Q.1) Which one is the type of detailed specification

A) Technical Specification
B) Manufacturers Specification
C) Particular Specification
D) Open Specification
Ans- A

Q.2) Unit mode of measurement of excavation for foundation

A) Number
B) Length
C) Sq.m
D) Cubic per meter
Ans-D

Q.3) Unit mode of measurement of P.C.C


3
A) m
A) Sq.m
B) L*B*H in cubic meter
C) None of these
Ans- C

Q.4) In dam proof course which cement can be used

A) Portland pozzolana cement


B) Ordinary Portland cement
C) Rapid hardening cement
D) sulphate resisting cement
Ans- B

Q.5) Ceramic tile flooring nominal size of tile is

A) 80*80mm
B) 120*120mm
C) 150*150mm
D) 90*90mm
Ans- C
Q.6) Which factor affecting rate analysis

A) Place of work
B) Miscellaneous
C) labour cost
D) All of the above
Ans- D

Q.7) Overhead charges are taken as

A) 2%
B) 5%
C) 1%
D) 3%
Ans- B

Q.8) Item of construction which an average labourer of particular category can complete in

A) Four Clock hour


B) Six clock hour
C) Eight clock hour
D) None of these
Ans- C

Q.9) As per Maharashtra gov. P.W.D quantity per day of Ashlar masonary

A) 0.40cu.m
B) 0.20cu.m
C) 1.00cu.m
D) 8.00sq.m
Ans- A

Q.10) 12mm thick plastering with lime or cement quantity per day

A) 3.00 cu.m
B) 8.00 sq.m
C) 10.00 sq.m
D) 35.00 sq.m
Ans- B

Q.11) Horizontal distance between the trench pit and the place is known as

A) Lift
B) Loading
C) Lead
D) None of these
Ans- C

Q.12) vertical movement of material is called

A) Unloading
B) Lead
C) Both A & B
D) Lift
Ans- D
Q.13) normally lead is taken as

A) 25m
B) 30m
C) 20m
D) 50m
Ans- D

Q.14) A load of sand of one tonne is equivalent


3
A) 0.675m
B) 1m
C) 0.5m
3
D) 1.3m
Ans- A

Q.15) How much percentage price increase for second floor

A) 2%
B) 1%
C) 3%
D) 4%
Ans- B

Q.16) Normally lift is taken as

A) 1m
B) 1.2m
C) 1.5m
D) 2m
Ans- C
Q.17) Contractor Profit is taken as

A) 20%
B) 10%
C) 1%
D) 5%
Ans- B

Q.18) In plastering work how much percentage of mortar add to fill up joints

A) 20%
B) 30%
C) 40%
D) 50%
Ans- B

Q.19) Density of cement Construction material


A) 1440kg/m
3
B) 1480kg/m
3
C) 1440kg/m
D) 1445kg/m3
Ans- C
Q.20) Density of concrete Construction material
3
A) 2080kg/m
3
B) 1600kg/m
3
C) 2380kg/m
3
D) 2370kg/m
Ans- D

Q.21) Density of cement mortar Construction material


3
A) 2080kg/m
3
B) 1600kg/m
3
C) 2380kg/m
3
D) 2370kg/m
Ans- A

Q.22) Density of Brick Construction material


3
A) 2080 to 2200 kg/m
3
B) 1600 to 1920 kg/m
3
C) 2380 to 2580 kg/m
3
D) 2370 to 2470 kg/m
Ans- B

Q.23) Density of Dry sand Construction material

A) 1600kg/m
3
B) 1680kg/m
3
C) 1540kg/m
D) 1645kg/m3
Ans- A

Q.24) Density of River sand Construction material

A) 1800kg/m
3
B) 1680kg/m
3
C) 1840kg/m
3
D) 1745kg/m
Ans- C

Q.25) Density of Aggregate Construction material


3
A) 2080 to 2200 kg/m
3
B) 1600 to 1880 kg/m
3
C) 2380 to 2580 kg/m
3
D) 2070 to 2270 kg/m
Ans- B
Q.26) Volume of one cement bag is
3
A) 0.0347m
3
B) 0.0328m
3
C) 0.0447m
D) none of these
Ans- A
3
Q.27) The number of cement bags required in 1m
A) 28.5
B) 28
C) 28.8
D) 27.5
Ans- C

Q.28) Pick up the correct statement from the following

A) To find out the present rate per unit of item at locality


B) To fix up labour contract rates
C) To examine most economical method for construction
D) All of the above
Ans- D

Q.29) Pick up the incorrect factor of rate analysis from the following

A) Labours cost
B) Cost of tools & plants
C) Task work
D) Contractor’s profit
Ans- C

Q.30) Which data required for rate analysis

A) Market rate of materials


B) job overhead
C) Travelling expenses
D) All of the above
Ans- A

Q.31) The cost of construction material is taken as

A) 5% to 8%
B) 40% to 50%
C) 20 to 25%
D) 30 to 35%
Ans- B

Q.32) which factors affecting Task works


A) Job satisfaction & working condition may increase the out turn
B) To examine most economical method for construction
C) The maximum load which vehicle can safely carry
D) All of the above
Ans- A
Q.33) Per unit rate of Male Mazdoor

A) Rs.539
B) Rs.620
C) Rs.493
D) Rs.512
Ans- C

Q.34) per unit rate of Bhisti

A) Rs.539
B) Rs.620
C) Rs.493
D) Rs.512
Ans- D

Q.35) Cost of labour is taken as

A) 20%
B) 30%
C) 10%
D) 5%
Ans- B

Q.36) Select incorrect method of specification used in describing material :

A) Open Specification
B) Restricted Specification
C) Detailed Specification
D) Closed Specification
Ans- C

Q.37)How to store material, use and install them, this type specification is used

A) Open Specification
B) Restricted Specification
C) Particular specification
D) Manufacturer’s specification
Ans – D

Q.38)Choose Incorrect Principle of good specification

A) Correctly worded
B) Fair to both party
C) Dual meaning
D) Use Shall
Ans: C

Q.39)Choose Incorrect step , while drafting specification of Brickwork item

A) Mode of Measurement
B) Curing
C) Mixing cement mortar
D) Site Clearance
Ans: D
Q.40) Choose Incorrect step , while drafting specification of GI Sheet Roofing

A) Fixing Sheet
B) Curing
C) laps of sheet
D) Mode of Measurement
Ans: B
Q.41)Choose Incorrect factor of rate analysis

(a) Quantity of materials and cost (b) Labour cost

(c) Depreciation (d) Cost of equipments, tools and plants


Ans: C

Q.42)Which of following not include in Job Overhead

A) Amenities to labour
B) Telephone bill, rent and taxes
C) Salaries of all persons like engineer, supervisor
D) Compensation of worker
Ans: B

Q.43)Which of following not include in General Overhead

A) Amenities to labour
B) Telephone bill, rent and taxes
C) Stationary, printing, postage charges
D) Travelling expenses
Ans: A

Q.44) Sundris include

A) Binding wire used to tie bars, cover block


B) Cement bag
C) Machinery
D) labour Payment
Ans: A

Q.45)Incorrect example of Indirect cost is

A) Rent
B) Insurance
C) Machinery cost
D) Supervisor salaries
Ans: C

Q.46)Select correct relation of concrete

A) Dry volume of concrete = 52% more of wet volume of concrete


B) Dry volume of concrete = 25% more of wet volume of concrete
C) Dry volume of concrete = 30% more of wet volume of concrete
D) Dry volume of concrete = 35 more of wet volume of concrete
Ans: A
Q.47)Select correct relation of concrete

A) Dry volume of mortar= 52% more of wet volume of mortar


B) Dry volume of mortar= 25% more of wet volume of mortar
C) Dry volume of mortar= 30% more of wet volume of mortar
D) Dry volume of mortar= 35% more of wet volume of mortar
Ans: B

Q.48)How much % is add for wastages in brick quantity calculation

A) 20%
B) 30%
C) 10%
D) 5%
Ans: C

Q.49)How much bring required in 1 cubic meter

A) 500
B) 600
C) 100
D) 1000
Ans: A

Q.50)Correct Ration M-20 is

A) 1:5:10
B) 1:3:6
C) 1:1.5:3
D) 1:2:4
Ans: C