Record of Continuity and Insulation Resistance Test: A. Particulars of The Installation
Record of Continuity and Insulation Resistance Test: A. Particulars of The Installation
C&I
JKR MALAYSIA Sheet of
C. TEST RESULTS (Please X where not applicable. Please refer to Page 2 for notes and test procedures)
Circuit No. 1 2 3 4 5 6 7 8 9 10 11 12
Type of Wiring [see note 2 ]
Circuit Reference [see note 3 ]
Numbers of Points
Phase (mm²)
Cable Size
CPC (mm²)
Neutral & CPC , or (ohms)
RADIAL CIRCUITS (R1+R2)
Phase & CPC (ohms)
C O N T I N U I T Y
(R1+R2)
Confirmation of CPC in a radial circuit is continuous
(Mark Y for yes and N for no)
Phase (ohms)
RING FINAL CIRCUITS
Neutral (ohms)
CPC (ohms)
Phase & Neutral (ohms)
Confirmation of
Ring final Circuit Is Phase & CPC (ohms)
Wired In A Ring
Mark Y for yes and N for no
Tandatangan: Tandatangan:
mri/ra/wan/johor/MAC2008
Page 1 of 2
FORM NO : JKR.C&I
Sheet of
1 FORM NO: JKR.C&I is for single phase points in a single phase DB or three phase DB
FORM NO: JKR.IR &C is for three phase points and submain cables
2 CODES FOR TYPE OF WIRING
PVC Cables in PVC Cables PVC Cables PVC Cables PVC Cables PVC/PVC Fire
surface GI in surface in concealed in concealed in trunking Cables Resistance
conduit UPVC conduit GI conduit UPVC conduit Cables
3 CIRCUIT REFERENCE
B. TEST PROCEDURES
It should be noted that the continuity and insulation resistance tests for lighting circuit describe below can only be applied to a
1.10 Test method 1 (CPC conductor terminated at the last point of the circuit and using the neutral conductor as a return lead)
1.11 Connect the neutral conductor to the CPC conductor at the last point of the circuit under test.
1.12 Test between neutral and earth of the circuit at the DB
1.13 Record the test result obtained.
1.14 The readings should be compared with the " Resistance of copper conductors " table for a particular
length and size.
1.15 See Fig. 1a for Test method connections.
1.20 Test method 2 ( CPC terminated at the switch panel and using the phase conductor as a return lead)
1.21 Connect the phase conductor (phase wire) to the CPC conductor at the switch panel
1.22 Test between the phase and earth of the circuit at the DB
1.23 Record the test result obtained.
1.24 The readings should be compared with the " Resistance of copper conductors " table for a particular
length and size.
1.25 See Fig. 1b for Test method connections.
2.10 The phase, neutral and CPC conductors are identified and the end-to-end resistance of each conductor
is measured separately. Record the resistance readings.
2.20 A finite reading confirms that there is continuity on the ring conductors under test
2.30 See Fig 2 for Test method connections
3.0 CONFIRMATION OF RING FINAL CIRCUIT IS WIRED IN A RING (4 ends joined method)
mri/ra/wan/johor/MAC2008