DOCUMENT TRANSMITTAL
To: Zhang Zhi | China Petroleum Pipeline Engineering Co., Ltd.| RMCOP Project – Phase 1
Email: [email protected]
cc: Xing Hang | Project Manager | China Petroleum Pipeline Engineering Co., Ltd.
Transmittal Title: PROCEDURES & ITP - EXPANSION AND TIE IN SPOOL FABRICATION
Documents For:
☒ A – Action ☐ IFR – Review ☐ IFA – for Approval
DOCUMENTS
ITEM DOCUMENT/DRAWING
NO. NO. DESCRIPTION/TITLE Rev Status
9686-TR-OT-8868 Page 1 of 2
RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE1)
DOCUMENT TRANSMITTAL
REMARKS
CPP to revise the subject document as per Company comments in attached mark -up document and copy all
Company comments into CRS and provide item -wise response.
9686-TR-OT-8868 Page 2 of 2