Preliminary Level 1 Schedule

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Global Projects Group Preliminary Karawang TM15 Level 1 Schedule June 25, 2014

ID Task Name Duration Start Finish 2015 2016


M Ju Jul Au Se Oc No De Ja Fe M Ap M Ju Jul Au Se Oc No De Ja Fe M Ap M Ju Jul Au Se Oc No
1 Preliminary Karawang TM15 Schedule 556 days Jun 11 '14 Dec 18 '15 Preliminary Karawang TM15 Schedule

2 Engineering Design 212 days Jun 11 '14 Jan 8 '15 Engineering Design

3 Civil Detail Design 90 days Jun 11 '14 Sep 8 '14 Civil Detail Design

4 MEIP Design Completion 0 days Jan 8 '15 Jan 8 '15 MEIP Design Completion

5 Permit 60 days Sep 9 '14 Nov 7 '14 Permit

6 Construction Drawing Review by Local Authority 28 days Sep 9 '14 Oct 6 '14 Construction Drawing Review by Local Authority

7 Apply for Construction Permit 31 days Oct 8 '14 Nov 7 '14 Apply for Construction Permit

8 Receipt of Construction Permit 0 days Nov 7 '14 Nov 7 '14 Receipt of Construction Permit

9 Procurement 90 days Aug 10 '14 Nov 7 '14 Procurement

10 Tender & Award Piling 50 days Aug 10 '14 Sep 28 '14 Tender & Award Piling

11 Tender & Award Civil 50 days Sep 19 '14 Nov 7 '14 Tender & Award Civil

12 Construction 431 days Oct 13 '14 Dec 18 '15 Construction

13 Civil Constructioin Start 0 days Oct 13 '14 Oct 13 '14 Civil Constructioin Start

14 Piling Completion 0 days Nov 13 '14 Nov 13 '14 Piling Completion

15 Foundation Completion 0 days Jan 21 '15 Jan 21 '15 Foundation Completion

16 Upper Concrete Structures Completion 0 days Apr 28 '15 Apr 28 '15 Upper Concrete Structures Completion

17 Steel Structure Installation Completion 0 days Jun 30 '15 Jun 30 '15 Steel Structure Installation Completion

18 MEIP Installation Start 0 days Jun 4 '15 Jun 4 '15 MEIP Installation Start

19 Commissioning Start 0 days Nov 14 '15 Nov 14 '15 Commissioning Start

20 TM15 Startup 0 days Dec 18 '15 Dec 18 '15 TM15 Startup

Task Milestone Summary Project Summary

Rev:A Page 1 Form: GPG-100-14-SHD Schedule Jan 23, 2014