Table of Contents: Method Statement FOR Lightning Protection System Installation
Table of Contents: Method Statement FOR Lightning Protection System Installation
FOR
LIGHTNING PROTECTION SYSTEM INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1.SCOPE
This procedure to clear the method of the supply, installations for
Lightning Protection System for the project.
This document details the Lightning Protection System Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
4. OPERATION
Material:
Installation:
Site survey of the proposed Lightning Protection System based on
approved CSD by foreman/sub-contractor together with Engineer.
Installation must be carried out based on approved shop drawings
& samples by foreman/ sub-contractor.
Method and material used for the installation of Lightning protection
system shall comply BS6651. (Protection of structure against
lightning).
The earth electrode pits location shall be marked out on site before
commencement of hammering in electrodes. The earth pits shall be
near the location of the down conductors.
Those earth pits located in the basement shall be provided with
seals to prevent penetration of the ground slab.
Electrodes are hammered into the ground and reading is taken to
ensure that the resistance is less than 10 ohms per electrode.
Lightning Protection System accessories.
Earth termination network: The means of dissipating the current to
the general mass of earth. Choose an earth electrode to suit the
ground conditions in the locality of the structure. Electrodes are
available in the form of rods and plates (lattice or solid)
Earth rod clamps: Select a high copper content alloy earth rod
clamp for the connection of the earthing conductor to the earth rod.
In this below ground application, the clamp must ensure a good
electrical contact and resist corrosion throughout the lifetime of the
installation.
Earth inspection chambers: Select an earth inspection chamber to
protect the earth electrode connections.
Bonding: Bonding is the most commonly employed method of
avoiding the damaging effects of side flashing. All continuous
metalwork should be considered for bonding. All metallic services,
eg cable armouring, gas, water or steam piping, entering the
building should also be bonded as directly as possible to the earth
termination network.
Select the correct type of metalwork bond for the application, ie a
flat column face, a circular rainwater pipe or a ribbed reinforcing
bar.
Depending on the specification, the down conductor tapes can be
thermal weld to the rebar and casted in the column or run in a
continuous strip on the surface of the external wall.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
2. To ensure that his assistant foreman/ charge hand are aware of
the job requirements and they have enough information to carry
out their duties properly.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
Lightning Protection System Components and Accessories
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Lightning Protection works will be
as follows:
1. Center punch
2. Brace
3. Hammer
5. Diagonal-Cutting Pliers
7. Side-Cutting Pliers
8. Level
9. Shank Screwdriver
10. P.P.E. – Personal Protective Equipment (safety helmet, Boots, gloves
& safety vest )
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information / action / comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper