Bridges, Cofferdams and Caissons A Bridge: Is A Structure Which Provides Passage Facilities Over An Obstacle
Bridges, Cofferdams and Caissons A Bridge: Is A Structure Which Provides Passage Facilities Over An Obstacle
Culverts: These are small bridges construction to cross small stream. Types of
culvert: (1) Box culvert: for larger spans and in loose soil. It can be rectangular
or square formed from reinforced concrete precast unit. (2) Ring culvert: This
has similar properties as box culvert. (3) Pipe culvert: This consists of one or
more pipes placed side by side below the embankment of the road or railway.
(4) Slab culvert: This consists of placing a reinforced concrete slab directly as
simply supported beam or piers or abutments.
COFFERDAMS
Cofferdams are the best approach for any heavy structure e.g. bridge pier where
free-flowing water, unstable soils or heavy surcharge loads are encountered.
When used in water the bottom is sealed by using underwater concrete of
sufficient thickness to counter cut the effect of uplift pressure before dewatering
is carried out.
1
Factors to be considered when selecting cofferdam
Caisson are structure which is sunk through ground or water to provide working
space and which subsequently become an integral part of the permanent work.
Large caissons are used as foundation for bridge piers and other water
structures.
Types of Caisson
1. Open caisson
2. Pneumatic caisson (compressed air)
3. Box caisson
4. Monoliths caisson
Caisson
2
PIPELINES
Materials
Pipeline Classification
- Rigid Pipe
- Flexible Pipe
Flexible ones will deform significantly and transmit the load to the
surrounding field.
Construction Techniques
Steps Required
1. Site survey and line alignment coupled with production of working
drawing
2. Clearing of right of way (scrapper)
3. Pipe slinging (carrying) along the line
4. Excavation work using pail loader or wheel loader for excavating
trench for smaller diameter pipe, crane for laying bulldozer D6, or
D8 for final backfilling
Dewatering equipment for muddy water, or depending on the H 2O
table (centrifugal pump or diaphragm pump)
5. Laying, backfilling and disposal of surplus spoil
6. Manhole inspection chamber construction
7. Manhole dressing including installation of iron stop and manhole
cover.
3
Manholes are required at:
i. Change of direction
ii. Intersection
iii. Change of slope
iv. At least every 30m depending on pipe sizes
Bedding
These are required to avoid corrosion, wear & tear, abbration and leakage.
4
SEWAGE TREATMENT
Sludge Disposal
Methods of Sludge Disposal
(a) Tipping Method
(b) Aerobic
(c) Sterilization
(d) Road
Tipping Method
The sludge is transported and tipped into the lagoon. This is after treatment in
the sewage treatment plant.
Aerobic Digestion
The sludge is heated in closed ranks which converts it into an inoffensive
human-like material which is suitable for agricultural use.
Sterilization Method
When the sludge is sterilized, it produced methane which can be used to
generate power.
Road Method
After some chemical treatment, it is used for road construction in lieu of
bitumen.
5
Fig. 7a – Percolating Filter Plant
6
TUNNELLING
Purposes of Tunnels
Advantages of Tunnels
i. They protect the system for which they are constructed from
weathering effects such as rain, sun etc. thus tunnels reduce the
maintenance cost of the system e.g. railway, highway, sewer line etc.
ii. They protect those systems during war times from destruction due to
bombarding.
iii. In certain places tunnels have proved cheaper for cross the mountain
or river than bridges or open cuts.
iv. In most congested urban cities, underground railway or highway is the
best alternative to provide means of transportation e.g. the aborted
metroline project for Lagos.
v. In a circuitous route to reach the other side of the hill, tunnel reduces
the length of the railway line, highway etc considerably.
Disadvantages
i. It is costly as it requires special construction equipment and modern
technique.
ii. It requires experienced and skilled staff for its construction.
iii. It takes longer period for its construction than bridges and open cuts.
Methods of Tunneling
The method of construction to be used will depend on so many factors namely;
a. Type of tunnel to be constructed
b. This ground conditions
c. Depth of tunnel
7
d. Time available for the construction
e. The equipment available
2. Pre-Deck
Here, the tunnel walls are sunk by the diagram walling method and the
upper surface of the ground is removed to allow the positioning of the
tunnel deck.
1. Full Face Method: This is used for tunnels whose lengths are not more
than 3m. It involves boring the entire face, loading the holes and
discharging the explosives.
2. Other methods of boring of tunnel are: heading and bench, drift, pilot
method, perimeter method and tunneling in soft grounds.
Ventilation of Tunnel
A tunnel should be well ventilated during and after construction operation due
to the following reasons:
ELECTRICAL INSTALLATION
Transmission
This is the process whereby electrical power is carried in bulk either by
underground cables or overhead power line over long distances. It is transmitted
in high voltage current to reduce/avoid power loss in a cable.
Distribution
A distribution system connects all the loads in the particular area to the
transmission lines.
Types of Installation
1. Indoor Installation
– Surface wiring
- Conduit wiring
- Trunking wiring
2. Outdoor Installation – It deals with perimeter and high street light.
Materials normally use are street light column, fitting and armoured
cable. The street light shall be steel fabricated and properly earthed after
erection.
3. Rural Electrification
Scope of work – (1) planning (b) design (c) installation and (d)
commissioning of 111kv interconnection, 33/11/0.45kv
Earthing: The basic reason for earthing is to prevent or minimize the risk of
shock to human beings.
Earth Leakage Circuit Breaker: This is an automatic device for making and
breaking a circuit both under normal and abnormal condition, such as those of a
short circuit.
Earth Loop Impedance: this is a cable linking two or more earth electrode
Earth Electrode: it is a rod buried in the earth to which earth wire is connected,
it transfer the current from the earth wire to the earth.
CABLE
Cable consists of the following: (1) conductor (2) insulation (3) mechanical
protection.
10
ARTIFICIAL LIGHTING
Location Fittings
1) Banking Hall: Modular fitting with diffuser (minimum of 4 bulk).
2) Classroom (Primary & Secondary) Fluorescent (White)
3) Bedroom: (i) Wall bracket (for mellow light) the glass is opaque
(ii) Fluorescent: There is need in case where you are
searching for something
(iii) Bedside lamp for reading.
4) Football Pitch: Flood light of 15m high on steel plate, placed at 4 corners
all pointing to the pitch. Minimum of 1000W bulb used for maximum
illumination; 48 per board
5) Toilet: (i) Guest Toilet: Bulk head ceiling fittings
(ii) Your own toilet (Rest room) Bulk head ceiling fitting
and minor light for sharing.
6) Restaurant or Cafes: Fluorescent
7) Shop: Tungsten halogen lamp
Factors to be considered when designing artificial lighting
1. The purpose for which the lighting is being provided
2. The function being performed in the space being lighted
3. The environment in which the lighting is being fixed
4. The equipment available and method of fixing
5. The flexibility required of the installation
6. The length of time the installation is likely to be required
7. The cost of running the installation
8. The probable quality of maintenance of the installation and the amount of
money likely to be avoidable for the replacements, repairs, cleaning,
general maintenance.
DIVERSITY FACTOR: This is the current under the normal load condition
over total load connected current. It is the percentage of usage when considering
the design of electrical installation. Factors that determine the choice of a wiring
system are:
(a) Type of Building construction (e) Economy
(b) Flexibility (f) Safety
(c) Installation condition (g) Aesthetics
(d) Durability
11
BOREHOLE
Sketch showing of 250mm diameter Borehole with a depth of 200m
12
THE VARIOUS BOREHOLES DRILLING SYSTEM
b. Mechanical Boring
This involves the use of mechanical power driven boring equipment
comprising of compressor, mud pump and tank. It could be in the
following ways:
Wash boring:- for loose and week soils
Rotary boring: for rocks and very hard soils
NOTE: The most preferred option for the 200metre borehole under
consideration will be mechanical boring of mud-rotary drilling types, because of
the deepness of depth.
13
ACOUSTICS: SOUND CONTROL, NOISE PROBLEM AND THEIR
ELIMINATION
Direct sound: This is the one recentered and incident in one ears directly from
source of emission.
Indirect Sound: This is the ones recentered from reflection air borne sound,
vibration and flanking transmission.
Sound Control:
Sound inference can be curtailed or eliminated through the following methods:
1. Mass-construction (for generator base)
2. Sound insulation
3. Hollow wall construction
4. Provision of barrier
5. Discontinuous construction
6. Proper planning during design by use grouping – (grouping of rooms)
14
AIR CONDITIONING: FORMS, PLANT EQUIPMENT AND
INSTALLATION
Ventilation: Moving air from one space to another i.e. entirely separate space as
a matter of air volume
Or
This is the process of changing air in an enclosed space.
(i) Ventilation is required for supply of sufficient oxygen for breathing. (ii)
Also to create air movement (iii) prevention of undue concentration of odour,
bacteria (iv) Removal of heat from product of combustion
1. Extract system
2. Input system – supply system
3. Combined extract and input system.
AIR CONDITIONING
Air Conditioning is a primarily a system of heating and cooling rather on the
ventilating system. It is aimed at controlling within predetermined unit, the
temperature, humidity and cleanly of air within a building (Air movement).
15
3. Air movement (cleaning of air within a building)
4. Prevention of dust
5. Prevention of bacteria and toxic gases
6. Prevention of odours
16
OTHER ASPECTS OF BUILDING WORKS
RAFT FOUNDATION
This is a large combined slab design to cover the whole or a larger part of the
available site. It is required into the following:
This is used where the thickness of the raft will exceed 300mm. it is an inverted
floor directly on the ground with the beam projecting above it. This is called
upstand beam and slab has the advantage of providing rigidity beam and
stiffness to the bottom of the beams. However, the downstand beam and slab
may be necessary where the top surface of the slab is to be used as floor. This
alternative also reduces the volume of excavation to be carried out during
construction. It is only economical at a depth of 900mm.
Cellular Raft
This is used where high rigidity is required especially in subsidence soils, where
stresses are high and the depth exceeds 900mm. It consists of top and bottom
slabs with edge and intermediate beams in both directions to reduce differential
settlement; it might be taken to some depth as much as a basement
17
BUILDING REGULATIONS AND APPROVAL
The main function of the local planning authority is to give planning approval,
which is the permission granted any individual, firm or governmental
organizations to erect a structure and carry out a development in an area.
Approval Procedure
The drawings are submitted to the registry of the Area planning office for
registration and assessment. The drawings are assessed according to its type and
magnitude and the client is charged certain fees for the payment accordingly.
From the registry, the drawings go to the technical registry where the drawings
are checked to see whether they are prepared in accordance with all planning
statutory regulations and whether they conform with architectural principles of
ventilation, lighting, comfort, safety and structural stability.
The drawings then go to the inspection section where the site on which the
building is to be erected would be inspected for suitability of otherwise after site
inspection. The drawings are sent to the planning officers who will consider all
comments made on the plan including commends of the site inspector(s), to
18
make his own recommendation to the Area Planning Officer. The Area Planning
Officer considers the various reports and gives the final approval or disapproval.
The drawings also go the land officer in the lands department for the assessment
and payment of allocation fees before they are returned to the Area Planning
Officer.
From the Area Planning Officer the drawing is sent back to the registry for
stamping and collection. Two out of the four sets submitted are returned to the
owner, however he can collect an additional set on special request.
Contractor
19
CURTAIN WALLING
Curtain walling is the system of cladding buildings with thin sheet of glass,
metal or other impermeable materials supported by slender metal mullions and
transoms and they are attached to the structural frame of the building.
To fulfill its primary functions, a curtain wall must meet the following
requirements:
1. Resistance to the elements
2. Adequate strength
3. Ease of assembly and fixing
4. Required degree of fire resistance
5. Required degree of sound insulation
6. Provision for thermal and structural movements
20
21
INDUSTRIALIZED SYSTEM BUILDING
Limitations of ISB
1. Handling equipment for the components. Specialized equipment are
needed for handling the heavy components such as wall panels, floor
unites etc.
2. Limits or road and rail transport. If the road network is poor (as in
Nigeria), the use of ISB may not be effective as components may be
impaired.
3. The problem of offsite assembly and packaging in an obstacle.
4. The jointing method may limited its use if there is no skilled labour.
5. Importation of skilled labour and components is a limitation.
Close: Design to any that is required, but is better but expensive. Here, the
components are not interchangeable with any other system or method and thus
the building is formed from components specially designed for and applicable
to the particular building type in question. For example, schools or housing.
22
Differences between Industrialized System Building (ISB) and Traditional
Method (TM)
23