0% found this document useful (0 votes)
57 views

Daily Task List: Month: February

The daily task list for Simone Benoit's Project XIV in February 2018 includes updating senior leadership, testing features for a legacy interface, performing employee evaluations, migrating data to a new system over multiple weeks, planning future company events, and submitting mandatory reports. Key tasks are migrating legacy data and testing features for an old system interface. The status of tasks ranges from completed to in process to not started by the end of the month.

Uploaded by

fendi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
57 views

Daily Task List: Month: February

The daily task list for Simone Benoit's Project XIV in February 2018 includes updating senior leadership, testing features for a legacy interface, performing employee evaluations, migrating data to a new system over multiple weeks, planning future company events, and submitting mandatory reports. Key tasks are migrating legacy data and testing features for an old system interface. The status of tasks ranges from completed to in process to not started by the end of the month.

Uploaded by

fendi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Daily Task List

Month: February Year: 2018 Project: XIV Owner: Simone Benoit (PM)

Monday Tuesday Wednesday Thursday Friday


01/02/2018 02/02/2018
Task: Update the Task: Test the
CEO regarding the legacy interface
project’s status. for feature 1A.
Status: Done Status: Done

05/02/2018 06/02/2018 07/02/2018 08/02/2018 09/02/2018


Task: Test the Task: Test the Task: Test the Task: Perform Task: Perform
legacy interface legacy interface legacy interface employee employee
for feature 1B. for feature 1C. for feature 1D. evaluation review evaluation review
Status: Done Status: Done Status: Cancelled for Tyreese Jones. for Laneya Cox.
Status: Done Status: Done

12/02/2018 13/02/2018 14/02/2018 15/02/2018 16/02/2018


Task: Update the Task: Initiate the Task: Transfer 20% Task: Transfer 20% Task: Transfer 20%
high level plan. data migration of the legacy of the legacy of the legacy
Status: Done phase. information to the information to the information to the
Status: In Process new system. new system. new system.
Status: Done Status: Done Status: In Process

19/02/2018 20/02/2018 21/02/2018 22/02/2018 23/02/2018


Task: Transfer 20% Task: Transfer 20% Task: Holiday. Task: Holiday Task: Submit the
of the legacy of the legacy year end expense
information to the information to the report.
new system. new system. Status: Not
Status: In Process Status: In Process Started

26/02/2018 27/02/2018 28/02/2018


Task: Approve the Task: Plan the Task: Build the
data migration companies retreat. monthly status
report. Status: Not deck.
Status: Cancelled Started Status: Not
Started