Creating Basic Time Schedule in MSP

The document provides instructions on creating a basic time-schedule in Microsoft Project. It includes creating a work breakdown structure (WBS) for a villa project, adding activities with durations and predecessors, and sequencing the activities to generate a schedule report.

Uploaded by

Priyanshi Mittal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
71 views

Creating Basic Time Schedule in MSP

The document provides instructions on creating a basic time-schedule in Microsoft Project. It includes creating a work breakdown structure (WBS) for a villa project, adding activities with durations and predecessors, and sequencing the activities to generate a schedule report.

Uploaded by

Priyanshi Mittal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Creating Basic Time-schedule in MSP

Learning Objectives:

➢ Creating WBS
➢ Adding Activities
➢ Sequencing activities
➢ Scheduling project and generating schedule report

Lab Exercise

1. Create the following WBS in the Project

Villa Project

Post-
Preconstruction Construction
construction
Phase Phase
phase

Subctructure Ground Floor


Terrace Work External Work Final Finishes
Work Work

2. Create the following schedule in activity window:


S.No. WBS Task Name Duration Predecessors
0 VILLA PROJECT 90 days
1 1 Project Start 0 days
2 2 Preconstruction Phase 5 days
3 2.1 Site Mobilization 3 days 1
4 2.2 Layout 2 days 3
5 3 Construction Phase 78 days
6 3.1 Substructure Works 10 days
7 3.1.1 Excavation 6 days 4
8 3.1.2 Foundations 7 days 7SS+3 days
9 3.2 G.Floor Works 53 days
10 3.2.1 Walls and Columns 10 days 8
11 3.2.2 Roof slab 7 days 10SS+7 days
12 3.2.3 Conduiting, water and sanitary pipes 4 days 11FS+14 days
13 3.2.4 Fixing of wooden frames and plastering 7 days 12SS+2 days
14 3.2.5 Kitchen and toilet tiling 10 days 13SS+4 days
15 3.2.6 Flooring 10 days 14SS+6 days
16 3.3 Terrace Works 28 days
17 3.3.1 Parapet, Waterproofing etc. 7 days 11
18 3.3.2 Services 10 days 17
19 3.3.3 Terrace Finish 7 days 18
20 3.4 External Works 59 days
21 3.4.1 Outside plastering 8 days 17,13SS+4 days
22 3.4.2 External services and Boundary wall 7 days 8
23 3.4.3 Paths and Pavements 7 days 22,21
24 3.4.4 Boundary wall gates 7 days 23
25 3.5 Final Finishes 23 days
26 3.5.1 Doors and Windows fixing 3 days 21,15
27 3.5.2 Internal Painting (Initial Coats) 3 days 26
28 3.5.3 External Painting (Initial Coats) 3 days 21
29 3.5.4 Wood Polishing 3 days 27,28
30 3.5.5 Hardware, Sanitary, Plumbing, Electrical
3 days 29
fixtures fixing
31 3.5.6 Final coats (Internal and External painting) 3 days 30,28
32 4 Post Construction Phase 7 days
33 4.1 Defects Rectification and Handing over 7 days 31,24
34 4.2 Project finish 0 days 33