SIMOPS Plan Rev.2
SIMOPS Plan Rev.2
SIMOPS Plan Rev.2
16-Mar-20
17-Mar-20
18-Mar-20
19-Mar-20
Unit-10 SIMOPS
spool removal and +ve isolation for E-02 to start first then move to E-01/03 , cutting of outlet line to start after spool removal of E-02 and at E-02 side , No interference between two activities in the
SIMOPS-2 E-02 outlet line cutting X spool removal and +ve isolation
same skid
swapping of E-02 will cross the crane utilized for E-02 outlet line cutting , So during the E-02 swapping agreed with PMT to stop the lifting activities for outlet line cutting and to be resumed after
SIMOPS-3 E-02 outlet line cutting X cold box swapping
completing the E-02 swapping
two activities in the same area using two cranes , E-01/03 spools assembly lifting activities to be conducted at E-01/03 side while the lifting activities for E-02 outlet line welding conducted at E-02 side , So two
SIMOPS-4 E-02 , E01/03 spools assembly X E-02 outlet line welding
cranes can be utilizied separately , in case welding lifting activities for E-02 oulet line will cross spools assembly , the periorty for E-02 outlet line welding lifting activities
two activities in the same area using two cranes , samrt layer flare line lifting activities to be conducted at E-01/03 side while the lifting activities for E-02 outlet line conducted at E-02 side , So two
SIMOPS-5 Smart layer flare line X E-02 outlet line welding
cranes can be utilizied separately , in case lifting activities for E-02 oulet line will cross flare line lifting activities , the periorty for E-02 outlet line welding lifting activities
the comp. discharge line cold cut will be prior to expander removal so the lifting operation for Comp. modification doesn’t cross the expander lifting , the only interferance during expander instllation and
SIMOPS-7 Comp. discharge line modification X expander MCS replacement
one flange welding of removed elbow , Maint. To complet expa. lifting and placed in its location then both team working for elbow alignment and welding
SIMOPS-8 CPC manual valves replacment X manual valve of 10-PSV-36 replacement both tasks needed crane and lifting operation , planning to separat the two tasks not to be implemnted in the same time as the crane should mounted in the same position / area
SIMOPS-9 check valve replacement for 40-X-01 unitA/B X Bundle unit B replacement check valve will replace for Turbine A while bundle of unit B replaced , No multiple lifting for the same unit in the same time
SIMOPS-10 plant boundary modification X bundle replacement of Unit B location of modification is far than Bundle replacement and check valve replacement
20-Mar-20
March SD SIMOPS Plan
21-Mar-20
22-Mar-20
Main. Main. Main. Main. Main. Main. Main. Main. Main. Main. Main. Main.
PMT PMT PMT PMT PMT PMT PMT PMT PMT PMT PMT PMT
March SD SIMOPS Plan
23-Mar-20
24-Mar-20
25-Mar-20
26-Mar-20
27-Mar-20
28-Mar-20
29-Mar-20
30-Mar-20
31-Mar-20
1-Apr-20
PMT PMT PMT PMT
Maint. Maint. Maint. Maint. Maint. Maint. Maint. Maint. Maint. Maint. Maint. Maint.
3-Apr-20
2-Apr-20
No.
SIMOPS-1
SIMOPS-2
SIMOPS-3
SIMOPS-4
SIMOPS-5
SIMOPS-6
SIMOPS-7
SIMOPS-8
SIMOPS-9
SIMOPS-10
SIMOPS Description Unit
insulation works to start for E-02 before mechanical work then moved to E-01/03 , while insulation works at E-01/03
spool removal and +ve isolation for E-02 to start first then move to E-01/03 , cutting of outlet line to start after spool
swapping of E-02 will cross the crane utilized for E-02 outlet line cutting , So during the E-02 swapping agreed with
two activities in the same area using two cranes , E-01/03 spools assembly lifting activities to be conducted at E-01
separately , in case welding lifting activities for E-02 oulet line will cross spools assembly , the periorty for E-02 outle
tw activities in the same area using two cranes , smart layer flare line lifting activities to be conducted at E-01/03 sid
case lifting activities for E-02 outlet line will cross flare line lifting activities , the priority for E-02 outlet line welding lift
perlite filling activities to focused on night shift and during the day shift to be in other side of mechanical activities (i.e
the comp. discharge line cold cut will be prior to expander removal so the lifting operation for Comp. modification do
elbow , Main. To complete expa. lifting and placed in its location then both team working for elbow alignment and we
both tasks needed crane and lifting operation , planning to separate the two tasks not to be implemented in the sam
check valve will be eplaced for Turbine A while bundle of unit B being replaced , No multiple lifting for the same unit
location of modification is far than Bundle replacement and check valve replacement
er
Precautions and Mitigations
ation works at E-01/03 , mechanical works start at E-02 , No interference between two activities in the same skid
ne to start after spool removal of E-02 and at E-02 side , No interference between two activities in the same skid
swapping agreed with PMT to stop the lifting activities for outlet line cutting and to be resumed after completing the E-02 swapp
be conducted at E-01/03 side while the lifting activities for E-02 outlet line welding conducted at E-02 side , So two cranes can
e periorty for E-02 outlet line welding lifting activities
nducted at E-01/03 side while the lifting activities for E-02 outlet line conducted at E-02 side , So two cranes can be utilized sep
2 outlet line welding lifting activities
echanical activities (i.e. filling for E-01/03 while mechanical actives on E-02 and Vis versa
Comp. modification doesn’t cross the expander lifting , the only interference during expander installation and one flange welding
bow alignment and welding
plemented in the same time as the crane should mounted in the same position / area
fting for the same unit in the same time , for unit B check valve replacement to be done after Crane 200 ton complet lifting
action By
PMT / process
Miantenance / process
200 ton complet lifting Hallibrtun / Maint. / process