Preliminary Level 1 Schedule
Preliminary Level 1 Schedule
Preliminary Level 1 Schedule
2 Engineering Design 212 days Jun 11 '14 Jan 8 '15 Engineering Design
3 Civil Detail Design 90 days Jun 11 '14 Sep 8 '14 Civil Detail Design
4 MEIP Design Completion 0 days Jan 8 '15 Jan 8 '15 MEIP Design Completion
6 Construction Drawing Review by Local Authority 28 days Sep 9 '14 Oct 6 '14 Construction Drawing Review by Local Authority
7 Apply for Construction Permit 31 days Oct 8 '14 Nov 7 '14 Apply for Construction Permit
8 Receipt of Construction Permit 0 days Nov 7 '14 Nov 7 '14 Receipt of Construction Permit
10 Tender & Award Piling 50 days Aug 10 '14 Sep 28 '14 Tender & Award Piling
11 Tender & Award Civil 50 days Sep 19 '14 Nov 7 '14 Tender & Award Civil
13 Civil Constructioin Start 0 days Oct 13 '14 Oct 13 '14 Civil Constructioin Start
16 Upper Concrete Structures Completion 0 days Apr 28 '15 Apr 28 '15 Upper Concrete Structures Completion
17 Steel Structure Installation Completion 0 days Jun 30 '15 Jun 30 '15 Steel Structure Installation Completion
18 MEIP Installation Start 0 days Jun 4 '15 Jun 4 '15 MEIP Installation Start