ECSS-E-ST-10C

6 March 2009

Space engineering
System engineering general
requirements
 

ECSS Secretariat
ESA-ESTEC
Requirements & Standards Division
Noordwijk, The Netherlands
ECSS‐E‐ST‐10C 
6 March 2009 

Foreword
This  Standard  is  one  of  the  series  of  ECSS  Standards  intended  to  be  applied  together  for  the 
management,  engineering  and  product  assurance  in  space  projects  and  applications.  ECSS  is  a 
cooperative  effort  of  the  European  Space  Agency,  national  space  agencies  and  European  industry 
associations for the purpose of developing and maintaining common standards. Requirements in this 
Standard are defined in terms of what shall be accomplished, rather than in terms of how to organize 
and  perform  the  necessary  work.  This  allows  existing  organizational  structures  and  methods  to  be 
applied where they are effective, and for the structures and methods to evolve as necessary without 
rewriting the standards. 
This  Standard  has  been  prepared  by  the  ECSS‐E‐ST‐10C  Working  Group,  reviewed  by  the  ECSS 
Executive Secretariat and approved by the ECSS Technical Authority. 

Disclaimer
ECSS does not provide any warranty whatsoever, whether expressed, implied, or statutory, including, 
but not limited to, any warranty of merchantability or fitness for a particular purpose or any warranty 
that  the  contents  of  the  item  are  error‐free.  In  no  respect  shall  ECSS  incur  any  liability  for  any 
damages, including, but not limited to, direct, indirect, special, or consequential damages arising out 
of,  resulting  from,  or  in  any  way  connected  to  the  use  of  this  Standard,  whether  or  not  based  upon 
warranty, business agreement, tort, or otherwise; whether or not injury was sustained by persons or 
property or otherwise; and whether or not loss was sustained from, or arose out of, the results of, the 
item, or any services that may be provided by ECSS. 

Published by:   ESA Requirements and Standards Division 
ESTEC, P.O. Box 299,
2200 AG Noordwijk
The Netherlands
Copyright: 2009 © by the European Space Agency for the members of ECSS 


ECSS‐E‐ST‐10C 
6 March 2009 

Change log

ECSS‐E‐10A  First issue 
19 April 1996 
ECSS‐E‐10 Part 1B  Second issue 
18 November 2004 
ECSS‐E‐ST‐10C  Third issue 
6 March 2009   
The main driver for the changes in this issue of the standard comes from the 
intention to include in this document only requirements and moving to an 
ECSS Handbook (ECSS‐E‐HB‐10) all the informative material related to the 
process, in line with the ECSS Task Force #2 recommendations. 
Consequently, the former clause 5 “System engineering process”, which 
contained a thorough description of a reference space system development 
process has been replaced by a brief overview of the project phases and related 
system engineering tasks in the current clause 6 “Overview of system 
engineering tasks per project phase”. 
Former Clause 4 has now been split into an introductory clause 4 “Overview of 
Systems engineering” and clause 5 “General Requirements”. 
The remaining requirements have been reworded for readability and 
consistency. Repetition of requirements included in other related standards 
have been eliminated. 
 
Regarding the documentation model, the only significant modification 
originates in the simplification of the concept of Functional Specification and 
Technical Specification, established in the previous issue of ECSS‐E‐10‐06. In 
the new issue of ECSS‐E‐ST‐10‐06 only one specification, the technical 
requirements specification (customer specification), is considered. This is 
reflected in this standard, as explained in clause 5.2.3.1 
 
Other changes are explained below: 
• Clause 2: Normative references 
Extended and completed 
• Clause 3: Terms, definitions and abbreviated terms 
Includes additional definitions and abbreviated terms. In particular 
definition of the Technology Readiness Levels (TRL) has been added. 
 


ECSS‐E‐ST‐10C 
6 March 2009 

• Clause 4: Overview of system engineering 
Includes the first clause of former clause four  “The system engineering 
discipline”. A brief characterisation of the System engineering process has 
been added to this introductory clause.  
• Clause 5: General requirements 
The set of requirements initially contained in clause 4 of previous issue 
have been considerably restructured. 
Non mandatory requirements contained in previous issue have been 
eliminated, leaving only “mandatory requirements” or “shall” 
requirements. 
Descriptive text has been eliminated and it will be included in the System 
engineering handbook (to be published). 
The use of technology readiness level (TRL) is introduced in clause 5.6.7. 
• Clause 6: Overview of system engineering tasks per project phase 
This new issue contains high level requirements on the system engineering 
tasks to be complied with for each of the project phases. 
• Annex A: System engineering documents delivery per review 
This annex replaces and expands old annex B. It includes the listing of the 
main documents per phase of the project development indicating when the 
document needs to be available. 
• Annexe B to Q: Document Requirements Descriptions (DRD) 
This annexes include all the project documents pertinent to this standard. 
In the previous issue of the standard the DRDs were not included. 
• Annex R: Mapping of typical DDP to ECSS documents 
This is an addition with respect to the previous issue. It presents where 
specific subjects contained in the previously used Design and 
Development Plan are located in the new set of ECSS documents. 
 


ECSS‐E‐ST‐10C 
6 March 2009 

Table of contents

Change log .................................................................................................................3

1 Scope.......................................................................................................................8

2 Normative references ...........................................................................................10

3 Terms, definitions and abbreviated terms..........................................................11


3.1 Terms from other standards ..................................................................................... 11
3.2 Terms specific to the present standard .................................................................... 11
3.3 Abbreviated terms .................................................................................................... 14

4 Overview of system engineering.........................................................................16


4.1 The system engineering discipline ........................................................................... 16
4.2 The system engineering process ............................................................................. 20

5 General requirements...........................................................................................21
5.1 System engineering plan.......................................................................................... 21
5.2 Requirement engineering ......................................................................................... 21
5.2.1 General....................................................................................................... 21
5.2.2 Requirement traceability............................................................................. 22
5.2.3 Requirement engineering process.............................................................. 22
5.3 Analysis .................................................................................................................... 24
5.3.1 System analysis.......................................................................................... 24
5.3.2 System environments and design and test factors..................................... 25
5.3.3 Trade-off analyses...................................................................................... 26
5.3.4 Analysis methods, tools and models .......................................................... 26
5.4 Design and configuration.......................................................................................... 27
5.4.1 Design ........................................................................................................ 27
5.4.2 Configuration .............................................................................................. 29
5.5 Verification................................................................................................................ 29
5.5.1 General....................................................................................................... 29
5.5.2 Product verification ..................................................................................... 29
5.6 System engineering integration and control ............................................................. 30


ECSS‐E‐ST‐10C 
6 March 2009 
5.6.1 Management of system engineering activities............................................ 30
5.6.2 Planning...................................................................................................... 31
5.6.3 Engineering data ........................................................................................ 31
5.6.4 Interface control.......................................................................................... 32
5.6.5 Coordinate systems and units .................................................................... 32
5.6.6 Technical budgets and margin policy ......................................................... 32
5.6.7 Technology ................................................................................................. 32
5.6.8 Risk control................................................................................................. 33
5.6.9 Changes and nonconformances control..................................................... 33

6 Overview of system engineering tasks per project phase................................34


6.1 Overview .................................................................................................................. 34
6.2 General..................................................................................................................... 34
6.3 Phase 0: Mission analysis-need identification .......................................................... 35
6.4 Phase A: Feasibility.................................................................................................. 35
6.5 Phase B: Preliminary definition ................................................................................ 35
6.6 Phase C: Detailed definition ..................................................................................... 35
6.7 Phase D: Qualification and production ..................................................................... 36
6.8 Phase E: Operations / utilization .............................................................................. 36
6.9 Phase F: Disposal .................................................................................................... 36

Annex A (informative) System engineering documents delivery per review .....37

Annex B (normative) Mission description document (MDD) – DRD....................41

Annex C (normative) System concept report – DRD ............................................45

Annex D (normative) System engineering plan (SEP) – DRD ..............................46

Annex E (normative) Technology plan (TP) – DRD...............................................55

Annex F (normative) Technology matrix - DRD ....................................................58

Annex G (normative) Design definition file (DDF) - DRD......................................60

Annex H (normative) Function tree - DRD .............................................................65

Annex I (normative) Technical budget - DRD........................................................67

Annex J (normative) Specification tree - DRD ......................................................69

Annex K (normative) Design justification file (DJF) - DRD ..................................71

Annex L (normative) Trade-off report - DRD .........................................................78

Annex M (normative) Interface requirement document (IRD) - DRD ...................81


ECSS‐E‐ST‐10C 
6 March 2009 
Annex N (normative) Requirements traceability matrix (RTM) - DRD .................83

Annex O (normative) Requirements justification file (RJF) - DRD ......................85

Annex P (normative) Product user manual (PUM or UM) - DRD..........................88

Annex Q (normative) Analysis report – DRD.........................................................96

Annex R (informative) Mapping of typical DDP to ECSS documents .................98

Bibliography...........................................................................................................100

Figures
Figure 4-1: System engineering functions and boundaries .................................................... 18
Figure 4-2: System engineering functions and relationships.................................................. 19
Figure B-1 : Relationship between documents....................................................................... 42

Tables
Table A-1 : System engineering deliverable documents ........................................................ 38


ECSS‐E‐ST‐10C 
6 March 2009 

1
Scope

This  standard  specifies  the  system  engineering  implementation  requirements 


for space systems and space products development. 
Specific objectives of this standard are: 
• to  implement  the  system  engineering  requirements  to  ensure  a  firm 
technical basis and to minimize technical risk and cost for space systems 
and space products development; 
• to  specify  the  essential  system  engineering  tasks,  their  objectives  and 
outputs; 
• to  implement  integration  and  control  of  engineering  disciplines  and 
lower level system engineering work; 
• to  implement  the  “customer‐system‐supplier  model”  through  the 
development of systems and products for space applications. 
This  Standard  is  intended  to  apply  to  all  space  systems  and  product,  at  any 
level  of  the  system  decomposition,  including  hardware,  software,  procedures, 
man‐in‐the‐loop, facilities and services. Through the document and its annexes 
the requirements however apply as they are to complex systems only; for lower 
level elements tailoring is necessary. 
Specific requirements related to system engineering, like technical specification, 
verification,  and  testing  are  specified  in  dedicated  documents  and  standards 
within the set of ECSS system engineering standards ECSS‐E‐ST‐10‐XX. 
Discipline  or  element  specific  engineering  implementation  requirements  are 
covered  in  dedicated  ECSS  standards.  These  standards  are  based  on  the  same 
principles,  process  and  documentation  model.  The  applicability  of  each  these 
standards can therefore not be considered in isolation from the others. 
ECSS‐E‐HB‐10  “System  engineering  guidelines”  contains  guidelines  related  to 
this  standard,  including  a  description  of  the  reference  system  engineering 
process for a space system and its products. 
NOTE 1  The term “Discipline” is defined in ECSS‐M‐ST‐
10,  as  “a  specific  area  of  expertise  within  a 
general  subject”.  The  name  of  the  discipline 
normally indicates the type of expertise, e.g. in 
the  ECSS  system  mechanical  engineering, 
software  and  communications  are  disciplines 
within the engineering domain. 


ECSS‐E‐ST‐10C 
6 March 2009 
NOTE 2  The  requirements  on  the  system  engineering 
process  are  gathered  in  this  standard;  specific 
aspects of the SE process are further elaborated 
in dedicated standards.  
This standard may be tailored for the specific characteristic and constrains of a 
space project in conformance with ECSS‐S‐ST‐00. 


ECSS‐E‐ST‐10C 
6 March 2009 

2
Normative references

The  following  normative  documents  contain  provisions  which,  through 


reference  in  this  text,  constitute  provisions  of  this  ECSS  Standard.  For  dated 
references, subsequent amendments to, or revision of any of these publications 
do not apply, However, parties to agreements based on this ECSS Standard are 
encouraged to investigate the possibility of applying the more recent editions of 
the  normative  documents  indicated  below.  For  undated  references,  the  latest 
edition of the publication referred to applies. 
 
ECSS‐S‐ST‐00‐01  ECSS system ‐ Glossary of terms 
ECSS‐E‐ST‐10‐02  Space engineering – Verification 
ECSS‐E‐ST‐10‐06  Space engineering – Technical requirements specification 
ECSS‐E‐ST‐10‐09  Space engineering – Reference coordinate system 
ECSS‐E‐ST‐10‐24  1)  Space engineering – Interface control 
ECSS‐M‐ST‐10  Space project management – Project planning and 
implementation 
ECSS‐M‐ST‐40  Space project management – Configuration and 
information management 
ECSS‐Q‐ST‐20‐10 1)  Off‐the‐shelf items utilization in space systems 
 

                                                 
 To be published. 
1

10 
ECSS‐E‐ST‐10C 
6 March 2009 

3
Terms, definitions and abbreviated terms

3.1 Terms from other standards


For the purpose of this Standard, the terms and definitions from ECSS‐S‐ST‐00‐01 
apply, in particular for the following terms: 
acceptance  
approval 
configuration baseline 
design 
development 
equipment 
inspection 
integration 
need 
performance  (see also ECSS‐E‐ST‐10‐06) 
product tree 
requirement 
specification 
subsystem 
system 
test 
verification 

3.2 Terms specific to the present standard


3.2.1 agreement
act  of  an  authorized  representative  of  an  organization  by  which  it  confirms 
satisfactory performance of specific services 

11 
ECSS‐E‐ST‐10C 
6 March 2009 
3.2.2 critical
characteristic  of  a  process,  process  condition,  parameter,  requirement  or  item 
that deserves control and special attention in order to meet the objectives (e.g. 
of a mission) within given constraints 

3.2.3 design to cost


method of managing a project, which enables the project to be controlled from 
its  inception  in  order  to  meet  defined  performances  within  pre‐established 
objectives of cost and time 

3.2.4 integration
process  of  physically  and  functionally  combining  lower  level  products 
(hardware or software) to obtain a particular functional configuration 

3.2.5 mission statement


document expressing the set of collected needs 
NOTE  The  mission  statement  is  a  document 
established  by  the  customer,  which  reflects  the 
users needs, and is used as input to Phase 0 of a 
space system project. 

3.2.6 requirement traceability


requirement  attribute  that  links  each  single  requirement  to  its  higher  level 
requirements inside the requirement set 
NOTE  This  enables  the  derivation  of  a  requirement 
tree,  which  demonstrates  the  coherent  flow‐
down of the requirements. 

3.2.7 recurring product


product which conforms to a qualified design and is produced according to the 
corresponding production master file 

3.2.8 system engineering


interdisciplinary  approach  governing  the  total  technical  effort  required  to 
transform a requirement into a system solution 
NOTE  From IEEE P1220. 

3.2.9 system engineering organisation


entity  within  a  project  team  of  a  supplier  which  performs  the  system 
engineering activities of the project  
NOTE  For further details see clause 4.2. 

3.2.10 system engineering process


set  of  inter‐related  or  interacting  activities,  each  transforming  inputs  into 
outputs, to implement system engineering 

12 
ECSS‐E‐ST‐10C 
6 March 2009 
3.2.11 technical requirement
required technical capability of the product in terms of performances, interfaces 
and operations 
NOTE  These  are  requirements  related  to  a  product 
and  not  those  related  to  the  process  or 
management  of  the  project  or  business 
agreement. 

3.2.12 technology readiness level


achieved status of development of a technology 
NOTE  TRL levels 1 to 9 are defined as follows: 
TRL1  Basic principles observed and reported 
TRL2  Technology concept and/or application 
formulated 
TRL3  Analytical and experimental critical function 
and/or characteristic proof‐of‐concept 
performed 
TRL4  Component and/or breadboard validated in 
the laboratory environment 
TRL5  Component and/or breadboard validated in 
the relevant environment 
TRL6  System/subsystem model or prototype 
demonstrated in the relevant environment 
(ground or space) 
TRL7  System prototype demonstrated in a space 
environment 
TRL8  Actual system completed and flight‐
qualified through test and demonstrated 
(ground or flight) 
TRL9  Actual system “flight‐proven” through 
successful mission operations. 

3.2.13 verification matrix


initial issue of the VCD which contains for each requirement to be verified the 
methods, levels and stages of product verification 
NOTE  See  ECSS‐E‐ST‐10‐02  for  a  more  detailed 
definition of the VCD. 

13 
ECSS‐E‐ST‐10C 
6 March 2009 

3.3 Abbreviated terms


For the purpose of this Standard, the abbreviated terms from ECSS‐S‐ST‐00‐01 
and the following apply: 
 
Abbreviation  Meaning 
AIT  assembly, integration and test 
AIV plan  assembly, integration and verification plan 
AOCS  attitude and orbit control sub‐system 
AR  acceptance review 
CDR  critical design review 
COTS  commercial off‐the‐shelf 
CRR  commissioning results review 
NOTE  For space vehicles (e.g. launcher, transfer vehicle, 
crew transport vehicle) the CRR can be replaced or 
complemented by a flight qualification review 
(FQR).  
DDF  design definition file 
DDP  design development plan 
DJF  design justification file 
DRD  document requirements definition 
ECSS  European Cooperation for Space Standardization 
ELR  end‐of‐life review 
FDIR  failure, detection, isolation, recovery 
FM  flight model 
FMECA  failure modes, effects, and criticality analysis 
FRR  flight readiness review 
FTA  fault tree analysis 
GSE  ground support equipment 
ICD  interface control document 
ILS  integrated logistic support 
IRD  interface requirement document 
LRR  launch readiness review 
MCR  mission closed‐out review 
MDD  mission description document 
MDR  mission definition review 
MOP  mission operations plan 
MS  mission statement 
ORR  operational readiness review 

14 
ECSS‐E‐ST‐10C 
6 March 2009 

PDR  preliminary design review 
PMP   project management plan 
PRR  preliminary requirement review 
PUM   product user manual 
QR  qualification review 
RAMS  reliability, availability, maintainability, safety 
RF  radio frequency 
RJF  requirement justification file 
ROD  review of design 
ROM/RAM  read only memory / random access memory 
RTM  requirement traceability matrix 
R&D  research and development 
SE  system engineering 
SEP  system engineering plan 
SFT  system functional test 
SRR  system requirement review 
SVT  system validation test 
TP  technology plan 
TRL  technology readiness level 
TS  technical requirements specification 
UM   user manual 
VCD  verification control document 
VP  verification plan 
w.r.t.  with respect to 

15 
ECSS‐E‐ST‐10C 
6 March 2009 

4
Overview of system engineering

4.1 The system engineering discipline


System  engineering  is  defined  as  an  interdisciplinary  approach  governing  the 
total technical effort to transform requirements into a system solution. 
A  system  is  defined  as  an  integrated  set  of  elements  to  accomplish  a  defined 
objective.  These  elements  include  hardware,  software,  firmware,  human 
resources,  information,  techniques,  facilities  services,  and  other  support 
elements. 
In  this  standard  the  concept  of  “system”  is  used  in  a  wide  sense.  The  highest 
level, often called “mission level” or “space system”, consists usually of one (or 
more) space segment(s), of a ground segment, and of a user segment. Elements 
of system decomposition are also considered a system. For the purpose of this 
standard  the  system  can  be  any  element  at  any  level  of  decomposition  as 
defined by the function tree (see Annex H) or the product tree (see ECSS‐M‐ST‐
10  Annex  B).  The  scope  of  an  element  can  include  hardware,  software, 
procedures, man‐in‐the‐loop, facilities and services. 
From the perspective of the considered system, requirements originate from the 
next upper level (the customer) and elements are procured from the next lower 
level (the suppliers).  
NOTE 1  The  customer‐supplier  model  is  described  in 
ECSS‐S‐ST‐00. 
NOTE 2  Through  this  standard  the  notion  of  customer 
refers to several actors ,in relation to the project 
phase.  In fact a customer can be e.g. a scientific 
community  in  phase  0,  a  commercial  user  in 
phase A or an Agency in phase B. A supplier can 
on the other hand be an Agency in both phase 0 
and phase A. 
Figure  4‐1  shows  the  boundaries  of  the  system  engineering  discipline,  its 
relationship  with  production,  operations,  product  assurance  and  management 
disciplines and its internal partition into the following functions: 
• requirement  engineering,  which  consist  on  requirement  analysis  and 
validation, requirement allocation, and requirement maintenance; 
• analysis,  which  is  performed  for  the  purpose  of  resolving  requirements 
conflicts,  decomposing  and  allocating  requirements  during  functional 
analysis, assessing system effectiveness (including analysing risk factors); 

16 
ECSS‐E‐ST‐10C 
6 March 2009 
and  complementing  testing  evaluation  and  providing  trade  studies  for 
assessing effectiveness, risk, cost and planning; 
• design and configuration which results in a physical architecture, and its 
complete system functional, physical and software characteristics; 
• verification,  which  objective  is  to  demonstrate  that  the  deliverables 
conform  to  the  specified  requirements,  including  qualification  and 
acceptance; 
• system  engineering  integration  and  control,  which  ensures  the 
integration  of  the  various  engineering  disciplines  and  participants 
throughout all the project phases. 

Figure  4‐2  shows  system  engineering  functions,  their  relationships  and  their 
main activities during the system engineering process. 
System  engineering  functions  are  applied  in  an  iterative  mode  during 
implementation of the system engineering process described in clause 4.2. 
Within  the  frame  of  a  project,  the  system  engineering  functions  are 
implemented by a system engineering organisation of the supplier which is in 
charge of transforming the requirements of the customer into a system solution 
delivered by the supplier. 
NOTE  With  respect  to  the  next  lower  level,  the 
supplier plays the role of the customer. 

17 
ECSS‐E‐ST‐10C 
6 March 2009 

Figure 4‐1: System engineering functions and boundaries 

18 
System Engineering Data Base
Technical Plans
System Engineering Tools and Models
Integration and Control

 
System Analysis System Analysis

P la n s a n d D a ta
System Analysis
P la n s a n d D a ta

Analysis

Requirement Functional Analysis Design and


Customer input Engineering and allocation configuration

Requirement Engineering Design and configuration

P la n s a n d D a ta
Requirements Functional Product Qualified product design
Verification Verification Verification

Verification

Figure 4‐2: System engineering functions and relationships 

19 
6 March 2009 
ECSS‐E‐ST‐10C 
ECSS‐E‐ST‐10C 
6 March 2009 

4.2 The system engineering process


The system engineering activities of a project are conducted by an entity within 
the  project  team  of  a  supplier.  This  entity  is  called  in  this  document  “system 
engineering organisation”. 
The  system  engineering  process  consists  of  activities  to  be  performed  by  the 
system  engineering  organisation  within  each  project  phase.  The  objective  is  to 
obtain  a  product  which  satisfies  the  customer  technical  requirements  within 
pre‐established objectives of cost and time. The requirements for these activities 
are described in clause 5. 
The system engineering process is intrinsically iterative across the whole life of 
a project, in particular in the initial phases (i.e. 0, A, and B) of the development 
of a complex system (e.g. a spacecraft), procured through a multilayered set of 
suppliers. 
During  these  phases,  the  system  engineering  organisation  derives  design 
oriented technical solutions using as an input the design‐independent customer 
requirements  contained  in  a  technical  requirements  specification  (TS).  This  is 
achieved  through  an  iterative  top‐down  process  by  trading  off  several  design 
solutions at increasing level of detail. 
NOTE  For  definition  and  requirements  for  a  technical 
requirements specification see ECSS‐E‐ST‐10‐06. 
Through  this  process  the  system  engineering  organisation  performs  a 
multidisciplinary  functional  decomposition  to  obtain  logical  lower  level 
products  (both  hardware  and  software).  At  the  same  time  the  system 
engineering  organisation  decides  on  balanced  allocations,  throughout  the 
system,  of  resources  allocated  by  the  customer  and  respects  agreed  margin 
philosophies as a function of the relevant technology readiness levels. 
The system engineering process is in turn applied by each system engineering 
organisation of each supplier of the elements of the product decomposition. 
The functional decomposition defines, for each level of the system, the technical 
requirements for the procurement of subassemblies or lower level products as 
well as the requirements for the verification of the final characteristics of each 
product. 
The system engineering process uses the results of these lower level verification 
activities  to  build  a  bottom‐up  multilayered  evidence  that  the  customer 
requirements have been met. 
The  system  engineering  process  is  applied  with  various  degrees  of  depth 
depending on the level of maturity of the product (e.g. new development or off‐
the‐shelf). 
The system engineering process can be applied with different level of tailoring 
as agreed between customer and supplier in their business agreement. 
The  system  engineering  organization  has  interfaces  with  organizations  in 
charge of management, product assurance, engineering disciplines, production, 
and operations and logistics. 
NOTE 1  The  system  engineering  process  is  defined  in 
detail  in  ECSS‐E‐HB‐10  “System  engineering 
guidelines”. 
NOTE 2  The project phases are defined in ECSS‐M‐ST‐10. 

20 
ECSS‐E‐ST‐10C 
6 March 2009 

5
General requirements

5.1 System engineering plan


a. The system engineering organization shall produce a system engineering 
plan (SEP) in conformance with Annex D. 
b. The  system  engineering  organization  shall  establish  the  SEP  with  the 
contributions  and  constraints  of  management,  product  assurance, 
engineering disciplines, production, and operations and logistics. 
c. The  system  engineering  plan  shall  relate  to  the  lower  level  plans  and 
ensure consistency between these plans. 
NOTE 1  The  early  version  of  the  Project  Management 
Plan (PMP), which includes the early version of 
the SEP, contains all the information which was 
traditionally  contained  in  the  Design  and 
Development  Plan  (DDP).  See  Annex  R  which 
illustrates the mapping between a typical DDP 
and ECSS DRDs.  
NOTE 2  The  SEP  content  evolves  with  the  phase  of  the 
project, with more information on risk analysis 
and new technologies in early phases 0, A and 
B,  and  more  information  on  verification  and 
validation aspects in phases C, D 

5.2 Requirement engineering

5.2.1 General
a. The  system  engineering  organisation  shall  analyse  the  requirements  for 
the system issued by the customer. 
NOTE  This  analysis  enables  transforming  these 
requirements into a system solution. 
b. The  system  engineering  organisation  shall  derive,  generate,  control  and 
maintain  the  set  of  requirements  for  the  lower  level  elements,  defining 
their  design  and  operational  constraints  and  the  parameters  of 
functionality, performance, and verification necessary to meet the system 
requirements issued by the customer. 

21 
ECSS‐E‐ST‐10C 
6 March 2009 
c. The  system  engineering  organisation  shall  ensure  consistency  of  the 
requirements at system level, at lower levels, as well as amongst levels. 
d. The  system  engineering  organisation  shall  ensure  conformance  of  each 
requirement with characteristics specified in ECSS‐E‐ST‐10‐06 clause 8. 
NOTE  Main  characteristics  are:  traceable,  unique, 
single, verifiable, unambiguous. 
e. The system engineering organisation shall ensure that each requirement 
for  the  lower  level  elements  has  a  justification  reflected  in  the 
requirement justification file in conformance with Annex O. 
NOTE  This  applies  also  to  a  standard  as  a  whole. 
Tailoring  of  a  standard  in  a  list  of  applicable 
standards, or of a requirement in an applicable 
standard,  is  possible  where  each  tailoring 
measure is duly justified. 

5.2.2 Requirement traceability


a. The system engineering organisation shall ensure forward and backward 
traceability of all requirements: 
1. to their sources;  
NOTE  For  example:  a  higher  level  requirement,  an 
imposed management constraint, an applicable 
standard, an accepted lower level constraint. 
2. to the lower level requirements; 
3. to  changes  in  the  design  inducing  modifications  of  the 
requirements; 
4. to their verification close‐out. 
b. The  system  engineering  organisation  shall  establish  the  requirements 
traceability matrix in conformance with Annex N. 
c. The  system  engineering  organisation  shall  ensure  that  the  close‐out 
traceability is documented in the VCD in conformance with ECSS‐E‐ST‐
10‐02 Annex B.  

5.2.3 Requirement engineering process

5.2.3.1 Technical requirements specifications


a. The  system  engineering  organisation  shall  establish  technical 
requirements  specifications  of  the  next  lower  level  products  consistent 
among  them  and  with  the  technical  specification  received  from  the 
customer  
b. The  system  engineering  organisation  shall  ensure  that  the  technical 
requirements  specifications  it  establishes  conform  to  ECSS‐E‐ST‐10‐06 
and its DRD in Annex A. 

22 
ECSS‐E‐ST‐10C 
6 March 2009 
c. The  system  engineering  organisation  shall  establish  for  its  own  product 
and lower level ones a specification tree in conformance with Annex J. 
d. In systems where the supply chain consists of at least 3 layers (including 
the  customer),  the  system  engineering  organisation  of  the  highest  level 
supplier shall define at the beginning of a project, a set of requirements 
specifications  covering  aspects  common  to  more  than  one  lower  level 
product.  
NOTE 1  These  “common”  technical  specifications  have 
been  historically  called  support  specifications 
(e.g.  GDIR  “General  Design  and  Interface 
Requirements”,  environmental,  test,  EMC 
requirements  specifications)  and  are  separated 
from  other  requirements  specifications 
addressing  product  specific  characteristics  and 
functionalities. 
NOTE 2  Requirements for equipment level products (or 
below)  can  be  issued  in  self  contained 
specifications. 

5.2.3.2 Requirement consolidation


a. The  system  engineering  organisation  shall  identify  and  resolve  at  the 
beginning  of  each  project  phase,  incomplete,  ambiguous,  and 
contradictory  requirements  (with  the  customer  for  requirements  issued 
by him). 
b. The  system  engineering  organisation  shall  reflect  the  consolidated 
requirements in updates of the specifications. 

5.2.3.3 Requirement analysis


a. The  system  engineering  organisation  shall  identify  requirements 
impacting strongly on system risk. 
b. The  system  engineering  organisation  shall  perform  the  requirements 
analysis to the level of depth necessary to identify elements impacting on 
system risks. 

5.2.3.4 Requirements verification methods


a. The  system  engineering  organisation  shall  ensure  that  for  each 
requirement contained in the technical requirements specification, one or 
a combination of verification methods are identified.  
NOTE  Technical  requirements  specification  is  defined 
in ECSS‐E‐ST‐10‐06 Annex A. 
b. The  system  engineering  organisation  shall  ensure  that  for  each 
requirement  contained  in  the  technical  requirements  specification,  the 
verification methods are reflected in the verification matrix. 
NOTE  Technical  requirements  specification  is  defined 
in ECSS‐E‐ST‐10‐06 Annex A. 

23 
ECSS‐E‐ST‐10C 
6 March 2009 
5.2.3.5 Requirement allocation
a. The  system  engineering  organisation  shall  ensure  that  the  system 
requirements  (and  their  verification  methods)  are  allocated  to  lower 
levels and included in the specifications of the related products. 

5.2.3.6 Requirements consistency


a. The  system  engineering  organisation  shall  verify  that  requirements  are 
individually and globally consistent and non redundant. 
b. The  system  engineering  organisation  shall  verify  that  the  lower  level 
requirements are consistent with system requirements. 

5.2.3.7 Requirements validation


a. In  phase  0  the  system  engineering  organisation  shall  validate  the 
requirements against the expressed needs together with the customer. 
NOTE  For definition of “needs” see ECSS‐E‐ST‐10‐06. 

5.2.3.8 Requirements maintenance


a. The system engineering organisation shall ensure that agreed changes to 
requirements are implemented in system and lower levels specifications. 
b. The  system  engineering  organisation  shall  exercise  the  maintenance 
during the system life cycle, down to end of the Phase F Mission Close‐
out Review. 

5.2.3.9 Requirements baseline


a. The system engineering organisation shall establish the list of documents 
constituting  the  system  requirements  baselines  in  contribution  to  the 
configuration baselines. 
NOTE  Details on configuration baselines are provided 
in ECSS‐M‐ST‐40. 

5.3 Analysis

5.3.1 System analysis


a. In phase 0 the system engineering organisation shall perform an analysis 
of  the  Mission  Statement  document,  produce  Mission  Description 
document(s)  in  conformance  with  Annex  B,  and  maintain  this  latter 
document for the final selected concept.  
b. The system engineering organisation shall perform a functional analysis, 
produce the functional architecture, and produce the function tree which 
satisfy the customer technical requirements specification, in conformance 
with Annex H. 

24 
ECSS‐E‐ST‐10C 
6 March 2009 
c. The  system  engineering  organisation  shall  document  the  functional 
architecture  in  the  design  definition  file  (DDF)  in  conformance  with 
Annex G. 
d. The  system  engineering  organisation  shall  justify  the  functional 
architecture in the DJF in conformance with Annex K. 
e. The  system  engineering  organisation  shall  perform  a  physical  analysis, 
produce  the  physical  architecture  and  produce  the  product  tree  in 
conformance with ECSS‐M‐ST‐10 Annex B. 
f. The  system  engineering  organisation  shall  document  the  physical 
architecture in the DDF in conformance with Annex G. 
g. The  system  engineering  organisation  shall  justify  the  physical 
architecture in the DJF in conformance with Annex K. 
h. The  system  engineering  organisation  shall  analyse  the  performances  of 
the system, including end‐to‐end evaluation, documenting the results of 
the analysis in the Design Justification File in conformance with Annex K. 
i. The  system  engineering  organisation  shall  analyse  influence  of  mission, 
design, development, operations and constraints on cost and schedule as 
input to the project cost and schedule consolidation and to the utilisation 
recurring cost (design to cost). 
j. The  system  engineering  organisation  shall  ensure  that  any  analysis  is 
documented in an analysis report, in conformance with Annex Q. 

5.3.2 System environments and design and test


factors
a. The  system  engineering  organisation  shall  establish  the  influence  of  all 
types  of  environments  applied  during  each  life  profile  event  on  system 
and  its  elements  in  terms  of  nominal  and  extreme  environmental 
conditions including all applicable operational phases.  
b. The  system  engineering  organisation  shall  establish  the  criteria  for 
qualification and acceptance in conformance with Annex K of system and 
system elements for all types of environment. 
c. The  system  engineering  organisation  shall  ensure  that  analyses  include 
design induced effects between system components or the system and its 
external  environment  and  account  for  analysis  uncertainties,  in 
conformance with Annex K. 
d. The  system  engineering  organisation  shall  establish  the  design  and  test 
factors and margins applicable for design in conformance with Annex K. 
NOTE 1  Design  factors  are  factors  applied  to  specified 
loads to ensure robustness of the design. 
NOTE 2  Test  factors  are  factors  applied  to  specified 
loads to demonstrate margins w.r.t. these loads 
(e.g. qualification / acceptance factors). 
e. The  system  engineering  organisation  shall  establish  environment 
conditions for product verification. 

25 
ECSS‐E‐ST‐10C 
6 March 2009 

5.3.3 Trade-off analyses


a. The system engineering organisation shall conduct or consolidate trade‐
off analyses to: 
1. assist  in  selecting  system  concepts,  designs  and  solutions 
(including people, parts and materials availability); 
2. support material selection and process decisions; 
3. support make‐or‐buy and supplier selection; 
4. examine  alternative  technologies  to  satisfy  functional  and  design 
requirements;  
5. evaluate  environmental  and  cost  impacts  of  materials  and 
processes; 
6. evaluate  alternative  physical  architectures  to  select  preferred 
products and processes; 
7. establish the system and its configuration items; 
8. analyze planning critical paths and propose alternatives; 
9. select standard components, techniques, services and facilities that 
reduce system life‐cycle cost; 
10. establish model and product verification philosophy for achieving 
qualification  and  acceptance  objectives  while  considering 
testability; 
11. assess design capacity to evolve. 
b. The system engineering organisation shall evaluate alternative concepts, 
designs  and  solutions  against  each  other  in  a  Trade‐off  report  in 
conformance with Annex L. 
c. The  system  engineering  organisation  shall  document  alternative  system 
concepts considered during system trade‐off studies in a System Concept 
Report in conformance with Annex C. 

5.3.4 Analysis methods, tools and models


a. The  system  engineering  organisation  shall  define  the  analysis  methods 
and tools to be used during the product life cycle, as well as the related 
models and data exchanges between the tools, and document these in the 
SEP in conformance with Annex D. 
b. The system engineering organisation shall ensure that analysis tools are 
validated. 
c. The system engineering organisation shall ensure that analysis tools are 
maintained. 
d. The system engineering organisation shall ensure that analysis tools are 
capable of exchanging and using models and data. 
NOTE 1  For  exchange  of  models  and  data,  see  ECSS‐E‐
TM‐10‐20 and ECSS‐E‐TM‐10‐21. 
NOTE 2  Exchange can be either direct or via interfaces. 

26 
ECSS‐E‐ST‐10C 
6 March 2009 
e. The system engineering organisation shall ensure that analysis tools are 
capable of transferring models and data for multi‐disciplinary analysis.  
NOTE 1  Details  on  product  data  exchange  and  system 
modelling  and  simulation  are  provided  in 
ECSS‐E‐TM‐10‐20 and ECSS‐E‐TM‐10‐21. 
NOTE 2  Exchange can be either direct or via interfaces. 
f. The system engineering organisation shall ensure that models produced 
by  analysis  tools  are  validated  based  on  documented  procedures  and 
results. 
g. The system engineering organisation shall ensure that modelling and test 
accuracy as well as limitations are considered (as part of Annex K) when 
establishing  the  performances  and  specifying  environmental  conditions 
for product verification. 
h. The  system  engineering  organisation  shall  ensure  that  models  are  kept 
operational for the lifetime of the product. 

5.4 Design and configuration

5.4.1 Design

5.4.1.1 General
a. The  system  engineering  organisation  shall  establish  a  design  of  the 
system  from  its  functional  architecture,  requirement  allocation,  and 
technology selection. 
NOTE  This  includes  definition  of  the  interfaces  and 
corresponding ICDs. 
b. The  system  engineering  organisation  shall  ensure  that  the  design 
addresses  system  aspects,  covering  its  whole  lifecycle,  producing  the 
physical architecture documented in conformance with Annex G and the 
product tree in conformance with ECSS‐M‐ST‐10 Annex B. 
c. The system engineering organization shall take into account the outcome 
of the design and verification activities of the lower level products. 
d. The system engineering organisation shall ensure that the design covers 
hardware, software, and man in the loop. 
e. The  system  engineering  organisation  shall  ensure  that  the  design  is 
supported by analyses consistent with the level of maturity of the design. 
f. The system engineering organisation shall ensure that all interface points 
with the production organisation are duly supported by communication, 
cooperation and provision of inputs between the two organizations. 
NOTE  This  relates  to  integration  procedures  and 
production master file. 

27 
ECSS‐E‐ST‐10C 
6 March 2009 
5.4.1.2 Budgets
a. The  system  engineering  organisation  shall  define  and  maintain  all 
technical budgets of the system in conformance with Annex I in terms of 
target, current status and their trends. 
b. The system engineering organisation shall apportion and control budget 
requirements to all levels of system decomposition. 
c. The  system  engineering  organisation  shall  apply  the  margin  policy  as 
defined in the SEP. 

5.4.1.3 Design methods, tools and models


a. The  system  engineering  organisation  shall  define  the  design  methods, 
tools  and  related  models  to  be  used  during  the  product  life  cycle  and 
document them in the SEP. 
b. The  system  engineering  organisation  shall  ensure  that  design  tools  are 
validated and maintained. 
c. The  system  engineering  organisation  shall  ensure  that  design  tools  are 
capable of exchanging and using design models and data). 
d. The  system  engineering  organisation  shall  ensure  that  design  models 
related to the product as documented in the final DDF and DJF are kept 
operational for the lifetime of the product. 
e. The  system  engineering  organisation  shall  ensure  that  design  models 
produced by design tools shall are validated. 
f. The  system  engineering  organisation  shall  ensure  that  all  design  models 
refer  to  a  coordinate  system  agreed  with  the  customer  and  related  to  the 
project Coordinate System Document in conformance with ECSS‐E‐ST‐10‐09 
Annex A with transformation methods as defined in ECSS‐E‐ST‐10‐09. 

5.4.1.4 Design files


a. The  system  engineering  organisation  shall  establish  and  maintain  a 
design definition file in conformance with Annex G. 
b. The  system  engineering  organisation  shall  establish  and  maintain  a 
design justification file in conformance with Annex K. 
c. The  system  engineering  organisation  shall  establish  and  maintain  a 
product  user’s  manual  (PUM)  or  user’s  manual  (UM)  in  conformance 
with Annex P. 
NOTE  In  case  the  product  considered  is  a  space 
segment,  the  Space  Segment  User  Manual 
defined  in  ECSS‐E‐ST‐70  Annex  E  is  generated 
with  support  of  the  system  engineering 
organization. 

28 
ECSS‐E‐ST‐10C 
6 March 2009 

5.4.2 Configuration

5.4.2.1 Configuration content


a. The  system  engineering  organisation  shall  ensure  that  the  configuration 
includes  the  complete  system  functional,  physical  and  software 
characteristics,  budgets,  interfaces  and  relationships  between  external 
and internal items. 
b. The  system  engineering  organisation  shall  ensure  that  the  configuration 
includes all lower decomposition levels. 
c. The  system  engineering  organisation  shall  ensure  that  the  configuration 
is documented in the DDF and in configuration definition documents. 
NOTE  Details  on  configuration  definition  documents 
are provided in ECSS‐M‐ST‐40. 

5.4.2.2 Configuration baselines


a. The  system  engineering  organisation  shall  establish  the  system 
configuration  baselines  to  be  placed  under  control  at  defined  project 
milestones. 
NOTE  Details  on  system  configuration  baselines  are 
provided in ECSS‐M‐ST‐40.  

5.4.2.3 Configuration assembly constraints


a. The  system  engineering  organisation  shall  define  the  hierarchy  and 
assembly sequence of the system elements with the physical architecture. 
b. The  system  engineering  organisation  shall  document  the  hierarchy  and 
assembly sequence of the system elements with the physical architecture. 

5.5 Verification

5.5.1 General
a. The  system  engineering  organisation  shall  implement  the  product 
verification according to ECSS‐E‐ST‐10‐02. 
NOTE  By  implementing  the  product  verification  as 
per  ECSS‐E‐ST‐10‐02  the  system  engineering 
organisation  defines  the  Verification  Plan,  as 
specified in ECSS‐E‐ST‐10‐02 Annex A. 

5.5.2 Product verification


a. The system engineering organisation shall ensure that the verification of the 
product is performed on the physical architecture as defined in the DDF. 

29 
ECSS‐E‐ST‐10C 
6 March 2009 
b. The  system  engineering  organisation  shall  assign  the  product  to  a 
verification product category, as defined in ECSS‐E‐ST‐10‐02 Table 5‐1. 
c. The system engineering organisation shall specify the configuration and 
environment  conditions  for  product  verification  and  the  criteria  for  its 
qualification and acceptance. 
d. The  system  engineering  organisation  shall  confirm  that  all  product 
verification  objectives  are  achieved  by  analysing  the  results  of  the 
verification activities.  
NOTE  This  includes  analysis  of  Verification  Control 
Document  and  its  closeout  documents,  as 
defined in ECSS‐E‐ST‐10‐02 Annex B. 
e. The  system  engineering  organisation  shall  ensure  that  validation  of 
systems  with  man‐in‐the‐loop  takes  into  account  the  man  related 
limitations. 
f. The  system  engineering  organisation  shall  ensure  that  the  verification 
covers  the  complete  product  including  hardware,  software,  man  in  the 
loop,  operations  and  representative  mission  scenarios  (including  pre‐
launch,  launch  and  early  orbit,  in‐orbit,  post‐landing,  or  other  mission 
scenario). 
NOTE 1  The testing performed during and at the end of 
the integration of a system is defined as System 
Functional Test (SFT). 
NOTE 2  For  system  composed  of  different  segments 
(e.g.  space  segment,  ground  segment),  the 
testing  performed  to  ensure  operability  and 
functionality of the complete system is defined 
as System Validation Test (SVT). 

5.6 System engineering integration and control

5.6.1 Management of system engineering


activities
a. The system engineering organization shall define, plan, and manage the 
integrated  technical  effort  in  accordance  with  the  SEP  and  the  previous 
clauses  of  this  document, including  quantification  of  this  effort  as  input 
to management. 
b. The system engineering organization shall set up the system engineering 
organization  and  interfaces  in  accordance  with  the  system  engineering 
plan. 
NOTE  For  example:  to  customer,  to  lower  levels, 
management,  product  assurance,  production, 
operations and logistics. 
c. The  system  engineering  organization  shall  initiate  and  control,  in 
accordance  with  the  SEP,  the  activities  of  engineering  disciplines,  of 

30 
ECSS‐E‐ST‐10C 
6 March 2009 
product assurance, of production, and of operations and ILS relevant for 
the achievement of its objectives. 
NOTE  Examples of such activities are: 
• Engineering  disciplines:  mechanical  and 
thermal; 
• PA: FMECA and RAMS; 
• Production: producibility; 
• ILS: operability, maintainability. 
d. The  system  engineering  organization  shall  make  engineering  decisions 
with the support and implementation of: 
1. studies, trade‐offs and analyses, 
2. models, simulators, breadboards, 
3. development activities, 
4. technical optimisation efforts. 
e. The  system  engineering  organization  shall  ensure  the  availability  of 
product  and  process  data  which  enables  the  complete  system  to  be 
produced,  tested,  delivered,  operated,  maintained,  and  properly 
disposed of. 
f. The system engineering organisation shall establish a working link to the 
project configuration control to ensure that all binding changes resulting 
from  engineering  changes,  dispositions  and  decisions  are  correctly 
picked‐ up and processed. 
g. The  system  engineering  organization  shall  ensure  that  the  experience 
gained in past and in parallel activities is systematically considered. 

5.6.2 Planning
a. The  system  engineering  organization  shall  ensure  that  the  SEP  is  in 
agreement with the project schedule. 
NOTE  Details  on  the  project  schedule  content  are 
provided  in  ECSS‐M‐ST‐60,  in  particular  the 
DRD Annex B. 

5.6.3 Engineering data


a. The system engineering organization shall define the engineering data to 
be stored in a data repository. 
b. The  system  engineering  organization  shall  ensure  that  engineering  data 
can be exchanged in electronic form between the different organizations 
in charge of the elements of the product decomposition levels via agreed 
and validated interfaces. 

31 
ECSS‐E‐ST‐10C 
6 March 2009 

5.6.4 Interface control


a. The  system  engineering  organization  shall  control  external  interfaces  as 
well as internal interfaces to the system by means of technical requirements 
specification in conformance with ECSS‐E‐ST‐10‐06 Annex A and interface 
control documents in conformance with ECSS‐E‐ST‐10‐24 Annex A. 
NOTE 1  The  control  of  the  external  interfaces  is 
performed  in  cooperation  with  the  parties 
involved in the interface. 
NOTE 2  Interface  requirements  can  be  rolled‐out  of  the 
technical specification as interface requirements 
documents 
b. When  the  interface  requirements  are  rolled  out  in  a  self  standing  IRD, 
this document shall be in conformance with Annex M. 
c. All  interface  requirements  shall  be  accompanied  by  their  verification 
requirements.  

5.6.5 Coordinate systems and units


a. The system engineering organisation shall define the coordinate systems 
and related units in conformance with the Coordinate System Document 
DRD ECSS‐E‐ST‐10‐09 Annex A. 
b. The  system  engineering  organisation  shall  define  the  units  system  to  be 
used during the product life cycle and document it in the SEP. 

5.6.6 Technical budgets and margin policy


a. The  system  engineering  organization  shall  control  all  technical  budgets 
defined in conformance with Annex I. 
b. The  system  engineering  organization  shall  define  the  margin  policy  as 
applicable to the maturity level of the product. 
NOTE  Details are provided in the system engineering 
plan in Annex D <4.2>b.5.). 

5.6.7 Technology
a. The  system  engineering  organization  shall  identify  candidate 
technologies,  and  document  them  in  the  Technology  Matrix  in 
conformance with Annex F. 
b. The  system  engineering  organization  shall  ensure  that  the  technologies 
proposed  are  assessed  and  confirmed  in  terms  of  availability  and 
maturity (according to TRL levels defined in 3.2.12), and documented in 
the Technology Plan in conformance with Annex E. 
c. The  system  engineering  organization  shall  demonstrate  supportability 
and  feasibility  within  the  defined  industrial  organization’s  cost  and 
schedule constraints. 

32 
ECSS‐E‐ST‐10C 
6 March 2009 

5.6.8 Risk control


a. The system engineering organization shall contribute to the identification 
of the risk and of its mitigation measures. 
b. The  system  engineering  organization  shall  ensure  the  availability  of 
engineering data and approaches in support of risk management. 
NOTE  Details  on  risk  management  are  provided  in 
ECSS‐M‐ST‐80. 
c. The  system  engineering  organization  shall  implement  and  control  the 
elements  of  the  risk  management  plan  which  are  within  system 
engineering responsibility. 

5.6.9 Changes and nonconformances control


a. The  system  engineering  organization  shall  provide  a  technical 
assessment on any change proposal to the baseline of the product. 
b. The  system  engineering  organization  shall  provide  a  technical 
assessment on any nonconformance to the status of the product. 
c. The system engineering organization shall implement and control agreed 
actions. 
NOTE 1  Change is related to a request for deviation. 
NOTE 2  Nonconformance  is  related  to  a  request  for 
waiver. 
NOTE 3  The change procedure/control is defined as part 
of the configuration management as defined in 
ECSS‐M‐ST‐40. 

33 
ECSS‐E‐ST‐10C 
6 March 2009 

6
Overview of system engineering tasks per
project phase

6.1 Overview
The allocation of specific system engineering requirements per phase depends 
strongly on the type of business agreement established between Customer and 
Supplier  and  the  nature  and  level  of  complexity  of  the  system  subject  of  the 
agreement.  The  breakdown  and  the  details  of  the  tasks  are  defined  in  the 
business agreement specific documents. 
NOTE  Some  projects  define  them  in  a  Statement  of 
work (SoW). 
The  actors  in  the  customer‐supplier  relationship  change  between  phases  and 
across  levels.  In  the  following  clauses each  system  engineering organisation is 
meant to be the supplier’s system engineering organisation during that phase. 

6.2 General
a. The  system  engineering  organisation  shall  plan  its  activities  in 
conformance with the project phases as defined by management. 
NOTE  The  phases  or  combination  thereof  to  be 
implemented  for  a  project  are  specified  in  the 
business agreement. 
b. The  system  engineering  organisation  shall  plan  the  system  engineering 
activities  for  the  considered  project  phases  in  accordance  with  ECSS‐M‐
ST‐10. 
NOTE  This  includes  contribution  to  the  associated 
reviews. 
c. The  system  engineering  organization  shall  monitor  the  execution  of  all 
system engineering activities including lower levels. 
NOTE  For  details  regarding  system  engineering 
activities, see ECSS‐E‐HB‐10.  
d. The system engineering organisation shall identify the critical elements. 
e. The  system  engineering  organisation  shall  ensure  that  for  critical 
elements which are not at the next lower level, the technical requirements 

34 
ECSS‐E‐ST‐10C 
6 March 2009 
specification, the design definition file and the design justification file are 
available early in the project to control the project risk. 
NOTE  Information regarding the expected delivery of 
system engineering documents for each project 
review is provided in Annex A. 
The documents to be approved by the customer 
as well as the time of their approval are listed in 
the business agreement. 

6.3 Phase 0: Mission analysis-need identification


a. The  system  engineering  organization  shall  support  the  customer  in 
identifying his needs. 
b. The  system  engineering  organization  shall  propose  possible  system 
concepts. 
c. The system engineering organization shall support the MDR and ensure 
implementation of the MDR actions. 

6.4 Phase A: Feasibility


a. The  system  engineering  organization  shall  finalise  the  expression  of  the 
needs identified in Phase 0. 
b. The  system  engineering  organization  shall  propose  solutions  (including 
identification of criticalities and risks) to meet the perceived needs. 
c. The  system  engineering  organization  shall  support  the  PRR  and  ensure 
implementation of PRR actions. 

6.5 Phase B: Preliminary definition


a. The  system  engineering  organization  shall  establish  the  system 
preliminary definition for the solution selected at end of Phase A. 
b. The system engineering organization shall demonstrate that the solution 
meets  the  technical  requirements  according  to  the  schedule,  the  budget, 
the target cost and the organization requirements.  
c. The  system  engineering  organization  shall  support  the  SRR  and  PDR, 
and ensure implementation of the SRR and PDR actions. 

6.6 Phase C: Detailed definition


a. The  system  engineering  organization  shall  establish  the  system  detailed 
definition. 
b. The  system  engineering  organization  shall  demonstrate  its  capability  to 
meet  the  technical  requirements  of  the  system  technical  requirements 
specification. 
c. The  system  engineering  organization shall support  the  CDR  and ensure 
implementation of the CDR actions. 

35 
ECSS‐E‐ST‐10C 
6 March 2009 

6.7 Phase D: Qualification and production


a. The  system  engineering  organization  shall  finalize  the  development  of 
the system by qualification and acceptance. 
b. The  system  engineering  organization  shall  finalize  the  preparation  for 
operations and utilization. 
c. The  system  engineering  organization  shall  support  QR  and  AR  and 
ensure implementation of the QR and AR actions. 

6.8 Phase E: Operations / utilization


a. The system engineering organization shall support the launch campaign. 
b. The system engineering organization shall support the entity in charge of 
the  operations  and  utilization  following  the  terms  of  a  business 
agreement. 
c. The  system  engineering  organization  shall  support  the  FRR,  ORR,  LRR, 
CRR, ELR, and recurring products AR, and ensure implementation of the 
actions of those reviews. 
d. The system engineering organization shall ensure execution of all system 
engineering activities and provision of documents in support to anomaly 
investigations and resolutions. 
NOTE  Phase E and its reviews as presented in Table A‐1 
refer only to mission level. In case of lower level 
product, activities to be considered by the system 
engineering  organisation  are  only  related  to 
maintenance and anomaly investigations. 

6.9 Phase F: Disposal


a. The system engineering organization shall support the entity in charge of 
the disposal following the terms of a business agreement. 
b. The system engineering organization shall support the MCR and ensure 
implementation of the actions of the MCR. 
NOTE  Phase F and its review as presented in Table A‐1 
refer only to mission level. In case of lower level 
product, activities to be considered by the system 
engineering  organisation  are  only  related  to 
disposal. 

36 
ECSS‐E‐ST‐10C 
6 March 2009 

Annex A (informative)
System engineering documents delivery
per review

Scope  of  the  Table  A‐1  is  to  present  relation  of  documents  associated  to 
engineering activities to support project review objectives as specified in ECSS‐
M‐ST‐10. 
NOTE  This  table  constitutes  a  first  indication  for  the 
data  package  content  at  various  reviews.  The 
full content of such data package is established 
as  part  of  the  business  agreement,  which  also 
defines  the  delivery  of  the  document  between 
reviews. 
The  table  lists  the  documents  generated  by  the  engineering  organization 
necessary  for  the  project  reviews  (identified  by  “+”),  except  for  verification 
documents, which are identified in Table G‐1 of ECSS‐E‐ST‐10‐02. 
The  various  crosses  in  a  row  indicate  the  increased  levels  of  maturity 
progressively expected versus reviews. The last cross in a row indicates that at 
that review the document is expected to be completed and finalized. 
For  the  SEP,  DDF  and  DJF,  the  elements  of  these  documents  which  are  not 
identified by a “+” in the table are not expected to be delivered for the quoted 
review. 
NOTE  All  documents,  even  when  not  marked  as 
deliverables  in  Table  A‐1,  are  expected  to  be 
available  and  maintained  under  configuration 
management  as  per  ECSS‐M‐ST‐40  (e.g.  to 
allow for backtracking in case of changes). 
Documents listed in Table A‐1 are either ECSS‐E‐ST‐10 DRDs, or DRDs to other 
ECSS‐E‐XX,  ECSS‐M‐XX,  or  ECSS‐Q‐XX  standards,  or  defined  within  the 
referenced DRDs. 
 
 
 

37 
ECSS‐E‐ST‐10C 
6 March 2009 

Table A‐1: System engineering deliverable documents 
Phase 0  Phase A  Phase B  Phase C  Phase D  Phase E  Phase F 
Document title  ECSS document  DRD ref.  
MDR  PRR  SRR  PDR  CDR  QR  AR   ORR  FRR  LRR  CRR  ELR  MCR 
Mission description 
document 
ECSS‐E‐ST‐10  Annex B  +  +                        

                                               

Specifications                                              
Preliminary technical 
requirements  ECSS‐E‐ST‐10‐06  Annex A  +  +                           
specification  
Technical requirements 
specification  
ECSS‐E‐ST‐10‐06  Annex A       +                     
Interface requirements 
document 
ECSS‐E‐ST‐10  Annex M     +  +  +                      

                                               
System engineering plan  ECSS‐E‐ST‐10  Annex D  +  +  +  +  +  +  +                  

Technology plan  ECSS‐E‐ST‐10  Annex E    +  +  +                         

Technology matrix  ECSS‐E‐ST‐10  Annex F     +  +  +                        

Verification plan  ECSS‐E‐ST‐10‐02  Annex B     +  +  +  +  +  +                   

AIT QM/FM plan   ECSS‐E‐ST‐10‐03  Annex A         +  +  +  +                   


Orbital debris mitigation 
plan 
ISO 24113    +  +  +  +  +  +  +  +  +  +    +  + 

Other related plans 
(as called in ECSS‐E‐ST‐          +  +  +  +  +  +                  
10 Annex D) 
Coordinate system 
document 
ECSS‐E‐ST‐10‐09  Annex A    +  +  +  +  +               

                                               

38 
ECSS‐E‐ST‐10C 
6 March 2009 

Phase 0  Phase A  Phase B  Phase C  Phase D  Phase E  Phase F 


Document title  ECSS document  DRD ref.  
MDR  PRR  SRR  PDR  CDR  QR  AR   ORR  FRR  LRR  CRR  ELR  MCR 

Design definition file  ECSS‐E‐ST‐10  Annex G     +  +  +  +  +                     

Function tree  ECSS‐E‐ST‐10  Annex H     +  +  +                         

Product tree  ECSS‐M‐ST‐10  Annex B     +  +  +                          

Specification tree  ECSS‐E‐ST‐10  Annex J        +  +                         

Technical budget  ECSS‐E‐ST‐10  Annex I     +  +  +  +  +  +                   


Preliminary technical 
requirements 
specifications for next 
ECSS‐E‐ST‐10‐06       +  +                     
lower level  
Technical requirements 
specifications for next  ECSS‐E‐ST‐10‐06        +  +                   
lower level  
Design definition file for 
next lower level  
          +  +  +  +             
Interface control 
document  
ECSS‐E‐ST‐10‐24  Annex A        +  +  +  +  +  +  +  +          
Product User manual /  
User Manual 
ECSS‐E‐ST‐10  Annex P               +  +  +  +  +  +  +  +  + 

                                              

Design justification file  ECSS‐E‐ST‐10  Annex K     +  +  +  +  +                      


Requirements 
traceability matrix w.r.t.  ECSS‐E‐ST‐10  Annex N     +  +  +                           
next lower level 
Requirement justification 
file 
ECSS‐E‐ST‐10  Annex O  +  +  +  +                          

System concept report  ECSS‐E‐ST‐10  Annex C  +  +                             

Trade off reports  ECSS‐E‐ST‐10  Annex L  +  +  +  +  +                          

39 
ECSS‐E‐ST‐10C 
6 March 2009 

Phase 0  Phase A  Phase B  Phase C  Phase D  Phase E  Phase F 


Document title  ECSS document  DRD ref.  
MDR  PRR  SRR  PDR  CDR  QR  AR   ORR  FRR  LRR  CRR  ELR  MCR 
Verification control 
document 
ECSS‐E‐ST‐10‐02  Annex C     +(1)  +(1)   +(1)   +  +  +  +  +  +  +  +  + 

Test specification  ECSS‐E‐ST‐10‐03  Annex D              +  +  +  +  +  +  +  +  + 

Analysis report  ECSS‐E‐ST‐10  Annex Q     +  +  +  +  +  +  +  +  +  +  +  + 


Mathematical model 
description  
          +  +  +  +                      

Correlation report                  +  +                      

Test procedure  ECSS‐E‐ST‐10‐03  Annex C              +  +  +  +  +             

Test report  ECSS‐E‐ST‐10‐02  Annex D              +  +  +  +  +  +  +  +  + 

Verification report  ECSS‐E‐ST‐10‐02  Annex H              +  +  +  +  +  +  +  +  + 


Design justification file 
for next lower level  
                  +  +  +                   

Review of design report   ECSS‐E‐ST‐10‐02  Annex F              +  +                      

Inspection report  ECSS‐E‐ST‐10‐02  Annex G              +  +  +                   

GSE specifications                 +  +  +  +                   

GSE Data packages                    +  +  +                   

                                               

Other documents                                              

                               

                                               

                                               

Note (1) :  Document limited to the verification matrix 

40 
ECSS‐E‐ST‐10C 
6 March 2009 

Annex B (normative)
Mission description document (MDD) –
DRD

B.1 DRD identification

B.1.1 Requirement identification and source document


This DRD is called from ECSS‐E‐ST‐10, requirement 5.3.1a. 

B.1.2 Purpose and objective


The objective of the mission description document (MDD) is to provide input for 
the  later  selection  of  the  best  concept  meeting  the  mission  statement  (MS)  in 
iteration  with  the  preparation  of  the  preliminary  technical  requirements 
specification (TS) (as defined in ECSS‐E‐ST‐10‐06 Annex A). 
It is prepared in Phase 0 and Phase A for each possible concept, as indicated in 
requirement 5.3.1a. 
Links and chronology amongst the MS, TS, MDD, system engineering plan, project 
management plan and system concept report are provided on the Figure B‐1. 
The  MDD  is  produced  by  system  engineering  organization  of  the  mission 
responsible  (typically  an  Agency  or  other  institutional  actors  )  )  and  defines  a 
concept  that  aims  at  satisfying  the  preliminary  technical  requirements 
specification,  and  presents  how  the  objectives,  operation  profile,  major  system 
events and capabilities, contingencies and performance standards are expected to 
be achieved.  
For  each  mission  concept,  the  MDD  is  a  complete  description  of  that  concept. 
And to each MDD a SEP evaluating the related system engineering effort and a 
report evaluating the related programmatic aspect are associated. 
The  system  concept  report  assesses  the  different  concepts  from  a  technical, 
programmatic  and  risk  point  of  view,  includes  a  trade‐off  including  weighting 
factors  which  bears  some  management  aspects,  followed  by  a  system  concept 
selection. 

41 
ECSS‐E‐ST‐10C 
6 March 2009 

Figure B‐1: Relationship between documents  

B.2 Expected response

B.2.1 Scope and content

<1> Introduction 
a. The MDD shall contain a description of the purpose, objective, content and 
the  reason  prompting  its  preparation  (e.g.  logic,  organization,  process  or 
procedure). 

<2> Applicable and reference documents 
a. The  MDD  shall  list  the  applicable and reference  documents  in support  to 
the  generation  of  the  document,  and  include,  as  a  minimum,  the  current 
preliminary technical requirements specification. 

<3> Preliminary technical requirements specification 
summary 
a. The  MDD  shall  provide  a  summary  of  the  preliminary  technical 
requirements  specification  objectives  and  list  the  design  driving 
requirements, derived from the current initial specification. 

42 
ECSS‐E‐ST‐10C 
6 March 2009 

<4> Concept description 
a. The MDD shall provide: 
1. Overview of the concept 
2. Mission analysis 
3. System description, element by element 
NOTE  For example: For a spacecraft, its ground control 
segment, and a user segment, e.g. 
Space Segment  
• Payload  
• Platform  
• Launch Vehicle  
• Orbit related aspects 
• On‐Board Data Handling  
• Reference  Operation  Scenarios  /  Observation 
characteristics 
• Operability / Autonomy Requirements  
Ground Segment  
• Functional Requirements and Major Elements  
• Monitoring and Control Segment  
• Data Processing Segment  
User segment 
• Functional Requirements and Major Elements  
• Monitoring requirements  
b. Description of how the system works in each mission phase 
1. Performance drivers 
2. Constraints 
3. Main events 
4. Operations scenarios 
NOTE  For  example:  For  a  spacecraft,  the  following 
phase: 
• Launch preparation  
• Launch and Early Orbit Phase  
• In Orbit Commissioning  
• Nominal Operations  
• Spacecraft Disposal  

43 
ECSS‐E‐ST‐10C 
6 March 2009 

<5> Assessment of the performance 
a. The MDD shall provide the 
1. assessment  against  the  current  preliminary  technical  requirements 
specification requirements, and 
2. identification  of  non‐compliances,  and  their  impact  on  the  current 
preliminary technical requirements specification. 

<6> Identification of risk areas 
a. The  MDD  shall  provide  the  list  of  identified  risk  related  to  the  concept, 
including  as  a  minimum  technology,  contingencies  handling,  and 
programmatic aspects. 

<7> Conclusion 
a. The MDD shall summarize the strengths and weaknesses of the concept. 

B.2.2 Special remarks


None. 

44 
ECSS‐E‐ST‐10C 
6 March 2009 

Annex C (normative)
System concept report – DRD

C.1 DRD identification

C.1.1 Requirement identification and source document


This DRD is called from ECSS‐E‐ST‐10, requirement 5.3.3c. 

C.1.2 Purpose and objective


The  system  concept  report  describes  the  principal  technical  characteristics  of 
alternative  system  concepts,  relating  to  performance,  architectures,  driving 
technologies,  interfaces,  risk,  their  evaluation  and  classification,  and  later 
addresses the selected concept. 

C.2 Expected response

C.2.1 Scope and content


a. The system concept report shall be an instantiation of the trade‐off report 
at system level in Phase 0 and Phase A of a project, conforming to ECSS‐E‐
ST‐10 Annex L. 
NOTE  The  system  concept  report  can  be  extended  to 
Phase B where needed (e.g. late trade‐offs). 
b. This  report  shall  address  all  technical  (e.g.  engineering  disciplines), 
programmatic and related aspects relevant to the system. 
c. Where  relevant,  specific  e.g.  discipline  trade‐off’s  shall  be  performed, 
contributing  to  the  system  trade‐off,  each  one  being  reported  in  a 
document conforming to ECSS‐E‐ST‐10 Annex L. 

C.2.2 Special remarks


None.

45 
ECSS‐E‐ST‐10C 
6 March 2009 

Annex D (normative)
System engineering plan (SEP) – DRD

D.1 DRD identification

D.1.1 Requirement identification and source document


This DRD is called from ECSS‐E‐ST‐10, requirements 5.1a and 5.3.4a. 

D.1.2 Purpose and objective


The  objective  of  the  system  engineering  plan  (SEP)  is  to  define  the  approach, 
methods, procedures, resources and organization to co‐ordinate and manage all 
technical  activities  necessary  to  specify,  design,  verify,  operate  and  maintain  a 
system  or  product  in  conformance  with  the  customer’s  requirements.  In 
particular  the  SEP  is  established  to  fulfil  the  major  technical  project  objectives, 
taking  into  account  the  defined  project  phases  and  milestones  (as  defined  in 
ECSS‐M‐ST‐10).  
The  SEP  covers  the  full  project  lifecycle  according  to  the  scope  of  the  business 
agreement. It is established for each item of the product tree (as defined in ECSS‐
M‐ST‐10). 
It highlights the risks, the critical elements, the specified technologies, as well as 
potential commonalities, possibilities of reuse and standardization, and provides 
means for handling these issues. 
The SEP is an element of the project management plan (as defined in ECSS‐M‐ST‐10). 
NOTE  It  is  important  to  adapt  the  SEP  content  to  the 
phase  of  the  project,  with  more  information  on 
risk  analysis  and  new  technologies  in  early 
phases 0,  A  and  B,  and  more  information  on 
verification and validation aspects in phases C, D. 

46 
ECSS‐E‐ST‐10C 
6 March 2009 

D.2 Expected response

D.2.1 Scope and content

<1> Introduction 
a. The SEP shall contain a description of the purpose, objective, content and 
the reason prompting its preparation (e.g. programme or project reference 
and phase). 

<2> Applicable and reference documents 
a. The SEP shall list the applicable and reference documents in support to the 
generation of the document. 
b. The  SEP  shall  include  the  references  to  the  following  applicable 
documents: 
1. Business agreement 
2. Project management plan, as defined in ECSS‐M‐ST‐10 Annex A 
3. Product assurance plan, as defined in ECSS‐Q‐ST‐10 Annex A 
4. Configuration  management  plan,  as  defined  in  ECSS‐M‐ST‐40 
Annex A 
5. Production plan 
6. Mission operations plan, as defined in ECSS‐E‐ST‐70 Annex G 
7. ILS plan. 

<3> Project overview 

<3.1> Project objectives and constraints 
a. The SEP shall contain the following description of: 
1. The  project  objective  and  the  main  elements  that  characterize  the 
user’s need. 
2. The  objective  of  the  system  or  product  as  established  by  the  TS  (as 
defined in the ECSS‐E‐ST‐10‐06 Annex A). 
3. The main elements of the system architecture (i.e. first level elements 
of the architecture adopted for the system and identification of their 
reuse constraints). 
4. The  principal  characteristics  of  the  project  lifecycle  and  the 
incremental  development  of  the  system  (e.g.  successive  versions, 
progressive implementation of system functions). 
5. The  main  elements  supporting  the  project  lifecycle  (e.g.  ground 
support equipments, and facilities). 

47 
ECSS‐E‐ST‐10C 
6 March 2009 
6. The  organizational  constraints  impacting  system  engineering 
activities (e.g. the external and internal industrial organization (e.g. 
contractors, partners, suppliers, own company) constraints). 
7. The list of the critical issues identified at the beginning of the project 
phase(s). 
8. The list of national and international regulations. 
9. The  capacity  for  verification  and  validation  of  the  product,  taking 
into  account  the  means  available,  e.g.  for  tests,  analysis,  or 
simulation. 

<3.2> Product evolution logic 
a. The SEP shall detail the incremental development of the system:  
1. progressive implementation of system functionalities, 
2. identification of possible successive versions,  
3. objectives  and  strategy  for  the  implementation  of  the  successive 
versions. 

<3.3> Project phase(s), reviews and planning 
a. The  SEP  shall  provide  an  implementation  and  schedule  of  the  system 
engineering  activities  and  identify  for  the  considered  phase(s),  as  a 
minimum: 
1. the main project milestones driving the system engineering process, 
2. the  phase(s)  of  the  project  lifecycle  and  the  main  reviews  in 
accordance to project management plan. 
b. The  SEP  shall  provide  dates  of  milestones  or  the  duration  of  phases  and 
the critical path according to the project master schedule. 

<3.4> Procurement approach 
a. The  SEP  shall  describe  the  strategy  for  acquisition  of  the  items  of  the 
system or products defined in the product tree (e.g. make or buy, product 
line, incremental development). 

<3.5> Initial critical issues 
a. The  SEP  shall  list  the  critical  issues  identified  at  the  beginning  of  the 
project  phase(s)  covered  in  the  SEP  (e.g.  any  specific  issues,  problems, 
critical  subjects,  which  require  dedicated  attention,  investigation,  action 
and planning). 

<4> System design approach 

<4.1> System engineering inputs 
a. The  SEP  shall  list  the  driving  inputs  for  the  system  engineering  activities 
described and defined by the: 
1. business agreement, 

48 
ECSS‐E‐ST‐10C 
6 March 2009 
2. outputs  from  previous  phase(s)  or  expected  under  the  heading  of 
activities which are not controlled within the context of this SEP (e.g. 
data  provided  by  the  customer,  data  coming  from  other  projects, 
upstream or predevelopment studies, product lines), 
3. project management plan, product assurance plan, risk management 
plan, and configuration and documentation management plans. 
b. The  SEP  shall  list  the  external  means  and  facilities  (e.g.  equipment, 
software,  and  premises)  made  available  by  the  customer  or  by  any  other 
entity external to the organization that is responsible of this SEP, and, for 
each  identified  mean  or  facility,  identify  the  applicable  interface 
requirements (e.g. interface control documentation) as well as the authority 
in charge of it. 
c. The  SEP  shall  list  the  internal  means  and  facilities  (e.g.  equipment, 
software,  and  premises)  made  available  by  the  organization  in  charge  of 
the development of the system or product. 
d. The  SEP  shall  contain  the  Coordinate  System  Document  (as  defined  in 
ECSS‐E‐ST‐10‐09 Annex A). 
e. The SEP shall define the units system to be used in the project. 

<4.2> System engineering outputs 
a. The  SEP  shall  list  the  specified  system  engineering  outputs  as  defined  in 
ECSS‐E‐ST‐10 clause 6 for the specific project phase(s) covered in the SEP. 
NOTE  An  overview  of  document  delivery  is  given  in 
Annex A. 
b. The SEP shall describe the following: 
1. The  strategy  for  the  system  engineering  activities  in  line  with  the 
guidelines  addressed  by  the  management  plan.  In  particular, 
identifying  intermediate  technical  events  for  each  phase  in 
compliance with the master program schedule. 
2. The system design activities, with their objectives and major outputs 
according to the phase. 
3. The  major  engineering  activities  for  each  intermediate  technical 
events,  showing  their  mutual  interactions  and  their  relationships 
with  the  principal  milestones  (i.e.  internal  or  contractual)  of  the 
project. 
4. The  model  philosophy  (as  defined  in  ECSS‐E‐ST‐10‐02  clause  4.2.5) 
in terms of number and characterization of models, from system to 
the requested lower level, necessary to achieve a high confidence in 
the product verification.  
5. The margin policy according to project phase, product category and 
maturity level. 
c. The SEP shall also describe  
1. the  method(s)  and  process(es)  considered  for  the  engineering 
activities  (e.g.  concurrent  engineering,  value  analysis,  or  iteration 
cycle),  

49 
ECSS‐E‐ST‐10C 
6 March 2009 
2. the  interrelation  between  the  different  engineering  disciplines  and 
other  project  activities  (e.g.  production,  quality  assurance,  and 
operations and logistics),  
3. the interaction with other actors (e.g. customer and suppliers), 
4. the  consistency  and  coherency  of  simultaneous  activities  (e.g. 
performed in parallel), 
5. which and how, control activities are implemented, 
6. Assessment of potential COTS usage 
d. In  the  case  of  a  system  incremental  evolution,  the  SEP  shall  describe  the 
design strategy for the: 
1. development of the initial release of the product, 
2. development,  the  verification  of  subsequent  releases  and  their 
deployment, 
3. introduction of new technologies, 
4. tools and methods used for analysis, 
5. control of the evolutions for each release. 

<4.3> System engineering team responsibilities and organization 
a. The SEP shall contain the following: 
1. Definition  of  the  entities  participating  in  the  system  engineering 
activities  and  the  corresponding  functions  according  to  the  project 
management plan. 
2. Identification  of  key  engineering  roles  and  responsibilities  (e.g. 
system engineers, disciplines engineers, and technical managers). 
3. Description  of  the  co‐operative  work  amongst  the  different  teams 
participating in the system design. 

<4.4> System engineering interfaces 
a. The SEP shall describe the external and internal interfaces in line with the 
project management plan. 

<5> Implementation and related plans 

<5.1> System engineering tasks description 
<5.1.1> System engineering process description 
a. The  SEP  shall  describe  the  system  engineering  process  tailored  to  the 
specifics of the considered project, and identify all the system engineering 
tasks to be implemented from the starting conditions (e.g. kick‐off) to the 
closing  event  (e.g.  review),  their  relationship,  and  their  interfaces  with 
other actors of the project, and identify and describe any existing iteration 
within the process. 
NOTE  Details  are  provided  in  ECSS‐E‐HB‐10  “System 
engineering guidelines”. 

50 
ECSS‐E‐ST‐10C 
6 March 2009 
b. For  each  task,  the  input  information  and  their  origin,  the  document(s) 
delivered  (i.e.  expected  output)  and  their  destination,  the  system 
engineering  function(s)  performed  and  the  contribution  of  other  actors 
shall be identified. 
NOTE  Details  are  provided  in  ECSS‐E‐HB‐10  “System 
engineering guidelines”. 
<5.1.2> Engineering disciplines integration 
a. The  SEP  shall  address  the  following  activities  that  concern  the  different 
engineering  disciplines,  recalling  the  relevant  applicable  standards  and 
ancillary dedicated plans that are considered integral part of this SEP. 
b. The  SEP  shall  define  the  process  and  control  to  be  put  in  place  to  meet 
requirements  for  the  thermal,  structures,  mechanisms,  environmental 
control  and  life  support,  propulsion,  pyrotechnics,  mechanical  parts,  and 
materials functions and interfaces. 
NOTE  These  requirements  refer  to  Mechanical 
engineering as defined in ECSS‐E‐ST‐3x series of 
standards. 
c. The  SEP  shall  define  the  process  and  control  to  be  put  in  place  to  meet 
requirements  for  electrical  and  electronic  engineering,  covering  all 
electrical  and  electronic  aspects  of  the  relevant  space  product,  including 
functions  such  as  power  generation,  storage,  conversion  and  distribution, 
and  optical,  avionics  and  microwave  domains,  electromagnetic 
compatibility, and electrical interfaces.  
NOTE  These  requirements  refer  to  Electrical  and 
electronic engineering as defined in ECSS‐E‐ST‐20. 
d. The  SEP  shall  define  process  and  control  to  be  put  in  place  to  meet 
requirements  for  software  engineering,  covering,  amongst  others,  flight 
and ground software, checkout software and simulation software. 
NOTE  These requirements refer to Software engineering 
as defined in ECSS‐E‐ST‐40. 
e. The  SEP  shall  define  process  and  control  to  be  put  in  place  to  meet 
requirements  for  communication  engineering,  covering,  amongst  others, 
spacecraft‐to‐ground,  spacecraft‐to‐spacecraft,  ground‐to‐ground  and  on‐
board communications links.  
NOTE 1  These  requirements  refer  for  Communications 
engineering as defined in ECSS‐E‐ST‐50. 
NOTE 2  It  includes  aspects  such  link  budgets,  data 
management,  RF,  audio  and  video 
communications and protocols. 
f. The  SEP  shall  define  process  and  control  to  be  put  in  place  to  meet 
requirements  for  control  engineering,  covering,  amongst  others,  AOCS, 
robotics, rendez‐vous and docking. 
NOTE  These  requirements  refer  to  Control  engineering 
as defined in ECSS‐E‐ST‐60. 

51 
ECSS‐E‐ST‐10C 
6 March 2009 
g. The  SEP  shall  define  the  process  and  control  to  be  put  in  place  to  meet 
requirements  specifying  natural  environment  for  all  space  regimes  (e.g. 
debris  regulations,  or  planetary  contamination  protection)  and  general 
models and rules for determining the local induced environment 
NOTE  These  requirements  refer  to  Space  environment 
as defined in ECSS‐E‐ST‐10‐04. 
h. The  SEP  shall  define  the  process  and  control  to  be  put  in  place  to  meet 
requirements  for  the  approach,  methods,  procedures,  organization  and 
resources to be implemented to ensure proper technical interfaces between 
system engineering and production.  
i. The  SEP  shall  define  the  process  and  control  to  be  put  in  place  to  meet 
requirements  of  operations  of  the  space  segment,  covering,  amongst 
others: 
1. mission operation definition and preparation,  
2. mission and trajectory analysis, and 
3. operability  analysis  (e.g.  autonomy,  operational  scenario,  nominal 
and non‐nominal modes, failure detection isolation and recovery). 
NOTE  These  requirements  refer  to  Operations 
engineering as defined in ECSS‐E‐ST‐70. 
j. The  SEP  shall  define  the  process  and  control  to  be  put  in  place  to  meet 
requirements  for  ground  and  in‐orbit  logistics  and  maintenance, 
addressing,  amongst  others,  technical  activities,  related  engineering 
standards,  methods  and  analyses  to  be  performed  to  ensure  that  the 
development of space systems (i.e. manned and unmanned) properly takes 
into account and integrates the supportability and support aspects for the 
whole life cycle. 
k. The  SEP  shall  define  the  process  and  control  to  be  put  in  place  to  meet 
requirements for human activities and environments associated with space 
systems.  
NOTE  These  requirements  refer  to  Human  factors 
engineering as defined in ECSS‐E‐ST‐10‐11. 
l. The  SEP  shall  define  process  and  control  to  be  put  in  place  to  meet 
requirements  for  implementation  of  design  selections  relating  to  humans 
for  any  item  with  associated  human  interface,  including  computer  based 
system and equipment. 
<5.1.3> Work package 
a. The  SEP  shall  define  and  describe  the  work  package(s)  for  the  relevant 
engineering tasks, which are maintained in the work breakdown structure. 

<5.2> Related plans 
a. When  the  SEP  includes  sub‐plans  covering  parts  of  system  engineering 
activities, these sub‐plans shall be annexed to the SEP. 
b. The  system  engineering  organization  shall  identify  in  the  SEP  the  other 
plans relevant to its activity belonging to the following categories: 
NOTE  Some of these plans can be integrated in the SEP 
in the early phases of a project.  

52 
ECSS‐E‐ST‐10C 
6 March 2009 
1. Programmatic plans 
NOTE  Examples  of  programmatic  plans  are:  the  SEP 
plans  of sub‐products  constituting  the system  or 
product,  Industrial  procurement  plan,  risk 
management  plan,  off‐the‐shelf  plan  (see  ECSS‐
Q‐ST‐20‐10). 
2. Verification plans 
NOTE 1  Examples  of  verification  plans  are:  verification 
plan  (VP),  AIT  plan,  AIV  plan  and  technology 
plan,  system  calibration  plan,  Security  Aspects 
Verification  Plan.  Some  of  those  DRDs  are 
defined in this document, in ECSS‐E‐ST‐10‐02 or 
ECSS‐E‐ST‐10‐03.  
NOTE 2  VP  and  AIT  plans  can  be  integral  parts  of  the 
SEP,  or  rolled  out  separately  (without  overlap), 
or  combined  as  the  AIV  Plan  which  can  also  be 
rolled  out  separately.  However,  the  existence  of 
the  AIV  Plan  excludes  independent  VP  and  AIT 
plans 
3. Engineering discipline plans 
NOTE  Examples  of  engineering  discipline  plans  are: 
Fracture Control Plan (see ECSS‐E‐ST‐32), Micro‐
gravity  Control  Plan,  Electro‐Magnetic 
Compatibility  Plan  (see  ECSS‐E‐ST‐20),  Audible 
Noise  Control  Plan,  Radio  Frequency  Plan, 
Alignment  Requirements  and  Control  Plan, 
System  Performance  Simulations  Plan,  Software 
Development  Plan,  Orbital  Debris  Mitigation 
Plan and Disposal Plan (as defined in ISO 24113), 
Planetary  protection  Plan,  Cleanliness  and 
Contamination Control Plan.  
4. Operations plans 
NOTE  Examples  of  operation  plans  are:  launch  site 
operations  and  logistics  plan,  system 
commissioning and operation support plan,  
c. The  SEP  shall  describe  the  constraints  and  the  interactions  impacting  the 
system  engineering  activities  derived  from  the  analysis  of  the  plans 
identified as relevant in D.2.1<5.2>b. 

<5.3> System engineering methods, tools and models 
a. The SEP shall list and briefly describe the methods, tools, and data models 
that the system engineering team uses in performing their tasks. 
b. In  relation  to  requirements  traceability  and  demonstration  of  verification 
(compliance with requirements, VCD), the specific methods and tools shall 
be described (including interfaces to next lower level suppliers), and reuse 
of elements (e.g. COTS) identified. 

53 
ECSS‐E‐ST‐10C 
6 March 2009 

<5.4> Critical issues 
a. The  SEP  shall  describe  any  specific  issues,  problems  requiring  dedicated 
attention,  investigations  or  actions  during  the  current  phase  and  identify 
risks, and risk mitigation measures. 

<6> System engineering for the following phase(s) 
a. The SEP shall introduce the system engineering activities, to be conducted 
during  subsequent  phase(s)  of  the  project,  and  as  a  minimum,  list  any 
identified  critical  issue  and  risk  to  be  mitigated  during  the  subsequent 
phase(s). 

D.2.2 Special remarks


None. 

54 
ECSS‐E‐ST‐10C 
6 March 2009 

Annex E (normative)
Technology plan (TP) – DRD

E.1 DRD identification

E.1.1 Requirement identification and source document


This DRD is called from ECSS‐E‐ST‐10, requirement 5.6.7b. 

E.1.2 Purpose and objective


The  objective  of  the  technology  plan  (TP)  is  to  define  the  approach,  methods, 
procedures,  resources  and  organization  to  evaluate  the  ability  of  a  critical 
technology to meet the intended requirements. Also, the objective of this plan is 
to  ensure  effective  preparation  of  the  technologies  necessary  for  a  timely 
implementation of the system, in accordance to the requirements imposed by the 
specific characteristics of the relevant product.  
It  is  established  for  each  item  of  the  function  tree  (as  defined  in  ECSS‐E‐ST‐10, 
Annex H), and highlights the technical requirements, and the critical technology 
of each item.  
The TP is part of the system engineering plan (SEP) (as defined in ECSS‐E‐ST‐10, 
Annex E). 

E.2 Expected response

E.2.1 Scope and content

<1> Introduction 
a. The  TP  shall  contain  a  description  of  the  purpose,  objective,  content  and 
the reason prompting its preparation (e.g. programme or project reference 
and phase). 

<2> Applicable and reference documents 
a. The TP shall list the applicable and reference documents in support to the 
generation  of  the  document  and  include  the  reference  to  the  following 
applicable documents: 

55 
ECSS‐E‐ST‐10C 
6 March 2009 
1. SEP 
2. Technology matrix (as defined in ECSS‐E‐ST‐10, Annex F) 
3. Function tree 
4. Specification tree. 

<3> Project overview 
a. The TP shall contain a summary of the main aspects of: 
1. project objectives and constraints (i.e. section <3.1> of ECSS‐E‐ST‐10, 
Annex D ʺSEP DRDʺ); 
2. product evolution logic (i.e. section <<3.2> of ECSS‐E‐ST‐10, Annex D 
ʺSEP DRDʺ); 
3. project phase(s), reviews and planning (i.e. section <3.3> of ECSS‐E‐
ST‐10, Annex D ʺSEP DRDʺ), 
4. Procurement approach (i.e. section <3.4> of ECSS‐E‐ST‐10, Annex D 
ʺSEP DRDʺ) 

<4> Tasks description 

<4.1> TP expected outputs 
a. The  TP  expected  output  shall  be  an  answer  concerning  the  possibility for 
using the identified or needed technology to perform a function. 

<4.2> TP inputs 
a. For each system function, the TP input shall be: 
1. technical requirements,  
2. the selected technology or technological element and its TRL,  
3. the list of the identified project risks and critical aspects, and 
4. the schedule for Engineering activities. 

<4.3> TP tasks 
a. The TP shall establish and describe the necessary activities to complete the 
acquisition  of  each  technology  or  technological  element,  including 
verification  strategies  and  methods,  and  the  link  to  product  assurance 
aspects. 
b. The  TP  shall  define  the  model  philosophy  for  each  technology  or 
technological element, based on an assessment on the maturity status and 
on the criticality of the technology with respect to functionsʹ requirements. 
c. The TP shall describe the technology development activities, their required 
or  possible  interrelations  and  timings,  as  necessary  for  the  satisfactory 
acquisition  of  the  technologies  and  procurement  of  the  technological 
elements. 

56 
ECSS‐E‐ST‐10C 
6 March 2009 
d. The  TP  shall identify  technical  milestones,  showing  their  interactions and 
relationships with the SEP milestones. 

<4.4> Responsibilities and organization 
a. The TP shall contain the following: 
1. definition  of  the  entities  participating  in  the  engineering  activities 
and the corresponding functions according to the SEP; 
2. identification  of  key  engineering  roles  and  responsibilities  for  each 
technology or technological element. 

<4.5> TP interfaces 
a. The TP shall describe the external and internal interfaces in conformance to 
the SEP. 

<5> Critical issues 
a. The TP shall describe, for any identified technology risk and related critical 
aspects for the project, the specific actions taken for risk mitigation based 
on identified technology readiness level (TRL). 

E.2.2 Special remarks


a. The content of the TP may be merged with the content of the SEP. 
b. The  TP  shall  introduce  the  related  activities,  to  be  conducted  during  all 
phase(s) of the project. 

57 
ECSS‐E‐ST‐10C 
6 March 2009 

Annex F (normative)
Technology matrix - DRD

F.1 DRD identification

F.1.1 Requirement identification and source document


This DRD is called from ECSS‐E‐ST‐10, requirement 5.6.7a. 

F.1.2 Purpose and objective


The technology matrix presents, for each technical requirement/function, the list 
of technologies or technological elements, which have the potential to meet  this 
requirement. It summarizes candidate technologies per individual requirement. 
The technology matrix is part of the Design Justification File (as defined in ECSS‐
E‐ST‐10, Annex K). It is the basic document for presenting all identified potential 
technologies for the product. 

F.2 Expected response

F.2.1 Scope and content

<1> Introduction 
a. The technology matrix shall contain a description of the purpose, objective, 
content and the reason prompting its preparation. 

<2> Applicable and reference documents 
a. The technology matrix shall list the applicable and reference documents in 
support to the generation of the document and include the reference to the 
following applicable documents: 
1. Specification tree 
2. Preliminary technical requirements specifications 
3. Function tree. 

58 
ECSS‐E‐ST‐10C 
6 March 2009 

<3> List of technical requirements/functions 
a. The  technology  matrix  shall  list  the  system  technical 
requirements/functions  as  defined  in  the  functional  architecture  and  its 
corresponding function tree, and their associated preliminary TS. 

<4> List of potential technologies for each technical 
requirement/function 
a. The  technology  matrix  shall  list  the  system  technical 
requirements/functions  and  for  each,  a  potential  technology  or 
technological element. 
NOTE  Sources  to  identify  potential  technologies  are 
technology  watch,  corporate  technology  plan,  or 
research and development programme. 
b. For  each  technology  or  technological  element,  the  following  information 
shall be listed: 
1. index of technology readiness and maturity as defined in proposed 
table in definition 3.2.12 “technology readiness level”; 
2. proof  of  companyʹs  maturity  concerning  the  knowledge  and 
mastership  of  the  technology,  including  a  description  of  the 
necessary technology acquisition activities; 
3. identification  of  potential  risks,  e.g.  technology  availability, 
programmatic and financial aspects. 

<5> Ranking of the potential technologies for each function 
a. The technology matrix shall propose a ranking of the potential technology 
or technological element for each system requirement/ function. 

<6> Conclusion 
a. The  technology  matrix  shall  provide,  for  each  system 
requirement/function,  the  selected  technology  or  technological  element,  a 
list  of  the  identified  project  risks  and  critical  aspects,  and  an  identified 
back‐up technological solution. 

F.2.2 Special remarks


None. 

59 
ECSS‐E‐ST‐10C 
6 March 2009 

Annex G (normative)
Design definition file (DDF) - DRD

G.1 DRD identification

G.1.1 Requirement identification and source document


This  DRD  is  called  from  ECSS‐E‐ST‐10,  requirements  5.3.1c,  5.3.1f,  5.4.1.1b  and 
5.4.1.4a. 

G.1.2 Purpose and objective


The  objective  of  the  design  definition  file  (DDF)  is  to  establish  the  technical 
definition  of  a  system  or  product  that  complies  with  its  technical  requirements 
specification (as defined in ECSS‐E‐ST‐10‐06 Annex A). 
The design definition file is a basic structure referring to all information relative 
to  the  functional  and  physical  architectures  and  characteristics  of  a  system  or 
product,  necessary  for  its  identification,  manufacturing,  utilization,  support, 
configuration management and removal from service. 
The  DDF  is  a  collection  of  all  documentation  that  establishes  the  system  or 
product  characteristics  such  as  lower  level  technical  specifications,  design  and 
interface  description,  drawings,  electrical  schematics,  specified  constraints  (e.g. 
on materials, manufacturing, processes, and logistic). 
It details the as‐designed configuration baseline (as defined in ECSS‐M‐ST‐40) of 
the system or product and is built up and updated under the responsibility of the 
team  in  charge  of  system  engineering.  It  is  the  technical  baseline  for  the 
production,  assembly,  integration  and  test,  operations  and  maintenance  of  the 
product. 
The  DDF,  the  technical  requirements  specification,  and  the  Design  Justification 
File  (as  defined  in  ECSS‐E‐ST‐10  Annex  K)  are  the  basic  documents  used  for 
product development. They are interrelated such as: 
• the design (i.e. DDF) is the response to the requirements stated in the TS,  
• the justification (i.e. DJF) demonstrates the conformance of the design (i.e. 
DDF) to the requirements stated in the TS. 
NOTE  The  DDF  is  a  logical  file  covering  all  TS 
disciplines required for the considered system. In 
general, the elements of the DDF are “rolled out” 
as separate documents. 

60 
ECSS‐E‐ST‐10C 
6 March 2009 

G.2 Expected response

G.2.1 Scope and content

<1> Introduction 
a. The  DDF  shall  contain  a  description  of  the  purpose,  objective  and  the 
reason prompting its preparation (e.g. programme or project reference and 
phase).  

<2> Applicable and reference documents 
a. The DDF shall contain the list of applicable and reference documents, used 
in support to the generation of the document.  
b. The  DDF  shall  include  the  reference  to  the  following  applicable 
documents: 
1. Business agreement 
2. System engineering plan (as defined in ECSS‐E‐ST‐10 Annex D) 
3. Coordinate  system  document  (as  defined  in  ECSS‐E‐ST‐10‐09 
Annex A) 
4. Technical requirements specification (TS) 
5. Product assurance plan 
6. Configuration management plan (as defined in ECSS‐M‐ST‐40) 
7. Configuration status report (as defined in ECSS‐M‐ST‐40). 
c. The DDF shall refer to DDFs of next higher and lower level products. 

<3> Summary of the project and technical requirements  
a. The  DDF  shall  contain  a  brief  description  of  the  product  and  of  the  main 
technical  requirements  throughout  its  life  cycle  phases  (e.g.  launch, 
deployed, operations, end‐of‐life). 
b. The  DDF  shall  contain  the  description  of  the  system  or  product  design 
documentation,  based  on  the  product  tree  (as  defined  in  ECSS‐M‐ST‐10) 
and also include, or refer to, the specifications tree (as defined in ECSS‐E‐
ST‐10 Annex J). 
c. The  DDF  of  a  system  shall  contain  at  least  the  technical  requirements 
specifications of the elements in which the system is broken down  

<4> Functional description 

<4.1> Functional architecture 
a. The DDF shall contain the description of the functional architecture of the 
system  or  product  i.e.  the  arrangement  of  functions,  their  sub‐functions 

61 
ECSS‐E‐ST‐10C 
6 March 2009 
and interfaces (internal and external), and the performance requirements to 
satisfy the requirements of the TS. 
b. The  DDF  shall  present  the  data  and  their  flow  interchanged  between  the 
different  functions,  the  conditions  for  control,  and  the  execution 
sequencing for the different operational modes and states. 
NOTE  The  Functional  Architecture  is  an  output  of  the 
functional  analysis  process  (as  defined  in  ECSS‐
E‐ST‐10 clause 5.3.1a) 

<4.2> Function tree 
a. The DDF shall contain or refer to the system or product function tree, the 
latter conforming to ECSS‐E‐ST‐10 Annex H. 

<4.3> Description of functional chains 
a. The  DDF  shall  describe  the  functional  chains  that  contribute  to  the 
realization of the functional requirements of the TS and their contributing 
functions, consider the different operational modes and states, and indicate 
the selected physical implementation for each of the functions. 

<5> Physical description 

<5.1> Physical architecture 
a. The  DDF  shall  contain  the  description  of  physical  architecture  of  the 
system  or  product  i.e.  the  arrangement  of  elements,  their  decomposition, 
interfaces (internal and external), and physical constraints, which form the 
basis  of  a  system  or  product  design  to  satisfy  the  functional  architecture 
and the technical requirements. 
NOTE  The  Physical  Architecture  is  an  output  of  the 
preliminary  design  definition  activities  (as 
defined in clause 5.3.1f). 

<5.2> Product tree 
a. The DDF shall contain or refer to the product tree of the system or product, 
as defined in ECSS‐M‐ST‐10 Annex B. 
NOTE  The Product Tree is a breakdown of the Physical 
Architecture. 

<5.3> Specification tree 
a. The  DDF  shall  contain  or  refer  to  the  specification  tree  of  the  system  or 
product, the latter conforming to Annex J. 

<5.4> Description of elements of the physical architecture 
a. The DDF shall provide 
1. the nomenclature of the system or product,  
2. the overall system or product drawings, 

62 
ECSS‐E‐ST‐10C 
6 March 2009 
3. for  each  element  of  the  system,  the  description  of  the  different 
constituents of the physical architecture, 
4. the characteristics of the respective elements,  
5. their  configuration  management  identifier  (e.g.  hardware  part 
number,  software  version  number,  drawings  number,  electrical 
schematics numbers). 
b. The DDF shall reference any documentation containing detailed technical 
descriptions  and  associated  matrices  to  ensure  overall  consistency  and 
completeness. 

<5.5> Description of interfaces 
a. The  DDF  shall  describe  the  physical  and  functional  characteristics  of  the 
internal and external interfaces of the system and refer to the relevant IRD 
and ICD, respectively conforming to Annex M and ECSS‐E‐ST‐10‐24. 

<6> System technical budget, margins and deviations 
a. The DDF shall present the budget allocation of the technical parameters of 
the  system  and  provide  the  actual  status  of  the  system  margins,  and 
deviations.  
b. The DDF shall contain or refer to the system or product technical budget, 
the latter conforming to Annex I. 

<7> System design constraints 

<7.1> Constraints for production 
a. The  DDF  shall  present  the  constraints  induced  by  the  system  or  product 
design  definition  on  the  production  activities  e.g.  operational  allowable 
envelopes,  restrictions  on  assembling  sequences,  procedures  and  testing 
modes,  exclusion  zones,  manufacturing  environmental  conditions,  and 
conditions for procurement. 

<7.2> Constraints for operation  
a. The  DDF  shall  present  the  constraints  induced  by  the  system  or  product 
design definition on the implementation of the operations e.g. operational 
allowable envelopes, restrictions on operating modes, and exclusion zones. 

<7.3> Constraints for transportation and storage 
a. The  DDF  shall  present  the  constraints  induced  by  the  system  or  product 
design definition on the transportation activities and during the periods of 
storage  of  the  product  e.g.  allowable  envelopes,  restrictions  on 
transportation  and  storage,  exclusion  zones,  packaging,  shock  levels, 
temperature  environments,  humidity,  cleanliness,  regulations,  and 
dangerous materials. 

63 
ECSS‐E‐ST‐10C 
6 March 2009 

<7.4> Constraints for maintainability 
a. The  DDF  shall  present  the  constraints  induced  by  the  system  or  product 
design  definition  on  the  maintenance  activities  and  procedures  e.g. 
operational  allowable  envelopes,  accessibility,  tooling,  support  materials, 
parts availability, and deliveries. 

<8> Engineering database 
a. The  DDF  shall  contain  the  information  on  the  system  or  product 
engineering database that contains the complete set of design parameters, 
or a reference to it. 
NOTE  Information about the set of design parameters is 
provided in ECSS‐E‐TM‐10‐10. 

<9> Conclusion 
a. The DDF shall list and summarize all deviations of the design with respect 
to  the  technical  specifications  and  constraints  induced  by  the  system  or 
product design definition. 

G.2.2 Special remarks


None. 

64 
ECSS‐E‐ST‐10C 
6 March 2009 

Annex H (normative)
Function tree - DRD

H.1 DRD identification

H.1.1 Requirement identification and source document


This DRD is called from ECSS‐E‐ST‐10, requirement 5.3.1b. 

H.1.2 Purpose and objective


The  objective  of  the  function  tree  document  is  to  describe  the  hierarchical 
decomposition  of  a  system  or  product  capabilities  into  successive  level  of 
functions and sub‐functions.  
The function tree is part of the Design Definition File. It is the starting point for 
the establishment of the Product Tree (as defined in ECSS‐M‐ST‐10) and is a basic 
structure  to  establish  preliminary  technical  requirements  specification(s)  (as 
defined in ECSS‐E‐ST‐10‐06 Annex A).  

H.2 Expected response

H.2.1 Scope and content

<1> Introduction 
a. The  function  tree  document  shall  contain  a  description  of  the  purpose, 
objective and the reason prompting its preparation. 

<2> Applicable and reference documents 
a. The  function  tree  document  shall  contain  the  list  of  applicable  and 
reference documents, used in support to the generation of the document. 

<3> Project summary and user’s need presentation 
a. The function tree document shall contain a brief description of the project 
and of the key user’s needs. 

65 
ECSS‐E‐ST‐10C 
6 March 2009 

<4> Tree structure 
a. The  function  tree  document  shall  provide  the  complete  list  of  functions 
that  the  system  or  product  shall  perform,  and  contain  a  graphical 
representation where the main specified function(s) (i.e. at the top level of 
the tree) is/are decomposed into lower level functions. 
b. When  recurrent  products  from  previous  space  projects  are  used,  the 
product’s  functions  shall  be  identified  in  the  tree  structure,  and  addition, 
every  necessary  function  by  the  system  or  product  that  is  not  under  the 
supplier’s responsibility identified in the tree structure. 

H.2.2 Special remarks


a. The function tree shall be coherent with other functional descriptions of the 
system or product (e.g. functional architecture, functional block diagram). 

66 
ECSS‐E‐ST‐10C 
6 March 2009 

Annex I (normative)
Technical budget - DRD

I.1 DRD identification

I.1.1 Requirement identification and source document


This DRD is called from ECSS‐E‐ST‐10, requirement 5.4.1.2a. 

I.1.2 Purpose and objective


The technical budget defines for each key engineering parameter of a system or 
product,  the  nature  of  this  parameter,  its  measure,  specified  value,  metrics 
requirements and current actual or computed value and assessed value. 
The technical budget is part of the Design Definition File (as defined in ECSS‐E‐
ST‐10  Annex  G).  It  is  the  basic  document  for  providing  adequate  control  of  the 
key  engineering  parameter  properties  to  meet  the  system  or  product  technical 
requirements. 

I.2 Expected response

I.2.1 Scope and content

<1> Introduction 
a. The technical budget shall contain a description of the purpose, objective, 
content and the reason prompting its preparation. 

<2> Applicable and reference documents 
a. The  technical  budget  shall  list  the  applicable  and  reference  documents  in 
support to the generation of the document. 

<3> List of selected key engineering parameters 
a. The technical budget shall:  
1. list  the  selected  key  engineering  parameters  (those  specified  by  the 
customer and those selected by the supplier), 

67 
ECSS‐E‐ST‐10C 
6 March 2009 
NOTE  Examples  of  key  engineering  parameters  are 
mass, communication links, power, and on‐board 
computer memory capacity. 
2. present the reason for their selection, 
3. identify for each key engineering parameters the stages of maturity 
of the design. 
4. present the related margin policy for these parameters. 

<4> Assessment of key engineering parameters 
a. For each key engineering parameter, the technical budget shall: 
1. provide the specified value of the parameter, 
2. provide  the  supplier’s  margin  resulting  of  the  allocation  of  the 
parameter to the lower level products, 
3. provide  the  specified  values  with  the  reference  to  the  relevant 
technical requirement of the lower level products,  
4. propose a specific program to conform to the specified value in case 
of nonconformance, 
5. contain  a  chart  of  parameter  history  that  presents  the  evolution  of 
the  parameter’s  value  at  the  different  design  maturity  steps  for 
which the evaluation of the parameter is performed, 
6. list  the  documentation  sources  (e.g. analysis  report and  verification 
report). 

<5> Conclusion 
a. The  technical  budget  shall  contain  a  conclusion  that  identifies  the  key 
engineering parameters having a negative margin, and identify for each of 
those: 
1. the impact on the technical requirements and the associated risk for 
the project, and 
2. the  specific  program  to  conform  to  the  specified  value  and  for 
project risk mitigation. 

I.2.2 Special remarks


None. 

68 
ECSS‐E‐ST‐10C 
6 March 2009 

Annex J (normative)
Specification tree - DRD

J.1 DRD identification

J.1.1 Requirement identification and source document


This DRD is called from ECSS‐E‐ST‐10, requirement 5.2.3.1c. 

J.1.2 Purpose and objective


The  objective  of  the  specification  tree  document  is  to  define  the  hierarchical 
relationship of all technical requirements specifications for the different elements 
of a system or product. 
The specification tree is part of the Design Definition File (as defined in ECSS‐E‐
ST‐10  Annex  G).  It  is  the  basic  structure  to  perform  the  system  or  product 
requirements traceability and to manage their internal interfaces. 

J.2 Expected response

J.2.1 Scope and content

<1> Introduction 
a. The specification tree document shall contain a description of the purpose, 
objective and the reason prompting its preparation.  

<2> Applicable and reference documents 
a. The  specification  tree  document  shall  contain  the  list  of  applicable  and 
reference documents, used in support to the generation of the document.  

<3> Project summary and user’s need presentation 
a. The  specification  tree  document  shall  contain  a  brief  description  of  the 
project and the key user’s needs. 

69 
ECSS‐E‐ST‐10C 
6 March 2009 

<4> Tree structure 
a. The  specification  tree  document  shall  provide  the  complete  list  of 
specifications  defining  the  system  or  product,  and  contain  a  graphical 
representation  where  the  system  or  product  specification  (i.e.  at  the  top 
level of the tree) is decomposed into lower level product specifications. 
b. When  recurrent  products  from  previous  space  projects  are  used,  their 
specification  shall  be  identified  in  the  tree  structure,  and  in  addition,  for 
every  necessary  product  that  is  not  under  the  supplier’s  responsibility, 
their specification shall be identified in the tree structure. 

J.2.2 Special remarks


a. The specification tree shall be coherent with the product tree (see ECSS‐M‐
ST‐10) and the business agreement structure (see ECSS‐M‐ST‐60). 

70 
ECSS‐E‐ST‐10C 
6 March 2009 

Annex K (normative)
Design justification file (DJF) - DRD

K.1 DRD identification

K.1.1 Requirement identification and source document


This  DRD  is  called  from  ECSS‐E‐ST‐10,  requirements  5.3.1d,  5.3.1g,  5.3.1h  and 
5.4.1.4b. 

K.1.2 Purpose and objective


The objective of the design justification file (DJF) is to present the rationale for the 
selection  of  the  design  solution,  and  to  demonstrate  that  the  design  meets  the 
baseline requirements. 
The  DJF  is  progressively  prepared  during  the  detailed  design  process  and 
according  to  the  system  engineering  plan  (SEP)  (as  defined  in  ECSS‐E‐ST‐10 
Annex D), and serves the following purposes: 
• it provides access to the necessary justification information, 
• it presents a review of all acquired justifications, 
• it  constitutes  a  basic  element  for  decision  taking  concerning  the  product 
definition qualification. 
The  DJF  together  with  the  Design  Definition  File  (DDF)  (as  defined  in  Annex  G) 
and  the  technical  requirements  specification  (TS)  (as  defined  in  ECSS‐E‐ST‐10‐06 
Annex A) are the basic documents used for the development of the product. These 
documents are used to monitor the evolution of the design. 
The DJF is a collection of all documentation that traces the evolution of the design 
during  the  development  and  maintenance  of  the  product.  The  DJF  is  updated 
according to the evolution of the DDF, in accordance with the above‐mentioned 
objectives. 
The  DJF  provides  also  access  to  coherent  and  substantiated  information  which 
can be used to support decision‐making in the analysis of change requests for the 
management of non conformances. 
The  DJF  contains  results  obtained  during  the  evolution  of  the  design  as  a 
consequence of the activities performed along the design process: 
• Analysis  and  trade‐off  reports  concerning  the  evaluation  of  alternative 
design solutions and the justification of the choice. 

71 
ECSS‐E‐ST‐10C 
6 March 2009 
• All results obtained during the verification of the design as a consequence 
of the activities performed along the verification process. 
• Test  Reports  on  engineering  model,  structural  and  thermal  model  and 
qualification model (e.g. Protoflight Models). 
NOTE  The  DJF  is  a  logical  file  covering  all  technical 
disciplines required for the considered system. In 
general, the elements of the DJF are “rolled out” 
as separate documents. 

K.2 Expected response

K.2.1 Scope and content

<1> Introduction 
a. The DJF shall contain a description of the purpose, objective, content and 
the reason prompting its preparation. 

<2> Applicable and reference documents 
a. The DJF shall list the applicable and reference documents in support to its 
generation. 
b. The  applicable  document  list  shall  contain  the  reference  to  the  relevant 
product specifications, and the relevant DDF and system engineering plan. 
c. The reference document list shall contain the reference to: 
1. Trade‐Off‐Reports, as defined Annex L. 
2. Analysis  Reports  (e.g.  requirements  allocation  analysis,  functional 
analysis). 
3. Requirements Traceability Matrix, as defined in Annex N (with link 
to analysis). 
4. Verification Control Document  
5. All verification documentation, such as: 
(a) Analysis Reports (e.g. reports w.r.t. qualification aspects) 
(b) Test Reports 
(c) ROD Reports 
(d) Inspection Reports 
(e) Verification Reports 

<3> Design description 
a. The  DJF  shall  contain  a  description  of  the  expected  product,  its  intended 
mission, architecture and design, and the functioning principles on which 
it is based. 

72 
ECSS‐E‐ST‐10C 
6 March 2009 
b. The  DJF  shall  define  the  requirement  criteria  levels  for  qualification  and 
acceptance verification of the product. 

<4> Design Justification File Synthesis  
a. The  DJF  shall  present  status  of  the  design  justification  in  response  to 
requirements, with emphasis on the driving requirements that have a big 
impact  on  the  system  design,  production  and  maintainability  (see  also 
K.2.1<8.2.4>a.) 
b. The  DJF  shall  present  an  overall  system  qualification  status  synthesis, 
including: 
1. the  list  of  requirements  which  have  not  been  met  (e.g. 
nonconformances), including proposed actions, 
2. the  list  of  all  critical  points,  and  how  criticalities  have  been  or  are 
intended to be resolved, 
3. the identification of requirements which have not been justified yet, 
and associated risks analysis, with emphasis on those that can have 
an impact at system level. 

<5> Justification of the Functional Architecture 
a. The  DJF  shall  contain  the  demonstration  that  all  requirements  of  the 
preliminary technical requirements specification are allocated to functional 
blocks of the system functional architecture. 
b. Where requirements assigned to functional blocks do not have their origin 
within  any  of  the  customer  preliminary  technical  specifications,  these 
requirements shall be justified.  

<6> Justification of the Physical Architecture 
a. The DJF shall contain the demonstration that the system design conforms 
to  the  requirements  of  the  technical  specification,  and  identify  products 
which are reused (e.g. COTS). 
b. The  DJF  shall  also  provide  the  justification  for  the  choice  of  architectural 
elements  at  the  next  lower  level,  or  lower  levels  in  case  of  system  critical 
elements. 
c. Where requirements do not have their origin within any of the upper level 
technical specifications, these shall be justified.  

<7> Development activities and synthesis of development 
results  
a. The  DJF  shall  present  the  development  activities  (e.g.  assessments, 
analyses,  tests,  and  trade‐offs)  and  the  design  drivers,  which  lead  to  and 
justify  the  design  as  defined  in  the  DDF,  in  line  with  the  development 
approach identified in the SEP. 

73 
ECSS‐E‐ST‐10C 
6 March 2009 
b. The  justification  shall  concern  all  the  engineering  disciplines  contributing 
to design and development of the product (including its operational modes 
and scenarios). 
c. The DJF shall include the status of DJF of lower level products. 
NOTE  Activities related to verification are dealt with in 
section K.2.1<8>. 
d. For  the  system  and  each  discipline,  following  information  shall  be 
produced: 
1. Activity  inputs,  such  as  requirements,  operational  modes, 
assumptions,  analysis  cases,  boundary  conditions,  model 
descriptions and limitations. 
2. Activity results, such as 
(a) raw results, 
(b) evaluation of results, 
(c) evaluation  of  margins  with  respect  to  the  technical 
requirements contained in the TS, 
(d) identification of any marginal areas. 
3. Activity synthesis, such as 
(a) evidence  of  compliance  to  the  technical  requirements 
contained in the TS, 
(b) list  of  technical  requirements  which  have  not  been  met, 
including proposed actions, 
(c) list of all critical points, and how criticalities have been or are 
intended to be resolved, 
(d) identification  of  aspects  of  the  design,  which  are  not  yet 
justified, and assessment of inherent risks.  
e. The  DJF  shall  reference  the  requirements  traceability  matrix,  e.g.  w.r.t. 
building up the justification of a considered system top level requirements 
in  terms  of  the  various  elements  contributing  to  it,  including  where 
relevant contribution from other disciplines (e.g. pointing as a function of 
thermal, structures, and AOCS). 

<8> Verification activities and synthesis of results 

<8.1>  Verification plan 
a. The  DJF  shall  integrate  or  refer  to  the  document  that  conforms  to  the 
verification plan DRD defined in ECSS‐E‐ST‐10‐02 Annex A. 
NOTE  The  verification  activities  are  detailed  in  the 
Verification  Plan  (VP),  which  also  contains  the 
justification  of  the  verification  strategy  (as 
defined in ECSS‐E‐ST‐10‐02). 

74 
ECSS‐E‐ST‐10C 
6 March 2009 

<8.2> Qualification verification and synthesis of results 
<8.2.1> Qualification evidence 
a. The  DJF  shall  present  the  evidence  of  the  qualification  of  the  design  in 
conformance  to  the  applicable  technical  requirements  and  proper 
qualification margins.  
NOTE  This  is  done  in  line  with  the  qualification 
approach identified in the VP.  
b. The DJF shall cover the system and all disciplines relevant to the product 
in  all  its  operational  modes  and  scenarios,  addressing  all  applicable 
technical requirements and proper qualification margins.  
NOTE 1  This  is  done  in  line  with  the  system  verification 
matrix.  
NOTE 2  The  formal  compliance  with  the  qualification 
requirements  is  recorded  in  the  VCD,  together 
with references to the close‐out documents. 
<8.2.2>  Implementation of the qualification plan 
a. The DJF shall present the implementation of the qualification plan and the 
status thereof, addressing the detailed definition of qualification activities 
(e.g. analysis, test, ROD, and inspection), including the detailed definition 
of the tests, the prediction of expected test results, test success criteria, test 
specifications, and model validations. 
NOTE  Details  on  test  specifications  are  provided  in 
ECSS‐E‐ST‐10‐03 Annex B. 
<8.2.3>  Validation of models 
a. The  DJF  shall  contain  all  evidence  (e.g.  analyses,  test  results,  and  model 
descriptions and correlations) regarding the suitability and validation of all 
models used for the analysis of the system. 
<8.2.4>  Requirements status log 
a. The  DJF  shall  include  a  requirement  status  log  addressing  each 
requirement in turn, and including the 
1. reference to relevant elements of the verification plan, 
2. synthesis  of  the  justifications  acquired,  calling  up  references  to  the 
supporting  activities  and  evidence  (e.g.  Technical  Notes  listed  in 
section K.2.1<4>), 
3. list of justifications to be acquired and related activities, 
4. conclusion / action flag. 
<8.2.5>  Manufacturing process status log 
a. The DJF shall include a requirement status log, addressing design relevant 
aspects  of  manufacturing  processes,  and  recording  their  characteristics  in 
regard to qualification. 

75 
ECSS‐E‐ST‐10C 
6 March 2009 

<8.3> Acceptance verification 
a. The  DJF  shall  present  the  implementation  of  the  acceptance  verification 
and  the  status  thereof,  addressing  the  detailed  definition  of  acceptance 
activities (e.g. inspection, test, analysis), including the detailed definition of 
the  tests,  the  prediction  of  expected  test  results,  test  success  criteria,  and 
test specifications. 
NOTE  Details  on  test  specifications  are  provided  in 
ECSS‐E‐ST‐10‐03 Annex B. 
a. The DJF shall cover the system and all disciplines relevant to the product, 
addressing  all  acceptance  verification  activities  in  line  with  the  system 
verification Plan (VP). 

<9> Justification of System Technical Budgets and Margins 
a. The DJF shall present a synthesis of all technical budgets and margins for 
specific parameters according to the functional and physical architectures. 
NOTE  For  technical  budgets  and  margins,  see  ECSS‐E‐
ST‐10 Annex I. 

<10> Justification of Constraints imposed by the System 
Design 

<10.1> Design constraints on the production 
a. The DJF shall present the justification of constraints induced by the system 
or  product  design  definition  on  the  production  activities  e.g.  operational 
allowable envelopes, restrictions on assembling sequences, procedures and 
testing  modes,  exclusion  zones,  manufacturing  environmental  conditions, 
and conditions for procurement. 

<10.2> System design constraints for operation  
a. The DJF shall present the justification of constraints induced by the system 
or product design definition on the implementation of the operations e.g. 
operational  allowable  envelopes,  restrictions  on  operating  modes,  and 
exclusion zones. 

<10.3> System design constraints for transportation and storage 
a. The DJF shall present the justification of constraints induced by the system 
or product design definition on the transportation activities and during the 
periods of storage of the product e.g. allowable envelopes, restrictions on 
transportation  and  storage,  exclusion  zones,  packaging,  shock  levels, 
temperature  environments,  humidity,  cleanliness,  regulations,  and 
dangerous materials. 

<10.4> System design constraints for maintainability 
a. The DJF shall present the justification of constraints induced by the system 
or product design definition on the maintenance activities and procedures 

76 
ECSS‐E‐ST‐10C 
6 March 2009 
e.g.  operational  allowable  envelopes,  accessibility,  tooling,  support 
materials, parts availability, and deliveries.  

<11> Constituent documents 
a. The DJF shall integrate or refer to the documents that conform to the: 
1. ECSS‐E‐ST‐10 Annex L, Trade‐Off‐Report ‐ DRD 
2. ECSS‐E‐ST‐10 Annex Q, Analysis Report ‐ DRD 
3. ECSS‐E‐ST‐10 Annex O, Requirement Justification File ‐ DRD 
4. ECSS‐E‐ST‐10 Annex N, Requirements Traceability Matrix – DRD 
5. ECSS‐E‐ST‐10‐02 Annex B, Verification Control Document ‐ DRD 
6. ECSS‐E‐ST‐10‐02 Annex C, Test Report ‐ DRD 
7. ECSS‐E‐ST‐10‐02 Annex D, Review Of Design Report ‐ DRD 
8. ECSS‐E‐ST‐10‐02 Annex E, Inspection Report ‐ DRD 
9. ECSS‐E‐ST‐10‐02 Annex F, Verification Report ‐ DRD 
b. The  DJF  shall  include  or  refer  to  the  DJF  of  lower  level  elements  of  the 
product. 

K.2.2 Special remarks


None.

77 
ECSS‐E‐ST‐10C 
6 March 2009 

Annex L (normative)
Trade-off report - DRD

L.1 DRD identification

L.1.1 Requirement identification and source document


This DRD is called from ECSS‐E‐ST‐10, requirement 5.3.3b. 

L.1.2 Purpose and objective


The  Trade‐off  report  provides  the  system‐engineering  point  of  view  on 
alternative  design solutions,  an evaluation  and a  classification  of  the  alternative 
design solutions, and the justification of their ranking. 

L.2 Expected response

L.2.1 Scope and content

<1> Introduction 
a. The  trade‐off  report  shall  contain  a  description  of  the  purpose,  objective, 
content and the reason prompting its preparation. 

<2> Applicable and reference documents 
a. The  trade‐off  report  shall  list  the  applicable  and  reference  documents  in 
support to the generation of the document and include the reference to the 
following applicable documents: 
1. Mission description document, if relevant 
2. Technical requirements specification 
3. System engineering plan 
4. Project phasing and planning requirement document. 

78 
ECSS‐E‐ST‐10C 
6 March 2009 

<3> Objective and context of the trade‐off study 
a. The trade‐off report shall contain a brief description of the purpose of the 
trade‐off  study  and  its  context  (e.g.  logic,  organization,  process  or 
procedure). 

<4> Key technical requirements 
a. The  trade‐off  report  shall  list  the  key  technical  requirements  from  the  TS 
(as  defined  in  ECSS‐E‐ST‐10‐06)  to  be  satisfied  by  the  possible  alternative 
design solutions to conform to the needs or requirements of the user. 
b. The  research  of  possible  alternative  design  solutions  should  not  preclude 
the  identification  of  design  solutions  which  are  not  currently  mature 
enough,  but  which  can  be  potential  design  solution  for  future  similar 
applications. 
NOTE  A  possible  design  solution  is  a  technical  answer 
that  has  the  capability  to  meet  a  set  of  technical 
requirements. 
c. The  system  trade‐off  report  shall  identify  and  present  the  sources  of 
information used to identify the possible design solution, e.g. R&D results, 
lessons learned, or similar applications. 

<5> Evaluation criteria 
a. The  trade‐off  report  shall  list  the  selected  evaluation  criteria  and  precise 
the  justification  for  selecting  those  criteria,  and  provide  the  weighting  of 
criteria and their justifications. 
NOTE  The criteria are selected theme by theme from the 
Technical Specification (as defined in ECSS‐E‐ST‐
10‐06  Annex A),  the  programmatic  aspects 
(including  e.g.  budget,  schedule,  etc…  for 
development,  manufacturing,  as  well  as  target 
cost for operations and recurrent items), and the 
technical risks. 
b. The trade‐off report shall identify the entity responsible for the evaluation 
of the design solutions for any criteria, as well as the source and agreement 
regarding weighting factors (e.g. with management). 

<6> Presentation of the alternative design solutions  
a. The  trade‐off  report  shall  present  every  different  alternative  design 
solutions proposed by the organization in charge of the development of the 
system  or  product,  the  proposals  from  the  customer  and  supplier  if  any, 
and emphasize the technical description that is correlated to the criteria of 
evaluation.  
b. The  trade‐off  report  shall  characterize  each  alternative  design  solution  in 
terms of technology status or maturity, performances capability, and risks. 

79 
ECSS‐E‐ST‐10C 
6 March 2009 

<7> Evaluation of the alternative design solutions 
a. The  system  trade‐off  report  shall  present  the  result  of  the  evaluation  of 
every  identified  alternative  design  solution  with  regard  to  the  key 
technical requirements. 
b. For each alternative design solution the following shall be performed:  
1. assessment of all the key technical requirements / evaluation criteria, 
2. presentation of the pros and cons of the design solution, and 
3. identification of the technical and programmatic risks. 
c. The trade‐off report shall present, in a table, the result of the evaluation per 
criteria. 

<8> Classification of the alternative design solutions  
a. Based  on  the  proposed  scheme  for  weighting  the  evaluation  criteria,  the 
trade‐off  report  shall  provide  a  classification  of  the  different  alternative 
design solutions. 

<9> Analysis of the robustness of the classification 
a. The trade‐off report shall provide the result of a sensitivity analysis of the 
criteria  that  provide  advantage  to  the  solution  ranked  first,  e.g.  when 
changing the weighting of the evaluation criteria.  

<10> Conclusion 
a. The trade‐off report shall recommend one solution and explain the reason 
for  this  choice  (e.g.  evaluation  criteria  where  the  selected  solution  take 
advantage),  and  precise  the  condition  for  the  application  of  the 
recommended solution. 
b. The  trade‐off  report  shall  present  the  identified  technical  and 
programmatic  risks  induced  by  the  choice  of  the  recommended  solution, 
and any additional activity necessary to be performed for risk mitigation. 

L.2.2 Special remarks


None. 

80 
ECSS‐E‐ST‐10C 
6 March 2009 

Annex M (normative)
Interface requirement document (IRD) -
DRD

M.1 DRD identification

M.1.1 Requirement identification and source document


This DRD is called from ECSS‐E‐ST‐10, requirement 5.6.4b. 

M.1.2 Purpose and objective


For  a  product,  the  interface  requirement  document  (IRD)  is  a  specific  type  of 
technical specification that defines the requirements for the interfaces among the 
items ‐ at the same level in the product tree structure ‐ constituting this product. 
The  IRD  is  a  document  either  included  in  or  called  up  by  the  technical 
requirements  specification  (TS)  (as  defined  in  ECSS‐E‐ST‐10‐06  Annex A)  of  the 
product. 

M.2 Expected response

M.2.1 Scope and content

<1> Introduction 
a. The IRD shall contain a description of the purpose, objective, content and 
the reason prompting its preparation. 

<2> Applicable and reference documents 
a. The IRD shall list the applicable and reference documents in support to the 
generation of the document. 
b. The IRD shall include the following references: 
1. Product tree (as defined in ECSS‐M‐ST‐10 Annex B) 
2. Specification tree (as defined in ECSS‐E‐ST‐10 Annex J). 

81 
ECSS‐E‐ST‐10C 
6 March 2009 

<3> Interface requirements  
a. The  interface  requirements  shall  be  grouped  per  couple  of  product 
elements having an interface. 
b. The interface requirements shall be expressed according to ECSS‐E‐ST‐10‐06. 
c. The interface requirements shall be grouped per nature of interface. 
NOTE  For  example:  Nature  of interface  includes,  but  is 
not  restricted  to,  mechanical,  electrical,  thermal 
and software interfaces. 

M.2.2 Special remarks


a. The  content  of  the  IRD  may  be  merged  with  the  content  of  the  technical 
requirements specification (as defined in ECSS‐E‐ST‐10‐06 Annex A) of the 
elements of the product. 

82 
ECSS‐E‐ST‐10C 
6 March 2009 

Annex N (normative)
Requirements traceability matrix (RTM) -
DRD

N.1 DRD identification

N.1.1 Requirement identification and source document


This DRD is called from ECSS‐E‐ST‐10, requirement 5.2.2b.  

N.1.2 Purpose and objective


The requirement traceability matrix (RTM) defines the relationships between the 
requirements  of  a  deliverable  product  defined  by  a  technical  requirements 
specification  and  the  apportioned  requirements  of  the  productʹs  lower  level 
elements. 
The purpose of the RTM is to help verify that all stated and derived requirements 
are allocated to system components and other deliverables (forward trace).  
The matrix is also used to determine the source of requirements (backward trace). 
Requirements  traceability  includes  tracing  any  information  that  satisfy  the 
requirements such as capabilities, design elements, and tests. 
The  RTM  is  also  used  to  ensure  that  all  requirements  are  met  and  to  locate 
affected system components when there is a requirements change. The ability to 
locate  affected  components  allows  the  impact  of  requirements  changes  on  the 
system to be determined, facilitating cost, benefit, and schedule determinations. 

N.2 Expected response

N.2.1 Scope and content

<1> Introduction 
a. The RTM shall contain a description of the purpose, objective, content and 
the reason prompting its preparation. 

83 
ECSS‐E‐ST‐10C 
6 March 2009 

<2> Applicable and reference documents 
a. The  RTM  shall  list  the  applicable  and  reference  documents  in  support  to 
the generation of the document. 
b. The RTM shall include the following: 
1. Technical requirements specification (as defined in ECSS‐E‐ST‐10‐06 
Annex A) of the product and its lower level elements 
2. Product tree (as defined in ECSS‐M‐ST‐10 Annex B) 
3. Specification tree (as defined in ECSS‐E‐ST‐10 Annex J). 

<3> Requirement traceability 
a. The RTM shall list all the technical requirement of the product TS. 
b. The RTM shall list all the lower level elements constituting the product and 
their technical requirements (contained in the lower‐level element TS). 
c. The  requirement  identification  shall  be  identical  in  the  RTM  and  the 
different TS. 
d. Each  technical  requirement  of  the  product  shall  be  linked  to  at  least  one 
requirement of a lower level element. 
NOTE  The  required  visibility  of  the  traceability  down 
the elements of the product tree is depending on 
the criticality of some lower level elements w.r.t. 
the product requirements. 
e. Each technical requirement of a lower level element should be linked to a 
technical requirement of the product. 
f. When  a  technical  requirement  of  a  lower  level  element  is  not  linked  to  a 
technical  requirement  of  the  product,  this  requirement  shall  be  justified 
and  an  evaluation  of  its  existence  or  removal  on  the  product  shall  be 
agreed between the customer and the supplier. 

N.2.2 Special remarks


None. 

84 
ECSS‐E‐ST‐10C 
6 March 2009 

Annex O (normative)
Requirements justification file (RJF) - DRD

O.1 DRD identification

O.1.1 Requirement identification and source document


This DRD is called from ECSS‐E‐ST‐10, requirement 5.2.1e. 

O.1.2 Purpose and objective


The  requirement  justification  file  (RJF)  is  a  generic  title  referring  to  all 
documentation which: 
• Records  and  describes  the  needs  and  the  associated  constrains  resulting 
from the different trade‐offs. 
• Demonstrates  how  the  requirements  of  the  technical  requirements 
specification  (TS)  (as  defined  in  ECSS‐E‐ST‐10‐06  Annex A)  at  each  level 
can satisfy the needs and the constraints of the TS of the level above. 
NOTE  A  top  level  RJF  document  is  established  at  the 
upper  level  of  the  project  structure  that  is, 
according  to  ECSS‐M‐ST‐10,  the  first‐level 
customer  situated  at  level  0  of  the  customer 
supplier network. For other levels, the RJF is part 
of the design justification file (DJF) (as defined in, 
Annex K). 

O.2 Expected response

O.2.1 Scope and content

<1> Introduction 
a. The  RJF  shall  contain  a  description  of  the  purpose, objective,  content  and 
the reason prompting its preparation. 

85 
ECSS‐E‐ST‐10C 
6 March 2009 

<2> Applicable and reference documents 
a. The RJF shall list the applicable and reference documents in support to the 
generation of the document. 
b. The  RJF  shall  include  the  reference  to  the  technical  requirements 
specification. 

<3> Selected concept/solution justification 
a. The  RJF  shall  present  the  rationale  for  the  selection  of  a  concept  for  the 
technical requirements specification. 
NOTE  For  justification,  reference  can  be  made  to  the 
system concept report of the considered project. 

<4> Life profile justification for the selected concept/solution 
a. The RJF shall present and justify the life profile situations for the concept 
presented in the technical requirements specification. 
NOTE  For  justification,  reference  can  be  made  to  the 
system  concept  report  of  the  considered  project 
where relevant. 

<5> Environments and constraints justification 
a. The  RJF  shall  present  and  justify  the  different  environments  and 
constraints for each life profile situations for the concept presented in the 
technical requirements specification. 
NOTE  For  justification,  reference  can  be  made  to  the 
system  concept  report  of  the  considered  project 
where relevant. 

<6> Technical requirements justification 
a. The  RJF  shall  list  all  the  technical  requirements,  and  their  identifier, 
expressed  by  the  corresponding  TS  as  they  are  organized  in  these 
documents.  
b. For  each  technical  requirement  the  following  information  shall  be 
provided: 
1. the justification of the requirement (i.e. justified source), 
2. the Entity or owner responsible for the requirement, 
3. if  one  technical  requirement  is  induced  by  several  sources,  the 
reason of the specified performance, 
4. the justification of the quantified performance (such as the range, the 
approach used to determine the level, e.g. measure, estimation),  
5. the justification of the selected verification method. 

86 
ECSS‐E‐ST‐10C 
6 March 2009 

<7> Requirement traceability 
a. The  RJF  shall  present  the  requirement  traceability  between  the  technical 
requirements of the TS, and their justified source. 

<8> Compliance matrix for COTS 
a. For COTS, the RJF shall contain a compliance matrix between the technical 
specification/characteristics  of  the  COTS  and  the  technical  requirement 
expressed by the TS. 

O.2.2 Special remarks


a. The  RJF  may  be  part  of  the  design  justification  file  (DJF)  (as  defined  in 
ECSS‐E‐ST‐10 Annex K). 

87 
ECSS‐E‐ST‐10C 
6 March 2009 

Annex P (normative)
Product user manual (PUM or UM) - DRD

P.1 DRD identification

P.1.1 Requirement identification and source document


This DRD is called from ECSS‐E‐ST‐10 requirement 5.4.1.4c. 

P.1.2 Purpose and objective


The  objective  of  the  product  user  manual  (PUM)  is  to  provide  information  on 
design, operations and data of the product that is required by the user to handle, 
install, operate, maintain and dispose the product during its life time.  

P.2 Expected response

P.2.1 Scope and content

<1> Introduction 
a. The introduction shall describe the purpose and objective of the PUM. 

<2> Applicable and reference documents 
a. The  PUM  shall  list  the  applicable  and  reference  documents  in  support  of 
the generation of the document. 

<3> Product function definition 

<3.1> Product expected functions 
a. The PUM shall provide a general description of the expected functions of 
the  product  during  its  lifetime  in  expected  operational  context  and 
environment. 

<3.2> Product functional constraints 
a. The PUM shall describe all product functional constraints. 

88 
ECSS‐E‐ST‐10C 
6 March 2009 

<3.3> Life time phases and purposes 
a. The PUM shall address the whole product life cycle and all its modes:  
1. Handling 
2. Storage 
3. Installation 
4. Operations (nominal and contingency) 
5. Maintenance 
6. Disposal. 
b. The  PUM  shall  consider  potential  consequences  of  the  environment  on 
those sequences (e.g. sensor blinding, eclipses); 

<4> Product description 

<4.1> Design summary 
a. The PUM shall include the following: 
1. summary  of  the  product  design,  showing  the  definition  of  the 
product, its constituents, the distribution of functions and the major 
interfaces; 
2. block diagram of the product; 
3. top‐level description of the product software architecture; 
4. description of nominal product operations scenarios and constraints 
e.g.  mutually  exclusive  modes  of  operation,  power  or  resource 
sharing. 

<4.2> Product level autonomy 
a. The PUM shall include the following: 
1. description  of  product‐level  autonomy  provisions  in  the  areas  of 
fault management (FDIR); 
2. definition, for each autonomous function, of the logic or rules used 
and of its internal (product constituents) and external interfaces.  

<4.3> Product configurations 
a. The PUM shall include the following: 
1. drawings of the overall product configuration in all product modes; 
2. definition of the product reference axes system(s); 
3. drawings of the product layouts. 

<4.4> Product budgets 
a. The  PUM  shall  provide  the  distribution  (or  allocation)  of  the  following 
budgets, per product constituent, or per operating mode, as appropriate: 
1. mass properties; 

89 
ECSS‐E‐ST‐10C 
6 March 2009 
2. alignment; 
3. power consumption for all operational modes; 
4. thermal budget and constraints and predictions; 
5. Description of interfaces and related budgets. (e.g. RF links); 
6. telemetry and telecommand date rates; 
7. memory; 
8. timing. 

<4.5> Interface specifications 
a. The  PUM  shall  provide  a  cross‐reference  to  the  applicable  version  of  the 
ICD. 

<4.6> Handling 
a. The PUM shall describe the conditions and procedures for the handling of 
the product, be it integrated or stand‐alone. 
b. The  PUM  shall  describe  the  specific  design  features,  transport  and 
environmental  conditions,  required  GSE,  and  limitations  for  the  handling 
of the product. 

<4.7> Storage 
a. The  PUM  shall  describe  the  conditions  and  procedures  for  the  storage  of 
the product, be it integrated or stand‐alone. 
b. The  PUM  shall  describe  the  specific  design  features,  environmental 
conditions,  required  GSE,  monitoring  requirements,  life‐limited  items, 
health maintenance procedures (activation, monitoring) and limitations for 
the storage of the product. 

<4.8> Installation 
a. The PUM shall describe the conditions and procedures for the installation 
of the product, be it integrated or stand‐alone. 
b. The PUM shall describe the specific design features, required GSE, modes, 
environmental  conditions,  and  limitations  for  the  installation  of  the 
product. 

<4.9> Product operations 
<4.9.1> General 
a. The  PUM  shall  include  timelines,  modes  and  procedures,  constraints  to 
operate  the  product  during  its  life  cycle  in  nominal  and  contingency 
conditions, and highlight critical operations. 
NOTE 1  When  the  product  is  a  space  segment,  the 
product  operations  aspects  are  included  in  a 
specific  part  of  the  UM  called  Flight  Operations 
Manual (FOM). 

90 
ECSS‐E‐ST‐10C 
6 March 2009 
NOTE 2  The  implementation  of  the  FOM  by  the  ground 
segment responsible organisation is contained in 
the Mission Operations Plan (MOP, as defined in 
ECSS‐E‐ST‐70 Annex G). 
<4.9.2> Timelines 
a. The PUM shall include: 
1. Baseline event timelines for all nominal and contingency modes and 
phases. 
2. Related constraints. 
b. Each timeline shall contain a detailed description (i.e. down to the level of 
each single operational action) of the complete sequence of operations to be 
carried  out,  including  a  description  of  the  rationale  behind  the  chosen 
sequence  of  events,  a  definition  of  any  constraints  (e.g.  absolute  timing, 
relative  timing)  and  the  interrelationships  between  operations  in  the 
sequence. 
<4.9.3> Product modes 
a. The PUM shall describe all nominal and contingency modes, including: 
1. their purpose (i.e. circumstances under which they are used), 
2. the related procedures, 
3. operational constraints, 
4. resource utilization, 
5. the definition of the associated modes, and 
6. monitoring requirements. 
b. The PUM shall describe the allowable mode transitions and the operations 
procedure corresponding to each such transition. 
c. Appropriate  cross‐reference  shall  be  made  to  product  constituent  modes 
and procedures. 
<4.9.4> Product failure analysis 
a. The PUM shall provide the results of the product failure modes, effects and 
criticality analysis (FMECA) and the resulting list of single point failures. 
b. Potential  product  failures  shall  be  identified  by  means  of  a  fault‐tree 
analysis (FTA). 

<4.10> Maintenance 
a. The  PUM  shall  describe  the  conditions,  procedures  and  logistics  for  the 
maintenance of the product, be it integrated or stand‐alone. 
NOTE  The  description  can  refer  to  the  document  that 
conforms to the Integrated Logistic Support Plan 
in conformance with ECSS‐M‐ST‐70. 

91 
ECSS‐E‐ST‐10C 
6 March 2009 

<4.11> Disposal 
a. The PUM shall describe the conditions and procedures for the disposal of 
the product, be it integrated or stand‐alone. 
b. The procedures shall include passivation, as relevant. 
c. The PUM shall identify the risks during and after disposal. 

<5> Products constituents description 

<5.1> General 
a. The information specified in P.2.1<5.2> to P.2.1<5.9> shall be provided for 
each product constituent. 

<5.2> Product constituent design summary 
a. The PUM shall describe the product constituent including: 
1. the overall functions of the product constituent and the definition of 
its operational modes during the different mission phases; 
2. description of any product constituent management functions, fault 
management concept and redundancy provisions; 
3. a  summary  description  of  the  component  units/equipment  and 
software including the functions which each supports; 
4. product  constituent  functional  block  diagrams  and  a  diagram 
showing  the  source  of  telemetry  outputs  and  the  sink  of 
telecommand inputs; 
5. interfaces; 
6. budgets. 

<5.3> Product constituent design definition 
a. The following shall be provided for each product constituent: 
1. a  detailed  design  description,  including  block  diagrams,  functional 
diagrams, logic and circuit diagrams; 
2. physical  characteristics  including  location  and  connections  to  the 
support  structure,  axes  definition  and  alignment  where  relevant, 
dimensions and mass properties; 
3. principle  of  operation  and  operational  constraints  of  the  product 
constituent; 
4. if  a  product  constituent  is  composed  of  many  complex  elements,  it 
may be necessary to provide a lower level of breakdown. 

<5.4> Software 
a. The PUM shall include: 
1. description of software design, 
2. product constituent software, 

92 
ECSS‐E‐ST‐10C 
6 March 2009 
3. application process service software, and 
4. memory map. 
b. The  PUM  shall  describe  the  organization  of  the  software  and  its  physical 
mapping onto hardware. 
c. The  PUM  shall  describe  the  details  of  each  software  component  i.e. 
scheduler,  interrupt  handler,  I/O  system,  telecommand  packet  handling 
system,  telemetry  packet  handling  system,  including  for  each  component 
its  functions,  component  routines,  input/output  interfaces,  timing  and 
performance  characteristics,  flowcharts  and  details  of  any  operational 
constraints. 
d. For the application process service software, the PUM shall: 
1. describe the services implemented making cross‐reference to ECSS‐
E‐ST‐70‐41  “Telemetry  and  telecommand  packet  utilization”,  as 
tailored for the mission; 
2. summarize  all  telemetry  and  telecommand  structures  (e.g.  packets) 
including  the  conditions  under  which  they  are  generated,  the 
generation frequency, content and interpretation. 
e. For each memory block, a map shall be provided showing RAM and ROM 
address areas, areas allocated for program code, buffer space and working 
parameters (e.g. content of protected memory). 

<5.5> Product component performance 
a. The  PUM  shall  describe  all  relevant  product  constituent  performance 
characteristics, define the expected performance degradation as a function 
of  time  during  the  mission,  and  identify  the  resulting  impact  in  terms  of 
modifications to operational requirements or constraints. 

<5.6> Product component telemetry and telecommand lists 
a. For each product constituent, the following lists shall be provided: 
1. a list of the housekeeping telemetry parameters; 
2. a list of the telecommands. 
b. Each  housekeeping  telemetry  shall  have  a  functional  description  with 
validity  conditions,  telecommand  relationship,  and  all  technical 
information necessary for using it. 
c. Each  telecommand  shall  have  a  functional  description  with  utilization 
conditions  (e.g.  pre‐transmission  validity,  criticality  level),  command 
parameters (syntax and semantics) and execution verification in telemetry. 

<5.7> Product component failure analysis 
a. The PUM shall describe: 
1. Identification of potential product constituent failures by means of a 
systematic  failure  analysis  (including  a  subsystem  FMECA  and 
FTA). 

93 
ECSS‐E‐ST‐10C 
6 March 2009 
2. Identification of the methods by which the higher levels can identify 
a failure condition from analysis of the telemetry data and isolate the 
source of the failure. 

<5.8> Product components operations 
a. The PUM shall describe: 
1. product constituent modes; 
2. nominal operational procedures; 
3. contingency procedures. 
b. product  constituent  modes  shall  be  defined  for  all  distinct  nominal  and 
back‐up modes of the subsystem including: 
1. purpose (i.e. conditions under which each is used); 
2. operational constraints; 
3. resource utilization; 
4. the  definition  of  the  associated  modes  for  each  product  constituent 
and its software functions; 
5. higher level monitoring requirements; 
6. identification  of  the  allowable  mode  transitions  and  any  product 
constituent operational constraints. 
c. Nominal  operational  procedures  shall  be  defined  for  each  nominal  mode 
transition identified under P.2.1<5.8>b.6. 
d. For  each  procedure  described  in  P.2.1<5.8>c.,  the  following  shall  be 
provided: 
1. an  introduction  describing  the  purpose  of  the  procedure  and  the 
phase(s) or conditions when applicable; 
2. the body of the procedure, structured according to operational steps, 
including: 
(a) pre‐conditions  for  the  start  of  the  step  defining,  where 
applicable: 
− product or product constituent level pre‐requisites (e.g. 
configuration and resource requirements, such as power, 
fuel); 
− external interfacing products pre‐requisites. 
(b) telecommands to be sent; 
(c) telemetry  data  to  be  monitored  to  verify  correct  execution  of 
the step; 
(d) interrelationships  between  steps  (e.g.  conditional  branching 
within  the  procedure,  timing  requirements  or  constraints, 
hold and check points); 
(e) conditions for completion of the step. 

94 
ECSS‐E‐ST‐10C 
6 March 2009 
e. Contingency procedures shall be defined for each failure case identified in 
the product constituent failure analysis (FMECA/FTA). 
NOTE  This can utilize a nominal operational procedure 
already identified in P.2.1<5.8>c. above. 
f. For  contingency  procedures,  the  same  details  shall  be  provided  as  for 
nominal operational procedures in P.2.1<5.8>d. above. 
g. Where  the  recovery  method  for  a  failure  or  group  of  failures  is  mode, 
mission,  or  phase  dependent,  separate  procedures  shall  be  described  for 
each mode/mission phase. 

<5.9> Product component data definition 
a. For each operational mode of the product constituent, sensor output data, 
conditions  under  which  they  are  generated,  their  contents,  and  data  rate 
shall be described. 
b. Required  on‐board  processing  performed  on  sensor  data  and  algorithms 
used for this shall be described. 

P.2.2 Special remarks


a. Where  the  objective  is  to  allow  for  the  accommodation  of  equipment 
designed  a  posteriori  w.r.t  an  existing  platform  or  vehicle,  the  following 
documents shall be part of the UM:  
1. The  accommodation  handbook  describing  the  location,  mounting, 
all interfaces and clearances of equipment in a platform or vehicle. 
2. The installation plan describing the approach, methods, procedures, 
resources  and  organization  to  install,  commission,  and  check  the 
operation of the equipment in its fixed operational environment. 

95 
ECSS‐E‐ST‐10C 
6 March 2009 

Annex Q (normative)
Analysis report – DRD

Q.1 DRD identification

Q.1.1 Requirement identification and source document


This DRD is called from ECSS‐E‐ST‐10, requirement 5.3.1j. 

Q.1.2 Purpose and objective


The  analysis  report  describes,  for  each  analysis,  the  relevant  assumptions, 
utilized methods, techniques and results. 
NOTE  When  the  analysis  report  is  used  for  product 
verification  purposes,  specific  requirements  as 
per clause Q.2.1<8> apply. 

Q.2 Expected response

Q.2.1 Scope and content

<1> Introduction 
a. The  analysis  report  shall  contain  a  description  of  the  purpose,  objective, 
content and the reason prompting its preparation. 
b. Any open issue, assumption and constraint relevant to this document shall 
be stated and described. 

<2> Applicable and reference documents 
a. The  analysis  report  shall  list  the  applicable  and  reference  documents  in 
support to the generation of the document, and make a clear reference to 
the configuration baseline of the product considered for the analysis. 

96 
ECSS‐E‐ST‐10C 
6 March 2009 

<3> Definitions and abbreviations 
a. The analysis report shall list the applicable dictionary or glossary and the 
meaning  of  specific  terms  or  abbreviations  utilized  in  the  document  with 
the relevant meaning. 

<4> Analysis approach 
a. The  analysis report  shall summarize  the  analysis  content  and  the  method 
utilized. 

<5> Assumptions and limitations 
a. The  analysis  report  shall  describe  the  basic  assumptions,  the  boundary 
conditions, validity of the analysis, life profile aspects, and all other related 
limitations. 

<6> Analysis description 
a. The  analysis  report  shall  describe  and  justify  the  analysis  methods  used 
including software, tools and associated models. 

<7> Analysis results 
a. The analysis report shall present the main calculations, associated results, 
accuracies, sensitivities, margins where relevant. 

<8> Conclusions 
a. The analysis report shall: 
1. summarize the analysis results, 
2. summarize the conditions of validity of this analysis,  
3. clearly state and describe any open issue. 
b. Where  the  analysis  report  is  used  for  the  verification  of  requirements  it 
shall  list  the  requirements  to  be  verified  (in  correlation  with  the  VCD), 
summarize the analysis results, present comparison with the requirements, 
and  indicate  the  verification  closeout  judgements  (e.g.  requirement  met  / 
not met). 

Q.2.2 Special remarks


None. 

97 
ECSS‐E‐ST‐10C 
6 March 2009 

Annex R (informative)
Mapping of typical DDP to ECSS
documents

 
Design Development Plan (DDP) content  ECSS coverage 
Introduction  M‐ST‐10 ‐ PMP <3> 
• General summary of the scope, objective and constraints  E‐ST‐10 ‐ SEP <3.1> 
• Definition of responsibilities and pre‐requisites  M‐ST‐10 ‐ PMP <4> 
System definition including high level product tree  M‐ST‐10 ‐ PT 
• Identification of customer furnished products  M‐ST‐60 ‐ 9.6.2 req.  
• Availability of and need to reuse existing products  E‐ST‐10 ‐ SEP <4.2>.6 and <5.2.13> 
• Specification tree   M‐ST‐10 ‐ PT <3>.e 
E‐ST‐10 ‐ Annex J 
Technology assessment  E‐ST‐10 ‐ SEP <5.2.5>  
Availability of and need to develop new technologies  E‐ST‐10 ‐ TP <4.3> 
System design flow and philosophy of models  E‐ST‐10 ‐ SEP <4.2>.4 
• Model philosophy   E‐ST‐10 ‐ SEP <4.2>.5 
• Design margin philosophy for budgets   
‐ Margin philosophy for requirements as flown 
down from system to subsystem‐ assembly – and 
equipment level  
‐ Management of system resource allocation over the 
entire project phases and resource reporting to the 
next higher level 
‐ Rationale 
 
System control and verification  E‐ ST‐10 ‐ SEP <5.2.2>  
• Qualification and acceptance philosophy   ‐> E‐ ST‐10‐02 ‐ VP 
• Budget allocation philosophy  ‐> E‐ ST‐10‐02 ‐ VCD (inc. VM) 
• Compliance to requirements demonstration philosophy 
• High‐level Assembly, Integration & Verification Plan, incl.: 
‐ end to end test 
‐ mission simulation and Dress Rehearsals 

98 
ECSS‐E‐ST‐10C 
6 March 2009 

Planning and definition of milestones and reviews  M‐ ST‐10 ‐ PMP <7>  
including the analysis of the critical path(s)  ‐> M‐ ST‐60 ‐ S 
• definition and scope of reviews in terms of    
‐ baselining of requirements and requirements  M‐ ST‐10‐01  
control 
E‐ST‐10 ‐ SEP <3.3> 
‐ design releases and control of released design 
including external and internal interfaces 
Definition of required Ground Support Equipment   
and schedule of development and delivery 
Risk assessment linked to development choices  E‐ ST‐10 ‐ SEP <5.4> <3.5> 
M‐ ST‐80 ‐ RAR 
M‐ST‐10 ‐ PMP  = ECSS‐M‐ST‐10, Project management plan DRD ‐ Annex A 
M‐ST‐10 ‐ PT  = ECSS‐M‐ST‐10, Product tree DRD ‐ Annex B 
M‐ST‐60 ‐ S  = ECSS‐M‐ST‐60, Schedule DRD ‐ Annex B 
M‐ST‐80 ‐ RAR  = ECSS‐M‐ST‐80, Risk assessment report DRD ‐ Annex C 
E‐ST‐10 ‐ SEP  = ECSS‐E‐ST‐10, System engineering plan DRD ‐ Annex D 
E‐ST‐10 ‐ TP  = ECSS‐E‐ST‐10, Technology plan DRD ‐ Annex E 
E‐ST‐10‐02 ‐ VP  = ECSS‐E‐ST‐10‐02, Verification plan DRD ‐ Annex B 
E‐ST‐10‐02 ‐ VCD  = ECSS‐E‐ST‐10‐02, Verification control document DRD ‐ Annex C  
(Note: Verification matrix = 1st issue of CVD) 
 
 

99 
ECSS‐E‐ST‐10C 
6 March 2009 

Bibliography

ECSS‐S‐ST‐00  ECSS system – Description, implementation and 
general requirements 
ECSS‐E‐ST‐10‐03  Space engineering – Testing 
ECSS‐E‐ST‐10‐04  Space engineering – Space environment 
ECSS‐E‐ST‐10‐11  Space engineering – Human factors engineering 
ECSS‐E‐ST‐20  Space engineering – Electrical and electronic 
ECSS‐E‐ST‐3x series  Space engineering – Materials series 
ECSS‐E‐ST‐40  Space engineering – Software general requirements 
ECSS‐E‐ST‐50  Space engineering – Communications 
ECSS‐E‐ST‐60  Space engineering – Control engineering 
ECSS‐E‐ST‐70  Space engineering – Ground systems and 
operations 
ECSS‐E‐ST‐70‐41  Space engineering – Telemetry and telecommand 
packet utilization 
ECSS‐E‐HB‐10  Space engineering – System engineering guidelines 
ECSS‐E‐TM‐10‐10  Space engineering – Logistic engineering 
ECSS‐E‐TM‐10‐20  Space engineering – Product data exchange 
ECSS‐E‐TM‐10‐21  Space engineering – System modelling and 
simulation 
ECSS‐M‐ST‐60  Space project management – Cost and schedule 
management 
ECSS‐M‐ST‐70  Space engineering – Integrated logistic support  
ECSS‐M‐ST‐80  Space project management – Risk management 
ECSS‐Q‐ST‐10  Space product assurance – Product assurance 
management 
IEEE P1220  Standard for application and management of the 
systems engineering process 
ISO/CD 24113   Space systems – Space debris mitigation 
 