0% found this document useful (0 votes)
240 views10 pages

Method of Procedure Semi Auto Integration On Site XL Axiata Project

Uploaded by

bintang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
240 views10 pages

Method of Procedure Semi Auto Integration On Site XL Axiata Project

Uploaded by

bintang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

Method of Procedure Semi Auto Integration

On Site XL Axiata Project

Work Instruction

Contents

1 Purpose of this document .................................................................................... 2


2 Revision information ............................................................................................ 2
3 Scope of MOP ......................................................................................................... 2
4 Tools and Software Required ............................................................................. 2
5 Preparation............................................................................................................. 2
6 Laptop Preparation............................................................................................... 3
7 On Site Integration ............................................................................................... 4
8 Troubleshooting .................................................................................................. 10

2020-02-24 Rev A
1 Purpose of this document
This document acts as a guideline for integrating Baseband using semi auto integration
procedure.

2 Revision information
A First draft ehenrer

3 Scope of MOP
In this document the procedure describe is only limited for Baseband on site procedure.
For other steps required such as transport readiness or remote procedure is considered out
of scope or will be describe on other document.

4 Tools and Software Required


• Internet Browser (Internet Expoler, Chrome, etc)

• Moshell or EMCLI latest version

• SFTP Server Software (mini FTP, Core FTP, etc)

• CDD, CDR and ATND

• Latest SW Package: CXP9024418/6_R55L62 (18Q4)

5 Preparation
Before doing semi auto integration procedure, field engineer needs to do the following:

✓ Contact TAC and request SiteInstallation.xml


XML file will be shared by TAC. The file contains OAM IP Address, subnet, port and
VLAN based on the latest update from DLD/ATND
✓ Perform end to end ping tests using laptop to make sure the transmission is ready
and configured correctly based on DLD/ATND.

2020-02-24 Rev A © Ericsson AB 2020 2 (10)


Public
6 Laptop Preparation
Follow this procedure to change IP address of the local terminal to allow it to connect to
Baseband:

• Connect a standard Ethernet cable from the local terminal to the LMT port of the
Baseband

• Go to the Start (Windows) Button, and select Search Programs and Files, and type
cmd

• Under Programs, cmd.exe is listed, right click on it and select Run as administrator.

• When User Access Control asks: “Do you want to allow the following program to
make changes to this computer?”
select Yes

• In the command window that opens type:


For Windows 7:
netsh interface ip set address name="Local Area Connection" static 169.254.2.1
255.255.255.0 169.254.2.2
For Windows 10:
netsh interface ip set address name="Ethernet" static 169.254.2.1
255.255.255.0 169.254.2.2

How to show addresses "Local Area Connection"

How to show addresses "Ethernet"

2020-02-24 Rev A © Ericsson AB 2020 3 (10)


Public
Or change IP address using control panel/network setting:

7 On Site Integration
Only perform the procedure describe in this section if end to end ping tests are OK.

• Open internet browser and connect to the Baseband Emergency Access window.
Go to address: https://169.254.2.2/ea.html
• Check node Status make sure “node has not been up”

2020-02-24 Rev A © Ericsson AB 2020 4 (10)


Public
Note: Approve the security certificate for this node local web site. The IP address of the
LMT port is by default 169.254.2.2.

• If Node status shows "Node is working" then click on "Board restore" to clear all
existing data from the Baseband.

2020-02-24 Rev A © Ericsson AB 2020 5 (10)


Public
• Open a new internet browser window and connect to the Baseband LMT IP
address. Go to address: https://169.254.2.2/
• Select LMT integration" tab

2020-02-24 Rev A © Ericsson AB 2020 6 (10)


Public
• Input Username and Password under SMRS Credentials section

Use ENM username and password with field technician role from TAC

• Click "Browse" to open up the windows file explorer window, select file site
installation.xml for your specific site. The file will be provided from TAC (see
Preparation section)

• Click “Download file” to start auto integration process

Example Download files process. Wait until the status is complete before continuing
with next step:

2020-02-24 Rev A © Ericsson AB 2020 7 (10)


Public
Note: After download is completed, the button for “Integrate” will be ready for click
(button will not be gray anymore)

2020-02-24 Rev A © Ericsson AB 2020 8 (10)


Public
• Click “Integrate” to continue auto integration process and wait until the process is
completed.

Sample log of Successful integration:

2019/11/02 10:37:38 AutoIntegration started


2019/11/02 10:37:41 Enabling boot on installed software
2019/11/02 10:37:41 Updating logs
2019/11/02 10:37:41 Integrate will continue after reboot
2019/11/02 10:40:01 Start loading configuration files
2019/11/02 10:40:15 Configuration files loaded
2019/11/02 10:40:30 Mgmt set rbsConfigLevel to SITE_CONFIG_COMPLETE
2019/11/02 10:49:00 Mgmt set rbsConfigLevel to OSS_ACTIVATING_CONFIGURATION
2019/11/02 10:49:40 Mgmt set rbsConfigLevel to UNLOCKING_CELLS
2019/11/02 10:49:49 Mgmt set rbsConfigLevel to INTEGRATION_COMPLETE
2019/11/02 10:50:35 Mgmt set rbsConfigLevel to READY_FOR_SERVICE

Note: The progress bar at the bottom of the web page should go all the way to “100%
Ready for Service” as shown in screenshot above.

2020-02-24 Rev A © Ericsson AB 2020 9 (10)


Public
• Click on the "Export Autointegration log" button and provide your local laptop IP
address, username, password, and filename you would like to give for the log. The
web browser will use sftp to send the log file to your PC.

Note: Save the log for reference in case needed in the future.

8 Troubleshooting

If there’s an error during auto integration procedure, check the Autointegration Log with
error message and send the information to TAC. The error message is needed for analysis
and troubleshooting procedure or escalation.

2020-02-24 Rev A © Ericsson AB 2020 10 (10)