Topic 7 - The Quantity Measurement
Topic 7 - The Quantity Measurement
The Quantity Surveying (QS) profession has been on-going for many years.
The earliest quantity surveying practice on record is a Reading firm, (Henry Cooper and
Sons), in 1785 (Seeley & Winfield, 1999)
QS deal with the costs and contracts of a construction project.
The Taking Off process is part of the contract documents in a construction project. Thus
when signing the contract document you are willing to accept that it is correct and you
will be held (liable) to everything in it.
The BQ is a document which is used for the tendering process in a construction project, in
which materials, parts, and labour are itemized.
The Bill of Quantities (BQ) is prepared by a QS.
The Bill of Quantities (BQ)
ELEMENT : SUBSTRUKTUR
ELEMENT :
SUB-ELEMENT : PAGE 1 OF 17 SUB-ELEMENT : KOREKAN UNTUK PEMBERSIHAN TAPAK PAGE 2 OF 17
DESCRIPTION DESCRIPTION
Korekan untuk permukaan tanah hingga ke aras laras purata kedalaman 150mm, bermula dari aras tanah, diangkut dan dibuang tanah
selebihnya tidak melebihi 100m daripada tapak binaan
TAKING OFF LIST
DIMENSION
DIMENSION
length: 3/3600
10800
1 Site Clearing (m2)
add
(F1) 275
2 Pad Foundation
11075
a. Excavate pit (m3)
13.35 add
b. Lean Conc (m2) 10.35 (F1) 275
c. Vibrated Reinf. Conc (m3) 138.17 11350
d. Reinforcement (m) add
e. Formwork (m2) 2/1000 2000
13350
3 Column Stump
a. Vibrated Reinf. Conc (m3)
b. Reinforcement (m) width: 3300
c. Link (m) add 4500
d. Formwork (m2) 7800
add
4 Ground Beam F1 275
a. Excavate trench (m3) 8075
b. Lean concrete (m2) add
QTY : TAKER-OFF :
QTY : TAKER-OFF :
UNIT : m2 SQUARED BY :
UNIT : SQUARED BY :
RATE : ABSTRACT BY :
RATE : ABSTRACT BY :
COST : CHECKED BY : COST : CHECKED BY :