Estimates - Jongoy
Estimates - Jongoy
DIRECT COST
Unit Quantity Price Amount
A. MATERIAL
a. (2" x 2" x 12') bd.ft - Coco Lumber bd.ft 50 20.00 1,000.00
b. #70 Nylon rolls 2 50.00 100.00
c. CWN Nails #3 kgs 2 80.00 160.00
DIRECT COST
Unit Quantity Price Amount
A. MATERIALS
Sub-total for A 0.00
Description Quantity No. of Hours Hourly Rate Amount
B. LABOR
a. Construction Foreman 1 36 87.36 3,144.96
b. Laborers 5 36 50.46 9,082.80
DIRECT COST
Unit Quantity Price Amount
A. MATERIALS
a. Scaffold Tube lot 1 10,000.00 10,000.00
DIRECT COST
Unit Quantity Price Amount
A. MATERIALS
Sub-total for A 0.00
Description Quantity No. of Hours Hourly Rate Amount
B. LABOR
a. Construction Foreman 1 50 87.36 4,368.00
b. Laborers 5 50 50.46 12,615.00
DIRECT COST
Unit Quantity Price Amount
A. MATERIALS
a. Common Borrow (w/ 25% Shrinkage Factor) cu.m 19.44 200 3,888.00
DIRECT COST
Unit Quantity Price Amount
A. MATERIAL
a. Lumber, Good - 3 uses bd.ft. * 70.0000 18.00 1,260.00
b. Marine Plywood (1/2" x 4' x 8') - 3 uses pc. * 5.000 840.00 4,200.00
c. Assorted CWN (1kg/100 bd.ft.) kg. * 7.000 80.00 560.00
d. Cement 9.50 bag 917.37 290.00 266,036.58
e. Sand 0.50 cu.m. 48.28 1,000.00 48,282.50
f. Gravel 1.00 cu.m. 96.57 1,500.00 144,847.50
Steel Diameter,
L Quantity Factor Total Weight, kg Price per kg Amount
mm
10 pcs 125 3.7 462.50 22.00 10,175.00
12 pcs 115 5.33 612.95 22.00 13,484.90
6-m
16 pcs 100 9.47 947.00 21.8 20,644.60
20 pcs 30 14.8 444.00 21.8 9,679.20
2,466.45 53,983.70
DIRECT COST
Unit Quantity Price Amount
A. MATERIAL
a. Reinforcing Steel bars kg 2,466.45 - 53,983.70
b. #16 G.I Tire wire kg 49.33 30.00 1,479.87
DIRECT COST
Unit Quantity Price Amount
A. MATERIAL
a. 4" CHB Ordinary pc 1,513 15.00 22,695.00
b. Portland Cement bag 63 290.00 18,270.00
c. Fine Aggregate cu.m. 5 1,000.00 5,000.00
DIRECT COST
Unit Quantity Price Amount
A. MATERIAL
a. Portland Cement bag 59 290.00 17,110.00
b. Fine Aggregate cu.m. 5 1,000.00 5,000.00
DIRECT COST
Unit Quantity Price Amount
A. MATERIAL
a. Cement mortar bag 18 290.00 5,220.00
b. White Cement kg 105 1,000.00 105,000.00
c. Tile (20x20 cm Glazed Tile) sq.m 60 700.00 42,000.00
d. Tile adhesive bag 23 300.00 6,900.00
DIRECT COST
Unit Quantity Price Amount
A. MATERIAL
a. Fiber Cement board sht 55 500.00 27,500.00
b. 0.8mm thk. -12mm x 38mm x 5.00m kg 35 120.00 4,200.00
Metal Furring
c. Rod suspension hanger w/
set 25 80.00 2,000.00
adjustment spring
d. Pre-formed wire clip set 50 10.00 500.00
e. Toks screw pc 200 2.00 400.00
DIRECT COST
Unit Quantity Price Amount
A. MATERIAL
Gate Valve pc 1 1,500.00 1,500.00
Check Valve pc 1 5,700.00 5,700.00
Foot Valve pc 1 2,400.00 2,400.00
Pressure Gauge pc 1 300.00 300.00
Tee (4" x 4") pc 5 100.00 500.00
Tee (2" x 2") pc 5 90.00 450.00
Elbow (90 deg. 4" x 4") pc 5 110.00 550.00
Elbow (90 deg. 3" x 3") pc 5 95.00 475.00
Wye (4" x 3") pc 5 100.00 500.00
Wye (3" x 3") pc 5 90.00 450.00
Water Closet pc 2 4,500.00 9,000.00
Lavatory pc 3 3,900.00 11,700.00
Floor Drain (type 1) pc 3 150.00 450.00
Floor Drain (type 2) pc 2 100.00 200.00
P-trap (4" x 4") pc 5 125.00 625.00
Downspout 100mm dia pc 6 100.00 600.00
Cleanout pc 4 100.00 400.00
Magnetic Contractor pc 2 5,000.00 10,000.00
Main Circuit Breaker pc 1 1,000.00 1,000.00
Drainage Pipe 50 mm dia. pc 3 350.00 1,050.00
Drainage Pipe 100 mm dia. pc 3 775.00 2,325.00
Teflon pc 10 30.00 300.00
Solvent can 5 80.00 400.00
Water Tank - 2 gal pc 1 50,000.00 50,000.00
DIRECT COST
Unit Quantity Price Amount
A. MATERIAL
a. 1-18W, Compact Fluorescent Lamp set 10 720.00 7,200.00
d. Lamp Post set 4 3,500.00 14,000.00
e. Convenience Outlets set 20 400.00 8,000.00
f. Circuit Breaker set 18 450.00 8,100.00
g. Junction Box set 35 40.00 1,400.00
h. Panel Board set 1 12,500.00 12,500.00
i. Wire Stranded m 150 40.00 6,000.00
j. 1-gang Switch set 3 150.00 450.00
k. 2-gang Switch set 5 190.00 950.00
l. 3-gang Switch set 2 275.00 550.00
m. Electrical Conduit uPVC Pipe Price 3/4" pc 12 85.00 1,020.00
n. Electrical Conduit uPVC Pipe Price 1" pc 5 120.00 600.00
o. Electrical Conduit uPVC Pipe Price 1 1/4" pc 6 150.00 900.00
p. Electrical Conduit uPVC Pipe Price 1 1/2" pc 5 190.00 950.00
q. Electrical Conduit uPVC Pipe Price 3 1/8" pc 7 600.00 4,200.00
DIRECT COST
Unit Quantity Price Amount
A. MATERIAL
a. Concrete Neutralizer quartz 5 290.00 1,450.00
b. Concrete Primer Sealer gal. 13 1,000.00 13,000.00
c. Skim coat cement bag 108 500.00 54,000.00
d. Paint thinner gal. 15 250.00 3,750.00
e. Acrylic Gloss Latex Paint can 13 1,100.00 14,300.00
f. 9'' roller paint w/ tray pc 10 100.00 1,000.00
g. 4'' paint brush pc 5 70.00 350.00
h. 2'' paint brush pc 5 50.00 250.00
i. Sandpaper #60 pc 10 95.00 950.00
j. Sandpaper #100 pc 10 100.00 1,000.00
k. Sandpaper #200 pc 10 150.00 1,500.00
l. Pallete Knife pc. 10 180.00 1,800.00
DIRECT COST
Unit Quantity Price Amount
A. MATERIAL
a. Zoning, BFP, and Occupancy Permits 1 1 250,000.00 250,000.00
DIRECT COST
Unit Quantity Price Amount
A. MATERIAL
a. Hard Hat pc 10 600 6,000.00
b. Powermix pc 2 700 1,400.00
c. Cement Topping pairs 5 200 1,000.00
d. First-aid Kit set 2 20,000.00 40,000.00
DIRECT COST
A. MATERIAL COST ₱ 1,531,838.15
B. LABOR COST LABOR COST ₱ 343,734.95
C. EQUIPMENT EXPENSES EQUIPMENT EXPENSES ₱ 13,514.50
TOTAL DIRECT COST ₱ 1,889,087.59
INDIRECT COST
A. OVERHEAD, CONTINGENCIES, &MISCELLANEOUS (OCM) - 9% OF DC ₱ 170,017.88
B. CONTRACTOR'S PROFIT (CP) - 8% OF DC ₱ 151,127.01
TOTAL INDIRECT COST ₱ 321,144.89
VAT (5% OF DC+IC)
VAT ₱ 110,511.62
TOTAL PROJECT COST ₱ 2,320,744.10
COST PER SQUARE METER ₱ 11,840.53
BILL OF MATERIALS
PROJECT TITLE : PROPOSED ONE-STOREY RESIDENTIAL BUILDING
LOCATION : Sitio Tabok, Brgy. Imelda, Tubajon, Dinagat Island
A. MATERIALS
B. LABOR
C. EQUIPMENT
A. DIRECT COST
MATERIAL COST ₱1,531,63
LABOR COST ₱343,73
EQUIPMENT COST ₱13,51
TOTAL DIRECT COST
B. INDIRECT COST
OVERHEAD, CONTINGENCIES, & MISCELLANEOUS (OCM) - [9% OF DC] ₱170,01
CONTRACTOR'S PROFIT (CP) - [8% OF DC] ₱151,12
TOTAL DIRECT COST
C. VAT (5% OF DC+IC)
TOTAL VAT
TOTAL PROJECT COST
ESTIMATED COST PER SQUARE METER
PREPARED BY:
ALJEANN L. JONGOY
BSCE - 5
AMOUNT
1,000.00
100.00
160.00
10,000.00
3,888.00
1,260.00
4,200.00
560.00
266,036.58
48,282.50
144,847.50
10,175.00
13,484.90
20,644.60
9,679.20
1,479.87
22,695.00
18,270.00
5,000.00
17,110.00
5,000.00
5,220.00
105,000.00
42,000.00
6,900.00
27,500.00
4,200.00
2,000.00
300.00
400.00
1,500.00
5,700.00
2,400.00
300.00
500.00
450.00
550.00
475.00
500.00
450.00
9,000.00
11,700.00
450.00
200.00
625.00
600.00
400.00
10,000.00
1,000.00
1,050.00
2,325.00
300.00
400.00
50,000.00
47,500.00
4,000.00
8,300.00
5,000.00
110,000.00
7,200.00
14,000.00
8,000.00
8,100.00
1,400.00
12,500.00
6,000.00
450.00
950.00
550.00
1,020.00
600.00
900.00
950.00
4,200.00
1,450.00
13,000.00
54,000.00
3,750.00
14,300.00
1,000.00
350.00
250.00
950.00
1,000.00
1,500.00
1,800.00
250,000.00
6,000.00
1,400.00
1,000.00
40,000.00
1,531,638.15
343,734.95
1,420.00
1,733.00
3,379.00
3,000.00
2,840.00
439.50
703.00
13,514.50
₱1,531,638.15
₱343,734.95
₱13,514.50
₱1,888,887.59
₱170,017.88
₱151,127.01
₱321,144.89
₱110,511.62
₱2,320,544.10
₱11,840.53
PROGRAM OF WORKS
Project Title :PROPOSED
DESIGN ONE-STOREY
OF A HILLTOPRESIDENTIAL
THREE-STOREY BUILDING
PARKING BUILDING
Location : SitioJose
Tabok,
Sering
Brgy.
Road,
Imelda,
Capitol,
Tubajon,
Surigao
Dinagat
City,Island
Surigao del Norte
TOTAL
PREPARED BY:
ALJEANN L. JONGOY
BSCE - 5
AM OF WORKS
1
5
10
1
1
PENSES 343,734.95
EXPENSES 13,514.50
% WEIGHT AMOUNT (P)
0.44 10,191.64
0.81 18,707.30
0.59 13,639.49
0.90 20,863.62
0.32 7,485.40
29.82 691,999.72
6.44 149,373.92
2.79 64,764.28
1.53 35,458.42
8.93 207,330.75
2.25 52,326.19
6.46 150,035.48
12.95 300,638.52
4.66 108,198.91
5.31 123,146.07
13.23 307,125.00
2.56 59,459.40
100 ₱ 2,320,744.10
₱ 1,889,087.59
₱ 321,144.89
RACT COST ₱ 2,210,232.48
₱110,511.62
OJECT COST ₱ 2,320,744.10
ARE METER ₱ 11,840.53
ACTIVITY DESIGN
Project Title : PROPOSED ONE-STOREY RESIDENTIAL BUILDING
Location : Sitio Tabok, Brgy. Imelda, Tubajon, Dinagat Island
PREPARED BY:
ALJEANN L. JONGOY
BSCE - 5
ESTIMATED TIME (DAYS)
7
7
9
7
5
11
7
24
24
14
10
10
9
12
7
13
9
185
Name of Sub-Project: Total Sub-Project Cost :
PROPOSED ONE-STOREY RESIDENTIAL BUILDING
Direct Cost :
Physical Target : 210.00 sq.m. Indirect Cost :
Region : CARAGA REGION XIII Date Started : 16-Mar
Province : Surigao Del Norte Target Completion Date : 18-Jul
Municipality/City : Tubajon :
Barangay: : Imelda Mode of Implementation :
I. To be filled up by Deputy Area Coordinator
WEIGHT
Item No. DESCRIPTION QTY UNIT AMOUNT (%) PHYSICAL TARGET
Week 1
3.78% Planned 3.78%
B.3 PERMITS AND CLEARANCES 1.00 lot 307,125.00
0.00% Actual
3.78% Planned
B.7 OCCUPATIONAL AND HEALTH PROGRAM 1.00 lot 59,459.40
0.00% Actual
4.86% Planned
100 CLEARING AND GRUBBING 400.00 sq.m. 10,191.64
0.00% Actual
3.78% Planned
101 REMOVAL OF STRUCTURES AND OBSTRUCTIONS 2,500.00 cu.m. 18,707.30
0.00% Actual
2.70% Planned
B.24 GENERAL SCAFFOLDING AND SHORING 1.00 lot. 13,639.49
0.00% Actual
5.95% Planned
103 STRUCTURAL EXCAVATION 125.00 cu.m. 20,863.62
0.00% Actual
3.78% Planned
102 EMBANKMENT 15.55 cu.m. 7,485.40
0.00% Actual
12.97% Planned
405 STRUCTURAL CONCRETE 96.57 cu.m. 691,999.72
0.00% Actual
12.97% Planned
404 REINFORCING STEEL 2,182.12 kgs 149,373.92
0.00% Actual
7.57% Planned
506 MASONRY WORKS 121.00 sq.m. 64,764.28
0.00% Actual
5.41% Planned
1027 CEMENT PLASTER CEMENT 245.00 sq.m. 35,458.42
0.00% Actual
5.41% Planned
1018 TILEWORKS 210.00 sq.m. 207,330.75
0.00% Actual
4.86% Planned
1003 CARPENTRY AND JOINERY WORKS 1.00 lot 52,326.19
0.00% Actual
6.49% Planned
1002 PLUMBING WORKS 1.00 lot 150,035.48
0.00% Actual
3.78% Planned
SPL II DOORS AND WINDOWS 1.00 lot 300,638.52
0.00% Actual
7.03% Planned
SPL III ELECTRICAL WORKS 1.00 lot 108,198.91
0.00% Actual
4.86% Planned
SPL V PAINTING WORKS 1.00 lot 123,146.07
0.00% Actual
100% Planned
TOTAL 2,320,744.10
0.00% Actual
PERIODIC 3.78%
% PROGRESS (PLANNED)
CUMMULATIVE 3.78%
PHYSICAL
PHYSICAL
PERIODIC
% PROGRESS (ACTUAL)
CUMMULATIVE
2,320,744.10 LABOR
1,889,087.59
SKILLED
321,144.89
16-Mar-20
UNSKILLED
18-Jul-20
TOTAL
3.78%
4.86%
3.78%
5.95%
No. of days
MALE
FEMALE
MALE
FEMALE
MALE
FEMALE
2.70%
5.95%
3.78%
12.97%
DURATION
Week 10 Week 11 Week 12 Week 13 Week
12.97%
7.57%
6.49%
7.03%
5.41%
5.41%
4.86%
3.78%
4.86%
5.41%
5.41%
00.00%