Locations containing a bath or shower
IEC 60364-7-711:Electrical installations of buildings ‐ Part 7‐711: Requirements for special installations or
locations ‐ Exhibitions, shows and stands
Page 14 of 282
IEC 60335-2-75-Households and similar electrical appliances particular requirement for commercial
dispensing appliances and bending machines
IEC 61850:Communication networks and systems in substations ‐ ALL PARTS
IEC 608-70-104 - Communication between Substation Automation System (SAS) and power plant
devices
NIS IEC 60557-Dissolved gas analysis carried out on all transformers periodically
IEC 60726:Dry‐type power transformers
IEC 60502-2: Power cables with extruded insulation and their accessories for rated voltages from 1 kV (Um =
1,2 kV) up to 30 kV (Um = 36 kV) – Part 2: Cables for rated voltages from 6 kV (Um = 7,2 kV) up to 30 kV (Um = 36
kV)
IEC 60898: Electrical accessories ‐ Circuit‐breakers for overcurrent protection for household and similar
installations
IEC 62271-200: High‐voltage switchgear and controlgear ‐ Part 200: AC metal‐enclosed switchgear and
controlgear for rated voltages above 1 kV and up to and including 52 kV
IEC 60099 -8: Surge arresters ‐ Part 8: Metal‐oxide surge arresters with external series gap (EGLA) for
overhead transmission and distribution lines of a.c. systems above 1 kV
2, 3 & 4-for the design, selection and specification of lightning arresters for use in distribution
networks
Page 15 of 282
IEC 60099-8Surge arresters - Part 8: Metal-oxide surge arresters with external series gap (EGLA) for
overhead transmission and distribution lines of a.c. systems above 1 kV
IEC 60255-1: Measuring relays and protection equipment - Part 1: Common requirements
IEC 60255-Electrostatic relay which are relays that do not have moving parts used
IEC 61810-7: Electromechanical elementary relays - Part 7: Test and measurement procedures
IEC 60364-5-54: Low-voltage electrical installations - Part 5-54: Selection and erection of electrical
equipment - Earthing arrangements and protective conductors
IEEE 519Guide-for-Harmonic-Control-and-Reactive-Compensation-of-Static-Power-ConvertersBS
7671-2008:Every means of earthing to be selected and erected
Word Definition
Arcing Horn (Sometimes arc-horns) are projecting conductors used to protect insulators on
high voltage electric power transmission systems from damage
during flashover.
Bayonet cap Cap (international designation B) with bayonet pins on its shell which engage in
slots in a lamp holder
Buchholz Is a gas and oil operated device installed in the pipe‐work between the top of the
transformer main tank and the conservator
Captive Generation Generation of electricity for the purpose of consumption by a licensee itself and
not sold to a third party
Catenary a longitudinal cable supporting the contact wire or wires either directly or
indirectly
Cold-rolled -
Page 16 of 282
COREN Council for the Regulation of Engineering in Nigeria
CT Current Transformer
D – Iron Mechanical support for low tension overhead lines manufactured and
fabricated in the form of D shape to provide support for the porcelain insulators
Earth mat Earth mat is an earth electrode that is manufactured or fabricated in the form of
a mat.
Equi-Potential Refers to a region in space where every point in it is at the same potential;
always perpendicular to the electric field
Extraneous Conductive part not forming part of the electrical installation and liable to
introduce an electric potential, generally the electric potential of a local earth
Furan Analysis Test on transformer oil that indicates the degree of depreciation of paper
insulation.
Gantry guy Gantry: A bridge like overhead structure supporting equipment such as a crane
or a tall framework supporting a space rocket prior to launching.
Generating Station means a station for generating electricity, including buildings, plant and
machinery and all accessories used for that purpose and the site to be used for
the station or accessories
Grid Code means instructions, rules, procedures, guidelines, etc., for the operation and
planning of an interconnected power system and accounting requirements
relating thereto
Guy assembly Guy: a steel wire rope or rod, working under tension, connecting a point of a
support to a separate anchor, or connecting two points of the support
Interturn Fault an insulation fault between neighboring turns of the same winding in a coil
Interutility Any transfer of allowances from one utility operating company's account to a
different utility operating company's account, provided the operating companies
are not controlled by the same parent company. Both transferor and transferee
Page 17 of 282
accounts can be either general or unit accounts.
Kingbolts A vertical iron bolt, by which the forward axle and wheels of a vehicle or the
trucks of a railroad car are connected with the other parts.
Knee Point Voltage is the maximum secondary voltage that the CT will provide to a standard
burden without saturating the transformer
Licensee means any person who holds a licence issued under Part IV of the EPSR Act
2005;
Lighting Arresters is a device used on electrical power systems and telecommunications systems
to protect the insulation and conductors of the system from the damaging
effects of lightning
Opepe wood A typical West African tree that yields timber that is used in harbor work
because of its resistance to marine borers.
Page 18 of 282
Person includes an individual, company, partnership or any other association of
individuals, whether incorporated or not;
Pilot Cables a control cable laid in parallel with a power cable and intended for transmitting
signals related to the operation of that cable
Prima facie a Latin expression meaning accepted as correct until proved otherwise
SCADA Supervisory Control and Data Acquisition; a computer system for gathering
and analyzing real time data
Synchronism the state in which two time-varying phenomena, time-scales, or signals are
identical
Toe compression A steel-toe boot (also known as a safety boot, steel-capped boot or safety
shoe) is a durable boot or shoe that has a protective reinforcement in the toe
which protects the foot from falling objects or compression, usually combined
with a mid sole plate to protect against punctures from below
Tower Footing The ohmic resistance between a transmission-line tower and the earth.
Resistance
Vector Group the IEC method of categorizing the high voltage (HV) windings and low voltage
(LV) winding configurations and angular displacement between them of three-
phase transformers.
Vermin pests or nuisance animals, especially those that threaten human society by
spreading diseases.
Page 19 of 282
Wide Area This is a protection type used to save the system from partial or total blackout
Protection or brownout in operational situations when no particular equipment is faulty or
operated outside its limitations. The situation could appear after the clearance
of a very severe disturbance in a stressed operation situation or after an
extreme load growth. Since it is a protection system, it will operate in such
operational situation when the power systems will breakdown if no protective
actions were taken.
Page 20 of 282
1.5 General Provisions
1.5.1 Compliance with the Nigerian Electricity Supply and Installation Standards
Regulations
Any person engaged in the generation, transmission, distribution, system operation, and trading in
electricity or in any aspect in the chain of supply of electricity, including but not limited to engineering
designs, installations, commissioning and maintenance of electric power systems for the purpose of
achieving safe and reliable supply, and utilization of electricity in Nigeria, shall comply with the
provisions of the Electric Power Sector Reform (EPSR) Act 2005, The Nigerian Electricity Supply and
Installation Standards (NESIS), license terms and conditions and all other regulations, Codes,
Standards made pursuant to the EPSR Act.
1.5.3.2. Pursuant to Section 95 of the EPSR Act, the Commission may appoint inspectors to inspect
electrical facilities to ensure safety of operations and compliance with the EPSR Act, NESIS,
Distribution Code, Grid Code, Metering Code and any other regulation, Codes and Standards made
pursuant to the EPSR Act.
(i) The proper documentation of its activities and processes in accordance with the provisions
of the EPSR Act, NESIS, Distribution Code, Grid Code, Metering Code and any other
regulations, Codes, and Standards applicable to it and made pursuant to the EPSR Act.
(ii) Compliance with reporting obligations in the EPSR Act, NESIS, Reporting Compliance
Regulations 2009, Distribution Code, Grid Code, Metering Code and any other regulations,
Codes and Standards applicable to it and made pursuant to the EPSR Act.
Page 21 of 282
1.5.5.1. Pursuant to Section 75 & 94 (1) of the EPSR Act and without prejudice to the Enforcement
Regulations, any person who contravenes or violates any provisions of the NESIS commits an offence
and is liable on conviction, where no specific penalty is prescribed therefore:
(i) As a first offender to a fine not exceeding N100, 000.00 (One Hundred Thousand Naira)
only or to imprisonment for a period not exceeding 1(one) year or to both fine and
imprisonment; or
(ii) For subsequent convictions to a fine not exceeding N500, 000.00 (Five Hundred Thousand
Naira) or to imprisonment for a period not exceeding 3 (three) years or to both fine and
imprisonment.
(i) Fails or refuses to furnish a return or to supply information in the manner or in the time
prescribed or furnishes a false or incomplete return or supplies false or incomplete
information; or
(ii) Delays, obstructs or prevents an inspector appointed by the Commission from carrying out
the inspection; or
(iii) Fails or refuses, without reasonable cause to give information to an inspector when
required to do so by the Inspector, or gives false, misleading or incomplete information;
(iv) Commits an offence and is liable on conviction to imprisonment not exceeding one year or
to a fine not exceeding N100, 000 (One Hundred Thousand Naira).
1.5.5.3.1.Without prejudice to the provisions of the EPSR Act 2005 and notwithstanding the provisions
of other Regulations made pursuant thereto, the Commission may impose administrative fines of not
more than N10, 000.00 (Ten Thousand Naira) per day, on any licensee, other undertaking or any
person involved in the business of electricity generation, transmission, distribution, trading, system
operation or any other aspect of the electricity supply chain, who contravenes or violates any provision
of the NESIS.
1.5.5.3.2. The fine imposed shall be calculated on a daily basis and shall be in force until the violation
or contravention is abated or discontinued.
(i) In the case of a licensee, lead to the suspension or removal of the licensees management
by the Commission;
(ii) In the case of other undertaking, lead to the Commission issuing directives to a licensee to
take over operations of the undertaking.
Page 22 of 282
1.5.6.2. The EIA Certificate shall always be prominently displayed in the principal place of business of
the licensee or person and shall be renewed as and when due.
1.5.7.2. The Panel may on its own or upon receipt of a request for a review of NESIS from the
respective power industry participants or members of the public through the Chairman of the NESIS
Review Panel, first consider the request for a review before forwarding the request to the Commission
for consideration.
1.5.7.3. In considering the request for a review, the Panel shall consult and expose the proposal to
industry stakeholders and operators for their comments, and the Panel shall provide evidence of this
consultation together with their comments to the Commission in seeking the Commissions consent for
amendment.
1.5.7.4. Upon the consideration of the request for review and or amendment as submitted by the
NESIS Review Panel and other further representations and views made in respect of the proposed
amendment, the Commission shall approve the amendment as requested or in an amended form, or
reject the amendment.
i. Generation Companies
ii. Transmission Company
iii. Distribution Companies
iv. Trading Companies
v. System operator
vi. Representatives of Consumers
vii. Representatives of COREN
viii. Representative of electric network inspectors
ix. Legal Experts
x. The Commission
1.5.8.3. The panel shall be a standing body to carry out the functions referred to in the NESIS, and
shall be maintained and funded by the Electricity Market.
Page 23 of 282
1.5.8.5. Composition of membership of the NESIS Review Panel shall be as follows and each of the
members shall be appointed by their respective industry sector. Each member shall be COREN
registered professional except the two(2) legal experts;
1.5.8.6. The Chairman and Secretary of the Review Panel shall be elected by a simple majority of
members present and voting.
. The Review Panel shall have the following functions amongst others;
1.5.9 Derogation
1.5.9.1. If a licensee or person involved in the business of electricity generation, transmission,
distribution, system operation, trading or in any other aspect of the electricity supply chain, finds that it
is or will be unable to comply with any of the provisions of NESIS, then such licensee, other
undertaking or any person involved in the electricity supply chain, shall comply fully with the processes
for seeking derogation outlined in the " Derogation" provisions of the Grid Code, Distribution Code,
Metering Code, but in particular, if such undertaking is not a licensee, it shall;
i. Without delay, report such inability to comply, to the distribution company within its area of
operation and shall make such reasonable efforts as are required to remedy such non-
compliance as soon as is reasonably practicable.
ii. If such an undertaking is a licensee, it shall without delay, report such inability to comply
with the Commission and shall make such reasonable efforts as are required to remedy
such non-compliance as soon as practicable.
1.5.9.2. A request for derogation shall contain from any provisions of the NESIS shall contain;
Page 24 of 282
i. The details of the equipment and connection point in respect of which derogation is sought
and the nature of and extent of non compliance
ii. The provision of licensee or person NESIS, which the licensee or person has stated, it
might not be able to comply with.
iii. The reason for its inability to comply.
iv. The remedial actions and the date by which compliance could be achieved.
1.5.9.3. On receipt of any request for derogation, the Commission shall ensure that consent is not
unreasonably withheld, PROVIDED that the Commission promptly considers the reasonableness of
such a request.
1.5.9.4. In considering a request for derogation, the Commission may contact the licensee or person
for further clarification on the request, or seek further information and additional information or to
discuss changes to the request, and review possible remedial actions to achieve compliance as soon
as reasonably practicable.
1.5.9.5. Any request for derogation to a licensee by other undertaking, shall on application by the
licensee obtain the Commission's consent after consideration of the request by the Commission,
PROVIDED that the licensee makes available to the Commission all relevant documents and
information that will enable it reach a reasonable decision.
Page 25 of 282
Chapter 2: Transmission Substations
2.1 Overview
These standards outline the Standard Technical Requirements for the construction of civil works and
buildings for the 330/132/33 kV Transmission and Sub-transmission Substations of the National Grid
of Nigeria.
a. All structures, buildings, foundations and layout shall be designed and developed in
accordance with the operational and technical functional requirements of the line and sub-
station facilities.
b. All design and construction including all materials, testing and other procedures shall be
undertaken in accordance with Nigerian Electricity Supply Industry Standards regulation.
c. All aspects of the civil works shall be designed to provide a low maintenance durable end
product suitable for the purpose intended. Particular emphasis shall be placed on security of
the site. Design life for structural elements shall be a minimum of 50 years.
d. The design of buildings and structures shall be in accordance with the requirements of the
Nigerian Building Code (NBC), and shall be carried out in such a manner to ensure that
construction, maintenance and demolition are carried out in a safe manner.
e. Structures shall be designed and built to an approved standard and finishing shall be
aesthetically acceptable.
f. The design of the civil works and the specification of civil materials shall take into account the
environmental impact of all elements. At all times, ’environmentally friendly’ materials shall be
incorporated into the works.
g. There shall be adequate provision made to prevent and limit fire damage including properly
designed and constructed firewalls between Power Transformers. This shall be in accordance
with NERC Health and Safety Code.
h. This regulation shall also be used as a guide for clearances around switchgear and other
equipment. Power and control cables shall be routed and/or segregated such that minimal loss
of control or supplies occurs in the event of fire or damage.
i. If any object of archaeological value is found during excavation the contractor or any third
party shall report to the relevant agency.
j. This regulation shall be read in conjunction with other relevant Regulations and Codes of
Practice published by NERC.
k. In case, there are discrepancies between the requirements stipulated herein and the other
Regulations and Codes of Practice, this regulation shall prevail.
l. The requirements in this standard may be reviewed as new equipment become available, new
technologies being developed or because of new requirements.
Page 26 of 282
with drainage to evacuate water in all conditions and of sufficient size to allow access
to maintenance equip ment and gravelling of switchyard surface.
ii. Fences along the perimeter of the substation for security of the installation, foundations
for equipment pedestals, bus supports and gantry structures for incoming lines and
strain buses.
iii. Concrete cable trenches and imbedded ducts with pulling boxes and cable pits.
iv. Access roads and switchyard maintenance roads, drainage network made of perimeter
trenches, switchyard internal sub soil drainage trenches or pipes.
v. Power transformers and reactors oil containment basin with oil/water separator.
vi. Substation Control building, with sanitary and water supply installations.
vii. Other related works to make a complete installation as may be required.
a. Substation construction project procedure shall include all site data gathering, analysis and
engineering design necessary for the construction namely:
i. Topographical survey
ii. Geotechnical soil investigation
iii. General location drawing with reference coordinates and surrounding
iv. Drawings of earthworks
v. Drainage system with construction details
vi. Access road drawings
vii. Foundation layout drawings with detailed design of each foundation including
calculation brief and bill of armour rods.
viii. Cable trenches layout and details
ix. Fences and access gate
x. Concrete retaining wall with calculation brief and bill of armour rods
xi. Comprehensive architectural drawings of each building and dependency showing
layout, side view, finishing materials, list of main components, sanitary accessories and
carpentry.
xii. Building structure drawings with calculation brief and bill of armour rods
xiii. Building electrical distribution diagram with bill of materials
xiv. Sewage system with piping, septic tank, filtration pit, drainage.
b. Every project, be it a replacement, upgrade or new building, the ground shall be levelled to
provide a flat and stable surface for the foundations.
c. The building shall be made in such a way to withstand prevailing environmental situation.
d. For sites that are exposed to pollution, for example in heavily industrialized areas or exposed
to salt pollution, there shall be a building to install sensitive equipment.
e. Excavation for foundations shall be made and steel reinforcement or piles installed where
necessary, before casting of concrete. This forms the platform on which the equipment shall
be supported or building in which the equipment shall be housed.
f. All brickwork and block work shall be of an approved standard. Internal walls shall be
constructed to give a durable, low maintenance, dust free finish and shall be painted with
smooth masonry paint. The final coat of paint is to be applied after installation of electrical
equipment.
g. All brickwork and block work shall be laid in mortar of appropriate strength for the location and
exposure of the wall, and solid walls of one brick thickness or greater to be cross bonded or
tied together with stainless steel reinforcement or ties.
Page 27 of 282
h. Where expansion or contraction joints are incorporated, they shall be constructed with
approved joint filler and finished with appropriate sealant.
i. The building shall be designed to be as ‘energy efficient’ as possible while accommodating the
various cables entries required.
j. Windows shall be provided for daylight conditions or ventilation in substation building and
adequate mechanical ventilation shall be considered according to extant Building Regulations.
k. Emergency exit shall be provided.
l. Substations and switch stations shall preferably be erected above ground but where
necessarily constructed underground there shall be due provision for ventilation and drainage.
b. General arrangement drawing shall include floor layout and indicating clearances
between and around equipment, plant ingress/egress, emergency egress, fire
segregation, cable entry and outgoing services, elevations, including doors and
natural ventilation.
c. Pedestrian safety barriers shall be provided where the site layout is such that
emergency egress from the substation is towards a vehicular traffic route, and that
these barriers shall be required to be demountable if this were also a plant access
route for the substation.
d. Foundations shall be classified in terms of shallow and deep elements and retaining
structures that distribute loads from structures to the underlying soil.
e. Foundations shall be designed to maintain soil pressures at all depths within the
allowable bearing capacity of the soil and also must limit total and differential
movements to within levels that can be tolerated by the structure.
f. Vehicular crash barrier protection shall be required external to the substation where
the site layout is such that there is a risk of impact from vehicular traffic.
g. Substation design shall be such that sprinkler systems, gas, water, drainage or
other third party service pipes, cables or heating and ventilation ducts are detailed
within, through or under substations.
h. The design and construction shall be robust such that minimum time before
maintenance is reasonably long.
i. General functional requirements such as suitable access for and cover to high and
low voltage cables, security, unauthorized entry including sealed cable entries to
substations containing Indoor Equipment shall be met to prevent below
the ground ingress of moisture, gas and vermin.,
Page 28 of 282
j. Structural steelwork shall be hot dipped galvanized, including members, internal to
substation enclosures.
b. In ensuring that a safe and hazard free high earth resistivity working area
(switchyard) is observed in surfacing, and growth of weeds and grass within the
working area is prevented, the following shall be duly observed:
c. Formation Level (FL) of substations shall be fixed minimum 600 mm distance higher
than the surroundings on the basis of the drainage conditions and the Highest Flood
Level in the area.
b. The bottom of excavated areas shall be trimmed, levelled or graded and well
rammed or otherwise compacted.
c. The construction sequence shall be such that undue exposure of the formation level
to excavations is avoided.
d. Excavations shall be kept free from all water from whatever source, and reinforced
concrete foundations shall incorporate a minimum 50 mm thick layer of blinding
concrete.
Page 29 of 282
made for entry of power, multicore, telephone and pilot cables, water supply and
foul drainage pipes.
d. Sufficient width and depth shall be available for the cable routes such that de-rating
of the cables is kept to a minimum.
e. Ducts from buildings shall normally extend a minimum distance of 500mm from the
external face of the building, but if the access road is immediately adjacent to the
building, then the ducts shall be continued beneath the access road to facilitate
cable installation.
Page 30 of 282
2.2.3.1 Chainlink Fencing with Gates (Vehicular/Pedestrian) shall be provided to protect the
Switchyard from intruders within the block wall fencing of the Property
a. Control/relay room
b. 110V battery room
c. Telecommunication room
d. 50V battery room (communication)
e. Store room
f. Personnel office
g. Conference room (For a 330kV substation)
h. Toilet/bathroom
i. Kitchenette
b. Separate external access shall normally be provided to each individual room; and
there shall be no direct connecting doors between rooms. For larger sites the use of
a central ‘lobby’ shall be utilised.
c. On smaller sites the requirements shall be a compact building layout with switch
room, control room, battery, store and rest room. The sites with space restrictions,
other optional layouts approved by NERC shall be adopted.
d. On larger sites with several rooms the provision of a central lobby shall be
considered giving access to control and switch rooms. There shall still be
segregation between rooms with separate entrances from the lobby area, all fitted
with suitable fire doors. If convenient the rest room and kitchenette (where
provided) can also be accessed from the lobby.
i. Transformer relay and AVC panels (including space for future units where
appropriate)
Page 31 of 282
iv. Substation battery
v. Telecontrol battery
x. Telephone
xv. Door mat – recessed type for ‘computer’ floors, otherwise standard surface mat with
non-slip backing.
c. The height of the control room shall usually be the same as the adjacent
switchroom, but as a minimum there shall be 1000mm clearance above the relay /
control panels.
d. Suitable provision shall be made for personnel and equipment access and exit.
Usually one door shall be suitable for all requirements but on some larger sites two
doors may be required. The control room access door must be clearly marked, as
this shall be the normal substation building entry point providing access to the
intruder alarm panel.
Page 32 of 282
civil engineer shall be consulted for guidance on the above matters.) to be
considered.
c. In seismic areas, the stability of the unit with respect to turning over shall be
evaluated, whether placed outside or in a building. Also refer to paragraph 4 & 5 in
civil design subsection above
Water Supply & Sewage: Water supply & sewage system shall be designed to meet the
total water requirement of the substations, facilities and emergency reserve for
complete performance of the works. The design and construction of septic tanks and
soak away pits shall have a minimum volume of 6 m3.
2.2.7 Drainage
Where a substation or switch station is situated in any building so that a fire in the
substation or switch station might involve risk to the said building and the said sub-
station or switch station contains oil-immersed transformers or switches involving the
use of oil in a tank receptacle or chamber, provision shall be made for the draining
away or removal of any oil which may leak or escape from the tanks, receptacles or
chambers containing the same; special precautions shall be taken to prevent the
spread of any fire resulting from the ignition of the oil from any cause; and adequate
provision shall be made for the extinguishing of any fire which may occur.
For the design of drainage, the rainfall data shall be obtained and the storm water
drainage system including culvert, drains, and slope to accommodate the most intense
rainfall that is likely to occur over the catchment area in one hour period on an average
of once per 10 years.
a. Invert level of drainage system at outfall point shall be decided in such a way that
any water over flow from water harvesting recharge shafts can easily be discharged
outside the substation boundary wall. For easy drainage of water, minimum slope of
1:1000 shall be provided from the ridge to the nearest drain. The above slope shall
be provided at the top of base layer of cement concrete. The following minimum
slopes & design parameters for drains shall be met:
i. Switchyard shall be sloped to prevent pounding of water and no area left un-
drained;
ii. Pipe drains shall be constructed on both sides of roads and open
trapezoidal drains along switchyard and as per requirement in other areas;
iii. Maximum spacing between two drains shall be less than 100 meter within
the switchyard;
Page 33 of 282
iv. Open trapezoidal drains shall have 300 mm bottom width and sides slope of
1:1.5;
v. Longitudinal slope shall range from 1:1000 to 1:2000 depending upon
expected discharge;
vi. Side wall(s) of the drains shall be 25mm above the gravel level & covered
with CI grating;
vii. RCC pipe of class NP-3 (80 mm – 2600 mm) shall be used in normal pipe
drains;
viii. RCC pressure pipe of class NP-4 (80 mm – 2600 mm) shall be used in
culverts where heavy vehicle movement is expected;
ix. Pipe drains shall be connected through manholes within intervals of
maximum 30 m;
2.2.9 Gravelling
Gravel spreading shall be done in areas presently in the scope of the scheme. No
stone spreading shall be done in the areas kept for future expansion (bays). To hold the
stone (gravel) from spreading out of the gravel filled area, a 115 mm thick and 300 mm
deep toe wall 25 mm above top of gravel shall be provided. All visible portions of toe-
wall shall be plastered and cement painted.
2.2.10 Landscaping
a. Any landscaping treatment around substations shall be carefully designed so as not
to create potential security problems.
i. Watering;
ii. Fertilization;
iii. Approved chemical application;
iv. Pruning and vegetation control;
v. Lawn maintenance;
vi. Plant replacement as needed.
Page 34 of 282
2.3 Electromechanical Works
2.3.1 Substation Design
a. This section details the general principles to be applied to the design of
Transmission substations, including indoor and outdoor substations.
b. For substations situated in a special environment, special designs for the substation
shall be adopted subject to the approval of the Commission.
c. Transmission substations shall be designed to the same standard, and fully comply
with statutory requirements of NERC and SON.
d. Transmission substations shall be planned having in mind the future loading and
development of the area.
e. Many of the requirements shall be associated with the safety of the operational
personnel, the public and the equipment. Priority shall be given to safety, the
maximum number and type of plant to be accommodated, and personnel access
and equipment access (including power cables).
b. Standard (or typical) substation site or layout plans submitted shall be approved by
the Surveyor General or the relevant Authority.
Page 35 of 282
iv. Economical in cost of installation and operation
The minimum bus-bar capacity (ampacity) for 330 kV & 132 kV sides shall be 4000 and
3000 Amps respectively.
2.3.4.1 Transformers
a. Power Transformers:
i. 330 / 132 kV Transformers shall be 2-winding or auto-transformers of rating
90 - 300 MVA with 33 kV tertiary winding of 22.5 -75 MVA active capacity
and On Load Tap Changer (OLTC) with + 4x1.25%/ -12x1.25% range.
Vector group shall be YNy0d11 in the case of 2-winding transformers,
YNynd1 and
a. When planning, a location shall be selected to comply with all relevant safety codes
such that there shall be no interference with the normal movement of personnel,
equipment, and material. The location shall not expose the transformer to possible
damage from cranes, trucks, or moving equipment. Other site considerations shall
require closer analysis.
b. The following hereunder, shall be observed to ensure that transformer produces a
the lowest possible sound level in line with the provisions of NERC Health & Safety
Code on noise level:
i. Connections to primary and secondary terminals made with flexible
connectors,
ii. All transit bolts and shipping braces are loosened so the unit shall float on
rubber isolation pads,
iii. All enclosure hardware is tightened so panels do not vibrate.
Page 36 of 282
c. Transformers shall be adequately grounded. Grounding is necessary to remove
static charges that may accumulate and also is needed as a protection should the
transformer windings accidentally come in contact with the core or enclosure (or
tank for wet types).
d. All grounding or bonding systems shall meet the provisions of relevant codes and
standards.
e. The power transformer and any supporting structures shall be adequately packaged
and sealed against water ingress.
f. The power transformer shall conform in all respect to highest standards of
engineering design, workmanship and latest revision of IEC 60076, and
workmanship, maintainability standards relevant to the areas listed below:
S/No.g. Subject Standard
i. Power transformers – IEC 60076 – 1
Part 1: General
ii. Power transformers – IEC 60076 – 2
Part 2: Temperature rise for liquid-immersed transformers
iii. Power transformers – IEC 60076 – 3
Part 3:
Insulation levels, dielectric tests and external clearances in air
iv. Power transformers – IEC 60076 – 4
Part 4:
Guide to the lightning impulse and
switching impulse testing –
Power transformers and reactors
v. Power transformers – IEC 69976 – 5
Part 5:
Ability to withstand short circuit
vi. Power transformers – IEC 60076 – 6
Part 6: Reactors
vii. Power transformers – IEC 60076 – 7
Part 7: Loading guide for oil-immersed power transformers
The 33 kV earthing reactor will be used in conjunction with the 132/33 kV power
transformer dedicated to the Supply of distribution feeders. The earthing reactor will
provide grounding and earth current return to the 33 kV network. The 33 kV earthing
transformer will be used in conjunction with the 330/132/33 kV autotransformers to
supply the substation auxiliary services loads from the tertiary winding.
The number of secondary cores (protection or metering), accuracy class and burden
shall be in accordance with the requirements of the protection system. The accuracy
class for metering core shall be equal to or better than the accuracy class of the meter
specified in the Metering Code
The rated currents and ratios, the number of secondary cores (protection or metering),
accuracy class, burden, secondary winding resistance, knee point voltage and
excitation current shall be in accordance with the requirements of the protection
system. The accuracy class for metering core shall be equal to or better than the
accuracy class of the meter specified in the Metering Code
Page 38 of 282
2.3.4.1.6 Combined CTs and VTs
Combined CTs and VTs shall be deployed where there is constraint of space and shall
conform to the applicable standards for Current and Voltage Transformers.
Interrupting medium of circuit breakers shall be SF6. Circuit breakers of 132KV and 330
kV voltage class shall be suitable both for single phase and three phases auto-
reclosing. Each circuit breaker shall be provided with 2 nos. of trip coils. Two sets of trip
circuits shall be connected to separate fuse or MCB controlled DC supplies for greater
reliability. The circuit breaker shall have the provision for local manual trip, which shall
be at a position easily accessible to the operating person. Maximum rated break time in
ms for circuit breakers shall be as given below:
The circuit breaker specifications shall be in accordance with the following IEC60056,
60947-1, 60694, and 60815.
Disconnect switches shall be provided as visible means of isolation. Disconnectors for 132 kV
and 330 kV rating shall have provision for remote and manual operation. Earthing switches
shall be provided at appropriate locations to facilitate earthing of outgoing Transmission lines
to enable maintenance. Main blades and earth blades shall be interlocked with both electrical
and mechanical means, which shall be fail-safe. Earthing switches shall be suitable for induced
current switching duty as per relevant standard. Earthing switches shall be suitable for
electrical and manual operation. Only local operation is recommended for earth switches.
All such Surge Arresters to be deployed in the NESI shall comply with the provisions of
IEC 60099-4 on Surge Arresters. The design and dimensioning of the surge arresters
shall take cognisance of the energization of the different lines as well as the lightning
protection of the substation equipment.
2.3.4.3 Reactors
Page 39 of 282
2.3.4.3.1 Shunt Reactors
Any shunt reactor to be deployed in the NESI shall comply with the following standards:
IEC 60296, 60044, 60273, 60282-2, 60289, 60529 and 60947.
2.3.5.2 Relays
The relays to be selected shall take into consideration the expected types of failure that
will be experienced and the characteristics of the failure; with the ultimate aim of
causing the defective apparatus or lines to be disconnected and minimize damage and
maintain service continuity to the rest of the system in accordance with IEC Standard
60255
All differential relays for these applications shall comply with IEC 60076
Suitable provision shall be made, either by connecting with earth a point of the system
at the lower voltage or otherwise, to guard against danger by reason of the said system
Page 41 of 282
becoming accidentally charged above its normal voltage by leakage from or contact
with the system at the higher voltage.
2.3.5.5.2 Protection
Page 42 of 282
a. All transformers above 7.5MVA shall be protected by main and back up protection
comprising Bucholz, differential, Restricted Earth fault, overcurrent and standby
earth fault. The tripping contact must be wired to operate the tripping coil of the
primary and secondary circuit breakers fitted adjacent to the transformers.
b. Means shall be provided at the origination of every main circuit to automatically cut
off the supply of energy in the event of-
i. The passage of a current of such magnitude and duration as would be
liable to damage the substation transformer, switchgears or its
associated lines, joints and fittings:
ii. Leakage, of current to earth in excess of the amount permitted by these
regulations.
c. The means provided in compliance with paragraph (1) of this regulation shall be
circuit breakers with appropriate nominal voltage and breaking current ratings
constructed and installed in conformity with the NIS/IEC as shall be capable of
interrupting, without damage to the equipment or danger to the operator.
d. Means shall be provided to isolate the substation equipment from system short-
circuit currents or fault currents likely to be handled under conditions of use to which
they are subjected; and further shall similarly withstand, without damage to the
equipment or danger to the operator, the currents flowing if closure is made on to a
line that is, Switch-On-to- fault (SOT) or circuit which is short circuited.
e. Every Circuit Breaker shall be provided with means to show its status (closed,
open) and the same indication shall be duplicated remotely on the control panel. All
Circuit breaker should be provided with two (2) numbers disconnector switch so that
it can be locked in the "OFF” position to prevent unauthorized interference. During
the time that the device is locked in the "OFF” position the relevant keys for the lock
shall be kept in safe custody in the manner prescribed in the Grid code.
f. The clauses above shall be read in conjunction with the Principles of Protection
contained in Chapter 8.
Page 43 of 282
sulphuric-acid cells or eight nickel-iron alkaline cells the stands also shall be
insulated.
d. Suitable means shall be provided for controlling the current with which battery is
being charged. Such means shall comprise, as a minimum, an automatic cut-in and
cut-out, or alternatively, a circuit breaker with overload and reverse-current trips.
e. Ventilation system forced or natural shall be maintained to prevent build up of
explosive mixtures. In which case, an alarm system shall be provided against
excess gas accumulation.
f. Eye and body wash apparatus shall be maintained in operable condition.
The strappings inside the LMU/ LMDU must be connected in the required manner so as
to match with impedance of the coaxial cable (75Ω /125Ω as the case may be).
Page 44 of 282
2.4.2 Remote Terminal Unit (RTUs)
Remote Terminal Unit (RTU), Phase Monitoring Unit (PMU) and Load Dispatch Centre
shall comply with NIS/IEC standard.
2.4.3 Communications
Communication between Intelligent Electronic Devices (IED) shall be in accordance
with IEC 61850 and Communication between Substation Automation System (SAS)
and power plant devices shall comply with IEC 60870-104
Page 45 of 282
Chapter 3: Transmission Lines
GENERAL PROVISIONS
The standards as outlined deals with requirements and compulsory procedures and practices
necessary for overhead transmission line construction in Nigeria power sector. It is designed to
meet service reliability, safe operation and maintenance of transmission lines. Such
transmission lines shall be capable of withstanding expected electrical and climatic loads while
maintaining design consistency between strengths of line components. There shall be a written
approval granted by NERC prior to the construction of transmission lines. The transmission line
shall be designed to meet the following fundamental requirements and shall comply with the
provisions of IEC 60826;
3.1 Right‐of‐Way
The Right Of Way (ROW) width required for Overhead power lines of any voltage level shall be as
indicated in the table below.
Table 3.1: Right ‐of ‐Way
330kV 50
132kV 30
33kV 11
11kV 11
NB: The Right of Way measurement shall be divided equally from the centre of the line on
either side. For safety reasons, no structures shall be built under the Overhead line Right of
Way. Where such structures are built after the construction of the lines, the licensee shall not
be liable.
Page 46 of 282
(ACRS). The properties of the conductor and appropriate cross sectional area suitable for the
designed electrical load shall be as specified in IEC 61089
b. Bare Conductors:
Bare conductors and overhead ground wires (including overhead ground wires
containing optical fibre cables) that are used for transmission lines shall conform
to the following requirements:
i. Properties of Solid Wires
Solid wires (hard-drawn copper wire, hard-drawn aluminium wire, galvanized
steel wire, aluminum alloy wire, etc.) which compose an electrical conductor,
shall have conductivity and tensile strength not lower than the values specified
in the IEC standards (e.g. IEC60028, 60889, 60888, 61232, and 60104).
The tensile strength of hard-drawn copper wires shall conform to Table 3.1.
Table 3.1
2
Diameter of solid wire (mm) Tensile strength (N/mm )
No less than 0.4 but no more than 12.0 No less than (462 – 10.8d)
Page 48 of 282
iii. The electrical conductors shall be jointed using jointing sleeves and other
tools
iv. Where copper conductors are jointed with aluminium conductors, bi-metal
couplers or bi-metal line tap shall be used so as not to generate
electrochemical corrosion in the joint.
Page 49 of 282
i. Vertical Load: The vertical load shall be the sum of the weight of electrical
conductors, the weight of insulator devices and the vertical component of
force generated by the assumed maximum tension of the electrical
conductors.
ii. Horizontal Transverse Load: The horizontal transverse load shall be the sum
of the wind pressure loads of electrical conductors and insulator devices and
the horizontal component of load generated by the assumed maximum
tension of the electrical conductors. The wind pressure loads shall be
calculated based on the values listed in Table 3.2.
Table 3.2
2
Wind pressure on vertical projected area (N/m )
Subject to wind pressure
Electrical Multiple conductor * 710
conductor Single conductors 790
Insulator device 1100
* This applies only to cases where two compositional conductors are arranged horizontally and the distance
between such electrical conductors is no more than twenty times their outer diameter.
b. Safety Factor: A safety factor of no less than 2.5 shall be applied to the insulator
devices for overhead transmission lines. The safety factor mentioned above shall
be obtained as follows:
i. Tension insulator device (Insulator device that anchors electrical conductors).
ii. Suspension insulator device (Insulator device that electrical conductors are
hung from).
Page 50 of 282
3.3 Dielectric Strength of Overhead Transmission Lines
3.3.1 Clearance between Supporting Structures and Electrical Conductors
The clearance between overhead transmission conductors (excluding cables) and their
supporting structures, cross arms or guys (pole braces) shall not be smaller than the
values shown in Table 3.3 even when the electrical conductor sways by a wind velocity
of about 20m/s.
c. In case where cables are used for overhead transmission lines, the test shall
conform to subsection 3.8.1.1. below
Steel members and bolts to be used for a steel tower or an iron pole of overhead
transmission lines shall have the strength as specified in Table 3.4.
Page 52 of 282
Table 3.4
Classification of strength Strength
Compression strength Y
Flexural strength Y
Ʌ ≤ k
2 2
1.5π E / 2.2k
Where
Y: Yield point strength of steel members and bolts
B: Tensile strength of steel members and bolts
k: Effective slenderness ratio ( = Lk / r )
Lk : Effective buckling length of steel members
r: Turning radius of a steel member cross-section
E: Elastic modulus (20.6 × 102 N/m2)
Ʌ: π
Page 53 of 282
Table 3.5
K K0 K1 K2
Table 3.6
[×106N/m2]
ii. Bond strength of concrete: The bond strength of concrete at yield point shall be
based on the design standard strength (4-week strength; Fc) and conform to
Table 3.7
Table 3.7
[×106N/m2]
Page 54 of 282
than 1.32
Deformed Fc/10 and no more than 3Fc/20 and no more than Fc/10 and no more than
round bar 1.32+3Fc/75 99+3Fc/50 1.32+3Fc/75
iii. Strength of shaped steel, flat steel and steel bars: The strength of shaped steel,
flat steel, and steel bars at yield point shall conform to Table 3.8.
Table 3.8
2
Yield tensile strength (N/mm ) Yield compression
2
strength (N/mm )
Tubular bar Y and no more than 234 Y and no more than 234
Deformed Diameter ≥ 29mm Y and no more than 294 Y and no more than 294
tubular bar
29mm > Diameter > Y Y
25mm
25mm ≥ Diameter Y and no more than 322 Y and no more than 322
Vertical load The load applied by the weight of strung wires and insulating devices Wc
If the electrical line has a remarkable vertical angle, the vertical load from the line
Page 55 of 282
shall be added
If guys are used (in case of a steel tower, this shall be limited to a temporary Ws
electrical line specified in Paragraph 2 in Article 107), the load by a vertical
component of force generated by tension of the guys shall be added.
Horizontal transverse Wind pressure load applied to the supporting structure (including cross arms) Ht
load
Where strung wires mean electrical conductors and overhead ground wires. The same applies
hereafter in this standard.
Table 3.10
Classification Type of
Load Horizontal Horizontal
of supporting supporting Wind direction Vertical load
condition transverse load longitudinal load
structure structure
Wt Wc Ws Ht Hc Ha q H’t P1 P2 q1
Perpendicular to the
electrical line
Class A Wind pressure
All types
reinforced load
Parallel to the
concrete pole
electrical line
Perpendicular to the
Wind pressure electrical line
Class A iron
All types load and
pole
vertical load Parallel to the
electrical line
Page 56 of 282
Parallel to the
electrical line
Perpendicular to the
electrical line
Assumed
Strain type
normal load
Parallel to the
electrical line
Perpendicular to the
electrical line
Assumed
normal load
Parallel to the
electrical line
Common
type
Perpendicular to the
electrical line
Assumed
abnormal load
Parallel to the
electrical line
Perpendicular to the
electrical line
Assumed
normal load
Parallel to the
electrical line
Steel tower Anchor type
Perpendicular to the
electrical line
Assumed
abnormal load
Parallel to the
electrical line
Perpendicular to the
electrical line
Assumed
normal load
Parallel to the
electrical line
Strain type
Perpendicular to the
electrical line
Assumed
abnormal load
Parallel to the
electrical line
Note: Circles indicate the assumed loads to be considered at the same time. The wind direction that brings the bigger
assumed load should be selected.
The supporting structures in Table 3.10 shall have the following types:
i. Anchor type: Supporting the structure for use of anchoring all strung
wires
ii. Strain type: Supporting structure for use of reinforcing the linear parts of
electrical lines or use in a place where there is a large difference in the
span at both sides of the supporting structure
iii. Common type: Supporting Structures, excluding (i) and (ii) above, with
tension type or suspension type insulator devices
Page 57 of 282
b. Where strung wires are arranged asymmetrically on the supporting structure,
the assumed vertical eccentric load shall be added to the load in Table 3.10,
and the load by normal torsional load shall also be added for anchor or strain
type.
i. This shall not apply when calculation is made based on values obtained
by a wind pressure (wind duct) test using a wind at a velocity of not less
than 35m/s.
ii. The wind receiving area shall be the vertical projected area of the
structural member. For cross arms of a concrete pole, an iron pole
except a columnar pole, and steel tower, the wind receiving area shall be
the vertical projected area of the front structures that receive the wind.
Table 3.11
3
Wind pressure to 1m of the
Subject to the wind pressure vertical projected area of the
structural member (N)
Columnar pole 630
Triangle or rhombic pole
1500
Supporting
Others 1740 when the web members
structure
overlap in the front and the back
1890 in other cases
Reinforced concrete Columnar pole 630
pole Others 950
Shaped steel tower 2290
Steel tower Steel pipe tower 1350
Single pole Columnar 630
Page 58 of 282
pole
Hexagonal or
octagonal 1180
pole
Cross arms for an iron pole (limited to a columnar pole) and a reinforced 1260 when it is used as a single
concrete pole member
1740 other cases
When the wind blows to the electrical line at an angle of 60o, the wind pressure
load in an assumed normal load of a common type steel tower shall be that
calculated by the wind power pressure load multiplier (in case of a square tower)
in Table 3.12
Table 3.12
Table 3.13
Page 59 of 282
Shaped steel tower Steel pipe tower
Height
Below 330kV No less than 330kV Below 330kV No less than 330kV
No higher than 50m 2,450 2,610 1,430 1,500
ii. Wires and insulators: When a steel tower is higher than 80m, the wind
pressure shall be calculated by increasing the wind velocity
appropriately. (this statement should be Reviewed)
Table 3.14
Page 60 of 282
a. For steel towers, the strung wires shall be cut according to the following
requirements depending on the total number of phases of electrical conductors
(which means phases for each circuit; the same shall apply hereafter).
i. The overhead ground wire shall not be cut at the same time as the electrical
conductors and only one wire shall be cut.
ii. Where the total number of phases of electrical conductors is no more than
twelve (12), one phase that maximizes the stress generated in each
structural member (Two electrical conductors from one phase in case of
multiple conductors for steel towers other than anchor type)
iii. Where the total number of phases of electrical conductors is over twelve
(12) (excluding the case specified in the following item iv.), two phases in
different circuits that maximize the stress generated in each structural
member (Two electrical conductors from one phase in case of multiple
conductors for steel towers other than anchor type)
iv. Where electrical conductors are arranged so that nine or more phases are in
a longitudinal row and two phases are in a transverse row, one of the top six
phases in the longitudinal row (two electrical conductors from one phase in
case of multiple conductors for steel towers other than anchor type) and one
phase from the other phases (two electrical conductors from one phase in
case of multiple conductors for steel towers other than anchor type) that
maximize the stress generated in each structural member.
C The unbalanced tension generated by cutting the strung wire shall be equal to
the assumed maximum tension.
Provided, however, that the unbalanced tension may be 0.6 times the assumed
maximum tension if, depending on the mounting method of strung wire, the supporting
point of the strung wire shifts when the wire is cut or the strung wire slides at the
supporting point.
Page 61 of 282
Table 3.15
Table 3.16
Safety factor
Classification of supporting structure
Assumed normal load Assumed abnormal load
Reinforced concrete pole and iron pole 2.0 3.0
a. For the foundation subject to a lifting load, two thirds or less of the weight of the
foundation (or weight of the foundation of a steel tower to an abnormal load) may be
included in the lift bearing power.
Page 62 of 282
b. For the foundation subject to a compressive load, the weight of the foundation shall
be included in the compressive load.
a. For every five poles or less frequently, guys shall be installed on both sides of wires
in the direction perpendicular to the electrical line. The same shall not apply when
voltage of 33kV or below is used.
b. Where 15 or more of such poles are successively, guys shall be installed on both
sides of wires in the direction of the electrical line for every 15 poles or less.
c. The guys installed according to Item (a) and Item (b) can be used in common with
the guys installed according to the provisions of subsection 3.4.5.1 of section 3.4.5.
Page 63 of 282
a. Guys for Class A reinforced poles, Class A iron poles, Class B reinforced concrete
poles and Class B iron poles used for overhead transmission lines shall be installed
according to Paragraph 1 and 3 of 5.2.3.5
b. Steels towers used for overhead transmission lines shall have no guys that share
the strength of the towers. However, steel towers to be used temporarily within six
months may be equipped with guys. In this case, the guys shall be installed
according to Item (1) of Paragraph 1 of 5.2.3.5-to be coordinated with distribution
group.
c. Guys used for reinforced concrete poles, iron poles and steel towers shall conform
to Paragraph 2 in 5.2.3.5
a. The circuit of the higher voltage shall always cross over the circuit of the lower
voltage;
Table 3.17
Lower Circuit (Voltage between phases) Upper Circuit (Voltage between phases)
Earth
wire 400
3,300 6,600 11,000 33,000 66,000 132,000 330,000
(415)
Convert (cm) (cm) (cm) (cm) (cm) (cm) (cm) (cm) (cm)
to
Metres
(m)
Earth wire 30 20 30 30 30 120 60 120 240
Page 64 of 282
3,300V 30 –– –– 120 120 120 150 180 270
Where the circuit of the higher voltage is fully insulated the minimum clearance
calculated in accordance with 3.5.1c above may be reduced by 50%.
b. Fully insulated service lines operating at a voltage not exceeding 400Volts may be
terminated on buildings at a height of not less than 2.7 m from ground level
provided that the street clearance at any point of its span is not less than 5.8 m.
Table 3.18
Page 65 of 282
330,000 Volts 7.0 m 7.0 m 5.8 m
750,000 Volts ?? ?? ??
Table 3.19
Nominal voltage Vertical Clearance
No higher than 33 kV 2m
This shall not apply when overhead transmission lines are installed according to the
following requirements:
a. Overhead transmission conductors with a voltage not higher than 33 kV, for
which insulated conductors are used, shall be installed so as not to contact
plants.
b. Overhead transmission conductors with a voltage not higher than 132 kV, for
which cables are used, shall be installed so as not to contact plants.
Page 66 of 282
No overhead transmission line shall be installed in urban areas or other densely built-
up areas.
The restrictions above shall not apply where the nominal voltage of the overhead
transmission line is not more than 132kV and the electrical conductors are cables or the
installation is carried out according to the following requirements:
Table 3.20
Nominal voltage Strength of electrical conductor
No higher than 33kV Stranded wire with a tensile strength no less than 30 kN
Higher than 33kV but no higher
Stranded wire with a tensile strength no less than 40 kN
than 132kV
b. Limitation of Span
The length of span of overhead transmission lines shall conform to Table 3.21
below
Table 3.21
Classification of supporting
Length of span
structure
Class A reinforced concrete pole
No longer than 75 m
or class A iron pole
No longer than 400 m (or no longer than 250m when two or more
Steel tower electrical conductors are arranged horizontally and the distance
between the electrical conductors is less than 4 m)
Page 67 of 282
This shall not apply to overhead transmission lines for a span connecting the
yard of a power plant, substation or similar place to the outside.
Table 3.22
Nominal voltage Height of electrical conductor above the ground
Not higher than 33kV 10.06 m (8 m when insulated conductors are used)
Value obtained by adding 6 cm for each 10kV over 33kV and
Higher than 33kV
fraction thereof to 10.06m
d. Indication of danger
An urban area or other densely built-up area shall be defined according to the
building-to-land ratio specified in Table 3.23
Where the building-to-land ratio means the ratio of (the area covered with
buildings / 50,000 m2 MINUS the area of roads] in the zone (excluding roads)
that is the rectangular area of 50,000 m2 extending for 50 m on both sides of an
overhead transmission line and 500 m in the direction of that line.
Table 3.23
An urban area or other densely built-up area
New transmission conductor (when The building-to-land ratio is no less than 25%.
installed)
3.5.5 Regulations for Side‐by‐side Installation and at Adjacency to and Crossing with Other Objects
Page 68 of 282
(Conductor sag at maximum design temperature PLUS length of suspension
insulator string) PLUS B, where "B" is a constant dependent on the voltage
between phases of the conductors of the line-
b. Where the conductors of the circuit are fully insulated the constant "B" may be
reduced by 50%.
The electrical conductor with a higher voltage shall be installed above the electrical
conductor with a lower voltage, using separate cross arms.
i. Clearance
Page 69 of 282
The clearance between any overhead transmission conductor and any
overhead distribution conductor shall be not shorter than the values specified in
Table 3.24.
a) Those with a tensile strength no less than 5 kN where the span of the
overhead distribution conductor is no longer than 50 m
b) Those with a tensile strength no less than 8 kN where the span of the
overhead distribution conductor is longer than 50 m
b. Overhead transmission conductors with a nominal voltage over 33kV but below
132kV and low-voltage overhead distribution conductors shall not be installed on
the same supporting structure.
When overhead transmission conductors with a nominal voltage over 33kV but
below 132kV and medium-voltage overhead distribution conductors are installed on
the same supporting structure, the installation shall be carried out in accordance
with the following requirements:
Page 70 of 282
iv. Clearance
c. The clearance between any overhead transmission conductor and any overhead
distribution conductor shall be no less than the values specified in Table 3.25 below
.
Table 3.24
a. Overhead transmission conductors with a nominal voltage higher than 132kV and
overhead distribution conductors shall not be installed on the same supporting
structure excluding the case of the following paragraph.
b. Other than in the case of a fully insulated services line all electric lines, except with
the written authority of the relevant statutory body , shall cross over Post and
Telecommunications lines with a minimum clearance, under the most adverse
operating conditions at the point of crossing of :
Page 71 of 282
Table 3.25
i. So far as may be practicable the licensee shall leave one side of each street
free for telecommunication line and where the street is continuous the licensee's
line shall be kept to the same side of the street for the whole distance.
ii. Except with the permission of the relevant statutory body Posts and
Telecommunications Authorities all overhead lines shall be placed on the
opposite side of the street to that on which any telecommunication lines are
erected, and where the erection or operation of the electric lines necessitates an
alteration of an existing telecommunication line, and such alteration is approved
by the Posts and Telecommunications Authorities, the expense of the alteration
shall be borne by the licensee; provided that where existing telecommunication
lines of the Telecommunications Service Providers Authorities occupy both
sides-of the street that Organization shall bear the cost of putting all
telecommunication lines on the one side of the street or if agreeable to the
licensee, consent to an arrangement for the joint use of poles on both sides of
the street.
iii. Where electric lines are on one side of the street and telecommunication lines
on the other, and service is required to be given from either side to the other, the
licensee and the Posts and Telecommunications Service Provider shall give to
each other reasonable facilities as far as possible to effect supply. Where
possible electric service lines, unless fully insulated, shall pass over
telecommunication service lines otherwise pass under electric lines.
Page 72 of 282
Notwithstanding, this shall not apply where the overhead transmission conductors are
cables.
b. Where the electrical circuit as specified in the preceding item is coupled with
another electrical circuit through a transformer, an insulating transformer shall
be used.
c. One terminal on the loaded side of the insulating transformer as specified in the
preceding item or a neutral point shall be provided with class A earthing work.
b. Where the conductors of the circuit are fully insulated the constant "A" may be
reduced by 50%.
b. The licensee shall at least within thirty days and not more than ninety days prior
to the placing of such work serve written notice on the appropriate authorities
specifying the intended use of the works, the voltage of operation and such
other information that the authorities may require him to supply.
d. The authorities may within 21 days of the receipt of such a notice of intention
served under Clause 3.6.2.3b serve a counter notice on the licensee
i. Objecting to the siting of the works specifying the reason in the counter
notice; and
ii. Requiring protective features to be fitted, such features to be specified in
the counter notice.
a. An overhead conductor may not cross a railway track at a more acute angle
than 60° unless special permission is obtained from the Nigerian Railway
Corporation.
c. No supporting structure shall be situated nearer to the centre line of the track
than the total height of the supporting structure plus 2.5 meters.
Page 74 of 282
d. When the railway line is in a cutting, the supporting structure must be at a
distance from the edge of the cutting not less than its total height.
b. Clearance
Page 75 of 282
i. The clearance shall be as specified below. The clearance shall be secured
to provide for the occurrence of such case that the electrical conductor dips
at the maximum design operating temperature or sways in the wind. (The
same shall apply hereafter in this article.)
Table 3.26
Page 76 of 282
b. Clearance
c. Horizontal Clearance
b. Clearance
c. Horizontal clearance
iv. Where the overhead Transmission conductors with a normal voltage lower
than 132kV kV are insulated conductors or cables.
Page 78 of 282
a. Transmission Line Strengthening Work
Table 3.28
Closing distance of overhead
Strengthening work
distribution conductors or the like
No longer than 50 m Type 2 transmission line strengthening work
Type 1 transmission line strengthening work
(Note that type 2 transmission line strengthening work will do for
Over 50 m
overhead transmission lines with a nominal voltage no higher
than 33kV.)
b. Clearance
c. Others
The overhead distribution conductor or the like (the uppermost one when there are
two or more located vertically) shall has a tensile strength no less than 10 kN or it is
a cable.
This shall not apply where overhead transmission conductors are insulated
conductors with a nominal voltage no higher than 33kV or cables with a nominal
voltage below 132kV kV.
3.6.2.10 Adjacency to and Crossing of Overhead Transmission conductors with other ones
Where overhead transmission conductors are installed close to or across other
overhead transmission conductors, they shall be installed in accordance with the
following requirements:
(2) Clearance
Table 3.29
Page 80 of 282
Nominal
Type of electrical conductor Clearance
voltage
One overhead transmission conductor
uses a cable and the other uses an 0.5 m
insulated conductor or cable
No higher
than 33kV Both overhead transmission conductors
1m
use insulated conductors
Others 2m
The value obtained by adding 6 cm for
Both overhead transmission conductors
every 10 kV and fraction thereof over
use cables
33kV to 1 m
Over 33kV
The value obtained by adding 6 cm for
Others every 10 kV and fraction thereof over
33kV to 2 m
Table 3.30
Nominal voltage Clearance
2 m (or 1 m when the electrical conductor is an insulated conductor and
No higher than 33kV
0.5 m when it is a cable)
The value obtained by adding 6 cm for every 10 kV and fraction thereof
Over 33kV
over 33kV to 2 m (or 1 m when the electrical conductor is a cable)
(1) Clearance
Page 81 of 282
a. The clearance between overhead transmission conductors with a
nominal voltage no higher than 33kV and other facilities shall conform to
Table 3.31.
Note that the clearance shall conform to Clause 3.6.2.1 where overhead
transmission conductors are installed above the buildings strong enough under
which people can walk around freely.
Table 3.31
Clearance
The electrical
Classification of other facilities The electrical The electrical
conductor is an
conductor is a conductor is a
insulated
cable bare conductor
conductor
(1) Clearance
Page 82 of 282
(2) Transmission line strengthening work
Where overhead transmission conductors are installed below and close to other
facilities, the horizontal clearance between the two shall be no less than 3 m, and the
clearance between them shall conform to Table 3.30 above. .
Note that the clearance between overhead transmission conductors and other facilities
need not necessarily exceed 3m when the overhead transmission conductors use
insulated conductors and have a nominal voltage no higher than 33kV or when they
use cables and have a nominal voltage below 132kV.
a. Overhead ground wires shall be installed for the overhead transmission lines with a
nominal voltage over 33 kV. Note that the distribution lines of SWER systems
installed on the top of a tower can be regarded as overhead ground wires.
b. Arcing horns shall be installed for insulator devices of overhead transmission lines
with a nominal voltage over 33 kV.
a. Cut trees by the necessary length in an area where the facilities could be damaged
by falling trees.
Page 83 of 282
b. Secure the height of electrical conductors so as not to damage the facilities by
falling trees.
c. All supports carrying high voltage conductors shall have danger notices
attached. These danger notices shall be of metal enameled or painted white
and/or conventional with lettering and/or conventional signs in scarlet as
approved by NERC.
d. Where the lines are erected on the side of a road the notice shall be so fixed
that it is plainly visible from the road
Page 84 of 282
3.8 Underground Transmission Lines
3.8.1 Dielectric Strength of Underground Transmission Lines
Underground transmission lines shall withstand the dielectric strength tests using the
test methods specified in IEC 60840 or IEC 60502-2 "Electrical tests after installation"
depending on the voltage.
2. Electrical conductor
Electrical conductors of cables shall have the electric resistance specified in IEC 60228
and shall be stranded wires composed of solid wires, such as annealed copper wire,
annealed aluminium wire, hard-drawn aluminium wire and semi hard-drawn aluminium
wire that satisfy the mechanical characteristics specified in Table 3.32..
Table 3.32
Type of solid 2
Diameter of solid wire Tensile strength (N/mm ) Elongation (%)
wire
No less than 0.10, no more than No less than 15.0
0.28
More than 0.28, no more than 0.29 No less than 20.0
Annealed More than 0.29, no more than 0.45 No less than 196, No less than 20.0
copper wire More than 0.45, no more than 0.70 below (462 - 10.8d) No less than 20.0
More than 0.70, no more than 1.6 No less than 25.0
More than 1.6, no more than 7.0 No less than 30.0
More than 7.0, no more than 16.0 No less than 35.0
Annealed No less than 2.0, no more than 5.2 No less than 10.0
No less than 59, below 98
aluminium wire More than 5.2, no more than 7.0 No less than 20.0
No less than 1.2, no more than 1.3 No less than 159 No less than 1.2
More than 1.3, no more than 1.5 No less than 186 No less than 1.2
More than 1.5, no more than 1.7 No less than 186 No less than 1.3
More than 1.7, no more than 2.1 No less than 182 No less than 1.4
Hard-drawn
More than 2.1, no more than 2.4 No less than 176 No less than 1.5
aluminum wire
More than 2.4, no more than 2.7 No less than 169 No less than 1.5
More than 2.7, no more than 3.0 No less than 166 No less than 1.6
More than 3.0, no more than 3.5 No less than 162 No less than 1.7
More than 3.5, no more than 3.8 No less than 162 No less than 1.8
Page 85 of 282
More than 3.8, no more than 4.1 No less than 159 No less than 1.9
More than 4.1, no more than 5.2 No less than 159 No less than 2.0
More than 5.2, no more than 6.6 No less than 155 No less than 2.2
No less than 1.2, no more than 1.3 No less than 98, below 159 No less than 1.2
More than 1.3, no more than 1.5 No less than 98, below 186 No less than 1.2
More than 1.5, no more than 1.7 No less than 98, below 186 No less than 1.3
More than 1.7, no more than 2.1 No less than 98, below 183 No less than 1.4
More than 2.1, no more than 2.4 No less than 98, below 176 No less than 1.5
Semi hard-drawn More than 2.4, no more than 2.7 No less than 98, below 169 No less than 1.5
aluminium wire More than 2.7, no more than 3.0 No less than 98, below 166 No less than 1.6
More than 3.0, no more than 3.5 No less than 98, below 162 No less than 1.7
More than 3.5, no more than 3.8 No less than 98, below 162 No less than 1.8
More than 3.8, no more than 4.1 No less than 98, below 159 No less than 1.9
More than 4.1, no more than 5.2 No less than 98, below 159 No less than 2.0
More than 5.2, no more than 6.6 No less than 98, below 155 No less than 2.2
d: diameter of solid wire (mm)
3. Insulator
A cable shall have an insulator that is a butyl rubber compound, an ethylene propylene
rubber compound or a polyethylene compound and have an electric shielding layer
made of metal provided on the insulated conductor, or shall be a lead-covered cable,
aluminium-covered cable or a cable with some other metal cover.
Note that a cable used in an underwater transmission line specified in Clause 3.9.1 of
this regulation (Underwater Transmission Lines) may not necessarily have the electric
shielding layer made of metal.
Deviation from the above shall be subject to the written approval of NERC
a. The joint box shall not increase the electric resistance of cables.
b. The joint box shall have the dielectric strength equal to or higher than that of cables.
Page 86 of 282
protecting devices that house the cables (except for cable support hardware). This
shall not apply to the parts where anticorrosion measures are taken.
b. The licensee shall at least thirty days and not more than ninety days prior to the
placing of such work serve written notice on the appropriate authorities specifying
the intended use of the works, the voltage of operation and such other information
that the authorities may require him to supply.
(4) The authorities may within 21 days of the receipt of such a notice of
intention served under clause 3.6.2.3b serve a counter notice on the licensee -
–
Page 87 of 282
(a) objecting to the siting of the works specifying the reason in the counter
notice; and
(b) requiring protective features to be fitted, such features to be specified in the
counter notice.
3.8.2.8 Cables
All cables, whether for A.C. or D.C. and for all voltages, shall be insulated as required
and manufactured in accordance with appropriate Nigerian Standard. Where steel
armouring is employed, it shall be effectively earthed and bonded at all joint boxes so
as to be electrically continuous.
b. To prevent the cables being damaged by stones the cables shall be laid in a bed of
sifted soil or sand and to prevent mechanical damage the cables shall be protected
by inter-locked tiles sufficiently wide to give a minimum of 50 mm on each side of
the cable and laid approximately 150 mm above the cables.
c. The cable route shall be indicated at surface level with cable markers at suitable
intervals, particularly at positions where the cable changes direction.
b. High voltage lines shall not pass through the same street box as other electric lines
unless they are enclosed in a strong metal casing effectively earthed.
c. Street boxes containing high voltage lines shall not contain water, gas or other
service pipes, or electric lines belonging to another licensee.
b. Installation Methods
i. Conduit systems and culvert systems
(a) These systems shall be rigid and durable and shall not affect other
adjacent buried objects.
Page 89 of 282
(b) Where these systems are buried under roads, they shall withstand the
pressure from vehicles or other heavy objects and shall not affect the
strength of the road.
(a) To protect cables against shock, the direct burial systems shall be
installed using any of the following methods:
(ii) Use cables with durable insulating covers, such as copper bars
and steel pipes, for underground transmission conductors and
install them by covering the top and the side of the underground
transmission cable with durable plates or conduits.
(i) The buried depth shall be over 1.2 m in a place where there is a
possibility of receiving pressure from vehicles or other heavy
objects.
Page 90 of 282
a. The name of the line, the responsible person and the voltage shall be indicated.
b. Such indications shall be given noticeably with intervals of about 10 m. This shall
not apply to restricted areas or places where the position of the electrical
conductors can be recognized clearly.
A conduit shall have the structure that conforms to the following requirements:
i. A conduit shall withstand the pressure of vehicles and other heavy objects.
ii. A conduit shall be structured so that it is difficult for water to enter it.
iii. A conduit shall have the inside diameter that allows cables to be drawn in
and out smoothly and the inner surface shall be flat and smooth.
iv. The radius of curvature of a curve on the conduit and the length of conduit
between manholes shall be such that the tensile strength and the lateral
pressure applied on cables when they are drawn in are less than the
allowable limit.
b. Structure of a Culvert
A culvert shall have the structure that conforms to the following requirements:
i. A culvert shall have the structure that can withstand the pressure of vehicles
and other heavy objects.
ii. A culvert shall be structured so that water can hardly enter into it.
iii. A culvert shall have the form and dimensions that allow smooth installation
and maintenance work of cables. The tolerable bending radius of cable
shall be taken into consideration particularly at bends and branch points of
the culvert.
iv. If necessary, a drain, a ventilator, lighting, scaffolding for going up and down,
a ladder and other facilities shall be installed.
Page 91 of 282
c. Structure of a Manhole
A manhole shall have the structure that conforms to the following requirements:
i. A manhole shall have the structure that can withstand the pressure of
vehicles and other heavy objects.
ii. A lid of a manhole shall be such that people other than operators cannot
open it easily.
iii. A manhole shall be structured so that it is difficult for water to enter it and
water entering it can be removed.
iv. Where a manhole has the size of 1.0 m3 or larger and there is a possibility
that explosive or flammable gas may enter it, the manhole shall be equipped
with a device to diffuse the gas.
vi. If necessary, facilities for going up and down shall be installed in the
gateway.
vii. If there is a possibility that a manhole lid can be moved by a cable accident,
a chain shall be installed on the lid.
Page 92 of 282
a. Clearance
ii. When the clearance mentioned above is less than 0.60m, any of the following
counter measures shall be carried out.
d. Alternative Measures
Page 93 of 282
iii. Where underground telecommunication conductors are optical fibre cables
covered with materials that are non-flammable or are self-extinguishing and
fireproof or optical fibre cables nested in pipes that are non-flammable or are
self-extinguishing and fireproof, and the responsible person has given the
consent to the installation, or
e. Where those electrical conductors are installed close to or across each other in a
manhole
Page 94 of 282
3.8.5.3 Adjacency to and Crossing with Other Underground Objects
a. Adjacency to and Crossing with Gas Pipes and Oil Pipes
Where telecommunication lines are placed below ground in any street and the
licensee desires to place his works below ground in the same street they shall
be placed on the opposite side of the street to the telecommunication line
unless the Telecommunications Service Provider expressly authorizes in writing
a relaxation of this requirement. Any such relaxation shall be subject to such
conditions as to the provision of minimum separating distance and protective
features which at its discretion he deems it desirable and necessary to impose
for the protection of the telecommunication cable.
d. Exchange of plans
e. Breaking up streets
i. A licensee shall not break up streets for the purpose of placing new works,
including works in replacement of existing works, unless they shall have
served notice of their intention on the responsible administrative authority for
the repair of any street to be broken in addition to the local authority.
ii. Every notice required to be served under the provision of this clause above
shall be served at least thirty days but not more than ninety days prior to the
date on which it is intended to break up any street or streets, and shall be
accompanied by a plan of a suitable scale indicating the course, nature,
width and depth of all intended excavations and the purpose thereof.
iii. The local authority or the road authority responsible for normal maintenance
of the street or both may within 21 days of receipt of a notice served under
the provisions of clause (e.i) serve a counter notice on the licensees
requiring them to amend the scheme the reason thereof being stated in the
counter notice.
iv. Where no counter notice is served on the licensee as provided for the works
shall be deemed to be approved and it shall be lawful for the licensee to
proceed with the works on the expiration of the term specified in the notice
served under clause (e.i) above.
v. Streets shall only be broken up in strict conformity with the original theme or
any amendment thereof required by counter notice served under Section
(e.iii).
vi. Where the licensees are of the opinion that the requirements of a counter
notice served under clause (e.iii) are unreasonable and they are unable to
reach an amicable settlement with the local authority or the road authority or
both, the matter shall be referred to the NERC whose decision shall be final
and binding on both parties.
The road authority will reinstate any street broken up by the licensee and
charge them the cost of so doing.
Page 96 of 282
to be placed above ground, shall be approved by the local authority or
where the local authority does not maintain or repair the street, the road
authority.
Where a piped water supply is provided in any area in which the licensee
proposes to place any new works, the water authority not being a local
authority, shall be deemed, for the purposes of this Part to be a local
authority, and the provisions of clauses (e) and f(a) above together with
the following special conditions, shall apply–
(ii) on receipt of the plan referred to in clause b(i) above hereof the
licensee shall take such steps as may be necessary to ensure that, in
placing their works, the separating distance between the respective
works is either not less than 1m or where this separating distance is
impracticable such lesser distance as may be mutually agreed to in
writing by the respective parties.
(iii) in the event of any differences or dispute an arising between the
parties the matter shall be settled in the manner provided for in clause
e(vi) above
(2) Every notice served in conformity with clause a(1) above shall be
accompanied by a plan of a suitable scale indicating the course, nature and
depth of all intended excavations, switches, transformers, and other apparatus
intended to be used.
Page 97 of 282
(3) The Telecommunications service provider may within 21 days of the receipt
of a notice of intention served under clause a(1) above hereof serve a counter
notice on the licensee requiring them to-
(a) re-route their works;
(b) provide protective features to be specified in the counter notice between his
works and the intended works;
(c) provide guarding between his works and those of the licensee which
guarding he may itself provide at the expense of the licensee if he so
advises the licensee in the counter notice.
(2) At least fourteen days prior to the date on which it is desired to bring into use
any projects aforesaid, the licensee shall serve notice on the NERC r Services
sending a copy to the area, specifying the date on which the projects or any
part thereof will be completed and ready for inspection. Every such notice shall
be accompanied by-
(a) a plan and description of the projects as erected;
(b) copies of any notices and plans served under the provisions of clauses e,
f(b), a, b, and c.
(c) copies of any counter notices received.
(3) On receipt of a notice under the provisions of clause d(2) above the
inspecting engineer shall inspect the relevant projects and if he is satisfied that
there is compliance with be regulations to certify in writing sending the original
certificate to the licensee and a copy to the NERC , Services: Provided that any
certificate issued under the provisions of this regulation shall not be deemed to
relieve the licensee of any of their obligations under the provisions of the
Principal Act or of these Regulations.
Page 98 of 282
(4) On the representations of the licensee that the commissioning of the new
projects is imperative and urgent and cannot be delayed, NERC if he is satisfied
that there is urgency may in tis absolute discretion by writing under tis hand
authorize the licensee to commission the projects prior to inspection:
(a) Provided always that any projects so commission herein Provided for
shall be subjected to inspection and test not later than three months
following the date they were commissioned.
(b) provided further that where the inspection and tests disclose that the
projects do not comply with the requirements of these regulations, any
defects so disclosed shall ht: made good within 21 working days (twenty
one days) of the date of the inspection tailing which the projects shall be
taken out of use and remain unused until the defects are remedied to the
satisfaction of the Inspecting Engineer
b. Cables shall be housed in durable pipes or cables armoured with metal wires with a
mechanical strength not less than that of galvanized steel wires with a diameter of 6
mm shall be used for underwater transmission lines.
iii. Class A earthing work shall be provided to the metallic parts of tubes and
other protectors that contain cables, metallic electrical conductor joint boxes,
and metallic members to be used for covering the cables (Class D earthing
work be provided where they are installed so that nobody shall touch them),
Page 99 of 282
except where corrosion prevention measures are provided or the electric
resistance to the ground is not more than 10.
iv. Where electrical lines over bridges are installed close to or across other
facilities, the clearance between them shall be not less than the values
specified in Table 3.33.
Table 3.33
Earthing work shall be classified into Class A, Class B, Class C and Class D,
and each resistance value to earth is listed in Table 57-2.
Classification of Resistance to
Conditions for easement of resistance value
earthing work earth
Class A 10 or less
In cases where voltage to earth of a low-voltage
230 electrical circuit exceeds 330kV due to power contact
Class B
or
I* 1
between the medium-voltage electrical circuit and the
low-voltage electrical circuit of the transformer, when an
Page 100 of 282
less earth leakage breaker that cuts off the electrical circuit
600
within 1 second is installed, or less. However, if
I *1
a calculated value becomes less than 5, it shall not
be necessary to obtain resistance less than 5, and if a
calculated value becomes more than 10, it shall not
be necessary to obtain resistance more than 10.
In the case where earthing arises in a low-voltage
electrical circuit, when an earth leakage breaker that
Class C 10 or less acts within 0.5 seconds is installed, the resistance
value shall be 500 or less.
In the case where earthing arises in a low-voltage
electrical circuit, when an earth leakage breaker that
Class D 100 or less
acts within 0.5 seconds is installed, the resistance
value shall be 500 or less.
[Notes]
*1 Single-line earth fault current (I) of an electrical circuit in the medium-voltage side in Class B earthing may conform to
an actual value or either of the following values.
Page 101 of 282
Chapter 4: Injection Substation Installations
4.1 Civil Works
4.1.1 Civil Design
The Design of civil works for Injection Substations shall be based on the following
specifications: All materials used shall be in accordance with approved engineering
designs and specifications in conformity with relevant extant Nigerian Industrial
Standards and Codes.
Geotechnical Investigations shall be carried out on all Injection Substation sites. The
report of the soil tests shall form the basis for all related civil design works for
Injection Substation construction.
The design, site preparation and execution of all related civil works as it affects the
construction of Injection Substations shall be in accordance with the following
guidelines:
4.1.2.1 Earthworks
Earthworks shall include, but is not limited to, the clearing of the site, the supply and
compaction of fill materials, excavation and compaction of backfill materials for
foundation, access road construction, drainage, trenches and final gravelling as
specified in the National Building Code (NBC).
Page 102 of 282
4.1.2.2 Access Road
Access road to Injection Substation sites shall measure, and not be less than 7.3 m
wide from any adjoining/existing public road with adequate clearance for
manoeuvring of heavy-duty vehicles.
Within substation fencing, roads to be provided for access along with car parking lot
shall have capacity to accommodate a minimum of five cars with adequate
clearance from installed equipment and building. Layout of the roads shall be based
on layout drawing for the substation. Parking areas shall be provided for site
personnel and visitors as per layout drawing. Adequate turning space for vehicles
shall be provided and bend radius shall be set accordingly.
All access roads, up to the control room building, shall be constructed to have a
minimum load-bearing capacity that will support the transportation of heavy-duty
equipment up to 100MT. All access roads shall be provided with paving stones and
clearly demarcated with side kerbs. The roadside kerbs used for the construction of
all access roads shall be of a minimum thickness of 80 mm with compressive
strength of not less than 450 kg/cm2.
All perimeter fencing shall be designed to meet critical loading conditions peculiar to
the site under consideration such as to withstand the prevailing wind speed within
the environment.
Page 103 of 282
the finished laterite level but flushing with the top level of the crush rock. The top of
the concrete foundation of the steel pipes shall be cambered to prevent water
stagnations that might lead to rusting.
The vehicular and pedestrian gates shall be plastic coated chain link with galvanized
steel frames/posts.
The widths of the vehicular and pedestrian gates in fully opened position shall be 5.0
m and 1.0 m respectively.
The widths of the vehicular and pedestrian gates in fully opened position shall be 5.0
m and 1.0 m respectively.
b. Gates shall be provided for men and machines/equipment to be taken into and
out of the substation.
c. Capacitor bank cage, which shall be part of the capacitor bank installed.
Wherever necessary, anti-reptile fixture/arrangement shall be provided along
with fencing.
Page 104 of 282
4.1.2.8 Electric Fencing
Where Electric Fencing is installed as part of security measures to prevent
unauthorized entry and access into substation premises, it shall be mandatory that
clearly marked Warning Signs be displayed within visible range of not more than six
metres apart on all sides of the perimeter fencing.
The control room building design shall take the following into consideration:
The construction of control room building shall conform with the requirements of the
National Building Code. The structural design and details of the control room
building shall be able to guarantee the following stability conditions:
An open workspace of a minimum of 1.2 m shall be provided between the wall and
the switchgears to allow for movement and access as well as maintenance.
The construction of the equipment plinths shall take into consideration the site
geotechnical investigation report and shall be designed to meet the load bearing
capacity that will adequately support the weight of the intended equipment to be
installed in the substation.
In addition, the design and construction of the equipment plinth shall accommodate
the equipment manufacturer’s specifications.
Page 106 of 282
4.1.4.1 Plinth Filling
Plinth Filling shall be carried out with approved materials in layers not exceeding 150
mm watered and compacted with mechanical compaction machine or hard-tempers
where mechanical compaction is not possible. The compacted surface shall be
properly shaped, trimmed and consolidated.
4.1.5 Drainage
The entire substation area shall be provided with adequate drainage facilities to
prevent flooding and accumulation of water.
Building drains shall be provided for the collection and evacuation of storm water
from the roof and the adjoining facilities. The design of drain collectors shall be
adequate to effectively evacuate storm water from the substation.
a. Operating Voltages
b. Ambient temperature
d. Soil Resistivity
f. Cable type
g. Method of earthing
h. Load cycle
Cable trenches shall be of a minimum depth of 1.0 m except under the switchgear
where the trench shall be of a depth of 1.2 m and a minimum width of 800 mm for
cable trench and switchgear panels;
Page 107 of 282
Manhole capable of permitting bending radius of 3.0 m shall be provided along the
trench route prior to cable entry into the control room.
Trenches must be watertight and must not be connected to the outside drainage
system.
Trench covers must be suitably constructed to support pedestrian traffic. The covers
must be divided into sections of maximum of 1.0 m lengths, each weighing not more
than 20 kg.
The trench cover when laid across the trench shall be flush with the surrounding
floor level.
4.1.8 Graveling
The Injection Substation active switchyard area shall be demarcated using roadside
kerbs and gravelled with 25 mm aggregate chippings to a minimum depth of 150
mm.
4.1.9 Landscaping
Landscaping shall be carried out in non-active areas of Injection Substation.
Non-active areas within the Injection Substation shall be landscaped for proper
levelling, paving, sloping, consolidation and grassing.
Page 108 of 282
Substation design shall be carried out in accordance with loading design
parameters, calculations, site survey, engineering design layout, earthing and
bonding requirements, and equipment specification for indoor and or outdoor types.
Equipment layout design for Injection Substations shall take into considerations the
type of usage i.e. indoor/outdoor type and shall have enough spacing for operators
to install, operate and move their equipment safely.
Equipment shall be located such that any other equipment may be removed within
the layout with the remaining equipment in service and under load. A passageway of
at least 2500 mm wide shall be allowed for transformers and 1500 mm wide for the
high voltage and low voltage boards.
a. Switchgear and control gear – IEC 60694, IEC 60298, IEC 62271-200, IEC
60529.
b. Circuit Breaker; IEC 62271 – 100
c. Isolating and earthing switches – IEC 62271-102
d. Current Transformer – IEC 60185
e. Voltage Transformer – IEC 60186
f. Relays – IEC 60215
A clear passageway of at least 1.0 m wide shall be allowed from each item of
switchgear to the access door.
Page 109 of 282
concrete poles of adequate sizes that shall give adequate ground to line clearance
of not less than 4.2 m.
Active switchyard area in the Injection Substation shall have the following primary
equipment installed:
4.2.4.1 Transformers
Transformers to be installed in Injection Substations shall consist of the following:
ii The range of capacity shall include 2.5 MVA and up to 30 MVA, 33/11 kV.
Nominal voltage
Iv The system operating conditions shall conform with to the provisions of the Grid
Code, and Distribution Code and IEC 60076 (All Parts).
Page 110 of 282
S/No. Subject Standard
i. Power transformers – IEC 60076 – 1
Part 1: General
ii. Power transformers – IEC 60076 – 2
Part 2: Temperature rise for liquid‐immersed
transformers
iii. Power transformers – IEC 60076 – 3
Part 3:
Insulation levels, dielectric tests and external
clearances in air
iv. Power transformers – IEC 60076 – 4
Part 4:
Guide to the lightning impulse and
switching impulse testing –
Power transformers and reactors
v. Power transformers – IEC 6 60076 – 5
Part 5:
Ability to withstand short circuit
vi. Power transformers – IEC 60076 – 6
Part 6: Reactors
vii. Power transformers – IEC 60076 – 7
Part 7: Loading guide for oil‐immersed power
transformers
viii. Power transformers – IEC 60076 – 8
Part 8: Application guide
ix. Power transformers – IEC 60076 – 10
Part 10‐1:
Determination of sound levels –
Application guide
x. Power transformers – IEC 60076 – 13
Part 13:
Self‐protected liquid‐filled transformers
xi. Power transformers – IEC 60076 – 14
Part 14: Design and application of liquid‐immersed
power transformers using
high‐temperature insulation materials
The power transformer shall be capable of supplying its rated power continuously under
ambient temperature conditions without the temperature rise of the top oil exceeding
500C. The ambient temperature conditions are as follows:
Page 111 of 282
The power transformer may be overloaded during emergency up to 150% of its
continuous rating in accordance with IEC 60076-1
The power transformer tap changer (on-load) shall be suitable to compensate for
system voltage variation of ±5% maintained at nominal tap position 33/11kV voltage
ratio.
Vector group of the 11/0.415kV distribution transformers shall be Dyn11 and Dyn1 for
33/11 Kv, 2.5MVA capacity and above in accordance with IEC 60076 – 1.
The power transformer for Injection Substations shall be equipped with bushing current
transformers suitable for protection and metering purposes.
The voltage transformers shall be suitable for base mounting on steel channel
structure.
Current transformers for Injection Substation shall conform to with the requirements
of IEC 61869-1, 2 and suitable for base mounting on steel channel structure.
Wound type current transformers, other than bar-type primary, shall be equipped
with primary bypass devices for protecting the windings against high-voltage surges.
The insulating materials used for the construction of current transformers shall
conform to IEC xxx.
Page 112 of 282
Injection Substation current transformers shall be tested in accordance with the
provisions of IEC61869-1, 2.
The positioning and installation of the station service transformer shall be adequately
provided for in the Injection Substation Layout and minimum safety clearance for
operations and maintenance shall be observed.
Switchgears for indoor and outdoor operations shall meet the following conditions as
specified below:
All indoor switchgear for Injection Substations shall be of the extensible metal
clad, compartmentalized, air insulated, and draw out type complying with the
requirements of IEC 62271-200.
Page 113 of 282
Non-hygroscopic and non-flammable materials shall be used for the
manufacture of switchgear equipment and apparatus. Insulating materials for
switchgears shall have a high resistance to tracking. Switchgears shall be
installed in Injection Substation building with a cable basement and mounted
on a concrete floor.
The mounting height of the Circuit Breaker live part shall not be less than
2.5m measured from the plinth level. The operating characteristics shall
comply with IEC 62271-100, 200.
The circuit breaker arc interrupter unit may be of vacuum, SF6 gas type or
any other approved type based on innovation in technology. The SF6
breakers using the SF6 gas shall be handled in accordance with the
procedures specified in IEC 62271-4.
The main blade and grounding switch contacts shall be self-aligning and self-
wiping contacts. Fixed contacts shall be capable of preventing contact
burning and pitting under fault conditions.
Page 114 of 282
closed conditions. The material used for contacts shall be such that there will
be no irritation of contact metals after 1,200 open/close switching operations.
Bypass Isolator shall be installed between the main bus and the reserved
bus and / or circuit breakers to allow for safe maintenance without loss of
power to the adjourning circuit.
All protective devices associated with the bypassed circuit breaker must be
transferred to an adjoining circuit breaker in line with the same circuit so as
not to leave the circuit unprotected.
Page 115 of 282
4.2.4.3 Compensators
Compensators such as Static VAR Compensator or Dynamic Voltage Restorer shall
be installed on distribution network to ensure and guarantee the quality of power
supply at locations where the line voltage drop is below the allowable nominal
values.
4.2.4.4 Capacitors
Capacitors shall be installed to compensate the inductance of long distance
transmission / distribution lines where the parameters of the line drop below the
acceptable nominal value as specified in the Grid and Distribution Codes.
Shunt capacitor banks shall be properly fenced out with wire gauze chain link and
solidly grounded.
Page 116 of 282
4.2.5.2 Relays
All relays used in Injection Substations shall conform to with the requirements of IEC
60255.
Page 117 of 282
Distribution networks shall be designed, operated and maintained to allow for
interoperability of substation automation devices in accordance with the
requirements of IEC 61850.
Communication equipment to be installed shall be such that can interface with the
substation IEDs to acquire data to determine the operation status of each IED,
support standard protocol to enable the substation integration and maintenance.
The source of the potable water supply shall be separated from the wastewater
collection point with a minimum distance of 5.0 m.
A minimum illumination level of 100 lux shall be provided within the main switchyard
area.
Page 119 of 282
Chapter 5: Distribution Network
5.1 General
Distribution Network Standards and Specifications outline compulsory procedures and
practices necessary for safe workspace for persons working on Nigeria’s distribution
network. It is the responsibility of all persons involved in network operations to ensure that a
safe work method is employed and that statutory requirements are met. In this context, all
electrical works shall be designed to be safe for the electrical conditions likely to be
experienced during service and the physical environment in which they will operate, taking
into account foreseen and unforeseen risks likely to be encountered.
a. Materials:
All materials used for electrical works, their components, accessories and support
structures shall be such as to ensure safe operational performance within the
anticipated life span of the installation.
b. Environmental Issues:
The design, construction and installation of electrical works shall take into consideration
environmental issues and concerns, which include but not limited to:
- The promotion of energy efficiency,
- The social impact of new projects, and community concerns,
- The minimization of environmental damage, including visual impacts, tree and
forestry management programmes,
- The consideration of Electromagnetic radiation.
- Erosion prone environment.
c. Thermal Ratings
The thermal capacity of electrical works shall be sufficient to pass the electrical load for
which they are designed, without reduction of electrical and mechanical properties to a
level below that which provides safe operational performance.
Page 120 of 282
e. Mechanical Loading Conditions
The electrical works shall have sufficient mechanical and structural strength to withstand
anticipated stresses and strains due to environmental and electrical service conditions.
i. Systems of Supply
The following system standards shall apply–
a. Frequency – The frequency shall operate within a narrow operating
band of ± 0.5% from 50Hz (49.75 – 50.25 Hz); but under System
Stress, the Frequency on the Power System could experience
variations within the limits of 50 Hz ± 2.5% (48.75 – 51.25 Hz).
b. Standard A.C. voltages – shall be 230 V ± 6% between phase
conductor and neutral conductor and 400 Volts ± 6% between
phases conductor; Primary distribution high voltage shall be 33,000
Volts ± 6% and secondary distribution high voltage shall be 11,000
Volts ± 6%;
Page 121 of 282
d. This regulation shall also apply to Captive Generation Licensee.
Page 122 of 282
All materials, equipment, devices and accessories used directly in construction,
installation and maintenance of distribution network shall constitute electrical
network equipment and installation devices. They shall include but not limited to:
Page 123 of 282
Where overhead lines with bare conductors are routed across sites used for public
recreation and work activities other than farming, they shall be protected with cradle
guards.
Where bare overhead lines present a risk, the following alternatives shall apply in
order of preference with appropriate insulation
a. Underground Cables
b. Insulated Conductors.
The size of the neutral conductor shall not be less than that of phase conductor. The
street lighting switch conductor shall be 35mm2 (2.65mm) Aluminium or 25mm2
(7/2.34mm) hard drawn copper.
The PVC insulated conductors shall comply with NIS 359.
Page 125 of 282
5.2.9 Arrangements
In the network where street lighting switch wire is not required, the normal
arrangement of conductors for a three phase, 4-wire line from top to bottom shall be
as follows:
Neutral No. 4
Where street lighting is required, this shall occupy position No. 4 and the neutral
shall be placed in a fifth position below the switch wire. If the switch wire is not to be
erected initially, position No. 4 shall be left vacant. For a single phase, two wire line,
position Nos 3 and 5 shall be used. Two-phase three-wire construction is not
permissible, and shall be avoided in the design of new overhead networks.
The rated breaking strength of the conductors shall be capable of withstanding the
mechanical loading without undue sagging within acceptable temperature limits and
other adverse weather and environmental conditions they shall be subjected to
during their service years.
5.2.11 Load Bearing Capacity for Overhead Distribution Lines and Safety Factors
Overhead distribution lines shall have capacity capable of withstanding loading due
to;
Page 126 of 282
i. Designed current capacity within its temperature threshold
ii. Weather conditions such as wind, ambient temperature, solar radiation, rain and
storm
iii. Mechanical loading (line tension without undermining voltage-specific ground
clearance)
Page 127 of 282
i. Support: 50% of the factors of safety given in Regulations 53 (f) to 53 (1);
ii. Foundations: 50% of the factors of safety given in paragraph (m) of this
regulation.
The minimum factor of safety shall be based on such load as would cause failure of the
support to perform its function (assuming that the foundation and other components of the
structure are intact).
Joints between conductors of overhead lines shall be mechanically secure and electrically
continuous under the conditions of operation. The ultimate strength of the joint shall not be
less than 95 per cent of that of the conductor and the electrical conductivity not less than
that of the conductor. No conductor of an overhead line shall have more than two joints in a
span.
Insulators used in the distribution network shall be of high grade devoid of impurities and
have insulation/dielectric strength that shall suffer minimal adverse effect when exposed to:
Homogenous and non-homogenous electric field
Mechanical stress
Chemical effects
Conductor surface effects
Page 128 of 282
Other ambient effects like pressure and temperature
The Insulators shall meet the requirements of IEC 60071-2. The minimum acceptable failure
rate of the insulators shall be 0.004/year for apparatus and 20/100km/year for distribution
lines.
Cradle guards, guard nets, earth bars and protective devices shall be installed where
necessary in accordance with Clauses 5.2.15 to 5.2.21 below. The cost of such installation
shall be borne by the last service provider to arrive at the point.
a. The height of an electric line under the most adverse operating conditions, above
the highest recorded water level, over harbours, rivers and waterways, shall not
be less than that required by the appropriate authorities for physical safety
clearance PLUS a minimum electrical safety clearance of 3 metres of 1 metre
per 78 kV or phase to neutral voltage of the electric line, whichever the greater.
b. The licensee shall have at least thirty days and not more than ninety days prior
to the placing of such work serve written notice on the appropriate authorities
specifying the intended use of the works, the voltage of operation and such other
information that the authorities may require him to supply.
c. Every notice served in conformity with Clause 5.2.15.(b) shall be accompanied
by a plan of suitable scale indicating the site of the crossing, the location of all
supports, stays, struts, switches, transformers and other apparatus intended to
be used.
d. The authorities may within 21 days of the receipt of such a notice of intention
served under Clause 5.2.15(b) serve a counter notice on the licensee -–
i. Objecting to the siting of the works specifying the reason in the
counter notice; and
ii. Requiring protective features to be fitted, such features to be specified
in the counter notice.
Where mutual agreement is not reached the matter shall be referred to the Commission
whose decision shall be final.
Page 129 of 282
The provision of Clauses 5.2.15(b) to 5.2.17 shall apply where the licensee intends to
place an electric line, other than a service line, in the proximity of, over or under a
railway line.
a. The provision of Clause 5.2.15(b) to 5.2.17 shall apply where the licensee
intends to place an electric line, other than a service line, in the proximity of, over
or under Posts and Telegraphs line.
b. Other than in the case of a fully insulated services line all electric lines, except
with the written authority of the Commission, shall cross over Post and
Telegraphs lines with a minimum clearance, under the most adverse operating
conditions at the point of crossing of –
c. So far as may be practicable the licensee shall leave one side of each street free
for telegraph line and where the street is continuous the licensee's line shall be
kept to the same side of the street for the whole distance.
d. Except with the permission of the Posts and Telegraphs Authorities all overhead
lines shall be placed on the opposite side of the street to that on which any
telegraph lines are erected, and where the erection or operation of the electric
lines necessitates an alteration of an existing telegraph lines, and such alteration
is approved by the Posts and Telegraphs Authorities, the expense of the
alteration shall be borne by the licensee; provided that where existing telegraph
lines of the Posts and Telegraphs Authorities occupy both sides-of the street that
Authority shall bear the cost of putting all telegraph lines on the one side of the
street or if agreeable to the licensee, consent to an arrangement for the joint use
of poles on both sides of the street.
e. Where electric lines are on one side of the street and telegraph lines on the
other, and service is required to be given from either side to the other, the
licensee and the Posts and Telegraphs Authorities shall give to each other
reasonable facilities as far as possible to effect supply. Where possible electric
service lines, unless fully insulated, shall pass over telegraph lines and telegraph
service lines shall pass under electric lines.
Page 130 of 282
The provision of Clauses 5.2.15(b) to 5.2.17 shall apply where the licensee intends to
place an electric line in the proximity of an airfield
The provision of Clauses 5.2.15(b) to 5.2.17 shall apply where the licensee intends to
place an electric line, other than a service line, in the proximity of a radio or television
aerial.
Cradle guards, guard nets and protective devices shall be installed in accordance with
under the provisions of Clause 5.2.14 the cost of such installation shall be borne by the last
service provider to arrive at the point.
Where guarding is required under these rules the provisions of sub rules (2) to (4) shall
apply:
i. Every guard-wire shall be connected with earth at each point at which its electrical
continuity is broken.
ii. Every guard-wire shall have an actual breaking strength of not less than 635kN or
kg and if made of iron or steel, shall be galvanised.
iii. Every guard-wire or cross-connected systems of guard-wires shall have sufficient
current-carrying capacity to ensure the rendering dead, without risk of fusing of
the guard-wire or wires till the contact of any live wire has been removed.
Pole line surveys – A survey shall produce a plan and profile of the surveyed route. The
plan shall show the route the line will follow and the significant topography adjacent to the
route and the profile shall show the ground elevation along the line and the top elevations of
the poles. These elevations shall be set in accordance with minimum allowable clearances
specified in Clause 5.2.3 of these Regulations.
Poles for distribution lines shall be placed on the side of the streets that is most free of other
lines and trees. A distance of 45 m shall be maintained between adjacent poles up to a
maximum of 50 m where it becomes difficult to maintain the statutory distance between
poles. A long roads, poles shall be placed at a minimum distance of 1.5 m from the inside
edge of the kerbs or 1.5 m from the edge of the road surface where kerbs do not exist. On
open roadways or highways, poles should be set at 0.45 m from the outside of fences.
All engineering designs shall be carried out, certified and approved by qualified COREN
Registered Engineer(s).
Page 131 of 282
Engineering designs of overhead distribution lines shall also take into consideration the
following;
Compliance with Statutory Regulations
Safety of equipment, employees and the general public
Economic utilization of materials
Conformity with international best practices that meet the need of users with
minimum environmental impact
To conform to acceptable standards, both from an engineering point of view and
aesthetics.
Materials and accessories for overhead line construction shall be designed to meet all the
electrical and mechanical loads likely to be experienced in service as far as reasonably
practicable.
Selection of Insulators
The following factors shall be considered in the selection of the appropriate insulation of
overhead lines:
50 Hz performance
Impulse capabilities
Switching capabilities
Page 132 of 282
For design purposes, the average minimum and maximum ambient temperatures shall be
20°C and 45°C respectively.
Unless otherwise authorized by the Commission in writing, the following working conditions
shall be assumed for design purposes-
Stay Insulators
The stay insulators shall be mounted not less than 2.7 m vertically above ground and have
a wet power frequency flashover voltage not less than one and a half times the highest
voltage conductor supported by the pole.
Conductor Sag
The sag for overhead distribution lines, which is the vertical distance between the point
where the line is joined to the support structure and the lowest point on the line, shall be
parabolic in shape.
Clearances must also be observed when stringing a line. The normal clearances for
overhead lines are as shown in the table below.
Cross - arms
Cross arms shall be fiber, treated opepe wood or steel constructed. The mechanical loads
to which cross arms may be subjected shall take into consideration t the conditions likely to
be experienced in service so as to minimize the probability of failure.
Page 133 of 282
• Bending moment due to direct horizontal pull of conductors (termination or strain and
stress structures only).
• Maintenance loads resulting from additional conductor lowering or anchoring
activities.
• The self weight of the cross arm
The foundation shall be so constructed taking into account the reaction of the soil at all
times of the year in which they are planted for the load they are to carry so as to withstand
the transverse, horizontal and vertical loads without exceeding the material strength limits
set out in the factor of safety requirements.
Pole foundation depth shall comply with the standards set in the table below;
Page 134 of 282
1 6.10 1.22
2 7.32 1.52
3 8.54 1.52
4 10.06 1.84
5 10.98 1.84
6 12.20 1.98
7 13.72 1.98
8 15.25 2.13
9 16.77 2.13
10 18.36 2.29
11 18.82 2.29
12 19.85 2.44
Poles planted along sandy, swampy and clay soils shall in addition, have concrete bases
with a depth of 0.8 m below ground level and 0.6 m above ground level.
a. Every support carrying electric lines shall be made of wood, steel or reinforced concrete
or any combination of any of such materials or any other approved materials and in the
case in which wood or steel is used in the construction of the support, such wood or
steel or any other approved materials shall be, so far as is reasonably practicable,
protected against decay, corrosion or other deterioration.
c. In no case shall the strength of a support in a direction parallel to the overhead line be
less than one quarter of the strength in a direction transverse to the said line.
d. All overhead electric lines shall be attached to suitable insulators carried on cross-arms
or brackets of suitable materials and cross-section, and they shall be so attached to the
insulators, or guarded, that they cannot fall away from the supports in case they become
detached from the insulator, but will fall on the cross-arm or insulator support.
e. All lines at angles shall be attached to the insulator so that the insulator, and not the
binding wire, takes the strain.
Page 135 of 282
f. The minimum diameter of wooden supports shall be in accordance with the relevant
Nigerian Standards.
5.1.3.8 Load Bearing Capacity for Support Structures of Distribution Lines and Safety Factor
The transverse load on any support carrying an electric line shall be calculated in
accordance with its average height above ground level throughout its span, and the wind
pressure on the leeside of lattice steel or other compound structures shall be deemed to be
one half of the pressure on the leeward side. The vertical loads on supports shall comprise
the weight of the supports themselves and any insulators and fittings attached thereto,
together with the loads imposed by the electric lines and their fittings.
Factors of safety
Overhead electric line supports, in conjunction with stays and struts if provided, shall
withstand the longitudinal, transverse and vertical loads due to fittings, conductors and wind
loadings under the most adverse temperature conditions and with the factors of safety
herein under specified
Page 136 of 282
strength corresponding to failure
(m) I foundation for supports against overturning 2.5
lateral shearing, toe compression and uprooting under
maximum simultaneous working loads based on soil
bearing strength
(n) J under a single broken electric line or earth i. Support: 50% of the factors of safety
wire condition the factors of safety for supports and given in under items F TO H above
foundations shall not be less than ii. Foundations: 50% of the factors of
safety given in item I above..
a. Stay wires connected to wooden supports carrying electric lines of all voltages, and also
stay wires connected to concrete supports carrying electric lines at 400 volts or less
shall be insulated to prevent danger from leakage. For this purpose, an insulator of the
same or greater rating as the insulator supporting the electric lines, shall be inserted in
the stay wire not less than 3.0 m vertically above ground and below the level of the
electric line.
b. Stay wires connected to steel supports or any other supports made of an electrically
conducting material shall be insulated.
c. Where a stay wire crosses over a road or street a minimum distance of 5.8 meters to
ground level shall be maintained.
e. Stay insulators shall have a mechanical strength equal to or greater than that of the stay
in which it is installed.
f. Where a stay wire is installed in a public place or in any other location in which it may
constitute a hazard, it shall be:–
(1) The height above ground of any electric line under the most adverse operating
conditions shall not, except with the written authority of the Commission, be less than the
height appropriate to the system voltage and situations tabulated below-
(2) Fully insulated service lines operating at a voltage not exceeding 400 volts may be
terminated on buildings at a height of not less than 2.7 metres from ground level provided
that the street clearance at any point of its span is not less than 6.1 metres.
d. Where the circuit of the higher voltage is fully insulated, the minimum clearance
calculated in accordance with the provision of above Table may be reduced by 50%.
7 Alternative provisions
(1)Where the conditions, provided for under the clearance of electric lines to buildings
above cannot be met, the line shall be erected so that the minimum horizontal distance in
metre of the nearest conductor in still air is not less than-
(Conductor sag at maximum design temperature plus length of suspension insulator
string) plus “B”, where "B" is a constant dependent on the voltage between phases
of the conductors of the line-
415 volts - 11,000 volts .............................. 2.4 m
33,000 volts ................................................. 3.0 m
132,000 volts ……………………………… . 4.0 m
330,000 volts …………………………………6.0 m
Page 139 of 282
Over 330,000 volts ....................................... 9.0 m
(2) Where the conductors of the circuit are fully insulated, the constant "B" may be
reduced by 50%.
(3) In the case of specially designed fully insulated aerial cables, clearance to buildings
may be reduced at the discretion of the Commission.
(4) No building or other structure shall be erected under or adjacent to an electric line
without adhering to the provisions of these Regulations.
Page 140 of 282
of a consumers installations shall not be lower than which the licensee would be
prepared to accept under these Section 7.
c. The obligation imposed by Clause 5.4.1.4a of this regulation in regard to the
maintenance of any electric lines and apparatus as aforesaid situated on the
consumers side of the supply terminals and forming the whole or part of a consumer
installation shall be subject to the terms of any agreement entered into between the
licensee and the consumer with respect to the letting on terms or hire-purchase of
the said whole or part of the consumers installation.
d. Nothing in this regulation shall relieve the owner or occupier of any premises, being
a consumer within the meaning of these regulations. From any obligation imposed
on him/her by the provisions of clauses 5.2.1.4(a) to 5.2.1.4(c)
Page 143 of 282
(h) adequate means are provided for preventing any unauthorized person from
coming into contact with any part of the consumer’s installation which is
designed to be electrically charged at high voltage and that an appropriate
danger notice is displayed at points of access thereto; or
(2) Where the consumers, in writing that the installation has been installed and will be
maintained in compliance with the provisions of the XXX the installation shall be
deemed to fulfill the requirements of this regulation save in so far as these Regulations
specifies any requirements not contained in the Section XX.
(3) Provided that where it can be shown that in the event of an accident involving death
or injury to any person or persons, the customer had failed to install or maintain the
installation in compliance with any written guarantee shall be liable to prosecution under
the provisions of these Regulations.
b. Underground connections from the nearest service pole to the customer meter position.
Customers with load profile up to 10kW shall be serviced on three phase 4-wire with
cable of minimum cross sectional area of 10mm2 x 4core or 16mm2 aluminium PVC
insulated cable.
a. Prospective customer shall apply to the licensee for temporary electricity supply using
prescribed format.
b. The licensee or his representative shall inspect or examine the possibility of providing
the electrical power as requested.
c. The licensee shall advice the customer of requirements for provision of temporary
electric supply if found that electric power supply can be extended.
e. Electrical service connections including metering shall be arranged by the licensee if all
the requirements have been met.
f. If the electrical load requirements cannot be met, the customer shall be informed in
writing. On receipt of the decline of connection, the contractor/customer shall make
alternative arrangements for supply of electrical power to his installation.
g. If the electrical load requirement can be met, the licensee shall approve request as per
application.
Page 146 of 282
h. The customer shall draw from the network the energy required as per request up to a
total load indicated in the application.
i. The electrical power to the customer shall be in the form of single phase or three-phase
alternating current at a nominal frequency of 50Hz.
j. The customer shall pay the cost towards electrical installation and security deposit as
demanded by the licensee.
k. The customer shall pay for the cost of electrical energy as agreed upon by both parties.
l. If customer fails to pay for the energy consumed within the time as stipulated by the
licensee, it shall be lawful for the distribution company to cut off the supply of power after
giving 15 days notice.
m. The quantity of electrical energy supplied by the licensee to the customer shall be
ascertained by means of a meter or meters to be provided by the licensee.
n. The said meter or meters, shall at all reasonable time be open to the licensee or his
authorized representatives and shall be properly sealed on behalf of both parties and
shall not be interfered with by either party except in the presence of the other party or his
representatives duly authorized on that behalf.
o. The customer shall not make any alteration on the machinery or equipment either by
way of addition or substitutions or transfer which is liable to increase the obligation of the
licensee to supply electrical energy in excess of the agreed demand and or which may
affect the supply system of the licensee to its detriment.
p. In any event, the customer shall notify the licensee of the intended alterations, additions,
substitutions or transfer and obtain the prior approval of the licensee in writing before
execution of any such action.
q. The power factor of the plant and apparatus owned and operated by the customer at
individual points of supply shall not ordinarily be less than 0.90. If it tends to drop below
0.9, it shall be improved by the installation of static capacitors, failing which; the supply
shall be disconnected with a 10 working days notice.
s. The licensee and customer shall agree that it shall be competent for either party to
terminate this agreement by issue of 10 working days notice sent by registered post.
t. Safe operation and maintenance of internal wiring, electrical fittings and installations will
be the responsibility of the customer in such conditions as to be free from danger as per
provisions stipulated in this regulation
Page 147 of 282
u. Power supply shall be used only for the purpose asked for and not for any other
purpose. If the supply is used for any other purpose, or extended to a third party, the
licensee will disconnect the supply after due notice except in circumstances covered by
Section 6 of Connection and Disconnection Procedure Regulations of NERC.
v. The licensee does not in any way hold itself responsible for any accident, damage or
injury that may result from or through the presence of electrical connection in the above
place.
Page 148 of 282
5.5 Underground Distribution
General Requirements
Underground distribution lines shall consist of networks constructed with cables and
associated equipment according to prescribed standards. All cables, whether for A.C. or
D.C. and for all voltages, shall be insulated as required and manufactured in accordance
with appropriate Nigerian Industrial Standard Specifications. Where steel armouring is
employed, it shall be effectively earthed and bonded at all joint boxes so as to be electrically
continuous.
Standard cable sizes and characteristics for underground distribution lines are as contained
in NIS IEC 60502.
Cables shall be of hard drawn stranded copper. Bare aluminium cables shall not be used for
underground distribution network.
Classification of cables
Cables shall be classified according to the operating voltages as follows
Low Voltage Cables Rated up to 2,000 volts
Medium Voltage Cables Rated 2,001 through 46,000 volts
High Voltage Cables Rated 69,000 volts to 500,000 volts
Extra High Voltage Cables
Voltage rating
Distribution cables to be used in the underground distribution network shall be rated based
on phase-to-phase voltage values.
Materials
Cables for use on medium and low voltage circuits shall be copper conductor impregnated
paper insulated belted 4-core, lead sheathed cables complying with NIS IEC 60055-2, to be
checked 4-core cables shall be steel tape or stranded armoured, PVC insulated cables
complying with NIS IEC 60502 to be checked shall also be used. Cross-linked polyethylene
(XLPE) cables shall also be accepted in medium voltage underground distribution lines.
The sizes of cables shall be as shown below:
Page 149 of 282
Number of Cores Nominal Conductor Size and Material
2
4 35mm copper for customer’s services only
2
4 70mm copper for mains and uprisers
2
4 150mm copper for mains and uprisers
Single 185mm2 copper from Transformer to Feeder Pillar (LV Cable)
2
“ 300mm copper Transformer to Feeder Pillar (LV Cable)
2
“ 500mm copper Transformer to Feeder Pillar (LV cable)
2
3 120 – 185mm (Medium voltage)
2
1 240 – 500mm (Medium voltage)
All components used for jointing and terminations (including cable components), which will
come into contact with either masking tape or adhesive sealants, shall be thoroughly
cleaned and degreased prior to the application of these sealing agents. Cleaning shall only
be done using lint-free cloth.
Heat shrink tubings shall be positioned correctly, and properly and evenly shrunk, free of
voids and shall not be damaged due to overheating. Heat shrink components with adhesive
sealant coatings shall provide effective sealing against moisture ingress when installed.
The specified overlapping distances between various heat shrink tubings and cable
components shall always be adhered to.
Completed joints and terminations shall be allowed to either cool down or set before they
are subjected to any further mechanical load.
The three active cable cores shall be coloured red, yellow and blue. The neutral core shall
be coloured black.
The completed joint if directly buried, shall be surrounded in soft bedding material up to a
depth of 100 mm above the joint.
Page 150 of 282
The minimum internal bending radius of the cable, electrical clearances in cable end boxes
and the practical aspects of cable laying shall dictate termination of 3-core cables.
Trifurcation, three core terminations and three-to-one joint methods of termination shall
apply to appropriate cable sizes to meet the requirements of internal bending radius and
safe clearances at the end boxes.
The lugs shall be of the compression type and shall have sealed palms and barrels (except
for the cable entry end). Compression lugs shall be installed in strict compliance with the
manufacturer’s recommendations of crimps. Lugs shall be long barrel type and suitably
sealed for outdoor use.
Excavation of Trenches
(1) The cables shall be laid at a depth of not less than 1 metre below surface level and in
cases where two or more power cables are laid in the same trench, a minimum distance of
300mm shall be maintained between the cables.
(2) To prevent the cables being damaged by stones the cables shall be laid in a bed of sifted
soil or sand and to prevent mechanical damage the cables shall be protected by inter-locked
tiles sufficiently wide to give a minimum of 50 mm on each side of the cable and laid
approximately 150 mm above the cables.
(3) The cable route shall be indicated at surface level with cable markers at suitable
intervals, particularly at positions where the cable changes direction stating the voltage
levels.
Page 151 of 282
Route Identification of Underground Distribution Cables
5.5.4.1 Cable routes
Underground cable routes shall be planned bearing in mind the type of use, or foreseeable
use, to which the land is or may be put into use.
Cable routes shall be along the footpaths and across roads.
Routes shall not be planned along carriageway unless other alternative routes are not
reasonably practicable.
Where a cable route crossing a private land is unavoidable then a permanent easement
shall be obtained.
Laid-In Footpaths
If one medium voltage and one high voltage circuit are to be accommodated, the high
voltage cable shall be laid 230 mm deeper than the medium voltage cable, topped with 80
mm of backfilled and covered with the cable slab. The maximum depth of the trench shall be
600 mm and its width shall be 380 mm. The cable cover shall overlap the high voltage and
any associated pilot cable by at least 40 mm on either side. If one medium voltage and two
high voltage cables are to be laid in the same trench, the two high voltage cables shall be
laid at the bottom of the trench and the medium voltage cable laid midway between them at
a height of 230 mm above them on a level with the cable protective covers. The width of the
trench shall be 530 mm and its overall depth 600 mm.
Page 152 of 282
Laid-In Ducts
When medium and high voltage cables are to be laid in ducts in the same trench, the
arrangement shall be as described below and one of the spare ducts shall be used for the
medium voltage cable.
Depth Width
One Circuit 600 mm 300 mm
One Circuit plus one spare or two Circuits 600 mm 600 mm
Two Circuits plus two spares 760 mm 600 mm
Ducts
Cable ducts shall be non-metallic and comply with IEC 61084:1-2. The size of ducts
required for different type of cables is shown in the following table:
Page 153 of 282
5.6.4.3 Proximity to Water and Petrol Pipes
Cables shall not be laid at a distance of less than 1.0 m from pipes carrying water or
petrol.
(c) Insulation
The insulation shall be of extruded cross-linked polyethylene (XLPE), Dry Gas cured
of nominal insulation thickness of 3.6 mm.
There shall be no joints in any wire of the stranded messenger conductor except
those made in the base rod or wires before final drawing.
Low voltage Aerial Bundled Cables (ABC) shall be polyethylene insulated Aluminium
cables twisted over a central bare Aluminium alloy messenger wire for use on L.T.
overhead lines. The rated voltage of the cables shall be 1000 Volts.
The phase conductors and street lighting conductors where applicable shall be
made of Aluminium and shall be stranded in construction and shall be insulated with
black weather resistant polyethylene suitable for 1000 Volts insulation.
The phase conductors shall be provided with suitable means for quick identification.
The tensile strength of the Aluminium wires used in the conductors shall not be less
than 90 N/sq.mm.
The standard sizes shall include 16 mm2, 25 mm2, 35 mm2, 50 mm2, 70 mm2, 95
mm2 and 120 mm2.
Page 155 of 282
Messenger (Neutral Conductor)
The bare messenger wire shall be made of Aluminium alloy composed of 7 strands
and shall be suitably compacted to have smooth round surface to avoid damage to
the polyethylene insulation of the phase conductors twisted around the messenger.
There shall be no joints in any wire of the stranded messenger conductor except
those made in the base rod of wires before final drawing. The standard sizes shall
include 25 mm2, 35 mm2, 50 mm2 and 70 mm2.
Page 156 of 282
Chapter 6: Distribution Substations
6.1 Civil Works
The Design of the civil works for Distribution Substations shall be as specified in Clause 4.1
of these regulations.
The insulation withstand voltage of high tension cables shall not be less than twice
the nominal voltage rating of the cable as specified in IEC 60502-2.
Page 157 of 282
All Low Voltage cables shall be in compliance with Clauses XXX. The low voltage
cables for 400/230 V level are to consist, according to requirement of single, two and
four-core low voltage power cables.
The standard phase colour shall be Red (L1 or R), Yellow (L2 or Y), Blue (L3 or B)
(RYB), unless otherwise specified in IEC 60173.
The insulation withstand voltage of low tension cables shall not be less than twice
the nominal voltage rating of the cable as specified in IEC 60502-1.
Rear mounted phase bus bar, double door construction, weather proof coating,
rubber seal gasket must have neutral and neutral earth bus bars.
Feeder Pillars shall be installed on a plinth of not less than 600 mm from the ground
furnished with tamper proof lock and appropriate cable clamp.
6.3.3 Metering
Low Voltage Distribution Feeder Pillars shall be metered for the purpose of
measuring the parameters of the distribution network at each substation in
accordance with the Nigerian Metering Code.
The following instruments shall be installed for the measuring of LV feeder pillar
parameters;
a. Ammeter:
At least one ammeter shall be installed on a feeder pillar incomer bus bar.
b. Voltmeter:
Voltmeter shall be installed on a feeder pillar to show line-to-line and line-to-
neutral voltages.
c. Energy Meter:
Energy Meter for low voltage distribution feeder pillar panels shall be installed in
accordance with the requirements of the Nigerian Metering Code.
The nominal operating voltage for pole mounted transformer substation shall lie between
the medium voltage range and low voltage.
Page 159 of 282
Chapter 7: User’s Sites Electrical Installations
This Regulation applies to all user’s sites installations connected to any electrical power
supply under the authority of a license granted under the Act (whether granted before or
after the coming into force of this Regulation), and to all user’s sites irrespective of their
source of supply shall be in the following configurations and voltages:
The indoor installation for any user’s site shall meet the following general criteria:
The Standards set out hereunder are aimed at achieving these criteria and shall require
sound and accurate information of the user’s site. The approving authority shall ensure strict
compliance with the applicable Standards.
7.2.2.1
In the case of TT earthing type (See Figure 7.2.2a), Earthing work Class D of Table 5.3.2b
shall be given to any single-phase low-voltage equipment irrespective of the user’s site.
Page 160 of 282
Figure 7.2.2a: TT System
Table 7.2.2.1
7.2.2.2
The indoor wiring shall contain protective earthing conductors beforehand to ensure the
earthing of electric equipment.
Page 161 of 282
7.2.3.1 Materials and Types of Cables
7.2.3.1.1
All cable conductors for internal wiring other than the outer conductors of earthed concentric
systems shall be of annealed copper, and shall conform to NIS IEC 60228.
7.2.3.1.2
Every non-flexible cable for use as fixed wiring operating at low and medium voltages shall
comply with the relevant NIS and shall be selected from one of the following types:
7.2.3.1.3
Bus bars and bus-bar connections on switchboards shall comply with NIS IEC 60439-2. The
requirement does not apply to a bus-bar trunking system.
7.2.3.1.4
Every conductor for use as an overhead line within a User’s site shall comply with the
relevant NIS and shall be selected from one of the following types:
7.2.3.1.5
The insulation of every flexible cable and flexible cord shall comply with the relevant NIS
and shall be selected from one of the following types:
Page 162 of 282
IEC 60245-1. Such rubber insulated flexible cables and flexible cords, may
incorporate flexible armour of galvanized steel or phosphor bronze, or a screen of
tinned copper-wire braid.
f. Any other flexible cable with insulation complying with applicable IEC standards.
Provided this regulation does not apply to a flexible cord forming part of a portable
appliance or light fitting where the appliance or light fitting as a whole is a special flexible
cable and flexible cord for combined power and telecommunication wiring.
7.2.3.1.6
All cables, including flexible cables and flexible cords, for use at extra-low voltage shall
comply with the applicable NIS.
7.2.3.2.1
The type of insulation and protective covering if any, of every cable for fixed wiring shall be
selected so as to allow compliance with the requirements of this Section as as a precaution
against mechanical damage or damage by heat, fire or explosion, damp and corrosion.
7.2.3.2.2
Cables insulated and/or sheathed with general-purpose PVC shall not be installed in
refrigerated spaces or other situations where the temperature is considered consistently
below 0oC.
7.2.3.2.3
Every flexible cable and flexible cord shall be selected from one of the following types:
Provided that these types shall be used only in dry situations for light fitting or for other
applications where the cord is not subject to abrasion or undue flexing.
7.2.3.2.4
Flexible cables and flexible cords, where they are exposed to risk of mechanical damage,
shall as a minimum be of a type sheathed with rubber or PVC and where necessary shall
also be armoured.
7.2.3.2.5
Flexible cables and flexible cords, which in normal use are exposed, to risk of contact with
water shall be of a type sheathed with rubber or PVC.
7.2.3.2.6
Page 163 of 282
Where flexible cables or flexible cords are exposed to risk of contact with oil or petrol, or
where the cable that will not support combustion is required, cables or cords having a PVC,
HRFR or oil resisting and flame retardant sheath shall be used as appropriate.
7.2.3.4.1
The size of every bare conductor or cable conductor shall be such that its current rating as
stated in Table 15-33 after the application of any factors appropriate to the type of cable, the
conditions of installation, and the class of excess-current protection provided it is not less
than the maximum sustained current which will normally flow through it. This standard does
not apply to certain conductors on switchboards.
TABLE 15
Sing‐circuit current ratings and associate volt drops for single core p.v.c insulated cables
Non‐armoured, with or without sheath
(Copper, conductors)
1.0mm2 to 35 mm2
The rating tabulated applies where cable is provided with coarse excess‐current protection (see item 2 (b) of the preface) for close excess‐current
protection, see rating factor below.
Phase a.c. or d.c Three‐ phase a.c Phase a.c or d.c Three‐phase a.c
Page 164 of 282
mm2 1 A mV A mV A mV A mV
1.0 1/1.13 11 40 9 35 13 40 12 35
1.5 1/1.38 13 27 11 23 27 23
7/0.50 30 26 16 30 15 2.6
2.5 1/1.78
7/0.67 18 16 14 23 16 20 14
16
4 7/0.85 24 10 88 30 10 27 8.8
22
6 7/1.04 31 68 5.9 38 6.8 34 5.9
28
10 7/1.35 42 40 3.5 51 4.0 46 3.5
39
16 7/1.70 56 26 2.2 63 2.6 61 2.2
50
25 7/2.14 73 16 1.4 89 1.6 80 1.4
66
35 7/2.53 90 12 1.0 109 1.2 98 1.0
80
Total volt drop between the consumer’s and any other point in the installation must not exceed 2 .5% of the nominal voltage. The rating in columns 3 and 5 relate to
cables in metal non‐ metallic conduct and trucking. For cables in underground pipes and ducts see item 4 (iv) of the preface the tables.
RATING FACTORS
FOR CLASS OF EXCESS‐CURRENT PROTECTION
1.33 may multiply the rating tabulated where there close excess current protection can be assured
Page 165 of 282
7.2.3.4.2
No cable having a conductor of nominal cross sectional area less than 1.5 mm2 and flexible
cord having a conductor of nominal cross sectional area less than 0.75 mm2 shall be used
in User Site Installations.
7.2.3.4.3
Mains service cable shall be stranded, and have a current carrying capacity of not less than
the maximum demand for the installation. In no case shall the cable be smaller than 6mm2.
7.2.3.5.1
If load assessment is not readily available for a user’s site, it shall be assessed according to
the following user‘s site classifications:
The above stated procedural guidelines for load assessment shall be subject to appropriate
review to capture penetration of future energy efficient lighting system, appliances and
heavy industrial equipment and to the extent permitted by superior judgment of the design
engineer.
7.2.3.5.2
The load assessment of a building area in a user’s site shall be for all the floors as per plan
or as actually constructed, whichever is higher.
7.2.3.5.3
Where electrical energy is used for more than one purpose in a user’s site, the maximum
load demand shall be appropriately computed from the various loads assessed and
applicable diversity factor as decided upon by the design engineer using Table 7.2.3.
TABLE 7.2.3
Allowance for diversity
Estimation of the maximum current, which will normally flow in an installation. For use in
calculating the size of cables and switchgear except for final sub‐circuits.
Purpose of final sub‐circuits fed from Types of installation
the wiring to which diversity applies Individual Block of Hotel, boarding Shops, etc e.g.
domestic residential flats houses, lodging offices and
installation houses, etc business
including premises, other
Individual flats of than
a block Factories
1. Lighting 66% 50% 75% 90%
2. Heating and power appliances 100% fl up to 10 100% fl of the 100% fl of the 100% fl of the
(but see 3‐8 below) amperes largest largest appliance largest appliance
appliance
+50% of any load +50% fl of 2nd +80% fl of 2nd +75% fl of
in excess of 10 largest largest appliance remaining
amperes appliance appliance
appliance +33% fl of 3rd +60% fl of
largest remaining
appliance appliances
+20% of
Page 167 of 282
remaining
appliance
3. Cooking appliances permanently 10 amperes 100% fl of 100% fl of largest 100% fl of largest
connected largest appliance appliance
appliance
30% fl of +50% fl of 2nd +80% fl of 2nd +80% fl of 2nd
connected largest largest appliance largest appliance
cooking appliance
appliances in
excess of 10
amperes
+5 ampere if +33% fl of 3rd +80% fl of 2nd +80% fl of 2nd
socket‐outlet largest largest appliance largest appliance
incorporated in appliance
unit
+25% fl of 4th
largest
appliance
+20% of
remaining
appliances
4. Motors other than Kft motors 100% fl of the 100% fl of the
which are subject to special NO DIVERSITY ALLOWED largest motor largest motor
conditions
+50% fl of 80% fl of 2nd
remaining largest motors
motors
5. Water heaters (instantaneous 100% fl of the largest appliance To be assessed by a competent
type) person
To be assessed by a competent
150% fl of 2nd largest appliance
person
To be assessed by a competent
+25% of remaining appliances
person
6. Water heaters (thermostatically
NO DIVERSITY ALLOWED **
controlled)
7. Socket‐outlets and stationery 100% largest 100% largest 100% largest fuse 100% largest
appliances in accordance with fuse or circuit‐ fuse or circuit‐ or circuit‐breaker fuse or circuit‐
Table breaker rating of breaker rating of rating of breaker rating of
individual circuits individual individual circuits individual circuits
circuits
+40% sum of +40% sum of +50% sum of fuse +40% sum of
fuse or circuit‐ fuse or circuit‐ or circuit‐breaker fuse or circuit‐
breaker rating of breaker rating of rating of other breaker rating of
other circuits other circuits circuits other circuits
8. Socket‐outlet and stationery 100% fl of largest 100% fl of largest 100% fl of largest 100% fl of largest
appliances other than those point point point point
listed above
Page 168 of 282
40% fl of other 40% fl of other 75% fl of points 75% fl of other
points points in main rooms points
(dining room,
etc)
40% fl of
remaining points
*For the purpose of this Table, an instantaneous water‐heater is deemed to be water‐heater of any loading,
which heats water only while the tap, is turned on and therefore uses electricity intermittently.
**It is important to ensure that the distribution boards are of sufficient rating to take the total load connected to
them without the application of any diversity.
7.2.3.5.4
Other special loads of a user site that meet the approval of the supply authority shall be
appropriately assessed in accordance with relevant Standards.
7.2.3.5.5
It shall be the responsibility of the design engineer to provide each user’s site load limiter of
suitable capacity in accordance with the actual assessed maximum demand of users’ sites.
The load limiter shall only be accessible to authorized persons and under no circumstance
shall modifications be made to the approved user’s site installation without prior approval
given by the local electricity distribution company.
7.2.3.5.6
After electrical installation work has been duly certified and approved at the user’s site, any
modification that may involve addition or alteration to the existing installation, beyond
replacement of lamps (preferably by energy efficient lamps), weather sensitive efficient
appliances, fuses, switches and other replaceable component parts of the installations
which in no way increase the installation capacity, shall not be carried out in the user’s site
unless:
7.2.3.6 Specification for Earth Continuity Conductors and Allowable Voltage Drop
7.2.3.6.1
Every conductor used as earth continuity conductors shall have cross-sectional area of not
less than the cross-sectional area of the largest live conductor but in any case not less than
1.5mm2.
7.2.3.6.2
Cables connected in parallel shall be of the same type, size and length, to ensure proper
division of the current.
Page 169 of 282
7.2.3.6.3
The size of every conductor approved for indoor wiring shall be such that the drop in voltage
from the consumer’s terminals to any point in the installation does not exceed 2.5 % of the
rated nominal voltage when the conductors are carrying the full load current, but
disregarding starting conditions of appliances driven by motors. This requirement shall not
apply to wiring fed from an extra-low voltage secondary of a transformer.
7.2.3.6.4
Where allowance is made for diversity, it may be taken into account in calculating voltage
drop.
7.2.3.6
The earthing-lead shall be stranded copper cable or flat copper, the latter not less than 19
mm by 3 mm. No conductor of a cross-sectional area less than 6mm2 shall be used as an
earthing lead.
7.2.3.7.1
All conductors and cables shall be adequately protected against any risk of mechanical
damage to which they may be exposed in normal conditions of service.
7.2.3.7.2
Where cables pass through holes in metalwork, precautions shall be taken to prevent
abrasion of the cables on any sharp edges.
7.2.3.7.3
Non-sheathed cables shall be protected by enclosure in conduit, duct or trunking.
7.2.3.7.4
Cables shall not be run in a lift (or hoist) shaft unless they form a part of the lift installation.
Cables of lift installations, other than traveling cables, in such a shaft shall be:
a. Armoured;
b. Mineral-insulated, metal-sheathed;
c. Of a type having a HRFR or ORFR (oil-resisting and flame-retardant); or
d. Enclosed in metal conduit, duct or trunking, high impact rigid PVC conduit, or
otherwise effectively protected against mechanical damage.
Page 170 of 282
TABLE 7.2.3.8
Minimum internal radius of bends in cables for fixing wiring.
Insulation Finish Overall diameter Factor to be applied to
overall diameter of cable to
determine minimum internal
radius of bend
Rubber or p.v.c.(circular Non‐armored Not exceeding 10mm 3
copper or circular standard Exceeding 10mm but not
aluminum conductors) exceeding 35mm… 4
Exceeding 25mm………. 6
Armored Any …………………………. 6
p.v.c.(solid aluminum or Armored or non‐armored Any ………………………… 8
shaped copper conductors)
Impregnated paper Lead or corrugated Any …………………………. 12
aluminium sheath with or
without armour
Smooth aluminium sheath Not exceeding 30mm 12
with or without armour Exceeding 30mm but not
50mm………………. 15
Copper or aluminium sheath Exceeding 50mm………. 18
Mineral with or without p.v.c Any …………………………. 6
covering
*The factors are applied to the diameter over the aluminum sheath.
7.2.3.9.1
For non-sheathed cable, installation in conduit without further fixing of the cables, provided
that precautions are taken against undue compression of the installation at the top of any
vertical runs exceeding 5 m in length.
7.2.3.9.2
For non-sheathed cables, installation in trunking without further fixing of the cables,
provided that vertical runs shall not exceed 5m in length without intermediate support.
7.2.3.9.3
For sheathed and/or armoured cables installed in accessible positions shall be supported by
clips at appropriate spacings.
7.2.3.9.4
For cables of any type, resting without fixing in horizontal runs of ducts or trunking,
7.2.3.9.5
Page 171 of 282
For sheathed and/or armoured cables installed in horizontal runs, which are inaccessible
and unlikely, to be disturbed shall rest without fixing on part of a building provided that the
surface is dry and reasonably smooth.
7.2.3.9.6
For sheathed-and-armoured cables in vertical runs, which are inaccessible and unlikely to
be disturbed, shall be supported at the top of the run by a clip and a round support of a
radius not less than the appropriate value stated in Table 7.2.3.8.
7.2.3.9.7
For sheathed cables without armour in vertical runs which are inaccessible and unlikely to
be disturbed, support by the method described in 7.2.3.9.6 above shall apply provided that
the length of run without intermediate support shall not exceed 2m for a lead/sheathed cable
or 5m for a rubber or PVC sheathed cable.
7.2.3.9.8
For rubber or PVC sheathed cables, installation in conduit without further fixing of the cables
shall apply provided that any vertical run shall be in conduit of suitable size and shall not
exceed 5m in length.
7.2.3.9.9
For rubber or PVC sheathed cables installed as surface wiring, clips shall be spaced at
intervals not exceeding 200 mm.
7.2.3.9.10
Support by a catenary wire incorporated in the cable during manufacture shall be sufficient
provided that the spacings between supports shall not exceed those stated by the
manufacturer.
7.2.3.9.11
For flexible cords used as pendants, attachment to a ceiling rose or similar accessory by the
cord-grip or other method of strain relief provided in the accessory shall apply.
7.2.3.9.12
For cables of the types described in standard 7.2.3.7.4 (a) and (c) support by clips at
spacing shall not exceed 1m.
7.2.3.11.1
If it is necessary to install cables in a situation where flammable and/or explosive dust,
flammable volatile liquid or vapour or gas is likely to be present, or where explosive
Page 172 of 282
materials are handled or stored, one or more of the following types of wiring systems shall
be used:
Provided that this type of cable shall not be directly buried in the ground, which may be
contaminated by flammable volatile liquid.
This standard does not apply to cables of intrinsically - safe circuits; nor does it apply to
adequately ventilated battery rooms or garages.
7.2.3.11.2
Where cables, conduits, ducts or trunking pass through floors, walls, partitions or ceilings,
the surrounding hole shall be made good with cement or similar fire-resisting material to the
full thickness of the floor, wall and space through which fire or smoke might spread shall not
be left around the cable, conduit, duct or trunking. In addition, where cables, conduits or
conductors are installed in channels, ducts, trunking, or shafts which pass through floors,
walls, partitions or ceilings, suitable internal fire-resisting barriers shall be provided to
prevent the spread of fire.
7.2.3.12.1
Every cable shall be installed where it will not be exposed to rain, dripping water,
condensed water, accumulations of water or oil, or corrosive substances or shall be of a
type designed to withstand such conditions.
7.2.3.12.2
In damp situations and wherever they are exposed to the weather, all metal sheaths and
armour of cables, metal conduit, duct, or trunking, and clips and their fixings, shall be of
corrosion-resisting material or finish and shall not be placed in contact with other metals
with which they are likely to set up electrolytic action; conduit, if of steel shall be galvanized
heavy-gauge.
7.2.3.12.3
Armoured PVC insulated cables and mineral-insulated metal-sheathed cables installed in
damp situations or in concrete ducts or wherever exposed to the weather or other risk of
corrosion, shall be of a type having an overall extruded covering of PVC.
7.2.3.12.4
Aluminum-sheathed cables installed in underground pipes or in concrete ducts shall be
provided with a corrosion-resistant finish.
7.2.3.13.1
Types of circuits described in 7.2.3.13 are divided into categories as follows:
a. Category I circuits: Circuits (other than fire alarm circuits) operating at low voltage
and supplied directly from a mains supply system.
b. Category II circuits: With the exception of fire-alarm circuits, all extra low-voltage
circuits; and telecommunication circuits (e.g. radio, telephone, sound-distribution,
burglar-alarm, CCTV, Cable TV, bell and call circuits), which are not supplied directly
from a mains supply system.
c. Category III circuits: Fire-alarm/smoke detector circuits.
7.2.3.13.2
Cables of Category I circuits shall not be drawn into the same conduit or duct as cables of
Category II circuits, unless the latter cables are insulated in accordance with the
requirements of these standards for the highest voltage present in the Category I circuits.
7.2.3.13.3
Cables of Category I circuits shall not in any circumstance be drawn into the same conduit
or duct as cables of Category III circuits.
7.2.3.13.4
Where a common channel or trunking is used to contain cables of Category I circuits, and
Category II circuits, all cables connected to Category I circuits, shall be effectively
partitioned from the cables of the Category II circuits, or alternatively the latter cables shall
be insulated in accordance with the requirements of these Standards for the highest voltage
present in the Category I circuits.
7.2.3.13.5
Where a common channel or trunking is used to contain cables of Category I and Category
III circuits, the two Categories of circuits shall be separated by continuous partitions of fire-
resisting material; provided that this requirement shall not apply where the Category III
circuits are wired in mineral-insulated metal-sheathed cable.
7.2.3.13.6
In conduit, duct, or trunking systems, where controls or outlets for Category I and Category
II circuits are mounted in or on common boxes, switch-plates or blocks, the cables and
connections and the two Categories of circuits shall be partitioned by means of rigid fixed
screens or barriers.
7.2.3.13.7
At any common outlets in a trunking system for Category I and Category III circuits, the two
categories of circuits shall be separated by continuous partitions of fire resisting material.
Page 174 of 282
7.2.3.13.8
Where cores of Category I and Category II circuits are contained in a common multi-core
cable, flexible cable or flexible cord, the cores of the Category II circuits shall be insulated
individually or collectively as a group, in accordance with the requirements of these
Standards, for the highest voltage present in the Category I circuits, or alternatively shall be
separated from the cores of the Category I circuits by an earthed metal braid of equivalent
current-carrying capacity to that of the cores of the Category I circuits.
7.2.3.13.9
Where terminations of the two categories of circuits are mounted in or on common boxes,
switch-plates or blocks, they shall be partitioned in accordance with Clause 7.2.3.13.8 or
alternatively be mounted on separated and distinct terminal blocks adequately marked to
indicate their functions.
7.2.3.13.10
Cores of Category I and Category III circuits shall not in any circumstances be contained in
a common multi-core cable, flexible cable or cord.
7.2.3.13.11
Metal sheaths and armour of all cables operating at low voltage, and metal conduits, ducts
and trunking and bare earth-continuity conductors associated with such cables; which might
otherwise come into fortuitous contact with other fixed metalwork shall be either effectively
segregated therefrom, or effectively bonded thereto so as to prevent appreciable voltage
differences at such possible points of contact.
7.2.3.13.12
Current carrying conductors/cables shall not be installed in the same conduit or trunking as
pipes or tubes of non-electrical services e.g. air, gas, oil or water.
7.2.3.14.1
The identification of conductors for non-flexible cables shall be as follows:
a. For rubber and PVC insulated cables, the use of core colours in accordance
with the requirements of Table 5A of the Schedule 1(Table 7.2.3.14-A) or the
application at termination of sleeves or discs of the appropriate colours
prescribed in the table.
b. For armoured PVC insulated cables as an alternative to the method
described in item (a) above, the use of numbered cores, provided that the
numbers 1, 2 and 3 shall signify live conductors, the number 0 the neutral
conductor, and the number 4 the fifth (special-purpose) core, if any.
c. For paper-insulated cables, the use of numbered cores, provided that the
numbers 1, 2 and 3 shall signify live conductors, the number 0 the neutral
conductor, and the number 4 the fifth (special-purpose) core, if any.
Page 175 of 282
d. For mineral-insulated cables, the application at terminations of sleeves or
discs of the appropriate colours prescribed in Table 5A Schedule 1 (Table
7.2.3.14-A).
7.2.3.14.2
Bare conductors shall be made identifiable where necessary by the application of sleeves
or discs of the appropriate colours prescribed in Table 5A Schedule 1 or by painting with
those colours.
7.2.3.14.3
Any scheme of colouring used in a consumer’s installation to identify switchboard bus bars
or poles shall comply with the requirements of Table 7.2.3.14-A so far as these are
applicable.
7.2.3.14.4
The cores of every flexible cable including a flexible cord, shall be coloured throughout in
accordance with the requirements of Table 7.2.3.14-A
7.2.3.14.5
The colour combination, green and yellow is reserved exclusively for identification of
earthing conductors and shall not be used for any other purpose. This provision does not
apply to PVC installed parallel-twin non-sheathed flexible cords.
7.2.3.14.6
Flexible cables or flexible cords having the following core colours shall not be used; green
alone; yellow alone; or any bi-colour other than the colour combination green-and-yellow
mentioned in Clause 7.2.3.14.4.
Table 7.2.3.14-A
Colour Identification of cores of non-flexible cables and bare conductors for fixed wiring
Page 176 of 282
Negative of d.c 2-wire circuit Black
TABLE 7.2.3.14.1-B
Colour identification of cores of flexible cables and flexible cords
7.2.3.15 Terminations
7.2.3.15.1
All terminations of cable conductors and bare conductors shall be mechanically sound and
electrically continuous.
7.2.3.15.2
Every connection at a cable termination shall be made by means of a terminal, soldering
socket, or compression-type socket; shall securely contain and anchor all the wires of the
conductor, and shall not impose any appreciable mechanical strain on the terminal or
socket.
7.2.3.15.3
An aluminum conductor shall not be placed in contact with a terminal of brass or other metal
having a high copper content, unless the terminal is suitably plated or other suitable
precautions are taken to prevent corrosion.
7.2.3.15.4
At every cable termination, the insulation shall be removed no further than is necessary for
compliance with Clause7.2.3.15.2.
Page 177 of 282
7.2.3.15.5
At every cable termination, any braid, tape, sheath, or armour over the insulation shall be
cut back from the end of the insulation, as may be necessary to prevent undue leakage from
live parts of the braid, tape, sheath, or armour. This provision does not apply to mineral-
insulated cables.
7.2.3.15.6
In any situation, the exposed conductor and insulation of cables insulated with impregnated
paper shall be protected from ingress of moisture by being suitably sealed.
7.2.3.15.7
The ends of mineral-insulated metal-sheathed cables shall be protected from moisture by
being suitably sealed and the insulation shall be thoroughly dry before the sealing material
is applied. Such sealing material, and any material used to insulate the conductors where
they emerge from the insulation, shall have adequate insulating and moisture proofing
properties, and shall retain these properties through the range of temperatures to which the
cable shall be subjected.
7.2.3.15.8
Soldering fluxes, which remain acidic or corrosive at the completion of the soldering
operation, shall not be used.
7.2.3.15.9
Where a non-metallic outlet box of thermoplastic material (e.g. PVC) is used for the
suspension of, or is in contact with, a light fitting, care shall be taken to ensure that the
temperature of the box does not exceed 60oC. The mass suspended from the box shall not
exceed 3 kg.
7.2.3.15.10
The termination of cables in a situation where flammable and/or explosive dust, flammable
volatile liquid vapour or gas is likely to be present, or where explosive materials are handled
or stored, shall be avoided wherever possible. Otherwise, terminations shall be enclosed in
a flameproof fitting or alternatively, where methods are employed for avoiding the explosion
hazard other than by the use of flameproof equipment the terminations shall be enclosed in
a box suitable for such use.
7.2.3.15.11
Cable glands shall securely retain the outer sheath or armour of the cables without damage
to these, and where necessary shall incorporate adequate means of maintaining earth
continuity between the sheath or armour and the threaded fixing component of the gland.
7.2.3.16.1
Where joints in cable conductors and bare conductors are necessary they shall be
mechanically sound and electrically continuous. Joints in non-flexible cables shall be
Page 178 of 282
accessible for inspection provided that this requirement shall not apply to joints in cables
buried underground, or joints buried or enclosed in non-combustible building material so
that no danger can arise. Joints in non-flexible cables shall be made by either soldering,
brazing, welding, or mechanical clamps, or be of the compression type; provided that
mechanical clamps shall not be used for, inaccessible joints buried or enclosed in the
building structure. All mechanical clamps and compression-type sockets shall securely
retain all the wires of the conductors.
7.2.3.16.2
Every joint in a cable shall be provided with insulation not less effective than that of the
cable cores and shall be protected against moisture and against mechanical damage.
Soldering fluxes which remain acidic or corrosive at completion of soldering operation shall
not be used.
7.2.3.16.3
For joints in paper-insulated metal-sheathed cables, a wiped metal sleeve or joints box,
filled with insulating compound, shall be provided.
7.2.3.17.1
All metal sheaths and cable armouring and associated accessories shall be earthed in
accordance with these Standards.
Where non-metal joints boxes are used with metal-sheath and, or armoured cables, the
continuity shall be maintained by a metal bonding strip or similar means having a resistance
not higher than that of an equivalent length of metal cable sheath or, (for armoured non-
metal sheathed cables), the armour of the largest cable entering the box.
7.2.3.19.1
The conduits for each User’s site shall be completely erected before any cable is drawn in.
This requirement does not apply to prefabricated flexible conduit systems which are not
wired in-situ.
7.2.3.19.2
Conduits shall be securely fixed, and where they are liable to mechanical damage they shall
be adequately protected.
7.2.3.19.3
Inspection type conduit fittings such as inspection boxes, draw boxes, bends, elbows, and
toes, shall be so installed that they can remain accessible for such purposes as the
withdrawal of existing cables or the installing of additional cables.
Page 179 of 282
7.2.3.19.4
The number of single core rubber insulated, braided and compounded cable, of PVC
insulated non-sheathed cables run in one conduit shall be such as to permit of easy
drawing in. The number of cables drawn in shall not be greater than the appropriate number
given in Table 6 (Table 7.2.3.20-A) or Table 7 (Table 7.2.3.20-B) of schedule I as
applicable.
7.2.3.19.5
For types of cables having large overall diameters than those shown in the table,
appropriate reduction shall be made in the number of cables drawn in.
7.2.3.19.6
For groups of cables other than those provided in Table 6 (Table 7.2.3.20-A) and 7 (Table
7.2.3.20-B), the number and sizes of the cables installed shall be such that a space factor of
40% is not exceeded.
7.2.3.19.7
The numbers stated in the tables; and the space factor of 40% relate to conduit runs
incorporating not more than two 90o bends or radius not less than that specified for normal
bends or for runs having more bends than this or having opposing adjacent bends for runs
containing additional sets or other restrictions, appropriate reduction shall be made in the
number of cables installed.
Maximum capabilities of steel conduits, for the simultaneous drawing in of single core p.v.c
cables or rubber cables
Number Nominal
Nominal and overall
1/4
Conductor diameter of 16mm or 5/8 in 20 mm or ¾ in 25 mm or 1 in 32 mm or 1 in
2
Size mm wire Diameter
2
No/mm mm
1 2 3 4 5 6 7 8 9 10 11
Metric
Light
Page 180 of 282
1.0 1/1.13 2.9 8 7 13 12 22 19 38 35
4 7/0.85 4.3 3 3 6 5 10 9 17 16
6 7/1.04 4.9 3 2 5 4 7 7 13 12
10 7/1.35 6.2 - - 3 2 4 4 8 7
16 7/1.70 7.1 - - 2 - 3 3 6 5
25 7/1.24 9.0 - - - - 2 2 4 4
35 19/1.53 10.1 - - - - - - 3 2
50 19/1.78 12.0 - - - - - - 2 2
Rubber
cables
1.0 3.4 6 5 10 8 16 14 28 25
1/1.13
1.5 3.6 5 4 9 8 14 13 27 23
1/1.38
2.5 4.0 4 3 7 6 11 10 20 18
1/1.78
4 5.2 2 2 4 3 7 6 12 11
7/0.85
6 6.0 2 - 3 2 5 4 9 8
7/1.04
10 7.3 - - 2 - 3 3 6 5
7/1.35
16 8.4 - - - - 2 2 4 4
7/1.70
25 10.1 - - - - - - 3 2
7/2.14
35 11.7 - - - - - - 2 2
19/1.53
0
Note; The maximum numbers of cables in the table related to conduit ruins incorporating not more than two 90 bends or
the equivalent. Where runs include additional bends, sets or other restrictions, the numbers must be appropriately
reduced. This applies particularly where solid conductor cables are to be drawn
Page 181 of 282
TABLE 7 (Table 7.2.3.20-B) Capacities of PVC conduits
Maximum Capacities of steel conduits for the simultaneous drawing in of single core p.v.c cables or
rubber cables.
1 2 3 4 5 6 7
4 7/0.85 4.3 3 5 9 15
6 7/1.04* 4.9 2 4 7 12
10 7/1.35 6.2 - 2 4 7
16 7/1.70 7.1 - 2 3 5
25 7/1.24 9.0 - - 2 3
35 19/1.53 10.1 - - 2 3
50 19/1.78 12.0 - - - 2
Rubber cables
Page 182 of 282
4 7/0.85 5.2 2 4 6 10
6 7/1.04 6.0 - 3 4 8
10 7/1.35 7.3 - 2 3 5
16 7/1.70 8.4 - - 2 4
25 7/2.14 10.1 - - - 2
35 19/1.53 11.7 - - - 2
NOTE: The maximum number of cables in the table relate to conduit runs incorporating not more than two 90o bends
equivalent. Where runs include additional bends, sets or other restrictions, the number must be appropriately reduced.
This applies particularly where solid conductor cables are to be drawn.
7.2.3.19.8
The use of solid (non-inspection) conduit, elbows or tees shall be restricted to:
i. Locations at the ends of conduits immediately behind a light fitting outlet box or
accessory of the inspection type; or
ii. One solid elbow located at a position not more than 500mm from a readily
accessible outlet point provided that all other bends in the conduit run are not
more than the equivalent of one right angle.
7.2.3.19.9
Ends of lengths of conduits shall be so reamed and where they terminate at boxes, trunking
and accessories not fitted with spout entries, shall be so bushed, as to obviate abrasion of
cables.
7.2.3.19.10
Substantial boxes of ample capacity shall be provided at every junction involving a cable
connection in a conduit system. Where non-metallic conduits are used, and where metal
conduits are terminated, boxes may be of non-absorbent, non-flammable material other
than metal. All unused conduit entries shall be blanked off, and all removable covers firmly
secured to provide complete enclosure.
7.2.3.19.11
Conduit systems not intended to be gas-tight shall be self-ventilating, and drainage outlets
shall be provided at any points in the installation where condensed moisture might
otherwise collect.
7.2.3.20.1
Metal conduits and fittings for use in wiring systems shall comply with NIS Specifications for
rigid steel conduits and fittings; for flexible steel conduits and adaptors and for aluminum or
Page 183 of 282
zinc-base-alloy conduits and fittings as appropriate. Where steel pipes are used as
conduits, they shall comply with appropriate NIS specifications and shall have a corrosion-
resistant finish inside and outside.
7.2.3.20.2
Metal conduits systems shall be earthed. All joints shall be made mechanically and
electrically continuous by screwing or by substantial mechanical clamps, or by inserts but
plain slip or pin-grip sockets shall not be used.
7.2.3.20.3
For the purposes of these Standards, flexible steel conduits having an outer sheath of
insulation material (e.g. PVC) shall be deemed to be metal conduits.
7.2.3.20.4
Cables of a. c. circuit installed in steel conduit shall always be so bunched that the cable of
all phases and the neutral conductor (if any) are contained in the same conduit.
7.2.3.21.1
Rigid non-metallic conductors and fittings for use there-with shall comply with relevant NIS
specifications as appropriate.
7.2.3.21.2
Non-metallic systems shall be used only where it is ensured that they are suitable for the
extremes of ambient temperatures to which they are likely to be subjected to in service, and
where used, earth continuity conductor shall be installed throughout the system.
7.2.3.21.3
The method of support for rigid PVC conduit shall allow for the longitudinal expansion and
contraction of the conduits that may occur with variation of temperature under normal
operating conditions.
7.2.3.21.4
For the purposes of these Standards, conduits comprising metal parts having an inner and
outer covering of insulating materials are deemed to be non-metallic conduits, provided that
effective precautions are taken to prevent the metal parts of the conduits at their ends from
coming into contact with any other metal parts.
7.2.3.21.5
Flexible metal conduit and fittings shall comply in all respects with NIS IEC 61386-1.
Flexible non-metallic conduit shall comply with NIS IEC 61386-1 and fittings for use
therewith shall also comply with the NIS IEC 61386-25.
7.2.3.21.6
i. Flexible metal conduit shall not be used as the sole means of providing earth-
continuity, and earth-continuity conductor complying with the requirements of NIS
specifications shall be provided for every part of a system formed by such conduit.
Page 184 of 282
ii. Where necessary, flexible conduit shall be adequately supported.
7.2.3.22.1
In the prefabrication of conduit systems that are not to be wired in-situ, adequate allowance
shall be made for variations in building dimensions so that the conduits or cables are not
subjected to tension or other strain during installation. Adequate precautions shall also be
taken against damage to such systems during installation and any subsequent building
operations, especially against deformation of the conduits and damage to any exposed
cable ends.
7.2.3.22.2
Ducts of metal or insulating material, and trunking, shall be securely fixed, and where they
are liable to mechanical damage they shall be adequately protected.
7.2.3.22.3
Trunking shall be constructed of metal or non-combustible insulating material.
7.2.3.22.4
Cables of a.c. circuits installed in steel ducts or trunking shall always be so bunched that the
cables of all phases and the neutral conductor (if any) are contained in the same duct or
trunking.
7.2.3.22.5
Every entry to finished ducts or trunking shall be so placed as to prevent the ingress of
water, or be protected against such ingress. All removable covers shall be securely fixed
after wiring is completed.
7.2.3.22.6
Every outlet for cables from a duct system, every joint in such a system, and every joint
between such a system and another type of duct or conduit, shall be so formed that the
joints are mechanically sound and that the cables drawn in are not likely to suffer abrasion.
7.2.3.22.7
Every bend formed in a concrete duct (whether or not formed by channels or formers
retained in position after the concrete has set) shall be of an inner radius not less than four
times the diameter of the completed duct.
7.2.3.22.8
Ducts cast in-situ in concrete, by means of a suitable formwork laid before the concrete is
poured, into which cables are to be drawn (whether or not the former is retained in position
after the concrete has set) shall be so formed that the radial thickness of concrete or screed
surrounding the cross-section of the completed duct is not less than 15mm at every point.
Where all or any part of the completed duct is formed by the concrete or the screed rubber-
insulated, braided and compound cables, non-sheathed PVC-insulated cables are installed
in this type of duct and there is a risk that the duct may become damp, the cable shall be of
a type having overall extruded covering of PVC.
Page 185 of 282
7.2.3.22.9
The number of cables to be installed in ducts shall as will permit easy drawing-in without
damage to the cables and shall be such that a space factor of 35% is not exceeded. This
space factor relates to runs of ducts incorporating not more than two 900 bends or the
equivalent; for runs having more bends than this, appropriate reduction shall be made in the
number of cables installed.
7.2.3.22.10
The number of cables to be installed in trunking or channels shall be such that a space
factor of 45% is not exceeded.
7.2.3.23.1
Flexible cables or flexible cords shall be used for all connections to movable apparatus. For
the purposes of this provision, an electric cooker of rated input exceeding 3kW is deemed
not to be movable.
7.2.3.23.2
Where armoured flexible cables and flexible cords are used, the armouring shall not be
used as the sole means of providing earth continuity conductor, an additional earth
continuity conductor shall be provided.
7.2.3.23.3
Flexible cables and flexible cords shall not be used as fixed wiring unless contained in
earthed metal or other non-combustible and mechanically strong enclosure; provided that
this requirement shall not apply to short lengths of sheathed flexible cable or flexible cord
used for final connections to fixed apparatus or connection of control gear of fluorescent
lamps or discharge lamps. Non-sheathed flexible cables and flexible cords shall not be
drawn into conduits or ducts.
7.2.3.23.4
Exposed lengths of flexible cables or flexible cord used for final connections to fixed
apparatus shall be as short as possible and connected to the fixed wiring by one of the
following means:
b. a fused spur-box having suitable provision for the entry of the flexible cable or
flexible cord;
7.2.3.23.5
Where a twin flexible cord supports, or partly supports, a light fitting, the maximum mass
supported by the cord shall not exceed the appropriate value indicated below:
Page 186 of 282
Nominal cross-sectional area of
2 Maximum mass (kg)
conductor mm
0.75 3
1.0 5
7.2.3.23.6
No flexible extension shall be taken more than 2m across a ceiling to a droplight. An
insulated hook fixed to the ceiling shall support such flexible extensions.
7.2.3.24.1
Consumer’s wiring intended for operation at low voltage and installed underground for
distribution between a building and point of utilization not attached thereto (e.g. another
building), shall be in the form of one or more of the following systems, using the types of
cable indicated in Clauses 7.2.3.25.1.1 to 7.2.3.25.1.3.
7.2.3.24.1.1
In ducts:
7.2.3.24.1.2
In conduits or pipes:
7.2.3.24.1.3
Laid Direct in the Ground
Page 187 of 282
7.2.3.24.2
Consumer’s wiring intended for operation at low voltage and installed on exterior surface
walls, boundary walls and the like for distribution between a building and a point of
utilization not attached thereto (e.g. another building), shall be in the form of one or more of
the following systems:
7.2.3.24.3
Consumer’s overhead wiring intended for operation at low voltage and for distribution
between a building and a point of utilization not attached thereto (e.g. another building),
shall be in the form of one or more of the following systems using the types of cable or
conductor indicated. Lengths of span shall not exceed, and heights above ground shall not
be less than, the appropriate values indicated in Table 8 Schedule 1– Table 7.2.3.25
TABLE 7.2.3.24
Maximum lengths of span and minimum heights above ground for consumers’ overhead
wiring between buildings etc
m m m m
Page 188 of 282
Cables sheathed with PVC
or having an ORFR 3 3
or HRFR sheath, in
heavy-gauge steel
conducts (item (ii))
PVC covered overhead line
conductors 30 5.8 (for all 5.2 (for all 3.5
insulators without types) types)
intermediate
support (item (iii))
Cables sheathed with or
having an ORFR No limit 3.5
and HRFR sheath
supported by a
centenary wire
(item (iv))
Aerial cable incorporating No limit subject
A catenary wire (item (v)) to regulation 7.3 3.5
(x)
Page 189 of 282
7.2.3.25 Electric Bells, Telephone and Signaling Devices
7.2.3.25.1
Cables which are used in connection with the electric bells, telephone and signaling
devices, and other similar devices, in a building shall be kept away from or not be installed
in the same casing or conduit as the cables used for distribution of the electrical supply
throughout the building.
7.2.3.25.2
Bell and signaling circuits (except telephone circuits,) may be operated from the electric
lighting, heating, or power supply mains, provided that they are connected to the secondary
side of double-wound transformers, having a secondary voltage of twelve volts, and further
provided that:
7.2.3.25.3
The control-circuit wiring and accessories in wiring systems having extra-low voltage
control shall comply with the following requirements:
a. Remote controlled switches shall have their live parts enclosed in non-
combustible and non-absorbent cases. They shall be fixed in full view in readily
accessible positions. The insulation resistance between the supply terminals and
the control terminals of the switch shall not be less than 100 Mega ohms;
b. All control wiring shall be run entirely separate from the supply wiring;
c. The voltage of the control circuit shall not exceed twenty-four (24) volts.
Transformers shall be double-wound with one side of the secondary earthed and
shall be securely mounted and accessible and be controlled by a switch and fuse
on the primary side;
d. Where subject to mechanical injury conductors shall be protected. When un-
enclosed they shall be secured with clips having rounded edges or insulated
staples. But two or more conductors shall not be secured under the same staple;
e. Between roof and ceiling, conductors may be fastened to the sides of joists or
battens-without further protection. Where buried in plaster or concrete they shall
be enclosed in an approved metallic sheathing. All joints shall be accessible, and
be efficiently soldered and insulated;
f. Push Buttons shall be of substantial mechanical strength. The conductors shall
terminate in suitable terminals and be secured by a metal thread screw. Heating/
Page 190 of 282
air-conditioning circuits shall not be controlled by this system unless fitted with an
indicating/temperature-sensing device.
7.2.3.26.1
Electric wires, fittings, consuming devices, electrical storage batteries, and associated
equipment installed in hazardous locations in which explosive or highly inflammable
substances are produced, manufactured, refined, stored or packed shall be installed and
maintained to comply with the following additional requirements:
7.2.3.26.2
In this standard “certified as flame-proof” means to comply with the IEC 60079-0. The
Commissioner, ESS shall be notified in writing in any particular case to approve an
alternative certification as being an adequate substitute for the requirements of this
provision.
7.2.3.26.3
In rooms containing stationary electric storage batteries of the lead-acid or alkaline types, or
where corrosive gases or liquids which are not explosive or highly inflammable are present:
a. The system of wiring employed shall be such that all electrical conductors
including earthing connections are enveloped in a corrosion-proof non-metallic
sheath;
Page 191 of 282
b. Where metallic enclosures are necessary used for motors, switch-gear or other
accessories, including conductors which are liable to mechanical damage, all
exposed metallic surfaces shall be effectively painted or otherwise coated to
resist corrosion;
c. All cable entries and accessories shall be such that the non-corrosion sheath of
conductors enters the terminal chamber of the equipment accessory and the
entry hole or holes are fitted with an accessory to exclude the corrosive liquid or
gas present; and
d. All unused entry holes shall be effectively sealed.
7.2.3.26.4
In freezing or cooling environments, the following shall be adhered to:
7.2.3.26.5
In hot environment, the following shall be adhered to:
a. Cable insulated with rubber shall not be used in situations where the temperature
of the conductor would exceed 60oC for short periods, or 50oC for long periods;
b. Cable insulated with paper or fibre shall not be used in situations where the
temperature of the conductor would exceed 80oC;
c. Cables used shall comply with the appropriate temperature class as specified by
the manufacturer for the environment in which they are to be installed;
d. Where higher temperatures are likely to be experienced, the wiring shall be in
accordance with the requirements of the NIS IEC 60079.
7.2.3.26.6
All cables shall be installed in such a manner as will not damage or weaken the building
unnecessarily and with the least possible cutting-away of any structural work.
7.2.4.1.1
Bare or lightly insulated conductors may be installed in building for the following purposes
only:
7.2.4.1.2
Bare or lightly insulated conductors of extra-low voltage systems shall have adequate
insulators, and further protection where necessary, to ensure that they do not cause risk of
fire.
7.2.4.1.3
Where bare conductors are used for rising-main and bus-bar systems operating at low
voltage, they shall
7.2.4.1.4
Bare conductor wires of the type described in Clause 7.2.4.1.1(e) that are necessarily
exposed in normal service shall be efficiently protected against accidental contact by
screens or barriers or by adequate clearance. At each strain position for such wires, suitable
straining gear fitted with double insulators shall be provided.
7.2.4.2.1
Bare conductors may be used as collector or trolley wires for travelling cranes and similar
appliances and for battery connections. The conductors shall be supported upon insulators,
and so spaced that risk of accidental contact between the conductors themselves or
between conductors and walls or any other conducting structure is reduced to a minimum.
7.2.4.2.2
The circuit supplying current to such bare conductors shall, except in the case of the
regulating cells of batteries, be protected either by a suitable circuit breaker or by a suitable
switch and fuse.
7.2.4.2.3
Bare conductors extended to positions liable to lightning-discharge shall be fitted with
lightning-arrestors on each pole or phase.
Page 193 of 282
7.2.4.2 4
Wall rosettes or brackets used as supports for span-wires shall not be fixed within 300mm
of any gas-pipe.
7.2.5.1.1
Factors to be considered in sizing of cables shall be:
a. Conductor material;
b. Insulating material;
c. Ambient temperature;
d. Method of installation;
e. Effect of thermal insulating material;
f. Allowable maximum voltage drop from the origin of the circuit to the load.
7.2.5.1.2
The low-voltage indoor wiring shall be annealed copper wire of cross sectional area not less
than 1.5 mm2 or other equally sized wire which may be of superior quality.
7.2.5.1.3
For Category I circuits as provided in Clause 7.2.3.13, live conductors shall have a cross-
sectional area of:
a. Not less than 1.5 mm2 for surface wiring using PVC insulated PVC sheath
copper cables;
b. Not less than 1.5 mm2 for single core PVC insulated copper cables installed in
conduit, duct, or trunking;
c. Not less than 16 mm2 for aluminium conductors;
d. Not less than 0.75 mm2 for flexible cables and flexible cords.
7.2.5.2.1
Page 194 of 282
Live conductors shall be completely covered with insulation which:
a. Can withstand the mechanical, electrical, thermal and chemical stresses to which
it may be subjected in service; and
b. Can only be removed by destruction.
7.2.5.2.2
Where insulation is applied during the erection of the installation, the quality of the insulation
shall be verified by tests equivalent to those specified in the applicable NIS 358 for similar
type-tested equipment.
7.2.5.2.3
Non-impregnated paper, asbestos, fabric, wood or pressed hemp shall not be used for
insulating purposes.
7.2.5.2.4
Where insulating tapes are permitted to be used in low voltage installations, they shall have
a minimum thickness of 0.21 mm.
7.2.5.3 Voltage Grading of Cables for Low Voltage Applications
Page 195 of 282
2
(nominal sectional area, mm ) (diameter, mm) hard-drawn aluminum alloy wire
copper wire wire
1.0 or more and less than 1.2 16 12 12
1.2 or more and less than 1.6 19 15 14
1.6 or more and less than 2.0 27 21 19
2.0 or more and less than 2.6 35 27 25
2.6 or more and less than 3.2 48 37 35
3.2 or more and less than 4.0 62 48 45
4.0 or more and less than 5.0 81 63 58
5.0 107 83 77
0.9 or more and less than 1.25 17 13 12
1.25 or more and less than 2 19 15 14
2 or more and less than 3.5 27 21 19
3.5 or more and less than 5.5 37 29 27
5.5 or more and less than 8 49 38 35
8 or more and less than 14 61 48 44
14 or more and less than 22 88 69 63
22 or more and less than 30 115 90 83
33 or more and less than 38 139 108 100
38 or more and less than 50 162 126 117
50 or more and less than 60 190 148 137
60 or more and less than 80 217 169 156
80 or more and less than 100 257 200 185
100 or more and less than 125 298 232 215
125 or more and less than 150 344 268 248
150 or more and less than 200 395 308 284
200 or more and less than 250 469 366 338
250 or more and less than 325 556 434 400
325 or more and less than 400 650 507 468
400 or more and less than 500 745 581 536
500 or more and less than 600 842 657 606
600 or more and less than 800 930 745 690
800 or more and less than 1,080 875 820
1000
1000 1,260 1,040 980
Page 196 of 282
Table 176-2 Current reduction factor
Allowable current Formula (b) of current
Insulator material
correction factor (a) reduction factor
60
PVC (excluding heat-resistant polymers) 1.00
30
90
XLPE (limited to cross-linked polymers) 1.41
30
Page 197 of 282
tion Other Other
Dry Other Dry Other Dry Dry Other Dry Other Dry
Kind of work place place
place places place places place place places place places place
s s
Synthetic resin tube
○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○
work
Metallic tube work ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○
Flexible conduit ○
work ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○
Cable work ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○
Insulator work ○ ○ ○ ○ ○ ○ ○ ○
Synthetic resin
○ ○
raceway work
Metallic raceway
○ ○
work
Metallic duct work ○ ○ ○ ○
Bus duct work ○ ○ ○ ○ ○
Floor duct work ○
Cellular duct work ○
Lighting duct work ○ ○
Flat protective layer
○
work
The mark ○ indicates a place where the work concerned can be executed.
Page 199 of 282
case of 3.2 mm or
less)
Lighting Lighting duct Earthing work Class D Duct supporting clearance shall be 2 m or less
duct work shall be applied to the Do not install a duct through a building part.
duct (excluding ducts 4 m
or less in length).
Flat Flat conductor- Earthing work Class D Used on a branch circuit protected by an
protective synthetic resin shall be applied to the overcurrent circuit breaker of 30 A or less
layer work insulated upper protective layer, Line-to-earth voltage of the circuit shall be 300 V
conductor upper installed protective or less
layer, joint box, and Install a leakage circuit breaker on the power
metallic case of an supply circuit.
insertion connector.
(*1) Use bare conductor if Article 167-1-(1), (2) or (3) is complied with.
(*2) Apply earthing work Class D of Article 57-2 if 300 V is exceeded and there is no danger of a person’s
touching the duct.
7.2.8.1
In installing the low-voltage indoor mains from the service entrance switch or the
switchboard in the receiving room to the branching point of a branch circuit, the following
conditions shall be complied with:
a. If motors and the like are not connected to the overcurrent circuit breakers:
An overcurrent circuit breaker having a rated current equal to or less than the
allowable current of the mains shall be installed.
b. If motors and similar household appliances that require a large starting current the
like are connected to the overcurrent circuit breakers:
An overcurrent circuit breaker having a rated current equal to or less than the value
3 times the total of rated current of the motors similar household appliances that
require a large starting current and the like to which the total of rated current of other
household appliances is added shall be installed.
However, it shall not exceed 2.5 times the allowable current of the mains.
Page 200 of 282
Installation of an overcurrent circuit breaker may be omitted in the following cases:
i. The case where the allowable current of the mains is 55% or more (*2) of the
rated current of an overcurrent circuit breaker that protects other mains
connected to the power supply side of the mains concerned
(*2) If the length of such mains is 8 m or less, the rated current shall be
35% or more.
ii. The case of which length of mains is 3 m or less and to which no other mains
are connected on the load side
If the allowable current of the electrical conductor from the branching point to the switching
device and overcurrent circuit breaker is 55% or more (*2) of the rated current of the
overcurrent circuit breaker that protects the mains connecting to that electrical conductor,
the switching device and overcurrent circuit breaker may be installed at a place beyond 3 m
from the branching point.
(*1) For the overcurrent circuit breaker, the neutral pole is to be excluded.
(*2) If the length of electrical conductor from the branching point to the switching device
and overcurrent circuit breaker is 8 m or less, it shall be 35% or more.
7.2.9.2.1
Branch circuit supplying electricity to lamp load equipment with a rated current exceeding 50
A
A branch circuit supplying electricity to one household electric appliance, other than a
motor, with a rated current exceeding 50 A shall be installed as follows:
a. No other load than this household electric appliance shall be connected to this
branch circuit.
b. The rated current of the overcurrent circuit breaker shall not exceed the value 1.3
times the rated current of that household electric appliance (*3).
Page 201 of 282
(*3) If that value does not fit any standard rating of overcurrent circuit
breakers, employ the nearest larger rating.
c. The allowable current of the electrical conductor shall be equal to or greater than the
rated current of that household electric appliance and the overcurrent circuit breaker
according to (b) above.
7.2.9.2.2
Branch Circuit Supplying Electricity to an Electric Motor Alone
A branch circuit supplying electricity to an electric motor alone shall be installed as follows:
a. The rated current of the overcurrent circuit breaker shall be 2.5 times the allowable
current of the electrical conductor connecting to that overcurrent circuit breaker (*4).
(*4) If the rated current of that electrical conductor exceeds 100 A and the said rated
current value does not fit any standard rating of overcurrent circuit breakers, employ the
nearest rating larger than that value.
b. For each portion of the low-voltage indoor wiring, the allowable value of the
electrical conductor of that portion shall be equal to or greater than the value 1.25
times (*5) the total of rated current of the electric motors supplied from that portion of
the low-voltage indoor wiring.
(*5) If the total of the rated current of the electric motors concerned exceeds 50 A, the
allowable current shall be equal to or greater than 1.1 times that current.
Thickness of electrical
conductor in the portion
Installation Thickness of Receptacle to Screw connector
(limited to 3 m or less)
Type of low-voltage low-voltage which to or socket to which
from a screw connector,
indoor circuit indoor wiring connect to connect
socket or receptacle to
its branching point
Circuit protected by an Receptacle Socket of the screw
overcurrent circuit breaker with a rated type with a nominal
with a rated current of 15 A current of 15 A diameter of 39 mm
or less or less or less, or a socket
Diameter other than the
Circuit protected by an -
1.6 mm Receptacle screw type, or
overcurrent circuit breaker
with a rated screw connector
with a rated current of
current of 20 A with a nominal
greater than 15 A and 20 A
or less diameter of 39 mm
or less
or less
Page 202 of 282
Excluding a Socket for halogen
Circuit protected by an
receptacle to lamps, or a socket
overcurrent circuit breaker
which a plug for incandescent
(excluding a distributing Diameter
with a rated lamps other than
circuit breaker) with a 2 mm
current of less halogen lamps or
rated current of greater
than 20 A can for mercury lamps,
than 15 A and 20 A or less Diameter 1.6 mm
be connected with a nominal
Circuit protected by an Receptacle diameter of 39 mm,
overcurrent circuit breaker with a rated or a screw
Diameter
with a rated current of current of 20 A connector with a
2.6 mm
greater than 20 A and 30 A or over and 30 nominal diameter of
or less A or less 39 mm
Receptacle
Circuit protected by an
with a rated
overcurrent circuit breaker
Sectional current of
with a rated current of 2 Diameter 2 mm
area 8 mm greater than
greater than 30 A and 40 A
30 A and 40 A
or less
or less
Receptacle
Circuit protected by an
with a rated
overcurrent circuit breaker
Sectional current of
with a rated current of 2 Diameter 2 mm
area 14 mm greater than
greater than 40 A and 50 A
40 A and 50 A
or less
or less
7.2.13.1.1
A switching device shall be installed on the low-voltage indoor circuit in a place near the
service entrance and it shall be easy to open and close.
7.2.13.1.2
An installation shall be provided with a main switch or circuit breaker and a means of
isolation to cut off all voltages. These two functions may be incorporated in a single device.
The main switch or circuit breaker should interrupt all live conductors (i.e. phase and neutral
conductors) and be capable of cutting off the full load current of the installation from supply.
For a 3-phase 4-wire a.c. supply, a linked switch or linked circuit breaker may be arranged
to disconnect the phase conductors only and in such case, a link should be inserted in the
neutral conductor and securely fixed by bolts or screws.
7.2.13.1.3
For an installation serving more than one building, the installation inside separate buildings
shall be treated as a separate installation, and a separate main switch or circuit breaker and
a separate means of isolation for each building are required as in Clause 7.2.13.1.2
Page 203 of 282
7.2.13.1.4
Every circuit or group of circuits shall be provided with a means of:
a. Isolation; and
7.2.13.1.5
Where a standby generator is installed, electrically and mechanically interlocked 4-pole
changeover devices should be used for interconnection between the normal and standby
sources to ensure that any neutral unbalance and fault current return to the correct source
of supply.
7.2.13.1.6
Under no circumstances shall a means of isolation or a switching device be provided in a
protective circuit.
7.2.13.1.7
A circuit breaker used to receive supply direct from the Local electricity distribution
company’s transformer. An isolator may be used in conjunction with a fixed type circuit
breaker provided that it is mechanically interlocked with the circuit breaker.
7.2.13.2.2
An appliance, equipment or luminaire, other than that connected by means of a plug and
socket outlet shall be provided with a means of interrupting the supply on load.
7.2.13.2.3
For electric discharge lighting installations operating normally at an open-circuit voltage
exceeding low voltage, an effective local means for isolation of the circuit from supply (such
means being additional to the switch normally used for controlling the circuit) shall be
provided for the isolation of every self-contained luminaire, or of every circuit supplying
luminaires at a voltage exceeding low voltage.
7.2.13.3.1
Means shall be provided for emergency switching using a self latching push button such
that any part of the installation where it may be deemed necessary to control supply so as to
remove an unexpected danger, thereby keeping the installation isolated until the push
button is unlatched.
Page 204 of 282
7.2.13.3.2
Means for emergency switching shall be provided for the purpose of cutting off the
appropriate supply to the circuit concerned as rapidly as possible in order to obviate or to
remove a dangerous condition as soon as it becomes apparent. A typical example where
means for emergency switching shall be provided is a machine driven by electrical means
which may give rise to danger.
7.2.13.3.3
Where electrically powered equipment is operated within the scope of NIS IEC 60204, the
requirements for emergency switching of that standard apply.
a. Domestic/Residential
b. Commercial
c. Industrial
d. Specialized Installations (military, telecommunications, infrastructure, mobile,
construction sites, temporary installations, mining)
e. Others
7.2.14.1.1
Supply to every User Site installation shall be adequately controlled by Switchgear readily
accessible to the consumer which shall incorporate means of:
7.2.14.1.2
All such installations shall be easily accessible to the consumer and as near as possible to:
a. The point or points of entry of the service mains in the case of a public supply;
b. The generator in the case of private plant; or
c. The inverter unit, in the case of renewable energy and fossil fuel energy sources.
7.2.14.1.3
In the case of a private plant where the building containing the generator is isolated from the
building in which the electricity is consumed, a main switch shall be installed at a point at
which the main cables enter the latter building. Where more than one building is supplied
from common mains, switches shall also be installed at each building.
7.2.14.1.4
The means of isolation required by Clause 7.2.14.1.1 shall comprise a linked switch suitable
for operation on load or a linked circuit-breaker arranged to disconnect all supply having an
excess-current release fitted in each live conductor of the supply.
Page 205 of 282
7.2.14.2 Supply Protection
7.2.14.2.1
The means of excess-current protection required by Clause 7.2.141.1 shall comprise either
a suitably rated fuse in each live conductor of supply or circuit-breaker having an excess-
current release fitted in each live conductor of the supply.
7.2.14.2.2
Every means of excess-current protection shall be suitable for the maximum short-circuit
current attainable.
7.2.14.2.3
The characteristics and settings of excess-current protective gear, including fuses and
arrangement of the installation, shall be such that discrimination in the operation of the
excess-current protection gear is ensured.
7.2.14.2.4
Throughout a 2-wire installation connected to a source of supply having one pole connected
with earth, all fuses and single-pole control devices, e.g. switch or circuit-breakers,
thermostats and the like, shall be connected in the live conductor only. This does not
preclude the use of double-pole linked devices controlling both conductors of the supply.
7.2.14.2.5
Throughout a 2-wire installation connected to a source of a supply having neither pole
connected with earth, every switch or circuit-breaker shall be of the double-pole linked type,
and fuses (where installed) shall be fitted in both poles.
7.2.14.2.6
Every conductor in the installation shall be protected against excess current by a fuse or
circuit breaker fitted at the origin of the circuit of which the conductor forms a part. The
current rating of every fuse used for this purpose shall not exceed that of the lowest-rated
conductor in the circuit protected, account being taken of the class of excess-current
protection afforded by the fuse. Every circuit breaker used for this purpose shall operate
when the circuit protected is subjected to a sustained excess current of 1.5 times the rating
(appropriate to this form of protection) of the lowest-rated conductor in the circuit. Sizes of
fuse elements for semi-enclosed fuses are given in Table 1 Schedule 1.
7.2.14.3.1
For low and medium voltage cut-out shall comply with Clause 7.2.14.1.1
7.2.14.3.2
The cut out fuse shall be provided with a suitable incombustible and insulating carrier for the
fuse of such shape as to protect a person handing it from shock and burns; and contacts
shall be provided on the carrier to which the ends of the fuse can be readily attached.
Page 206 of 282
7.2.14.3.3
The cut out fuse base shall be provided with fixed circuit contacts of such shape as to retain
the carrier in position in the presence of vibration.
7.2.14.3.4
The bus bars, fixed contacts, removable contacts, and fuses shall be so shielded as to
protect a person against contact with live metal parts when the fuse-carrier is being inserted
or removed.
7.2.14.4.1
Switchboards shall be constructed wholly of durable, non-ignitable, non-absorbent materials
in accordance with NIS IEC 60439, and all insulation shall be of permanently high strength
of not less than 100MΩ.
7.2.14.4.2
All switchboards with metallic frames shall be provided with suitable terminals, to which the
earthing lead shall be attached.
7.2.14.4.3
The various exposed live parts of switchboards shall be so arranged by suitable spacing or
shielding with non-ignitable insulating materials that an arc cannot be maintained between
any such parts or between such parts and earth. For voltage not exceeding 250 volts the
minimum clearance between the live metal parts of fuses of opposite polarity or phase, or
between any live metal and any earthed metal shall be 50 mm. Fuses which on blowing
expel the gas parallel to the axis of the fuse, and which are of opposite polarity or phase,
may be mounted one above the other if an insulating shield is fixed between them.
7.2.14.4.4
The arrangements of all parts shall be such that the connections to all instruments and
apparatus can be readily traced.
7.2.14.4.5
All parts, including connections, shall be readily accessible; and no fuse, circuit-breaker, or
switch other than an isolating switch shall be fixed on the back of the switchboard panel if it
is necessary to operate the same from behind.
7.2.14.4.6
All nuts or parts carrying over 25A shall be effectively locked so that they cannot become
loose.
7.2.14.4.7
All bus bars and connections on switchboards shall be in accordance with relevant NIS IEC
61439-1.
Page 207 of 282
7.2.14.4.8
Where a scheme of colouring is employed to distinguish switchboard busbars and
connections to individual poles or phases, such scheme of colouring shall be in accordance
with relevant NIS.
7.2.14.4.9
The arrangement of bus bars carrying alternating currents shall be in accordance with
relevant NIS IEC 60947.
7.2.14.4.10
Conductors must be symmetrically placed and spaced apart, and so arranged that the
course of every conductor may be readily traced.
7.2.14.4.11
All circuits, instruments, and important apparatus shall be clearly and indelibly labelled for
identification.
7.2.14.4.12
Switches shall be so arranged that their blades or moving parts are disconnected from the
supply in the off position. They shall be so mounted that the top of the handle is at a height
not exceeding 2.3m above floor level.
7.2.14.4.13
In every case in which the switches and fuses are fitted on the same pole or phase these
switches shall preferably be so arranged that the fuses are disconnected from the supply
when their respective switches are in the “off” position.
7.2.14.4.14
Where meters, service fuses or other apparatus belonging to the Local electricity distribution
company are to be mounted on a switchboard, loops shall be left in the leads of sufficient
length to allow the ends of the conductors to be properly connected by the Local electricity
distribution company.
7.2.14.4.15
Each distribution board shall have fitted in or on its case or cover, or in an adjacent
conspicuous position, an indication of the circuit protected by each fuse or circuit-breaker
contained therein and of the appropriate current rating for the circuit so protected.
7.2.14.4.17
Where service meters are not mounted on the main switchboard they shall be mounted on a
substantial base.
7.2.14.4.18
Where instrument transformers are used, and are easily accessible, all live metal parts shall
be effectively insulated.
Page 208 of 282
7.2.14.5 Final Sub-Circuits
7.2.14.5.1
The number of points which may be supplied by a final sub-circuit of rating not exceeding 15
amperes is limited by their aggregate demand as determined from Table 2 ; there shall be
no other allowance for diversity in the final sub-circuit and the current rating of the cable
must not be exceeded.
TABLE 2
Note 1: In the interest of good planning it is undesirable that whole of the fixed lighting of an installation should
be supplied from one final sub-circuit.
Note 2: In the interest of providing the consumer with an adequate installation it is recommended that use should
be made of ring final sub-circuits where applicable.
7.2.14.5.2
All socket outlets in any one room shall be connected to the same phase (or pole of a 3 wire
system).
7.2.14.5.3
Not more than one phase supply shall be brought into a multi-gang switch box.
7.2.14.5.4
Where an installation comprises more than one final sub-circuit, each shall be connected to
a separate way in a distribution board.
7.2.14.5.5
The wiring of each final sub-circuit shall be electrically separated from that of every other
final sub-circuit. To facilitate disconnection of each sub-circuit for testing, the neutral
conductors shall be connected at the distribution board in the same order as that in which
the live conductors are connected to the fuses or circuit-breakers.
Page 209 of 282
7.2.14.5.6
A final sub-circuit having a rating exceeding 15 amperes shall not supply more than one
point. For the purpose of this Clause, the following items may each be regarded as one
point –
7.2.14.5.7
To determine the rating of a final sub-circuit supplying stationary cookers in domestic
premises, the current demand of each cooker shall be assessed to be not less than 30A.
The minimum size of cable should be 6 mm2.
7.2.14.5.8
Every stationary cooking appliance in domestic premises shall be controlled by a switch
separate from the appliance and installed within 2m of the appliance.
7.2.14.6.1
Diversity shall not be allowed for when calculating the size of circuit conductors and
switchgear and circuits other than final sub-circuits, to the extent specifically permitted by
IEC standards for cooking appliances.
7.2.14.6.2
Diversity may be allowed for when calculating the size of circuit conductors and switchgears
and circuits other than final sub-circuits provided this is justified by known or anticipated
conditions.
Note: Allowance for diversity is a matter calling for special knowledge and experience. The
application of diversity shall be decided by the engineer responsible for designing each
particular installation.
7.2.14.7.1
In domestic installations either radial or ring final sub-circuit conforming with Table 3 may be
installed to serve socket outlets complying with the relevant NIS Specification and
Stationary appliances of rating not exceeding 13A provided that the general requirements of
this Standard and in case of ring sub-circuits, the special requirements of Clauses
7.2.14.7.5 to 7.2.14.7.11 are met.
Page 210 of 282
7.2.14.7.2
Each socket outlet of a twin or multiple socket outlet units shall be counted as one socket
for the purposes of Clause 7.2.14.7.1 and Table 3.
7.2.14.7.3
A stationary appliance connected permanently (i.e. not through a plug and socket outlet) to
a radial or ring final sub-circuit conforming with Clause 7.2.14.7.1 shall be locally protected
by a fuse of rating not exceeding 13A and controlled by a switch or protected by a circuit-
breaker of rating not exceeding 15A.
7.2.14.7.4
The conductor sizes tabulated in Table 3 are minimum values and shall be increased if
necessary where circuits are installed in groups or in conditions of high ambient
temperature, taking account of the class of excess-current protection provided. In such
circumstances it must be ensured that –
a. for radial final sub-circuits, the current rating of the conductors is not less than that of
the fuse or circuit-breaker protecting the final sub-circuit, and
b. for ring final sub-circuits, the current rating of the conductors forming the ring is not
less than 0.67 times the rating of the fuse or circuit breaker protecting the final sub-
circuit.
7.2.14.7.5
Each circuit conductor of a ring final sub-circuit shall be run in the form of a ring,
commencing from a way in a distribution board (or its equivalent), looping into the terminals
of socket outlets and joint boxes (if any) connected in the ring and returning to same way of
the distribution board.
Page 211 of 282
7.2.14.7.6
Except where a ring final sub-circuit is run throughout in metallic conduit, ducts or trunking,
or in metal-sheathed cable, the earth-continuity conductor shall also be run in form of a ring
having both ends connected to earth at the distribution board (or its equivalent).
7.2.14.7.7
Each ring final sub-circuit conductor shall be looped into every socket-outlet or joint box
which forms parts of the ring and shall either remain unbroken throughout its length or,
alternatively, if the conductor is cut, its electrical continuity shall be ensured by joints.
7.2.14.7.8
For ring final sub-circuits complying with Clauses 7.2.3.44.1 to 7.2.3.44.4 the total number
of spurs shall not exceed the total number of socket-outlets and stationary appliances-
connected directly in the ring.
7.2.14.7.9
For ring final sub-circuits complying with Clauses 7.2.14.7.1 to 7.2.14.7.4, the total number
of spurs shall be connected through fused spur boxes. The rating of the fuse shall not
exceed that of the cable forming the spur and in any event shall not exceed 13A. The total
current demand of points served by a fused spur shall not exceed 13A.
7.2.14.7.10
For ring final sub-circuits complying with Clauses 7.2.14.7.1 to 7.2.14.7.4 non-fused spurs
shall be connected to the ring at the terminals of socket-outlets or at joint boxes or at the
origin of the ring in the distribution board. Non-fused spurs shall have a current rating not
less than that of the conductors forming the ring. Not more than two socket-outlets, or one
twin socket-outlet, or one stationary appliance, shall be fed from each non-fused spur.
7.2.14.7.11
In domestic premises, a ring final sub-circuit may serve an unlimited number of points but
shall not serve more than one room. Where two or more ring final sub-circuits are installed,
the socket-outlets and stationary appliance to be served shall be reasonably distributed
among the separate ring final sub-circuits.
7.2.14.7.12
For industrial, commercial and other non-domestic installations radial and ring final sub-
circuits otherwise conforming to the requirements of Clauses 7.2.14.7.1 to 7.2.14.7.10 may
be installed where, owing to diversity, the maximum demand of apparatus to be connected
is estimated not to exceed the corresponding fuse or circuit-breaker ratings set out in Table
3.
7.2.14.7.13
Provision shall be made so that every portable appliance and portable light fitting can be fed
from an adjacent, conveniently accessible socket outlet.
Note 1: For industrial and commercial premises, it may be desirable to provide pilot lamps
to indicate when portable non-luminous heating appliances such as smoothing irons and
soldering irons, are in operation.
Page 212 of 282
Note 2: For hand-held appliances which are likely to be used out-door or in damp situations,
attention is drawn to the added safety which can be obtained by the use of a double-wound
transformer having a reduced secondary voltage or alternatively by the use of monitored
earth-continuity circuits.
TABLE 3
Radial and ring final sub‐circuits
Description and special Minimum copper Minimum Minimum copper Rating of fuse Maximum number of
condition if any conductor size or copper clad conductor size of or circuit socket –outlets and
rubber or p.v.c. aluminum mineral insulated breaker stationary appliance of
insulated cable conductor size cable used protecting rating not exceeding
used throughout. of p.v.c. throughout final sub‐ 13 amperes.
insulated cable (alternative to circuits.
used Col.2)
throughout
1 2 3 4 5 6
mm2 mm2 mm2 A
(a) Radial final sub circuit Provided that no fixed
serving one room only water‐heating
of less than 30m2 floor appliance shall be
area which is not a connected to any of
kitchen……………….. these points.
Radial final sub circuit, 2.5 4
serving rooms other 2
than in (a) above……….. 2.5
4
Ring final sub circuit,
with spurs if 4.0 6
1.5 20
any…………………. See regulation 31 (8) –
(b) 6
2.5 (12)
1.5 20
4
2.5 30
(c)
1.5 30
Appliance of 15VA rating or less may be ignored.
7.2.14.8.1
All sockets used in low voltage circuit shall comply with the requirements of NIS IEC60884.
Page 213 of 282
7.2.14.8.2
Where the supply is direct current, each socket-outlet shall be controlled by a switch
immediately adjacent thereto or combined therewith. Where the supply is alternating current
and the plug is readily withdrawable, such a switch need not be provided.
7.2.14.8.3
An appliance or light fitting connection to an installation other than by means of a plug and
socket outlet shall be controlled by a switch or switches which shall be arranged to
disconnect all live supply conductors. For an appliance fitted with heating elements which
can be touched or into which more than one phase of the supply is introduced, the switch
shall be a linked switch arranged to break all the circuit conductors.
7.2.14.8.4
The switch required by Clause 7.2.14.8.3 shall be separate from the appliance or light
fittings in a readily accessible position subject to the provisions of Clauses 7.2.14.8.5,
7.2.14.8.6 and 7.2.14.8.7 where applicable.
7.2.14.8.5
The switch required by Clause 7.2.14.8.3 may be mounted on the appliance or light fittings
provided the connections are so arranged that the appliance or light fittings can be
dismantled for maintenance without exposing any parts which remain live. Where live
cables/parts are exposed, they shall be as short as possible, separated from any other
conductors or cables by screens of earthed metal or suitable barriers of insulating material
and so installed that they are not adversely affected by any heat from the appliance or light
fittings.
7.2.14.8.6
Where clause 7.3.3.16 requires a switch to be situated so as to be normally inaccessible to
a person who is using a bath or shower, it is admissible for the switch to be placed in a
suitable position outside and immediately adjacent to the normal access door of the room,
or to be of the type operated by an insulating cord.
7.2.14.8.7
The switch or switches providing control of comprehensive space cooling, or light
installations, comprising more than one appliance or light fitting may be installed in a
separate room.
7.2.14.9.4
a. As a general guide, all motors shall be provided with control gears so that their
starting currents at user's site installations do not exceed the limits given in the
following table:
Single Phase Up to and including 0.75kW five times full load current
Single/three phase Above 0.75kW and up to and Three times full load current
including 5.6kW
three phase Above 5.6kW and up to and including Twice full load current
12kW
b. Cables carrying the starting, accelerating and load current of a motor shall be of
rating at least equal to the full-load current rating of the motor when rated in
accordance with the relevant NIS requirements.
A final sub-circuit supplying a motor shall be protected in accordance with the
requirements of Clause 7.2.14.2.6 unless Clause 7.2.14.9.7 applies.
d. The sizes of the cables for motor circuits for slip ring or commutator induction motors
shall be suitable for the starting and loading conditions. Insulated conductors
installed shall be such that no stress can be applied by the conductors to any
terminal to which they may be connected.
Page 215 of 282
e. Fittings shall be so designed and fixed that neither dust not moisture can readily
accumulate on live parts.
f. Where a hanging fitting exceeds 5kg in weight it shall be supported by a metal chain,
tube, or rod, or by several flexible cords in such a manner that the maximum weight
to which any cord is subjected shall not be greater than that specified in Clause
7.2.3.23.5
g. Open-type fittings shall be furnished with inflammable shades unless such shades
are kept free from contact with the lamps by suitable guards or supports.
h. Enclosed type fittings shall be provided with a removable glass receptacle arranged
to enclose the lamp completely, and of such size or construction as to prevent undue
heating of the lamp; and if the position of the fitting be such that the glass receptacle
is liable to mechanical damage, the glass shall be protected by a suitable wire
guard.
i. Fittings whether fixed or portable, shall, whenever exposed to rain, drip or externally
condensed moisture, be of the weatherproof type.
j. Fittings for lamp shall be designed to provide for adequate dissipation of heat from
such lamps.
l. The handle of every hand-lamp (not being a hand-lamp made entirely of metal
specified in the last preceding standard) shall be made of treated hard-wood, or of
some suitable non-ignitable composite insulating material capable of withstanding all
round usage in service.
m. Where portable fittings, appliances, or accessories are likely to be used, the voltage
between any two points in one room or compartment shall not exceed 250 V unless:
Page 216 of 282
other; or the metal frames and sheathing of all such portable appliances and
accessories are earthed.
ii. Flexible conductors of portable fittings or apparatus shall be connected
through appropriately sized wall plugs.
iii. Portable fittings shall be mounted on a base-block or a suitably fixed hook.
iv. Accessories other than fuses shall be mounted on a base-block unless they
are completely enclosed in metallic casing, and where the surface on which it
is mounted is liable to become damp the base-block shall be rendered
impervious to moisture.
7.2.14.12 Lamp-Holders
a. Lamp-holders for lamps shall normally be used only in circuits operating at a
voltage not exceeding 250 volts.
b. Every lamp-holder for a bayonet-cap lamp in any damp situation or in any
situation in which it can readily be touched by a person in contact with or
standing on earthed metal shall be–
i. Earthed, or
ii. Constructed of, or shrouded in, insulating material and for moulded
insulated bayonet, fitted with a protective shield.
c. Where bayonet or Edison screw lamp-holders are connected to a source of
supply having an earthed neutral conductor, the outer or screwed contact shall
be connected to that conductor. Where such lamp-holders are used in circuits
having neither pole connected with earth, or in any damp situation in which they
can readily be touched by a person in contact with or standing on earthed metal,
they shall be provided with a protective shield of insulating material or shall be
placed or safe guarded, so that neither the lamp cap nor the outer or screwed
contact of the lamp-holder can be inadvertently touched when the lamp cap is
engaged with that contact.
d. Where arc lamps are used in positions where danger might otherwise arise, they
shall be protected either by a metal reflector rigidly fixed beneath the arc or by a
globe or lantern. Wherever noxious fumes are likely to be emitted from such a
Page 217 of 282
lamp, suitable ventilation shall be provided.
7.2.14.14 Capacitor
a. Every capacitor, unless incorporated for the sole purpose of radio interference
suppression or directly connected across a motor winding, shall be provided with
a means, such as a high-resistance leak, for its prompt automatic discharge
immediately the supply is disconnected. This requirement shall not apply to small
capacitors where no risk of shock can arise.
b. For Every user site supplied from L.T. and having connected load that includes
induction motor(s) of 2.23 kW rating and above shall install low tension shunt
capacitors of appropriate capacity across the terminals of such motors to
improve average power factor to 0.85. Such capacitor(s) shall be maintained in
working condition. The local electricity distribution company deserves the right to
disconnect the user site if this clause is infringed upon to ensure compliance only
after which supply shall be restored.
Page 219 of 282
TABLE 10
Connection of plugs, socket‐outlets and connectors
Corresponding conductor
Terminal marking For circuits having an earthed neutral For circuits in which neither pole of
conductor the supply is earthed
L Live conductor
N Neutral conductor Live conductors
I or E Earth‐continuity conductor Earth‐continuity conductor
7.2.15 Appliances
Page 220 of 282
mounted as to secure freedom from electrical hazard. This plug shall have a
separate contact connected to earth and any portable apparatus used from this plug
shall be earthed in accordance with the requirement of these Standards.
7.2.16 Preventions of Interferences Caused By High Frequency Current, Voltage Flickers And
Dips
All electrical appliances, equipment and luminaires capable of generating high frequencies
shall be suppressed at their respective generating sources to mitigate interference with
other vulnerable devices via conduction and radiation channels. In addition, equipment
such as electric arc welding machines and arc furnaces shall be operated in accordance
with NIS IEC 60974-9 to minimize effects of voltage dips and flickers on other consumers.
7.2.16.1 Appliances Generating High Frequency Signals, Voltage Dips And Flickers
a. If the electrical appliance has the possibility of generating high frequency radio
waves or radio frequency currents that might continuously and seriously interfere
with the function of radio, television or other wireless devices, it shall be installed
according to Clauses 7.2.16.1.2 and 7.2.16.1.3 to prevent such interference.
b. For fluorescent lamps, a suitably rated capacitor shall be provided in an appropriate
place to suppress the interference in accordance with NIS IEC 60081.
c. For a small AC series motor with an operation voltage in the low-voltage range and a
rated output of 1 kW or less, one of the following shall be adhered to:
i. Capacitors 0.1 µF and 0.003 µF in capacitance values and of appropriate
voltage rating shall be inserted respectively between motor terminals and
between each motor terminal and the metallic case of the electrical
appliance or the frame of the small AC series motor or the ground.
ii. For an electrical appliance containing a small AC series motor where the
frame of the motor is insulated from the appliance’s metallic case, steel
stand and other accessible metallic parts, capacitors of 0.1 µF and
0.003 µF respectively shall be inserted between motor terminals and
Page 223 of 282
between each motor terminal and the motor frame or ground.
iii. A capacitor of 0.1 µF shall be inserted between each terminal of the AC
series motor and ground.
iv. Where the AC series motor is inaccessible, capacitors of 0.1 µF and
0.003 µF respectively shall be inserted between electrical conductors that
are connected to the electrical appliance at a place close to that
appliance between each electrical conductor and the metallic case of the
appliance or ground.
d. For a small AC series motor with an operating voltage in the low-voltage range and a
rated output of 1 kW or less used for electric drills, a non-inductive capacitor 0.1 µF
shall be inserted between motor terminals and through-type capacitor of 0.003 µF
with sufficient shunting effect shall be inserted between each motor terminal and the
ground.
e. For a neon lamp flasher, an appropriately designed filter shall be installed between
power terminals and at a place close to each contact to prevent a radio-frequency
current from occurring in the electrical circuit connected to the neon lamp flasher.
f. All LV installations where welding transformers are connected shall be required to
install suitable capacitor(s) so as to ensure power factor of not less than 0.85 and
reduce voltage dips and flickers to the barest minimum.
g. Electric arc welding sets having a current rating exceeding 25A single phase or 50%
of the maximum demand of an installation in any one phase shall be permanently
connected to the mains on a 3-phase supply. All exposed conductive parts of
welding sets shall be effectively connected to earth.
h. All installations where arc furnaces of high capacities are connected shall require
suitably rated Static Var Compensators (SVCs) to be sited at the points of common
coupling so as to achieve power factor greater than 0.85 and minimize voltage
fluctuations and flickering effects otherwise experienced by other consumers.
i. All appliances, luminaires and apparatus shall be designed, constructed and
appropriately located so as to avoid interference and nuisance and shall exhibit
maximum operational integrity and comply with EMC of NIS IEC61000-3-11.
7.2.17 User’s Site Protection and Over Current Circuit Breakers for Electric Motors
Every User’s site shall be adequately protected against any mal-operation of installed
appliances, equipment and failure of the wiring system. In addition, over current circuit
breakers shall be provided at the user’s site for electric motors.
7.2.17.1.1
The following devices shall be used as protective devices against overcurrent:
7.2.17.1.2
Page 224 of 282
a. Every electrical circuit and sub-circuit shall be protected against excess current by
fuses, circuit breakers, or other similar devices which:
i. Will operate automatically at current values which are suitably related to
the safe current, ratings of the circuit, and
ii. Are of adequate making and breaking capacity, and
iii. Are suitably located and of such construction as to prevent danger from
over-heating, arcing or the scattering of hot metal when they come into
operation and
iv. Permit ready renewal of fuse-elements without danger.
b. Where the earth-fault-leakage current from a circuit due to a fault of negligible
impedance from a live conductor to earthed metal is sufficient to operate the fuses or
circuit-breakers or other similar devices provided so as to comply with Clause
7.2.17.1.1, the current shall be protected against the persistence of earth-leakage
currents liable to cause danger by suitably rated earth-leakage circuit-breaker
(ELCB) or equivalent device.
c. No fuse, or circuit breaker other than a linked circuit breaker, shall be inserted in a
conductor connected with earth, and any linked circuit breaker inserted in a
conductor connected with earth shall be arranged to break also all the live
conductors.
d. Every single-pole switch shall be inserted in the live conductor only, and any switch
connected in the conductor connected with earth shall be a linked switch and shall
be arranged to break also all the live conductors.
e. Overload protective and fault current protective devices shall be in accordance with
the specifications of NIS IEC 60947.
f. For devices providing protection against both overload current and fault current, they
shall satisfy both the requirements of overload protective devices and fault current
protective devices.
g. The characteristics of devices for overload protection shall be coordinated so that
the energy let-through by the fault current protective device does not exceed that
which can be withstood by the overload protective device without damage.
7.2.17.2.1
If an electric motor is installed indoors with a rated output exceeding 0.4 kW, an appropriate
device shall be installed to automatically isolate, or alert the operator of an overcurrent that
may damage the motor.
7.2.17.2.2
The overload protective device is not required to be installed provided:
a. the electric motor is installed at such a position where the operator can normally
monitor it while it is in operation,
b. there is no danger of such an overcurrent being able to damage the motor stator
winding, due to the loading condition of the motor,
c. the electric motor is an integral component of an appliance or equipment complying
as a whole with an appropriate NIS. .
Page 225 of 282
7.2.17.3 Installation of Overcurrent and Fault Current Protective Devices
7.2.17.3.1
Overcurrent and fault current protective devices shall be installed in places at user’s site
readily accessible for maintenance.
7.2.17.3.2
Overload protective devices shall be so installed:
a. Where a reduction occurs in the value of current carrying capacity of the conductors
of the installation.
b. At any point along the run of those conductors provided that the part of the run
between the point where the value of current carrying capacity is reduced and the
position of the protective device has no branch circuits or outlets for the connection
of current using equipment.
7.2.17.3.3
Fault current protective devices, subject to clause 7.2.17.3.1, shall be installed in such a
manner as to reduce to the barest minimum the risk of fault, fire or danger to persons.
7.2.18.1.1
All lamps or household appliances shall be installed so that no live part is exposed.
(a) Capacitors and chokes should normally be fitted inside the luminaire. Where they
are fitted separately, they should be mounted in a metal box. Precautions should be
taken to prevent the components from overheating, e.g. by the provision of adequate
ventilation.
(b) The type and size of cables should be properly selected with due regard to the
ambient temperature, the inrush current and high voltages generated during starting.
The neutral conductor in every discharge lamp circuit should have a cross-sectional
area not less than that of the phase conductor.
(c) Where fluorescent and gas discharge lamp are directly mounted on the ceiling care
should be taken to ensure that the choke does not pose a fire risk.
7.2.18.2
Low-voltage business electrical appliances shall be installed so that the live parts are not
exposed. This shall, however, not apply to electric furnaces, electric welders, electric motors
and other appliances that are used with some live part inevitably exposed andin such cases
where these are installed in a place made inaccessible for any person other than the
operator.
Page 226 of 282
7.2.18.3
A household or business electric appliance with live parts accessible to persons shall not be
installed indoors.
7.2.18.4
If the indoor electric appliance is to be connected to an electrical conductor, the same shall
be securely connected by means of screw fastening or similar means of fastening. In
addition, no tension shall act on the connection point.
7.3.1.1
The wiring to a traffic sign lamp shall be installed according to the following conditions:
c. For the metallic wire of Item (b) for electrical conductor suspension, an insulator
shall be inserted at or near the supporting structures.
7.3.1.2
The hanger wire of a traffic sign lamp shall be installed according to the following conditions:
a. The height of the electrical conductor shall be 2.5 m or more above the ground
surface.
7.3.1.3
On the power supply side of the control device of a traffic signal lamp, a dedicated switching
device and overcurrent circuit breaker shall be installed on each pole.
7.3.1.4
If the wiring of a traffic signal lamp circuit approaches or crosses a facility other than a
building, road, pedestrian overpass, railroad, overhead telecommunication conductor,
antenna or overhead electrical conductor, the clearance from the wiring of the traffic signal
lamp circuit to such object shall be 60 cm or more. If the wiring of the traffic sign lamp is a
Page 227 of 282
cable, the clearance shall be 30 cm or more.
b. The light fitting shall be strong and durable and shall be attached to a pole firmly.
d. The light fitting shall have a structure that allows for easy replacement of the lamps
and other replaceable components.
e. The live conductor of the light fitting shall have a sectional area of 1.5 mm2 or more.
f. The light fitting attaching band and attaching accessory hardware shall be made of
steel plate given an anticorrosive treatment of galvanizing or stainless steel, which
allows for easy attachment and detachment.
b. The Luminaries for road and street lighting system shall be in accordance with IEC
60598-2-3
Page 228 of 282
increased by a reduction in body resistance and contact of the body with earth
potential. Swimming pools and fountains installations shall comply with the
requirements of NIS IEC 60364-7-702.
Note: Additional requirements may be necessary for swimming pools for medical
purposes.
7.3.4
Special locations (which include public places, parks, garden, sporting areas,
illumination of monuments and flood lights) shall be installed in accordance with IEC
60364-7-714.
7.3.5
Electrical installation in ships shall be in accordance with IEC 60092-306.
7.3.6
Bath and shower electrical installation shall be in accordance with IEC60364-7-701.
7.3.7
Construction and demolition site installations shall be in accordance with IEC60364-
7-704.
7.3.8
Agricultural and Horticultural premises installation shall be in accordance with
IEC60364-7-705.
7.3.9
Households and similar electrical appliances particular requirement for commercial
dispensing appliances and vending machines shall be in accordance with IEC
60335-2-75.
7.3.10
The installations at Marinas and similar locations shall meet the requirements of NIS
IEC 60364-7-709.
Page 229 of 282
Chapter 8: Protection, Control and Metering
Page 231 of 282
8.1.1.8 Wide Area Protection
Wide area protection may be implemented to ensure the security, reliability and stability
of the grid system.
The owner of a network shall determine when it becomes reasonably necessary to
implement Wide Area Protection and propose an implementation plan in writing to
NERC.
All SCADA/EMS software shall comply with the industry-accepted software standards
produced by national and international organizations, such as ANSI, ISO, IEC, and IEEE
and shall be CIM (Common Information Model) compliant.
The requirement of hardware shall be optimized for servers/processors where one or more
applications can be combined or distributed in any combination with adequate redundancy.
Page 232 of 282
8.4.1 SCADA Control Room
SCADA Control Room shall be constructed in accordance with NIS IEC 61850
standard.
8.4.3 Communications
Communication between Intelligent Electronic Devices (IED) shall be in accordance
with NIS IEC 61850 and Communication between Substation Automation System
(SAS) and power plant devices shall comply with IEC 608-70-104.
Page 233 of 282
Chapter 9: Classification of Equipment and Types of Tests
Equipment used in the distribution network shall be classified as outdoor or indoor equipment.
Indoor equipment shall consist of equipment used in distribution network installed within a building
or an enclosure free or shielded from direct sunlight.
Examples include but not restricted to;
Transformer control panels,
Line/feeder control panels,
Battery banks,
Chargers and Tripping units,
Communication gadgets among others.
Outdoor equipment shall consist of equipment used in distribution network installed outside a
building or any enclosure and not protected from direct sunlight or other weather effects.
Examples include but not restricted to;
Transformers,
Circuit breakers,
Power isolators, among others.
Types of Tests
The condition and service reliability of equipment used in distribution network shall at all times be
kept in the most efficient and safe operating condition while undergoing periodic basic and
necessary tests.
Basic tests to be carried out on distribution equipment shall include but not limited to the following;
Page 234 of 282
Single phase excitation tests,
Insulation resistance test.
These tests shall comply strictly with the provisions of IEC 60726.
Standard power transformer capacities shall be 2.5 MVA, 5 MVA, 7.5 MVA, 10 MVA, 15
MVA and up to 30 MVA suitable for 33000/11000 V and distribution transformers shall be 25
KVA, 50 KVA, 100 KVA, 200 KVA, 300 KVA, 500 KVA, 1000 KVA, 1500 KVA and 2500
KVA suitable for 33 kV or 11 kV operation with 400 V at secondary at a nominal frequency
of 50 Hz.
All transformers must comply with the provisions of IEC 60076-1 to IEC 60076-10 including
other international standards on distribution and power transformers. The transformers shall
be constructed to achieve lower no-load losses, noise levels and high operating efficiency
without posing risk(s) to lives and property.
Materials:
The transformer core shall be cold-rolled grain-oriented magnetic silicon steel or amorphous
metal. Winding material shall be copper. Materials other than copper shall be used with
approval duly obtained from Nigerian Electricity Regulatory Commission (NERC).
Page 235 of 282
Suppression of Harmonics
The transformer shall be designed as to suppress or eliminate the harmonics voltages and
current, especially in the 3rd, 5th and 7th order harmonics, eliminate waveform distortions that
reduce electromagnetic and electrostatic interfaces in communication circuits and higher
frequency disturbances.
Filters shall be installed against harmonics in the networks.
Environmental Impact
Impact of transformer operation on the following hazardous and loss conditions shall be at
the barest minimum:
Noise pollution.
Land pollution, due to escaping oil in case of leaks.
The use of PCBs (polychlorinated biphenyls) in cooling liquids.
Energy losses in transformers.
Visual pollution to the environment caused by the siting of transformers and
substations without due consideration to the impact on the landscape.
Safety of people and environment
This process shall be repeated for all tap position to further confirm the nameplate
specification by the manufacturer.
Test results obtained shall be compared with the manufacturers winding resistance to
ascertain level of deterioration.
Page 236 of 282
9.1.7 Insulation Resistance Test
(1) Electric lines and apparatus of the licensee for use at high voltage shall not be
connected to a system for the purposes of the supply of energy unless the insulation of the
electric lines and apparatus has withstood either–
(a) the test prescribed in that behalf in the appropriate Nigerian Standard (NIS IEC
60076-3) or
(b) in case where no such tests have been prescribed, the continuous application
between conductors and earth during a period of not less than fifteen minutes of
alternating current either at testing voltage equal to at least one and one –quarter
times the normal working voltage to which the electric lines of apparatus will be
subject under conditions of supply, or at a testing voltage equal to the aforesaid
working voltage with the addition of 10,000 volts, whichever be the higher.
(a) the testing voltage between the outer conductor and earth in cases where the outer
conductor of an electric line having concentric conductors is to be connected directly
with earth shall be 1,000 volts;
(b) the aforesaid working voltage between any phase of an alternating current system
and earth in cases when the neutral conductor of the said system is not to be
connected with earth shall be deemed to be the voltage between phases;
(c) the duration of the test may be reduced to one minute in the case of apparatus for
use at high voltages subject to the testing volts being increased so as to equal not
less than one and one-half times the aforesaid working voltage, or aforesaid working
voltage with the addition of 20,000 volts whichever be the less;
(d) Direct current may be used instead of alternating current subject to the testing
voltage being increased so as to exceed by at least fifty per cent the corresponding
testing voltage prescribed for alternating current.
(3) If the testing prescribed in this regulation are made prior to the said electric lines
and apparatus being placed in position for the purposes of the supply of energy, the
said electric lines and apparatus after having been placed in position and before
being connected to the system shall have withstood a further test for resistance of
insulation either by the application of the tests
Where any electric line has been disconnected from a system for alteration or repair, such
electric line or apparatus shall not be reconnected to the system until the licensee have
applied the test prescribed in paragraph (3) of these regulation and have satisfied
themselves that the insulation of the electric line or apparatus and the phase sequence of
the system are in sound condition
Page 237 of 282
All power transformers prior to their installation and commissioning shall be sufficiently
tested and confirmed to possess insulation resistance of not less than 5 to 10 times its rated
voltage level. And this value must be reasonably maintained as to prevent danger or
interruption of supply as far as is reasonably practicable.
Page 238 of 282
9.1.19 Temperature Rise
The provisions of IEC 60076-1-8.3, -2 and -11 shall be strictly complied with.
Power transformer prior to its installation arrangement shall be made to sample the
transformer oil in its entire chamber and put to test in accordance with the specification of
this standard. The test to be conducted shall include part or all analysis detailed thus (1)
Dielectric strength test (2) Furan analysis (3) Tan delta analysis and (4) Dissolved gas
analysis test.
Dissolved gas analysis shall be carried out on all transformers periodically in accordance
with NIS/IEC 60557.
Transformer bushings shall be provided with arcing horn(s) to mitigate effects of flash over
due to surge and lightning.
Earthing resistance test shall be carried out on every installation to ensure efficient earthing
Soil Resistance Test shall be performed for all installations to ensure the maintenance of an
acceptable earth resistance value in accordance with the provision of IEC XXX.
- Polarity
Circuit breakers for use for LV applications shall comply with the requirements of the
respective standards IEC 60947-1 & -2 and IEC 60898.
All substation equipment shall be solidly earthed and the continuity to earth of all metallic
parts shall be regularly confirmed and established in conformity with the minimum specified
values given in 12.4.
Page 242 of 282
9.5.1 Standards and Specifications
The design, selection and specification of lightning arresters for use in distribution networks
shall take into cognisance amongst other considerations the prevailing atmospheric
conditions (Isokeraunic level) of the environment in accordance with the requirements of
IEC 60099-5, 6 & 8, and IEC 62305-1, 2, 3 & 4.
9.5.2 Ratings
The ratings of lightning arresters shall be as stated in 10.7.1.
Page 243 of 282
9.5.3 Tests
Annual tests shall be carried out on lightning arresters to ensure their operational
effectiveness in conducting to earth over-voltage surges that may occur during lightning
strikes in accordance with the requirements of IEC 60099-6 & 8 on testing.
The acceptable nominal voltage for lightning arresters shall be in accordance with the
values specified in 10.7.2 (Table 1).
Batteries used for substation d.c. supply shall be of vented flooded lead acid type.
The nominal d.c. operating voltage at substations shall be 110V. The d.c. supply cabling
shall be sufficiently sized to prevent voltage drop at the load end, particularly for long cable
runs.
9.6.2 Installations
Page 244 of 282
Charge controllers shall be installed to control the battery charge current to maintain float
charges.
Every battery shall be so arranged that a potential difference exceeding 50V does not
exist between adjacent cells without adequate protections against electrical hazards,
and each cell shall be readily accessible from the top of the battery bank and from at
least one side.
Persons entering the room shall be provided with personal protective equipment including
nose mask and hand gloves.
9.7 Relays
9.7.1 Standards and Specifications
The design, selection and specification of relays for use on distribution substation
switchgear shall be of the appropriate type to monitor, protect and measure electrical
signals and input and initiate appropriate predetermined changes in the electrical circuit in
accordance with IEC 60255-1.
The types of relay to be used in distribution substations shall include but not limited to:
Electromechanical Relays
Electrostatic Relays
Numerical Relays
Page 245 of 282
Electromechanical relay used on distribution substation switchgears shall comply
with the requirements of IEC 61810-1.
The test so carried out shall be in accordance with the specification of IEC 60255 and IEC
61810-7.
Page 246 of 282
Relays shall be calibrated after every setting changes or repairs.
9.7.10 Maintenance
Maintenance shall be carried out on all installed Injection Substation relays as may become
necessary in accordance with the manufacturers recommendation.
Substation Relays found to be inoperative during tests shall be replaced with relays with the
same or compatible characteristics.
Page 247 of 282
Chapter 10: Inspection Checks and Preventive Maintenance
10.1 Transmission Installation
All transmission installations shall be inspected after construction is completed before
energisation by NERC staff or appointed Inspectors. Confirmatory checks shall be made on
the following:
a. Conductor condition.
b. Conductor sag and clearance to ground, trees, and structures.
c. Insulator conditions.
d. Line hardware for roughness and tightness. Excess inhibitor found should be
removed from conductors to prevent corona discharges.
e. Structure vibration and alignment.
f. Guys for anchors that are pulling out, guy wire conditions, and missing guy guards.
g. Ground-wire connections and conditions.
h. Ground resistance at each structure.
i. Structure footings for washouts or damage.
j. Obstruction light operations for aircraft warning.
k. Transformers and instrument transformers
l. Circuit breakers
m. Clamps
n. Isolators
o. Re-gravelling of switchyard
p. Battery banks
q. Chargers
r. Protective panels
s. Lightning arrestors.
The preventive maintenance measures shall also take into cognizance the safety of persons
in accordance with the requirements of the Nigerian Electricity Health and Safety Code
2014.
The preventive maintenance checklist(s) shall include but not limited to the following
facilities, which are critical to system reliability:
a. Poles,
b. Overhead conductors,
c. Underground cables,
d. Transformers,
Page 248 of 282
e. Breakers,
f. Isolators,
g. Earthing Switch,
h. Auto Reclosure,
i. Sectionalisers,
j. Protective devices,
k. Substation premises.
A visual inspection of distribution lines and equipment shall be carried out periodically at
least once every six months to check for:
a. Broken insulators,
b. Broken/tilted poles,
c. Environmental Conditions that may adversely affect the overhead distribution
line,
d. Developing defects or abnormalities on equipment.
In the event of any test indicating failure to comply, that test and those preceding,
the results of which may have been influenced by the fault indicated, should be
repeated after the fault has been rectified.
Page 250 of 282
between the two cables that form the neutral conductor and between the two cables
that form the protective conductor.
b. The testing method in Clause 10.3.2.4.a above is only applicable when the ring
circuit has been inspected throughout, prior to the test, to ascertain that no
interconnection (multi-loops) exists on the ring circuit.
Page 251 of 282
iv. Where the circuits contain voltage sensitive devices, the test shall measure
the insulation resistance to earth with all live conductors (including the
neutral) connected together.
f. Where apparatus is disconnected for the test and the equipment has exposed
conductive parts required to be connected to protective conductors, the insulation
resistance between the exposed conductive parts and all live parts of the equipment
should be measured separately and should have a minimum insulation resistance
not less than 1 megaohm.
Page 252 of 282
10.3.2.9 Periodic inspections and tests
a. The results of a periodic inspection and test of an installation, or any part thereof,
shall be recorded on an inspection certificate and given by the contractor or by an
authorized person acting on his behalf, to the person ordering the inspection.
b. A notice of such durable material as to be likely to remain easily legible throughout
the life of the installation shall be fixed in a prominent position at or near the main
distribution board of every installation upon completion of the work. The notice shall
be inscribed in indelible characters no smaller than those here illustrated and shall
read as follows–
“IMPORTANT” –This installation should be periodically inspected and tested
and a report on its condition obtained, as prescribed in the Standard for
Electrical Installations.
Periodic inspection and tests of electrical installation shall be carried out and
recorded on an inspection certificate at intervals of not more than three
years.
(i) After having inspected and tested an installation the authorized inspector,
if satisfied that the work has been done in a workmanlike manner in
accordance with the requirements of these Standard and if the test made as
required by the foregoing provisions of this Part of these Standard have been
satisfied, shall certify in writing to the electricity/local electricity distribution
company that the installation has been duly inspected and tested and may be
safely connected with the source of supply.
Nothing in any such certificate shall relieve the owner or occupier of any
premises from the obligation to bring any installation into conformity with
these Standards if on any subsequent inspection any defects are discovered
which render such installation electrically hazardous.
Page 253 of 282
Chapter 11: Earthing
The earthing of all electrical equipment at Transmission networks shall be of solid type for
the purpose of protecting personnel and equipment installed at various locations from
lightning strikes, surges, static charges and for the discharge of fault current to earth in
accordance with the requirement of IEC 60364-5-54 and the provisions of the Nigerian
Code of Practise on Earthing (NCP 09).
For every installation operating at any voltage level, the installation earthing terminal shall
be provided adjacent to the equipment terminals. Throughout every circuit of such an
installation, an earth-continuity shall be provided and connected to the equipment earthing
terminals.
11.1.1
All metal work of wiring system (other than current-carrying parts), including cable sheathes
and armour, conduits, ducts, trunking, boxes, and catenary wires, shall be connected to
appropriate earth-continuity conductors.
11.1.2
11.1.3
11.1.4
At every lighting point with metal fitting, an earthing terminal shall be provided and
connected to the earth continuity conductor of the final sub-circuit.
11.1.5
An earthing terminal connected to the earth-continuity conductor of the final sub-circuit shall
be provided at every metal lighting switch position unless this takes the form of an earthed
metal box having a means of fitting the switch-plate in reliable electrical contact with the
box.
11.6.7
Isolated metal
(1) Where isolation of metal is adopted for the prevention of dangerous earth-leakage currents, it
shall be confined to the following items-
i. Short isolated lengths of metal used for the mechanical protection of cables having a
non-metallic sheath, other than over-head spans of conduit between buildings or conduit
used for protection of cables in circuits operating at voltages exceeding low voltage in
discharge-lighting installations.
ii. Metal clips used for fixing cables,
iii. Metal lamp caps,
iv. Small metal parts such as screws or name-plates isolated by insulating material,
v. Metal chains for the suspension of lighting fittings,
vi. Metal lighting fitting using filament lamps installed above a non-conducting floor and so
mounted, or so screened in non-conducting material, that they cannot readily be
touched by a person standing on or within reach of earthed metals.
vii. Catenary wires where insulated hangers are used
11.6.8. Bonding
1. The consumer’s earthing terminal shall be bonded to the metalwork of any public gas
services and any water services on the consumer’s premises in addition to the connection to the general
mass of the earth.
2. It shall be noted that before the consumer’s earthing terminal is bonded to the metalwork of
any gas or water service, connection of the earthing terminal to an effective means of earthing shall be
completed.
Page 255 of 282
11.6.9.
The bonding connections to any gas or water service shall be made as near as practicable to the
point of those services within the premises; provided that where there is an insulating section or
insert at that point, the connection shall be made to the metalwork on the consumer’s side of that
section or insert and, in the case of a gas service on the consumer’s side of the gas meter.
11.6.10
Copper bonding leads used in compliance with Clause 11.6.9 shall be of cross-sectional area not
less than the appropriate value shown in Table 11.1 subject to a minimum size of 6mm2. For the
purposes of this regulation, the associated circuit conductor shall be the largest conductor
connected into the input side of the consumer’s switchgear. Conductors of material other than
copper shall have a resistance not exceeding that of the prescribed copper conductor. Connections
to the pipes of other services shall be made by means of clamps.
TABLE 11.1
5 16
10 8
15 5.3
20 4
30 2.7
45 1.8
60 1.35
100 0.8
11.6.11
The exposed metalwork of all apparatus which is required by these Regulations to be earthed,
which might otherwise come into accidental contact with extraneous fixed metalwork shall be either
effectually segregated therefrom, or effectually bonded thereto so as to prevent appreciable voltage
differences at such possible points of contact. Copper bonding leads shall be of cross sectional
area not less than the appropriate value shown in Table 11.1, subject to a minimum of 1.5 mm2
Page 256 of 282
where the bonding lead is un-enclosed. Conductors of material, other than copper shall have
resistance not exceeding that of the prescribed copper conductor.
11.6.12
Bathrooms
In a room containing a fixed bath or shower cubicle, parts of a lamp-holder within a distance of 2.5
m from the bath or shower cubicle shall be constructed of, or shrouded in, insulating material.
Bayonet-type lamp-holders shall be fitted with a protective shield. As an alternative, totally enclosed
light fittings may be used.
11.6.13
Every switch or other means of electrical control or adjustment shall be located outside the inner
walls of a fixed bathroom normally inaccessible to a person using a fixed bath or shower. This
requirement does not apply to insulating cords or cord-operated switches. No stationary appliance
having elements, which can be touched, shall be installed within reach of a person using the bath
or shower.
11.6.14
In a room containing a fixed bath or shower, there shall be no socket-outlets and there shall be no
provision for connecting a portable appliance except for shavers supply unit. In a room containing a
fixed bath or shower, electric shavers shall be connected only by means of shaver supply unit
where the secondary circuit supplying the output sockets shall be isolated both from the supply
mains and from earths
11.6.15.
The earthing of the consumer’s installation shall be effected in such a manner that no fault of
negligible impedance to earthed metal shall be so sustained as to cause danger and shall be in
accordance with the appropriate requirements of these Regulations
11.6.16
Earth-leakage protection may be effected by means of fuses or, excess-current circuit breaker
provided the earth fault current so generated will operate the protective devise and so make the
faulty circuit dead exceeds–
Page 257 of 282
i. 3 times the current rating of any semi-enclosed fuse having a fusing factor exceeding 1.5,
used to protect the circuit (see Table 11.1). Or
ii. 2.4 times the rating of any cartridge fuse having a fusing factor not exceeding 1.5, used to
protect the circuit, or.
iii. 1.5 times the tripping current of any excess-current circuit breaker used to protect the
circuit.
11.6.17
Where the requirement of Clause 11.6.16 cannot be satisfied, earth-leakage protection shall
be provided by one or more earth-leakage circuit-breaker for all parts of an installation to which the
requirement of earthing applies, installation of the earth-leakage circuit-breakers shall satisfy the
test requirements of these provisions.
11.6.18
A current-operated earth-leakage circuit breaker shall be used only where the product of its
operating current in amperes and the earth-loop impedance in ohms does not exceed 40. Where
such a circuit breaker is used the consumer’s earthing terminal shall be connected to a suitable
electrode.
11.6.19
Every voltage-operated earth-leakage circuit breaker shall be arranged to have its operating
coil connected between the consumer’s earthing terminal (which may serve the whole or part of an
installation) and an earth electrode, the connecting lead shall be insulated.
11.6.20
The earth electrode used with any voltage-operated earth-leakage circuit breaker shall be
placed outside the resistance area of any parallel earth, which may exist, for example where a
water heater is installed. If by subdivision of the earthing system, discrimination in operation
between a number of voltage-operated earth-leakage circuit breakers is to be afforded, the
resistance areas of the associated earth electrodes shall not overlap.
11.6.21
Every conductor used, as an earth-continuity conductor shall satisfy the requirements stated
below–
i. Where the conductor forms part of the same cable as the associated circuit
conductors, other than a flexible cable or flexible cord, conductor shall comply with
the relevant requirements for the cables.
ii. Where the conductor is contained in a flexible cord, it shall have a cross-sectional
area not less than that of the largest associated current-carrying conductor,
Page 258 of 282
iii. Every cable sheath and/or armouring used as an earth-continuity conductor shall
satisfy the relevant requirements of standards mentioned in these Regulations;
iv. Conductors of copper other than those mentioned in items (i) to (iii) above, shall
have a cross-sectional area not less than the appropriate value shown in Table 11.2,
subject to a minimum of 1.5 mm2 where the conductor is unenclosed. Conductor of
material other than copper shall have a resistance not exceeding that of the
prescribed copper conductor.
11.6.22.
Installation
The installation of every earth-continuity conductor and earthing lead shall satisfy the
requirements stated below–
i. Every earth –continuity conductor of cross-sectional area 1.5 mm2 up to and including 6
mm2, other than copper strip, shall be protected throughout by installing at least
equivalent to that provided for a single-core, non-sheathed cable of appropriate size.
ii. Where the sheath of earth-continuity conductors is removed adjacent to joints and
terminations, earth-continuity conductors of cross-sectional area up to and including 6
mm2 shall be protected by installing slaving.
iv. Every bare earth-continuity conductor of the types other than copper strip shall be
identified at terminations as appropriate.
vi. Connections to cable sheaths and/or armouring, and to pipes, shall be soundly made by
soldered joints or by clamps. Every clamp shall be so installed as to provide reliable
connection without damage to the associated cable or pipe.
vii. Copper clad aluminum conductors shall not be used for bonding connections to water
pipes likely to be frequently subjected to condensations in normal use, or in other
situations where the terminations of the conductors are likely to be exposed to sustained
wet conditions. This requirement does not apply to terminations, which may be only
initially damp during building construction.
Pipe such as gas or water, or members of structural metalwork, shall not by themselves constitute
an earth-continuity conductor where this is necessary.
Page 259 of 282
11.6.24 Size of Earthing Conductors
The cross-sectional area of every copper conductor used as an earthing lead shall not be less than
that shown in Table 2 except that for connection of an earth-leakage circuit-breaker to an earth
electrode, where a cross-sectional area of 2.5 mm2 need not be exceeded. A maximum size of
copper conductor of 70 mm2 cross-sectional areas need not normally be exceeded except for the
earthing of a transformer neutral or electrode boiler. For the purpose of this regulation, the
associated circuit conductor shall be the largest conductor connected into the input side of the
consumer’s switchgear. Every conductor of material other than copper shall have a resistance not
exceeding that of the prescribed copper conductor. Copper-clad aluminum conductors shall not be
used for final connections to earth electrodes.
11.6.25
Every connection of an earthing lead to an earth electrode or other means of earthing shall be
readily accessible and soundly made by use of soldered joints or clamps: a permanent label
indelibly marked with the words “Safety Electrical Earth – DO NOT REMOVE”, in a legible type not
less than 4.75 mm high, shall be permanently fixed at the point of this connection.
11.6.26
Where protection against dangerous earth-leakage current by fuses or excess –current circuit
breakers is admissible, one of the following methods of earthing shall be employed–
i. Where the supply undertaking provides an earthing point which affords a metallic
return path to the means of earthing of the supply system, the earthing lead shall
connect the consumer’s earthing terminal to this point;
ii. Where a means of earthing has not been provided by the supply undertaking, the
consumer’s earthing terminal shall be connected by the earthing lead to an effective
earth electrode or electrodes, such as copper strip or rod, which shall be buried in
the ground at a position as near as practicable to the consumers earthing terminal
and shall satisfy the tests specified in Appendix 3.
11.6.27
The metalwork of public gas services and water services shall not be used as the sole earth
electrode of the installation.
153. If more than one plate or tubular earth electrode is employed for one earthing system they
shall be efficiently connected together.
11.6.28
Every fixed electric heating and cooking appliance shall for the purpose of earthing, be
provided with a suitable terminal to which the earthing lead shall be connected.
11.6.29
Page 260 of 282
In the case of fixed heating and cooking appliances and of motors of over 3.75 kW an
earthing lead other than the conduit shall be taken direct from the appliance or motor to the nearest
earth.
11.6.30
(1) Where the multiple-earthed neutral system is used, the earthing lead shall be taken from
the neutral bar or stud, and the conduit shall (in addition to being itself earthed) be connected to
this earthing lead.
(2) Save as provided in the last preceding paragraph the neutral wire of any system shall not be
used as an earthing lead.
11.6.31
Precautions in earthing
Pipes conveying gas, hot water, or an inflammable liquid shall not be used as an earthing system.
(i) Enclosure in insulation which is durable and substantially continuous, i.e., “all-insulated”
construction;
(iii) Earthing of exposed metal parts in accordance with the requirements of these
regulations;
(iv) Isolation of metal in such a way that is not liable to come into contact with live parts or
with earthed-metal.
Page 261 of 282
11.7.2
An earthing terminal, connected to the earth-continuity conductor, shall be provided at every outlet
point in the installation.
In situations accessible to livestock, a metal pipe or conduit shall not be used as a sole earth-
continuity conductor, though it may be used to supplement a separate earth-continuity conductor.
11.7.3
The earthing lead of an agricultural installation shall be adequately protected against disturbance or
damage by livestock or by mobile mechanical implements. Where the earthing lead is not enclosed
in conduit or equivalent mechanical protection, it shall be of the armoured type.
Protection against earth-leakage currents by isolation of metal-work, as provided for in items (i), (v),
and (vi) of Clause 11.6.7, is not recognized for agricultural and horticultural installations, unless the
metalwork is out of reach of livestock and is not liable to accidental contact with passing machinery,
implements or vehicles.
Metalwork (other than current-carrying parts) and one point of the secondary winding shall be
connected to the appropriate earth-continuity conductor, provided that these regulations shall not
apply to–
i. A transformer in which the windings are mounted on separate limbs of an earthed core or
are separated by an earthed metallic screen; or
ii. A double-insulated transformer; or
iii. The secondary winding of a “high-reactance’ transformer serving solely to energise a tesla
coil or the heating element of an electric discharge lamp;
iv. The secondary winding of a transformer in a shaver supply unit; or
v. A transformer which is an integral part of an item of apparatus, where the apparatus as a
whole is the subject of and complies with Nigerian Industrial Standards; or
a transformer used in welding installations designed in accordance with the requirements in
Nigerian Industrial Standards and NCP 9.
Page 262 of 282
1. Connections to earth
(1) Earthing connections and earth electrodes shall be of copper or galvanized steel.
(2) Stranded or circular earthing leads shall have a minimum copper equivalent cross-
sectional area of not less than 16 mm squared.
(3) Flat earthing leads shall have a minimum copper equivalent cross-sectional area of not less
than 50 mm squared and a minimum thickness of 3 mm.
(4) Earth electrodes shall be in the form of plates or rods of the following minimum sizes –
(6)The earthing requirements in regulation 73 shall be read in conjunction with the Nigerian
Code of Practice on Earthing NCP 9.
1. System earthing
(1) In medium voltage and low voltage alternating current systems the connection of circuit with
earth shall be made in accordance with the Nigerian Standard Code of Practice on Earthing (NCP
9) and the following requirements-
Page 263 of 282
a. the intermediate conductor of a medium or, low voltage three-wire single phase system, and
the neutral conductor of a medium three-phase four-wire system, shall be earthed in
multiple. That is, at the point of supply (the generating station, sub-station or transformer)
every fifth pole and the terminal poles of the distribution line. The consumer’s earth must
not be connected to the neutral conductor.
b. the resistance between any point of the intermediate or neutral conductor and earth shall
not exceed 2 ohms.
c. the neutral point of a medium voltage three-phase three-wire system shall be effectively
earthed at the point of supply.
(2) In high voltage three-phase alternating current systems, the connections of the circuit with
earth shall be made in accordance with Regulations 44 and 45.
(1)The neutral point shall be earthed at the point of supply. - That is, the generator neutral
point or the neutral point of the transformer secondary where change of voltage occurs - and it may
be earthed at any other point, provided that no interference of any description is caused by such
earthing.
(2) In the event of an appreciable harmonic current flowing in neutral connection such as to
cause interference with communication circuits generator or transformer neutral shall not be
earthed, but a suitable earthing transformer shall he used.
(3) In unattended generating stations or sub-stations supplying overhead lines earth leakage
relays shall be provided, so that in the event of a leak earth occurring either the faulty line will be
cut out or the whole of the system supplied from this station or sub-station rendered dead.
(4) These leakage relays if connected to individual feeders or lines shall be set to operate with
a time lag not exceeding five seconds with a current exceeding ten per cent of the full load rating of
the feeder or line, or, connected between the neutral point of the generator or transformer and
earth at a current not exceeding one ampere.
(5) Where under any conditions the use of earth leakage relays may be impracticable such
relays may, with the written consent of the NERC be omitted: (it is suggested that addition devices
be considered).
(6) In continuously attended generating stations or sub-stations a visual and audible indication
may be used to supplement the automatic disconnect of supply. In each case, immediate steps
shall be taken to remove the fault and disconnect the faulty feeder or line.
(1) In the case of delta connected systems or star-connected system with isolated neutrals
earthing transformers or other means approved by NERC shall be provided to give an artificial,
neutral point which shall be earthed. Earthing equipment shall be of sufficient capacity to ensure
the effective operation of the protective apparatus; simple leakage protection or indication shall be
provided for these systems as specified in Regulations 44(')) and 44(9) for systems with earthed
neutrals.
Page 264 of 282
(2) High Voltage single-phase systems derived from Delta or Star connected systems shall be
earthed in a manner approved by NERC.
(3) Where any part of supply system other than on a consumer premises, is normally
connected with earth, no switch, fuse, or circuit-breaker shall be Inserted in the earthed conductor
or in any conductor connected there and the connection with earth, shall be efficiently maintained
except when interrupted for the purpose of periodical tests.
(4) Notwithstanding anything contained in the last preceding clause, systems including more
than one generator operating in parallel may have the neutral conductor of a three-phase star-
connected generator disconnected when necessary to prevent the circulation of local currents
provided that where all the generators are located in one power- house, at least one generator in
operation shall have its neutral point connected to earth: provided further that where the generators
are contained in more than one power-house, and the power-houses are inter-connected, a neutral
point shall be provided at each power house and earthed and all such neutral points shall be so
arranged that no earthed- circulating current will flow between the power-stations.
(5) When the return current of any individual distribution transformer does not exceed two
amperes, and the transformer supplying the lines and any distribution transformer supplied by such
lines are not less than 10 km from any telephone exchange, the earth may, with the previous
consent in writing of the Telephone Operator, be used to carry the return current of the distribution
transformers.
(6) If the insulation of any circuit of any system is faulty, immediate steps shall be taken to
make good the insulation before the current is again placed in service.
Where an un-energised steel pole or structure is erected either as tower or for a purpose
arrangement shall be made to protect such structure from the effect of lightning strike by the
provision of protective earthing.
Street furniture includes permanently site lighting columns illuminated traffic signs, billboards and
other electrically supplied equipment.
Class I Construction, in which exposed conductive parts are connected to the earthing terminal
within the equipment.
Class II Construction, in which no provision is made for connection of exposed metallic parts of
the street furniture to earth with this form of construction, care should be taken to ensure that any
protective or PEN conductor in the supply cable has an insulated termination preventing contact
with or connection to the metallic parts of the street furniture.
TABLE 11.2
Page 265 of 282
Minimum sizes of copper earthing leads, copper bonding leads and copper earthing continuity
conductors not forming part of the same cable as the associated circuit conductors
Nominal cross
Nominal cross Nominal cross
sectional area of Nominal cross sectional
sectional area of sectional area of
largest associated area of earthing lead
earthing lead bonding lead
copper circuit conductor
conductor conductor
conductor
1 2 3 4
2 2 2 2
mm mm mm mm
4 6 2.5 1.0
6 6 2.5 1.0
10 6 6 2.5
16 6 6 2.5
25 16 16 6
35 16 16 6
50 16 16 6
70 50 50 16
95 50 50 16
120 50 50 16
150 50 50 16
185 70 70 50
240 70 70 50
300 70 70 50
400 70 70 50
500 70 70 50
630 70 70 50
Page 266 of 282
All towers shall be effectively earthed. The footing resistance of all towers shall be
measured by the Transmission Service Provider (TSP) in dry weather after completing
tower erection; but before stringing of earth wire. Tower footing resistance shall not exceed
2.0 Ohms. In areas of high resistivity counterpoise system shall be used.
a. The reduction in risk to persons during the transfer of fault energy and load
imbalance conditions,
b. The protection of equipment to operate satisfactorily under normal HV, MV, LV fault
conditions,
c. Minimize the risk of voltage stresses in excess of the equipment Basic Impulse Level
(BIL),
d. Meet the basic earthing value for;
11.4.1 Substations
Substation earthing shall be done for the purpose of connecting neutral point of
transformers, station auxiliary generators and non-current carrying metal parts, such
as structures, overhead shielding wires, tanks, frames to the earth mat so that Touch
and Step potentials within the Substation are in accordance with the relevant IEC
XXXXX.
Page 267 of 282
Chapter 12: Generation
12.1 Site Requirements
12.1.1 Site Approval
a. The Licensee before siting and commencement of construction of Power Plant
shall first obtain prior approval of the site by the Commission and other relevant
agencies as well as consent of the host community.
b. The licensee shall have a resettlement plan in case of involuntary resettlement
and/or displacement of the host community or affected Persons where applicable
or likelihood of occurrence.
12.1.2 Documentation
Every application for site approval by a licensee shall be accompanied by the
following documentation:
12.1.4 Hydrology
A Generation Licensee shall submit a detailed hydrological report to indicate that the
site will not be a subject of seasonal floods.
Page 268 of 282
12.2 Plant Design
a. General Design Considerations
Licensee (s) and/or Generation Companies shall submit to the Commission a detailed
engineering design of the power station based on applicable National and International
Engineering codes. The design will ensure that the Power plant when built is able to
generate its design capacity in a cost effective, reliable and safe manner with minimal
impact on the environment.
b. Plant Layout
Power plant arrangement will permit reasonable access for operation and maintenance
of equipment. Careful attention shall be given to the arrangement of equipment, valves,
mechanical specialties, and electrical devices so that rotors, tube bundles, inner valves,
top works, strainers, contactors, relays, and like items can be maintained or replaced
safely if and when necessary. Adequate platforms, stairs, handrails, and kickplates shall
be provided so that operators and maintenance personnel can function conveniently and
safely
a. Fuel Source: The type and availability to be indicated taking into account
environmental regulatory requirements that may affect fuel and fuel characteristics of
the plant.
b. Stack emissions: Electric power plant is to be designed with the type of stack gas
cleanup equipment which meets both Federal (Nigerian Environmental Standards
and Regulatory Agency – NESREA) and state emission requirements. For a solid
fuel fired boiler, this may involve an electrostatic precipitator or bag house for
particulate, and a scrubber for sulphur compounds unless fluidized bed combustion
is employed. Boiler design will be specified.
c. Waste Disposal: For electric generating stations utilizing solid fuel, both solid and
liquid wastes will be handled and disposed off in an environmentally acceptable
manner. The wastes can be categorized generally as follows:
i. Solid wastes. These include both bottom ash and fly ash from boilers.
ii. Liquid wastes. These include boiler blowdown, cooling tower blowdown, acid
and caustic water treating wastes, coal pile runoff, and various contaminated
wastes from chemical storage areas, sanitary sewage and yard areas.
Page 269 of 282
12.2.1 Technical Documentation
a. Applicants shall submit the following technical documentation to NERC for
approval for the issuance of a construction permit
i. Site Survey Plan
ii. Soil Investigations
iii. EIA
iv. Site Layout Plan
v. Listing and Specifications of major equipment
vi. Construction Plan
b. Construction schedule
i. Engineering Drawings
a. Comply with all applicable sections of the National Building code as well as
Federal, State and Local Government Building and Environmental Health and
Safety Regulations and procedures.
b. Ensure that all workers are fully qualified and/or certified with respect to
mandated Environmental Health and Safety training as required by legislation
and the relevant Codes and regulations;
c. Provide Environmental Health and Safety documentation required under this
regulations to the Project Manager;
d. Provide all necessary Environmental Health and Safety equipment, including
Personal Protection Equipment, as required for safe execution of work;
e. Comply with the Environmental Health and Safety Regulations and Directives
Performance Requirements for Power Stations given by the Commission;
f. Record and report all incidents, injuries and accidents to the Environmental
Health and Safety Coordinator within 24 hours of the accident/incident;
g. Stop work if the conditions are such that work cannot be performed safely;
iv. Procedure to identify the need for, and for the preparation of, written work
procedures to implement Environmental Health and Safety practices,
including practices required by the Act and other relevant regulations;
vi. Procedure and process for issuing and cancelling work permits;
viii. A system for the recognition, evaluation, and control of hazards that
includes a means of evaluation and monitoring of the workplace to
Page 271 of 282
identify potential hazards and the associated risks; procedures and
schedules for regular inspections by management and committee
members; procedures for the identification, reporting, and control or
correction of hazards; and procedures for the prompt investigation of
hazardous occurrences to determine the cause for the occurrence and
the actions necessary to prevent a recurrence;
ix. A plan for the control of biological, radioactive and chemical substances
handled, used, stored, produced, or disposed of at the workplace;
xiii. A short Environmental Health and Safety induction exercise for all
visitors.
e. A weekly ‘’Toolbox Meeting” shall be conducted for all contracts. The Agenda
shall include, but not be limited to the following:
Page 272 of 282
iv. Reporting of Environmental Health and Safety incidents and injuries;
b. The induction process shall be based on the critical nature of the work and
shall specify the Environmental Health and Safety procedures and
guidelines.
d. The Induction program shall discuss Environmental Health and Safety Issues
which shall include but not be limited to the following subjects:
xiii. Housekeeping
a. Lockout/ Tagout
b. Excavation/Trenching procedures
h. Site Isolation
i. Fall Protection
m. Site Housekeeping
Page 274 of 282
q. Emergency exit from site
r. Asbestos
s. Smoking
t. Fire protection
w. First Aid
y. Chemical/Material handling
z. Machine guarding
Boiler Misc.
Parameter Fresh Brackish*
Feedwater Uses
Silica <50 <25 <0.21 -
Aluminium NS NS <0.01 -
Iron NS NS <0.01 <1.0
Manganese NS NS <0.01 -
Calcium <200 <420 <0.01 -
Mangnesium NS NS <0.01 -
Ammonia NS NS <0.07 -
Bicarbonate <600 <140 <0.5 -
Sulphate <680 <2700 NS -
Chloride <600 <19000 NS -
Dissolved solids <1000 <35000 <0.5 1000
Copper NS NS <0.01 -
Hardness <850 <6260 <0.07 -
Zinc NS NS <0.01 -
Alkalinity (as CaCo3) 500 <115 <1 -
pH unit 5.0-8.3 6.0-8.3 8.8-9.4 5.0-9.0
Organic material Methylene blue active
substances NS NS <0.1 <10
Carbon tetrachloride extract <NS NS NS <10
Chemical Oxygen Demand (COD) <75 <75 <1.0 -
Dissolved oxygen - - <0.007 -
Total suspended solids <500 <2500 <0.05 <5
Note:
* = Brackish water- dissolved solids more than 1000 mg/l
Page 275 of 282
NS = No Specification
Source: Guidelines and Standards for Environmental Protection in Nigeria, 1991
a. Particulates
Table 12.2 below specifies the National emission limits for particulates from
combustion of various fuels.
For all Power plants or units, PM emissions (all sizes) during construction shall not
exceed 500 mg/m3
Table 12.2: Emission Limits for Air Particulates from Stationary Sources
ii. Nitrogen oxides. The specific emissions of nitrogen oxides shall not exceed
500 µg/m3 during construction.
iv. Volatile Organic Carbon (VOC): Total emissions of VOC during construction
shall not exceed 6000 µg/m3.
Page 276 of 282
CO 5000
H2S 30
VOC 6000
Source: Guidelines and Standards for Environmental Protection in Nigeria, 1991
c. Liquid Effluent
Parameters mg/l
Page 277 of 282
d. Also, thermal power plants shall comply during construction with the guidelines
listed below.
Parameter Value
pH 6–9
Total Suspended Solids 50 mg/l
Oil and Grease 10 mg/l
Chromium (total) 0.5 mg/l
Total Residual Chlorine 0.2 mg/l
Copper 0.5 mg/l
Iron 1.0 mg/l
Zinc 1.0 mg/l
Polychlorinated Biphenyl ( PCB) 0.003 mg/l
Mercury 0.05 mg/l
o
Temperature Increase 3 C
Source: Pollution Prevention and Abatement Handbook, World Bank, 1998
Day Night
Residential 60 40
Commercial 75 50
Industrial 85 65
Page 278 of 282
Time Frame:
Day: 6.00 a.m. – 10.00 p.m.
Night: 10.00 p.m. – 6.00 a.m.
The time frame takes into consideration human activity.
Source: The National Environment (Noise Standards and control) Regulations 2003
140 100
Source: The National Environment (Noise Standards and Control) Regulations 2003
The maximum permissible level for impact noise during construction is given in
Table 12.7 above.
The noise level at receptors close to a Power Plant shall not exceed the limits
indicated in Table 12.8 below at any time.
E. Industrial 70 60
12.4.5 Technical Criteria for Plant and Apparatus at the Inter ‐ Connection Point
a. Generator Installations:
Page 280 of 282
Technical facilities must be installed on all Generator networks to provide the
following information to the responsible Control Centre:
i. Status indications of circuit breaker, isolator switches, and earth switches
in so far as they are required for operation of the network.
ii. Measurement of Active and Reactive power flow in both the import and
export directions, as well as voltages and frequency.
iii. Where applicable, reference values for control (activation/deactivation of
primary/ secondary control) and instantaneous Demand value of the
secondary control.
iv. Reference value of the Reactive Power in the form of the schedule or as
an instantaneous value (e.g. for voltage and Reactive Power control).
v. Critical protection information.
b. Generator Control Centre:
c. The control centre of each Generator shall provide the facilities to effectively
schedule the power interchange with the control centre of the interconnected
network.
iv. The active power output under steady state conditions of any Generating
Unit directly connected to the transmission network should not be
affected by voltage changes in the normal operating range. The Reactive
Power output of a Generating Unit having a synchronous alternator must,
under steady state conditions, be fully available within the voltage range
± 10% of nominal voltage at the connection point.
vi. A steam – turbine or gas – turbine Generating Unit which has been
synchronized must be capable of ramping up pursuant to a Dispatch
instruction at a rate of at least 3% Gas cooling rate (GCR) per minute. A
Page 281 of 282
steam – turbine or gas – turbine Generating Unit must be capable of de-
loading at a rate of at least 3% Gas cooling rate (GCR) per minute.
b. Power Producers shall be responsible for protecting all their Generating Units
against damage should system frequency variations exceed 51.5Hz or go below
47.5Hz. In the event that such variations occur, the Power Producer shall
disconnect the Generating Unit for reasons of safety of personnel, apparatus,
and/or plant.
c. All Power Stations shall meet the performance requirements as contained in Part
3 Section 4 of the Grid Code in respect of Turbine Controllers and Automatic
Voltage Regulators.
Page 282 of 282