ITD-GEN-000-CIV-CHK-0001 - 0 - Earthwork ITPs
ITD-GEN-000-CIV-CHK-0001 - 0 - Earthwork ITPs
ITD-GEN-000-CIV-CHK-0001 - 0 - Earthwork ITPs
"W" - WITNESS POINT - Work shall be witnessed for the inspection stage. Contractor shall notify the
COMPANY / PMC and raise RFI.
"S" - SURVEILLANCE - Surveillance can be carried out for on-going activity but formal notification and RFI is
not required.
"R" - REVIEW - Document shall submitted for review and approval through transmittal. Work shall not be
proceeded unless contractor has received Code-A / Code-B from PMC / COMPANY.
"RFI" - REQUEST FOR INSPECTION - Contractor shall submit the FRI along-with their inspection
notification.
SCOPE OF WORK
Contractor shall "briefly" specify their Scope of Work:
ITP - INSPECTION & TEST PLAN
EARTHWORK
Document No : ITD-GEN-000-CIV-CHK-0001;Rev-0
Reference Document Verifying Document Checklist
No. Activity Contractor PMC
Acceptance Criteria (Inspection Report & Checklist) Reference
OMC, MDD (Proctor), and CBR for Excavation, Backfill & Compaction
1.2 RFI & Lab Test Reports Checklist-1-1
backfilling material OMC & MDD Lab Reports
Construction Drawing
H R
1.5 Compaction Test Excavation, Backfill & Compaction RFI & Lab Test Reports H W Checklist-1-2
Construction Drawing
Note :
1. Contractor shall attach "Inspection Reports" of ITP along-with RFI.
2. PMC / Contractor to complete the "Inspection Checklist" attached with RFI.
3. PMC is to ensure that all inspection record is complete and has been placed in MC / PA / Dossiers.
Inspection Checklist
EARTHWORK-EXCAVATION
Document # :Checklist-1-1
Report # PRID #: Project Name: Contractor :
RFI #
Inspection Time Start: Finish: Inspection Date:
Dwg # / Line # : Area/Location:
Reference:
Inspector's Checklist
Inspector's Observation
Sr # Description of Activity
(Record the Data)
Yes No
Availability of DWG:
1
AFC drawing & Spec available at site
Surveying:
2 Survey setting-out done and excavated area marked (Survey report Yes No
attached).
existing UG facilities?
3 Yes No
If yes, One / All of the following action has been taken: UG facilities Explain:
were detected, exposed by manual excavation, protected, and/or ……………………………………………….
relocated.
Over Excavation:
Over excavation treated as per specification.
10 Yes No NA
1. Fill with approved material in layers and do compaction OR
2. Fill blinding for structures.
Yes No NA
Protection during Deep Excavation:
Protection for deep excavation provided include one / all of the
11 Specify What Action Taken:
following:
Slope, Side Bracing, Sheet Pile. …………………………………………………………
Sufficient Excavation:
Excavations for structures shall be extended for a sufficient distance
12 Yes No NA
required for placing and removing of shuttering, scaffolding and for
inspection.
HSE Precautions:
13 Ensure that after excavation, area shall be cleaned and all HSE Yes No NA
precautions are taken place.
Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements
(Specifications, Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or applicable, other
activities can be added to the checklist.
Contractor PMC
Name
Date
Signature
Inspection Checklist
EARTHWORK-BACKFILLING
Document # : Checklist-1-2
Report # PRID #: Project Name: Contractor :
RFI # :
Inspection Time Start: Finish: Inspection Date:
Dwg # / Line # : Area/Location :
Reference:
Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (Write N/A if Not Applicable)
(Record the Data)
Yes No
Elevation & Evenness:
3 Survey works for alignment, evenness, and elevations of the previous Specify average layer
and new layers done and checked. (Survey report attached).
THK:……………………………… mm.
Engineering Fill:
6 Engineering fill stocked in batches, a representative sample taken, Yes No NA
tested, and accepted (Procter test done)
The compacted fill mixed with a clean water free from oil, grease,
7 Yes No
organic, and suspended fine.
Moisture Contents:
8 Yes No
The fill moister well controlled within the optimum MC.
Inspector's Observation
Sr # Description of Activity (Write N/A if Not Applicable)
(Record the Data)
Equipment for
Availability of Compaction:
AFC DWG:
Yes
Yes No
No
9 A suitable
AFC compactors
drawing types - at
& Spec available vibratory
site if required to be used with a
sufficient number of passes
Yes No
FDT:
10 A Field Density Test carried out as per specification.
Specify FDT : ……………………...
Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements
(Specifications, Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or
applicable, other activities can be added to the checklist.
Contractor PMC
Name
Date
Signature