Report Continuity Megger Test

This document contains an insulation and continuity test report for electrical power cables used in the Oyong Development Project Phase II - Onshore Processing Facilities (OPF) GRATI. The report includes information about the project name, customer, equipment tested, test results, and instrument details. Insulation and continuity tests were performed on cable numbers between various pieces of equipment to test resistance between conductors and grounding.

Uploaded by

sugeng wahyudi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
100 views9 pages

Report Continuity Megger Test

This document contains an insulation and continuity test report for electrical power cables used in the Oyong Development Project Phase II - Onshore Processing Facilities (OPF) GRATI. The report includes information about the project name, customer, equipment tested, test results, and instrument details. Insulation and continuity tests were performed on cable numbers between various pieces of equipment to test resistance between conductors and grounding.

Uploaded by

sugeng wahyudi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 9

ELECTRICAL POWER CABLE

INSULATION AND CONTINUITY TEST REPORT


SANTOS (SAMPANG) PTY LTD PT. PAL INDONESIA
Project Name : Oyong Development Project Phase II - Onshore Processing Facilities (OPF) GRATI
Customer : SANTOS (Sampang) Pty. Ltd. E03CT
Drawing No. / Rev : System / Subsystem No. :
Single Line No. / Rev : System Description :
Location : Sub System Description :

ORIGINAL TERMINATION
INSULATION TESTS (M. ohm) CONTINUITY TEST VOLTAGE
No. CABLE NUMBER CABLE SIZE (FROM) (TO)
TEST (Volt DC)
EQUIPMENT EQUIPMENT R-S R-T S-T R-G S-G T-G

INSTRUMENT DETAIL
Equipment Name Serial No. Type Description Prepared By Witnessed / Approved By Witnessed / Approved By
Insulation Continuity Tester W0203197 KYORITSU 3005A Company

Notes :
Signature

Print Name
Date
ELECTRICAL POWER CABLE
INSULATION AND CONTINUITY TEST REPORT
SANTOS (SAMPANG) PTY LTD PT. PAL INDONESIA
Project Name : Oyong Development Project Phase II - Onshore Processing Facilities (OPF) GRATI
Customer : SANTOS (Sampang) Pty. Ltd. E03CT
Drawing No. / Rev : System / Subsystem No. :
Single Line No. / Rev : System Description :
Location : Sub System Description :

ORIGINAL TERMINATION
INSULATION TESTS (M. ohm) CONTINUITY TEST VOLTAGE
No. CABLE NUMBER CABLE SIZE (FROM) (TO)
TEST (Volt DC)
EQUIPMENT EQUIPMENT R-S R-T S-T R-G S-G T-G
ELECTRICAL POWER CABLE
INSULATION AND CONTINUITY TEST REPORT
SANTOS (SAMPANG) PTY LTD PT. PAL INDONESIA
Project Name : Oyong Development Project Phase II - Onshore Processing Facilities (OPF) GRATI
Customer : SANTOS (Sampang) Pty. Ltd. E03CT
Drawing No. / Rev : System / Subsystem No. :
Single Line No. / Rev : System Description :
Location : Sub System Description :

ORIGINAL TERMINATION
INSULATION TESTS (M. ohm) CONTINUITY TEST VOLTAGE
No. CABLE NUMBER CABLE SIZE (FROM) (TO)
TEST (Volt DC)
EQUIPMENT EQUIPMENT R-S R-T S-T R-G S-G T-G

INSTRUMENT DETAIL
Equipment Name Serial No. Type Description Prepared By Witnessed / Approved By Witnessed / Approved By
Insulation Continuity Tester W0203197 KYORITSU 3005A Company

Notes :
Signature

Print Name
Date
ELECTRICAL POWER CABLE
INSULATION AND CONTINUITY TEST REPORT
SANTOS (SAMPANG) PTY LTD PT. PAL INDONESIA
Project Name : Oyong Development Project Phase II - Onshore Processing Facilities (OPF) GRATI
Customer : SANTOS (Sampang) Pty. Ltd. E03CT
Drawing No. / Rev : System / Subsystem No. :
Single Line No. / Rev : System Description :
Location : Sub System Description :

ORIGINAL TERMINATION
INSULATION TESTS (M. ohm) CONTINUITY TEST VOLTAGE
No. CABLE NUMBER CABLE SIZE (FROM) (TO)
TEST (Volt DC)
EQUIPMENT EQUIPMENT R-S R-T S-T R-G S-G T-G
ELECTRICAL POWER CABLE
INSULATION AND CONTINUITY TEST REPORT
SANTOS (SAMPANG) PTY LTD PT. PAL INDONESIA
Project Name : Oyong Development Project Phase II - Onshore Processing Facilities (OPF) GRATI
Customer : SANTOS (Sampang) Pty. Ltd. E03CT
Drawing No. / Rev : 9820-62-105 (SHT No. 1 Of 3) / Rev.0 System / Subsystem No. :
Single Line No. / Rev : 9820-61-113 / Rev.1 System Description :
Location : Electrical / Instrument CCR Building Sub System Description :

ORIGINAL TERMINATION
INSULATION TESTS (M. ohm) CONTINUITY TEST VOLTAGE
No. CABLE NUMBER CABLE SIZE (FROM) (TO)
TEST (Volt DC)
EQUIPMENT EQUIPMENT R-S R-T S-T R-G S-G T-G
9820-NLDB-101
1 9820-NLDB101-L001 3/C+E #14AWG NLDB101-01-JB-01 >200 >200 >200 >200 >200 >200 OK 500
(CCT-01)
9820-NLDB101-L002 3/C+E #14AWG NLDB101-01-JB-01 SW2 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L003 3/C+E #14AWG NLDB101-01-JB-01 NLDB101-01S2-01 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L004 3/C+E #14AWG NLDB101-01S2-01 NLDB101-01S2-03 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L005 3/C+E #14AWG NLDB101-01-JB-01 NLDB101-01S2-05 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L006 3/C+E #14AWG NLDB101-01S2-05 NLDB101-01S2-02 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L007 3/C+E #14AWG NLDB101-01S2-02 NLDB101-01S2-04 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB-101
2 9820-NLDB101-L022 3/C+E #14AWG NLDB101-02-JB-01 >200 >200 >200 >200 >200 >200 OK 500
(CCT-02)
9820-NLDB101-L023 3/C+E #14AWG NLDB101-02-JB-01 SW8 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L024 3/C+E #14AWG NLDB101-02-JB-01 NLDB101-02-JB-02 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L025 3/C+E #14AWG NLDB101-02-JB-02 NLDB101-02S8-02 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L026 3/C+E #14AWG NLDB101-02-JB-02 NLDB101-02S8-03 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L027 3/C+E #14AWG NLDB101-02-JB-02 NLDB101-02S8-04 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L028 3/C+E #14AWG NLDB101-02-JB-01 NLDB101-02-JB-03 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L029 3/C+E #14AWG NLDB101-02-JB-03 SW7 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L030 3/C+E #14AWG NLDB101-02-JB-03 NLDB101-02S7-01 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L031 3/C+E #14AWG NLDB101-02-JB-03 NLDB101-02-JB-04 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L032 3/C+E #14AWG NLDB101-02-JB-04 SW16 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L033 3/C+E #14AWG NLDB101-02-JB-04 NLDB101-02S16a-07 >200 >200 >200 >200 >200 >200 OK 500
NLDB101-02S16b-05
9820-NLDB101-L034 & L035 3/C+E #14AWG NLDB101-02-JB-04 >200 >200 >200 >200 >200 >200 OK 500
NLDB101-02S16b-06
9820-NLDB-101
3 9820-NLDB101-L038 3/C+E #14AWG NLDB101-03-JB-01 >200 >200 >200 >200 >200 >200 OK 500
(CCT-03)
9820-NLDB101-L039 3/C+E #14AWG NLDB101-03-JB-01 SW10 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L040 3/C+E #14AWG NLDB101-03-JB-01 NLDB101-03-JB-02 >200 >200 >200 >200 >200 >200 OK 500
INSTRUMENT DETAIL
Equipment Name Serial No. Type Description Prepared By Witnessed / Approved By Witnessed / Approved By
Insulation Continuity Tester W0203197 KYORITSU 3005A Company

Notes :
Signature

Print Name
Date
ELECTRICAL POWER CABLE
INSULATION AND CONTINUITY TEST REPORT
SANTOS (SAMPANG) PTY LTD PT. PAL INDONESIA
Project Name : Oyong Development Project Phase II - Onshore Processing Facilities (OPF) GRATI
Customer : SANTOS (Sampang) Pty. Ltd. E03CT
Drawing No. / Rev : 9820-62-105 (SHT No. 1 Of 3) / Rev.0 System / Subsystem No. :
Single Line No. / Rev : 9820-61-113 / Rev.1 System Description :
Location : Electrical / Instrument CCR Building Sub System Description :

ORIGINAL TERMINATION
INSULATION TESTS (M. ohm) CONTINUITY TEST VOLTAGE
No. CABLE NUMBER CABLE SIZE (FROM) (TO)
TEST (Volt DC)
EQUIPMENT EQUIPMENT R-S R-T S-T R-G S-G T-G

9820-NLDB101-L041 3/C+E #14AWG NLDB101-03-JB-02 NLDB101-03S10-03 >200 >200 >200 >200 >200 >200 OK 500

9820-NLDB101-L042 3/C+E #14AWG NLDB101-03-JB-02 NLDB101-03S10-04 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L043 3/C+E #14AWG NLDB101-03-JB-02 NLDB101-03-JB-03 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L044 3/C+E #14AWG NLDB101-03-JB-03 NLDB101-03S10-01 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L045 3/C+E #14AWG NLDB101-03-JB-03 NLDB101-03S10-02 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L046 3/C+E #14AWG NLDB101-03-JB-01 NLDB101-03S10-05 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB-101
4 9820-NLDB101-L048 3/C+E #14AWG NLDB101-04-JB-01 >200 >200 >200 >200 >200 >200 OK 500
(CCT-04)
9820-NLDB101-L049 3/C+E #14AWG NLDB101-04-JB-01 SW13 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L050 3/C+E #14AWG NLDB101-04-JB-01 NLDB101-04S13-01 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L051 3/C+E #14AWG NLDB101-04-JB-01 NLDB101-04-JB-02 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L052 3/C+E #14AWG NLDB101-04-JB-02 NLDB101-04S13-02 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L053 3/C+E #14AWG NLDB101-04-JB-02 NLDB101-04S13-03 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L054 3/C+E #14AWG NLDB101-04-JB-02 NLDB101-04-JB-03 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L055 3/C+E #14AWG NLDB101-04-JB-03 NLDB101-04S13-04 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L056 3/C+E #14AWG NLDB101-04-JB-03 NLDB101-04S13-05 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L057 3/C+E #14AWG NLDB101-04-JB-03 NLDB101-04S13-06 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB-101
5 9820-NLDB101-L093 3/C+E #14AWG NLDB101-05-JB-01 >200 >200 >200 >200 >200 >200 OK 500
(CCT-05)
9820-NLDB101-L094 3/C+E #14AWG NLDB101-05-JB-01 SW17 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L095 3/C+E #14AWG NLDB101-05-JB-01 NLDB101-05S17-02 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L096 3/C+E #14AWG NLDB101-05S17-02 NLDB101-05-JB-02 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L097 3/C+E #14AWG NLDB101-05-JB-02 NLDB101-05S17-04 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L098 3/C+E #14AWG NLDB101-05-JB-02 NLDB101-05S17-03 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L099 3/C+E #14AWG NLDB101-05S17-03 NLDB101-05S17-01 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L100 NLDB101-05-JB-01 NLDB101-05-JB-03 >200 >200 >200 >200 >200 >200 OK 500
INSTRUMENT DETAIL
Equipment Name Serial No. Type Description Prepared By Witnessed / Approved By Witnessed / Approved By
Insulation Continuity Tester W0203197 KYORITSU 3005A Company

Notes :
Signature

Print Name
Date
ELECTRICAL POWER CABLE
INSULATION AND CONTINUITY TEST REPORT
SANTOS (SAMPANG) PTY LTD PT. PAL INDONESIA
Project Name : Oyong Development Project Phase II - Onshore Processing Facilities (OPF) GRATI
Customer : SANTOS (Sampang) Pty. Ltd. E03CT
Drawing No. / Rev : 9820-62-105 (SHT No. 1 Of 3) / Rev.0 System / Subsystem No. :
Single Line No. / Rev : 9820-61-113 / Rev.1 System Description :
Location : Electrical / Instrument CCR Building Sub System Description :

ORIGINAL TERMINATION
INSULATION TESTS (M. ohm) CONTINUITY TEST VOLTAGE
No. CABLE NUMBER CABLE SIZE (FROM) (TO)
TEST (Volt DC)
EQUIPMENT EQUIPMENT R-S R-T S-T R-G S-G T-G
9820-NLDB101-L101 NLDB101-05-JB-03 SW5 >200 >200 >200 >200 >200 >200 OK 500
9820-NLDB101-L102 NLDB101-05-JB-03 NLDB101-05S5-05 >200 >200 >200 >200 >200 >200 OK 500

INSTRUMENT DETAIL
Equipment Name Serial No. Type Description Prepared By Witnessed / Approved By Witnessed / Approved By
Insulation Continuity Tester W0203197 KYORITSU 3005A Company

Notes :
Signature

Print Name
Date
ELECTRICAL POWER CABLE
INSULATION AND CONTINUITY TEST REPORT
SANTOS (SAMPANG) PTY LTD PT. PAL INDONESIA
Project Name : Oyong Development Project Phase II - Onshore Processing Facilities (OPF) GRATI
Customer : SANTOS (Sampang) Pty. Ltd. E03CT
Drawing No. / Rev : 9820-62-106 (SHT No. 1 Of 3) / Rev.0 System / Subsystem No. :
Single Line No. / Rev : 9820-61-115 / Rev.1 System Description :
Location : Sub System Description :

ORIGINAL TERMINATION
INSULATION TESTS (M. ohm) CONTINUITY TEST VOLTAGE
No. CABLE NUMBER CABLE SIZE (FROM) (TO)
TEST (Volt DC)
EQUIPMENT EQUIPMENT R-S R-T S-T R-G S-G T-G
9820-ELDB-101
1 9820-ELDB101-L001 3/C+E #14AWG ELDB101-01-JB-01 >200 >200 >200 >200 >200 >200 OK 500
(CCT-01)
9820-ELDB101-L002 3/C+E #14AWG ELDB101-01-JB-01 SW6 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L003 3/C+E #14AWG ELDB101-01-JB-01 ELDB101-01S6-01 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L004 3/C+E #14AWG ELDB101-01-JB-01 ELDB101-01-JB-02 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L005 3/C+E #14AWG ELDB101-01-JB-02 SW1 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L006 3/C+E #14AWG ELDB101-01-JB-02 ELDB101-01S1-01 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L007 3/C+E #14AWG ELDB101-01-JB-02 ELDB101-01-JB-03 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L008 3/C+E #14AWG ELDB101-01-JB-03 SW3 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L009 3/C+E #14AWG ELDB101-01-JB-03 ELDB101-01S3-01 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB-101
2 9820-ELDB101-L022 3/C+E #14AWG ELDB101-02-JB-01 >200 >200 >200 >200 >200 >200 OK 500
(CCT-02)
9820-ELDB101-L023 3/C+E #14AWG ELDB101-02-JB-01 SW9 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L024 3/C+E #14AWG ELDB101-02-JB-01 ELDB101-02S9-01 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L025 3/C+E #14AWG ELDB101-02-JB-01 ELDB101-02-JB-02 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L026 3/C+E #14AWG ELDB101-02-JB-02 ELDB101-02S9-02 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L027 3/C+E #14AWG ELDB101-02-JB-02 ELDB101-02S9-03 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB-101
3 9820-ELDB101-L030 3/C+E #14AWG ELDB101-03-JB-01 >200 >200 >200 >200 >200 >200 OK 500
(CCT-03)
9820-ELDB101-L031 3/C+E #14AWG ELDB101-03-JB-01 SW11 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L032 3/C+E #14AWG ELDB101-03-JB-01 ELDB101-03S11-01 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L033 3/C+E #14AWG ELDB101-03-JB-01 ELDB101-03-JB-02 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L034 3/C+E #14AWG ELDB101-03-JB-02 ELDB101-03S11-02 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L035 3/C+E #14AWG ELDB101-03-JB-02 ELDB101-03S11-03 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L036 3/C+E #14AWG ELDB101-03-JB-02 ELDB101-03S11-04 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB-101
4 9820-ELDB101-L039 3/C+E #14AWG ELDB101-04-JB-01 >200 >200 >200 >200 >200 >200 OK 500
(CCT-04)
INSTRUMENT DETAIL
Equipment Name Serial No. Type Description Prepared By Witnessed / Approved By Witnessed / Approved By
Insulation Continuity Tester W0203197 KYORITSU 3005A Company

Notes :
Signature

Print Name
Date
ELECTRICAL POWER CABLE
INSULATION AND CONTINUITY TEST REPORT
SANTOS (SAMPANG) PTY LTD PT. PAL INDONESIA
Project Name : Oyong Development Project Phase II - Onshore Processing Facilities (OPF) GRATI
Customer : SANTOS (Sampang) Pty. Ltd. E03CT
Drawing No. / Rev : 9820-62-106 (SHT No. 1 Of 3) / Rev.0 System / Subsystem No. :
Single Line No. / Rev : 9820-61-115 / Rev.1 System Description :
Location : Sub System Description :

ORIGINAL TERMINATION
INSULATION TESTS (M. ohm) CONTINUITY TEST VOLTAGE
No. CABLE NUMBER CABLE SIZE (FROM) (TO)
TEST (Volt DC)
EQUIPMENT EQUIPMENT R-S R-T S-T R-G S-G T-G
9820-ELDB101-L040 3/C+E #14AWG ELDB101-04-JB-01 SW12 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L041 3/C+E #14AWG ELDB101-04-JB-01 ELDB101-04-JB-02 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L042 3/C+E #14AWG ELDB101-04-JB-02 ELDB101-04S12a-02 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L043 3/C+E #14AWG ELDB101-04-JB-02 ELDB101-04S12a-03 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L044 3/C+E #14AWG ELDB101-04-JB-02 ELDB101-04S12a-04 >200 >200 >200 >200 >200 >200 OK 500
9820-ELDB101-L045 3/C+E #14AWG ELDB101-04-JB-01 ELDB101-04S12b-01 >200 >200 >200 >200 >200 >200 OK 500

INSTRUMENT DETAIL
Equipment Name Serial No. Type Description Prepared By Witnessed / Approved By Witnessed / Approved By
Insulation Continuity Tester W0203197 KYORITSU 3005A Company

Notes :
Signature

Print Name
Date