Gin Pole
Gin Pole
Gin Pole
Pre-Engineered Structures
Topics
1.0.0 Pre-Engineered Buildings
2.0.0 K-Span Buildings
3.0.0 Steel Towers
4.0.0 Antenna Towers
Gas Welding
Gas Cutting
Introduction to Welding
Pre-engineered buildings are ideal for use as repair shops or warehouses because they
have a large, clear floor area without columns or other obstructions, as well as straight
sidewalls. This design allows floor-to-ceiling storage of material and wall-to-wall
placement of machinery. The column-free interior also permits efficient shop layout and
unhindered production flow.
After a building is up, it can be enlarged while in use by 20-foot bays, providing
additional space under one roof. If desired, PEBs can be erected side by side in
multiples, and when a building is no longer needed it can be disassembled, stored, or
NAVEDTRA 14250A 17-4
moved to another location and re-erected because only bolted connections are used,
with no welding or riveting. The rigid frame is strong, designed for working loads of 20
pounds per square foot load, plus the dead load and the load from a 70-mph wind.
The building can be easily modified to varying lengths and purposes by taking out or
adding bays, or by substituting various foundation and wall sections. A bay is the
distance between two column centers or between the end wall and the first column
center in from the end wall.
Formulas used to determine the number of bays, frames, and intermediate frames in a
building are as follows:
Length divided by 20 = number of bays
Bays + 1 = total number of frames
Total number of frames - 2 = number of intermediate frames
CAUTION
Proper anchor bolt placement is absolutely critical when erecting a PEB.
The threads of the bolts are greased and the nuts placed on them to protect the
threads. Concrete is then poured into the formwork and worked carefully into place
around these bolts, so they remain vertical and in place. Finally, according to the plans
and specifications, the slab is poured.
While the foundation is being prepared, the crew leader will assign personnel/crews to
perform various types of preliminary work, such as uncrating and inventorying all
material on the shipping list, bolting up rigid-frame assemblies, assembling door eaves,
and glazing windows. Box 1 contains the erection manual, the drawings, and an
inventory list; it should be opened first. If all of the preliminary work is done correctly, the
assembly and erection of the entire building is accomplished easily and quickly.
All material, except the sheeting, should be uncrated and laid out in an orderly manner
so the parts can be located easily. Do not uncrate the sheeting until you are ready to
install it. When opening the crates, use care not to cause any damage to the lumber.
Girts, purlins, eave struts, and brace rods should be equally divided along both sides of
the foundation. Panels and miscellaneous parts which will not be used immediately
should be placed on each side of the foundation on pallets or skids and covered with
tarps or a similar type of covering until needed. Parts making up the rigid-frame
assemblies are laid out ready for assembly and in position for raising.
Always use care in unloading materials. Remember that damaged parts will cause
delays in getting the job done. To avoid damage, lower the materials to the ground
slowly and do not drop them.
Figure 17-3 will help you identify the structural members of the building and their
location. Each part has a specific purpose and must be installed in its designated
location to ensure a sound structure.
CAUTION
Never omit any part called for on the detailed erection drawings.
Each of the members, parts, and accessories of the building is labeled by stencil so it is
not necessary to guess which one goes where. Refer to the erection plans to find the
particular members you need as you work.
CAUTION
The first bay must be aligned before erecting additional bays.
CAUTION
Never omit the brace rods, either sidewall or roof.
The diagonal brace rods are attached to the frames in the roof and sidewall through the
slotted holes provided. Use a half-round brace rod washer and a flat steel washer under
the nuts at each end of the rods. With the rods installed, plumb each frame column with
the carpenter’s spirit level.
Check the distance diagonally from the upper corner of one frame to the lower corner of
the adjacent frame. When this distance is the same for each rod, the columns will be
After the two frames have been plumbed and braced square with the diagonal rods, and
the purlins, girts, and eave struts have been installed, the guy lines or props can be
removed and the remaining frames of the building can be erected. Note the following
precautions:
• Do not omit the diagonal brace rods that are required in the last bay of the
building.
• Be sure to bolt the girts, purlins, and eave struts to the inside holes of the end
frames.
• Install the eave struts, girts, and purlins in each bay as soon as a frame is
erected.
• Exercise care to see that the diagonal brace rods are taut and do not project
beyond the flanges of the end frame to interfere with end-wall sheeting.
• To raise the next frame, attach blocks to the last frame raised and proceed to the
next bay frame.
CAUTION
Never omit diagonal brace angles. They are needed to support the inner flange
of the frame. Install them so they are taut.
While some members of the crew are installing brace angles, other members can be
installing base angles. When assigned this duty, first sweep off the top of the concrete
foundation so the base angles will set down evenly. Bolt the base angles in place with a
flat steel washer under the nut. Leave the nuts loose to permit later adjustments after
the wall sheeting has been applied.
1.2.7 Sheeting
Always start the sheeting, both sidewall and roof, at the end of the building toward
which the prevailing winds blow. For example, if the winds are predominately easterlies
(from the east), start your sheeting on the west end of the building to ensure that the
NAVEDTRA 14250A 17-11
exterior joint in the side laps is away from the blowing of the prevailing winds. When
installing roof sheeting, always use a generous amount of mastic on the upper side of
all roof sheets just before moving them to the roof. Turn the sheet over and put a bead
of mastic on the lip of one side of the corrugation and along one end--near the end but
never more than one 1 inch from the end. Be sure to apply a horizontal bead of mastic
between all sheets in the end laps below the lap holes. The roof sheets must be dry
when mastic is applied. Mastic is extremely important, and you must exercise care
whenever applying it to ensure a watertight seal. Apply generous beads, especially at
the comers of the sheets. Finally, install the ridge cap, ensuring proper watershed. As
previously stated, the information in this manual is general information common to pre-
engineered buildings.
If you are selected for the operator’s position, as you operate the panel, you will be
adjusting the various machine operating components. Make adjustments for thickness,
radius, and the curving machine according to the manuals. Do not permit short cuts in
adjustments. Any deviations in adjustments or disregard for the instructions found in the
operating manuals will leave you with a pile of useless material and an inconsistent
building.
2.1.3 Foundations
While the design of the foundation for a K-span building depends on the building’s size,
existing soil conditions, and wind load, the foundations are simple and easy to
construct. With the even distribution of the load in a standard arch building, the size of
the continuous strip footing is smaller and more economical than the foundations for
conventional buildings.
The provided concrete forms and accessories to form the foundations are sufficient for a
building 100 feet long by 50 feet wide, and forms are available upon request from the
manufacturer for different configurations.
The actual footing construction is based, as all projects are, on the building plans and
specifications. The location of the forms, placement of steel, and the psi (pounds per
square inch) of the concrete are critical. Since the building is welded to the angle in the
footer prior to the concrete placement, all aspects of the footer construction must be
thoroughly checked for alignment and square. Once concrete is placed, there is no way
to correct mistakes.
When the integrity of the end-wall panels is continuous from ground to roofline, the end
walls become self-supporting. The installation of windows (Figure 17-21) and aluminum
doors (Figure 17-22) presents no problem because the integrity of the wall system is not
interrupted. The installation of the overhead door (Figure 17-23) does present a problem
in that it does interrupt the integrity of the wall system. This situation is quickly
overcome by the easily installed and adjustable (in height and width) doorframe
package that supports both the door and end wall. This doorframe package is offered by
the manufacturer.
Figure 17-24 shows the fundamental steps in constructing a K-span from start to finish.
2. Pivoted tower base — used primarily on lightweight structures for ease of tower
erection.
3. Composite base — generally used with heavier towers because it affords much
greater supporting strength than the other two types.
All three are shown in Figure 17-30.
Sections for lightweight towers are usually assembled before delivery to expedite final
tower assembly, whereas heavier weight towers must be assembled completely in the
field.
Tower bracing should include diagonal bracing and horizontal struts in the plane of each
tower face for the full tower height.
2. Check all of the surface areas for proper preservation. Cover all the holes and
dents in galvanized materials with zinc chromate or another acceptable
preservative to prevent deterioration.
3. When high-strength bolts are used in a tower assembly, place a hardened steel
washer under the nut or bolt head, whichever is to be turned. Exercise care that
you do not exceed the maximum torque limit of the bolt. Maximum torque values
of several different sizes and types of bolts commonly used in antenna towers
are listed in Table 17-2.
3/4” — 13 38 105 26 43
5/8” — 11 84 205 60 92
1” — 8 236 850 — —
A gin pole with a top sheave to take the winch line is mounted close to the concrete
tower base. Permanent guys attached to the tower at three elevations are handled by
personnel during hoisting operations (Figure 17-35). Temporary rope guys provided with
a snatch block anchored to deadmen furnish the necessary lateral stability. As the mast
NAVEDTRA 14250A 17-39
approaches a vertical position, the permanent guys are fastened to the guy anchors,
which were installed before erection.
4.5.0 Guying
Temporary guying of steel towers is always necessary where more than one tower
section is erected. Under no circumstances should the tower be advanced more than
two sections without guying, and always install permanent guys before removing
temporary guys.
A. Office space
B. Hangar
C. Supply building
D. Warehouse
3. What does the ABM 120 panel-forming machine produce for a K-span building?
A. L spans
B. Straight panels
C. Arched panels
D. Doorframes
4. The design of the foundation for a K-Span building does NOT depend on the
_______.
A. True
B. False
7. (True or False) A PEB is shipped with all materials and instructions necessary for
erection.
A. True
B. False
9. Which task should you perform before placing concrete for the foundation piers
of a rigid frame building?
10. While the foundation is being prepared for a 40 by 100 foot rigid frame building,
which work assignment can you perform?
11. Until ready for use, which material should remain crated?
A. Girts
B. Sheeting
C. Eave struts
D. Brace rods
12. What should you do to ensure building materials are accessible during assembly
of a PEB?
13. How is each of the members, parts, and accessories of the building marked so it
is not necessary to guess which one goes where?
A. True
B. False
15. Where must brace rods be installed to hold the frames in an upright position?
16. Where must sheeting installation be started on the sidewall and roof?
17. (True or False) Pre-engineered buildings can be set up side by side to increase
the working area under one roof.
A. True
B. False
A. Windows
B. Aluminum doors
C. Wood doors
D. Overhead doors
Description
_______________________________________________________________
_______________________________________________________________
_______________________________________________________________
(Optional) Correction
_______________________________________________________________
_______________________________________________________________
_______________________________________________________________