Technical Requirements For Power Generating Plants Connected To MV and HV Grid
Technical Requirements For Power Generating Plants Connected To MV and HV Grid
Technical Requirements For Power Generating Plants Connected To MV and HV Grid
Version 1.2
VERSION LOG
2
Preface
PREFACE
This document is a direct translation of the original Danish document “Tekniske betingel-
ser for nettilslutning af produktionsanlæg til lavspændingsnettet (> 1 kV), Version 1.2”. It
is provided for convenience; only the Danish version of the document has legal authority.
These technical requirements for connection of plants to the medium and high-voltage
grid (>1 kV) are provided by the distribution system operators in pursuance of
‘COMMISSION REGULATION (EU) 2016/631 of 14 April 2016 establishing a network
code on requirements for grid connection of generators’ (the RfG) and of the Danish
Electricity Supply Act (Elforsyningsloven).
The requirements apply to all new power-generating plants connected to the grid after 27
April 2019 and to plants in types C and D which are substantially modified after this date.
3
Table of contents
TABLE OF CONTENTS
Preface ....................................................................................................................................... 3
1. Introduction............................................................................................................................ 6
3. Definitions/Terms ................................................................................................................. 11
4
Table of contents
5
Introduction
1. INTRODUCTION
This document describes the requirements for power-generating plants connected to the
medium and high-voltage grid. The requirements for power-generating plants are divided
into four main types based on the plant’s active power capacity:
This document only contain requirements for power-generating plants in types B, C and
D as only plants in these types can be connected to the medium and high-voltage grid.
Smaller plants are connected to the low-voltage grid.
Requirements for type B power-generating plants are also available in ‘Technical re-
quirements for connection of power-generating plants to the low-voltage grid (≤1 kV)’.
Chapter 2 contains the administrative provisions. This chapter describes, among other
things, the purpose, statutory authority, appeal procedures and exceptions. The chapter
also contains a list of normative and informative references.
If you are to connect a type B power-generating plant to the grid, you only need to read
Chapters 2 and 3 and the chapter on type B plants, including the relevant annex. This also
applies to power-generating plants in types C and D which have their own chapters and
annex.
The term ‘power-generating plant’ is used to cover common requirements for power park
modules and synchronous power-generating plants. Where specific requirements apply to
‘power park modules’ or ‘synchronous power-generating plants’, they are designated as
such.
The sections are structured so that general requirements are stated first followed by spe-
cific requirements for synchronous power-generating plants and power park modules,
respectively.
6
Purpose and administrative provisions
2.1. P URPOSE
The purpose of these requirements is to describe the applicable technical and functional
requirements for a power-generating plant connected – or planned to be connected – to
the public medium and high-voltage distribution grid.
In case of doubt, the Danish version of the registered requirements will prevail.
An existing power-generating plant must comply with the requirements applicable at the
time of connection to the grid, or at the time when the plant owner entered into a final and
binding purchase agreement regarding the main generating plant.
Before any modification is made, the power-generating plant owner is obliged to notify
the DSO about the modification.
7
Purpose and administrative provisions
2.2. S COPE
The requirements for power-generating plants are divided into four types based on the
plant’s active power capacity.
*These power-generating plant types are covered in ‘Technical requirements for connec-
tion of power-generating plants to the low-voltage grid (≤1 kV)’. Type A plants connected
to medium voltage must comply with the requirements for type A plants in the ‘Technical
requirements for connection of power-generating plants to the low-voltage grid (≤1 kV)’.
(*) Type B power-generating plants can be connected to both the low and medium-
voltage grid depending on the size of the plant. This type is therefore included in both
requirements documents.
Back-up power generating units operated in parallel with the public electricity supply grid
for less than five minutes per month, excluding unit maintenance and commissioning
testing, are not required to comply with the requirements in this document. If the Back-up
power generating unit is operated for more than five minutes per month at normal opera-
tion, the unit must comply with the requirements for power quality and protection as pro-
vided in these requirements.
These requirements do not include the financial aspects related to grid connection and
settlement metering of power-generating plants.
8
Purpose and administrative provisions
The power-generating plant owner must send an exemption application to the DSO. De-
pending on the nature of the application, it will be forwarded to the Danish Utility Regu-
lator, which will make a decision.
All requirements apply to the Point of Connection (POC), unless otherwise specified.
2.7. R EFERENCES
2.7.1. Normative
EU Regulation 2016/631
Joint Regulation 2017 (Fællesregulativet 2017)
The Danish Electricity Supply Act (Elforsyningsloven)
Requirements for Generators (RfG) – requirements for simulation models, Energinet
2019
DS/EN 50160: Voltage characteristics of electricity supplied by public distribution net-
works.
prEN 50549-2: Requirements for generating plants to be connected in parallel with dis-
tribution networks – Part 2: Connection to a MV distribution network.
DS/EN 61000-4-30: Electromagnetic compatibility (EMC) – Part 4-30: Testing and
measurement techniques – Power quality measurement methods.
DS/EN 61400-21:2008: Wind turbines – Part 21: Measurement and assessment of power
quality characteristics of grid connected wind turbines.
DS/EN 60034-16-1:2011: ‘Rotating electrical machines – Part 16: Excitation systems for
synchronous machines – Chapter 1: Definitions’.
DS/CLC/TR 60034-16-3:2004: ‘Rotating electrical machines – Part 16: Excitation sys-
tems for synchronous machines – Section 3: Dynamic performance’.
2.7.2. Informative
IEC/TR 61000-3-6: Electromagnetic compatibility (EMC) – Part 3-6: Limits – Assess-
ment of emission limits for the connection of distorting installations to MV, HV and EHV
power systems.
9
Purpose and administrative provisions
10
Definitions/Terms
3. DEFINITIONS/TERMS
3.1. A BBREVIATIONS
3.1.1. ψ k
ψk denotes the short-circuit angle at the Point of Connection (POC).
3.1.2. C f
Cf denotes the flicker co-efficient. For a more detailed description, see DS/EN 61400-21.
3.1.3. COMTRADE
COMTRADE (Common Format for Transient Data) is a standardised file format speci-
fied in IEEE C37.111-2013.
3.1.4. d(%)
d(%) denotes rapid voltage changes. For a more detailed description, see 3.2.29.
3.1.5. DK1
Western Denmark. For a more detailed description, see 3.2.67.
3.1.6. DK2
Eastern Denmark. For a more detailed description, see 3.2.70.
3.1.7. df/dt
df/dt denotes frequency change. For a more detailed description, see 3.2.23.
3.1.8. DSO
Distribution system operator, see 3.2.10.
3.1.9. f <
f< denotes the operational setting for underfrequency in the relay protection.
For a more detailed description, see sections 4.5, 5.5 and 6.5.
3.1.10. f >
f> denotes the operational setting for overfrequency in the relay protection.
For a more detailed description, see sections 4.5, 5.5 and 6.5.
3.1.11. f R O
fRO denotes the frequency at which a power-generating plant is to begin downward regu-
lation with the agreed droop. For a more detailed description, see sections 4.3.1, 5.3.1 and
6.3.1.
3.1.12. f R U
fRO denotes the frequency at which a power-generating plant is to begin upward regula-
tion with the agreed droop. For a more detailed description, see sections 5.3.2 and 6.3.2.
3.1.13. I h
Ih denotes individual harmonic currents, where h denotes the harmonic order.
3.1.14. I n
In denotes nominal current. For a more detailed description, see 3.2.44.
11
Definitions/Terms
3.1.15. I Q
IQ denotes fast fault current. For a more detailed description, see 3.2.53.
3.1.16. k u
ku denotes voltage change factor. The voltage change factor is calculated as a function of
ψ k.
3.1.17. P pos s ib le
Ppossible denotes the maximum active power, which it is possible to produce under given
circumstances.
3.1.18. P mi n
Pmin denotes the minimum possible active power generation from a power-generating
plant.
3.1.19. P n
Pn denotes nominal active power. For a more detailed description, see 3.2.41.
3.1.20. P l t
Plt denotes long-term flicker emissions from a power-generating plant. Plt stands for ‘long
term’ and is evaluated over a period of two hours. For a more detailed description, see
IEC 61000-3-7.
3.1.21. P s t
Pst denotes short-term flicker emissions from a power-generating plant. Pst stands for
‘short term’ and is evaluated over a period of ten minutes. For a more detailed descrip-
tion, see IEC 61000-3-7.
3.1.22. PCC
Abbreviation for Point of Common Coupling. For a more detailed description, see 3.2.38.
3.1.23. PCI
Abbreviation for Point of Connection in Installation. For a more detailed description, see
3.2.31.
3.1.24. PCOM
Abbreviation for Point of Communication. PCOM is defined in section 3.2.34.
3.1.25. PF
Abbreviation for Power Factor. For a more detailed description, see 3.2.8.
3.1.26. PGC
Abbreviation for Point of Generator Connection. For a more detailed description, see
3.2.25.
3.1.27. POC
Abbreviation for Point of Connection. POC is defined in section 3.2.40.
3.1.28. PWHD
Abbreviation for Partial Weighted Harmonic Distortion. For a more detailed description,
see 3.2.49.
12
Definitions/Terms
3.1.29. Q n
Qn denotes nominal reactive power. For a more detailed description, see 3.2.42.
3.1.30. S i
Si denotes apparent power of power-generating unit no. i.
3.1.31. S k
Sk denotes short-circuit power. For a more detailed description, see 3.2.35.
3.1.32. S n
Sn denotes nominal apparent power. For a more detailed description, 3.2.45.
3.1.33. SCR
Abbreviation for Short-Circuit Ratio. For a more detailed description, see 3.2.37.
3.1.34. THD
Abbreviation for Total Harmonic Distortion. For a more detailed description, see 3.2.65.
3.1.35. U c
Uc denotes normal operating voltage. For a more detailed description, see 3.2.46.
3.1.36. U h
Uh denotes individual harmonic voltages, where h denotes the harmonic order.
3.1.37. U n
Un denotes nominal voltage. For a more detailed description, see 3.2.43.
3.1.38. UTC
Abbreviation for Universal Time, Coordinated.
3.1.39. Z ne t, h
Znet,h denotes grid impedance of the harmonic order h.
3.2. D EFINITIONS
13
Definitions/Terms
3.2.6. DC content
A DC current which results in an AC offset, meaning that the AC current is asymmetric
around zero at the Point of Connection (POC).
The DSO is the company licensed to operate the public electricity supply grid up to 100
kV.
The transmission system operator is the company licensed to operate the public electricity
supply grid above 100 kV.
14
Definitions/Terms
3.2.13. Flicker
A visual perception of light flickering caused by voltage fluctuations. Flicker occurs if the
luminance or the spectral distribution of light fluctuates with time. At a certain intensity,
flicker becomes an irritant to the eye.
3.2.15. Disconnect
When a power-generating plant breaks the electrical connection to the public electricity
supply grid.
3.2.16. Frequency
Frequency is measured in Hertz (Hz). The grid frequency in the public electricity supply
grid is 50 Hz. There are also other frequencies related to power quality. Such frequencies
are referred to as harmonics, interharmonic overtones and distortions in the 2-9 kHz fre-
quency range. In connection with power quality, grid frequency is referred to as the fun-
damental frequency.
In the RfG, this type of control is called LFSM-O (limited frequency sensitive mode at
overfrequency).
15
Definitions/Terms
In the RfG, this type of control is called LFSM-U (limited frequency sensitive mode at
underfrequency).
The sign for active/reactive power indicates the power flow as seen from the generator.
Consumption/import of active/reactive power is stated with a negative sign, while the
generation/export of active/reactive power is stated with a positive sign.
The desired Power Factor control is effected with a Power Factor set point, and the sign
determines if control is to be performed in the first or the fourth quadrant.
Power Factor set points thus combine two pieces of information in a single signal: a set
point value and choice of control quadrant.
16
Definitions/Terms
0°
P [kW]
Underexcited Overexcited
Inductive Capacitive
Leading Lagging
Q-import Q-export
P-export P-export
270° 90°
Q [kVAr]
Figure 3.1 – Definition of signs for active and reactive power, Power Factor and reference for Power
Factor angle.
3.2.26. Reconnection
Connecting after an event where the power-generating plant has been disconnected from
the public electricity supply grid.
3.2.28. Harmonics
Electrical disturbances caused by overharmonic currents or voltages. Harmonics are fre-
quencies which are a whole multiple (h) of the fundamental frequency (50 Hz).
3.2.30. Connection
When a power-generating plant is electrically connected to the public electricity supply
grid, thereby becoming energised from the public electricity supply grid.
17
Definitions/Terms
The distribution grid is defined as the public electricity supply grid with a nominal volt-
age below 100 kV.
The transmission grid is defined as the public electricity supply grid with a nominal volt-
age above 100 kV.
𝑆𝑘,𝑝𝑜𝑤𝑒𝑟𝑞𝑢𝑎𝑙𝑖𝑡𝑦
𝑆𝐶𝑅 =
𝑆𝑛
Electrically speaking, the Point of Common Coupling and the Point of Connection (POC)
may coincide. The Point of Common Coupling (PCC) is always the point deepest inside
the public electricity supply grid, i.e. furthest away from the power-generating plant, see
figure 3.3 and figure 3.4.
18
Definitions/Terms
Synchronous
Voltage regulator Excitation system Power System
generator
Excitation ssystem
All requirements specified in this document apply to the Point of Connection (POC),
unless otherwise specified.
Power-generating plants which have the same Point of Common Coupling (PCC) and the
same owner are deemed to be one plant.
Installation
PCC / POC
Consumption
PCOM
PCI PGC
Generating unit
Figure 3.3 – Installation-connected generation with indication of the PGC, PCI, POC and PCC.
19
Definitions/Terms
PCC POC
Figure 3.4 Grid-connected generation with indication of the PGC, POC, PCC and PCOM.
Figure figure 3.3 shows a typical installation connection of one or more power-generating
plants with indication of the typical locations of Point of Generator Connection (PGC),
Point of Connection (POC), Point of Connection in Installation (PCI) and Point of Com-
mon Coupling (PCC). In the illustrated example, the Point of Common Coupling (PCC)
coincides with the Point of Connection (POC).
20
Definitions/Terms
Normal operating voltage is determined by the DSO and is used to determine the normal
operating range and protection.
ℎ=40
𝑌ℎ 2
√
𝑃𝑊𝐻𝐷𝑌 = ∑ ℎ ∙ ( )
𝑌1
ℎ=14
3.2.51. Q control
A control function for reactive power which controls the reactive power independently of
the active power generated.
21
Definitions/Terms
3.2.54. Tolerance
Tolerance of voltage and frequency deviations to ensure that a power-generating plant
does not disconnect from the public electricity supply grid but instead maintains some
form of operation to support the public electricity supply grid.
3.2.55. Signal
A measurement, status, set point or command which is exchanged between the power-
generating plant and the DSO via the PCOM.
400
Extra high voltage (EHV)
220
Transmission system operator
150
132
High voltage (HV)
60
50
33
30
15
10
0.4
Low voltage (LV)
0.23
22
Definitions/Terms
3.2.61. Droop
The control parameter change (e.g. frequency) in per cent which will cause a power out-
put change corresponding to the nominal power of the power-generating plant.
ℎ=40
𝑌ℎ 2
𝑇𝐻𝐷𝑌 = √ ∑ ( )
𝑌1
ℎ=2
23
Definitions/Terms
3.2.69. Islanding
An operating situation which may occur in the distribution system where part of the dis-
tribution grid continues operating without being connected to the public electricity supply
grid.
24
Requirements for type B power-generating plants
A power-generating plant must maintain operation at different frequencies for the mini-
mum time periods specified in figure 4.1 without disconnecting from the grid.
UC [pu]
1.1
Minimum operation time
Minimum operation time
Normal operation
1.0
30 minutes
30 minutes
30 minutes
0.9
0.85
Frequency [Hz]
47.5 48.0 48.5 49.0 49.5 50 50.5 51.0 51.5
Figure 4.1 – Minimum time periods during which a power-generating plant must be capable of main-
taining operation at different frequencies without disconnecting from the grid.
25
Requirements for type B power-generating plants
Frequency [Hz]
47.5 48.0 48.5 49.0 49.5 50.0
0%
4%
6%
8%
10%
Reduction of Pn/Hz 6%
A power-generating plant may only reduce the active power if the plant is technically
incapable of continuing to supply of full active power at underfrequency. This applies
during normal operating conditions, which are guaranteed for 90% of the time, and must
occur to the best of its ability in relation to operating point and available primary energy.
26
Requirements for type B power-generating plants
Voltage Duration
1.15·Uc 60 s
1.20·Uc 5s
27
Requirements for type B power-generating plants
1,1
1
1,5; 0,9
0,9
0,8
0,25; 0,7
Voltge at POC [pu]
0,7
0,7; 0,7
0,6
0,5
0,4
0,3 0,25; 0,3
0; 0,3
0,2
0,1
0
-0,5 -0,25 0 0,25 0,5 0,75 1 1,25 1,5 1,75 2 2,25 2,5 2,75 3
Time [s]
A power park module must be capable of restoring normal generation of active power
after a fault as quickly as possible; however, no later than five seconds after voltage and
frequency have returned to the normal operating range, see section 4.1.1. During the re-
covery process, upward regulation of active power must be performed with a gradient of
at least 20% Pn/s.
28
Requirements for type B power-generating plants
1,1
1
1,5; 0,9
0,9
0,8
Voltage at POC [pu]
0,7
0,6
0,5
0,4
0,3
0,2 0; 0,15
0,25; 0,15
0,1
0
-0,5 -0,25 0 0,25 0,5 0,75 1 1,25 1,5 1,75 2 2,25 2,5 2,75 3
Time [s]
A power park module must be capable of supplying fast fault current (positive sequence
component) in the area above the solid line in figure 4.4 and up to 90% of normal operat-
ing voltage at the Point of Generator Connection.
Control of fast fault current from a power park module must follow figure 4.5.
It must be possible to supply fast fault current within 100 ms with an accuracy of ±20%
of In.
During a fault sequence, a power park module must prioritise the fast fault current before
supplying the active power in the range from 90% to 15% of Uc, see the hatched area in
figure 4.5.
29
Requirements for type B power-generating plants
100%
90%
80%
Voltage in PGC [% af Uc]
70%
60%
50%
40%
30%
20%
10%
0%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Fast fault current [IQ/In]
Figure 4.5 – Supply of fast fault current from a power park module.
DK 1 DK 2
(Western Denmark) (Eastern Denmark)
When a power-generating plant has been connected, the active power must not increase
by more than 20% of nominal power per minute.
4.2.1. Synchronisation
A power-generating plant must be capable of automatically synchronising to the public
electricity supply grid. It must not be possible to manually circumvent the automatic syn-
chronisation and allow the plant to connect without synchronisation.
30
Requirements for type B power-generating plants
To be able to detect islanding, downward regulation of the active power at the Point of
Connection (POC) must not be commenced until after an intentional delay of 500 ms.
If the plant’s natural delay (recovery time) for commencement of downward regu-
lation is 500 ms or more, the requirement for delay is met.
If the plant’s natural delay (recovery time) for commencement of downward regu-
lation is less than 500 ms, the delay must be extended to 500 ms. The intentional
delay is only imposed when transitioning to frequency response, i.e. when the fre-
quency threshold fRO is crossed.
Example
A plant’s natural delay (recovery time) for commencement of downward regula-
tion is 300 ms. An additional intentional delay (recovery time) of 200 ms is added
to make the total delay (recovery time) for the plant 500 ms.
When a power-generating plant’s lower limit for active power is reached in connection
with the downward regulation, the plant must keep this minimum level of active power
until the grid frequency drops again or until the plant is disconnected for other reasons.
P/Pn
fRO f>
(50.x Hz)
47.5 48.0 48.5 49.0 49.5 50.0 50.5 51.0 51.5 52.0 Frequency [Hz]
31
Requirements for type B power-generating plants
The frequency threshold for commencement of frequency response must be set in the
50.2 Hz - 50.5 Hz frequency range, both values inclusive, with a resolution of 10 mHz or
better.
The droop of the active power reduction must be in the 2-12% range with a resolution of
1% or better.
The settings for frequency response to overfrequency for Western and Eastern Denmark
are as follows:
DK 1 DK 2
(Western Denmark) (Eastern Denmark)
Droop 5% 4%
Table 4.4 – Default settings for power response to overfrequency for DK1 and DK2.
When the frequency response is enabled, the active power must follow the droop with a
deviation of 5% of nominal active power or better, measured over a period of one minute.
Absolute power limit is used to limit the active power from a power-generating plant to a
set point-defined maximum power limit at the Point of Connection (POC).
Absolute power limit is used to protect the public electricity supply grid against overload
in critical situations.
Control using a new parameter for the absolute power limit must be completed within
five minutes of receiving the parameter change order.
32
Requirements for type B power-generating plants
Ramp rate limit is used for reasons of system operation to prevent changes in ac-
tive power from adversely impacting the stability of the public electricity supply
grid.
The power-generating plant must have at least five different configurable adjustment
positions.
Control must be initiated within one second and completed within ten seconds of receipt
of a downward regulation order.
If the system protection receives an upward regulation order, e.g. from step 4 (25%) to
step 3 (40%), it is acceptable that completion of the order may take additional time due to
the design limits of power-generating plant generators or other plant units.
The power-generating plant must be capable of controlling its reactive power using the
functions and characteristics described in sections 4.4.2 to 4.4.4. It must be possible to
indicate set points in steps of 1% of Sn or better for power and 0.01 or better for Power
Factor.
33
Requirements for type B power-generating plants
The control accuracy may be less than ±2% of Sn when active power generation is below
10% of power-generating plant nominal apparent power. However, the exchange of un-
controlled reactive power must never be greater than 10% of plant nominal apparent
power.
When one or more power-generating units of a power park module are taken out of opera-
tion for scheduled maintenance, the plant’s supply of reactive power may be reduced
proportionate to the number of units taken out of operation.
Required capability
Allowed to reduce active power to deliver
reactive power because of technical limitations.
U/Uc
1.10
1.05
1.04
Q/Pn
0.329 0.329
0.96
0.95
0.90
Q-import Q-export
Underexcited Overexcited
0.85
Figure 4.7 – Requirements for supply of reactive power at maximum active power generation.
Inside the shaded blue area in figure 4.7, the power-generating plant must supply stable
reactive power in accordance with the selected control mode, which may only be limited
by the technical performance of the plant, e.g. saturation or undercompensation.
When the active power generation is below the maximum capacity, a power-generating
plant must be capable of operating within the area specified in figure 4.8.
34
Requirements for type B power-generating plants
Required capability
Reduced accuracy allowed during low production
P/Pn
PF = 0.95 PF = -0.95
Inductive/Leading Capacitive/Lagging
Q/Pn
-0.329 0.329
Figure 4.8 – Requirements for supply of reactive power at different active power levels.
When a new Power Factor set point is set, the control must be completed within one mi-
nute.
P/Pn
Inductive/Leading Capacitive/Lagging
Q/Pn
-0.329 0.329
35
Requirements for type B power-generating plants
A power-generating plant may not exchange reactive power with the public electricity
supply grid unless otherwise agreed with the DSO. I.e. the plant will as default produce at
a Power Factor of 1.
If the function is to be enabled, the current setting values for the control function are
agreed with the DSO.
Reactive power control must be completed within ten seconds of the active power having
been stabilised.
P/Pn
Point 3
1
Point 2
0,5
Inductive/Leading Capacitive/Lagging
Point 1
PF
0.9 -0.9
Figure 4.10 – Default setting for automatic Power Factor control [cos φ (P)].
Characteristics points
1 0.0 1.0
2 0.5 1.0
3 1 0.9 inductive
The function is normally activated at 105% of Uc, and deactivated at 100% of Uc.
36
Requirements for type B power-generating plants
A power-generating plant may not exchange reactive power with the public electricity
supply grid unless otherwise agreed with the DSO. I.e. the plant will as default always
produce at a Power Factor of 1.
If the function is to be enabled, the current setting values for the control function are
agreed with the DSO.
4.4.4. Q control
A power-generating plant must be capable of performing Q control as shown in figure
4.11.
P/Pn
Inductive/Leading Capacitive/Lagging
Q-import Q-export
P-export P-export
Q/Pn
-0.329 0.329
Control from one set point to another must be completed within one minute.
A power-generating plant may not exchange reactive power with the public electricity
supply grid unless otherwise agreed with the DSO. I.e. the plant will as default produce at
a Power Factor of 1.
If the function is to be enabled, the current setting values for the control function are
agreed with the DSO.
37
Requirements for type B power-generating plants
4.5. P ROTECTION
4.5.1. General
Power-generating plant protection must both protect the plant and help ensure stability in
the public electricity supply grid.
Relay settings cannot prevent specified power-generating plant functions from working
properly.
The power-generating plant owner is responsible for ensuring that the plant is dimen-
sioned and equipped with the necessary protection functions so that the plant:
• Is protected against damage due to faults and incidents in the public electricity
supply grid
• Protects the public electricity supply grid against unwanted impacts from the
power-generating plant
• Is not damaged and does not switch off during voltage dips as specified in section
4.1.3.
The DSO or the transmission system operator may demand that the setting values for
protection functions be changed after commissioning if it is deemed to be of importance
to the operation of the public electricity supply grid.
At the power-generating plant owner’s request, the DSO must state the highest and lowest
short-circuit current that can be expected at the Point of Connection (POC) as well as any
other information about the public electricity supply grid as may be necessary to config-
ure the plant’s protection functions.
Voltage and frequency must be measured simultaneously for the phases which the power-
generating plant is connected to at the Point of Connection (POC).
38
Requirements for type B power-generating plants
In connection with internal short circuits in the power-generating plant, the relay protec-
tion must be selective with the grid protection. This means that short circuits in the pow-
er-generating plant must be disconnected within 100 ms.
The trip time stated is the measuring period during which the trip condition must con-
stantly be fulfilled in order for the protection function to release a trip signal.
The accuracy of voltage and frequency measurements must be ±1% of Uc and ±0.05 Hz
or better respectively.
The frequency measurement used to calculate the frequency change is based on a 200 ms
measuring period where the mean value is calculated.
ROCOF [Hz/s] must be calculated as the difference between the currently performed
frequency mean value calculation and the calculation performed 20 ms before.
If a power-generating plant is isolated with part of the public electricity supply grid, the
plant must not cause temporary overvoltages that can damage the plant or the public elec-
tricity supply grid.
39
Requirements for type B power-generating plants
The DSO to whose grid the plant is connected calculates the setting values for the
synchronous undervoltage relay using the principles in the Research Association
of the Danish Electric Utilities (DEFU) technical report no. 293, 3rd edition on
‘Relay protection at local production with synchronous generators’, March 2018.
It is allowed to use a fuse instead of overcurrent (step 1). In this case, the fuse size and
characteristics must be approved by the DSO.
Symbol
Protection function Setting Trip time
[IEC]
40
Requirements for type B power-generating plants
2)** DSO
In Denmark, only passive islanding detection methods are used. The use of vector jump
relays (ANSI 78) or active islanding detection is not allowed on power-generating plants
connected to the Danish public electricity supply grid.
A power-generating plant must have the functions for islanding detection specified in
table 4.8. Unless otherwise agreed with the DSO, the default value in the table is used.
The ranges and resolutions are indicative, not required.
4.5.5. Earthing
Conditions related to earthing of the power-generating plant must be agreed with the
DSO.
41
Requirements for type B power-generating plants
4.6.1.1. DC content
A power-generating plant must not inject DC currents into the grid. This requirement is
met if the DC content of the current injected by the plant into the grid is below 0.5% of
the nominal current of the plant.
The reason for having a limit value for DC content is that DC currents are unde-
sirable in the public electricity supply grid and may have an adverse effect on
grid operation and protection. The limit value is set based on IEC/TR 61000-3-15,
which provides recommendations for requirements for local production connected
to the public electricity supply grid at low-voltage level.
Requirements for unbalance are made because unbalance in phase voltages be-
tween phases is undesirable in the public electricity supply grid as it may have an
adverse effect on grid operation and the units connected to the public electricity
supply grid.
According to the international standard DS/EN 50160, the limit for the total volt-
age unbalance in the public electricity supply grid is 2%. Voltage unbalance can
be distributed in accordance with the method described in IEC/TR 61000-3-13,
but this will yield impractically low limit values for the individual plant, which
are lower than the measurement uncertainty for measurement of unbalance.
When the plant has a balanced three-phase load, it will generally not add to the
voltage unbalance already present in the public electricity supply grid. Documen-
tation showing that the plant has balanced three-phase production will often be
sufficient to establish that the plant will not give rise to voltage unbalance in the
public electricity supply grid.
To ascertain that the plant does not give rise to voltage unbalance, the voltage
unbalance can be measured at the Point of Connection (POC) before and after
commissioning of the plant. If there is no significantly increased voltage unbal-
ance after commissioning of the plant compared to the measurements made before
commissioning, the voltage unbalance requirement is met.
42
Requirements for type B power-generating plants
Requirements for rapid voltage changes are based on DS/EN 61000-3-11 and the
Research Association of the Danish Electric Utilities (DEFU) report RA 557 as
well as the methods for determining limit values described in IEC/TR 61000-3-7.
4.6.1.4. Flicker
A power-generating plant must not cause flicker contributions exceeding the limit values
for short-term and long-term flicker as specified in table 4.10.
Flicker limit values are based on DS/EN 61000-3-11 and the Research Associa-
tion of the Danish Electric Utilities (DEFU) report RA 557 as well as the methods
for determining limit values described in IEC/TR 61000-3-7.
4.6.1.5. Harmonics
A power-generating plant may not emit harmonic currents exceeding the limit values in
table 4.11 for the individual harmonics, which are expressed as a percentage of the nomi-
nal current of the plant (Ih/In (%)).
3 5 7 9 11 13 15 2 4 6 8 10 12
3.4 3.8 2.5 0.5 1.2 0.7 0.35 0.5 0.5 1.0 0.8 0.6 0.5
In addition to the limit values for the individual harmonics, there are also limit values for
total harmonics. Limit values for THDI and PWHDI are specified in table 4.12.
43
Requirements for type B power-generating plants
THDI PWHDI
4.4 4.4
Table 4.12 – Limit values for THDI and PWHDI in current (% In).
The requirements for individual harmonics, THDI and PWHDI, are based on
DS/EN 61000-3-12 Table 3 and the Research Association of the Danish Electric
Utilities (DEFU) report RA 557 as well as the methods for determining limit val-
ues described in IEC/TR 61000-3-6.
The 2nd and 4th harmonic order are reduced compared to the method in RA 557,
because they may indicate DC content in the current supplied to the public elec-
tricity supply grid. Any exceeding of the limit values for the 2nd or 4th harmonic
orders may indicate that the plant does not meet the requirement for DC content.
Triplen harmonics are added based on their ratio of the limit values in DS/EN
50160. Triplen harmonics should not occur at all in balanced three-phase equip-
ment. However, three-phase inverters have been observed to produce these har-
monics at times due to the inverter control. Therefore, it has been decided to add
a limit value for them. In practice, the limit values for triplen harmonics in these
instructions have been set so high that they should never constitute a problem in a
balanced three-phase plant. If a plant exceeds these limits, this will indicate that
the plant cannot be categorised as being balanced, and it can therefore not be
connected, because it does not comply with the unbalance requirements.
Frequency (Hz)
75 Hz 125 Hz >175 Hz
0.44 0.66 83 *)
𝑓
*)
However, not less than the measurement uncertainty.
Limit values for interharmonic overtones are based on DS/EN 61000-3-12 and the
Research Association of the Danish Electric Utilities (DEFU) report RA 557 as
well as the methods for determining limit values described in IEC/TR 61000-3-6.
44
Requirements for type B power-generating plants
Limit value
0.2%
Table 4.14 – Limit value for harmonic currents for all frequencies between 2 kHz and 9 kHz stated in
per cent of In.
Limit value for distortions in the 2-9 kHz frequency range is based on the Re-
search Association of the Danish Electric Utilities (DEFU) report RA 557.
The power-generating plant owner must verify that emission limits at the Point of Con-
nection (POC) are complied with.
For calculation of power quality, the power-generating plant owner uses the typical three-
phase short-circuit power, Sk,powerquality at the Point of Connection (POC).
Subject to agreement, the plant owner can buy additional services (higher short-
circuit power or scope) from the DSO in order to comply with the specified limit
values.
The DSO must specify the short-circuit level Sk,powerquality with associated impedance angle
ψk at the Point of Connection (POC).
Measurement of harmonic distortion of voltage and current must be carried out as defined
in IEC 61000-4-7 in accordance with the principles (harmonic subgroup) and with the
accuracies specified for class I.
45
Requirements for type B power-generating plants
Measurement of distortions in the 2-9 kHz frequency range must be carried out as defined
in IEC 61000-4-7 Annex B and must be measured in 200 Hz windows with centre fre-
quencies from 2100 Hz to 8900 Hz.
A power-generating plant must be capable of ceasing its active power generation. Genera-
tion must be stopped no later than five seconds after the command to this effect has been
received. Furthermore, a power-generating plant must be capable of reducing active pow-
er upon receiving a command.
Figure 4.12 – Requirements for information which a power-generating plant below 1MW must be
capable of exchanging.
Remote control of these signals is assessed by the DSO at the time of grid connection.
A power-generating plant may start production after the requirements for reconnection
are fulfilled (see sect.4.2), and “Released for start” is received.
46
Requirements for type B power-generating plants
Current Measurement
Voltage Measurement
Q control Enabled/disabled
Table 4.15– Requirements for information which a power-generating plant of 1 MW or more must be
capable of exchanging in real time in the PCOM interface.
A power-generating plant may start production after the requirements for reconnection
are fulfilled (see sect. 4.2), and “Released for start” is received.
47
Requirements for type B power-generating plants
The power-generating plant owner is responsible for complying with the requirements
described in this document and for documenting such compliance.
The DSO may at any time request verification and documentation showing that the pow-
er-generating plant meets the requirements described in this document.
• CE Declaration of Conformity
• Protection functions
• Single-line diagram
• Power quality
• Tolerance of voltage dips
• Annex B1.1 complete with technical documentation in support of the answers
given.
• Annex B1.2 completed.
Product certificates issued by an approved certification body may also be used. The prod-
uct certificates may cover some of the documentation requirements.
4.8.2. Tests
As part of the documentation of the power-generating plant’s technical properties, testing
must be performed to demonstrate compliance with the requirements of this document.
The tests to be carried out include:
4.8.3. Simulations
As part of the documentation of the power-generating plant’s technical properties, simu-
lations must be performed to demonstrate compliance with the requirements of this doc-
ument. The simulations to be carried out include:
• Power response to overfrequency (LFSM-O)
o Must be carried out for frequency changes in both steps and ramps.
o Must show how the power-generating plant reacts when reaching the
lower active power limit.
• Tolerance to voltage dips
• Active power recovery
48
Requirements for type B power-generating plants
Simulation results and simulation model must be validated against the tests carried out to
demonstrate that model and simulations are accurate.
Product certificates issued by an approved certification body may be used instead of sim-
ulations.
CE Declaration of Conformity
CE Declarations of Conformity must be submitted for each of the main compo-
nents. The CE Declaration of Conformity must contain a list of relevant stand-
ards, codes of practice and directives which the component or plant complies
with.
Protection functions
Documentation of protection settings is a list of all relay configurations at the
time of commissioning.
Single-line diagram
A single-line diagram is a drawing that shows the plant’s main components and
how they are electrically interconnected. In addition, the location of the protec-
tion and measuring points are included in the diagram.
Power quality
Power quality is a collection of parameters characterising the electricity supplied.
A certificate or report demonstrating that the requirements are complied with
must be presented.
Completion of annexes
A completed Annex B1.1 means that the annex in these instructions must be com-
pleted, and that technical documentation verifying the correctness of the answers
given in the annex must be attached. Technical documentation may include a test
report, product certificate, user manual, simulations, etc.
49
Requirements for type C power-generating plants
5.2.1. Synchronisation
Same as for type B.
Active power control must be performed with a gradient of at least 1% P n/min for syn-
chronous power-generating plants and at least 20% Pn/min for power park modules. For
synchronous generators, there is also a 10 minutes reaction time, if required.
50
Requirements for type C power-generating plants
To be able to detect islanding, upward regulation of the active power at the Point of
Connection (POC) must not be initiated until after an intentional delay of 500 ms.
If the plant’s natural delay (recovery time) for commencement of upward regula-
tion is 500 ms or more, the requirement for minimum delay is met.
If the plant’s natural delay (recovery time) for commencement of upward regula-
tion is less than 500 ms, the delay must be extended to 500 ms. The intentional de-
lay is only imposed when transitioning to frequency response, i.e. when the fre-
quency threshold fRU is crossed.
Example
A plant’s natural delay (recovery time) for commencement of upward regulation
is 300 ms. An additional intentional delay (recovery time) of 200 ms is added to
make the total delay/recovery time for the plant 500 ms.
Upward regulation of active power must be initiated at a frequency threshold (fRU) and
follow a droop as indicated in figure 5.1.
51
Requirements for type C power-generating plants
P/Pn
f< fRU
(49.x Hz)
The frequency threshold for commencement of frequency response (fRU) must be set in
the 49.5 Hz - 49.8 Hz frequency range, both values inclusive, with a resolution of 10 mHz
or better.
The droop of the active power increase must be in the 2-12% range with a resolution of
1% or better.
The settings for frequency response during underfrequency for Western and Eastern
Denmark are as follows:
DK 1 DK 2
(Western (Eastern
Denmark) Denmark)
When the frequency response is enabled, the active power must follow the droop with an
accuracy of 5% of nominal active power or better, measured over a period of one minute.
Supply of frequency response in case of underfrequency must take the availability of the
primary energy source into consideration as well as the permitted reduction of active
power at underfrequency, see section 5.1.2.2.
52
Requirements for type C power-generating plants
Frequency control must be set in the 47.5 Hz - 51.5 Hz frequency range, both values in-
clusive. This frequency range includes frequency response for both underfrequency and
overfrequency as well as frequency control with deadband as shown in figure 5.2.
P/Pn
Frequency Frequency
response Frequency control response
(Underfrequency) (Overfrequency)
1
The actual frequency control is between fRU and fRO, which are the activation frequencies
for frequency response for underfrequency and overfrequency.
Control of power-generating plant active power with respect to frequency must be initiat-
ed within two seconds of a grid frequency change.
The measurement accuracy for the grid frequency must be ±10 mHz or better.
Frequency control must follow a droop as shown in figure 5.2. It must be possible to set a
negative slope droop in the 2-12% range with a resolution of 1% or better.
53
Requirements for type C power-generating plants
The active power ΔP/Pn, which is used for frequency control, must be set in the 1.5%-
10% range of power-generating plant maximum power capacity.
It must be possible to set a deadband around the nominal frequency in the 49.5 - 50.5 Hz
frequency range with a width of 0 - 500 mHz.
DK 1 DK 2
(Western (Eastern
Denmark) Denmark)
54
Requirements for type C power-generating plants
Min. 1% of Pn/min.
Min. 1% of Pn/min.
Table 5.3 – Maximum and minimum gradients in connection with upward and downward regulation.
Control to a new parameter value for the delta power limit must be initiated within two
seconds and completed within five minutes of receipt of a parameter change.
Delta power constraint is typically used to obtain a control reserve for upward
regulation in connection with frequency control of plants with varying availability
of the primary energy source, e.g. solar and wind power.
To ensure system stability, a wind power plant must be capable of gradually reducing
active power at high wind speeds to prevent sudden loss of active power when the wind
speed exceeds the wind power plant’s overspeed limitation.
The active power reduction must be within the shaded blue band as shown in figure 5.3.
Reduction can be continuous or in discrete steps. If the reduction is performed in discrete
steps, the step size must not exceed 25% of Pn. The settings for reduction of active power
at high winds must be agreed with the DSO prior to commissioning the wind power plant.
55
Requirements for type C power-generating plants
P/Pn
The power-generating plant must be capable of controlling its reactive power using the
functions and characteristics described in sections 5.4.2 to 5.4.4. It must be possible to
indicate set points in steps of 100 kVAr or better for reactive power and 0.01 or better for
Power Factor.
Control accuracy must be ±3% of Qn or better. The control accuracy is measured over a
period of one minute.
When one or more units of a power park module are taken out of operation for scheduled
maintenance, the plant’s supply of reactive power may be reduced proportionate to the
number of units taken out of operation.
The power-generating plant owner must compensate for the plant infrastructure’s reactive
power in situations where the plant is disconnected or not generating active power.
56
Requirements for type C power-generating plants
Required capability
Allowed to reduce active power to deliver
reactive power because of technical limitations.
U/Uc
1.10
1.05
1.04
0.2 0.4
Q/Pn
0.95
0.90
Q-import Q-eksport
0.85
Underexcited Overexcited
Figure 5.4 – Requirements for supply of reactive power at maximum active power generation.
Inside the hatched grey region in figure 5.4, the synchronous power-generating plant must
supply stable reactive power in accordance with the selected control mode, which may
only be limited by the technical performance of the plant, e.g. saturation or undercompen-
sation.
57
Requirements for type C power-generating plants
Required capability
Allowed to reduce active power to deliver
reactive power because of technical limitations.
U/Uc
1.10
1.05
1.04
Q/Pn
0.329 0.329
0.96
0.95
0.90
Q-import Q-export
Underexcited Overexcited
0.85
Figure 5.5 – Requirements for supply of reactive power at maximum active power generation.
Inside the hatched grey region in figure 5.5, the power park module must supply stable
reactive power in accordance with the selected control mode, which may only be limited
by the technical performance of the plant, e.g. saturation or undercompensation.
When active power generation is below the maximum capacity, a power park module
must be capable of operating within the area specified in figure 5.6.
In the solid blue area on figure 5.6, it is accepted that the ability to supply reactive power
may be limited by a reduced number of units in operation due to start-up and shutdown of
power park modules as a result of lacking primary power.
58
Requirements for type C power-generating plants
Required capability
Reduced accuracy allowed during low production
P/Pn
PF = 0.95 PF = -0.95
1
Inductive/Leading Capacitive/Lagging
Q/Pn
-0.329 0.329
Figure 5.6 – Requirements for supply of reactive power at different active power levels.
The voltage control droop slope must be set within the 2% - 7% range in steps no greater
than 0.5%.
The deadband must be set within ±5% of Uref with a step size of not more than 0.5% of
Uref and must be symmetric around the voltage control set point.
59
Requirements for type C power-generating plants
U/Uc
1.05
PF = 0.95 PF = -0.95
0.95
Q
- Qn Qn
The power-generating plant must be capable of achieving 90% of the reactive power
change within one second, and control must be completed within five seconds.
Unless otherwise agreed, this control function must be disabled. If the function is to be
enabled, the parameter values for the control function are agreed with the DSO.
5.4.4. Q control
Same text as for type B. However, with requirements for faster control.
Control from one set point to another must be initiated within two seconds and completed
within 30 seconds.
5.5. P ROTECTION
5.5.1. General
Same as for type B.
60
Requirements for type C power-generating plants
5.5.5. Earthing
Same as for type B.
In cases when a power-generating plant may have a significant impact on the public elec-
tricity supply grid (the distribution system and/or the transmission system), additional
requirements may apply, see section 5.6.2.
61
Requirements for type C power-generating plants
5.6.1.1. DC content
Same as for type B.
5.6.1.4. Flicker
The power-generating plant must comply with the flicker limit defined by the DSO.
When defining the requirements, the DSO uses the method described in IEC/TR
61000-3-7.
5.6.1.5. Harmonics
The power-generating plant must comply with the voltage limit values for harmonics
emissions defined by the DSO.
When defining the requirements, the DSO uses the method described in IEC/TR
61000-3-6.
When defining the requirements, the DSO uses the method described in IEC/TR
61000-3-6.
62
Requirements for type C power-generating plants
The power-generating plant owner must verify that emission limits at the Point of Con-
nection (POC) are complied with.
For calculation of power quality, the power-generating plant owner uses the typical three-
phase short-circuit power, Sk,powerquality at the Point of Connection (POC).
The DSO and the transmission system operator will perform a joint assessment of wheth-
er or not a power-generating plant may have significant impact on the public electricity
supply grid.
For power-generating plants with a significant impact on the public electricity supply
grid, the plant owner must also:
• Use frequency-dependent impedance loci to calculate power quality
• Verify that emission limits are also complied with towards the transmission sys-
tem
• Be capable of supplying an impedance model for the power-generating plant, see
section 5.8.
Compliance with emission limits for plants with a significant impact on the elec-
tricity supply grid is typically verified by performing calculations on a model
model given by the DSO, where one or two points in the model will contain emis-
sion limits to be complied with.
Subject to agreement, the plant owner can buy additional services (higher short-
circuit power or subscribed capacity) from the DSO in order to comply with the
specified limit values.
The DSO must specify the short-circuit level Sk,powerquality with associated short-circuit
angle ψk at the Point of Connection (POC).
63
Requirements for type C power-generating plants
The DSO must also state the frequency-dependent grid impedance at the Point of Connec-
tion (POC) Znet,h. The DSO may choose to state the grid impedance as a measured value
or as an approximate model. Using impedance loci, the grid company passes on the im-
pedance loci from the transmission system operation, adjusted to account for any inter-
mediate systems.
R50 and X50 are resistance and reactance at 50 Hz. They are calculated from
Sk,powerquality and the matching short-circuit angle ψk.
If a power-generating plant consists of more than one unit, a plant controller must be
installed to allow control of the whole plant at the PCOM, see figure 3.3 and figure 3.4.
64
Requirements for type C power-generating plants
Current Measurement
Voltage Measurement
Q control Enabled/disabled
Table 5.5 – Requirements for information which a power-generating plant must be capable of exchang-
ing in real time in the PCOM interface.
65
Requirements for type C power-generating plants
The power-generating plant owner must install logging equipment (a digital fault record-
er) at the Point of Connection (POC), which at least records:
Specific requirements for measurements are described in the grid connection agreement.
Logging must be performed as correlated time series of measuring values from ten sec-
onds before an event until 60 seconds after the event.
The specific settings for event-based logging must be agreed with the DSO and the
transmission system operator during plant commissioning.
All measurements and data exchanged at the PCOM must be logged with a time stamp
and an accuracy ensuring that they can be correlated with each other and with similar
records in the public electricity supply grid.
Logs must be kept on file for a minimum of three months after a fault event; up to a max-
imum 100 event logs.
The DSO and the transmission system operator must, upon request, be given access to log
data and other relevant information.
66
Requirements for type C power-generating plants
For power-generating plants with a capacity under 10 MW, the DSO can, in exceptional
circumstances, require that the plant owner delivers a simulation model. In this case, the
requirements are the same as for plants above 10 MW.
The power-generating plant owner is responsible for complying with the requirements
described in this document and for documenting such compliance.
The DSO may at any time request verification and documentation showing that the pow-
er-generating plant meets the requirements described in this document.
The documentation must be submitted to the DSO as part of the process for obtaining
operational notification. During the process, several types of permits must be obtained
before the final operational notification is issued. The permit stages are as follows:
To obtain final operational notification, the plant owner must submit Annex B2.2. Once
the DSO approves the documentation, the final operational notification is issued.
If the DSO does not receive Annex B2.2 before expiry of the interim operational
notification, the DSO is entitled to electrically disconnect the plant, as a valid op-
erational notification no longer exists after expiry of the interim operational noti-
fication.
If, based on Annex B2.2, the DSO deems that the plant does not comply with the
requirements of these instructions, a plan must be prepared for remedying the
outstanding items identified. The plan can be used to apply for an extension of the
interim operational notification.
Product certificates may be used as part of the documentation for compliance with the
requirements of this document.
67
Requirements for type C power-generating plants
• CE Declaration of Conformity
• Protection functions
• Single-line diagram
• Power quality
• Tolerance of voltage dips
• P-Q capability curve
• Signal list
• Simulation model
• Conformance testing plan
• Verification report
• Annex B2.1 complete with technical documentation in support of the answers
given.
• Annex B2.2 complete with technical documentation in support of the answers
given.
Product certificates issued by an approved certification body may also be used. The prod-
uct certificates may cover some of the documentation requirements.
5.9.2. Tests
As part of the documentation of the power-generating plant’s technical properties, testing
must be performed to demonstrate compliance with the requirements of this document.
The tests to be carried out include:
5.9.3. Simulations
As part of the documentation of the power-generating plant’s technical properties, simu-
lations must be performed to demonstrate compliance with the requirements of this doc-
ument. The simulations to be carried out include:
• Power response to overfrequency (LFSM-O)
o Must be carried out for frequency changes in both steps and ramps.
o Must show how the plant reacts when reaching the lower active power
limit.
• Tolerance to voltage dips
68
Requirements for type C power-generating plants
Simulation results and simulation model must be validated against the tests carried out to
demonstrate that model and simulations are accurate.
Product certificates issued by an approved certification body may be used instead of sim-
ulations.
69
Requirements for type C power-generating plants
CE Declaration of Conformity
CE Declarations of Conformity must be submitted for each of the main compo-
nents. The CE Declaration of Conformity must contain a list of relevant stand-
ards, codes of practice and directives which the component or plant complies
with.
Protection functions
Documentation of protection settings is a list of all current relay configurations at
the time of commissioning.
Single-line diagram
A single-line diagram is a drawing that shows the plant main components and
how they are electrically interconnected. In addition, the location of the protec-
tion and measuring points are included in the representation.
Power quality
Power quality is a collection of parameters characterising the electricity supplied.
A certificate or report demonstrating that the requirements are complied with
must be presented.
70
Requirements for type C power-generating plants
Signal list
A list of signals which the plant can exchange with the DSO in accordance with
section 5.7.
Simulation model
A simulation model complying with the requirements in section 5.8.
Verification report
A report which uses the conformance testing to demonstrate that the plant com-
plies with the requirements of this document.
Completion of annexes
Completed annexes B2.1 and B2.2 means that the annexes in these instructions
must be completed, and that technical documentation verifying the correctness of
the answers given in the annexes must be attached. Technical documentation may
include a test report, product certificate, user manual, simulations, etc.
71
Requirements for type D power-generating plants
Recurring faults
The power-generating plant owner must ensure that the plant is protected against the me-
chanical and electrical consequences of a potential reconnection after symmetric, as well
as asymmetric faults, in the transmission system.
Any measures taken in this respect must not compromise any other specified power-
generating plant properties.
72
Requirements for type D power-generating plants
Synchronisation must be possible when the frequency is within the 47.5 Hz - 51.5 Hz
frequency range, both values inclusive.
The specific requirements for the synchronisation devices and their settings must be
agreed between the DSO and the plant owner prior to plant commissioning.
73
Requirements for type D power-generating plants
Inside the grey hatched region in figure 6.1, the synchronous power-generating plant must
supply stable reactive power in accordance with the selected control mode, which may
only be limited by the technical performance of the plant, e.g. saturation or undercompen-
sation.
Required capability
Allowed to reduce active power to deliver
reactive power because of technical limitations.
U/Uc
1.10
1.05
1.04
0.2 0.4
Q/Pn
0.95
0.90
Q-import Q-export
Underexcited 0.85 Overexcited
Figure 6.1 – Requirements for supply of reactive power at maximum active power generation.
74
Requirements for type D power-generating plants
Required capability
Allowed to reduce active power to deliver
reactive power because of technical limitations.
U/Uc
1.10
1.05
1.04
Q/Pn
0.329 0.329
0.96
0.95
0.90
Q-import Q-export
Underexcited Overexcited
0.85
6.4.4. Q control
Same as for type C.
6.4.5.1. Generator
For type D power-generating plants, requirements for SCR and transient reactance are
defined in cooperation with the DSO and the transmission system operator based on the
plant design and stability analyses. The permissible values must appear in the grid con-
nection agreement for the power-generating plant.
75
Requirements for type D power-generating plants
If an on-load tap changer is installed on the transformer, the on-load tap changer may be
used to comply with the requirements for reactive control properties, subject to agreement
with the DSO. It must appear in the grid connection agreement for the power-generating
plant if such an agreement is made.
If an on-load tap changer is used on the transformer, the power-generating plant owner is
responsible for proper coordination between the plant’s reactive power control functions
and the load tap changer control.
Excitation system
A synchronous power-generating plant must be equipped with an automatic excitation
system. The purpose is to ensure stable plant operation and to provide the opportunity to
contribute to voltage control and/or the reactive power balance in the public electricity
supply grid.
The excitation system must be designed in accordance with the European standard
DS/EN 60034-16-1:2011 ‘Rotating electrical machines – Part 16: Excitation systems for
synchronous machines – Chapter 1: Definitions’ and DS/CLC/TR 60034-16-3:2004 ‘Ro-
tating electrical machines – Part 16: Excitation systems for synchronous machines – Sec-
tion 3: Dynamic performance’.
In case of system faults resulting in voltage reduction, the generator must be capable of
over-excitation for at least ten seconds with 1.6 times excitation current and voltage at
nominal power and tan φ = 0.4 at the POC and normal operating voltage. If the over-
excitation property is dependent on the voltage at the POC, the mentioned property must
be available at reduced grid voltage at the POC down to 0.6 pu.
The generator’s over-excitation protection and other protection must be designed and
adjusted to allow the generator’s capacity for temporary overload to be utilised without
exceeding the generator’s thermal limits.
The excitation system’s limit functions must be selective with the power-generating
plant’s protection functions, enabling short-term utilisation of overload properties without
disconnecting the plant.
The excitation system’s dynamic response (measured at the generator terminals) during
idling (when the generator is disconnected from the grid and operated at nominal rpm) in
case of a temporary 10% change of the reference voltage must be non-oscillatory and
have a rise time, as defined in DS/EN 60034-16-3, of maximum 0.3 seconds for a static
excitation system. For excitation systems with rotating exciters, the maximum allowed
time response is 0.5 seconds in case of a positive 10% change of the reference voltage
and 0.8 seconds in case of a negative 10% change of the reference voltage.
76
Requirements for type D power-generating plants
Control of the PSS function must be performed so that significant damping is achieved in
the 0.2 - 0.7 Hz frequency range.
In the 0.2 - 2 Hz frequency range, the phase of the added damping signal, produced by the
PSS function, must be in phase with the change of the generator rotor speed. Deviations
of up to -30 degrees (under-compensated) are acceptable.
At all operating points and during any fault while the PSS function is enabled, damping
of plant power oscillations (an exponentially decreasing function) must be performed
within one second.
The power-generating plant’s natural damping of ‘local mode’ power oscillations must
not be adversely affected by the PSS function.
Control of the PSS function must be performed so that changes to the plant operating
point (active power) during normal operation or in case of a fault in for example the tur-
bine controller, boiler plant, feedwater plant or other auxiliary power systems, do not
cause voltage changes on the high-voltage side of the plant generator transformer of more
than 1%.
The PSS output signal must be limited to prevent that activation of the PSS function re-
sults in a change of generator voltage of more than ±5% of nominal generator voltage. It
is allowed for the voltage control to reduce the limits automatically and dynamically, e.g.
by activating the excitation system’s limit functions.
The PSS function must be automatically deactivated when the active power generated is
less than 20% of nominal power. It must be possible to connect and disconnect the PSS
function. Disconnection of the PSS function must trigger an alarm.
6.5. P ROTECTION
Furthermore, the power-generating plant owner must ensure that the plant is protected
against the mechanical and electrical consequences of a potential reconnection after
symmetric as well as asymmetric faults in the transmission system.
77
Requirements for type D power-generating plants
Any measures taken in this respect must not compromise any other specified plant prop-
erties.
6.5.5. Earthing
Same as for types B and C.
6.6.1.1. DC content
Same as for type C.
6.6.1.4. Flicker
Same as for type C.
6.6.1.5. Harmonics
Same as for type C.
78
Requirements for type D power-generating plants
Current Measurement
Voltage Measurement
Q control Enabled/disabled
79
Requirements for type D power-generating plants
6.9.2. Tests
As part of the documentation of the power-generating plant’s technical properties, testing
must be performed to demonstrate compliance with the requirements of this document.
The tests to be carried out include:
80
Requirements for type D power-generating plants
6.9.3. Simulations
As part of the documentation of the power-generating plant’s technical properties, simu-
lations must be performed to demonstrate compliance with the requirements of this doc-
ument. The simulations to be carried out include:
• Power response to overfrequency (LFSM-O)
o Must be carried out for frequency changes in both steps and ramps.
o Must show how the plant reacts when reaching the lower active power
limit.
• Tolerance to voltage dips
• Active power recovery
• Supply of fast fault current (only power park modules)
• Power response to underfrequency (LFSM-U)
o Must be carried out for frequency changes in both steps and ramps.
o Must show how the plant reacts when reaching the upper active power
limit.
• Frequency control (FSM)
• Islanding (same characteristics with a weaker grid)
• Reactive power operating range
• Damping of oscillations (PSS)
Simulation results and the simulation model must be validated against the tests carried out
to demonstrate that model and simulations are accurate.
Product certificates issued by an approved certification body may be used instead of sim-
ulations.
Simulation, analysis and commissioning test must be used to document the satisfactory
dynamic characteristics of the excitation system.
81
Requirements for type D power-generating plants
Simulation, analysis and commissioning tests must be used to document that the setting
values applied result in the PSS function and the overall excitation system having satis-
factory dynamic characteristics.
The simulations performed must include the test scenarios below. With the exception of
Test 5, they must all be performed with the PSS function activated and deactivated, re-
spectively:
82
Requirements for type D power-generating plants
83
Requirements for type D power-generating plants
CE Declaration of Conformity
CE Declarations of Conformity must be submitted for each of the main compo-
nents. The CE Declaration of Conformity must contain a list of relevant stand-
ards, codes of practice and directives which the component or plant complies
with.
Protection functions
Documentation of protection settings is a list of all current relay configurations at
the time of commissioning.
Single-line diagram
A single-line diagram is a drawing that shows the plant main components and
how they are electrically interconnected. In addition, the location of the protec-
tion and measuring points are included in the representation.
Power quality
Power quality is a collection of parameters characterising the electricity supplied.
A certificate or report demonstrating that the requirements are complied with
must be presented.
84
Requirements for type D power-generating plants
Signal list
A list of signals which the plant can exchange with the DSO in accordance with
section 6.7.
Simulation model
A simulation model complying with the requirements in section 6.8.
Verification report
A report which uses the conformance testing to demonstrate that the plant com-
plies with the requirements of this document.
Completion of annexes
Completed annexes B2.1 and B2.2 means that the annexes in these instructions
must be completed, and that technical documentation verifying the correctness of
the answers given in the annexes must be attached. Technical documentation may
include a test report, product certificate, user manual, simulations, etc.
85
Documentation for type B power-generating plants
6 Identification
Power-generating plant name:
Other*
*Describe type:
86
Documentation for type B power-generating plants
Manufacturer/model:
Document reference:
Document reference:
Type/Model:
87
Documentation for type B power-generating plants
Type/Model:
Does the excitation system comply with relevant parts of the Yes
following European standards?: No
12
Type/Model:
88
Documentation for type B power-generating plants
tion enclosed? No
14
15
16 Normal operation
Within the normal operating range, see figure 4.1. Is the power- Yes
generating plant capable of starting up and generating continuously, No
limited only by the grid protection settings?
17
Will the power-generating plant remain connected to the public elec- Yes
tricity supply grid in case of frequency deviations as specified in sec- No
tion 4.1.1?
Is the active power reduction at underfrequency less than the limit Yes
specified in section 4.1.2.2? No
89
Documentation for type B power-generating plants
19
Does the power-generating plant stay connected to the public electrici- Yes
ty supply grid during voltage dips as specified in section 4.1.3.3? No
Does the power-generating plant stay connected to the public electrici- Yes
ty supply grid during voltage swells as specified in section 4.1.3.2? No
21
Does the power park module supply fast fault current as specified in Yes
section 4.1.3.3 (b)? No
25
90
Documentation for type B power-generating plants
28
30
Is the power-generating plant equipped with ramp rate limit as speci- Yes
fied in section 4.3.2.2? No
32
Where can documentation showing that this requirement has been met be
found?
Where can documentation showing that this requirement has been met be
found?
35
91
Documentation for type B power-generating plants
37
39
40 B1.1.8.4. Q control
41
42 Power quality
43
44
92
Documentation for type B power-generating plants
Does the power-generating plant comply with the limit value for rapid Yes
voltage changes specified in section 4.6.1.3? No
46
47 B1.1.9.2. DC content
48 Please only complete this section for power park modules.
Does the DC content during normal operation exceed 0.5% of nominal Yes
current, as specified in section 4.6.1.1? No
49
Does the plant have balanced three-phase load, as specified in section Yes
4.6.1.2? No
52
53 B1.1.9.4. Flicker
54 Please only complete this section for power park modules.
Is the flicker contribution for the entire plant below the limit value Yes
specified in section 4.6.1.4? No
55
56 B1.1.9.5. Harmonics
57 Please only complete this section for power park modules.
Are all the harmonics for the entire plant below the limit values speci- Yes
93
Documentation for type B power-generating plants
fied in 4.6.1.5? No
58
Are all the interharmonic overtones for the entire plant below the limit Yes
values specified in section 4.6.1.6? No
61
Are emissions of distortions in the 2-9 kHz frequency range less than Yes
0.2% of In as required in section 4.6.1.7? No
64
65 Protection
66
94
Documentation for type B power-generating plants
68
73
74 Signature
Date:
Installation contractor:
Commissioning manager:
Signature (commissioning
manager):
Plant owner:
75
76
77
95
Documentation for type B power-generating plants
81 Identification
Power-generating plant name:
82
85
96
Documentation for type B power-generating plants
________kW
87
89
91 B1.2.3.1. Q control
92
94
97
Documentation for type B power-generating plants
96
97 Protection
102
110 Signature
Date:
98
Documentation for type B power-generating plants
Installation contractor:
Commissioning manager:
Signature (commissioning
manager):
Plant owner:
111
112
113
99
Documentation for type C and D power-generating plants
120 Identification
Power-generating plant name:
121
Other*
*Describe type:
100
Documentation for type C and D power-generating plants
Manufacturer/model:
Document reference:
123
Type/Model:
101
Documentation for type C and D power-generating plants
126
Type/Model:
128
Type/Model
Does the excitation system comply with relevant parts of the Yes
following European standards?: No
102
Documentation for type C and D power-generating plants
131
134
136
137
103
Documentation for type C and D power-generating plants
Will the power-generating plant remain connected to the public elec- Yes
tricity supply grid in case of frequency deviations as specified in sec- No
tions 5.1.2.1 and 6.1.2.1 for type C and D plants, respectively?
Is the active power reduction at underfrequency less than the limit Yes
specified in section 4.1.2.2? No
139
Will the power-generating plant remain connected to the public elec- Yes
tricity supply grid in case of voltage dips as specified in sections No
5.1.3.2 and 6.1.3.2 for type C and D plants, respectively?
Will the power-generating plant remain connected to the public elec- Yes
tricity supply grid in case of voltage swells as specified in sections No
5.1.3.1 and 6.1.3.1 for type C and D plants, respectively?
141
Does the power park modules supply fast fault current as specified in Yes
section 5.1.3.2 or 6.1.3.2 for type C and D plants, respectively? No
104
Documentation for type C and D power-generating plants
144 B2.1.5.2. Recurring voltage dips in the public elect ricity supply grid
145 Please only complete this section for type D power-generating plants.
Will the power-generating plant remain connected in case of
recurring voltage dips at the POC as specified in section Yes
6.1.3.2? No
146
147
149
152
153
105
Documentation for type C and D power-generating plants
155
156
158
159
161
162
164
165
106
Documentation for type C and D power-generating plants
Is the plant equipped with a delta power limit function as specified in Yes
sections 5.3.4.3 and 6.3.4.3 for type C and D plants, respectively? No
168
169
Is the power-generating plant equipped with a ramp rate limit function Yes
as specified in sections 5.3.4.2 and 6.3.4.2 for type C and D plants, No
respectively?
171
172
Is it possible to use the resolution specified in sections 5.4 and 6.4 for Yes
type C and D plants, respectively, for the set point values? No
107
Documentation for type C and D power-generating plants
175
176
178
179
181
182
184
108
Documentation for type C and D power-generating plants
187
Does the power-generating plant comply with the limit value for rapid Yes
voltage changes specified in sections 5.6.1.3 and 6.6.1.3 for type C and No
D plants, respectively?
189
Does the DC content during normal operation exceed the limit values Yes
specified in sections 5.6.1.1 and 6.6.1.1 for type C and D plants, re- No
spectively?
192
Does the plant have balanced three-phase load, as specified in sections Yes
5.6.1.2 and 6.6.1.2 for type C and D plants, respectively? No
109
Documentation for type C and D power-generating plants
195
Is the plant’s flicker contribution below the limit values specified in Yes
sections 5.6.1.4 and 6.6.1.4 for type C and D plants, respectively? No
198
Are all plant harmonic distortions below the limit values specified in Yes
sections 5.6.1.5 and 6.6.1.5 for type C and D plants, respectively? No
201
Are all plant interharmonic overtones below the limit values specified Yes
in sections 5.6.1.6 and 6.6.1.6 for type C and D plants, respectively? No
204
The requirement for emission of distortions in the 2-9 kHz frequency Yes
range is specified by the DSO. Is the requirement met? No
110
Documentation for type C and D power-generating plants
207
208 Protection
Is the plant equipped with the protection functions required in sections Yes
5.5.3 and 6.5.3 for type C and D plants, respectively? No
209
211
111
Documentation for type C and D power-generating plants
217
218
220
112
Documentation for type C and D power-generating plants
222
225
226 Signature
Date:
Installation contractor:
Commissioning manager:
Signature (commissioning
manager):
113
Documentation for type C and D power-generating plants
Plant owner:
227
228
229
114
Documentation for type C and D power-generating plants
234 Identification
Power-generating plant name:
235
238
115
Documentation for type C and D power-generating plants
241
243
116
Documentation for type C and D power-generating plants
245
248
250
252
117
Documentation for type C and D power-generating plants
No
Controlled
online
255
256 Protection
258
260
261
262 Signature
Date:
Installation contractor:
Commissioning manager:
Signature (commissioning
manager):
Plant owner:
118
Documentation for type C and D power-generating plants
263
264
119